Contractors vie for schemes worth $270bn

21 December 2023

Following one of the best years for project contract awards in the Middle East and North Africa (Mena) region in a decade, 2024 has a lot to live up to if it is to generate a similar amount of project activity. 

By mid-December, the value of contract awards in 2023 had exceeded $230bn and was just $10bn shy of the $240bn-worth of regional contract awards let in 2014 – the best year on record to date. It was also on track to exceed that record year, with $36bn of projects in bid evaluation and expected for award by year’s end.

Nevertheless, 2024 has the potential to be an even better year for the Mena projects markets than 2023, with more than $270bn-worth of projects in the bidding phase and either overdue, due for award in the final weeks of 2023 – at the mid-December mark – or set for award at some point during 2024.

On top of this significant value of projects in the bidding stage, the region also has an estimated $250bn-worth of work in the design phase, with project trajectories that could quite reasonably see the schemes proceed through the prequalification, tendering and main contract award phases within the next 12 months.

Of the $270bn of value in the bidding stage, $126bn is in bid evaluation, with the main contract imminently due for award. A further $67bn is at the bid submission stage and $77bn is at the prequalification stage.

Imminent awards

Among the projects that are in the bidding phase and due for award in 2024 are six projects worth $4bn or more – all of which are in the GCC, with three in the UAE and one in each of Kuwait, Qatar and Saudi Arabia. They include three oil and gas projects, two power plants and one transport scheme.

The largest project contract in both the bidding phase, and specifically bid evaluation, is the estimated $7bn scheme for the development of surface facilities as part of the UZ1000 expansion programme by the offshore arm of Abu Dhabi National Oil Company (Adnoc Offshore) at the UAE’s Upper Zakum oil field. 

Bids for the project have been submitted by the UK’s Petrofac, the local Target Engineering Construction Company and Spain’s Tecnicas Reunidas.

The next largest project in the bidding phase is the $6bn first package of the Duwaiheen nuclear power plant project, which entails the construction of two 2,800MW nuclear reactors on behalf of the Saudi special purpose vehicle Duwaiheen Nuclear Energy Company. Expected bidders include France’s EDF, China National Nuclear Corporation, Korea Electric Power Corporation and Russia’s Rosatom.

The third largest scheme, and one that is at the prequalification stage, is the estimated $4.8bn Blue Line for the Dubai Metro, tendered by the Roads & Transport Authority after the project was greenlit in November 2023. Expressions of interest for the 12-station line are being sought from three consortiums.

Close behind this is the $4.5bn Ruwais liquefied natural gas terminal, which is being tendered by Adnoc Gas Processing, and for which more than half a dozen companies have submitted bids.

In Kuwait, the $4bn combined phases two and three of Al-Zour North independent water and power project are being tendered by the Ministry of Electricity & Water via the Kuwait Authority for Partnership Projects. Five bidders have submitted prequalification documents for the scheme. 

Pending in Qatar, there is the $4bn phase two, scope D of works on the North Field production sustainability project, for which submissions to QatarEnergy LNG are due by the end of December.

Top markets

The country with the highest value of project work in the bidding phase – and more than double that of the next most active projects market – is Saudi Arabia, which alone has schemes worth $107bn. This includes $46.5bn-worth of work in bid evaluation, $34.3bn in bid submission and $26.4bn at the prequalification stage.

The work in Saudi Arabia is concentrated in the hands of several large clients, led by Saudi Aramco, which has $22bn-worth of work under bid, and Neom, which has $19bn of associated projects under bid. 

There is a further $8.6bn-worth of work associated with the four other official gigaprojects: Diriyah Gate, Qiddiya, the Red Sea Project and Roshn. There is also $7.7bn-worth of work in the bidding phase as part of the Saudi Power Procurement Company’s renewable energy programme.

The projects market with the second-largest value of imminently pending work is the UAE, with $51.5bn-worth of work under bid, including schemes worth about $30bn in bid evaluation. This work is led by the oil and gas sector, with $22.6bn of work being tendered by Adnoc Group. 

Elsewhere in the GCC, Kuwait, Oman and Qatar have, respectively, $19.8bn, $17.9bn and $15.7bn of projects under bid. Overall, the GCC markets account for $216bn or 80 per cent of the $270bn total of work under bid, with Saudi Arabia and the UAE alone accounting for $159bn-worth of work, or 59 per cent of the total.

Close behind these markets is Algeria, which has $15.3bn-worth of schemes in the bidding phase, alongside lesser values in Egypt and Iraq, at $10.7bn and $7.7bn, respectively. There is then a further $24bn-worth of work under bid spread across the other countries in the Mena region.

Strongest sector

Segregated by industry, of the $270bn-worth of work in the bidding stage, there are: projects in the construction and transport sector worth a combined $97.7bn; schemes worth $97.6bn in the power, water and utilities sector; and programmes worth $74.8bn in energy industry.

This breaks down further into $53.1bn of transport projects, $44.6bn of construction projects, $59.7bn of power projects, $37.8bn of water projects, $32.9bn of gas projects, $29.2bn of oil projects, and $12.6bn of chemicals and other industrial schemes.

Top clients

The top 10 project clients in the region by value of projects currently in the bid stage account for $103bn or 38 per cent of the $270bn of total project value under bid. Out of this group of regional heavyweight project owners, five are Saudi entities: Saudi Aramco, Neom, Saudi Power Procurement Company (SPPC), Duwaiheen Nuclear Energy Company (DNEC) and Saudi Electricity Company (SEC).

The top project client outside of Saudi Arabia is the UAE’s Adnoc, which comes second only to Saudi Aramco in terms of the value of projects in the bidding stage. Adnoc is accompanied in its representation of the UAE in the ranking by Dubai’s Road & Transport Authority (RTA). 

The list is then rounded out by Algeria’s Sonelgaz and two Kuwaiti entities: Kuwait Authority for Partnership Projects (Kapp) and Kuwait Oil Company (KOC).

Both Saudi Aramco and Adnoc have more than $20bn-worth of projects under bid, followed closely by Neom, which has $17.6bn-worth of projects across its constituent masterplans, led by Oxagon, Trojena and The Line. 

The three Saudi utilities sector clients, SPPC, DNEC and SEC, then have $7.3bn, $6.5bn and $6.3bn under bid, respectively. Sonelgaz is close behind, with $6.2bn under bid, followed by Kapp, the RTA and KOC, with $6bn, $5.4bn and $4.9bn, respectively, under bid.

The line-up reflects the broader pattern of a strong concentration of project activity in the Mena region within the GCC, and especially within Saudi Arabia and the UAE, as the pre-eminent GCC projects markets. 

 Top pending projects in 2024 (to be published on 27 Dec 2023)

https://image.digitalinsightresearch.in/uploads/NewsArticle/11381712/main.gif
John Bambridge
Related Articles
  • Three groups bid for $5bn Asir-Jizan highway

    3 August 2026

     

    Three groups have submitted bids for an estimated SR20bn ($5bn) contract to develop and operate the Asir-Jizan highway project on a public-private partnership (PPP) basis.

    According to sources close to the project, the consortiums that bid are:

    • Lamar Holding (local) / Shaanxi Construction Engineering (China) / Safari (local)
    • Vision Invest (local) / China Harbour Engineering Company (China)
    • Plenary (Australia) / Alayuni (local) / Limak Holding (Turkey) / Nesma & Partners (local)

    Saudi Arabia’s Roads General Authority, the National Centre for Privatisation & PPP and the Aseer Development Authority (Asda) are the government agencies managing the tender and project.

    The 136-kilometre Asir-Jizan highway will have three lanes in each direction and include six intersections, 57 bridges totalling 18km and 11 tunnels totalling 9km.

    The project is one of four planned highway schemes in the kingdom’s privatisation and public-private partnership pipeline.

    The route begins in Al-Farah in Asir and extends to the Red Sea through Jizan.

    The 30-year contract will follow a design, build, finance, operate and maintain model.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18031383/main1110.jpg
    Colin Foreman
  • Adnoc Onshore extends bid deadline for field facilities project

    3 August 2026

     

    Abu Dhabi National Oil Company’s onshore business (Adnoc Onshore) has given contractors extra time to prepare bids for a project to build on-plot and off-plot facilities at the Rumaitha and Shanayel fields, part of the Northeast Bab cluster of oil fields in Abu Dhabi.

    The project aims to enhance and sustain oil production at the Rumaitha and Shanayel fields at a rate of 45,000 barrels a day (b/d). It forms part of Adnoc Onshore’s contribution to parent company Adnoc Group’s broader objective of increasing oil production capacity to 5 million b/d by 2027 through its Accelerated Integrated Programme 5 (AiP5). Adnoc Group currently has a production capacity of 4.85 million b/d.

    Adnoc Onshore issued the main tender for the engineering, procurement and construction (EPC) works package for the Rumaitha and Shanayel on-plot and off-plot facilities project on 19 June, MEED previously reported.

    The project operator has now extended the deadline for contractors to submit technical bids to 5 August, from 2 August previously, according to sources. The prior deadline had been 30 July.

    Adnoc Onshore issued the expression of interest for the Rumaitha and Shanayel on-plot and off-plot facilities project in early December, with contractors submitting their responses later that month, MEED previously reported.

    The prequalification and ongoing tendering process is understood to result from Adnoc Onshore revising its strategy for executing EPC works on an earlier, larger project covering the Northeast Bab cluster, which comprises the Al-Nouf, Rumaitha and Shanayel fields.

    MEED reported in December that Adnoc Onshore had cancelled the engineering, procurement and construction management (EPCm) phase it launched in 2024 for the Northeast Bab on-plot and off-plot facilities project in favour of executing the scheme under a conventional EPC model.

    The operator awarded a contract to state-owned China Petroleum Engineering & Construction Corporation (CPECC) to carry out EPCm services for the Northeast Bab off-plot facilities package in October 2024. However, the contract was subsequently cancelled last year.

    Separately, Adnoc Onshore received bids during the second quarter of 2025 for the EPCm tender covering the Northeast Bab on-plot facilities package, but that procurement process was also later cancelled.

    Project scope of work

    The detailed scope of work on the Rumaitha and Shanayel on-plot and off-plot facilities project is as follows:

    On-plot facilities:

    • Oil train: One new oil train with slug catcher, two-stage separation, desalting, exchangers for crude heating and stabilisation, and all associated interconnections, utilities and civil/structural works, etc.
    • Produced water treatment (PWT): New produced water treatment package to enable 100% produced water reinjection (PWRI), including chemical dosing, tanks, pumps, all associated controls and blending with aquifer water, etc.
    • Water injection system: New water injection system, including surface water injection pumps, necessary connections and controls from produced water systems, headers, chemical dosing, power and controls, etc.
    • Gas handling and export:
      • Low-pressure gas compression system
      • Medium-pressure gas compression system
      • Gas dehydration and regeneration system
      • Export gas compression system
    • Utilities and offsites: Plant air and instrument air systems, nitrogen generation system, potable water system, vapour recovery system (liquid ejector package), fuel gas import and distribution, closed and open drain systems, hot oil heater, snuffing nitrogen package, enclosed ground flare systems (high-pressure and tank flares), etc.
    • Modifications in existing systems, including, but not limited to, installation of a slug catcher at phase-I, connectivity of gas systems, water systems, existing high-pressure compressors modifications, etc
    • Electrical, instrumentation and control, and safety: Electrical systems, instrumentation and control system (ICSS, F&G system, field instrumentation, HIPPS, etc.), substation and ITR room building, fire water system, etc.
    • Overhead line (220 kV): Installation and extension of overhead lines and 220 KV GIS compound or equivalent power distribution solutions to the central processing plant and other designated areas, as necessary.

    Off-plot facilities:

    • New gas-lifted oil producers and water injectors installation with necessary piping, controls, etc. and their connections to the new or existing clusters and pipeline networks
    • New clusters with facilities such as control panels, ITR, production and test manifolds, headers, chemical injection skids, multiphase flow meters, closed drain systems, HIPPS valves, WHCPs, pig traps, ICSS/telecom extensions, etc.
    • Modifications in existing clusters, including the addition or extension of manifolds, headers, additional pipelines with pig traps, ICSS/telecom extensions, chemical injection kids, etc.
    • Gathering and injection networks: Construction of new and modified oil gathering and water injection trunklines/laterals, pigging facilities (launchers/receivers), valve stations, block valves, corrosion protection and monitoring, and all associated equipment, etc.
    • Export gas pipelines and Adnoc Gas interface: Provision for export gas pipeline and facilities from Rumaitha central processing plant to new manifold station and from NMS to Adnoc Gas, including isolation/blowdown, etc.
    • Overhead line: Installation and extension of 33kV overhead lines to clusters, etc., as required.

    The tendering exercise for the Rumaitha and Shanayel on-plot and off-plot facilities project is taking place as Adnoc Onshore continues to make progress with EPC works on another, similar project to build off-plot facilities at the Southeast cluster of oil fields in Abu Dhabi, which is also integral to Adnoc Group’s AiP5 campaign.

    The Southeast cluster comprises the Asab, Mender, Qusahwira, Sahil and Shah fields and accounts for approximately a third of Adnoc Onshore’s oil production capacity.

    MEED previously reported that Adnoc Onshore had awarded EPC works on the Southeast off-plot facilities project to state-owned China Petroleum Engineering & Construction Corporation (CPECC), with the value of the contract estimated to be around $1.2bn.

    The overall scope of work on the Southeast off-plot facilities project includes tying in more than 150 wells across the area’s fields, upgrading remote and central degassing stations, laying more than 270 kilometres of flowlines, digitising wells for remote monitoring, and implementing artificial intelligence-driven telemetry technologies.

    MEED also recently reported that CPECC awarded subcontracts on the Southeast off-plot facilities project, in its capacity as the main EPC contractor.

    The off-plot facilities project is a component of the overall $2bn-$3bn South East AIP5 development, with the on-plot facilities project forming the other part of the programme.

    CPECC is also performing EPC works on the Southeast on-plot facilities project in a consortium with Greece-headquartered Archirodon. Adnoc Onshore awarded an estimated $1.5bn contract for that project to the consortium in December 2024, with EPC works scheduled for completion in 2027.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18022436/main2622.jpg
    Indrajit Sen
  • Lebanon seeks interest for power generation projects

    3 August 2026

    Lebanon’s Electricity Regulatory Authority (ERA) has invited the private sector to submit expressions of interest (EoIs) for several upcoming power generation projects.

    The EoI covers up to five grid-connected solar photovoltaic projects with a combined installed capacity of 350MWp. The projects are also expected to include battery energy storage systems (bess) with a combined capacity of 1,000MWh. 

    The regulator is also seeking proposals for distributed dual-fired thermal power plants with net capacities ranging from 20MW to 100MW. The plants are expected to operate on natural gas as the primary fuel and heavy fuel oil as a backup fuel. 

    The submission deadline is 31 August. 

    Regulatory progress

    The EoI follows the establishment of Lebanon’s Electricity Regulatory Authority earlier this year, more than two decades after it was envisaged under Law No. 462/2002 but not implemented due to political delays. The electricity sector had previously been overseen by the Ministry of Energy & Water and state utility Electricite du Liban.

    Lebanon’s electricity sector continues to face insufficient generation capacity, fuel supply constraints, ageing generation assets and limited grid flexibility. These challenges have led to prolonged electricity shortages and increased reliance on private diesel generation and distributed solar systems, prompting the government to seek additional private investment in new generation capacity. 

    IPP model

    According to the EoI document, the projects are expected to be structured as independent power producer (IPP) schemes. Any future contractual arrangements, including power-purchase agreements, will be determined by the competent public authority under the applicable legal framework. 

    The ERA said the EoI is open to private investors, IPP operators, engineering, procurement and construction contractors, equipment suppliers and consortiums. It is intended to assess market interest, identify potential generation projects and evaluate the technical and financial capabilities of prospective developers. 

    Respondents are required to provide information on their technical and financial capabilities, proposed project locations, grid connection plans and relevant project experience. 

    For solar projects, developers are required to provide details including module and inverter technology, annual generation estimates and battery storage specifications where applicable. Thermal project submissions must include information on technology type, efficiency, fuel strategy, emissions performance and readiness for future natural gas operation. 

    The EoI states that developers will be responsible for land acquisition or leasing, permitting, financing, design, construction, grid interconnection, commissioning, and long-term operation and maintenance of the projects. 


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18018733/main.jpg
    Mark Dowdall
  • Saudi economy swings to 4.8% contraction

    3 August 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s economy contracted 4.8% year-on-year in the second quarter of 2026, as a sharp fall in oil activities outweighed continued growth in the non-oil economy, according to flash estimates from the General Authority for Statistics (Gastat).

    The contraction was driven by a 24.7% year-on-year drop in oil activities, which cut 5.4 percentage points from the headline figure. Non-oil activities grew 0.6% and government activities rose 0.9%, contributing 0.4 and 0.1 percentage points respectively. Net taxes on products added a further 0.1 percentage points.

    On a seasonally adjusted basis, real GDP fell 4.9% from the first quarter, with oil activities down 21.5% quarter-on-quarter. Non-oil activities eased 0.5% over the same period, while government activities rose 0.2%.

    The second-quarter figures mark a reversal from the first quarter, when the economy grew 3% year-on-year. In the first quarter, both oil and non-oil activities expanded by 2.9% and government activities rose 1.5%, with growth recorded across all major sectors. Oil activities have since swung from that modest expansion to a steep contraction, while non-oil growth has slowed from 2.9% to 0.6%.

    The divergence between the oil and non-oil economy has widened as a result. While crude output fell steeply in the second quarter, the broader non-oil sector, the focus of the kingdom’s economic diversification programme, continued to expand, albeit at a slower pace than in the opening months of the year.

    Public finances

    The contraction came in a quarter when higher oil revenue improved the public finances. The budget deficit narrowed to SR34.29bn in the second quarter, down from SR125.71bn in the first, as oil revenue rose 22% year-on-year to SR185.13bn, according to the Finance Ministry’s quarterly budget performance report. Total revenue reached SR338.78bn, up 12% on the same period of 2025, while non-oil revenue increased 3% to SR153.66bn.

    Total spending rose 11% year-on-year to SR373.07bn. The sharpest increases were in grants, up 199% to SR1.24bn, subsidies, up 73% to SR13.27bn, and financing expenses, up 41% to SR16.81bn. Capital spending rose 16% to SR46.23bn.

    For the first half, the deficit totalled SR160bn, financed entirely through borrowing with no drawdown on government reserves. Revenue for the six months rose 6% year-on-year to SR599.76bn, while spending increased 15% to SR759.76bn. Actual first-half spending reached 58% of the full-year budget of SR1.312tn. Health and social development recorded the highest sectoral outlay at SR170.61bn, followed by the military at SR124.57bn and education at SR109.73bn.

    Public debt reached SR1.684tn by the end of the first half, up from an opening balance of SR1.519tn. Domestic debt stood at SR1.060tn and external debt at SR624.9bn. The government reserve closing balance was SR399.07bn.

    The kingdom has continued to tap the domestic debt market. The National Debt Management Centre closed its July 2026 issuance under the Saudi Arabian Government riyal-denominated sukuk programme at SR5.35bn, divided into five tranches. The largest, at SR3.83bn, matures in 2031, with further tranches of SR515m maturing in 2033, SR204m in 2036, SR300m in 2039 and SR500m in 2041.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18015899/main.gif
    Colin Foreman
  • Emirates NBD buys HSBC Egypt retail business

    3 August 2026

    HSBC has agreed to sell the retail banking business of its Egyptian subsidiary to Emirates NBD Egypt, a unit of Dubai’s largest bank by assets, as the UK lender continues to simplify its global operations.

    The sale covers the assets and liabilities of HSBC Egypt’s entire retail banking business, including retail loans, deposits and accounts, along with the employees supporting the transferring business. The transaction is expected to complete in the second half of 2027, subject to regulatory approvals.

    There will be no immediate changes for retail customers, and their products and services in Egypt will continue to operate as normal. The two banks said they would work together to enable a smooth transition for staff and customers.

    Financial impact

    The sale is expected to generate an estimated pre-tax gain for HSBC Group of about $0.3bn, to be recognised largely at completion and classified as a material notable item. HSBC said the transaction would have an immaterial impact on the group’s Common Equity Tier 1 capital ratio.

    The disposal follows a strategic review of HSBC Egypt’s retail banking business announced last year. It forms part of an ongoing simplification of HSBC Group as the bank focuses on areas where it has a competitive advantage and the greatest opportunities to grow.

    Egypt remains an important market for HSBC, which said it would continue to support its corporate and institutional banking clients in the country and drive two-way trade and investment flows.

    Turkiye talks

    The Egypt agreement follows reports that Emirates NBD is in early talks to acquire HSBC’s business in Turkiye, a move that would deepen the Gulf lender’s presence in the country through its ownership of DenizBank. In late June, it was reported that discussions were at an early stage and might not lead to an agreement. Neither bank commented on the talks.

    HSBC’s Turkiye business has contracted sharply over the past decade. The bank, which has operated in the country since 1990, had 315 branches and about 6,000 employees in 2013, but its network had fallen to about 36 branches by March 2026, leaving it as Turkiye’s 15th largest lender by assets. Any deal would require approval from Turkish regulators and would mark one of Emirates NBD’s largest moves in the country since it acquired DenizBank from Russia’s Sberbank in 2019.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18014996/main.gif
    Colin Foreman