Contractors vie for schemes worth $270bn

21 December 2023

Following one of the best years for project contract awards in the Middle East and North Africa (Mena) region in a decade, 2024 has a lot to live up to if it is to generate a similar amount of project activity. 

By mid-December, the value of contract awards in 2023 had exceeded $230bn and was just $10bn shy of the $240bn-worth of regional contract awards let in 2014 – the best year on record to date. It was also on track to exceed that record year, with $36bn of projects in bid evaluation and expected for award by year’s end.

Nevertheless, 2024 has the potential to be an even better year for the Mena projects markets than 2023, with more than $270bn-worth of projects in the bidding phase and either overdue, due for award in the final weeks of 2023 – at the mid-December mark – or set for award at some point during 2024.

On top of this significant value of projects in the bidding stage, the region also has an estimated $250bn-worth of work in the design phase, with project trajectories that could quite reasonably see the schemes proceed through the prequalification, tendering and main contract award phases within the next 12 months.

Of the $270bn of value in the bidding stage, $126bn is in bid evaluation, with the main contract imminently due for award. A further $67bn is at the bid submission stage and $77bn is at the prequalification stage.

Imminent awards

Among the projects that are in the bidding phase and due for award in 2024 are six projects worth $4bn or more – all of which are in the GCC, with three in the UAE and one in each of Kuwait, Qatar and Saudi Arabia. They include three oil and gas projects, two power plants and one transport scheme.

The largest project contract in both the bidding phase, and specifically bid evaluation, is the estimated $7bn scheme for the development of surface facilities as part of the UZ1000 expansion programme by the offshore arm of Abu Dhabi National Oil Company (Adnoc Offshore) at the UAE’s Upper Zakum oil field. 

Bids for the project have been submitted by the UK’s Petrofac, the local Target Engineering Construction Company and Spain’s Tecnicas Reunidas.

The next largest project in the bidding phase is the $6bn first package of the Duwaiheen nuclear power plant project, which entails the construction of two 2,800MW nuclear reactors on behalf of the Saudi special purpose vehicle Duwaiheen Nuclear Energy Company. Expected bidders include France’s EDF, China National Nuclear Corporation, Korea Electric Power Corporation and Russia’s Rosatom.

The third largest scheme, and one that is at the prequalification stage, is the estimated $4.8bn Blue Line for the Dubai Metro, tendered by the Roads & Transport Authority after the project was greenlit in November 2023. Expressions of interest for the 12-station line are being sought from three consortiums.

Close behind this is the $4.5bn Ruwais liquefied natural gas terminal, which is being tendered by Adnoc Gas Processing, and for which more than half a dozen companies have submitted bids.

In Kuwait, the $4bn combined phases two and three of Al-Zour North independent water and power project are being tendered by the Ministry of Electricity & Water via the Kuwait Authority for Partnership Projects. Five bidders have submitted prequalification documents for the scheme. 

Pending in Qatar, there is the $4bn phase two, scope D of works on the North Field production sustainability project, for which submissions to QatarEnergy LNG are due by the end of December.

Top markets

The country with the highest value of project work in the bidding phase – and more than double that of the next most active projects market – is Saudi Arabia, which alone has schemes worth $107bn. This includes $46.5bn-worth of work in bid evaluation, $34.3bn in bid submission and $26.4bn at the prequalification stage.

The work in Saudi Arabia is concentrated in the hands of several large clients, led by Saudi Aramco, which has $22bn-worth of work under bid, and Neom, which has $19bn of associated projects under bid. 

There is a further $8.6bn-worth of work associated with the four other official gigaprojects: Diriyah Gate, Qiddiya, the Red Sea Project and Roshn. There is also $7.7bn-worth of work in the bidding phase as part of the Saudi Power Procurement Company’s renewable energy programme.

The projects market with the second-largest value of imminently pending work is the UAE, with $51.5bn-worth of work under bid, including schemes worth about $30bn in bid evaluation. This work is led by the oil and gas sector, with $22.6bn of work being tendered by Adnoc Group. 

Elsewhere in the GCC, Kuwait, Oman and Qatar have, respectively, $19.8bn, $17.9bn and $15.7bn of projects under bid. Overall, the GCC markets account for $216bn or 80 per cent of the $270bn total of work under bid, with Saudi Arabia and the UAE alone accounting for $159bn-worth of work, or 59 per cent of the total.

Close behind these markets is Algeria, which has $15.3bn-worth of schemes in the bidding phase, alongside lesser values in Egypt and Iraq, at $10.7bn and $7.7bn, respectively. There is then a further $24bn-worth of work under bid spread across the other countries in the Mena region.

Strongest sector

Segregated by industry, of the $270bn-worth of work in the bidding stage, there are: projects in the construction and transport sector worth a combined $97.7bn; schemes worth $97.6bn in the power, water and utilities sector; and programmes worth $74.8bn in energy industry.

This breaks down further into $53.1bn of transport projects, $44.6bn of construction projects, $59.7bn of power projects, $37.8bn of water projects, $32.9bn of gas projects, $29.2bn of oil projects, and $12.6bn of chemicals and other industrial schemes.

Top clients

The top 10 project clients in the region by value of projects currently in the bid stage account for $103bn or 38 per cent of the $270bn of total project value under bid. Out of this group of regional heavyweight project owners, five are Saudi entities: Saudi Aramco, Neom, Saudi Power Procurement Company (SPPC), Duwaiheen Nuclear Energy Company (DNEC) and Saudi Electricity Company (SEC).

The top project client outside of Saudi Arabia is the UAE’s Adnoc, which comes second only to Saudi Aramco in terms of the value of projects in the bidding stage. Adnoc is accompanied in its representation of the UAE in the ranking by Dubai’s Road & Transport Authority (RTA). 

The list is then rounded out by Algeria’s Sonelgaz and two Kuwaiti entities: Kuwait Authority for Partnership Projects (Kapp) and Kuwait Oil Company (KOC).

Both Saudi Aramco and Adnoc have more than $20bn-worth of projects under bid, followed closely by Neom, which has $17.6bn-worth of projects across its constituent masterplans, led by Oxagon, Trojena and The Line. 

The three Saudi utilities sector clients, SPPC, DNEC and SEC, then have $7.3bn, $6.5bn and $6.3bn under bid, respectively. Sonelgaz is close behind, with $6.2bn under bid, followed by Kapp, the RTA and KOC, with $6bn, $5.4bn and $4.9bn, respectively, under bid.

The line-up reflects the broader pattern of a strong concentration of project activity in the Mena region within the GCC, and especially within Saudi Arabia and the UAE, as the pre-eminent GCC projects markets. 

 Top pending projects in 2024 (to be published on 27 Dec 2023)

https://image.digitalinsightresearch.in/uploads/NewsArticle/11381712/main.gif
John Bambridge
Related Articles
  • Oil prices rise above $100 a barrel as conflict escalates

    9 September 2026

    Register for MEED’s 14-day trial access 

    Oil prices rose above $100 a barrel on 9 September for the first time since July as the US-Iran conflict escalated and Iran-backed Houthi forces attacked Saudi energy infrastructure.

    Brent crude futures reached $100.95 a barrel, while US benchmark West Texas Intermediate (WTI) rose to $95.60. Brent had last traded above $100 on 24 July.

    The latest escalation has heightened concerns about oil supplies from the region, with shipping through both the Strait of Hormuz and the Red Sea facing disruption.

    Flows through the Strait of Hormuz had fallen below 2 million barrels a day (b/d) from about 8-9 million b/d before the latest escalation, according to Rystad Energy.

    At the same time, Houthi attacks on Saudi Arabia threaten another important route for oil exports, with the group targeting energy infrastructure and shipping in and around the Red Sea.

    US strikes on Iranian tankers

    US forces destroyed five Iranian crude oil carriers on 8 September after Iran’s Islamic Revolutionary Guard Corps (IRGC) targeted a US Navy warship with ballistic missiles.

    The US Central Command (Centcom) said the warship successfully evaded two Iranian attacks and that no US personnel were harmed.

    Four of the Iranian vessels – Kaviz, Charminar, Horizon 1 and Riesco – were struck in the Gulf of Oman, while the Derya was attacked near Kharg Island, Iran’s main crude export hub.

    The M/T Riesco subsequently sank in the Gulf of Oman, according to Centcom.

    Iran responded by launching ballistic missiles towards Jordan. Jordan’s armed forces said 18 of 20 missiles were intercepted, with the remaining two falling in unpopulated areas.

    Iran’s IRGC also said it had attacked two US naval vessels, eight oil tankers and 10 other vessels in the Gulf, although it did not identify the vessels or provide evidence of the attacks.

    The latest exchanges mark a further escalation in the US-Iran conflict, which began on 28 February.

    Houthi attacks raise supply concerns

    The conflict has also widened into a renewed confrontation between Saudi Arabia and Yemen’s Iran-backed Houthi movement.

    On 8 September, Saudi authorities said Houthi attacks had targeted civilian and economic sites in Abha, Khamis Mushait, Jazan and Najran in the south of the kingdom, injuring 73 people.

    Saudi Arabia’s Ministry of Energy said several energy sector facilities and installations had been targeted, causing fires and forcing a temporary halt to some operations.

    The Houthis said their attacks were in response to Saudi military action in Yemen, including what they described as attacks on Houthi positions and a Saudi blockade of ports and airports.

    Riyadh condemns attacks

    Saudi Arabia has strongly condemned the Houthi attacks and warned that it would take measures to defend its territory and national assets.

    In a statement on 8 September, the Ministry of Energy said authorities were working to address the impact of the attacks and ensure the safety of facilities and personnel while maintaining operations in accordance with approved plans.

    Saudi Arabia’s Ministry of Foreign Affairs also condemned the attacks and said the kingdom had the right to take measures to defend its sovereignty and protect its citizens, residents and national assets.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19505512/main0138.jpg
    Indrajit Sen
  • What actually slows a gigaproject down

    9 September 2026

     

    Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.

    “None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.

    For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.

    “The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.

    The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.

    “Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”

    Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.

    Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.

    Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.

    “The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”

    Integration needs to be well understood

    “Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.

    Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.

    Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.

    “The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”

    That shared view, he argues, will be what the next phase of Gulf delivery is judged on.

    Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.

    “This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.

    From reporting progress to managing risk before it lands

    Digital tools have a role here, Caldwell says, but not as a headline in themselves.

    Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.

    “The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."

    None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”

    Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.

    With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.

    “The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.

    What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.

    “The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif
    Yasir Iqbal
  • Qatari firm wins $221m Qiddiya stadium MEP deal

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Qatari contractor Elegancia MEP, part of Estithmar Holding, has won a SR829m ($221m) mechanical package contract for the Prince Mohammed Bin Salman Stadium in Qiddiya, Saudi Arabia.

    The contract covers full mechanical, electrical and plumbing (MEP) works for the stadium, and is Elegancia MEP’s largest award in Saudi Arabia to date.

    The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.

    The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.

    Saudi gigaproject developer Qiddiya Investment Company awarded an estimated SR15bn ($4bn) deal to build the stadium in October 2024, as MEED exclusively reported.

    The contract covered the construction of a multipurpose stadium on top of the 200-metre-high Tuwaiq cliff in the new sports and entertainment district of Qiddiya City.

    Once completed, the stadium will be the home ground for Saudi Pro League football clubs Al-Nassr and Al-Hilal.

    US-based architect Populous is the project consultant.

    The stadium is one of the venues for the kingdom’s 2034 Fifa World Cup bid and will host events such as the Saudi King Cup, the Asian Cup and the 2034 Asian Games.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19501493/main.jpg
    Yasir Iqbal
  • Jordan tenders advisory for wastewater treatment plant

    9 September 2026

    The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.

    The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).

    The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.

    The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.

    The submission deadline is 21 September.

    The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.

    The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.

    The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.

    WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.

    The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.

    The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg
    Mark Dowdall
  • Consultants bid for Abu Dhabi light rail project management

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.

    The notice was issued on 7 September, with a submission deadline of 9 November.

    The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.

    The key sections of the tram are:

    AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.

    This section covers 13km and includes 13 at-grade stations and one underground station.

    Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.

    Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.

    The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.

    The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.

    Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.

    Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.

    Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.

    The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19493532/main.jpg
    Yasir Iqbal