Contractors vie for schemes worth $270bn
21 December 2023
Following one of the best years for project contract awards in the Middle East and North Africa (Mena) region in a decade, 2024 has a lot to live up to if it is to generate a similar amount of project activity.
By mid-December, the value of contract awards in 2023 had exceeded $230bn and was just $10bn shy of the $240bn-worth of regional contract awards let in 2014 – the best year on record to date. It was also on track to exceed that record year, with $36bn of projects in bid evaluation and expected for award by year’s end.
Nevertheless, 2024 has the potential to be an even better year for the Mena projects markets than 2023, with more than $270bn-worth of projects in the bidding phase and either overdue, due for award in the final weeks of 2023 – at the mid-December mark – or set for award at some point during 2024.
On top of this significant value of projects in the bidding stage, the region also has an estimated $250bn-worth of work in the design phase, with project trajectories that could quite reasonably see the schemes proceed through the prequalification, tendering and main contract award phases within the next 12 months.
Of the $270bn of value in the bidding stage, $126bn is in bid evaluation, with the main contract imminently due for award. A further $67bn is at the bid submission stage and $77bn is at the prequalification stage.
Imminent awards
Among the projects that are in the bidding phase and due for award in 2024 are six projects worth $4bn or more – all of which are in the GCC, with three in the UAE and one in each of Kuwait, Qatar and Saudi Arabia. They include three oil and gas projects, two power plants and one transport scheme.
The largest project contract in both the bidding phase, and specifically bid evaluation, is the estimated $7bn scheme for the development of surface facilities as part of the UZ1000 expansion programme by the offshore arm of Abu Dhabi National Oil Company (Adnoc Offshore) at the UAE’s Upper Zakum oil field.
Bids for the project have been submitted by the UK’s Petrofac, the local Target Engineering Construction Company and Spain’s Tecnicas Reunidas.
The next largest project in the bidding phase is the $6bn first package of the Duwaiheen nuclear power plant project, which entails the construction of two 2,800MW nuclear reactors on behalf of the Saudi special purpose vehicle Duwaiheen Nuclear Energy Company. Expected bidders include France’s EDF, China National Nuclear Corporation, Korea Electric Power Corporation and Russia’s Rosatom.
The third largest scheme, and one that is at the prequalification stage, is the estimated $4.8bn Blue Line for the Dubai Metro, tendered by the Roads & Transport Authority after the project was greenlit in November 2023. Expressions of interest for the 12-station line are being sought from three consortiums.
Close behind this is the $4.5bn Ruwais liquefied natural gas terminal, which is being tendered by Adnoc Gas Processing, and for which more than half a dozen companies have submitted bids.
In Kuwait, the $4bn combined phases two and three of Al-Zour North independent water and power project are being tendered by the Ministry of Electricity & Water via the Kuwait Authority for Partnership Projects. Five bidders have submitted prequalification documents for the scheme.
Pending in Qatar, there is the $4bn phase two, scope D of works on the North Field production sustainability project, for which submissions to QatarEnergy LNG are due by the end of December.
Top markets
The country with the highest value of project work in the bidding phase – and more than double that of the next most active projects market – is Saudi Arabia, which alone has schemes worth $107bn. This includes $46.5bn-worth of work in bid evaluation, $34.3bn in bid submission and $26.4bn at the prequalification stage.
The work in Saudi Arabia is concentrated in the hands of several large clients, led by Saudi Aramco, which has $22bn-worth of work under bid, and Neom, which has $19bn of associated projects under bid.
There is a further $8.6bn-worth of work associated with the four other official gigaprojects: Diriyah Gate, Qiddiya, the Red Sea Project and Roshn. There is also $7.7bn-worth of work in the bidding phase as part of the Saudi Power Procurement Company’s renewable energy programme.
The projects market with the second-largest value of imminently pending work is the UAE, with $51.5bn-worth of work under bid, including schemes worth about $30bn in bid evaluation. This work is led by the oil and gas sector, with $22.6bn of work being tendered by Adnoc Group.
Elsewhere in the GCC, Kuwait, Oman and Qatar have, respectively, $19.8bn, $17.9bn and $15.7bn of projects under bid. Overall, the GCC markets account for $216bn or 80 per cent of the $270bn total of work under bid, with Saudi Arabia and the UAE alone accounting for $159bn-worth of work, or 59 per cent of the total.
Close behind these markets is Algeria, which has $15.3bn-worth of schemes in the bidding phase, alongside lesser values in Egypt and Iraq, at $10.7bn and $7.7bn, respectively. There is then a further $24bn-worth of work under bid spread across the other countries in the Mena region.
Strongest sector
Segregated by industry, of the $270bn-worth of work in the bidding stage, there are: projects in the construction and transport sector worth a combined $97.7bn; schemes worth $97.6bn in the power, water and utilities sector; and programmes worth $74.8bn in energy industry.
This breaks down further into $53.1bn of transport projects, $44.6bn of construction projects, $59.7bn of power projects, $37.8bn of water projects, $32.9bn of gas projects, $29.2bn of oil projects, and $12.6bn of chemicals and other industrial schemes.
Top clients
The top 10 project clients in the region by value of projects currently in the bid stage account for $103bn or 38 per cent of the $270bn of total project value under bid. Out of this group of regional heavyweight project owners, five are Saudi entities: Saudi Aramco, Neom, Saudi Power Procurement Company (SPPC), Duwaiheen Nuclear Energy Company (DNEC) and Saudi Electricity Company (SEC).
The top project client outside of Saudi Arabia is the UAE’s Adnoc, which comes second only to Saudi Aramco in terms of the value of projects in the bidding stage. Adnoc is accompanied in its representation of the UAE in the ranking by Dubai’s Road & Transport Authority (RTA).
The list is then rounded out by Algeria’s Sonelgaz and two Kuwaiti entities: Kuwait Authority for Partnership Projects (Kapp) and Kuwait Oil Company (KOC).
Both Saudi Aramco and Adnoc have more than $20bn-worth of projects under bid, followed closely by Neom, which has $17.6bn-worth of projects across its constituent masterplans, led by Oxagon, Trojena and The Line.
The three Saudi utilities sector clients, SPPC, DNEC and SEC, then have $7.3bn, $6.5bn and $6.3bn under bid, respectively. Sonelgaz is close behind, with $6.2bn under bid, followed by Kapp, the RTA and KOC, with $6bn, $5.4bn and $4.9bn, respectively, under bid.
The line-up reflects the broader pattern of a strong concentration of project activity in the Mena region within the GCC, and especially within Saudi Arabia and the UAE, as the pre-eminent GCC projects markets.
Top pending projects in 2024 (to be published on 27 Dec 2023)
Exclusive from Meed
-
Qiddiya plans $7bn theme park hub near Paris25 August 2026
-
Masdar shelves Abu Dhabi green hydrogen project25 August 2026
-
Oman invites bids for Musandam renewables study25 August 2026
-
US launches sanctions campaign against Iran25 August 2026
-
Kuwait tenders $3.3bn gas processing facility25 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Qiddiya plans $7bn theme park hub near Paris25 August 2026
Saudi Arabia’s Qiddiya Investment Company plans to develop a mixed-use leisure destination worth about €6bn ($7bn) at Cergy-Pontoise in the Ile-de-France region, in one of the largest Saudi investments in French tourism infrastructure to date.
The plan was set out in a joint statement issued on 24 August at the close of a state visit to France by Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud. France and Saudi Arabia signed a memorandum of understanding (MoU) covering the project during the two-day visit.
The destination will bring together entertainment, leisure, hospitality, culture and sport, according to the joint statement. Current plans envisage up to three major entertainment anchors, hotels and complementary leisure experiences, with the €6bn figure covering the full development lifecycle.
One of the three parks is expected to be manga-themed, according to the French presidency. The themes of the other two have not been disclosed. The parks will be built and opened in stages, with construction expected to take several years. No opening date has been given.
The parks are expected to create about 22,000 direct jobs, according to the French presidency, compared with about 20,000 at Disneyland Paris. Cergy-Pontoise lies about 30 kilometres northwest of Paris.
Qiddiya is a subsidiary of the Public Investment Fund, Saudi Arabia’s sovereign wealth fund. Its flagship project is a giga-scale entertainment, sports and cultural city on the outskirts of Riyadh, one of several gigaprojects under Vision 2030.
The theme park plan was among a wider set of agreements reached during the visit. Both sides welcomed the announcement of 21 agreements and MoUs at a French-Saudi investment roundtable, spanning energy, industry, financial services, transport and logistics, health, culture, tourism and artificial intelligence. Bilateral trade reached about $11.8bn in 2025.
It is not the first time Saudi capital has backed a French theme park. Kingdom Holding Company was a longstanding investor in the operator of Disneyland Paris, first taking a stake in 1994 and participating in successive recapitalisations before Walt Disney Company moved to near-full ownership in 2017.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18987274/main.png -
Masdar shelves Abu Dhabi green hydrogen project25 August 2026

Abu Dhabi Future Energy Company (Masdar) has decided to cancel a planned project to build a green hydrogen plant in Abu Dhabi that would have supplied up to 100MW of renewable hydrogen to local steelmaker Emsteel for green steel production.
After contractors submitted bids for the project last year, Masdar asked bidders in the first quarter of this year to extend the validity of their proposals until the end of August to allow “more time to study and evaluate bids”, according to one source.
However, Masdar issued a notification to all bidders on 1 August stating that it had decided to cancel the project, sources told MEED.
Contractors that submitted bids for the Masdar green hydrogen project included:
- Envision (China)
- Larsen & Toubro (India)
- PowerChina (China)
- Samsung E&A (South Korea)
- Sinopec (China)
Masdar did not respond to MEED’s request for comment on the information.
In its current steelmaking process, Emsteel uses hydrogen produced by steam reforming of natural gas as a reducing agent to extract iron from iron ore. The core objective of Masdar’s planned project was to install a 100MW electrolyser at Emsteel’s main manufacturing hub in Musaffah, Abu Dhabi, to supply green hydrogen for future clean steel production.
Masdar initiated work on the project in 2024 by awarding a front-end engineering and design (feed) contract to locally based NT Energies, a joint venture of Abu Dhabi’s NMDC Energy and France-based Technip Energies.
Masdar then sought proposals last year for engineering, procurement, construction, demolition (if needed for brownfield activities), pre-commissioning, commissioning, start-up, and two years of operations and maintenance (extendable up to 20 years) at the planned facility.
Contractors submitted bids by the end of the year, according to sources.
The project involved green hydrogen production using alkaline water electrolysis, with a total installed electrolyser capacity of 100MW.
The scope of work involved building electrolyser stacks and modules, hydrogen separation and compression units, associated utilities and storage systems, and electrical, instrumentation and control systems.
It also included tie-ins to pre-defined interface points, including (but not limited to):
- a grid power supply connection to the MOSF substation in Musaffah that exists within the Emsteel complex and is operated by Taqa Transmission
- a water supply connection to a nearby Taqa Distribution network
Supporting infrastructure included a substation, a motor control centre, and ancillary plant buildings and facilities.
Masdar’s planned 100MW electrolyser project at the Emsteel facility would have represented a step up from a previous pilot project by the two Abu Dhabi-owned companies.
The partners inaugurated a pilot green hydrogen plant at Emsteel’s manufacturing complex in Musaffah in October 2024. It incorporates a 2.1MW electrolyser and is designed to support the production of up to 5,000 tonnes of green steel a year.
This made Emsteel the only steelmaker in the Middle East to use green hydrogen to produce green steel on a pilot basis.
“Sustainability is central to Emsteel’s innovation, competitiveness and long-term growth. Today, approximately 89% of our steel business electricity consumption comes from clean sources, and our steel carbon emissions intensity is around 40% lower than the World Steel Association global average,” Michael Rion, chief commercial officer of Emirates Steel, part of Emsteel Group, told MEED in a recent interview.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18911651/main0611.jpg -
Oman invites bids for Musandam renewables study25 August 2026
Oman’s Nama Power & Water Procurement Company (PWP) has issued a request for proposals (RFP) for techno-economic consultancy services to assess the feasibility of renewable energy options in Musandam Governorate.
The study will examine solar photovoltaic (PV), wind and hybrid renewable energy configurations. It will also assess battery energy storage systems (bess) and other renewable energy and energy storage technologies.
The consultant will be required to determine which technologies are technically and economically justified for the governorate.
The bid submission deadline is 24 September.
The Musandam power system is served primarily by the 123MW Musandam independent power plant (IPP), which began operating in 2017. The governorate has historically relied on small diesel-fired units, but has been seeking to move away from diesel-fired power generation for several years.
Nama PWP has previously said it was exploring renewable energy options in Musandam to meet future additional capacity requirements.
Its latest seven-year statement, released in March, forecasts peak electricity demand in Musandam to rise from 91MW in 2024 to 130MW in 2031, an average annual increase of 5%. Average demand is forecast to rise from 52MW to 73MW over the same period.
The plan says demand growth is being driven by distribution-level load and projects aimed at boosting tourism, economic and commercial activity.
Separately, the utility recently invited bids for financial and commercial consultancy services covering three 1GW solar IPPs targeted for commercial operation by the second quarter of 2030.
The bid submissions deadline is 10 September.
The three projects covered by the financial and commercial consultancy tender are understood to also be part of the 4GW programme, for which a technical advisory tender was issued on 15 July.
Bidding for this tender closes on 26 August.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18983679/main.jpg -
US launches sanctions campaign against Iran25 August 2026
The US has launched a sweeping sanctions campaign against Iran and the entities that trade with it, imposing measures on almost 60 individuals, companies and vessels while expanding the reach of secondary sanctions across five sectors of the Iranian economy.
The campaign, named Operation Economic Outcast, was announced on 24 August by US treasury secretary Scott Bessent, who described it as an economic D-Day for Iran. He said Washington’s objective was to sever every economic lifeline sustaining the Iranian regime.
The treasury’s Office of Foreign Assets Control (Ofac) issued five sectoral sanctions determinations under Executive Order 13902, covering digital assets, technology, gold, aviation and shipping. The determinations allow Ofac to sanction any person operating in those sectors, regardless of location. Washington said Iran uses cryptocurrency for sanctions evasion, seeks advanced technology for its weapons programmes, uses gold to stabilise the rial, and relies on commercial aviation and shipping networks to move fighters, weapons and oil revenue.
The measures build on earlier determinations targeting Iran’s financial, petroleum and petrochemical sectors.
Ofac also sanctioned close to 60 entities, individuals and vessels across multiple jurisdictions, including UAE-based entities, over alleged involvement in nuclear and missile procurement, cyber operations and oil revenue networks. The designations named a network of brokers, companies and shadow fleet vessels operating across the UAE, Hong Kong, China, Singapore, Switzerland and other regions to transport Iranian oil and channel revenue to the Islamic Revolutionary Guard Corps.
Among those designated were shipping brokers and bunkering firms based in the UAE that Washington said facilitated Iranian oil shipments and provided services to sanctioned vessels. The treasury also identified several shadow fleet tankers as blocked property, saying they had moved millions of barrels of Iranian crude and petroleum products, mainly to China.
Separately, the treasury targeted a procurement network spanning the Middle East and East Asia that it said supported Iran’s acquisition of proliferation-sensitive equipment, along with a cyber group directed by Iran’s Ministry of Intelligence & Security.
Bessent said Washington was pressing governments to shut down Iran-related activity within defined timelines, warning that entities facilitating money laundering or sanctions evasion for Iran risked being cut off from the US financial system. He declined to name specific countries.
The campaign follows the UAE’s own move against Tehran. On 19 August, the UAE suspended all trade, commercial exchanges and financial transactions with Iran with immediate effect, citing regional escalation. The UAE has historically been one of Iran’s most significant trading partners, with much of the relationship built on re-export trade routed through Dubai.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18983152/main.jpg -
Kuwait tenders $3.3bn gas processing facility25 August 2026

State-owned Kuwait Gulf Oil Company (KGOC) has issued the tender for the development of an onshore gas plant next to the Al-Zour refinery, according to industry sources.
The project budget is estimated at $3.3bn, and the bid deadline is 29 December, with a meeting for contractors scheduled for 14 September.
The tender was issued on 23 August.
The proposed plant will have the capacity to process up to 632 million cubic feet a day of gas and 60,000 b/d a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.
In February, MEED reported that at least seven companies had shown interest in participating in the tender.
Contractors that sent representatives to previous meetings to discuss the project include:
- Samsung E&A (South Korea)
- Larsen & Toubro (India)
- Tecnicas Reunidas (Spain)
- Saipem (Italy)
- Hyundai Engineering & Construction (South Korea)
- Hyundai Engineering Company (South Korea)
- JGC (Japan)
The tender process is using a fast-track model, which means that Kuwait’s Central Agency for Public Tenders (Capt) will not be involved in the tender process.
Capt typically reviews the technical and commercial evaluations of bids and verifies that the bidding process is competitive.
It is understood that not requiring Capt to approve this tender is expected to speed up the tender process.
Iran disputes ownership of the field, referring to it as Arash.
Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.
The Dorra field’s close proximity to Iran could make development difficult due to current security concerns.
The offshore elements of the wider Dorra field development project are expected to be especially difficult to protect from attacks from Iran.
Earlier this month, MEED revealed that Al-Khafji Joint Operations (KJO) had selected contractors for two major offshore packages under the Dorra field facilities development project.
KJO, which is jointly owned by Aramco subsidiary Aramco Gulf Operations Company and Kuwait Petroleum Corporation subsidiary KGOC, has divided the engineering, procurement and construction (EPC) scope for the Dorra gas production project into four packages: three offshore and one onshore.
US-based McDermott International has secured offshore package 2A, valued at about $1.5bn, according to sources.
A consortium of India’s Larsen & Toubro Energy Hydrocarbon (LTEH) and Italian contractor Saipem has secured package 2B, sources told MEED.
Estimated at about $3.7bn, package 2B is the largest of the three offshore EPC packages under the Dorra field facilities project.
MEED reported in March that the LTEH/Saipem consortium had emerged as the lowest bidder for offshore package 2B.
Contractors submitted bids for offshore packages 2A and 2B by the 9 March deadline, MEED previously reported. Bid validity was understood to expire on 15 August, prompting KJO to issue letters of intent to the selected contractors earlier this month, sources said.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18964461/main.png