UAE utilities ramp up capacity procurement
4 October 2024
Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) invited bids for contracts to develop three independent power producer (IPP) projects in rapid succession in the third quarter of 2024.
These projects comprise the 2,500GW Taweelah C combined-cycle gas turbine plant, the 1,500MW Madinat Zayed open-cycle gas turbine project and the 400MW battery energy storage system to be located in Al-Bihouth and Madinat Zayed.
They bring the number of Ewec’s electricity generation IPP projects currently under tender to four, in addition to the 1,500MW Al-Khazna solar photovoltaic (PV) IPP, which it tendered in April.
Ewec also issued the expression of interest notice on 1 October for a contract to develop the emirate’s fifth solar PV IPP, the 1,500MW Al-Zarraf project.
This robust project pipeline implies that the offtaker and developers, investors and contractors bidding for these projects have entered a hectic period compared to the past few years.
Abu Dhabi’s growing IPP pipeline will compete with Saudi Arabia’s equally robust pipeline for developers’ and contractors’ resources over the near to medium term as both states endeavour to meet their 2030 decarbonisation targets.
Abu Dhabi plans to procure 1,400MW of renewable energy capacity annually between 2027 and 2037 and to meet more than 50% of the emirate’s electricity demand from renewable and clean energy sources by 2030. This is expected to rise to 60% by 2035.
It also previously stated that it expects to reach a renewable energy installed capacity of 7,500MW by 2030, or three times its current capacity.
The expiry of power-purchase agreements for several generation assets over the next couple of years and the likelihood of these contracts not being extended also drive Abu Dhabi’s procurement programme for gas-fired capacity.
Dubai has a slightly different strategy. Dubai Electricity & Water Authority (Dewa) has abandoned any plans to procure additional gas-fired capacity in the foreseeable future.
Dubai’s future generation projects will be focused on the Mohammed Bin Rashid Solar Park, which is expected to reach an installed capacity of 5,000MW by 2030.
So far, Dewa has awarded contracts for the first six phases of the project, which have a total combined capacity of 4,600MW.
Further phases are being planned, with the state utility expected to appoint transaction advisers for phase seven, for which the capacity has not yet been made public, next year.
“The volume of projects coming to the market is almost unprecedented,” notes an industry source, who expects that utility developers are starting to be selective when bidding for new contracts regardless of the energy source.
Nuclear capacity
Notably, the UAE’s Federal Authority for Nuclear Regulation announced that the fourth reactor, or Unit 4, of the Barakah nuclear power plant in Abu Dhabi reached commercial operations in early September.
It marks the completion of the $43bn, 5,600MW Barakah 1 project, which was jointly implemented by the UAE’s Emirates Nuclear Energy Corporation (Enec) and South Korea’s Korea Electric Power Corporation (Kepco).
The entire plant reached full commercial operations approximately 16 years after Abu Dhabi first announced the project in 2008 and 12 years after construction works commenced on Unit 1.
The completion of Barakah 1 also implies that the project’s next phase is likely to proceed in earnest.
Hamad Alkaabi, the UAE’s permanent representative to the Austria-based International Atomic Energy Agency, said in July that the UAE government is considering initiating the tendering process for its next nuclear power plant this year.
Apart from the final tendering process decision, the market is also keen to know who will be invited to bid or submit proposals for the contract to implement the nuclear power facility’s next phase.
Washington and Abu Dhabi entered into the bilateral 123 Agreement for peaceful nuclear cooperation in 2009, which could determine to a large extent which companies or countries will be invited to participate in the project’s next phase.
What the rush is about
Ewec has made clear that expiring generation capacities and the need for gas-fired baseload as more renewable energy enters the UAE electricity grid underpin its ambitious capacity procurement pipeline.
Other factors influencing future capacity procurement plans include the UAE’s multibillion-dollar national industrialisation strategy. This strategy involves expanding downstream industries, including clean hydrogen production for both domestic and export use, potentially resulting in an exponential increase in peak demand.
This is in addition to the need to decarbonise while expanding the production of hard-to-abate sectors such as the oil and gas, steel and aluminium industries.
In addition to these demand sources, many believe the UAE’s 2031 National Artificial Intelligence (AI) Strategy is a major contributor to Abu Dhabi’s ongoing generation capacity buildout.
“They need to build power-hungry data centres to support their AI strategy,” notes an executive with an international infrastructure investment firm with offices in Dubai.
The UAE’s AI strategy encompasses deploying AI in priority sectors and “providing the data and infrastructure essential to become a test bed for AI”.
Meeting these and the other stated objectives, in addition to the data sovereignty regulations, has started driving a boom in data centre construction across the UAE.
State-backed enterprises, utilities, banks, logistics, tourism and service industries, and real estate companies have launched or are expected to launch AI programmes to boost productivity and efficiency, in line with the UAE’s 2050 net-zero target and circular carbon economy strategy.
These span industry-specific applications ranging from chatbots and small-language models to generative AI and large-language models, the latter of which require significant data bandwidth and consume enormous amounts of energy.
AI applications in defence and national security are also presumed to be a major component of the overall AI plan.
“The AI programme is progressing,” notes an Abu Dhabi-based utility executive, confirming a plan to procure 5,000MW of AI-dedicated thermal capacity.
Exclusive from Meed
-
Saudi housing entity awards infrastructure contract24 November 2025
-
Saudi utility firm awards water transmission contract24 November 2025
-
Larsen & Toubro climbs EPC contractor ranking24 November 2025
-
Chinese firm signs deal for Algerian steel project24 November 2025
-
Contractors submit Riyadh Expo infrastructure bids24 November 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi housing entity awards infrastructure contract24 November 2025

Saudi Arabia’s National Housing Company (NHC) has awarded Riyadh-based Alomaier Trading & Contracting Company a contract to carry out infrastructure works at its Khuzam residential development in Riyadh.
The scope of work covers all infrastructure works across an area of 4,000,000 square metres (sq m) in stage three, phase three of the Khuzam residential project.
Construction works have started, and the project is expected to be completed in 2028.
NHC’s Khuzam project is located to the north of Riyadh, near King Khalid International airport and the Expo 2030 site.
The development will offer more than 50,000 residential units and will include parks, commercial areas and other associated amenities.
It will also feature a grand park spanning an area of more than 4.5 million sq m.
MEED reported in 2020 that Riyadh planned to oversee the development of more than 1 million homes by 2025 to meet growing demand in the kingdom.
By 2030, the Saudi capital aims to more than double its population, from 7-8 million to 15-20 million, and become one of the 10 wealthiest cities in the world.
Alomaier Trading & Contracting is undertaking some major infrastructural development projects across the kingdom.
In 2023, MEED reported that Saudi Arabia’s National Water Company had awarded a contract worth SR371m ($99m) to Alomaier Trading & Contracting. It covers the construction of a sewage network in Dammam’s King Fahd suburb and adjacent areas.
The contract also involves the construction of regression lines with diameters of up to 700 millimetres (mm) and a total length of 300 kilometres (km), as well as five ejection lines with diameters of up to 500mm and a total length of 15km, according to data obtained from the regional projects tracker MEED Projects.
The firm specialises in the construction of roads, railways and other infrastructural development works.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15141143/main.jpeg -
Saudi utility firm awards water transmission contract24 November 2025
Saudi Arabia’s state-owned utility National Water Company (NWC) has awarded a contract for the operation and maintenance of water distribution networks to local firm International Water Distribution Company (Tawzea).
The project comprises the operation and maintenance of water transmission pipelines in Medina province, Sisco Holding announced.
Sisco Holding, also known as Saudi Industrial Services Company, holds a 50% stake in Tawzea. The other 50% stake is owned by Amiantit Water, a subsidiary of Saudi Arabian Amiantit Company.
The contract is valued at SR133.4m ($35.6m) and has a duration of 36 months.
It covers main and secondary pipelines, reservoirs, pumping stations, valves and all related components of the water distribution system.
NWC has also been advancing major sewer network expansion plans in Hafar Al-Batin and Al-Qaisomah.
The utility recently awarded local firm Alkhorayef Water & Power Technologies (AWPT) a contract to deliver the next phase of this project.
The phase four (part two) package involves constructing about 184 kilometres of sanitary sewer pipeline.
As of September, NWC had awarded $337m-worth of contracts. This includes a separate contract awarded to AWPT in August for a sewage network scheme in Al-Kharj governorate.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15140733/main.jpg -
Larsen & Toubro climbs EPC contractor ranking24 November 2025

The oil, gas and petrochemical engineering, procurement and construction (EPC) sector in the Middle East and North Africa (Mena) has enjoyed another strong year in historical terms.This remains true even though the total value of awards in 2025 – $62.5bn as of the first week of November – looks set to fall short of the record highs of $86bn in 2023 and $95bn in 2024. The level of market activity nevertheless remains well above the long-term average of $46bn and the 10-year average of $50bn.
Looking beyond the top line, the most notable trend of the year is the outsized success of India’s Larsen & Toubro (L&T) in securing many of the largest recent schemes in Saudi Arabia and Qatar.
Chinese contractors have also made steady progress in increasing their market share. Some industry stalwarts, by contrast, have seen considerably less success.
While some of this can be attributed to the cyclical nature of tendering and more selective bidding by established players with already large order books, MEED’s ranking of total execution values bears out the broader trends.

L&T’s dramatic surge
The most dramatic shift in the EPC landscape over the past 12 months (Q4 2024-Q3 2025) has been a $12.7bn surge in awards secured by L&T. This rapid expansion of its value of work under execution to $25.4bn has brought the company to within one place of the top of MEED’s EPC contractor rankings – falling just shy of the $26.9bn currently being executed by Italy’s Saipem.
L&T’s recent successes include the March win of the $4bn combined package 4A and 4B (Comp4) of QatarEnergy LNG’s North Field Production Sustainability programme – the largest project awarded during the period. L&T also won the $2.5bn fifth natural gas liquids train (NGL-5) project from QatarEnergy, and four separate contracts worth more than $1bn each with Saudi Aramco.
These wins built on an already burgeoning order book – one that also includes the $3.6bn phase 2: package 1 of the Jafurah gas treatment facility, awarded by Aramco in September 2023.
L&T’s rise has also been helped by relative inactivity among other top firms. Both Saipem and Italy’s Maire Tecnimont achieved prominent ranking positions a year earlier after securing, respectively, the $8.2bn offshore and $8.7bn onshore packages of Adnoc’s Hail and Ghasha programme in October 2023. Those awards, together with other contracts, saw the two Italian firms secure roughly $12bn in awards each in a single 12‑month stretch, catapulting them up the ranking.
However, neither company has added significantly to their pools of work over the past 12 months, in sharp contrast with L&T, which has seized momentum in the regional contracting landscape. So far, L&T has displaced Maire Tecnimont to reach second place regionally; another year of even marginally comparable momentum should put it at the top.
Also notable is the gap between L&T’s total awards over the past 12 months and those of its nearest competitors. L&T’s $12.7bn in wins rivals the combined value of the next three largest EPC contractors. As a share of an estimated $70bn in total awards across the sector over the same period, L&T secured about 18% of the work.The previous year, Saipem and Maire Tecnimont each secured closer to 12% of awards. This underlines L&T’s considerable momentum both in terms of its order book and market share growth.
Chinese push
Two other significant winners over the past 12 months are China Petroleum Engineering & Construction Corporation (CPECC) and China Offshore Oil Engineering Company (COOEC), which secured $5bn and $4.3bn-worth of awards, respectively.
These contracts wins have moved the two Chinese firms up into the top 20 EPC contractors. CPECC’s success is largely attributable to the niche it has developed in Iraq and Algeria, where about $4.4bn of its awards were won – led by a $1.6bn contract to deliver the central gas complex for Basra Oil Company’s Artawi development.
COOEC’s recent wins have been concentrated in the GCC, specifically on phases one and two of QatarEnergy’s Bul Hanine offshore oil field expansion, which are worth a combined $4bn.
The US’ McDermott and Spain’s Tecnicas Reunidas – two long-term regional players – recorded the next strongest order-book additions, securing about $3.8bn and $3.4bn, respectively. McDermott’s new work includes the $2bn phase two of Adnoc Offshore’s Umm Shaif long‑term development plan and a $1.8bn contract to lay offshore pipelines and subsea power cables for QatarEnergy LNG’s North Field South programme.
The next five biggest bookers over the period were South Korea’s Samsung C&T and Samsung E&A, the UAE’s Lamprell and Target Engineering, and Qatar’s Doha Petroleum Construction Company (DOPET) – each securing more than $2bn.
Samsung C&T’s top award was for QatarEnergy’s $2.5bn carbon sequestration complex; Samsung E&A’s was for Taziz Chemicals’ $1.7bn methanol plant in phase one of its industrial chemicals zone.
Lamprell secured five separate contracts from Saudi Aramco, the largest a $1.5bn award for offshore infrastructure on the Zuluf development.
Target secured three UAE contracts, led by a $1.5bn award from Adnoc Offshore for phase five of its Das Island terminal facilities (part of the Lower Zakum long‑term development).
DOPET secured two contracts from QatarEnergy, led by a $2bn award for phase three of the Bul Hanine offshore oil field expansion.
Across the activity, it remains conspicuous how rapidly values fall away from the top winners and how concentrated the recent awards are with L&T. While the contraction in total award value may partly explain this dynamic, the broader trend is clear: the concentration of work with L&T makes it the company to watch in regional bidding rounds in the year ahead.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15140734/main.gif -
Chinese firm signs deal for Algerian steel project24 November 2025
China’s Sinomach Heavy Equipment has signed a contract to develop a steel rolling facility in Algeria.
The project will be executed by its subsidiary, China National Heavy Machinery Corporation (CNHMC).
The turnkey contract includes planning, design, equipment supply, construction, installation and commissioning.
The scope of the project includes:
- A rolling mill production line
- Auxiliary facilities
- Steel structure workshops
In a statement, CNHMC said: “The signing of this contract marks a new stage in the company's market expansion in the African metallurgical sector.
“CNHMC will fully leverage its technological and management advantages in the metallurgical field, strictly control the project's quality and schedule, and strive to complete and deliver the project on schedule with high quality and high standards, making it a benchmark project in the Algerian market.”
The company said it will use its regional headquarters in Turkiye to ramp up its activities in the Algerian market and other neighbouring countries.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15139865/main3657.jpg -
Contractors submit Riyadh Expo infrastructure bids24 November 2025

Register for MEED’s 14-day trial access
Saudi Arabia’s Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, received commercial bids from contractors on 23 November for the tender to undertake the initial infrastructure works at the site.
The tender for the project’s initial infrastructure works was issued in September, MEED previously reported.
In October, MEED revealed that 16 firms had been invited to bid for the contract to undertake the initial infrastructure works at the Expo 2030 Riyadh site.
The firms invited to bid include:
- Shibh Al-Jazira Contracting (local)
- Hassan Allam Construction (Egypt)
- El-Seif Engineering Contracting (local)
- Al-Ayuni Investment & Contracting (local)
- Kolin Construction (Turkiye)
- Al-Yamama Trading & Contracting Company (local)
- Saudi Pan Kingdom (local)
- Unimac (local)
- Mapa Insaat (Turkiye)
- Yuksel Insaat (Turkiye)
- IC Ictas / Al-Rashid Trading & Contracting (Turkiye/local)
- Mota-Engil / Albawani (Portugal/local)
- Almabani / FCC Construction (local/Spain)
The overall infrastructure works – covering the construction of the main utilities and civil works at Expo 2030 Riyadh – will be split into three packages:
- Lot 1 covers the main utilities corridor
- Lot 2 includes the northern cluster of the nature corridor
- Lot 3 comprises the southern cluster of the nature corridor
In July, US-based engineering firm Bechtel Corporation announced it had won the project management consultancy deal for the delivery of the Expo 2030 Riyadh masterplan construction works.
The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, providing direct access to various landmarks within Riyadh.
Countries participating in Expo 2030 Riyadh will have the option to construct permanent pavilions. This initiative is expected to create opportunities for business and investment growth in the region.
The expo is forecast to attract more than 40 million visitors.
The Public Investment Fund (PIF), Saudi Arabia’s sovereign wealth vehicle, launched ERC in June as a wholly owned subsidiary to build and operate facilities for Expo 2030.
In a statement, the PIF said: “During its construction phases, Expo 2030 Riyadh and its legacy are projected to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs. Once operational, it is expected to contribute approximately $5.6bn to GDP.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/15140538/main.jpg
