UAE utilities ramp up capacity procurement

4 October 2024

Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) invited bids for contracts to develop three independent power producer (IPP) projects in rapid succession in the third quarter of 2024.

These projects comprise the 2,500GW Taweelah C combined-cycle gas turbine plant, the 1,500MW Madinat Zayed open-cycle gas turbine project and the 400MW battery energy storage system to be located in Al-Bihouth and Madinat Zayed.

They bring the number of Ewec’s electricity generation IPP projects currently under tender to four, in addition to the 1,500MW Al-Khazna solar photovoltaic (PV) IPP, which it tendered in April.

Ewec also issued the expression of interest notice on 1 October for a contract to develop the emirate’s fifth solar PV IPP, the 1,500MW Al-Zarraf project.

This robust project pipeline implies that the offtaker and developers, investors and contractors bidding for these projects have entered a hectic period compared to the past few years.

Abu Dhabi’s growing IPP pipeline will compete with Saudi Arabia’s equally robust pipeline for developers’ and contractors’ resources over the near to medium term as both states endeavour to meet their 2030 decarbonisation targets.

Abu Dhabi plans to procure 1,400MW of renewable energy capacity annually between 2027 and 2037 and to meet more than 50% of the emirate’s electricity demand from renewable and clean energy sources by 2030. This is expected to rise to 60% by 2035.

It also previously stated that it expects to reach a renewable energy installed capacity of 7,500MW by 2030, or three times its current capacity.

The expiry of power-purchase agreements for several generation assets over the next couple of years and the likelihood of these contracts not being extended also drive Abu Dhabi’s procurement programme for gas-fired capacity.

Dubai has a slightly different strategy. Dubai Electricity & Water Authority (Dewa) has abandoned any plans to procure additional gas-fired capacity in the foreseeable future.

Dubai’s future generation projects will be focused on the Mohammed Bin Rashid Solar Park, which is expected to reach an installed capacity of 5,000MW by 2030.

So far, Dewa has awarded contracts for the first six phases of the project, which have a total combined capacity of 4,600MW.

Further phases are being planned, with the state utility expected to appoint transaction advisers for phase seven, for which the capacity has not yet been made public, next year.

“The volume of projects coming to the market is almost unprecedented,” notes an industry source, who expects that utility developers are starting to be selective when bidding for new contracts regardless of the energy source.

Nuclear capacity

Notably, the UAE’s Federal Authority for Nuclear Regulation announced that the fourth reactor, or Unit 4, of the Barakah nuclear power plant in Abu Dhabi reached commercial operations in early September.

It marks the completion of the $43bn, 5,600MW Barakah 1 project, which was jointly implemented by the UAE’s Emirates Nuclear Energy Corporation (Enec) and South Korea’s Korea Electric Power Corporation (Kepco).

The entire plant reached full commercial operations approximately 16 years after Abu Dhabi first announced the project in 2008 and 12 years after construction works commenced on Unit 1.

The completion of Barakah 1 also implies that the project’s next phase is likely to proceed in earnest.

Hamad Alkaabi, the UAE’s permanent representative to the Austria-based International Atomic Energy Agency, said in July that the UAE government is considering initiating the tendering process for its next nuclear power plant this year.

Apart from the final tendering process decision, the market is also keen to know who will be invited to bid or submit proposals for the contract to implement the nuclear power facility’s next phase.

Washington and Abu Dhabi entered into the bilateral 123 Agreement for peaceful nuclear cooperation in 2009, which could determine to a large extent which companies or countries will be invited to participate in the project’s next phase.

What the rush is about

Ewec has made clear that expiring generation capacities and the need for gas-fired baseload as more renewable energy enters the UAE electricity grid underpin its ambitious capacity procurement pipeline.

Other factors influencing future capacity procurement plans include the UAE’s multibillion-dollar national industrialisation strategy. This strategy involves expanding downstream industries, including clean hydrogen production for both domestic and export use, potentially resulting in an exponential increase in peak demand.

This is in addition to the need to decarbonise while expanding the production of hard-to-abate sectors such as the oil and gas, steel and aluminium industries.

In addition to these demand sources, many believe the UAE’s 2031 National Artificial Intelligence (AI) Strategy is a major contributor to Abu Dhabi’s ongoing generation capacity buildout.

“They need to build power-hungry data centres to support their AI strategy,” notes an executive with an international infrastructure investment firm with offices in Dubai.

The UAE’s AI strategy encompasses deploying AI in priority sectors and “providing the data and infrastructure essential to become a test bed for AI”.

Meeting these and the other stated objectives, in addition to the data sovereignty regulations, has started driving a boom in data centre construction across the UAE.

State-backed enterprises, utilities, banks, logistics, tourism and service industries, and real estate companies have launched or are expected to launch AI programmes to boost productivity and efficiency, in line with the UAE’s 2050 net-zero target and circular carbon economy strategy.

These span industry-specific applications ranging from chatbots and small-language models to generative AI and large-language models, the latter of which require significant data bandwidth and consume enormous amounts of energy.

AI applications in defence and national security are also presumed to be a major component of the overall AI plan. 

“The AI programme is progressing,” notes an Abu Dhabi-based utility executive, confirming a plan to procure 5,000MW of AI-dedicated thermal capacity.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12650258/main.gif
Jennifer Aguinaldo
Related Articles
  • Kuwait awards $381m oil project

    23 September 2026

    Register for MEED’s 14-day trial access 

    State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).

    The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.

    The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.

    The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.

    The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.

    Meil will develop the new three-phase low-pressure wet separation facility at GC-25.

    The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.

    The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.

    Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.

    The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.

    At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.

    The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.

    Booster and injection pumps will transfer treated effluent water to designated injection wells.

    Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.

    The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.

    Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.

    Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.

    The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.

    Seven companies submitted bids for the project last November.

    The full list of bids was:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.

    Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg
    Wil Crisp
  • Kuwait refinery project on track for year-end completion

    23 September 2026

     

    A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.

    The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.

    One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).

    Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.

    The scope of the project includes:

    • Construction of a substation
    • Installation of transformers
    • Installation of medium-voltage switchgear
    • Installation of low-voltage auxiliary systems
    • Installation of network protection systems
    • Installation of disconnecting switches
    • Installation of surge arrestors
    • Installation of feeder breakers and cubicles
    • Installation of low-voltage A/C and D/C equipment
    • Installation of battery banks and battery chargers
    • Installation of related relay and control panel boards
    • Installation of fire alarm and fire protection equipment
    • Installation of a SCADA system
    • Installation of cables
    • Civil works
    • Associated facilities

    The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.

    On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.

    The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.

    Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.

    He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.

    Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg
    Wil Crisp
  • Contractor wins $208m Almoosa hospital MEP contract

    23 September 2026

    Register for MEED’s 14-day trial access 

    Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.

    Saudi Arabia’s Almoosa Health Company awarded the contract.

    The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.

    It will be built on a 45,000-square-metre site.

    A podium spanning the ninth and 10th floors will connect the two towers.

    The hospital will also include parking for 1,700 cars.

    BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.

    In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.

    In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.

    Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg
    Yasir Iqbal
  • UAE to develop integrated waste-to-resource pilot

    23 September 2026

    Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.

    The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.

    Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.

    Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.

    The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.

    A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.

    Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.

    The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.

    If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.

    The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg
    Mark Dowdall
  • Contractors prepare Oxagon Highway 55 bids

    23 September 2026

     

    Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.

    The project duration is 22 months.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
    Yasir Iqbal