UAE utilities ramp up capacity procurement
4 October 2024
Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) invited bids for contracts to develop three independent power producer (IPP) projects in rapid succession in the third quarter of 2024.
These projects comprise the 2,500GW Taweelah C combined-cycle gas turbine plant, the 1,500MW Madinat Zayed open-cycle gas turbine project and the 400MW battery energy storage system to be located in Al-Bihouth and Madinat Zayed.
They bring the number of Ewec’s electricity generation IPP projects currently under tender to four, in addition to the 1,500MW Al-Khazna solar photovoltaic (PV) IPP, which it tendered in April.
Ewec also issued the expression of interest notice on 1 October for a contract to develop the emirate’s fifth solar PV IPP, the 1,500MW Al-Zarraf project.
This robust project pipeline implies that the offtaker and developers, investors and contractors bidding for these projects have entered a hectic period compared to the past few years.
Abu Dhabi’s growing IPP pipeline will compete with Saudi Arabia’s equally robust pipeline for developers’ and contractors’ resources over the near to medium term as both states endeavour to meet their 2030 decarbonisation targets.
Abu Dhabi plans to procure 1,400MW of renewable energy capacity annually between 2027 and 2037 and to meet more than 50% of the emirate’s electricity demand from renewable and clean energy sources by 2030. This is expected to rise to 60% by 2035.
It also previously stated that it expects to reach a renewable energy installed capacity of 7,500MW by 2030, or three times its current capacity.
The expiry of power-purchase agreements for several generation assets over the next couple of years and the likelihood of these contracts not being extended also drive Abu Dhabi’s procurement programme for gas-fired capacity.
Dubai has a slightly different strategy. Dubai Electricity & Water Authority (Dewa) has abandoned any plans to procure additional gas-fired capacity in the foreseeable future.
Dubai’s future generation projects will be focused on the Mohammed Bin Rashid Solar Park, which is expected to reach an installed capacity of 5,000MW by 2030.
So far, Dewa has awarded contracts for the first six phases of the project, which have a total combined capacity of 4,600MW.
Further phases are being planned, with the state utility expected to appoint transaction advisers for phase seven, for which the capacity has not yet been made public, next year.
“The volume of projects coming to the market is almost unprecedented,” notes an industry source, who expects that utility developers are starting to be selective when bidding for new contracts regardless of the energy source.
Nuclear capacity
Notably, the UAE’s Federal Authority for Nuclear Regulation announced that the fourth reactor, or Unit 4, of the Barakah nuclear power plant in Abu Dhabi reached commercial operations in early September.
It marks the completion of the $43bn, 5,600MW Barakah 1 project, which was jointly implemented by the UAE’s Emirates Nuclear Energy Corporation (Enec) and South Korea’s Korea Electric Power Corporation (Kepco).
The entire plant reached full commercial operations approximately 16 years after Abu Dhabi first announced the project in 2008 and 12 years after construction works commenced on Unit 1.
The completion of Barakah 1 also implies that the project’s next phase is likely to proceed in earnest.
Hamad Alkaabi, the UAE’s permanent representative to the Austria-based International Atomic Energy Agency, said in July that the UAE government is considering initiating the tendering process for its next nuclear power plant this year.
Apart from the final tendering process decision, the market is also keen to know who will be invited to bid or submit proposals for the contract to implement the nuclear power facility’s next phase.
Washington and Abu Dhabi entered into the bilateral 123 Agreement for peaceful nuclear cooperation in 2009, which could determine to a large extent which companies or countries will be invited to participate in the project’s next phase.
What the rush is about
Ewec has made clear that expiring generation capacities and the need for gas-fired baseload as more renewable energy enters the UAE electricity grid underpin its ambitious capacity procurement pipeline.
Other factors influencing future capacity procurement plans include the UAE’s multibillion-dollar national industrialisation strategy. This strategy involves expanding downstream industries, including clean hydrogen production for both domestic and export use, potentially resulting in an exponential increase in peak demand.
This is in addition to the need to decarbonise while expanding the production of hard-to-abate sectors such as the oil and gas, steel and aluminium industries.
In addition to these demand sources, many believe the UAE’s 2031 National Artificial Intelligence (AI) Strategy is a major contributor to Abu Dhabi’s ongoing generation capacity buildout.
“They need to build power-hungry data centres to support their AI strategy,” notes an executive with an international infrastructure investment firm with offices in Dubai.
The UAE’s AI strategy encompasses deploying AI in priority sectors and “providing the data and infrastructure essential to become a test bed for AI”.
Meeting these and the other stated objectives, in addition to the data sovereignty regulations, has started driving a boom in data centre construction across the UAE.
State-backed enterprises, utilities, banks, logistics, tourism and service industries, and real estate companies have launched or are expected to launch AI programmes to boost productivity and efficiency, in line with the UAE’s 2050 net-zero target and circular carbon economy strategy.
These span industry-specific applications ranging from chatbots and small-language models to generative AI and large-language models, the latter of which require significant data bandwidth and consume enormous amounts of energy.
AI applications in defence and national security are also presumed to be a major component of the overall AI plan.
“The AI programme is progressing,” notes an Abu Dhabi-based utility executive, confirming a plan to procure 5,000MW of AI-dedicated thermal capacity.
Exclusive from Meed
-
Jordan allows phosphate rail line bidders more time30 January 2026
-
Acwa Power to develop $200m solar plant in Philippines30 January 2026
-
Algeria plans Constantine tramway extension30 January 2026
-
Dewa desalination plans offer timely boost30 January 2026
-
Projects show resilience in 202630 January 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Jordan allows phosphate rail line bidders more time30 January 2026

Abu Dhabi’s National Infrastructure Construction Company (NICC), a subsidiary of Etihad Rail, has allowed contractors until 15 February to submit their proposals for a contract to build the second section of the phosphate railway line that will run from Ghor Al-Safi to Aqaba in Jordan.
The tender was issued on 27 December, with an initial bid submission deadline of the end of January.
The scope of work for the railway includes civil engineering, tunnel construction, and mechanical, electrical and plumbing (MEP) works.
Tendering is also ongoing for the first section of the line. NICC is preparing to award the contract for the first section of the railway line, stretching from Al-Shidiya to Aqaba.
MEED understands that the evaluation is in its final stages and that the contract will be awarded soon.
In April last year, a French-Swiss joint venture of Egis and Arx was awarded the design consultancy contract for the project.
Etihad Rail announced in September 2024 that it had signed a memorandum of understanding (MoU) worth $2.3bn with Jordan’s Transport Ministry and local companies to develop the phosphate railway line.
In an official statement, Etihad Rail said it had signed an agreement with Jordan to build, operate and maintain the project.
The statement added that additional MoUs were signed with Jordan Phosphate Mines Company and Arab Potash Company to transport 16 million tonnes a year of phosphate and potash from mining sites to the Port of Aqaba via the Jordanian railway network.
The MoUs also cover the manufacture and supply of rolling stock; the construction of terminals in Aqaba, Ghor Al-Safi and Shidiya; and the maintenance, repair and operation of the railway line.
Project history
In 2015, Jordan’s Transport Ministry tendered a contract to construct the Shidiya rail link, intended to transport 6 million tonnes a year of phosphate from mines in Shidiya to Wadi Al-Yutum, near Aqaba.
In November of that year, a joint venture of China Communications Construction Company and the local contractor Masar United was confirmed as the lowest bidder. It was awaiting the formal award to build the 21-kilometre spur line.
The project was subsequently put on hold due to funding issues.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15541534/main.jpg -
Acwa Power to develop $200m solar plant in Philippines30 January 2026
Saudi Arabia’s Acwa Power is investing $200m to build a large-scale solar photovoltaic (PV) plant in the Philippines.
The renewables developer finalised the agreement with the Philippine government-owned Bases Conversion & Development Authority (BCDA) on the sidelines of the World Economic Forum in Davos last week.
Under the reservation agreement, a 500-hectare site has been selected within the New Clark City Special Economic Zone in Tarlac province, north of Manila.
The project must undergo a pre-feasibility study, technical assessments and regulatory approvals before any final investment decision is made.
The collaboration will also explore “potential battery energy storage system (Bess) integration,” Acwa Power said in a statement.
No details were provided on the project’s potential power generation capacity.
The reservation agreement follows a memorandum of understanding (MoU) signed between Acwa Power and BCDA in Riyadh last November.
Since then, the partners have evaluated multiple locations in New Clark City and shortlisted the 500-hectare site for further technical and commercial evaluation.
Acwa Power said it is targeting a threefold increase in its global assets under management to $250bn by 2030.
The company currently has a global renewables portfolio of 52GW, accounting for 56% of its total power capacity, and plans to deploy 5.6GWh of battery energy storage capacity.
As part of its foreign investment plans, the company also recently signed major agreements for large-scale renewable energy projects in Uzbekistan.
This comprised $1.8bn in financing for the Samarkand solar and battery energy storage project, Uzbekistan’s biggest solar development.
The project is being developed in partnership with Japan’s Sumitomo Corporation, Chubu Electric Power and Shikoku Electric Power.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15541146/main.jpg -
Algeria plans Constantine tramway extension30 January 2026

Algeria is planning another extension of its Constantine tramway network, which currently runs from Ben Abdelmalek Stadium in the city centre to the Ali Mendjeli area.
The project client, Algiers Metro Company (EMA), received bids on 14 December last year from consultants for a tender to undertake feasibility and detailed preliminary design studies for the project.
The client had tendered the contract in October.
The current tramway network spans approximately 19.3 kilometres (km).
The tramway is owned by EMA and operated by Societe d’Exploitation des Tramways (Setram), a joint venture of EMA and French firm RATP Group.
The first route of the tramway, with a length of 9km, was commissioned in July 2013, according to GlobalData’s sister company, Railway Technology.
The expansion phase began in July 2015 and was completed in June 2019, increasing total ridership to over 30,000 passengers a day.
The initial 9km-long section of the Constantine tramway system runs from the Zouaghi terminal to the Ben-Abdelmalek Stadium station through the old town and the university area.
The route includes 11 stations, three of which are multimodal, two viaducts measuring 465m and 114m long, and an underpass.
A 65,000-square-metre ground-level depot serves the fleet for maintenance and train parking.
The Ben-Abdelmalek Stadium was renovated as part of the project to accommodate the line's passage.
Contractors involved
EMA awarded a contract for the tramway line extension to France’s Alstom and the local firm Cosider Travaux Publics consortium in July 2015.
Spanish firm Idom was awarded the detailed design and construction works management, while US-based engineering firm Aecom was responsible for civil engineering and urban planning.
Cital, a joint venture of EMA, Spain’s Ferrovial and Alstom, delivered 24 trainsets to open the first phase of the extension in 2019.
The company also maintains 51 trainsets and the infrastructure of the Constantine tramway.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15540773/main.jpg -
Dewa desalination plans offer timely boost30 January 2026
Commentary
Mark Dowdall
Power & water editorDubai Electricity & Water Authority (Dewa) is taking early steps towards procuring its second independent water producer (IWP) project, a signal that the utility may be further expanding its role from service provider to long-term utility asset developer.
Consultancy bids were received this week for a pre-feasibility study that will assess capacity and location requirements for a planned seawater reverse osmosis (SWRO) desalination plant.
The project, being pursued with Etihad Water & Electricity (EtihadWE), would build on the 180-million-imperial-gallons-a-day Hassyan IWP, awarded to Saudi Arabia’s Acwa Power in 2024.
It would also align with Dewa’s wider objective to lift Dubai’s desalination capacity to 750 million imperial gallons a day by 2030, from around 495 million today. Achieving that target may require a further pipeline of privately developed water assets between now and then.
A useful point of comparison lies in Saudi Arabia’s power sector. Saudi Electricity Company has increasingly relied on independent power producers over the past decade to accelerate capacity expansion, ease pressure on public capital spending and deepen the project finance ecosystem.
For regional developers, competition in Saudi Arabia’s water market continues to intensify. In December, Saudi Water Partnership Company (SWPC) prequalified 50 developers to bid for five upcoming IWPs and 63 developers for independent sewage treatment plant (ISTP) projects.
Unlike Saudi Arabia, the UAE entered 2026 with limited visible momentum in desalination. EtihadWE’s $400m Fujairah SWRO IWP is the only large desalination plant expected to be tendered this year.
In a crowded market, increased activity by Dubai’s utility would provide a welcome boost.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15540724/main.jpg -
Projects show resilience in 202630 January 2026

While priorities may have shifted over the past two years, the region’s projects market continues to display resilience and will offer opportunities in 2026 in areas including Saudi Arabia’s gigaprojects progamme, regional rail schemes and other strategic sectors.
Despite much having been written over the past two years about the reprioritisation of Saudi Arabia’s gigaprojects, work is continuing.
“They are still going, all the gigaprojects,” says Pierre Santoni, president – infrastructure for Europe, Middle East and Africa (Emea) at US-based Parsons.
“Even Neom, where the slowdown has been widely publicised, we still have people there working on Oxagon, and we still have people on the Line. All the other ones are still ongoing,” he adds. “We just signed a contract to design all the infrastructure around the Mukaab for New Murabba. We have live tenders and are designing the public realm for Diriyah Gate 2. We are on Sports Boulevard, King Salman Park and the expansion of King Abdullah Financial District. All of those are ongoing.”
Another focus for the region is rail. Parsons led the Riyadh Metro Transit Consultants joint venture that project managed the first six lines of Riyadh Metro, which opened in late 2024. “Riyadh Metro was a great success for Parsons and our partners, and all the people involved. That was the original gigaproject. At one point, there were 50,000 workers on Riyadh Metro every day,” says Santoni.
The success of this project, and of earlier schemes such as Dubai Metro and Doha Metro, combined with high-level governmental backing, have given the rail sector in the region unprecedented momentum.
“Rail is a major market in the region at the moment,” says Santoni. “The UAE is a good example – you have the freight railway and the opening of passenger traffic. The high-speed rail project has also started. In Abu Dhabi, the tram on Yas Island was launched last year. In Dubai, the Blue Line is in full construction mode with delivery firmly scheduled for 2029. It is a major undertaking, and the intention of the Roads & Transport Authority is to continue with further extensions, which is much needed given the growth in population.”
Roads and airports are two other areas of focus for Parsons. The company continues to work as the lead consultant for major road schemes in the UAE, and it secured delivery partner roles in 2025 for the airside and landside infrastructure at Riyadh’s King Salman International airport.
Operations and maintenance
The infrastructure market is not just about building new projects. As the region’s infrastructure ages, operations and maintenance (O&M) has become a central pillar of Parsons’ strategy, Santoni notes.
“The game is not just about building new infrastructure; it’s about making existing infrastructure perform better,” he says.
“A lot of O&M considerations are coming to the forefront. We are deploying technology like iNET, which is Parsons’ proprietary intelligent traffic management system. We did the initial feasibility study last year and managed to improve transit times through 320 intersections in Riyadh. We just signed a contract to fully deploy the system.
The game is not just about building new infrastructure; it’s about making existing infrastructure perform better
“It’s not just physical infrastructure; it’s the management of all that through technology-enabled tools.”
Santoni says this technological “brain” is also being applied to the King Salman Park project, which involves developing the world’s largest urban park and requires a highly complex O&M system to manage it effectively. Automated management of soil and water for hundreds of plant species will remove the need for a vast on-site workforce.
Traditionally known for core engineering and transport, Parsons is increasingly recognised for work in other sectors, including hospitality and defence. The firm is currently managing over 30,000 luxury hotel keys in the region, a surge driven by Saudi Arabia’s tourism goals.
“We became recognised, sort of unknowingly, for these complex, niche-type hospitality projects where it’s about preserving heritage and respecting culture, but doing so in the most modern and technologically advanced way possible. This is going to be a very nice market for us in the future,” Santoni says.
“We also signed two major contracts last year for confidential defence clients in Saudi Arabia to deliver infrastructure.”
Capacity crunch
As the industry faces a talent shortage, Santoni highlights Parsons’ internal mobility as a competitive advantage. While competitors have struggled with project transitions, Parsons has focused on relocating staff to sustain its growth.
“We did see a lot of people either exiting Saudi Arabia or relocating within,” Santoni says. “We have been very good at relocating people. This is one of our strengths. When projects changed pace, we made a conscious effort to relocate people, give them options and extend them on the job until something else came up. Last year alone, about 350 people were relocated internally within the region. We are still in hiring mode.”
Being a multidisciplinary firm present in several countries gives flexibility. “In Saudi Arabia, most of Parsons’ work has traditionally been project management consultancy (PMC), although we have had for a number of years now a growing design office in Riyadh with an offshoot in Dammam and one in Jeddah.
“We currently have almost 300 people in our design office in Saudi Arabia, which is slightly less than 10% of our workforce in the kingdom. The rest are doing PMC work. In Dubai, Abu Dhabi, Doha, it’s mostly the more traditional model of design and construction supervision work with some PMC,” says Santoni.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15527825/main.jpg