UAE utilities ramp up capacity procurement
4 October 2024
Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) invited bids for contracts to develop three independent power producer (IPP) projects in rapid succession in the third quarter of 2024.
These projects comprise the 2,500GW Taweelah C combined-cycle gas turbine plant, the 1,500MW Madinat Zayed open-cycle gas turbine project and the 400MW battery energy storage system to be located in Al-Bihouth and Madinat Zayed.
They bring the number of Ewec’s electricity generation IPP projects currently under tender to four, in addition to the 1,500MW Al-Khazna solar photovoltaic (PV) IPP, which it tendered in April.
Ewec also issued the expression of interest notice on 1 October for a contract to develop the emirate’s fifth solar PV IPP, the 1,500MW Al-Zarraf project.
This robust project pipeline implies that the offtaker and developers, investors and contractors bidding for these projects have entered a hectic period compared to the past few years.
Abu Dhabi’s growing IPP pipeline will compete with Saudi Arabia’s equally robust pipeline for developers’ and contractors’ resources over the near to medium term as both states endeavour to meet their 2030 decarbonisation targets.
Abu Dhabi plans to procure 1,400MW of renewable energy capacity annually between 2027 and 2037 and to meet more than 50% of the emirate’s electricity demand from renewable and clean energy sources by 2030. This is expected to rise to 60% by 2035.
It also previously stated that it expects to reach a renewable energy installed capacity of 7,500MW by 2030, or three times its current capacity.
The expiry of power-purchase agreements for several generation assets over the next couple of years and the likelihood of these contracts not being extended also drive Abu Dhabi’s procurement programme for gas-fired capacity.
Dubai has a slightly different strategy. Dubai Electricity & Water Authority (Dewa) has abandoned any plans to procure additional gas-fired capacity in the foreseeable future.
Dubai’s future generation projects will be focused on the Mohammed Bin Rashid Solar Park, which is expected to reach an installed capacity of 5,000MW by 2030.
So far, Dewa has awarded contracts for the first six phases of the project, which have a total combined capacity of 4,600MW.
Further phases are being planned, with the state utility expected to appoint transaction advisers for phase seven, for which the capacity has not yet been made public, next year.
“The volume of projects coming to the market is almost unprecedented,” notes an industry source, who expects that utility developers are starting to be selective when bidding for new contracts regardless of the energy source.
Nuclear capacity
Notably, the UAE’s Federal Authority for Nuclear Regulation announced that the fourth reactor, or Unit 4, of the Barakah nuclear power plant in Abu Dhabi reached commercial operations in early September.
It marks the completion of the $43bn, 5,600MW Barakah 1 project, which was jointly implemented by the UAE’s Emirates Nuclear Energy Corporation (Enec) and South Korea’s Korea Electric Power Corporation (Kepco).
The entire plant reached full commercial operations approximately 16 years after Abu Dhabi first announced the project in 2008 and 12 years after construction works commenced on Unit 1.
The completion of Barakah 1 also implies that the project’s next phase is likely to proceed in earnest.
Hamad Alkaabi, the UAE’s permanent representative to the Austria-based International Atomic Energy Agency, said in July that the UAE government is considering initiating the tendering process for its next nuclear power plant this year.
Apart from the final tendering process decision, the market is also keen to know who will be invited to bid or submit proposals for the contract to implement the nuclear power facility’s next phase.
Washington and Abu Dhabi entered into the bilateral 123 Agreement for peaceful nuclear cooperation in 2009, which could determine to a large extent which companies or countries will be invited to participate in the project’s next phase.
What the rush is about
Ewec has made clear that expiring generation capacities and the need for gas-fired baseload as more renewable energy enters the UAE electricity grid underpin its ambitious capacity procurement pipeline.
Other factors influencing future capacity procurement plans include the UAE’s multibillion-dollar national industrialisation strategy. This strategy involves expanding downstream industries, including clean hydrogen production for both domestic and export use, potentially resulting in an exponential increase in peak demand.
This is in addition to the need to decarbonise while expanding the production of hard-to-abate sectors such as the oil and gas, steel and aluminium industries.
In addition to these demand sources, many believe the UAE’s 2031 National Artificial Intelligence (AI) Strategy is a major contributor to Abu Dhabi’s ongoing generation capacity buildout.
“They need to build power-hungry data centres to support their AI strategy,” notes an executive with an international infrastructure investment firm with offices in Dubai.
The UAE’s AI strategy encompasses deploying AI in priority sectors and “providing the data and infrastructure essential to become a test bed for AI”.
Meeting these and the other stated objectives, in addition to the data sovereignty regulations, has started driving a boom in data centre construction across the UAE.
State-backed enterprises, utilities, banks, logistics, tourism and service industries, and real estate companies have launched or are expected to launch AI programmes to boost productivity and efficiency, in line with the UAE’s 2050 net-zero target and circular carbon economy strategy.
These span industry-specific applications ranging from chatbots and small-language models to generative AI and large-language models, the latter of which require significant data bandwidth and consume enormous amounts of energy.
AI applications in defence and national security are also presumed to be a major component of the overall AI plan.
“The AI programme is progressing,” notes an Abu Dhabi-based utility executive, confirming a plan to procure 5,000MW of AI-dedicated thermal capacity.
Exclusive from Meed
-
Egypt approves plans for 869MW wind power plant22 June 2026
-
Local firm signs Jeddah drainage contracts22 June 2026
-
Qiddiya seeks contractors for indoor arena project22 June 2026
-
Egypt signs gas deal with Harbour Energy22 June 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Egypt approves plans for 869MW wind power plant22 June 2026
Egypt’s Cabinet has approved plans for French renewable energy developer Voltalia to develop an 869MW wind power project.
The scheme will be built on land allocated by the New & Renewable Energy Authority (NREA), according to a statement posted by the Cabinet following its most recent weekly meeting.
Voltalia will make an initial investment of $53m and has committed to achieving commercial operations by December 2028.
Voltalia already operates the 32MW Ra solar plant at the Benban solar complex in Aswan and is expanding its renewable energy portfolio in Egypt.
Previously, in 2024, it signed a framework agreement with Egypt’s Taqa Arabia to develop a green hydrogen and renewable power cluster near the Ain Sokhna port in the Suez Canal Economic Zone.
The green hydrogen development is planned in two phases, each centred on a 500MW electrolyser powered by more than 1.3GW of renewable generation capacity. The project, still in its early stages, is expected to produce up to 350,000 tonnes of green ammonia a year.
Voltalia’s partnership with Taqa Arabia also includes plans for a 3.2GW hybrid wind and solar project to repower the existing 545MW Zafarana wind farm in Suez Governorate. The Cabinet statement did not indicate whether the newly approved 869MW wind project forms part of that proposal.
Meanwhile, the developer won another contract, earlier this year, to develop a 132MW solar power project in Tunisia’s Gabes region.
The project, known as Wadi, marked Voltalia’s third major solar award in the country after the Sagdoud and Menzel Habib projects awarded in 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17376730/main.jpg -
Local firm signs Jeddah drainage contracts22 June 2026
Local contractor Alkhorayef Water & Power Technologies (AWPT) has announced it has signed two contracts with Jeddah Municipality to operate and maintain stormwater and surface water drainage networks across the city.
The contracts have a combined value of SR202.06m ($53.9m), and each will run for five years.
The first contract, valued at SR108.46m ($28.9m), covers the operation and cleaning of stormwater and surface water networks in the South and Al-Malisa sub-municipalities.
The second contract, worth SR93.59m ($25m), covers similar services for the Airport Sub-Municipality.
In March, MEED reported that the firm had won a long-term contract to carry out work in the airport’s sub-municipality area. The agreement was signed on 16 June.
Elsewhere, construction has yet to begin on phases one and two of the King Abdullah Road-Falasteen Road tunnel project, each valued at about $175m.
According to sources, Jeddah Municipality selected Saudi contractor Thrustboring Construction Company to build the large-diameter stormwater drainage tunnels in 2025. However, an official agreement has yet to be signed.
The municipality was also previously planning to rehabilitate the existing Al-Zahra pumping station. Prequalification for the project began in 2020; however, it is understood that the main contact tender was cancelled last year.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17376097/main.jpg -
Qiddiya seeks contractors for indoor arena project22 June 2026

Register for MEED’s 14-day trial access
Saudi Arabian gigaproject developer Qiddiya Investment Company (QIC) has invited contractors to prequalify for a contract to build an indoor sports arena within its Qiddiya entertainment city project.
The invitation was issued on 21 May, with a submission deadline of 28 June.
The multipurpose arena is designed to International Olympic Committee standards.
It will be located in District 18, in the Uptown South area of Qiddiya.
Once completed, the indoor arena will be capable of hosting a wide range of sports, cultural and entertainment events.
The arena will feature numerous sports courts for basketball, handball, futsal, volleyball, tennis, boxing and gymnastics.
It will have a seating capacity of 18,000 spectators.
The project is scheduled for completion by 2030.
QIC’s other major projects include an e-sports arena, the National Tennis Centre, Prince Mohammed Bin Salman Stadium, a motorsports track, a racecourse, the Dragon Ball and Six Flags theme parks, and Aquarabia.
QIC opened the Six Flags theme park to the public in December last year.
The park covers 320,000 square metres and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.
The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17375504/main.jpg -
Egypt signs gas deal with Harbour Energy22 June 2026
Egypt’s Ministry of Petroleum & Mineral Resources has signed a new agreement with London-headquartered Harbour Energy.
Under the scope of the agreement, Harbour Energy will drill two new exploration wells and carry out maintenance work for one of the existing wells within the Dsouq-1 development contract.
Harbour Energy committed an initial $6m investment and a $1m signing bonus for the Dsouq concession. Total investment could rise to $18m if commercial discoveries are made.
The signing was witnessed by Egypt’s Minister of Petroleum, Karim Badawi.
He said that his ministry is continuing to implement a package of investment measures and incentives aimed at encouraging partners to increase investments and intensify exploration, development and production activities.
The agreement was signed by Syed Saleem, a member of the executive branch of the state-owned Egyptian Natural Gas Holding Company (EGAS), and Samah Sabry, the executive director of Harbour Energy for the Middle East and North Africa region.
Harbour Energy drilled two new wells in Egypt during the fiscal year 2025/2026, resulting in the addition of reserves estimated at 35 billion cubic feet of gas.
The company aims to drill three new exploration wells during the fiscal year 2026/2027.
Egypt is currently pushing to boost the production of both oil and gas in its territory.
Earlier this month, Egypt’s Ministry of Petroleum & Mineral Resources announced that it had fully settled all outstanding arrears owed to oil and gas companies.
Two years ago, in June 2024, the country owed approximately $6.1bn to partners in the oil and gas sector.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17374536/main4731.jpg -
Iran invites companies to register for Kharg Oil Terminal development22 June 2026

Iran has invited companies to participate in a project to develop the existing Kharg Oil Terminal, according to documents released by the state-owned National Iranian Oil Company and Iranian Oil Terminals Company.
The project focuses on developing units capable of receiving, storing and exporting extra-heavy West Karun crude oil at a rate of 700,000 barrels a day.
The scope of the project includes design, purchase, installation and commissioning of the new facility.
The contract will use the engineering, procurement and construction (EPC) model, according to the tender documents.
The project aims to use existing oil storage tanks and reconstruct the deepwater crude oil export berth known as Berth Number One.
The berth known as Berth Number Three will serve as a backup berth for the project.
The winning bidder for the contract will be responsible for a range of works, including:
- Carrying out all stages of verification of the project’s basic design, design and engineering
- Supply and procurement of goods and materials
- Execution and installation
- Pre-commissioning and commissioning
The project is expected to take 30 months to complete, and the winning contractor will also be responsible for maintaining the facility for a further 12 months.
Companies that wish to submit bids need to do so through Iran’s Government Electronic Procurement System (Setad).
Companies interested in participating in the tender have seven days from the publication of the tender notice to receive the documents.
They then have a further 14 days to upload the required documents into the government procurement system.
Iran exports most of its oil via the Kharg Oil Terminal on Kharg Island.
US President Donald Trump said strikes in mid-March “obliterated” Kharg’s military assets but did not target the island’s oil infrastructure.
He warned that if Iran continued disrupting traffic through the Strait of Hormuz, he would reconsider the decision to spare energy targets on the island.
Trump has threatened several times to take “control” of Kharg Island, but he has not yet followed through on this threat.
The small coral island is located 33 kilometres from Iran’s coast and has strategic importance because Iran’s coastline is mostly too shallow for large tanker ships to dock.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17374518/main.jpg
