UAE utilities ramp up capacity procurement
4 October 2024
Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) invited bids for contracts to develop three independent power producer (IPP) projects in rapid succession in the third quarter of 2024.
These projects comprise the 2,500GW Taweelah C combined-cycle gas turbine plant, the 1,500MW Madinat Zayed open-cycle gas turbine project and the 400MW battery energy storage system to be located in Al-Bihouth and Madinat Zayed.
They bring the number of Ewec’s electricity generation IPP projects currently under tender to four, in addition to the 1,500MW Al-Khazna solar photovoltaic (PV) IPP, which it tendered in April.
Ewec also issued the expression of interest notice on 1 October for a contract to develop the emirate’s fifth solar PV IPP, the 1,500MW Al-Zarraf project.
This robust project pipeline implies that the offtaker and developers, investors and contractors bidding for these projects have entered a hectic period compared to the past few years.
Abu Dhabi’s growing IPP pipeline will compete with Saudi Arabia’s equally robust pipeline for developers’ and contractors’ resources over the near to medium term as both states endeavour to meet their 2030 decarbonisation targets.
Abu Dhabi plans to procure 1,400MW of renewable energy capacity annually between 2027 and 2037 and to meet more than 50% of the emirate’s electricity demand from renewable and clean energy sources by 2030. This is expected to rise to 60% by 2035.
It also previously stated that it expects to reach a renewable energy installed capacity of 7,500MW by 2030, or three times its current capacity.
The expiry of power-purchase agreements for several generation assets over the next couple of years and the likelihood of these contracts not being extended also drive Abu Dhabi’s procurement programme for gas-fired capacity.
Dubai has a slightly different strategy. Dubai Electricity & Water Authority (Dewa) has abandoned any plans to procure additional gas-fired capacity in the foreseeable future.
Dubai’s future generation projects will be focused on the Mohammed Bin Rashid Solar Park, which is expected to reach an installed capacity of 5,000MW by 2030.
So far, Dewa has awarded contracts for the first six phases of the project, which have a total combined capacity of 4,600MW.
Further phases are being planned, with the state utility expected to appoint transaction advisers for phase seven, for which the capacity has not yet been made public, next year.
“The volume of projects coming to the market is almost unprecedented,” notes an industry source, who expects that utility developers are starting to be selective when bidding for new contracts regardless of the energy source.
Nuclear capacity
Notably, the UAE’s Federal Authority for Nuclear Regulation announced that the fourth reactor, or Unit 4, of the Barakah nuclear power plant in Abu Dhabi reached commercial operations in early September.
It marks the completion of the $43bn, 5,600MW Barakah 1 project, which was jointly implemented by the UAE’s Emirates Nuclear Energy Corporation (Enec) and South Korea’s Korea Electric Power Corporation (Kepco).
The entire plant reached full commercial operations approximately 16 years after Abu Dhabi first announced the project in 2008 and 12 years after construction works commenced on Unit 1.
The completion of Barakah 1 also implies that the project’s next phase is likely to proceed in earnest.
Hamad Alkaabi, the UAE’s permanent representative to the Austria-based International Atomic Energy Agency, said in July that the UAE government is considering initiating the tendering process for its next nuclear power plant this year.
Apart from the final tendering process decision, the market is also keen to know who will be invited to bid or submit proposals for the contract to implement the nuclear power facility’s next phase.
Washington and Abu Dhabi entered into the bilateral 123 Agreement for peaceful nuclear cooperation in 2009, which could determine to a large extent which companies or countries will be invited to participate in the project’s next phase.
What the rush is about
Ewec has made clear that expiring generation capacities and the need for gas-fired baseload as more renewable energy enters the UAE electricity grid underpin its ambitious capacity procurement pipeline.
Other factors influencing future capacity procurement plans include the UAE’s multibillion-dollar national industrialisation strategy. This strategy involves expanding downstream industries, including clean hydrogen production for both domestic and export use, potentially resulting in an exponential increase in peak demand.
This is in addition to the need to decarbonise while expanding the production of hard-to-abate sectors such as the oil and gas, steel and aluminium industries.
In addition to these demand sources, many believe the UAE’s 2031 National Artificial Intelligence (AI) Strategy is a major contributor to Abu Dhabi’s ongoing generation capacity buildout.
“They need to build power-hungry data centres to support their AI strategy,” notes an executive with an international infrastructure investment firm with offices in Dubai.
The UAE’s AI strategy encompasses deploying AI in priority sectors and “providing the data and infrastructure essential to become a test bed for AI”.
Meeting these and the other stated objectives, in addition to the data sovereignty regulations, has started driving a boom in data centre construction across the UAE.
State-backed enterprises, utilities, banks, logistics, tourism and service industries, and real estate companies have launched or are expected to launch AI programmes to boost productivity and efficiency, in line with the UAE’s 2050 net-zero target and circular carbon economy strategy.
These span industry-specific applications ranging from chatbots and small-language models to generative AI and large-language models, the latter of which require significant data bandwidth and consume enormous amounts of energy.
AI applications in defence and national security are also presumed to be a major component of the overall AI plan.
“The AI programme is progressing,” notes an Abu Dhabi-based utility executive, confirming a plan to procure 5,000MW of AI-dedicated thermal capacity.
Exclusive from Meed
-
-
Riyadh seeks contractors for Expo Icon structure22 July 2026
-
EtihadWE tenders $150m Ajman substation project21 July 2026
-
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Firms submit bids for second Hassyan SWRO pipeline contract22 July 2026
Dubai Electricity & Water Authority (Dewa) has received bids from three contractors for a second pipeline contract relating to the Hassyan seawater reverse osmosis (SWRO) network expansion.
Project two requires contractors to supply, install, test and commission glass-reinforced epoxy (GRE) water transmission pipelines and associated works for the plant's phase two network.
Local firm Tristar Engineering & Construction submitted the lowest offer of AED792.59m ($215.8m), according to tender results published by the state utility.
Green Oasis General Contracting (UAE) submitted a bid of AED800.02m ($217.8m) and Wade Adams Contracting (UAE) made the other compliant offer of AED989.65m ($269.5m).
In January, Dewa announced that construction of the 180-million-imperial-gallon-a-day phase one of the Hassyan SWRO independent water project was 90% complete.
Earlier in July, eight contractors submitted bids for project one of the Hassyan pipeline network expansion.
Dewa also has a third contract out for tender for GRE water transmission pipeline work related to the Hassyan SWRO phase two network.
Project three was tendered on 26 January and has a bid submission deadline of 29 July.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17723861/main.jpg -
Riyadh seeks contractors for Expo Icon structure22 July 2026

Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, has asked contractors to express interest in the construction of the Icon, one of the key landmarks at the site.
The structure will be located at the entrance of the Expo 2030 Riyadh site, within the Collaboration Precinct.
ERC issued the expressions of interest notice on 20 July. The deadline for submissions of interest is 23 July.
The structure will be connected to the metro station and will serve as a gateway to the event.
It will be 66 metres tall and will comprise an observation platform, food and beverage outlets and other features.
The total built-up area will be approximately 16,279 square metres and it will be able to accommodate more than 1,450 visitors an hour during the event.
The contract duration is 29 months from the start of construction.
ERC tendered the contract for the construction of the Saudi Arabia pavilion at the site in May.
The pavilion is a major asset located within the venue's KSA District, on the eastern side of the Expo 2030 Riyadh masterplan, within the Loop of Nations district.
Construction progress
The tendering of the pavilion structure followed swift progress on the site’s infrastructure development works.
In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Al-Yamama Company.
The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.
These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners. That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.
The overall infrastructure works – covering the construction of main utilities and civil works at Expo 2030 Riyadh – are split into three packages:
- Lot 1 covers the main utilities corridor;
- Lot 2 includes the northern cluster of the nature corridor;
- Lot 3 comprises the southern cluster of the nature corridor.
The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.
The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17723204/main.jpg -
EtihadWE tenders $150m Ajman substation project21 July 2026
The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.
Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.
The bid submission deadline is 10 August.
According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.
The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.
Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.
This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.
EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.
In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg -
Seven seeks contractors for Dammam water park and hotel21 July 2026

Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.
The waterfront development sits on a 324,300-square-metre (sq m) plot.
A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.
Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.
The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.
The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.
Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.
Detailed design and issued-for-construction packages are complete.
Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.
The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.
The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.
Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.
Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.
The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.
The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg -
Al-Ula appoints equestrian village early works contractor21 July 2026

Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.
The contract was awarded to Al-Khobar-based Al-Shalawi International Company.
Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.
Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.
RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.
The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.
These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg