UAE utilities ramp up capacity procurement

4 October 2024

Abu Dhabi state utility Emirates Water & Electricity Company (Ewec) invited bids for contracts to develop three independent power producer (IPP) projects in rapid succession in the third quarter of 2024.

These projects comprise the 2,500GW Taweelah C combined-cycle gas turbine plant, the 1,500MW Madinat Zayed open-cycle gas turbine project and the 400MW battery energy storage system to be located in Al-Bihouth and Madinat Zayed.

They bring the number of Ewec’s electricity generation IPP projects currently under tender to four, in addition to the 1,500MW Al-Khazna solar photovoltaic (PV) IPP, which it tendered in April.

Ewec also issued the expression of interest notice on 1 October for a contract to develop the emirate’s fifth solar PV IPP, the 1,500MW Al-Zarraf project.

This robust project pipeline implies that the offtaker and developers, investors and contractors bidding for these projects have entered a hectic period compared to the past few years.

Abu Dhabi’s growing IPP pipeline will compete with Saudi Arabia’s equally robust pipeline for developers’ and contractors’ resources over the near to medium term as both states endeavour to meet their 2030 decarbonisation targets.

Abu Dhabi plans to procure 1,400MW of renewable energy capacity annually between 2027 and 2037 and to meet more than 50% of the emirate’s electricity demand from renewable and clean energy sources by 2030. This is expected to rise to 60% by 2035.

It also previously stated that it expects to reach a renewable energy installed capacity of 7,500MW by 2030, or three times its current capacity.

The expiry of power-purchase agreements for several generation assets over the next couple of years and the likelihood of these contracts not being extended also drive Abu Dhabi’s procurement programme for gas-fired capacity.

Dubai has a slightly different strategy. Dubai Electricity & Water Authority (Dewa) has abandoned any plans to procure additional gas-fired capacity in the foreseeable future.

Dubai’s future generation projects will be focused on the Mohammed Bin Rashid Solar Park, which is expected to reach an installed capacity of 5,000MW by 2030.

So far, Dewa has awarded contracts for the first six phases of the project, which have a total combined capacity of 4,600MW.

Further phases are being planned, with the state utility expected to appoint transaction advisers for phase seven, for which the capacity has not yet been made public, next year.

“The volume of projects coming to the market is almost unprecedented,” notes an industry source, who expects that utility developers are starting to be selective when bidding for new contracts regardless of the energy source.

Nuclear capacity

Notably, the UAE’s Federal Authority for Nuclear Regulation announced that the fourth reactor, or Unit 4, of the Barakah nuclear power plant in Abu Dhabi reached commercial operations in early September.

It marks the completion of the $43bn, 5,600MW Barakah 1 project, which was jointly implemented by the UAE’s Emirates Nuclear Energy Corporation (Enec) and South Korea’s Korea Electric Power Corporation (Kepco).

The entire plant reached full commercial operations approximately 16 years after Abu Dhabi first announced the project in 2008 and 12 years after construction works commenced on Unit 1.

The completion of Barakah 1 also implies that the project’s next phase is likely to proceed in earnest.

Hamad Alkaabi, the UAE’s permanent representative to the Austria-based International Atomic Energy Agency, said in July that the UAE government is considering initiating the tendering process for its next nuclear power plant this year.

Apart from the final tendering process decision, the market is also keen to know who will be invited to bid or submit proposals for the contract to implement the nuclear power facility’s next phase.

Washington and Abu Dhabi entered into the bilateral 123 Agreement for peaceful nuclear cooperation in 2009, which could determine to a large extent which companies or countries will be invited to participate in the project’s next phase.

What the rush is about

Ewec has made clear that expiring generation capacities and the need for gas-fired baseload as more renewable energy enters the UAE electricity grid underpin its ambitious capacity procurement pipeline.

Other factors influencing future capacity procurement plans include the UAE’s multibillion-dollar national industrialisation strategy. This strategy involves expanding downstream industries, including clean hydrogen production for both domestic and export use, potentially resulting in an exponential increase in peak demand.

This is in addition to the need to decarbonise while expanding the production of hard-to-abate sectors such as the oil and gas, steel and aluminium industries.

In addition to these demand sources, many believe the UAE’s 2031 National Artificial Intelligence (AI) Strategy is a major contributor to Abu Dhabi’s ongoing generation capacity buildout.

“They need to build power-hungry data centres to support their AI strategy,” notes an executive with an international infrastructure investment firm with offices in Dubai.

The UAE’s AI strategy encompasses deploying AI in priority sectors and “providing the data and infrastructure essential to become a test bed for AI”.

Meeting these and the other stated objectives, in addition to the data sovereignty regulations, has started driving a boom in data centre construction across the UAE.

State-backed enterprises, utilities, banks, logistics, tourism and service industries, and real estate companies have launched or are expected to launch AI programmes to boost productivity and efficiency, in line with the UAE’s 2050 net-zero target and circular carbon economy strategy.

These span industry-specific applications ranging from chatbots and small-language models to generative AI and large-language models, the latter of which require significant data bandwidth and consume enormous amounts of energy.

AI applications in defence and national security are also presumed to be a major component of the overall AI plan. 

“The AI programme is progressing,” notes an Abu Dhabi-based utility executive, confirming a plan to procure 5,000MW of AI-dedicated thermal capacity.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12650258/main.gif
Jennifer Aguinaldo
Related Articles
  • Egyptian contractor wins Abu Dhabi Ramhan Island deal

    4 September 2026

    Egypt-headquartered contractor Rowad Modern Engineering has been awarded the main works contract for the Marina Apartments project on Ramhan Island, Abu Dhabi.

    The contract was awarded by the local firm Eagle Hills, which is led by Mohamed Alabbar, the founder and chairman of Emaar Properties.

    Rowad’s scope includes structural and architectural works, finishing, and mechanical, electrical and plumbing systems.

    The company will also deliver infrastructure works, including utility connections to external networks, testing and commissioning.

    The development comprises two residential towers offering 187 residential units.

    The works will be carried out under the consultancy supervision of local engineering firm Mirage Leisure & Development.

    The latest contract award follows Eagle Hills awarding the local firm Arabian Construction Company (ACC) an estimated AED2.5bn ($680m) construction contract to build about 500 villas at the Ramhan Island development, as reported by MEED previously.

    Located off the coast of Abu Dhabi, the Ramhan Island development spans an area of over 4 million square metres.

    The overall development includes the construction of 1,800 villas, 900 residences, a hotel and retail facilities.

    Mohamed Alabbar launched the Ramhan Island development in May 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19355437/main.jpg
    Yasir Iqbal
  • Dubai sets deadline for Jebel Ali waste-to-energy PPP

    4 September 2026

     

    Register for MEED’s 14-day trial access 

    Dubai Municipality has set a 27 September deadline for developers to submit expressions of interest (EOIs) for its planned Jebel Ali waste-to-energy (WTE) public-private partnership (PPP), according to a source.

    The greenfield facility is planned to treat up to 6,000 tonnes of municipal solid waste a day.

    The municipality is seeking international and local developers to develop, finance and operate the facility. It is planning to prequalify developers later this year before issuing a request for proposals (RFP) in the first quarter of next year, a source said.

    The Jebel Ali facility is intended to support Dubai’s waste-management strategy and its target of reducing reliance on landfill.

    Dubai Municipality is being advised by a team led by Abu Dhabi’s Tribe Infrastructure Group, with UK-headquartered Ashurst and Germany’s Fichtner also involved.

    It was confirmed to MEED that the project is separate from the planned second phase of the Warsan WTE facility, for which Dubai Municipality issued a consultancy tender in February.

    That facility will be located in Warsan 2, next to the Al-Aweer sewage treatment plant. The expansion is expected to increase waste-conversion capacity at the existing Warsan site with an estimated budget of $500m. The consultancy contract has a duration of six years.

    The original Warsan WTE plant, Dubai’s first major WTE public-private partnership (PPP) project, reached full commercial operations in 2024.

    Located in the Warsan area, the AED4bn ($1.1bn) facility treats 1.9 million tonnes of municipal solid waste annually, generating up to 220MW of thermal energy that is fed into the local grid.

    In February 2023, state utility Dubai Electricity & Water Authority (Dewa) and Dubai Waste Management Company signed the power-purchase agreement (PPA) for the project.

    Dubai Waste Management Company, the special-purpose vehicle implementing the scheme, reached financial close in June 2021 for the project.

    The Warsan project was developed under a 35-year PPP concession by a consortium comprising Dubai Holding, Dubai Aluminium, Tech Group and Itochu Corporation. 

    The main contractor was a joint venture of Belgium’s Besix Group and Hitachi Zosen Inova of Switzerland.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19354502/main.jpg
    Mark Dowdall
  • Egypt to invest $4.5bn in refinery upgrades

    4 September 2026

    Egypt is planning to invest $4.5bn in refinery upgrades, according to the country’s Minister of Petroleum and Mineral Resources, Karim Badawi.

    Egyptian refineries are operating at 80% of capacity compared with 66% two years ago, according to Badawi, who wants further increases in utilisation of existing facilities.

    “We aim to invest around $4.5bn to develop existing refineries and build new units to reduce imports and achieve self-sufficiency in refined products,” he said in a statement.

    In May, Egypt said that it had increased its fuel import budget by almost 40% for the 2026-27 fiscal year amid higher global prices driven by the Iran war, which started when the US and Israel launched an attack on Iran on 28 February.

    Brent crude prices are up about a third since the conflict started, trading at more than $90 a barrel for most of this month so far.

    Badawi said a decline in Egypt’s oil and gas production between 2021 and 2024 occurred because foreign companies were reluctant to invest in the country’s energy sector due to unpaid government debts.

    He said: “We have settled all the debt, which reached $6.1bn in June 2024. As a result, hydrocarbon exploration and production activity grew by nearly 20% this year.

    “We are now moving in the right direction to increase oil and gas output gradually.”

    Despite the ongoing push to develop projects in the country’s oil and gas sector, several key projects have seen significant delays in recent years.

    These include a $2bn hydrocracking complex package that forms part of the wider Assiut oil refinery upgrade project.

    Earlier this month, MEED revealed that mechanical completion of the hydrocracking package is now unlikely to be reached until early next year due to complications in the final stages of construction.

    The hydrocracking complex package has experienced extensive delays over several years.

    In April this year, Badawi called for work to accelerate on the Assiut oil refinery upgrade project, saying it is important for reducing the country’s spending on imported refined products.

    At the time, the oil ministry said the project was 88% complete, with trial operations planned by the end of the year.

    Assiut Oil Refining Company (ASORC), a subsidiary of state-owned Egyptian General Petroleum Corporation, is the project operator.

    France’s Technip Energies is the main contractor, performing engineering, procurement and construction work on the Assiut hydrocracking complex under a $2bn contract awarded by ASORC in February 2020.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19353521/main.jpg
    Wil Crisp
  • North Field West platform bidders get extra time

    4 September 2026

     

    QatarEnergy has granted contractors additional time to prepare bids for a key tender for the engineering, procurement, construction and installation (EPCI) of large platforms for the giant North Field gas field in Qatari waters.

    The tender, issued earlier this year, forms part of the wider North Field West (NFW) project, the third and last phase of the state enterprise’s North Field liquefied natural gas (LNG) expansion programme.

    The core scope comprises the EPCI of four production deck modules (PDMs) and associated structures. The new PDMs will increase gas production from North Field reservoirs and provide additional gas feedstock for the NFW LNG development.

    QatarEnergy has set 15 September as the deadline for technical bid submissions, while commercial bids are due on 10 November, according to sources.

    The previous deadlines for submission of technical and commercial bids were 30 August and 25 October, respectively, MEED previously reported.

    The following contractors, among others, are understood to be bidding:

    • China Offshore Oil Engineering Company (China)
    • Larsen & Toubro Energy Hydrocarbon (India)
    • McDermott (US)
    • Saipem (Italy)

    Before issuing the PDM tender, QatarEnergy awarded McDermott a contract for the EPCI of four offshore jackets that will also support gas feedstock supply for the NFW LNG project. The contract is estimated to be worth about $200m, MEED reported in January.

    North Field LNG expansion

    QatarEnergy is advancing the three phases of its estimated $40bn North Field LNG expansion project. EPC works on all three giant projects are progressing.

    QatarEnergy is understood to have committed nearly $30bn to the first two phases – North Field East (NFE) and North Field South (NFS) – which will lift Qatar’s LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028.

    QatarEnergy awarded the main EPC contracts for NFE in 2021. The project was intended to raise LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the EPCI of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Japan’s Chiyoda and France’s Technip Energies.

    In May 2023, QatarEnergy awarded the $10bn main EPC contract for NFS to a consortium of Technip Energies and Consolidated Contractors Company (CCC). The contract includes two LNG trains, each with a capacity of 7.8 million t/y.

    Once fully operational, the first two phases are expected to add 48 million t/y of LNG supply to the global market.

    QatarEnergy took the final investment decision on NFW this year, awarding an EPC contract estimated at $8bn to a joint venture comprising Technip Energies, CCC and Gulf Asia Contracting (GAC) in February.

    Chiyoda carried out the front-end engineering and design (feed) work for the NFW LNG project.

    The NFW scope covers the EPC of two LNG trains with a combined capacity of 16 million t/y, as well as associated facilities for gas treatment, natural gas liquids recovery and helium extraction.

    In addition to LNG, NFW is expected to produce about 175,000 barrels of oil equivalent a day of condensate, ethane and LPG.

    With all three phases now under EPC execution – and NFE scheduled for commissioning later this year – QatarEnergy is positioning itself to remain one of the world’s largest LNG suppliers over the long term.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19352006/main.jpg
    Indrajit Sen
  • Contractors prepare Dubai Metro Gold Line prequalifications

    4 September 2026

     

    Register for MEED’s 14-day trial access 

    Contractors are preparing to submit their prequalification statements on 7 September for a contract to build the new Gold Line as part of the Dubai Metro network’s expansion.

    Dubai’s Roads & Transport Authority (RTA) issued the request for qualification notice for the project in June, with an initial submission deadline of 17 August, as MEED exclusively reported.

    This followed the RTA’s invitation to contractors to express interest in building the new Gold Line in May.

    Dubai officially announced the launch of the new Gold Line in April.

    In a post on social media site X, Sheikh Mohammed Bin Rashid Al-Maktoum, UAE Vice President and Prime Minister and Ruler of Dubai, said the project will cost about AED34bn ($9.2bn).

    The Gold Line will increase the Dubai Metro network’s total length by 35%.

    The project is scheduled for completion in September 2032.

    The Gold Line will be a fully underground network covering more than 42 kilometres, with 18 stations.

    It will pass through 15 areas in Dubai, benefiting 1.5 million residents.

    The project is expected to provide connectivity to over 55 under-construction real estate development projects.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai and end at Jumeirah Golf Estates.

    It will connect to Dubai Metro’s existing Red and Green lines and integrate with the Etihad Rail passenger line.

    The contractor will be responsible for the design and build of all civil works, electromechanical equipment, rolling stock and rail systems.

    The selected contractor will also be required to assist in the systems maintenance and operations during an initial three-year period.

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the Dubai Metro Gold Line project.

    Stage one covers concept design, stage two covers preliminary design, stage three covers the preparation of tender documents, stage four encompasses construction supervision, and stage five covers the defects and liability period.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19350865/main.png
    Yasir Iqbal