UAE ramps up decarbonisation of water sector
10 October 2023
This package on the UAE's water sector also includes:
> Dewa signs Hassyan water project agreements
> Petrojet joins Project Wave contractor team
> Project Wave first phase reaches financial close
> Alpha Dhabi acquires majority stake in Metito
> Hatta reservoir nears completion
> Sharjah moves Hamriyah bid deadline

As a water-scarce country, the UAE has relied on non-conventional water, particularly seawater treated in desalination plants, to meet rising demand.
Over the past decade, the energy-intensive water treatment process, especially when using older technologies, has been a key focus for policymakers tasked with aligning industries with the country’s energy diversification and, more recently, net-zero carbon dioxide emissions agendas.
Decarbonising the water supply has entailed decoupling power and water production and improving the level of treated sewage effluent (TSE) reuse. Other initiatives involve modernising the water pipeline transmission network and tapping renewable energy to power desalination plants.
Demand management initiatives such as tariff reforms and awareness campaigns to make end users conscious of their consumption have also been put in place.
The past few months have marked several milestones in the country’s plan to decarbonise its water sector.
Two private water desalination plants that use reverse osmosis technology to treat seawater are in the final commissioning stage, expanding the UAE’s water production capacity from more energy-efficient plants.
These are the 200 million-imperial-gallon-a-day (MIGD) seawater reverse osmosis (SWRO) plant in Taweela in Abu Dhabi and another plant in Umm al-Quwain, which has a capacity of 150MIGD.
Abu Dhabi’s second major SWRO project, the 120MIGD Mirfa 2 independent water producer (IWP), also reached financial close this year.
Crucially, Abu Dhabi dismantled the thermal-powered Taweelah A2 independent water and power producer (IWPP) plant last year, following the expiry of its long-term offtake contract. The plant’s desalination unit ran on the older multi-stage flash technology.
Hassyan 1
Dubai achieved an important milestone in October when state utility Dubai Electricity & Water Authority (Dewa) and Saudi-headquartered Acwa Power signed a 30-year water-purchase agreement (WPA) and shareholder agreement for the Hassyan 1 IWP project.
Acwa Power will develop and operate the power plant for 30 years at a levelised water cost of 36.5 $cents a cubic metre, a record low, although not nearly as low as the tariff proposed by another developer when the contract was first tendered.
The project supports Dewa’s plan to increase its water desalination capacity from 490MIGD to 750MIGD by the end of the decade.
Dewa has said the Hassyan 1 IWP will be powered by solar energy, further reducing the plant’s carbon footprint.
In Abu Dhabi, the official signing of a WPA for the Shuweihat S4 SWRO project is imminent, which will add another 70MIGD to the emirate’s installed water production capacity once complete.
The Shuweihat 4 plant will cater to potable water demand in Abu Dhabi’s Al-Dhafra region, a key focus of Abu Dhabi’s economic development plan.
The bidding process is also under way for two more SWRO plants in Abu Dhabi. The Hudayriat and Saadiyat RO plants, each with a capacity of 50MIGD, will be developed as one IWP contract.
Emirates Water & Electricity Company (Ewec) has not mandated the inclusion of a solar photovoltaic (PV) plant for its most recent IWP projects, as it did for the Taweelah RO plant in 2019. However, it will likely tap either solar or nuclear energy, or both, for its upcoming SWRO plants in line with its goal to halve its total carbon dioxide emissions to 22 million tonnes a year by 2035.
The northern Sharjah emirate is also procuring its first IWP. The planned Hamriyah SWRO plant will have a capacity of 90MIGD.
In addition to the utility clients, Abu Dhabi National Oil Company (Adnoc) has awarded the contract to develop the first phase of Project Wave, which aims to replace the aquifer water injection systems used to maintain reservoir pressure in Abu Dhabi's onshore oil fields.
The project is expected to reduce the water injection-related energy consumption of the oil fields by up to 30 per cent.
Wastewater
Dubai Municipality activated a major programme this year to develop deep tunnels and sewage treatment plants across the emirate. This long-term project could require an investment of up to AED80bn ($22bn).
Known as the Deep Tunnels Portfolio, the scheme will be developed as a public-private partnership (PPP) initiative and will expand the role of private companies in the emirate’s water infrastructure sector.
It involves the construction of two sets of deep tunnels terminating at two terminal pump stations located at sewerage treatment plants (STPs) in Warsan and Jebel Ali. A conventional sewage and drainage collection system and STPs will be built in Hatta. The scheme also includes recycled water distribution systems connected to the STPs.
Approved by Dubai’s Executive Council in June, the project has been designed to serve the needs of the Dubai population for the next 100 years in alignment with the Dubai Economic Agenda D33 and Dubai Urban Plan 2040.
In the UAE capital, Abu Dhabi Sustainable Water Solutions, formerly Abu Dhabi Sewerage Services Company, received bids for the contract to design, build and operate a planned TSE polishing plant in Al-Wathba earlier this year.
The plant is expected to have a design capacity of 700,000 cubic metres a day (cm/d), with the potential to expand this to 950,000 cm/d in a subsequent phase. The TSE facility will produce water for higher-end applications compared with TSE produced in a standard sewage treatment plant.
In addition to supporting the UAE’s long-term economic and demographic expansion, these water treatment projects also boost the country’s preferred circular carbon economy approach to energy transition.
Exclusive from Meed
-
Engineering progresses on Ras Laffan LNG terminal berths16 September 2026
-
Design completed for Libyan oil field development16 September 2026
-
QatarEnergy selects contractors for offshore oil field expansion16 September 2026
-
Contractors prequalify for Bahrain sports stadium15 September 2026
-
Riyadh Expo signs private real estate development deal15 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Engineering progresses on Ras Laffan LNG terminal berths16 September 2026

Register for MEED’s 14-day trial access
Front-end engineering and design (feed) works are progressing on a QatarEnergy LNG project to build 13 liquefied natural gas (LNG) loading berths at the south export terminal in Qatar’s Ras Laffan Industrial City.
Ras Laffan Industrial City, which lies about 90 kilometres north of Doha, is the world's largest integrated LNG production and export complex, comprising 15 processing trains with a total capacity of 77.5 million tonnes a year (t/y). QatarEnergy began LNG operations at the facility, which houses all its processing trains and export infrastructure, in 1984.
According to sources, QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, awarded the feed contract for the project to build 13 LNG berths at the south export terminal at Ras Laffan to Australia-headquartered Worley.
The contract was awarded to Worley in the second quarter of this year. Its duration is estimated to be 200,000-250,000 man hours, sources told MEED.
Ras Laffan’s LNG processing and export capabilities will increase by up to about 63% when the three phases of QatarEnergy’s estimated $40bn North Field LNG expansion project come into operation by the end of this decade. Engineering, procurement and construction (EPC) works on all three projects are progressing.
QatarEnergy is understood to have committed nearly $30bn to the first two phases – North Field East (NFE) and North Field South (NFS) – which will lift Qatar’s LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.
QatarEnergy awarded the main EPC contracts for NFE in 2021. The project was intended to raise LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the engineering, procurement, construction and installation of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Japan’s Chiyoda and France’s Technip Energies.
In May 2023, QatarEnergy awarded the $10bn main EPC contract for NFS to a consortium of Technip Energies and Consolidated Contractors Company (CCC). The contract includes two LNG trains, each with a capacity of 7.8 million t/y.
Once fully operational, the first two phases are expected to add 48 million t/y of LNG supply to the global market.
QatarEnergy took the final investment decision on the third phase, North Field West (NFW), this year, awarding an EPC contract estimated at $8bn to a joint venture comprising Technip Energies, CCC and Gulf Asia Contracting in February.
Chiyoda carried out the feed work for the NFW LNG project.
The NFW scope covers the EPC of two LNG trains with a combined capacity of 16 million t/y, as well as associated facilities for gas treatment, natural gas liquids recovery and helium extraction.
In addition to LNG, NFW is expected to produce about 175,000 barrels of oil equivalent a day of condensate, ethane and liquefied petroleum gas.
With all three phases under EPC execution – and NFE scheduled for commissioning later this year – QatarEnergy is positioning itself to remain one of the world’s largest LNG suppliers in the long term.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19715235/main5946.jpg -
Design completed for Libyan oil field development16 September 2026

Register for MEED’s 14-day trial access
Design work has been completed for a project to develop Libya’s I/R oil field, according to industry sources.
The front-end engineering and design work was completed by a team in the London offices of Italy’s EniProgetti and paves the way for the main engineering, procurement and construction contract to be tendered.
One source said: “At the moment, there is no fixed date for when the invitation to bid for the main contract will be issued, but the project has a lot of momentum and is progressing towards tendering.”
The I/R oil field is located in Murzuq Basin in southwestern Libya.
In June this year, Libya's National Oil Corporation (NOC) signed a unified operating agreement for the field.
The I/R field is operated by Akakus Oil Operations, which is a joint venture of NOC in partnership with Spain’s Repsol, France’s TotalEnergies Repsol, Austria’s OMV and Norway’s Equinor.
The agreement in June was signed by NOC as well as its concession partners.
NOC said the agreement would unify operational and administrative procedures related to field management, optimise resource utilisation and support production sustainability.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19711588/main.jpg -
QatarEnergy selects contractors for offshore oil field expansion16 September 2026

Register for MEED’s 14-day trial access
QatarEnergy has selected contractors for the two main engineering, procurement and construction (EPC) packages of its estimated $4bn-$5bn Maydan Mahzam offshore oil field expansion project in Qatar.
The Qatari energy giant has selected a consortium of state-owned PetroVietnam Technical Services Corporation (PTSC) and Singapore-based Seatrium for package one of the Maydan Mahzam field expansion project, according to sources.
State-owned China Offshore Oil Engineering Company (COOEC) has secured package two of the project, sources told MEED.
Additionally, PTSC has confirmed its contract award for the first engineering, procurement, construction and installation (EPCI) package in a disclosure to the Hanoi Stock Exchange, saying its wholly owned subsidiary PTSC Mechanical & Construction had received a letter of award from QatarEnergy. The company added that “the parties will continue discussions to finalise and execute the definitive contract, which is expected to be signed in October 2026”.
In its filing, PTSC added that its scope of work covers “the provision of engineering, procurement, construction, transportation, offshore installation, hook-up, commissioning and brownfield modification services for the [Maydan Mahzam] project”.
MEED reported in late August that the consortium of PTSC and Seatrium had emerged as the frontrunner for package one of the expansion project.
At the time, US-based McDermott was ahead in the race to win package two. However, COOEC is understood to have presented "better terms to the client in the final rounds of negotiations”, sources said.
QatarEnergy issued the main tender for the Maydan Mahzam oil field expansion project in February 2025, with EPC works divided into four packages, MEED previously reported.
Contractors submitted technical bids for the project’s two main EPC packages in September 2025, sources said.
After QatarEnergy granted several extensions to the deadline for the submission of commercial bids for the two packages – initially set for 1 March – contractors submitted their prices by 21 June, MEED reported.
The following contractors, among others, are understood to have submitted bids for the two main packages of the project:
Package one:
- China Offshore Oil Engineering Company (China)
- Hanwha Ocean (South Korea)
- Hyundai Heavy Industries (South Korea)
- Larsen & Toubro Energy Hydrocarbon (India)
- PetroVietnam Technical Services Corporation (Vietnam) / Seatrium (Singapore)
- Saipem (Italy)
Package two:
- Allseas (Netherlands)
- China Offshore Oil Engineering Company (China)
- Larsen & Toubro Energy Hydrocarbon (India)
- McDermott (US)
- Saipem (Italy)
The Maydan Mahzam oil field lies about 100 kilometres (km) northeast of the Qatari coastline and 28km southeast of Halul Island, located in water depths of about 40 metres. The field, together with the nearby Bul Hanine field, was discovered in the 1960s and has been in production since 1965.
QatarEnergy is undertaking the project to upgrade infrastructure at Maydan Mahzam to extend the life of this maturing asset and maintain productivity over the long term.
The scope of work for package one includes the EPC of seven new topsides, requiring the fabrication of structures weighing more than 78,000 metric tonnes in total. The main process topside will weigh 19,400 metric tonnes, while the other topsides will consist of 10-legged jackets.
The scope also includes modifications to five existing topsides, four new bridges, eight-tonne support platforms with jackets, brownfield work on Halul Island and the installation of pipelines and cables.
The scope of work for package two covers the EPCI of topsides, umbilicals and cables.
ALSO READ: Contractors submit bids for Dukhan field facilities upgrade
In addition to advancing its gas production and liquefied natural gas ambitions, QatarEnergy committed significant capital expenditure last year to increasing oil output capacity from its offshore fields.
In August 2025, QatarEnergy selected contractors for the EPC works on a project to maintain and increase production potential at the Bul Hanine offshore oil field. The EPC scope was divided into three main packages, with COOEC being awarded the first two packages and Qatari contractor Doha Petroleum Construction Company (Dopet) being selected for the third. In addition, COOEC appointed US-based KBR to provide detailed engineering services for the first and second packages.
Separately, last September, QatarEnergy awarded the main EPC contract for a project to add a fifth natural gas liquids (NGL) train at its complex in Mesaieed Industrial City. Indian contractor Larsen & Toubro Energy Hydrocarbon won the contract.
The project, estimated to be worth $2.5bn, aims to build a fifth NGL train with the capacity to process up to 350 million cubic feet a day of rich associated gas from QatarEnergy’s offshore and onshore oil fields.
ALSO READ: Contractors prepare bids for North Field West offshore platforms
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19688942/main3340.jpg -
Contractors prequalify for Bahrain sports stadium15 September 2026

Register for MEED’s 14-day trial access
Twenty-one local and Saudi Arabia-based contractors have been prequalified for a contract to build the first phase of the Bahrain International Sports City project in the Sakhir area.
The prequalification stage closed on 13 September.
The notice was first issued on 24 May, with an initial submission deadline of 26 July.
The prequalified firms are:
- Alfanar Projects (Saudi Arabia)
- Al-Ayuni Investment & Contracting (Saudi Arabia)
- Nesma Infrastructure & Technology (Saudi Arabia)
- Shar Construction (Saudi Arabia)
- Saudi Binladin Group (Saudi Arabia)
- Kooheji Contractors (local)
- B1 Trading & Services (local)
- Nass Contracting (local)
- RTCC / IC Ictas (Saudi Arabia / Turkiye)
- Moffareh Alharbi & Partners (Saudi Arabia)
- Al-Sharif Group Holding (Saudi Arabia)
- Cebarco (local)
- Midmac Contracting (Qatar)
- BEC Arabia (Saudi Arabia)
- Shibh Al-Jazira Contracting Company (Saudi Arabia)
- Poullaides Construction Poullaides Construction
- Isam Khairi Kabbani Partners (Saudi Arabia)
- El-Seif Engineering Contracting Company (Saudi Arabia)
- AlBawani (Saudi Arabia)
- Nesma & Partners (Saudi Arabia)
- Modern Building Leaders (Saudi Arabia)
The latest development follows US-based engineering firm Populous winning a BD5m ($13.5m) contract for the development, as MEED reported.
Populous’ scope covers pre-contract consultancy services, including finalising the masterplan and internal infrastructure, completing phase 1A design works and preparing tender documents.
The contract was first tendered in 2021, when Populous emerged as the sole bidder.
At the time, it was reported that the Sports City project would include Bahrain’s largest sports stadium and a multipurpose indoor sports arena.
The project is expected to provide renewed impetus to Bahrain’s construction and transport sector, which has struggled in recent years, with the total value of awarded contracts falling for a third consecutive year.
According to regional project tracker MEED Projects, about $400m-worth of contracts had been awarded in Bahrain by the end of October last year – less than half the $1.2bn recorded during the same period the previous year.
The sector has yet to return to pre-pandemic levels. Before 2020, Bahrain consistently awarded more than $2bn in contracts annually, peaking at nearly $4bn in 2016.
Bahrain’s construction industry is forecast to record average annual growth of 4.9% in 2026-29, supported by investments in transport infrastructure and renewable energy projects aligned with Bahrain’s Economic Vision 2030.
Vision 2030 includes the BD11.3bn ($30bn) Strategic Projects Plan, unveiled in October 2021, encompassing 22 national infrastructure projects. It also includes plans to create five new cities by 2030: Fasht Al-Jarm, Suhaila Island, Fasht Al-Azem, Bahrain Bay and Hawar Islands.
Growth over the forecast period is also expected to be driven by investments under the National Renewable Energy Action Plan, which targets a 30% reduction in carbon emissions by 2035, compared to 2015 levels, and aims to achieve net-zero emissions by 2060.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19670426/main.jpg -
Riyadh Expo signs private real estate development deal15 September 2026
Register for MEED’s 14-day trial access
Saudi Arabia's Expo 2030 Riyadh Company (ERC) has signed an agreement with Riyadh-based developer Mohammed Al-Habib Real Estate Company to develop and deliver Expo Village, the event's residential community.
The project will comprise about 2,300 apartments, housing around 5,500 residents, alongside retail and dining outlets, amenities, services and operational facilities.
The community will be connected to the Expo 2030 Riyadh site via the Expo metro station, as well as to King Khalid International airport and the city’s wider transport network.
The deal marks ERC’s first private-sector partnership deal for the site.
The latest agreement comes as ERC is gearing up to deliver several components of the site. Tendering is ongoing for the Saudi Arabia pavilion, and another tender is out for the delivery of the Souq areas within the expo site.
Site progress
Construction activity at the expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.
Earlier this month, Saudi Arabia’s Royal Commission for Riyadh City awarded a design-and-build contract for the construction of a new metro station catering to the Expo 2030 site.
In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Alyamama Company.
The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle (EV) charging.
These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.
That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems; and EV charging stations.
The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.
The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025, to build and operate facilities for Expo 2030.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19665616/main.jpg