UAE ramps up decarbonisation of water sector

10 October 2023

This package on the UAE's water sector also includes: 

Dewa signs Hassyan water project agreements
Petrojet joins Project Wave contractor team
Project Wave first phase reaches financial close

Alpha Dhabi acquires majority stake in Metito
Hatta reservoir nears completion
Sharjah moves Hamriyah bid deadline


 

As a water-scarce country, the UAE has relied on non-conventional water, particularly seawater treated in desalination plants, to meet rising demand.

Over the past decade, the energy-intensive water treatment process, especially when using older technologies, has been a key focus for policymakers tasked with aligning industries with the country’s energy diversification and, more recently, net-zero carbon dioxide emissions agendas.

Decarbonising the water supply has entailed decoupling power and water production and improving the level of treated sewage effluent (TSE) reuse. Other initiatives involve modernising the water pipeline transmission network and tapping renewable energy to power desalination plants.

Demand management initiatives such as tariff reforms and awareness campaigns to make end users conscious of their consumption have also been put in place.

The past few months have marked several milestones in the country’s plan to decarbonise its water sector.

Two private water desalination plants that use reverse osmosis technology to treat seawater are in the final commissioning stage, expanding the UAE’s water production capacity from more energy-efficient plants.

These are the 200 million-imperial-gallon-a-day (MIGD) seawater reverse osmosis (SWRO) plant in Taweela in Abu Dhabi and another plant in Umm al-Quwain, which has a capacity of 150MIGD.

Abu Dhabi’s second major SWRO project, the 120MIGD Mirfa 2 independent water producer (IWP), also reached financial close this year.

Crucially, Abu Dhabi dismantled the thermal-powered Taweelah A2 independent water and power producer (IWPP) plant last year, following the expiry of its long-term offtake contract. The plant’s desalination unit ran on the older multi-stage flash technology.

Hassyan 1 

Dubai achieved an important milestone in October when state utility Dubai Electricity & Water Authority (Dewa) and Saudi-headquartered Acwa Power signed a 30-year water-purchase agreement (WPA) and shareholder agreement for the Hassyan 1 IWP project.

Acwa Power will develop and operate the power plant for 30 years at a levelised water cost of 36.5 $cents a cubic metre, a record low, although not nearly as low as the tariff proposed by another developer when the contract was first tendered.

The project supports Dewa’s plan to increase its water desalination capacity from 490MIGD to 750MIGD by the end of the decade.

Dewa has said the Hassyan 1 IWP will be powered by solar energy, further reducing the plant’s carbon footprint.

In Abu Dhabi, the official signing of a WPA for the Shuweihat S4 SWRO project is imminent, which will add another 70MIGD  to the emirate’s installed water production capacity once complete.

The Shuweihat 4 plant will cater to potable water demand in Abu Dhabi’s Al-Dhafra region, a key focus of Abu Dhabi’s economic development plan.

The bidding process is also under way for two more SWRO plants in Abu Dhabi. The Hudayriat and Saadiyat RO plants, each with a capacity of 50MIGD, will be developed as one IWP contract.

Emirates Water & Electricity Company (Ewec) has not mandated the inclusion of a solar photovoltaic (PV) plant for its most recent IWP projects, as it did for the Taweelah RO plant in 2019. However, it will likely tap either solar or nuclear energy, or both, for its upcoming SWRO plants in line with its goal to halve its total carbon dioxide emissions to 22 million tonnes a year by 2035.

The northern Sharjah emirate is also procuring its first IWP. The planned Hamriyah SWRO plant will have a capacity of 90MIGD.

In addition to the utility clients, Abu Dhabi National Oil Company (Adnoc) has awarded the contract to develop the first phase of Project Wave, which aims to replace the aquifer water injection systems used to maintain reservoir pressure in Abu Dhabi's onshore oil fields.

The project is expected to reduce the water injection-related energy consumption of the oil fields by up to 30 per cent.

Wastewater

Dubai Municipality activated a major programme this year to develop deep tunnels and sewage treatment plants across the emirate. This long-term project could require an investment of up to AED80bn ($22bn).

Known as the Deep Tunnels Portfolio, the scheme will be developed as a public-private partnership (PPP) initiative and will expand the role of private companies in the emirate’s water infrastructure sector.  

It involves the construction of two sets of deep tunnels terminating at two terminal pump stations located at sewerage treatment plants (STPs) in Warsan and Jebel Ali. A conventional sewage and drainage collection system and STPs will be built in Hatta. The scheme also includes recycled water distribution systems connected to the STPs.

Approved by Dubai’s Executive Council in June, the project has been designed to serve the needs of the Dubai population for the next 100 years in alignment with the Dubai Economic Agenda D33 and Dubai Urban Plan 2040.

In the UAE capital, Abu Dhabi Sustainable Water Solutions, formerly Abu Dhabi Sewerage Services Company, received bids for the contract to design, build and operate a planned TSE polishing plant in Al-Wathba earlier this year.

The plant is expected to have a design capacity of 700,000 cubic metres a day (cm/d), with the potential to expand this to 950,000 cm/d in a subsequent phase. The TSE facility will produce water for higher-end applications compared with TSE produced in a standard sewage treatment plant.

In addition to supporting the UAE’s long-term economic and demographic expansion, these water treatment projects also boost the country’s preferred circular carbon economy approach to energy transition.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11193002/main.gif
Jennifer Aguinaldo
Related Articles
  • Dubai scales up its metro ambitions

    23 April 2026

     

    Dubai’s rail sector has rarely seen such a concentrated burst of procurement activity as it has in the past year.

    Within the space of a few months, Dubai’s Roads & Transport Authority (RTA) has moved simultaneously on three distinct fronts: tendering design consultancy for the Route 2020 extension that will connect the Expo 2020 metro station to Al-Maktoum International airport; inviting study-and-design bids for a 55-kilometre Airport Express Line linking Dubai International airport to Al-Maktoum International airport; and culminating in Dubai Ruler Sheikh Mohammed Bin Rashid Al-Maktoum’s approval of the AED34bn ($9.2bn) Gold Line, a 42km fully underground route that the emirate is calling the largest transportation project in its history.

    These projects form a key part of the Dubai Rail Network Plan 2032, which outlines the development of six public transportation schemes comprising a mix of metro, passenger and high-speed rail lines.

    The most prominent feature of the plan is the addition of new lines to Dubai Metro’s existing network, representing a systematic effort to support the shift of Dubai’s economic centre of gravity towards Dubai South and the vast development corridors in between.

    The city is also seeking to stay ahead of the curve by investing heavily in infrastructure. Data from regional projects tracker MEED Projects shows that the emirate has awarded over $14bn-worth of transport projects in the past two years alone, with several other multibillion-dollar schemes still moving through the planning stages.

    All of this work is being carried out in line with the Dubai 2040 Urban Master Plan, which forecasts the emirate’s population will reach 5.8 million by 2040 – a clear indication of the scale of daily movement the city must accommodate.

    Project progress

    Dubai Metro Gold Line

    On 21 April, Sheikh Mohammed officially announced the launch of the new AED34bn ($9.2bn) Gold Line project.

    The line will be a fully underground network spanning over 42 kilometres, with 18 stations.

    It will run from Al-Ghubaiba in Bur Dubai to Jumeirah Golf Estates.

    The Gold Line will connect with Dubai Metro’s existing Red and Green lines and integrate with the Etihad Rail passenger network.

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the project.

    Stage one covers concept design; stage two, preliminary design; stage three, preparation of tender documents; stage four, construction supervision; and stage five, the defects liability period.

    Airport Express Line

    Procurement has started for another metro line extending from Dubai International airport (DXB) in Al-Garhoud to Al-Maktoum International airport (DWC) in Jebel Ali.

    Earlier this month, the RTA invited consultants to bid for a contract to study and design what is referred to as the Airport Express Line.

    The proposed line will stretch about 55km and include five stations that will provide passengers with facilities such as remote airline check-in, baggage drop-off and security screening.

    The new line will run from the Red Line metro station at DXB through Al-Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC), before continuing on to DWC.

    There will be two spur lines. The first will run from the new JVC station to Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch toward Business Bay, where another station will be built.

    Expo 2020 route extension

    Dubai is also undertaking the Route 2020 extension of its metro system, which will start from the Expo 2020 metro station and connect with Al-Maktoum International airport’s West Terminal.

    Consultants submitted their bids earlier this month for the design contract.

    The extension will run for about 3km and feature two stations.

    The existing Route 2020 metro link is a 15km line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    Dubai Metro Blue Line extension

    Construction progress on the Dubai Metro Blue Line extension is expected to reach 30% by the end of 2026, according to official accounts.

    In December 2024, the RTA awarded a AED20.5bn ($5.5bn) main contract for the construction of the project.

    The contract was awarded to a consortium of Turkiye’s Limak Holding, Mapa Group, also of Turkiye, and the Hong Kong office of China Railway Rolling Stock Corporation (CRRC).

    The Blue Line will connect the existing Red and Green lines. It will be 30km long, with 15.5km underground and 14.5km above ground.

    The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.

    The project is scheduled for completion in September 2029.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16534887/main.png
    Yasir Iqbal
  • Sports Boulevard tenders Wadi Hanifa road works

    23 April 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Sports Boulevard Foundation has issued a tender inviting firms to bid for a contract to build a road and associated infrastructure in the Wadi Hanifa area of Riyadh.

    The bid submission deadline is 27 April.

    The scope includes construction of an 11.4-kilometre road and associated infrastructure, including public realm works, utilities and security systems.

    The scheme is the latest package to progress on Riyadh’s Sports Boulevard project.

    The Sports Boulevard Foundation is also evaluating bids for its Global Sports Tower in the development’s Athletics District.

    The 130-metre-tall Global Sports Tower will have a gross floor area of 84,000 square metres (sq m) and will include more than 30 sports facilities. The tower will feature what is billed as the world’s tallest indoor climbing wall, at 98 metres, and a 250-metre running track.

    Sports Boulevard will run across Riyadh from east to west. Once complete, it is intended to be the world’s longest park, stretching more than 135 kilometres.

    The project is divided into multiple districts, including the Wadi Hanifah, Arts, Urban Wadi, Entertainment, Athletics and Eco districts, as well as Sands Sports Park.

    The large-scale development aims to transform central Riyadh – currently dominated by major highways – into a recreational corridor.

    Sports Boulevard will include 4.4 million sq m of public realm and landmark buildings. Along with the Global Sports Tower, there will be a Centre for Cinematic Arts and a 2,000-seat amphitheatre.

    It will also deliver more than 2.3 million sq m of mixed-use commercial, residential and retail space, alongside sports facilities, around the park, known as the Linear Park.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16534345/main.jpg
    Yasir Iqbal
  • Masdar to develop renewables projects in Montenegro

    23 April 2026

    Abu Dhabi Future Energy Company (Masdar) and Elektroprivreda Crne Gore (EPCG) have agreed to establish a 50:50 joint venture to develop and operate renewable energy projects in Montenegro.

    The planned projects include solar photovoltaic (PV), wind, hydropower, pumped-hydro storage and battery energy storage systems.

    The joint venture will be headquartered in Niksic in western Montenegro and is intended to support Montenegro’s domestic energy needs while also enabling the export of renewable electricity to the Western Balkans and Southern Europe, Masdar said in a statement.

    The companies plan to leverage an existing sub-sea interconnection with Italy. Montenegro is connected to Italy via a 600MW HVDC submarine cable, enabling electricity exports to the Italian market.

    Masdar has an existing presence in Montenegro through its investment in the 72MW Krnovo wind farm.

    The developer has recently accelerated foreign investment plans as part of its broader expansion. In April, it signed a binding agreement with France’s TotalEnergies to establish a $2.2bn joint venture to develop, build and operate renewable energy projects across Asia.

    The combined business will have 3GW of operational capacity and 6GW of projects in advanced development, targeted for commissioning by 2030.

    Masdar is targeting a global renewable energy portfolio of 100GW by 2030. It recently reached 65GW, two-thirds of the way to that target.

    The company plans to deploy an additional $30bn-$35bn in equity and project finance by 2030, adding an average of 10GW of new capacity each year.

    This expansion will be funded through a mix of equity, green bonds and long-term project financing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16534112/main.jpg
    Mark Dowdall
  • Qiddiya sets new deadline for infrastructure package

    23 April 2026

     

    Saudi gigaproject developer Qiddiya Investment Company (QIC) has set a 13 May deadline for bids for a contract covering new infrastructure works at Qiddiya Entertainment City.

    The scope comprises two infrastructure development packages for District 0 of Qiddiya Entertainment City, including the construction of four event park-and-ride facilities.

    The tender was issued on 11 March, with an initial bid submission deadline of 22 April.

    Lebanese firm Dar Al-Handasah and Saudi-based Sets International are serving as project consultants.

    QIC is accelerating plans to develop additional assets at Qiddiya City. Earlier this month, the company received prequalification statements from firms for the engineering, procurement, construction and finance package for the Qiddiya high-speed rail project.

    MEED has also reported that QIC received bids from contractors on 23 February for a SR980m ($261m) contract covering the construction of staff accommodation at Qiddiya Entertainment City.

    The project will cover an area of more than 105,000 square metres (sq m).

    Also in February, QIC started the main construction works on its performing arts centre at the entertainment hub.

    The Qiddiya City performing arts centre is one of several major projects within the greater Qiddiya development. Other projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a motorsports track, the Dragon Ball and Six Flags theme parks, and Aquarabia.

    QIC officially opened the Six Flags theme park to the public in December last year.

    The park covers 320,000 sq m and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.

    The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to UK analytics firm GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.

    Saudi Arabia’s tourism sector posted record figures last year, with more than 130 million domestic and international visitors – a 6% increase on 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16533776/main.jpg
    Yasir Iqbal
  • Detailed design progressing for major Iraqi oil project

    23 April 2026

     

    Detailed design work is progressing on Iraq’s 950-kilometre seawater pipeline network under the Common Seawater Supply Project (CSSP), according to industry sources.

    They added that on-site construction would begin only after the detailed design is complete.

    Iraq’s state-owned Basra Oil Company (BOC) and China Petroleum Pipeline Engineering (CPP) signed a $2.5bn contract for the pipeline package in September last year.

    The project is being supervised by Austria’s ILF Consulting Engineers.

    The pipeline package is one of two main CSSP packages.

    The second focuses on a seawater treatment facility, expected to have a capacity of 5 million barrels a day (b/d), potentially rising to 7-8 million b/d in later phases.

    Processed water will be injected into some of Iraq’s largest oil fields – Rumaila, Zubair, West Qurna 1, West Qurna 2 and Majnoon – and also used in the Maysan and Dhi Qar fields.

    Iraq’s Oil Ministry said the injected water will help maintain reservoir pressure and sustain crude production.

    CPP is a subsidiary of state-owned China National Petroleum Corporation.

    TotalEnergies is responsible for the CSSP as part of the larger $27bn Gas Growth Integrated Project.

    Iraq approved a $2.45bn contract with South Korea’s Hyundai Engineering & Construction (Hyundai E&C) in August last year for the engineering, procurement and construction of the seawater treatment plant.

    Over recent weeks, Iraq’s oil exports have collapsed by about 80% due to fallout from the US and Israel’s war with Iran.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16527404/main.jpg
    Wil Crisp