UAE ramps up decarbonisation of water sector

10 October 2023

This package on the UAE's water sector also includes: 

Dewa signs Hassyan water project agreements
Petrojet joins Project Wave contractor team
Project Wave first phase reaches financial close

Alpha Dhabi acquires majority stake in Metito
Hatta reservoir nears completion
Sharjah moves Hamriyah bid deadline


 

As a water-scarce country, the UAE has relied on non-conventional water, particularly seawater treated in desalination plants, to meet rising demand.

Over the past decade, the energy-intensive water treatment process, especially when using older technologies, has been a key focus for policymakers tasked with aligning industries with the country’s energy diversification and, more recently, net-zero carbon dioxide emissions agendas.

Decarbonising the water supply has entailed decoupling power and water production and improving the level of treated sewage effluent (TSE) reuse. Other initiatives involve modernising the water pipeline transmission network and tapping renewable energy to power desalination plants.

Demand management initiatives such as tariff reforms and awareness campaigns to make end users conscious of their consumption have also been put in place.

The past few months have marked several milestones in the country’s plan to decarbonise its water sector.

Two private water desalination plants that use reverse osmosis technology to treat seawater are in the final commissioning stage, expanding the UAE’s water production capacity from more energy-efficient plants.

These are the 200 million-imperial-gallon-a-day (MIGD) seawater reverse osmosis (SWRO) plant in Taweela in Abu Dhabi and another plant in Umm al-Quwain, which has a capacity of 150MIGD.

Abu Dhabi’s second major SWRO project, the 120MIGD Mirfa 2 independent water producer (IWP), also reached financial close this year.

Crucially, Abu Dhabi dismantled the thermal-powered Taweelah A2 independent water and power producer (IWPP) plant last year, following the expiry of its long-term offtake contract. The plant’s desalination unit ran on the older multi-stage flash technology.

Hassyan 1 

Dubai achieved an important milestone in October when state utility Dubai Electricity & Water Authority (Dewa) and Saudi-headquartered Acwa Power signed a 30-year water-purchase agreement (WPA) and shareholder agreement for the Hassyan 1 IWP project.

Acwa Power will develop and operate the power plant for 30 years at a levelised water cost of 36.5 $cents a cubic metre, a record low, although not nearly as low as the tariff proposed by another developer when the contract was first tendered.

The project supports Dewa’s plan to increase its water desalination capacity from 490MIGD to 750MIGD by the end of the decade.

Dewa has said the Hassyan 1 IWP will be powered by solar energy, further reducing the plant’s carbon footprint.

In Abu Dhabi, the official signing of a WPA for the Shuweihat S4 SWRO project is imminent, which will add another 70MIGD  to the emirate’s installed water production capacity once complete.

The Shuweihat 4 plant will cater to potable water demand in Abu Dhabi’s Al-Dhafra region, a key focus of Abu Dhabi’s economic development plan.

The bidding process is also under way for two more SWRO plants in Abu Dhabi. The Hudayriat and Saadiyat RO plants, each with a capacity of 50MIGD, will be developed as one IWP contract.

Emirates Water & Electricity Company (Ewec) has not mandated the inclusion of a solar photovoltaic (PV) plant for its most recent IWP projects, as it did for the Taweelah RO plant in 2019. However, it will likely tap either solar or nuclear energy, or both, for its upcoming SWRO plants in line with its goal to halve its total carbon dioxide emissions to 22 million tonnes a year by 2035.

The northern Sharjah emirate is also procuring its first IWP. The planned Hamriyah SWRO plant will have a capacity of 90MIGD.

In addition to the utility clients, Abu Dhabi National Oil Company (Adnoc) has awarded the contract to develop the first phase of Project Wave, which aims to replace the aquifer water injection systems used to maintain reservoir pressure in Abu Dhabi's onshore oil fields.

The project is expected to reduce the water injection-related energy consumption of the oil fields by up to 30 per cent.

Wastewater

Dubai Municipality activated a major programme this year to develop deep tunnels and sewage treatment plants across the emirate. This long-term project could require an investment of up to AED80bn ($22bn).

Known as the Deep Tunnels Portfolio, the scheme will be developed as a public-private partnership (PPP) initiative and will expand the role of private companies in the emirate’s water infrastructure sector.  

It involves the construction of two sets of deep tunnels terminating at two terminal pump stations located at sewerage treatment plants (STPs) in Warsan and Jebel Ali. A conventional sewage and drainage collection system and STPs will be built in Hatta. The scheme also includes recycled water distribution systems connected to the STPs.

Approved by Dubai’s Executive Council in June, the project has been designed to serve the needs of the Dubai population for the next 100 years in alignment with the Dubai Economic Agenda D33 and Dubai Urban Plan 2040.

In the UAE capital, Abu Dhabi Sustainable Water Solutions, formerly Abu Dhabi Sewerage Services Company, received bids for the contract to design, build and operate a planned TSE polishing plant in Al-Wathba earlier this year.

The plant is expected to have a design capacity of 700,000 cubic metres a day (cm/d), with the potential to expand this to 950,000 cm/d in a subsequent phase. The TSE facility will produce water for higher-end applications compared with TSE produced in a standard sewage treatment plant.

In addition to supporting the UAE’s long-term economic and demographic expansion, these water treatment projects also boost the country’s preferred circular carbon economy approach to energy transition.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11193002/main.gif
Jennifer Aguinaldo
Related Articles
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall
  • Qatar receives bids for major power grid expansion

    24 August 2026

     

    Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.

    The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.

    It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    According to sources, bids were submitted for the following packages on 20 August:

    • Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
    • Package S3, covering new 66/11kV substations ($50m)
    • Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
    • Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
    • Cable packages C1 and C2, covering 400kV cables ($100m)

    Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.

    In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.

    The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.

    Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.

    Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg
    Mark Dowdall
  • Maaden closes $1bn term loan and credit facility

    24 August 2026

    Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.

    The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.

    The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.

    The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.

    ALSO READ: Maaden and Aramco sign deal to create joint venture

    “The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.

    “The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.

    “Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg
    Indrajit Sen
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp