UAE ramps up decarbonisation of water sector

10 October 2023

This package on the UAE's water sector also includes: 

Dewa signs Hassyan water project agreements
Petrojet joins Project Wave contractor team
Project Wave first phase reaches financial close

Alpha Dhabi acquires majority stake in Metito
Hatta reservoir nears completion
Sharjah moves Hamriyah bid deadline


 

As a water-scarce country, the UAE has relied on non-conventional water, particularly seawater treated in desalination plants, to meet rising demand.

Over the past decade, the energy-intensive water treatment process, especially when using older technologies, has been a key focus for policymakers tasked with aligning industries with the country’s energy diversification and, more recently, net-zero carbon dioxide emissions agendas.

Decarbonising the water supply has entailed decoupling power and water production and improving the level of treated sewage effluent (TSE) reuse. Other initiatives involve modernising the water pipeline transmission network and tapping renewable energy to power desalination plants.

Demand management initiatives such as tariff reforms and awareness campaigns to make end users conscious of their consumption have also been put in place.

The past few months have marked several milestones in the country’s plan to decarbonise its water sector.

Two private water desalination plants that use reverse osmosis technology to treat seawater are in the final commissioning stage, expanding the UAE’s water production capacity from more energy-efficient plants.

These are the 200 million-imperial-gallon-a-day (MIGD) seawater reverse osmosis (SWRO) plant in Taweela in Abu Dhabi and another plant in Umm al-Quwain, which has a capacity of 150MIGD.

Abu Dhabi’s second major SWRO project, the 120MIGD Mirfa 2 independent water producer (IWP), also reached financial close this year.

Crucially, Abu Dhabi dismantled the thermal-powered Taweelah A2 independent water and power producer (IWPP) plant last year, following the expiry of its long-term offtake contract. The plant’s desalination unit ran on the older multi-stage flash technology.

Hassyan 1 

Dubai achieved an important milestone in October when state utility Dubai Electricity & Water Authority (Dewa) and Saudi-headquartered Acwa Power signed a 30-year water-purchase agreement (WPA) and shareholder agreement for the Hassyan 1 IWP project.

Acwa Power will develop and operate the power plant for 30 years at a levelised water cost of 36.5 $cents a cubic metre, a record low, although not nearly as low as the tariff proposed by another developer when the contract was first tendered.

The project supports Dewa’s plan to increase its water desalination capacity from 490MIGD to 750MIGD by the end of the decade.

Dewa has said the Hassyan 1 IWP will be powered by solar energy, further reducing the plant’s carbon footprint.

In Abu Dhabi, the official signing of a WPA for the Shuweihat S4 SWRO project is imminent, which will add another 70MIGD  to the emirate’s installed water production capacity once complete.

The Shuweihat 4 plant will cater to potable water demand in Abu Dhabi’s Al-Dhafra region, a key focus of Abu Dhabi’s economic development plan.

The bidding process is also under way for two more SWRO plants in Abu Dhabi. The Hudayriat and Saadiyat RO plants, each with a capacity of 50MIGD, will be developed as one IWP contract.

Emirates Water & Electricity Company (Ewec) has not mandated the inclusion of a solar photovoltaic (PV) plant for its most recent IWP projects, as it did for the Taweelah RO plant in 2019. However, it will likely tap either solar or nuclear energy, or both, for its upcoming SWRO plants in line with its goal to halve its total carbon dioxide emissions to 22 million tonnes a year by 2035.

The northern Sharjah emirate is also procuring its first IWP. The planned Hamriyah SWRO plant will have a capacity of 90MIGD.

In addition to the utility clients, Abu Dhabi National Oil Company (Adnoc) has awarded the contract to develop the first phase of Project Wave, which aims to replace the aquifer water injection systems used to maintain reservoir pressure in Abu Dhabi's onshore oil fields.

The project is expected to reduce the water injection-related energy consumption of the oil fields by up to 30 per cent.

Wastewater

Dubai Municipality activated a major programme this year to develop deep tunnels and sewage treatment plants across the emirate. This long-term project could require an investment of up to AED80bn ($22bn).

Known as the Deep Tunnels Portfolio, the scheme will be developed as a public-private partnership (PPP) initiative and will expand the role of private companies in the emirate’s water infrastructure sector.  

It involves the construction of two sets of deep tunnels terminating at two terminal pump stations located at sewerage treatment plants (STPs) in Warsan and Jebel Ali. A conventional sewage and drainage collection system and STPs will be built in Hatta. The scheme also includes recycled water distribution systems connected to the STPs.

Approved by Dubai’s Executive Council in June, the project has been designed to serve the needs of the Dubai population for the next 100 years in alignment with the Dubai Economic Agenda D33 and Dubai Urban Plan 2040.

In the UAE capital, Abu Dhabi Sustainable Water Solutions, formerly Abu Dhabi Sewerage Services Company, received bids for the contract to design, build and operate a planned TSE polishing plant in Al-Wathba earlier this year.

The plant is expected to have a design capacity of 700,000 cubic metres a day (cm/d), with the potential to expand this to 950,000 cm/d in a subsequent phase. The TSE facility will produce water for higher-end applications compared with TSE produced in a standard sewage treatment plant.

In addition to supporting the UAE’s long-term economic and demographic expansion, these water treatment projects also boost the country’s preferred circular carbon economy approach to energy transition.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11193002/main.gif
Jennifer Aguinaldo
Related Articles
  • Consultant wins Dubai Al-Maktoum airport metro link

    11 September 2026

     

    Register for MEED’s 14-day trial access 

    US-based engineering firm Aecom has won a design contract for the Route 2020 extension, which will start from the Expo 2020 metro station and connect with Al-Maktoum International airport’s West Terminal.

    Dubai’s Roads & Transport Authority (RTA) awarded the contract.

    The extension will run about 3 kilometres (km) and include two stations.

    MEED understands the invitation to bid was issued in January, with a submission deadline in mid-March.

    The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    The RTA awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain’s Acciona, Turkiye’s Gulermak and France’s Alstom in 2016.

    The RTA also selected Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4, in October last year, as MEED reported.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19571676/main.jpg
    Yasir Iqbal
  • Saudi Arabia sets October deadline for Mecca metro design

    11 September 2026

     

    The Royal Commission for Makkah City & Holy Sites (RCMC) has set a deadline of 14 October for a contract covering the initial design studies for its long-planned metro network in the holy city.

    The scope includes reviewing existing studies, preparing a concept design, conducting land acquisition studies, developing an integration concept for future phases and other related studies.

    The notice was issued in May, with an initial submission deadline of 5 August, as MEED reported.

    In September last year, RCMC invited contractors to attend an early market engagement meeting for the project.

    In an explanatory document inviting companies to attend the event, the RCMC’s General Transport Centre said it was seeking to gauge market interest in the multibillion-dollar project and obtain feedback on its proposed procurement approach.

    MEED exclusively reported in June last year that the project was restarting. Current plans envisage a four-line network, named lines A-D, with 89 stations and three depots, to be implemented over three phases between 2032 and 2045.

    Project scope

    Stage 1 focuses on lines B and C, involving 2.4 kilometres of tunnelling under the Masar project and integration with the existing Mashaer line.

    The network will run just over 62km and comprise 31 stations, 21 of which will be underground, including three iconic stations. A total of 19.5km will run through tunnels, while 41.2km will be elevated, with the remainder at grade.

    The 66 required trainsets are projected to provide a daily passenger capacity of about 450,000, equating to annual ridership of 171 million.

    The 84.7km-long second phase, due to be operational by 2038, will extend the two lines towards the outskirts of Mecca and includes construction of the initial inner and central segments of lines A and D.

    Comprising 61.1km elevated and 18.6km underground, Phase 2 is planned to add 45 stations serving the two new lines, as well as two depots and a potential interconnection with the planned Saudi Landbridge. The 59 trainsets for Phase 2 will increase the network’s projected total annual passenger capacity to more than 500 million.

    Phase 3 covers the elevated 36km extension of lines A and D and involves procurement of a further 72 trainsets, increasing the network’s ultimate passenger capacity to 1.2 million daily and 642 million annually by completion in 2045.

    Associated development

    The metro plan also envisages several transit-oriented developments (TODs) at different points on the route. These will typically comprise commercial, residential and retail elements to maximise the investment case.

    The client’s proposed procurement approach involves three distinct packages: civil and systems works, TODs, and operations and maintenance.

    The initial concept calls for some of the project to be delivered on a public-private partnership (PPP) basis, wherein the private sector, through special purpose vehicles, will part-finance, build, operate and then transfer commercially viable elements of the scheme.

    The then-called Mecca Mass Rail Transit Company (MMRTC) first launched the metro project in 2013; however, the scheme has faltered for more than a decade due to funding issues, land acquisition challenges and scope changes.

    The relaunch of the procurement process raises hopes that the project will now come to fruition, although it is likely to be at least 18 months before any definitive works start.

    Mecca is home to Saudi Arabia’s first metro, the nine-station, 18km-long Mashaer line, which opened in 2010. It operates only seven days a year during Hajj, but carries more than 2 million pilgrims during that time.

    Some 30 million pilgrims visit the city each year, with this number set to grow. A known, quantifiable and growing demand base will help facilitate the use of a PPP mechanism if the framework is adopted.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19569659/main.jpg
    Yasir Iqbal
  • Consortiums submit bids for Sadara cogeneration plant

    11 September 2026

     

    Register for MEED’s 14-day trial access 

    At least three consortiums have submitted bids for the contract to develop and operate a cogeneration steam and power plant catering to the Sadara petrochemicals complex in Saudi Arabia.

    The planned independent steam and power plant (ISPP) project will have a capacity for 400MW-450MW of combined-cycle electricity generation and 550-700 tonnes an hour of steam.

    According to sources, bids were submitted for the contract at the end of August.

    The consortium bidders include: 

    • Abu Dhabi National Energy Company (Taqa) / Samsung C&T (South Korea)
    • Al-Jomaih Energy & Water (Saudi Arabia) / Albawani (Saudi Arabia) / Sepco 3 (China)
    • Acwa (Saudi Arabia), Korea Electric Power Corporation (Kepco) / Doosan Enerbility (South Korea)

    Sadara Chemical Company (Sadara) is the project client. It is the downstream joint venture of Saudi Aramco and US-headquartered Dow Chemical.

    The estimated $500m project includes construction of a power plant, substations, a seawater intake system and associated switchyards and switchgear.

    The project will also include gas turbines and a back-pressure steam turbine, as well as facilities for steam production.

    In 2024, MEED exclusively reported that Sadara had prequalified potential bidders for the project. It is understood that the request for proposals was issued towards the end of last year.

    The first units at the $20bn Sadara petrochemicals complex in Jubail began production in 2016, and the complex became operational in 2017.

    The Sadara complex is designed to produce more than 3 million tonnes a year (t/y) of chemicals and performance plastics, including polyurethanes, propylene oxide, propylene glycol, elastomers, polyethylene, glycol ethers and amines.

    Construction is also continuing on the Najim cogeneration facility, which will supply the Amiral petrochemicals complex with up to 475MW of power and approximately 452 tonnes an hour of steam.

    Previously known as the Amiral cogeneration independent steam and power plant, the project is being developed by a team comprising Abu Dhabi National Energy Company (Taqa) and Japanese power generation company Jera.

    South Korean contractor Samsung C&T is the engineering, procurement and construction contractor for the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19567716/main.jpg
    Mark Dowdall
  • UAE plans 150km Boring Company tunnel network

    11 September 2026

    The UAE plans to build more than 150 kilometres of underground tunnel with US tunnelling firm The Boring Company, in a programme backed by a $3bn funding round the UAE led.

    The Series D round values the Boring Company at $23bn, about four times the $5.7bn it was worth after a 2022 funding round. The UAE and affiliated investment entities led the round, which will accelerate a partnership to deploy underground infrastructure across the UAE, the firm said.

    The 150km target marks a substantial expansion of the company’s footprint in the country, extending work already committed through the Dubai Loop project. It contrasts sharply with what has been contracted so far. The Boring Company has signed a construction contract with Dubai’s Roads & Transport Authority (RTA) for the pilot phase of Dubai Loop, covering a 6.4km route and four stations linking Dubai International Financial Centre (DIFC) and Dubai Mall. The pilot is expected to cost about AED565m ($154m), with tunnelling due to begin in the second half of this year.

    The 150km figure therefore represents an ambition for the wider partnership rather than a contracted volume, with the bulk of the network yet to be tendered, designed or awarded. No timeframe has been attached to the target.

    A second Dubai Loop phase will connect Dubai World Trade Centre and DIFC with Business Bay, extending the tunnels to 22km across 19 stations. The total cost across both phases is expected to be about AED2bn ($545m), with completion scheduled within three years. The pilot route is projected to carry about 13,000 passengers a day, rising to about 30,000 a day across the full route.

    Other investors in the round include Human Capital, Vy Capital, Valor Equity Partners, Sequoia Capital, Andreessen Horowitz, Temasek, Shamal Holding and Baron Capital. The proceeds will also fund hiring, the scaling of the company’s Loop transit systems in the US cities of Las Vegas and Nashville, and further development of its Prufrock tunnel-boring machines, which it says can operate in both soft ground and hard rock.

    The RTA and the Boring Company signed a memorandum of understanding in February last year to explore developing the Dubai Loop, and the construction contract followed in February this year. In May, US engineering firm Parsons was appointed as programme manager for the pilot phase, with a scope covering independent design verification, permitting and multidisciplinary design reviews.

    The appointment comes amid a broader shift towards underground construction across the Gulf, as metro, sewerage and highway works in the UAE, Saudi Arabia and Qatar increasingly default to tunnelling.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19567623/main.jpg
    Yasir Iqbal
  • Heisco wins $359m oil contract in Kuwait

    11 September 2026

    Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco) has been awarded a contract worth KD111.05m ($359m) to develop storage tanks for Kuwait’s Jurassic Light Oil (JLO) export facilities, according to a stock market filing.

    The scope of the contract includes civil, mechanical, electrical and instrumentation works, as well as engineering, procurement and construction (EPC) services for the tanks.

    The contract was awarded by India’s Larsen & Toubro (L&T), the main contractor for a broader project to develop JLO storage and export facilities in Kuwait, as well as upgrade Kuwait Oil Company’s (KOC’s) existing export network.

    The $979.2m main contract for this broader project was awarded to L&T on 15 July.

    The contract for Heisco’s scope of work has a time period of 42 months, according to its stock market filing.

    Oil crisis

    Kuwait’s oil and gas sector is currently in crisis due to the regional war that started after the US and Israel attacked Iran on 28 February.

    The war has severely disrupted exports through the Strait of Hormuz, which Kuwait relies on in order to ship crude exports.

    It has also disrupted imports of equipment and materials for projects, raising project costs.

    Sheikh Nawaf Saud Al-Sabah, deputy chairman and CEO of Kuwait Petroleum Corporation (KPC), the country’s national oil company, has described the current conflict as the biggest oil crisis the country has faced since Iraq’s 1990 invasion.

    Despite the significant reduction in crude exports, Kuwait’s state-owned oil companies have continued to tender some projects.

    Export facilities

    The scope of work under the contract awarded to L&T in July includes the EPC of six new crude oil storage tanks, each with an operating capacity of 618,000 barrels, along with associated facilities, the Mumbai-headquartered company said on 29 July.

    The project also involves “the installation of new pipelines and comprehensive upgrades to Kuwait’s existing crude loading and export network, to seamlessly accommodate increased production and enhance the country’s crude handling capabilities”, the Bombay Stock Exchange-listed company said.

    L&T also said that the contract will be executed on a lump-sum turnkey basis.

    Only two companies submitted bids for the contract in October last year:

    • L&T (India): KD303.5m ($988m)
    • Petrofac (UK): KD310.6m ($1.01bn)

    Following bid submission, KPC discussed the potential cancellation of the tender due to bids coming in significantly over budget and Petrofac becoming ineligible to win contracts in Kuwait.

    The contractor was temporarily barred from participating in tenders in Kuwait’s oil and gas sector in December last year.

    Petrofac received the ban after the company announced it had applied to appoint administrators, a move that potentially put thousands of jobs at risk and increased uncertainty for projects worth billions of dollars in the Middle East and North Africa region.

    Despite discussions about cancelling the tender, KPC ultimately decided to proceed with the award process because it considered the project a high priority.

    One source previously told MEED: “Around the same time, projects worth around $8bn were cancelled because of bids coming in over budget, but this one has gone ahead because KPC sees it as an essential project.”

    The project was originally tendered in November 2024, with a bid deadline of 1 December the same year. The bid deadline was extended several times before bids were ultimately submitted.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19556019/main.png
    Wil Crisp