UAE PPP activity rises

8 October 2024

 

All eyes are on Dubai in the final quarter of the year as it endeavours to bring to the market its largest infrastructure project to date.

The prequalification process is under way for potential investors for the planned $22bn Dubai Strategic Sewerage Tunnels (DSST) project, which will be procured on a public-private partnership (PPP) basis.

The project's ambitious scope includes converting Dubai’s existing sewerage system from a pumped system to a gravity system by decommissioning the existing pump stations and providing “a sustainable, innovative, reliable service for future generations”.

Dubai currently has two major sewerage catchments. The first, in Deira, is Warsan, where the Warsan sewage treatment plant (STP) treats the flow. The second catchment is in Bur Dubai, where the wastewater is treated at the Jebel Ali STP.

The DSST will replace 120 pump stations, saving approximately 100 gigawatt-hours of electricity annually, MEED has been told. 

The 25-35-year design-build-finance procurement model is also ambitious, given that Dubai has a dismal PPP track record, with the exception of electricity and water generation projects.

The DSST project has met major interest from engineering, procurement and construction (EPC) contractors. A total of 21 individual companies and consortiums prequalified to bid for the project’s three tunnels and terminal pump station packages – J1, J2 and W. Nineteen have been prequalified to bid for package J3.

The client is expected to run a separate prequalification process for the packages to upgrade the two existing STPs.

At the time of writing, Dubai Municipality, the project client, has yet to receive the statements of qualifications from interested investors.

Industry sources have indicated, however, that those that have shown early interest include Japan's Marubeni Corporation and Itochu, Australia's Plenary Group, Belgium's Besix, China Railway Engineering Corporation and China Harbour Engineering Company, and potentially some Israeli investors.

The project is essential to support Dubai’s economic expansion and sustainability ambitions, notes a source close to the scheme, stopping short of saying that the lack of suitable infrastructure could limit the extent to which the emirate can grow.

So far, while everyone agrees that the project is imperative, some need further convincing of the likelihood of success for the project’s chosen PPP route.

“It is a civil construction project with limited operation and maintenance scope,” says a senior executive with an infrastructure investor, who adds that the government of Dubai can raise a bond much cheaper than equity.

A senior transaction adviser not linked to the project notes, however, that since PPPs are a combination of debt and equity, “overall, PPPs are cheaper for governments”.

The latter adds that the PPP route is doable if the project is tendered in phases or one at a time, as is currently planned.

 Water desalination and treatment projects

In recent months, the UAE has also seen an uptick in water desalination plants utilising reverse osmosis technology.

Three independent water projects (IWPs) are under construction, including Abu Dhabi’s Mirfa 2 and Shuweihat 4, and Hassyan 1 in Dubai. The three seawater reverse osmosis (SWRO) plants have a total combined capacity of 370 million imperial gallons a day (MIGD).

Negotiations are under way for the contract to develop Abu Dhabi’s next IWP on Saadiyat Island, while the request for qualifications for another project, the 90MIGD Al-Nouf IWP, is expected to be issued in December this year or January 2025.

Sharjah Electricity & Water Authority (Sewa) also awarded the contract to develop its first IWP scheme this year to Saudi Arabia-headquartered Acwa Power, which was the tender’s sole bidder.

The $682m, 90MIGD project is expected to reach financial close soon.

"This is Sharjah’s first IWP and, unlike other jurisdictions such as Oman, Abu Dhabi and Saudi Arabia, the emirate has yet to establish a track record with PPPs, especially in power and water," says Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting.

He notes that once the Hamriyah IWP reaches financial close and commercial operations, Sewa should be able to attract more developers for future IWPs. 

Sewa is not the only utility launching its maiden IWP. Etihad Water & Utility (Etihad WE) is understood to have conducted a market-sounding event earlier this year for a small SWRO plant to complement the capacity of an existing facility in Ghalilah in Ras Al-Khaimah, another of the UAE's northern emirates.

Ras Al-Khaimah's Public Services Department and Investment & Development Office have also started the tendering proceedings for the emirate's first independent sewage treatment plant project.

The proposed plant will be able to treat 60,000 cubic metres a day (cm/d) of sewage water, which could be expanded to 150,000 cm/d.

The project has garnered strong interest from the market, with the following companies and consortiums having been prequalified to bid for the contract:

  • Acciona (Spain)
  • Besix (Belgium)
  • China Harbour Engineering Company (China) / BOWT
  • Cobra (Tedagua, Spain)
  • GS Inima (Spain/South Korea) / Alkhorayef Water & Power Technologies (Saudi Arabia)
  • Etihad Water & Electricity (UAE) / Saur (France)
  • FCC Aqualia (Spain)
  • MA Kharafi (Kuwait) / Passavant Energy & Environment (UAE, Germany)
  • Metito
  • Miahona Company (Saudi Arabia)
  • Orascom Construction (Egypt)
  • Sustainable Water Solutions (UAE)
  • Veolia Middle East (France / local)

MEED understands that the scope of the build, own, operate and transfer scheme will include extensive sewerage and distribution works, in addition to the STP.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12673874/main1756.jpg
Jennifer Aguinaldo
Related Articles
  • Chinese and Saudi partners set up Hithium Manat

    17 October 2024

    Register for MEED's 14-day trial access 

    Chinese energy storage solutions firm Hithium Energy Storage Technology Company (Hithium) and the local Nabilah AlTunisi have formed a joint venture that will manufacture battery energy storage systems (bess) in Saudi Arabia.

    The joint venture is called Hithium Manat. The planned manufacturing facility has an annual production capacity target of 5 gigawatt-hours (GWh), according to an official statement.

    Hithium launched energy storage solutions designed for the region's harsh environment during a solar and storage conference held in Riyadh.

    According to Hithium, "These systems feature advanced sandstorm protection and robust high and low-temperature designs, supporting ultra-long discharge cycles of 12+ hours."

    It added that the new product line is "customised to meet the unique demands of the Middle East and Africa region".

    Nabilah AlTunisi is the founder and owner of Hithium Manat's local partner.

    "This strategic alliance will not only provide access to world-class energy storage technology but also generate local employment opportunities, stimulate technological innovation and actively contribute to realising the kingdom's Vision 2030 objectives," AlTunisi said.

    Battery energy storage market

    In August, National Grid Saudi Arabia, a subsidiary of state utility Saudi Electricity Company, awarded the engineering, procurement and construction (EPC) contracts for three energy storage systems to Riyadh-based investment group Algihaz Holding. The estimated $800m projects are located in Najran, Madaya and Khamis Mushait.

    National Grid also recently tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW across the kingdom.

    The planned facilities, each with a capacity of 500MW or roughly 2,000 megawatt-hours, are located in or within proximity of the following key cities and load centres:

    • Riyadh
    • Qaisumah
    • Dawadmi
    • Al-Jouf
    • Rabigh

    Every utility in the region is procuring or planning to procure bess capacity in light of growing intermittent renewable power in their grids. 

    The overall capacity of deployed bess globally is expected to reach 127GW by 2027, up from an estimated cumulative deployment of 36.7GW at the end of 2023, a GlobalData report issued in June said.

    The report cited Chinese companies BYD and CATL and South Korean companies LG Energy Solutions and Samsung SDI among the top battery technology providers globally.

    Related read: Battery storage gains foothold

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12742375/main.jpg
    Jennifer Aguinaldo
  • Kahramaa invites Ras Laffan substation bids

    17 October 2024

    Qatar state utility General Electricity & Water Corporation (Kahramaa) has tendered a contract to upgrade the Ras Laffan C substation.

    The scope of work covers the upgrade of existing 220-kilovolt (kV) and 400kV substations and the addition of 220kV gas-insulated switchgear bays and an 800-megavolt amps transformer.

    Kahramaa issued the tender on 15 October and expects to receive bids by 28 November.

    The project bid bond is valued at QR1.5m ($410,000).

    Separately, Kahramaa invited firms to submit their proposals for a contract to supply and install power transmission and distribution equipment, including providing and connecting substation main earth and equipment earthing, commissioning fitted substations and pre-commissioning protection testing for 11kV switchgear panels.

    Kahramaa expects to receive bids for this contract, with a bid bond of QR3m, by 14 November.

    Kahramaa is expanding its power generation capacity. Negotiations are under way with the sole bidder led by Japan's Sumitomo Corporation for a contract to develop and operate Qatar’s Facility E independent water and power producer (IWPP) project.

    The Facility E IWPP scheme will have a power generation capacity of 2,300MW and a water desalination capacity of 100 million imperial gallons a day.

    Earlier this month, Qatar Electricity & Water Company announced plans to develop a 500MW peak power unit in Qatar's Ras Abu Fontas area.

    Construction is also under way for two solar farms with a total combined capacity of 875MW in Mesaieed and Ras Laffan.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12742343/main.jpg
    Jennifer Aguinaldo
  • Neom starts Tabuk highway prequalifications

    17 October 2024

     

    Saudi Arabian gigaproject developer Neom expects firms to submit their prequalification applications for a project to build a mountain road near Tabuk later this month.

    The 11.5-kilometre (km) Tabuk mountain road project comprises a 4km tunnel and 7.5km dualisation of an existing road, according to an industry source.

    Neom expects to receive statements of qualifications from interested engineering, procurement and construction contractors by 29 October.

    The tender proceedings for Neom's transport infrastructure projects are gathering momentum.

    Neom received expressions of interest for a contract to build a coastal highway and infrastructure project catering to the Magna development on the Gulf of Aqaba on 15 October.

    The project, called Magna Infrastructure Packages, is split into three. Package one is 13km, package two is 42km and package three is 41km. The packages cater to the development’s north, central and south areas.

    The design-and-build project covers utilities for water, power, mobility, sewer, buildings and highways, in addition to the coastal highway. The project is expected to be completed by 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12738632/main.gif
    Jennifer Aguinaldo
  • Adnoc completes Fertiglobe stake acquisition

    16 October 2024

    Register for MEED's 14-day trial access 

    Abu Dhabi National Oil Company (Adnoc) has completed the transaction to acquire a majority stake in UAE-headquartered Fertiglobe, the largest nitrogen-based fertiliser producer in the Middle East and North Africa region.

    Adnoc has increased its shareholding in Fertiglobe to 86.2% through the acquisition of 50% + 1 share held by Netherlands-based OCI Global, which is backed by Egyptian billionaire Nassef Sawiris. The Abu Dhabi energy giant previously held a 36.2% stake in Fertiglobe.

    The remaining 13.8% of Fertiglobe’s shares trade on the Abu Dhabi Securities Exchange following the company's stock listing in October 2022.

    Adnoc announced the transaction to become the majority shareholder in Fertiglobe last December. Fertiglobe’s shares were priced at AED3.2 ($0.87) a share, valuing the deal at $3.62bn.

    Following the completion of the majority acquisition, “Fertiglobe’s current management team will stay in place”, including Ahmed El-Hoshy in his role as CEO, Adnoc said in a statement on 15 October.

    “Ahmed El-Hoshy spent 15 years growing OCI’s US and European business in ammonia and methanol via greenfields, brownfields and acquisitions, generating significant value for shareholders by leading recent divestments,” Adnoc said.

    Growing chemicals business

    Fertiglobe is the world’s largest seaborne exporter of urea and ammonia combined, exporting to 53 countries with a collective market share of about 10% of global trade in these products.

    “The acquisition represents … the expansion of Adnoc’s low-carbon fuels business, and supports its goal to become a top-five global chemicals player,” Adnoc said.

    “Fertiglobe will become the platform for Adnoc’s growth in fertiliser and low-carbon ammonia,” Adnoc said in its statement.

    Adnoc added it will transfer its stakes in existing and future low-carbon ammonia projects to Fertiglobe “at cost and when ready for startup”, including its two projects in Abu Dhabi and other projects in its global portfolio. Adnoc has yet to specify the low-carbon ammonia and blue ammonia production projects.

    MEED understands that the first Abu Dhabi project in question is the blue ammonia facility in the Taziz Industrial Chemicals Zone in Ruwais. Fertiglobe has partnered with South Korea’s GS Energy Corporation and Japanese investment firm Mitsui & Company to build the complex, which will have a production capacity of 1 million tonnes a year (t/y).

    In February last year, the joint venture awarded Italian firm Tecnimont the main contract for executing the engineering, procurement and construction works on the Taziz blue ammonia project.

    The second Abu Dhabi blue ammonia project that Adnoc could be referring to in its statement is a proposed scheme for which it signed a joint feasibility study agreement with British energy producer BP in May 2022.

    Adnoc further said that the two projects in Abu Dhabi will add 2 million t/y of output potential, more than doubling Fertiglobe’s current commercial ammonia capacity of 1.6 million t/y and increasing its total sellable capacity to 8.6 million t/y of net ammonia and urea combined, in addition to other announced global projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12735570/main1542.jpg
    Indrajit Sen
  • Neom receives interest for Magna coastal highway

    16 October 2024

     

    Saudi Arabia’s gigaproject developer Neom has received interest from firms for the contract to build a coastal highway and infrastructure project linking Neom to the Magna development on the Gulf of Aqaba.

    The project, called Magna Infrastructure Packages, is split into three. 

    Package 1 is 13 kilometres, package 2 is 42km and package 3 is 41km.

    The packages cater to the development’s north, central and south areas.

    According to an industry source, the design-and-build project covers utilities for water, power, mobility, sewer, buildings and highways. It could cost between $250m and $500m.

    Local and international engineering, procurement and construction (EPC) contractors are understood to have submitted their expressions of interest to participate in the tender on 15 October.

    The coastal highway and infrastructure project is expected to be completed by 2027, the source said.

    Magna consists of 12 developments featuring 15 hotels that offer 1,600 hotel rooms, suites and apartments and over 2,500 residences.

    The development will span a 120km-long coastal strip with an average width of 3.5km. The total land area is about 430 square kilometres.

    The Magna infrastructure is divided into six districts, as follows:

    • District 1 – Northern Gateway: includes 13 bridges and underpasses with a length of 1.9km, 18 wadi culverts and five drainage culverts
    • District 2 – Romantic Bay and the Cube: includes two bridges and underpasses spanning 360 metres, 40 wadi culverts and 24 drainage culverts
    • District 3 – Wadi Tayyib: includes two bridges and underpasses, 26 wadi culverts and nine drainage culverts
    • District 4 – Jungle Club: includes three bridges and underpasses and 17 wadi culverts
    • District 5 – Magna: includes two bridges and underpasses, 14 wadi culverts and two drainage culverts
    • District 6 – Southern Gateway: includes three bridges and underpasses, 31 wadi culverts and one drainage culvert
    https://image.digitalinsightresearch.in/uploads/NewsArticle/12735899/main.jpg
    Jennifer Aguinaldo