UAE PPP activity rises
8 October 2024

All eyes are on Dubai in the final quarter of the year as it endeavours to bring to the market its largest infrastructure project to date.
The prequalification process is under way for potential investors for the planned $22bn Dubai Strategic Sewerage Tunnels (DSST) project, which will be procured on a public-private partnership (PPP) basis.
The project's ambitious scope includes converting Dubai’s existing sewerage system from a pumped system to a gravity system by decommissioning the existing pump stations and providing “a sustainable, innovative, reliable service for future generations”.
Dubai currently has two major sewerage catchments. The first, in Deira, is Warsan, where the Warsan sewage treatment plant (STP) treats the flow. The second catchment is in Bur Dubai, where the wastewater is treated at the Jebel Ali STP.
The DSST will replace 120 pump stations, saving approximately 100 gigawatt-hours of electricity annually, MEED has been told.
The 25-35-year design-build-finance procurement model is also ambitious, given that Dubai has a dismal PPP track record, with the exception of electricity and water generation projects.
The DSST project has met major interest from engineering, procurement and construction (EPC) contractors. A total of 21 individual companies and consortiums prequalified to bid for the project’s three tunnels and terminal pump station packages – J1, J2 and W. Nineteen have been prequalified to bid for package J3.
The client is expected to run a separate prequalification process for the packages to upgrade the two existing STPs.
At the time of writing, Dubai Municipality, the project client, has yet to receive the statements of qualifications from interested investors.
Industry sources have indicated, however, that those that have shown early interest include Japan's Marubeni Corporation and Itochu, Australia's Plenary Group, Belgium's Besix, China Railway Engineering Corporation and China Harbour Engineering Company, and potentially some Israeli investors.
The project is essential to support Dubai’s economic expansion and sustainability ambitions, notes a source close to the scheme, stopping short of saying that the lack of suitable infrastructure could limit the extent to which the emirate can grow.
So far, while everyone agrees that the project is imperative, some need further convincing of the likelihood of success for the project’s chosen PPP route.
“It is a civil construction project with limited operation and maintenance scope,” says a senior executive with an infrastructure investor, who adds that the government of Dubai can raise a bond much cheaper than equity.
A senior transaction adviser not linked to the project notes, however, that since PPPs are a combination of debt and equity, “overall, PPPs are cheaper for governments”.
The latter adds that the PPP route is doable if the project is tendered in phases or one at a time, as is currently planned.
Water desalination and treatment projects
In recent months, the UAE has also seen an uptick in water desalination plants utilising reverse osmosis technology.
Three independent water projects (IWPs) are under construction, including Abu Dhabi’s Mirfa 2 and Shuweihat 4, and Hassyan 1 in Dubai. The three seawater reverse osmosis (SWRO) plants have a total combined capacity of 370 million imperial gallons a day (MIGD).
Negotiations are under way for the contract to develop Abu Dhabi’s next IWP on Saadiyat Island, while the request for qualifications for another project, the 90MIGD Al-Nouf IWP, is expected to be issued in December this year or January 2025.
Sharjah Electricity & Water Authority (Sewa) also awarded the contract to develop its first IWP scheme this year to Saudi Arabia-headquartered Acwa Power, which was the tender’s sole bidder.
The $682m, 90MIGD project is expected to reach financial close soon.
"This is Sharjah’s first IWP and, unlike other jurisdictions such as Oman, Abu Dhabi and Saudi Arabia, the emirate has yet to establish a track record with PPPs, especially in power and water," says Robert Bryniak, CEO of Dubai-based Golden Sands Management (Marketing) Consulting.
He notes that once the Hamriyah IWP reaches financial close and commercial operations, Sewa should be able to attract more developers for future IWPs.
Sewa is not the only utility launching its maiden IWP. Etihad Water & Utility (Etihad WE) is understood to have conducted a market-sounding event earlier this year for a small SWRO plant to complement the capacity of an existing facility in Ghalilah in Ras Al-Khaimah, another of the UAE's northern emirates.
Ras Al-Khaimah's Public Services Department and Investment & Development Office have also started the tendering proceedings for the emirate's first independent sewage treatment plant project.
The proposed plant will be able to treat 60,000 cubic metres a day (cm/d) of sewage water, which could be expanded to 150,000 cm/d.
The project has garnered strong interest from the market, with the following companies and consortiums having been prequalified to bid for the contract:
- Acciona (Spain)
- Besix (Belgium)
- China Harbour Engineering Company (China) / BOWT
- Cobra (Tedagua, Spain)
- GS Inima (Spain/South Korea) / Alkhorayef Water & Power Technologies (Saudi Arabia)
- Etihad Water & Electricity (UAE) / Saur (France)
- FCC Aqualia (Spain)
- MA Kharafi (Kuwait) / Passavant Energy & Environment (UAE, Germany)
- Metito
- Miahona Company (Saudi Arabia)
- Orascom Construction (Egypt)
- Sustainable Water Solutions (UAE)
- Veolia Middle East (France / local)
MEED understands that the scope of the build, own, operate and transfer scheme will include extensive sewerage and distribution works, in addition to the STP.
Exclusive from Meed
-
Shell approves Egypt offshore gas project31 August 2026
-
Contractors appointed for Group 1 battery storage projects27 August 2026
-
Accor and Al-Qimmah plan 4,000 Saudi rooms27 August 2026
-
Jeddah tenders stormwater drainage contracts27 August 2026
-
Technip Energies secures role in Umm Shaif Gas Cap project26 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Shell approves Egypt offshore gas project31 August 2026
BG Delta, a Shell subsidiary, has reached the final investment decision for phase 12a of the West Delta Deep Marine (WDDM) development project.
The project will be implemented in partnership with Malaysia’s Petronas and state-owned Egyptian General Petroleum Corporation (EGPC).
Shell, Petronas and EGPC formed a joint venture called Burullus Gas Company to operate the WDDM concession.
Phase 12a includes drilling and completing three deepwater gas wells, with production expected to begin in 2028, according to a statement from the London-headquartered company.
The wells will be tied into existing subsea infrastructure, helping accelerate development, improve capital efficiency and limit the need for additional facilities.
Dalia El-Gabry, the vice-president and chairperson of Shell Egypt, said: “This investment demonstrates our commitment to maximising the remaining potential in WDDM where the right technical and commercial conditions exist.
“By leveraging existing infrastructure and our proven development experience, we can accelerate delivery while reinforcing our partnership with the Egyptian government and joint venture partners to help meet Egypt’s energy needs.”
The new development builds on phases 10 and 11, which brought six wells online during 2024 and 2025.
Its scope also covers facility installation, tie-in operations, commissioning and connection to existing offshore infrastructure.
Egypt’s Ministry of Petroleum & Mineral Resources said in May that about $350m had been allocated to phase 12a.
In April, Egypt’s Petroleum Marine Services (PMS) was awarded a contract for offshore works for phase 12 of the WDDM field development project.
The contract awarded to PMS uses the engineering, procurement, installation and construction contract model.
Under the scope of the contract, PMS will install the required electrical, hydraulic and mechanical connections in deep waters to tie three new gas wells into production as part of phase 12.
The scope also includes the installation of three final triple tie-in spool bases to complete the connection between the wells.
During phases 10 and 11 of the WDDM project, PMS laid two offshore electrical cables at water depths reaching 660 metres, in addition to carrying out well tie-in and production connection works at depths of up to 880 metres.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19078753/main.jpg -
Contractors appointed for Group 1 battery storage projects27 August 2026

Register for MEED’s 14-day trial access
Two contractors have been appointed for engineering, procurement and construction (EPC) works on Saudi Arabia’s four Group 1 battery energy storage system (bess) projects with a combined capacity of 2,000MW, a source has confirmed to MEED.
Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), recently signed four storage service agreements for the bess projects, which will provide four hours of storage, equivalent to 8,000 megawatt-hours (MWh), and involve a total investment of more than SR4.35bn ($1.16bn).
Three projects were awarded to a consortium comprising Saudi Energy, Acwa and Al-Sharif Contracting & Commercial Development Company.
According to the source, India’s Larsen & Toubro will carry out EPC works for these three projects, comprising the Al-Muwyah and Haden bess independent storage providers (ISPs) in the Mecca region, and the Al-Kahafa bess ISP in the Hail region.
Each has a capacity of 500MW for four hours. The three projects have a combined capacity of 1,500MW and 6,000MWh.
L&T recently announced that it had secured “a major order” for bess projects in the Middle East but did not disclose the specific projects involved.
The fourth project, the Al-Khushaybi bess ISP in the Qassim region, was awarded to a consortium of France’s Engie and local firm Haji Abdullah Alireza & Co. This also has a capacity of 500MW for four hours.
China’s Sepco 3 has been appointed as the EPC contractor for this project, a source said.
The agreements cover the first group of ISP bess projects being procured by SPPC under a build, own and operate model. The projects are supervised by the Energy Ministry.
The projects form part of Saudi Arabia’s efforts to achieve an electricity generation mix comprising approximately 50% renewable energy by 2030.
As previously reported, the Group 2 programme comprises six ISP projects with a total capacity of 3GW, equivalent to 12,000MWh based on a four-hour storage duration.
Developers recently submitted a first round of clarification requests to SPPC as they prepare their bids in advance of an October deadline.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19052381/main.jpg -
Accor and Al-Qimmah plan 4,000 Saudi rooms27 August 2026
France’s hotel operator Accor has expanded its partnership with local firm Al-Qimmah Hospitality, a subsidiary of Saudi Arabia’s BinDawood Investment Company, to develop more than 4,000 hotel rooms in the kingdom.
The plan focuses on building a portfolio in Mecca and Medina.
The expanded agreement was announced in Paris during the French-Saudi Investment Roundtable. It follows a master development agreement signed in 2025. The partnership now covers five hotels in Jeddah, Mecca and Medina across the premium, midscale and economy segments.
One planned development is an 850-room Novotel in Mecca, due to open in 2030. The agreement also covers the Mercure Makkah Shesha, ibis Styles Makkah Mesfalah, Movenpick Madinah and Swissotel Jeddah properties.
The partnership will also support job creation and Saudi workforce development through Tamayyaz by Accor, the group’s national talent programme run with the Saudi Ministry of Tourism. The programme aims to develop and hire more than 3,000 Saudi nationals by 2030.
Accor has operated in Saudi Arabia for more than three decades and runs 48 hotels with more than 21,600 rooms nationwide. Its pipeline includes a further 47 properties comprising more than 11,400 rooms.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19051854/main.jpg -
Jeddah tenders stormwater drainage contracts27 August 2026
Jeddah Municipality has invited contractors to bid for a contract covering the construction of a rainwater drainage network for the Prince Fawaz neighbourhood.
The project aims to collect and convey rainwater away from residential streets and low-lying areas. It is valued at $60m and intended to reduce flooding risks during heavy rainfall.
The scope includes manholes, stormwater catch basins and connections to existing manholes as well as the restoration of road surfaces.
The bid submission deadline is 12 October.
The municipality is also progressing with a second stormwater drainage project for the first package of Zone (BC), Old Zahraa in Jeddah Governorate, with bids due on 2 September. The project is valued at about $30m.
The two projects are part of the municipality’s wider drainage programme, which includes the flagship King Abdullah Road-Falasteen Road tunnel project.
MEED previously reported that Saudi contractor Thrustboring Construction Company had been selected for phases one and two of the project, each valued at about $175m, covering the construction of large-diameter stormwater drainage tunnels.
It is understood that an official agreement has yet to be signed.
In June, MEED reported that local contractor Alkhorayef Water & Power Technologies (AWPT) had signed two contracts with Jeddah Municipality to operate and maintain stormwater and surface water drainage networks across the city.
The contracts have a combined value of SR202.06m ($53.9m), and each will run for five years.
The first contract, valued at SR108.46m ($28.9m), covers the operation and cleaning of stormwater and surface water networks in the South and Al-Malisa sub-municipalities.
The second contract, worth SR93.59m ($25m), covers similar services for the Airport Sub-Municipality.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19039514/main.jpg -
Saur and Nesma sign water infrastructure deal26 August 2026
French firm Saur and local contractor Nesma & Partners have signed a deal to jointly “pursue the design and construction” of two recycled water plants in Riyadh.
The memorandum of understanding (MoU) was signed during the French-Saudi Investment Roundtable Meeting in Paris on 24 August.
It builds on an earlier agreement by the companies last September focusing on developing desalination and sewage treatment plants across the kingdom, including project development, engineering, procurement and construction, and long-term operations and maintenance.
At the time, the companies agreed to “target industrial water treatment through concession and operations contracts”, extending the agreement beyond municipal water infrastructure.
The latest agreement appears to mark a move from the broader partnership towards specific project opportunities in the Riyadh market. Details of the projects were not disclosed.
In May, MEED exclusively reported that a consortium including Saur, Nesma and another local firm, Al-Bawani, was preparing to bid for the Riyadh East independent sewage treatment plant (ISTP) project, for which the submission deadline was recently extended to 29 September.
There are almost $2.5bn-worth of water treatment projects at the pre-execution stage in Saudi Arabia, according to regional tracker MEED Projects.
The French-Saudi Investment Roundtable Meeting was organised as part of Saudi Crown Prince and Prime Minister Mohammed Bin Salman’s state visit to France.
Saudi Aramco also announced agreements and an MoU with French companies worth a potential combined value of more than $3.7bn.
Among the other agreements signed during the conference was a cooperation agreement between Saudi Energy and French public investment bank Bpifrance, valued at up to $3bn, to support financing for projects to develop and expand Saudi Arabia’s power grid.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19011713/main.jpg