UAE power sector shapes up ahead of Cop28

3 April 2023

This package on the UAE's power sector also includes:

> Ewec rules out solar in desalination projects

> Dewa receives K station bid

> Dewa briefs 1.8GW solar bidders

> Italian firms pursue energy transition roles

> Majid al-Futtaim signs 36MW clean energy agreement

> Abu Dhabi eyes power and water contracts extension


There will be no shortage of milestones once November’s Cop28 turns the spotlight onto the UAE’s power generation sector.

Already, Abu Dhabi-based Emirates Water & Electricity Company (Ewec) has announced that, on 10 February at 2.26 pm, it met 80 per cent of total power demand using renewable and clean energy from its solar and nuclear power plants – supplying roughly 6.2GW of its total 7.7GW system power demand.

Before this, Bruce Smith, Ewec’s executive director for strategy and planning, told MEED that the company was working towards implementing control systems to enable clean and renewable energy to meet up to 100 per cent of power demand “under specific parameters or conditions”.

As things stand, Ewec is set to become the first offtaker in the region to build a utility-scale battery energy storage system (BESS), a key tool to address the intermittency of solar energy production. The company sought advisers for the development of its first two BESS facilities earlier this year.

The two projects will have a minimum capacity of 300MW plus one-hour of reserve-optimised BESS. The facilities are expected to come on-stream by 2026.

From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy

Higher peak demand not only requires additional thermal and solar generation capacity, but also batteries to enhance system reliability, Ewec noted in a presentation in March.

Based on its latest statement of future capacity requirements, Ewec foresees a 30 per cent peak demand increase from 16.7GW in 2022 to 21.6GW by 2029.

This year’s commissioning of a new power plant in Sharjah – the 1,800MW Hamriyah independent power producer (IPP) – is expected to reduce Ewec’s electricity exports. However, this will be offset by the addition of offshore demand starting in 2026 from Abu Dhabi National Oil Company (Adnoc).

In spite of rising demand warranting expansion in installed generation capacity – and with substantial contracted thermal capacity approaching expiry – Ewec forecasts halving its total carbon dioxide (CO2) emissions from 43 million tonnes a year (t/y) in 2019 to 22 million t/y by 2035.

Ewec needs to install 7.3GW of solar capacity by 2029 and 16GW by 2036, which implies procuring roughly 1GW to 1.5GW of new capacity annually during the period.

By the end of 2023, Ewec’s solar fleet will comprise the 935MW Noor Abu Dhabi project in Sweihan and the 1.5GW Al-Dhafra solar photovoltaic (PV) plant, which is nearing completion.

The procurement process is under way for the emirate’s third utility-scale solar PV IPP, also with a capacity of 1.5GW, in Al-Ajban.

Tendering for a fourth solar PV project, likely to be located in A-Ain, is also expected to begin in the third or fourth quarter of 2023.

This ambitious programme, including an aspiration to enable Ewec’s solar fleets to produce dispatchable loads similar to conventional power plants, makes the BESS projects of paramount importance.

Dubai green story

Dubai’s long-term capacity procurement plan is less clear, although state utility Dubai Electricity & Water Authority (Dewa)  has reported a 5.5 per cent increase in demand in the emirate in 2022, to reach 53,180 gigawatt-hours (GWh).

This is half of the 10 per cent growth in 2021, which marked the emirate’s resurgence from the Covid-19 pandemic. 

As of early 2023, over 2GW of clean energy from the Mohammed bin Rashid solar park accounted for 14 per cent of Dewa’s electricity production capacity, which stood at 14.5GW.

Based on the initial plan of 5GW of capacity once the solar park is complete, and with some 1GW still under construction, Dewa is expected to procure at least 2GW more.

The 1.8GW sixth phase of the solar park, which is currently being tendered, accounts for most of the outstanding capacity.

Unlike Abu Dhabi, which plans to expand its thermal generation capacity in light of the demand increase and expansion of intermittent renewable energy, Dubai has already ruled out gas as a feedstock for future greenfield generation capacity.

“We have a relatively new and modern fleet [of thermal power generation plants] that would be operational for another 20 to 30 years,” Saeed Mohammed al-Tayer, Dewa CEO and managing director, said in a forum in Dubai in 2020.

The Dubai Economic Agenda 2033 (D33), which aims to double the size of Dubai’s economy over the next decade and consolidate its position among the top three global cities, is expected to drive power and water demand within the emirate, without compromising its carbon abatement strategy and emissions reduction targets.

Diversification

The UAE already has the GCC’s most diversified electricity production installed capacity, with fleets deriving electricity from solar PV, thermal and nuclear power plants. The region’s first hydroelectric power plant in Hatta in Dubai will further expand the country’s power sources.

The completion of the 1.5GW Al-Dhafra solar IPP in Abu Dhabi and roughly 1GW from the fourth and fifth phases of the MBR solar park in Dubai will drive solar’s share from 8 per cent at the start of the year to 12 per cent by the end 2023. This will cause the overall share of thermal power generation to retreat by three percentage points to 79 per cent, in spite of the completion of the remaining units at Hassyan in Dubai, the Hamriyah IPP in Sharjah and the Fujairah F3 facility.

The three reactors at the Barakah nuclear power plant in Abu Dhabi also contribute an estimated 4.2GW of installed capacity, or roughly 9 per cent of Abu Dhabi, Dubai and Sharjah’s combined overall capacity, and 18 per cent in Abu Dhabi alone.

From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10723958/main.jpeg
Jennifer Aguinaldo
Related Articles
  • WEBINAR: End-of-Year Mena Market Review

    13 November 2026

    Webinar: The big questions shaping the Gulf market. You decide what gets debated.
    Tuesday 24 November 2026  | 11:00 AM GST  |  Register now


    What makes this session particularly interesting is that the audience gets to decide the agenda. Registrants can vote for the topics they’d like Ed and Colin to debate, with the most popular questions forming the final shortlist for the live session.

    Topics in the ballot:

    • Is the Gulf trying to build too much, too quickly?
    • Saudi Arabia or the UAE: where would you place your next big bet?
    • Are gigaprojects the best use of public money?
    • Who is really responsible when projects go wrong?
    • Should the lowest-price tender become a thing of the past?
    • Can private capital take over from the government in financing infrastructure and diversification?
    • Is the Gulf’s AI and data centre boom a smart bet or the next overbuilding risk?
    • Should the Gulf double down on hydrocarbons to fund diversification?
    • Is localisation strengthening the economy or making delivery harder?
    • Are Gulf countries building complementary economies or competing for the same customers?

    The session will also feature live audience polling and Q&A, giving attendees an opportunity to share their views.

    Hosted by: 

    Edward James, head of content and analysis at MEED

    A well-known and respected thought leader in Mena affairs, Edward James has been with MEED for more than 19 years, working as a researcher, consultant and content director. Today, he heads up all content and research produced by the MEED group. His specific areas of expertise are construction, hydrocarbons, power and water, and the petrochemicals market. He is considered one of the world’s foremost experts on the Mena projects market. He is a regular guest commentator on Middle East issues for news channels such as the BBC, CNN and ABC News and is a regular speaker at events in the region. 


    Colin Foreman, editor of MEED 

    Colin Foreman is editor and a specialist construction journalist for news and analysis on MEED.com and the MEED Business Review magazine. He has been reporting on the region since 2003, specialising in the construction sector and its impact on the broader economy. He has reported exclusively on a wide range of projects across the region including Dubai Metro, the Burj Khalifa, Jeddah Airport, Doha Metro, Hamad International airport and Yas Island. Before joining MEED, Colin reported on the construction sector in Hong Kong.

    Click here to register

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21380319/main.gif
    MEED Editorial
  • Syntys breaks ground on 20MW Qatar data centre

    13 November 2026

    Register for MEED’s 14-day trial access 

    Qatari data centre developer Syntys has broken ground on a 20MW facility to support hyperscale, cloud, artificial intelligence (AI) and advanced computing deployments.

    The groundbreaking ceremony took place on 12 November. It was attended by Qatar’s Communications & Information Technology Minister, Mohammed bin Ali bin Mohammed Al-Mannai, along with representatives from Ooredoo Group, Microsoft, Google, Kahramaa, the National Cyber Security Agency, Qatar Free Zones Authority and local banks.

    Syntys said the facility is being developed on an existing company campus, where power, fibre connectivity and an operational team are already in place. The company has yet to disclose the project value or planned completion date.

    The facility is designed to meet Tier 3 requirements and accommodate a range of rack densities, including higher-density configurations for graphics processing unit (GPU)-based AI and high-performance computing workloads.

    It will operate as a carrier-neutral facility, allowing customers to select connectivity providers and establish network resilience in line with their own technical and operational requirements.

    The project forms part of Syntys’ strategy to expand its Qatar platform through acquisitions and new development. Earlier this year, the company acquired QData QFZ, adding two operational, Tier 3-compliant, carrier-neutral facilities to its portfolio.

    Syntys now owns and operates four campuses in Qatar, allowing customers to establish primary and disaster-recovery environments at separate in-country locations.

    The company also designs and operates the facilities supporting Ooredoo’s sovereign AI cloud, which uses Nvidia Hopper GPUs.

    The development comes as Qatar implements its Digital Agenda 2030, which identifies digital infrastructure as one of six strategic pillars and targets about QR40bn ($11bn) in economic impact by 2030.

    The data centre is expected to support the growth of in-country digital services and enable sensitive workloads to remain within Qatar’s national borders.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21378257/main1028.png
    Yasir Iqbal
  • Riyadh airport tenders general consultancy services

    13 November 2026

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s King Salman International Airport Development Company has tendered a contract for general consultancy services for the King Salman International airport project in Riyadh.

    Tender documents were issued on 1 November and consultants have until 29 November to submit bids.

    Tender clarification queries closed on 11 November, following a mid-bid briefing meeting. Technical and commercial bids will be evaluated in December.

    The selected consultant will provide comprehensive engineering services, covering design, construction and completion stages, delivered through individual service orders issued by the client. 

    The scope of services includes:

    • Preparing requests for proposals for design and engineering-related packages;
    • Conducting technical feasibility studies;
    • Preparing design and related documentation for aviation and non-aviation assets, support facilities and commercial real estate across the airport masterplan;
    • Managing regulatory compliance and securing approvals from entities including the General Authority of Civil Aviation and Riyadh Airports Company;
    • Providing design peer review services to evaluate third-party designs for completeness, constructability, value engineering and code compliance.

    Under the procurement conditions, bidders must comply with local content rules established by the Local Content & Government Procurement Authority, including an audited baseline local content score, a target score and a Saudisation plan.

    Multinational firms operating in the region must also hold an active regional headquarters licence issued by Saudi Arabia’s Investment Ministry. Subcontracting will be restricted to a single tier.

    Planned to cover an area of 57 square kilometres (sq km), the project includes approximately 45 sq km of aeronautical land and an estimated 10 sq km terminal footprint featuring the Iconic Terminal, Terminal 6 and private aviation facilities.

    The airport is designed to handle 120 million passengers and 2 million tonnes of cargo a year by 2030, rising to 185 million passengers and 3.5 million tonnes of cargo by 2050, with an ultimate capacity of 225 million passengers. 

    The remaining 12 sq km of the site is allocated to Airport City, an urban development that will accommodate about 80,000 residents and will include residential, commercial, hospitality, retail, entertainment, logistics and industrial assets.

    The airport masterplan was launched in November 2022 by Crown Prince Mohammed bin Salman bin Abdulaziz Al-Saud. The project is backed by the Saudi sovereign wealth vehicle, the Public Investment Fund, as part of Saudi Arabia’s Vision 2030 economic transformation strategy.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21377681/main.jpg
    Yasir Iqbal
  • Jereh wins $392m Bu Hasa oil field facilities project

    13 November 2026

    Register for MEED’s 14-day trial access 

    The onshore oil and gas business of Abu Dhabi National Oil Company (Adnoc Onshore) has awarded China’s Jereh Group a contract valued at AED1.44bn ($392.1m) for the engineering, procurement and construction (EPC) of wellhead surface facilities and flowlines at the Bu Hasa cluster of oil fields in Abu Dhabi.

    The cluster includes the Bu Hasa, Bida Al-Qemzan and Huwaila fields. The objective of the project is to build wellhead surface facilities and lay gathering flowlines that will connect new wells to the existing production network.

    The scope of work on the project also covers the design, fabrication and installation of:

    • production well module skids
    • gas lift skids, which inject gas into wells to help lift the oil
    • skid-mounted wellhead control panels
    • solar power units

    The framework agreement awarded by Adnoc Onshore on a call-off basis has a duration of 36 months, with an extendable option of 24 months, Jereh said in a filing with China’s Shenzhen Stock Exchange, where it is listed.

    Adnoc Onshore is Adnoc Group’s largest production subsidiary, accounting for about 2 million barrels a day (b/d) of crude and about 7 billion cubic feet a day of associated gas from four primary onshore asset clusters: Bab, Bu Hasa, North East Bab and South East.

    Maintaining and enhancing oil output levels at the Bu Hasa asset is critical to Adnoc Onshore’s contribution to parent company Adnoc Group’s target of expanding crude oil production capacity to 5 million b/d by 2027, an initiative known as Accelerated Integrated Programme 5. The state energy company’s total production capacity currently stands at approximately 4.85 million b/d.

    Prior to this contract, Adnoc Onshore selected Jereh Oil & Gas Engineering Company in 2024 for a project to digitally connect 2,443 wells at the Bab, Bu Hasa and South East cluster of onshore oil fields in Abu Dhabi for remote operations. The contract, formally awarded in 2025, was valued at $920m.

    Abu Dhabi contracts

    The contract for the Bu Hasa wellhead facilities and flowlines is among a trio of projects totalling approximately $2.7bn that has been awarded by Adnoc Group in recent weeks, Jereh announced in its stock market filing.

    The largest of the three contracts, valued at $1.7bn, is for the Ruwais Diyab unconventional gas development in Abu Dhabi. Awarded to Jereh on a design, build and operate model, the contract has a duration of 29 months for construction works and 60 months of operations, with up to two five-year extensions available.

    Adnoc achieved final investment decision on the Ruwais Diyab unconventional gas development project on 2 November, during the Abu Dhabi International Petroleum Exhibition and Conference 2026.

    The project will deliver 345 million standard cubic feet a day (scf/d) of raw gas from 2029 over a 25-year period, with the potential to reach up to 1 billion scf/d in the future.

    The scope of work on the Ruwais Diyab project covers:

    • wellsite facilities
    • a central processing facility
    • gas gathering pipelines and product export pipelines
    • utilities

    The plant will treat the raw gas and recover the liquids produced with it. It will also treat produced water, which is the water that comes up from the wells with the gas, and recover sulphur. Finished products will be delivered to designated receiving facilities.

    When the operation period ends, Jereh will either hand the facilities over to Adnoc or decommission them and restore the site, as the contract and the owner require.

    The third contract covers Adnoc Onshore’s Bab and North East Bab 1 tie-in project, where the main scope of work involves tying in new oil producer wells and removing and modifying surface facilities at existing producer wells.

    The project’s scope also covers supporting works for water supply wells, water injection wells, disposal wells and water-alternating-gas injection wells. Several existing wells will also be upgraded with digital systems.

    Jereh said the value of its contract is $599m, with a duration of 60 months. Similar to the Bu Hasa project, this contract also uses a framework model wherein Adnoc Onshore will issue work orders in batches according to its execution plans.

    MEED previously reported that Adnoc Onshore had divided the scope of work on the Bab and North East Bab 1 tie-in project into 18 EPC packages. Along with Jereh, Adnoc Onshore has picked Abu Dhabi-based Robt Stone Middle East for a portion of work on the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21355151/main3320.jpg
    Indrajit Sen
  • PDO awards contract for Al-Ghubar oil field project

    12 November 2026

     

    Register for MEED’s 14-day trial access 

    Petroleum Development Oman (PDO) has awarded the main contract for a project to build a facility to handle additional oil production from the Al-Ghubar field in the sultanate.

    The Al-Ghubar field is located in the Ghaba Salt Basin at Qarn Alam, within majority state-owned PDO’s Block 6 concession area.

    The Al-Ghubar gas-oil gravity drainage (GOGD) facility will be designed as a sour (hydrogen sulphide) facility and is expected to handle a maximum oil production rate of 1,800 standard cubic metres a day (cm/d), a total water flow rate of up to 10,421 standard cm/d and gas lift of up to 256,934 standard cm/d. Production from the planned Al-Ghubar GOGD facility will be exported to PDO’s main oil line.

    China-based Jereh Group has won the contract for the Al-Ghubar GOGD facility project, sources told MEED.

    A project kick-off meeting between PDO and Jereh has also recently taken place, the sources said.

    MEED previously reported that Jereh had emerged as the lowest bidder for the project.

    The following contractors, among others, are understood to have been bidding for the Al-Ghubar GOGD facility project:

    • Engineering for the Petroleum & Process Industries (Egypt) / Petrojet (Egypt)
    • GS Engineering & Construction (South Korea)
    • Jereh (China)
    • Larsen & Toubro Energy Hydrocarbon (India)

    PDO floated the tender for the Al-Ghubar GOGD facility project in March, setting an initial bid submission deadline of 4 May, MEED previously reported.

    PDO later extended the deadlines for the submission of technical and commercial bids to 26 July and 7 August, respectively. Contractors submitted technical proposals by the revised deadline, according to sources.

    After receiving the technical bids for the project in July, PDO granted contractors until 16 August to submit commercial bids. It eventually extended the deadline to 1 September, with contractors submitting commercial proposals by that date, as MEED reported.

    The scope of work on the Al-Ghubar GOGD project covers the engineering, procurement and construction (EPC) of the following:

    • On-plot scope, consisting of:
      • Production separator  
      • Test separator  
      • Concentric wash tank
      • Wet oil pump
      • Water bath heater
      • Surge tank
      • Gas injection/gas lift compressor (centrifugal)
      • Utilities (instrument air compressors, chemical injection skids, drain system, vent system) 
      • Suction scrubber
      • Air coolers
      • Discharge scrubbers
      • Condensate flash drum
      • Atmospheric pressure knock-out drum 
      • Flare system
      • Gas heater
      • Water disposal pump
      • Oil shipping pump
      • 132kV substation and plant substation (housing 6.6kV and 415-Volt switchboard)
      • Control room
         
    • Off-plot scope consisting of:
      • Off-plot pipeline network (bulk header, test header, gathering infrastructure/ gathering line header, instrument air header, water disposal header)
      • Two remote manifold stations 
      • Tie-in connection to main oil line
      • Tie-in to gas network pipeline

    PDO previously intended to tender the Al-Ghubar GOGD project under its framework structure with selected EPC contractors, but ultimately tendered it separately.

    PDO is the operator of Oman’s Block 6 hydrocarbons concession, the sultanate’s largest and most prolific concession. Situated onshore and covering an area of 75,119 square kilometres, Block 6 contains 202 oil fields and 43 gas fields. PDO produces approximately 680,000 barrels a day of oil and condensates from the fields.

    The Omani government holds a 60% stake in PDO through Energy Development Oman. The other shareholders are UK-based Shell (34%), France’s TotalEnergies (4%) and Thailand’s state-owned PTTEP (2%).

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21345337/main2647.jpg
    Indrajit Sen