UAE power sector shapes up ahead of Cop28
3 April 2023
This package on the UAE's power sector also includes:
> Ewec rules out solar in desalination projects
> Dewa receives K station bid
> Dewa briefs 1.8GW solar bidders
> Italian firms pursue energy transition roles
> Majid al-Futtaim signs 36MW clean energy agreement
> Abu Dhabi eyes power and water contracts extension
There will be no shortage of milestones once November’s Cop28 turns the spotlight onto the UAE’s power generation sector.
Already, Abu Dhabi-based Emirates Water & Electricity Company (Ewec) has announced that, on 10 February at 2.26 pm, it met 80 per cent of total power demand using renewable and clean energy from its solar and nuclear power plants – supplying roughly 6.2GW of its total 7.7GW system power demand.
Before this, Bruce Smith, Ewec’s executive director for strategy and planning, told MEED that the company was working towards implementing control systems to enable clean and renewable energy to meet up to 100 per cent of power demand “under specific parameters or conditions”.
As things stand, Ewec is set to become the first offtaker in the region to build a utility-scale battery energy storage system (BESS), a key tool to address the intermittency of solar energy production. The company sought advisers for the development of its first two BESS facilities earlier this year.
The two projects will have a minimum capacity of 300MW plus one-hour of reserve-optimised BESS. The facilities are expected to come on-stream by 2026.
From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy
Higher peak demand not only requires additional thermal and solar generation capacity, but also batteries to enhance system reliability, Ewec noted in a presentation in March.
Based on its latest statement of future capacity requirements, Ewec foresees a 30 per cent peak demand increase from 16.7GW in 2022 to 21.6GW by 2029.
This year’s commissioning of a new power plant in Sharjah – the 1,800MW Hamriyah independent power producer (IPP) – is expected to reduce Ewec’s electricity exports. However, this will be offset by the addition of offshore demand starting in 2026 from Abu Dhabi National Oil Company (Adnoc).
In spite of rising demand warranting expansion in installed generation capacity – and with substantial contracted thermal capacity approaching expiry – Ewec forecasts halving its total carbon dioxide (CO2) emissions from 43 million tonnes a year (t/y) in 2019 to 22 million t/y by 2035.
Ewec needs to install 7.3GW of solar capacity by 2029 and 16GW by 2036, which implies procuring roughly 1GW to 1.5GW of new capacity annually during the period.
By the end of 2023, Ewec’s solar fleet will comprise the 935MW Noor Abu Dhabi project in Sweihan and the 1.5GW Al-Dhafra solar photovoltaic (PV) plant, which is nearing completion.
The procurement process is under way for the emirate’s third utility-scale solar PV IPP, also with a capacity of 1.5GW, in Al-Ajban.
Tendering for a fourth solar PV project, likely to be located in A-Ain, is also expected to begin in the third or fourth quarter of 2023.
This ambitious programme, including an aspiration to enable Ewec’s solar fleets to produce dispatchable loads similar to conventional power plants, makes the BESS projects of paramount importance.
Dubai green story
Dubai’s long-term capacity procurement plan is less clear, although state utility Dubai Electricity & Water Authority (Dewa) has reported a 5.5 per cent increase in demand in the emirate in 2022, to reach 53,180 gigawatt-hours (GWh).
This is half of the 10 per cent growth in 2021, which marked the emirate’s resurgence from the Covid-19 pandemic.
As of early 2023, over 2GW of clean energy from the Mohammed bin Rashid solar park accounted for 14 per cent of Dewa’s electricity production capacity, which stood at 14.5GW.
Based on the initial plan of 5GW of capacity once the solar park is complete, and with some 1GW still under construction, Dewa is expected to procure at least 2GW more.
The 1.8GW sixth phase of the solar park, which is currently being tendered, accounts for most of the outstanding capacity.
Unlike Abu Dhabi, which plans to expand its thermal generation capacity in light of the demand increase and expansion of intermittent renewable energy, Dubai has already ruled out gas as a feedstock for future greenfield generation capacity.
“We have a relatively new and modern fleet [of thermal power generation plants] that would be operational for another 20 to 30 years,” Saeed Mohammed al-Tayer, Dewa CEO and managing director, said in a forum in Dubai in 2020.
The Dubai Economic Agenda 2033 (D33), which aims to double the size of Dubai’s economy over the next decade and consolidate its position among the top three global cities, is expected to drive power and water demand within the emirate, without compromising its carbon abatement strategy and emissions reduction targets.
Diversification
The UAE already has the GCC’s most diversified electricity production installed capacity, with fleets deriving electricity from solar PV, thermal and nuclear power plants. The region’s first hydroelectric power plant in Hatta in Dubai will further expand the country’s power sources.
The completion of the 1.5GW Al-Dhafra solar IPP in Abu Dhabi and roughly 1GW from the fourth and fifth phases of the MBR solar park in Dubai will drive solar’s share from 8 per cent at the start of the year to 12 per cent by the end 2023. This will cause the overall share of thermal power generation to retreat by three percentage points to 79 per cent, in spite of the completion of the remaining units at Hassyan in Dubai, the Hamriyah IPP in Sharjah and the Fujairah F3 facility.
The three reactors at the Barakah nuclear power plant in Abu Dhabi also contribute an estimated 4.2GW of installed capacity, or roughly 9 per cent of Abu Dhabi, Dubai and Sharjah’s combined overall capacity, and 18 per cent in Abu Dhabi alone.
From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy.

Exclusive from Meed
-
UAE firm acquires majority stake in African power producer31 August 2026
-
Contract award nears for Saudi Landbridge Riyadh section31 August 2026
-
Prequalification begins for Dammam suburb boulevard PPP31 August 2026
-
Contractors submit bids for Kuwait power transmission works31 August 2026
-
Eni plans to drill 230 oil and gas wells in Egypt31 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
UAE firm acquires majority stake in African power producer31 August 2026
Abu Dhabi-based ePointZero has announced a deal to acquire a 90% stake in pan-African independent power producer Azura Power Holdings.
The transaction will give the subsidiary of UAE investment group 2PointZero control of 752MW of operating power generation capacity across Nigeria, Senegal and Mozambique.
The company will acquire the respective stakes held by existing shareholders Actis and Africa50 through an acquisition vehicle established with Amaya Capital, an Africa-focused investment firm based in London.
Amaya Capital founded Azuro Power in 2010 and will retain a 10% minority stake in the company, which also has a development pipeline of more than 1.5GW of planned power projects.
The pipeline includes expansions at existing sites, as well as new gas and renewable energy projects and battery energy storage systems.
Azuro Power’s operating portfolio comprises the 461MW Azura-Edo power plant in Nigeria, the 116MW Tobene power plant in Senegal and the 175MW Central Termica de Ressano Garcia plant in Mozambique. The company’s operating assets generate around 10% of each country’s grid baseload power, the statement said.
The company’s projects have received financing and support from development finance institutions including the World Bank, British International Investment, German Investment & Development Company, the US International Development Finance Corporation, the Dutch entrepreneurial development bank, the International Finance Corporation, the Multilateral Investment Guarantee Agency and France’s Proparco.
The deal, subject to regulatory approvals and other customary closing conditions, marks ePointZero’s entry into African power generation and follows the acquisition of a 20% stake in Egypt’s Elsewedy Electric in 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19171095/main.jpg -
Contract award nears for Saudi Landbridge Riyadh section31 August 2026

Saudi Arabia Railways (SAR) is preparing to award the main construction contract for the design-and-build of the Riyadh Rail Link, a new north-to-south railway line across the capital.
MEED understands that the commercial proposals were opened two weeks ago, with a decision expected imminently.
SAR began the post-tender clarifications with bidders in July, as MEED reported.
The bidders include:
- China Civil Engineering Construction Corporation / Al-Ayuni Investment & Contracting (China/local)
- Nesma & Partners / China Harbour Engineering Company (local/China)
- Al-Rashid Trading & Contracting / IC Ictas Construction / Saipem (local/Turkiye/Spain)
- Saudi Binladin Group (local)
In June, MEED exclusively reported that contractors submitted their commercial proposals on the 30th of that month.
The scope includes a 35-kilometre double-track line connecting SAR’s North-South Railway to the Eastern Railway network.
Issued on 29 January, the tender also covers the procurement, construction and installation of associated infrastructure, including viaducts, civil works, utility diversions/installations, signalling systems and other related works.
Once delivered, the Riyadh Rail Link is expected to become a key component of the Saudi Landbridge railway.
In January, SAR said it would deliver the Saudi Landbridge project through a “new mechanism” by 2034, after failing to reach an agreement with a Chinese consortium to construct it, as MEED reported.
In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said the consortium failed to meet local content requirements, and that the project would instead be delivered in several phases under a different procurement model.
Negotiations have been under way between Saudi Arabia and China-backed investors interested in developing the scheme through a public-private partnership (PPP). Al-Malik put the project cost at about SR100bn ($26.6bn).
Overall, it comprises more than 1,500km of new track. A core element is a 900km railway between Riyadh and Jeddah, providing the capital with direct freight access to King Abdullah Port on the Red Sea.
Other key elements include upgrading the existing Riyadh-Dammam line, a bypass around the capital known as the Riyadh Link, and a connection between King Abdullah Port and Yanbu.
The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. First announced in 2004, it was put on hold in 2010 before being revived a year later. Rights-of-way issues, route alignment and the high cost have been among the main stumbling blocks.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19161887/main.gif -
Prequalification begins for Dammam suburb boulevard PPP31 August 2026
Saudi Arabia’s Ministry of Municipalities & Housing, in collaboration with Ashraq Development Company and the National Centre for Privatisation & PPP, has issued a request for qualification (RFQ) notice for the development of the King Fahd suburb boulevard project in Dammam.
The notice was issued on 27 August, with a submission deadline of 22 October.
The public-private partnership (PPP) project will be delivered using a design, build, finance, operate, maintain and transfer model, with a 43-year contract term.
The project is located in Al-Bayda Governorate and features a 4 kilometre (km) mixed-use zone along a central boulevard, forming part of a larger 7.3km corridor.
The project will be developed in two phases and span about 1 million square metres.
According to a statement: “The private sector partner will be responsible for developing and operating the boulevard, which includes leisure and recreational facilities, public parks, entertainment venues, retail outlets, office spaces, hospitality zones, pedestrian walkways and road networks.”
The project is the latest addition to the growing number of PPP projects in the kingdom.
In January, Saudi Arabia launched a national privatisation strategy aimed at mobilising $64bn in private sector capital by 2030.
Building on the privatisation programme first introduced in 2018, the strategy focuses on unlocking state-owned assets for private investment and privatising selected government services.
In a statement, NCP said the strategy comprises 147 opportunities drawn from a broader pipeline of more than 500 projects across 18 sectors.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19160560/main.jpg -
Contractors submit bids for Kuwait power transmission works31 August 2026

Kuwait’s Public Authority for Housing Welfare (PAHW) has received bids for two tenders covering power transmission works at the South Saad Al-Abdullah residential development.
The first tender covers the supply, installation and maintenance of 10 main 132/11kV transformer substations for the third phase of the development.
According to sources, five contractors submitted bids on 26 August. The local Sayed Hamid Behbehani & Sons made the lowest offer of $104.2m.
The bids include:
- Sayed Hamid Behbehani & Sons: $104.2m (Kuwait)
- Industrial Electrical Projects (IEP): $111.5m (Kuwait)
- Larsen & Toubro: $114m (India)
- Oman National Engineering & Investment: $118m (Oman)
- National Contracting Company: $126m (Saudi Arabia)
The second PAHW tender covers the supply, installation and maintenance of 10 main 132/11kV transformer substations for the fourth phase of the project.
According to sources, five contractors also submitted bids on 26 August, with A-Ahleia Switchgear making the lowest offer of $103.3m.
The bids include:
- Al-Ahleia Switchgear: $103.3m (Kuwait)
- Industrial Electrical Projects (IEP): $111.7m (Kuwait)
- Larsen & Toubro: $114m (India)
- Oman National Engineering & Investment: $118.3m (Oman)
- National Contracting Company: $126m (Saudi Arabia)
Both projects were initially tendered in May. As reported by MEED, PAHW previously issued addendums for both substation tenders, revising the qualification requirements for bidders.
According to the revised requirements, contractors must be approved by Kuwait’s Ministry of Electricity, Water & Renewable Energy and have experience supplying and installing at least 10 132kV substations in Kuwait.
The addendums also introduced requirements related to transformer and gas-insulated switchgear manufacturing approvals, as well as operational performance records for installed equipment.
Sabah Al-Ahmad residential city
Meanwhile, bids remain under evaluation for two 132kV underground cable tenders for the South Sabah Al-Ahmad residential development, tendered by PAHW in May.
The first cable tender covers the supply, extension and maintenance of 132kV underground cables feeding eight main transformer substations serving the N1, N6 and N11 districts in the project’s fourth phase.
MEED previously reported that Egytech Cables, a subsidiary of Egypt’s Elsewedy Electric, was the lowest bidder with an offer of $42.37m.
The second cable tender covers the supply, extension and maintenance of 132kV underground cables linked to substations serving the N5, N6, N8 and N10 districts in the project’s third phase.
Egytech Cables submitted the lowest offer of $39.95m. TBEA Shandong Luneng Taishan Cable submitted a bid of $41.89m, along with Riyadh Cables ($42.05m) and The Contractor General Trading & Contracting ($44.97m).
https://image.digitalinsightresearch.in/uploads/NewsArticle/19151780/main.jpg -
Eni plans to drill 230 oil and gas wells in Egypt31 August 2026
Italy’s Eni is planning to drill 230 new oil and gas wells in Egypt, according to a statement from the country’s Ministry of Petroleum & Mineral Resources.
Eni’s chief executive, Claudio Descalzi, discussed his plans for exploration and development in Egypt on 25 August during a meeting with Egypt’s Prime Minister Mostafa Madbouly and the Minister of Petroleum and Mineral Resources Karim Badawi.
During the meeting, Descalzi said that the company has plans to drill 30 exploration wells in addition to 200 development wells.
Descalzi said his company plans to intensify its exploration and development programmes, especially in the Mediterranean and Western Sahara regions, to increase production of natural gas and crude oil.
He said that his company plans to use the latest seismic imaging and artificial intelligence technologies as a key part of its exploration and development plans.
In a separate statement, Eni also said that it is working with UK-headquartered BP and state-owned Egyptian General Petroleum Corporation (EGPC) to reach a final investment decision (FID) for a project to develop the major gas discovery of Denise West in Egypt’s Temsah concession.
Eni made the discovery in February and says it holds about 2 trillion cubic feet of gas and 130,000 barrels of condensate.
It is targeting first gas in less than two years and expects to reach FID “in the next few months”, according to its statement.
Eni’s total investments in Egypt have reached a value of $8.5bn, according to the statement from Egypt’s Ministry of Petroleum & Mineral Resources.
During the meeting on 25 August, Descalzi also stressed the importance of linking Cyprus’ Cronos gas field to Egyptian export infrastructure.
In July, Eni reached the FID to develop the Cronos project in deep waters offshore Cyprus, targeting the first Cypriot gas to market in 2028.
Production is expected to reach a plateau of 500 million standard cubic feet a day.
In October last year, Egypt and Cyprus signed provisional agreements to connect Cyprus’ Cronos gas field to Egypt’s gas infrastructure.
The agreements were signed by parties including Egypt’s Ministry of Petroleum and Mineral Resources, Eni, and the French oil and gas company TotalEnergies.
Connecting the Cronos field to Egypt is expected to involve the tendering of a major subsea pipeline project.
This will allow gas to be transported and processed in existing Zohr facilities in Egypt, then transferred and liquefied at the Damietta LNG plant for export as LNG to international markets, primarily Europe.
At the meeting on 25 August, Descalzi said the planned project to connect the Cronos field to Egypt will be considered a model for regional cooperation in the gas sector and will enhance Egypt’s status as a regional gas hub.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19079059/main.jpg