UAE power sector shapes up ahead of Cop28
3 April 2023
This package on the UAE's power sector also includes:
> Ewec rules out solar in desalination projects
> Dewa receives K station bid
> Dewa briefs 1.8GW solar bidders
> Italian firms pursue energy transition roles
> Majid al-Futtaim signs 36MW clean energy agreement
> Abu Dhabi eyes power and water contracts extension
There will be no shortage of milestones once November’s Cop28 turns the spotlight onto the UAE’s power generation sector.
Already, Abu Dhabi-based Emirates Water & Electricity Company (Ewec) has announced that, on 10 February at 2.26 pm, it met 80 per cent of total power demand using renewable and clean energy from its solar and nuclear power plants – supplying roughly 6.2GW of its total 7.7GW system power demand.
Before this, Bruce Smith, Ewec’s executive director for strategy and planning, told MEED that the company was working towards implementing control systems to enable clean and renewable energy to meet up to 100 per cent of power demand “under specific parameters or conditions”.
As things stand, Ewec is set to become the first offtaker in the region to build a utility-scale battery energy storage system (BESS), a key tool to address the intermittency of solar energy production. The company sought advisers for the development of its first two BESS facilities earlier this year.
The two projects will have a minimum capacity of 300MW plus one-hour of reserve-optimised BESS. The facilities are expected to come on-stream by 2026.
From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy
Higher peak demand not only requires additional thermal and solar generation capacity, but also batteries to enhance system reliability, Ewec noted in a presentation in March.
Based on its latest statement of future capacity requirements, Ewec foresees a 30 per cent peak demand increase from 16.7GW in 2022 to 21.6GW by 2029.
This year’s commissioning of a new power plant in Sharjah – the 1,800MW Hamriyah independent power producer (IPP) – is expected to reduce Ewec’s electricity exports. However, this will be offset by the addition of offshore demand starting in 2026 from Abu Dhabi National Oil Company (Adnoc).
In spite of rising demand warranting expansion in installed generation capacity – and with substantial contracted thermal capacity approaching expiry – Ewec forecasts halving its total carbon dioxide (CO2) emissions from 43 million tonnes a year (t/y) in 2019 to 22 million t/y by 2035.
Ewec needs to install 7.3GW of solar capacity by 2029 and 16GW by 2036, which implies procuring roughly 1GW to 1.5GW of new capacity annually during the period.
By the end of 2023, Ewec’s solar fleet will comprise the 935MW Noor Abu Dhabi project in Sweihan and the 1.5GW Al-Dhafra solar photovoltaic (PV) plant, which is nearing completion.
The procurement process is under way for the emirate’s third utility-scale solar PV IPP, also with a capacity of 1.5GW, in Al-Ajban.
Tendering for a fourth solar PV project, likely to be located in A-Ain, is also expected to begin in the third or fourth quarter of 2023.
This ambitious programme, including an aspiration to enable Ewec’s solar fleets to produce dispatchable loads similar to conventional power plants, makes the BESS projects of paramount importance.
Dubai green story
Dubai’s long-term capacity procurement plan is less clear, although state utility Dubai Electricity & Water Authority (Dewa) has reported a 5.5 per cent increase in demand in the emirate in 2022, to reach 53,180 gigawatt-hours (GWh).
This is half of the 10 per cent growth in 2021, which marked the emirate’s resurgence from the Covid-19 pandemic.
As of early 2023, over 2GW of clean energy from the Mohammed bin Rashid solar park accounted for 14 per cent of Dewa’s electricity production capacity, which stood at 14.5GW.
Based on the initial plan of 5GW of capacity once the solar park is complete, and with some 1GW still under construction, Dewa is expected to procure at least 2GW more.
The 1.8GW sixth phase of the solar park, which is currently being tendered, accounts for most of the outstanding capacity.
Unlike Abu Dhabi, which plans to expand its thermal generation capacity in light of the demand increase and expansion of intermittent renewable energy, Dubai has already ruled out gas as a feedstock for future greenfield generation capacity.
“We have a relatively new and modern fleet [of thermal power generation plants] that would be operational for another 20 to 30 years,” Saeed Mohammed al-Tayer, Dewa CEO and managing director, said in a forum in Dubai in 2020.
The Dubai Economic Agenda 2033 (D33), which aims to double the size of Dubai’s economy over the next decade and consolidate its position among the top three global cities, is expected to drive power and water demand within the emirate, without compromising its carbon abatement strategy and emissions reduction targets.
Diversification
The UAE already has the GCC’s most diversified electricity production installed capacity, with fleets deriving electricity from solar PV, thermal and nuclear power plants. The region’s first hydroelectric power plant in Hatta in Dubai will further expand the country’s power sources.
The completion of the 1.5GW Al-Dhafra solar IPP in Abu Dhabi and roughly 1GW from the fourth and fifth phases of the MBR solar park in Dubai will drive solar’s share from 8 per cent at the start of the year to 12 per cent by the end 2023. This will cause the overall share of thermal power generation to retreat by three percentage points to 79 per cent, in spite of the completion of the remaining units at Hassyan in Dubai, the Hamriyah IPP in Sharjah and the Fujairah F3 facility.
The three reactors at the Barakah nuclear power plant in Abu Dhabi also contribute an estimated 4.2GW of installed capacity, or roughly 9 per cent of Abu Dhabi, Dubai and Sharjah’s combined overall capacity, and 18 per cent in Abu Dhabi alone.
From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy.

Exclusive from Meed
-
KBR re-evaluates design for Libya oil project10 July 2026
-
Qiddiya to tender high-speed rail in September10 July 2026
-
-
Contractor appointed for Dubai’s One B Tower9 July 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
KBR re-evaluates design for Libya oil project10 July 2026

US-headquartered KBR is responsible for re-evaluating the front-end engineering and design (feed) for the project to develop the J6 North Gialo field in Libya, according to industry sources.
In June, MEED reported that Libya’s Waha Oil Company (WOC), a subsidiary of the state-owned National Oil Corporation (NOC), had launched a review into the tender process for the J6 North Gialo oil field development project, and that this would include re-evaluating the feed work.
The Waha concessions are held by a consortium of Libya’s NOC, which holds 59.16%; TotalEnergies, holding 20.42%; and US-based ConocoPhillips, with 20.42%.
They are operated by WOC, which is 100% owned by NOC.
KBR has previously provided engineering services for major national projects in Libya, such as the Great Man-Made River project, which is widely recognised as the largest irrigation project in the world.
In March, KBR was awarded a contract by Zallaf Exploration, Production & Refining of Oil & Gas Company to provide project management and technical services for the South Refinery project in Libya’s southern city of Ubari.
Under the terms of the contract, KBR will provide contract management, project management and supporting technical services throughout the engineering, procurement and construction (EPC) phases of the project.
The EPC work is expected to be executed over a 50-month period.
In its statement, KBR said that the project is aligned with its “long-standing commitment to advancing vital oil and gas infrastructure in Libya”.
In March, MEED reported that South Korea’s Daewoo had pulled out of the tender process for Libya’s J6 North Gialo oil field development project.
Daewoo had formed a partnership with Egypt’s Petrojet to participate in the tender process.
The only other company to submit a bid for the project was UK-based Petrofac, which filed for administration in October last year.
In January, TotalEnergies signed an agreement extending the Waha concessions agreement up to 31 December 2050.
This agreement set new fiscal terms, allowing an increase in the production of these concessions that were, at the time, producing about 370,000 barrels of oil equivalent a day (boe/d).
In January, TotalEnergies said that the deal paved the way for “a new phase of investments, including the development of the North Gialo field, which is expected to add 100,000 boe/d of production”.
The J6 North Gialo project is the first of three field development projects that WOC has prioritised.
The other two are known as NC98 and Gialo 3.
Together, the three projects are expected to double Waha’s production from about 300,000 barrels a day (b/d) of oil to 600,000 b/d.
The Waha concession covers 13 million acres.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17621475/main.jpg -
Qiddiya to tender high-speed rail in September10 July 2026

Saudi Arabia’s Royal Commission for Riyadh City, in collaboration with Qiddiya Investment Company and the National Centre for Privatisation & PPP, are expected to float the tender in September for the Qiddiya high-speed rail project in Riyadh.
MEED understands that the clarification process is ongoing for the engineering, procurement, construction and financing (EPCF), as well as the public-private partnership (PPP) packages.
The Qiddiya high-speed rail project, also known as Q-Express, will cover 84 kilometres, connecting King Salman International airport and King Abdullah Financial District with Qiddiya City.
In April, MEED exclusively reported that the clients had received prequalification statements from firms for the EPCF package of the project.
MEED also reported in May that firms were forming joint ventures for the PPP package of the project.
The line will operate at speeds of up to 250 kilometres an hour, reaching Qiddiya in 30 minutes.
There are five stations planned: Qiddiya Grand Central Station, Qiddiya Uptown Station, King Abdullah Financial District, Terminal 6 King Salman International airport (KSIA) and Iconic Terminal at KSIA.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17621301/main.jpg -
Middle East construction cost inflation to hit 5.1% by 20279 July 2026
Construction cost inflation in the Middle East is forecast to reach 5.1% in 2027, the second-highest of any region worldwide, as global demand for data centres tightens contractor capacity and deepens shortages of skilled labour.
The projection comes from the Global Construction Market Intelligence report, published by UK programme manager Turner & Townsend. The report draws on data from 112 markets across 44 countries, gathered between 2 March and 20 March 2026.
Only Africa is expected to see steeper cost escalation, at 7%. Australia and New Zealand follow the Middle East at 4.9%, while the EU records the lowest figure at 2.8%. Globally, construction cost inflation is set to rise from 4.2% in 2025 to 4.5% in 2026 before flattening in 2027.
The report identifies a two-speed market. Data centres are now the most in-demand construction sector globally, followed by industrial and logistics. More than 70% of the 112 markets surveyed report tightening or overstretched contractor capacity in the data centre sector. By contrast, more than 79% of markets show balanced or spare capacity across hospitality and leisure, residential and commercial development.
Skills shortage
Labour availability has displaced material costs as the primary driver of cost escalation. About 71% of markets report labour shortages. Skills deficits are most acute in mechanical, electrical and plumbing (MEP) trades, with 87% of markets reporting MEP shortages. These trades are central to data centre delivery.
The findings carry weight for the GCC, where sovereign programmes in Saudi Arabia and the UAE are competing for the same contractor pools that artificial intelligence (AI) infrastructure now draws on. Regional governments have announced large data centre commitments alongside gigaprojects, housing and transport schemes, placing further strain on an already stretched supply chain.
Turner & Townsend says that construction input costs have stabilised over the past year, with supply chain resilience built since the pandemic limiting the impact of recent volatility. Cost drivers are becoming more localised and sector-specific rather than the product of international shocks.
Energy market exposure introduces a separate risk. The report cites oil prices, higher transport and freight costs, and volatility in petrochemicals inputs as significant challenges. Disruption to shipping routes lengthens lead times and adds supply chain volatility.
Conflict assumptions
The baseline scenario assumes a relatively short-lived conflict in the Middle East and a moderate rise in energy commodity prices in 2026. A prolonged or escalating conflict would produce more pronounced effects on inflation, supply chains and construction costs.
New York remains the world's most expensive construction market at $7,938 a square metre, followed by San Francisco at $7,883 and Geneva at $6,985. London ranks fifth at $6,032.
North America carries the highest regional labour costs, with an average hourly wage of $79.5, ahead of the EU at $75.6 and Australia and New Zealand at $68.
Digital adoption remains uneven, though momentum is building. Sixty-six percent of markets report that AI capability now carries more weight in tendering and client discussions than it did 12 months ago.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17606750/main.gif -
Contractor appointed for Dubai’s One B Tower9 July 2026

Dubai-based construction firm Naresco Contracting has been awarded a contract to build One B Tower, located on Dubai's Sheikh Zayed Road.
Local real estate developer Wasl Group awarded the contract.
It covers a 47-storey high-rise tower offering a mix of one- to four-bedroom residential units.
The project is also known as One Billion Meals Endowment Tower.
The enabling works were undertaken by local firm APCC Building Contracting.
Netherlands-headquartered UN Studio is the project architect.
Dubai-based firm Studio International Engineering Consultants is the project consultant.
The project is slated for completion by 2028.
This is the second major contract to have been awarded by Wasl Group this year for a residential development.
In January, the firm awarded an estimated $250m deal to build the Avenue Park Towers project in Dubai to South Korean contractor Ssangyong Engineering & Construction.
The development comprises two mixed-use buildings offering residential and commercial facilities. One of the towers will have 43 floors while the other will have 37.
The project is slated for completion by 2028.
Wasl Group's latest contract award in the UAE market is backed by heightened real estate activity in the construction sector, with schemes worth over $323bn in the execution or planning stages, according to UK analytics firm GlobalData.
The company forecasts that output from the UAE’s residential construction sector will grow by 3% in real terms in 2026-29, supported by infrastructure, energy and utilities developments, as well as residential construction projects.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17605135/main.jpg -
Iran and US break peace deal and resume Gulf attacks9 July 2026
Iran and the US have once again traded attacks in the Gulf region, in the worst exchange of fire since the two nations signed an interim peace deal in June.
US Central Command (CentCom) said on 7 July that it had launched strikes in response to attacks on three oil tankers in the Strait of Hormuz, hitting more than 80 targets including air defence systems, coastal radar and fast boats.
In retaliatory attacks on 8 July, Iran said it had targeted US military sites in Bahrain and Kuwait.
Oil prices have spiked following the strikes, with global benchmark Brent crude trading at $77.32 a barrel as of 1pm Gulf Standard Time.
UK Maritime Trade Operations (UKMTO) said a tanker travelling through the strait had reported a fire after an unknown projectile hit an engine room on 6 July.
In two separate incidents on 7 July, a tanker reported it had been hit as it exited the strait but was able to proceed to its next port of call, while another tanker reported sustaining minor structural damage after being struck, UKMTO said.
Qatar and Saudi Arabia have denounced the attacks, each saying a tanker from its country had been hit while transiting in or near the strait, and blaming Iran.
A spokesperson for Qatar's foreign ministry, Majed Al-Ansari, said it held Iran fully responsible for an apparently targeted attack on a vessel called Al-Rekayyat as it transited near the Strait of Hormuz.
Saudi Arabia's foreign ministry said Iran had targeted the Saudi tanker Wedyan as it crossed the strait. The owner of the very large crude carrier, the kingdom’s national shipping company Bahri, confirmed the attack on the vessel in a statement on 7 July, adding that “all crew members are safe and accounted for, and the cargo remains secure”.
“The vessel remains in a seaworthy condition. The company promptly informed all relevant authorities and continues to work closely with them and other maritime stakeholders, while maintaining continuous communication with the vessel's crew and closely monitoring the situation,” Bahri said.
“Bahri continues to closely monitor developments in the region and has implemented appropriate precautionary measures to support the safety of its people, vessels and operations,” it added.
Breakdown of peace deal
Separately, the US also said it had revoked its temporary suspension of sanctions on Iranian oil sales. Iran's speaker Mohammad Bagher Ghalibaf accused the US of breaching their memorandum of understanding (MoU) on this issue, and others, including the attacks in southern Iran and "violating Iranian adjustments in the strait".
Missiles and drones were launched at "85 key US military facilities", including a US Navy headquarters and an air base in Kuwait, the Islamic Revolutionary Guard Corps (IRGC) said.
Iranian state media agency Irna also reported the death of an IRGC guard in the US strikes, “after being struck by shrapnel from a projectile".
Kuwait has responded to the Iranian strikes on its country, lambasting the "repeated attacks".
Talks on reaching a permanent peace deal have been on hold due to the state funeral in Iran for the late Supreme Leader Ayatollah Ali Khamenei, who was killed on 28 February – the first day of US-Israeli strikes on Iran.
Early on 7 July, Iran's deputy foreign minister described the US attacks as a violation of the US-Iran MoU signed on 14 June, and warned Tehran would "take decisive measures".
The US had said there would be consequences for what it called the "wholly unacceptable" attacks on the three tankers.
CentCom said that in addition to 60 small boats, it had struck Iranian missile launch sites and command centres. It did not give the locations of its targets.
It said the strikes were "to impose heavy costs for targeting and attacking commercial shipping crewed by innocent individuals in an international waterway".
Before the strikes, the US Treasury revoked a waiver that had temporarily lifted oil sanctions on Iran and was part of the MoU signed by Washington and Tehran in June.
Iran's foreign ministry called the move a breach of the MoU and said it proved the "bad faith, inconsistency and unreliability" of the US government.
It added that Tehran "will take whatever measures it considers necessary to safeguard its national interests and national security".
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17605530/main5658.jpg