UAE power sector shapes up ahead of Cop28

3 April 2023

This package on the UAE's power sector also includes:

> Ewec rules out solar in desalination projects

> Dewa receives K station bid

> Dewa briefs 1.8GW solar bidders

> Italian firms pursue energy transition roles

> Majid al-Futtaim signs 36MW clean energy agreement

> Abu Dhabi eyes power and water contracts extension


There will be no shortage of milestones once November’s Cop28 turns the spotlight onto the UAE’s power generation sector.

Already, Abu Dhabi-based Emirates Water & Electricity Company (Ewec) has announced that, on 10 February at 2.26 pm, it met 80 per cent of total power demand using renewable and clean energy from its solar and nuclear power plants – supplying roughly 6.2GW of its total 7.7GW system power demand.

Before this, Bruce Smith, Ewec’s executive director for strategy and planning, told MEED that the company was working towards implementing control systems to enable clean and renewable energy to meet up to 100 per cent of power demand “under specific parameters or conditions”.

As things stand, Ewec is set to become the first offtaker in the region to build a utility-scale battery energy storage system (BESS), a key tool to address the intermittency of solar energy production. The company sought advisers for the development of its first two BESS facilities earlier this year.

The two projects will have a minimum capacity of 300MW plus one-hour of reserve-optimised BESS. The facilities are expected to come on-stream by 2026.

From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy

Higher peak demand not only requires additional thermal and solar generation capacity, but also batteries to enhance system reliability, Ewec noted in a presentation in March.

Based on its latest statement of future capacity requirements, Ewec foresees a 30 per cent peak demand increase from 16.7GW in 2022 to 21.6GW by 2029.

This year’s commissioning of a new power plant in Sharjah – the 1,800MW Hamriyah independent power producer (IPP) – is expected to reduce Ewec’s electricity exports. However, this will be offset by the addition of offshore demand starting in 2026 from Abu Dhabi National Oil Company (Adnoc).

In spite of rising demand warranting expansion in installed generation capacity – and with substantial contracted thermal capacity approaching expiry – Ewec forecasts halving its total carbon dioxide (CO2) emissions from 43 million tonnes a year (t/y) in 2019 to 22 million t/y by 2035.

Ewec needs to install 7.3GW of solar capacity by 2029 and 16GW by 2036, which implies procuring roughly 1GW to 1.5GW of new capacity annually during the period.

By the end of 2023, Ewec’s solar fleet will comprise the 935MW Noor Abu Dhabi project in Sweihan and the 1.5GW Al-Dhafra solar photovoltaic (PV) plant, which is nearing completion.

The procurement process is under way for the emirate’s third utility-scale solar PV IPP, also with a capacity of 1.5GW, in Al-Ajban.

Tendering for a fourth solar PV project, likely to be located in A-Ain, is also expected to begin in the third or fourth quarter of 2023.

This ambitious programme, including an aspiration to enable Ewec’s solar fleets to produce dispatchable loads similar to conventional power plants, makes the BESS projects of paramount importance.

Dubai green story

Dubai’s long-term capacity procurement plan is less clear, although state utility Dubai Electricity & Water Authority (Dewa)  has reported a 5.5 per cent increase in demand in the emirate in 2022, to reach 53,180 gigawatt-hours (GWh).

This is half of the 10 per cent growth in 2021, which marked the emirate’s resurgence from the Covid-19 pandemic. 

As of early 2023, over 2GW of clean energy from the Mohammed bin Rashid solar park accounted for 14 per cent of Dewa’s electricity production capacity, which stood at 14.5GW.

Based on the initial plan of 5GW of capacity once the solar park is complete, and with some 1GW still under construction, Dewa is expected to procure at least 2GW more.

The 1.8GW sixth phase of the solar park, which is currently being tendered, accounts for most of the outstanding capacity.

Unlike Abu Dhabi, which plans to expand its thermal generation capacity in light of the demand increase and expansion of intermittent renewable energy, Dubai has already ruled out gas as a feedstock for future greenfield generation capacity.

“We have a relatively new and modern fleet [of thermal power generation plants] that would be operational for another 20 to 30 years,” Saeed Mohammed al-Tayer, Dewa CEO and managing director, said in a forum in Dubai in 2020.

The Dubai Economic Agenda 2033 (D33), which aims to double the size of Dubai’s economy over the next decade and consolidate its position among the top three global cities, is expected to drive power and water demand within the emirate, without compromising its carbon abatement strategy and emissions reduction targets.

Diversification

The UAE already has the GCC’s most diversified electricity production installed capacity, with fleets deriving electricity from solar PV, thermal and nuclear power plants. The region’s first hydroelectric power plant in Hatta in Dubai will further expand the country’s power sources.

The completion of the 1.5GW Al-Dhafra solar IPP in Abu Dhabi and roughly 1GW from the fourth and fifth phases of the MBR solar park in Dubai will drive solar’s share from 8 per cent at the start of the year to 12 per cent by the end 2023. This will cause the overall share of thermal power generation to retreat by three percentage points to 79 per cent, in spite of the completion of the remaining units at Hassyan in Dubai, the Hamriyah IPP in Sharjah and the Fujairah F3 facility.

The three reactors at the Barakah nuclear power plant in Abu Dhabi also contribute an estimated 4.2GW of installed capacity, or roughly 9 per cent of Abu Dhabi, Dubai and Sharjah’s combined overall capacity, and 18 per cent in Abu Dhabi alone.

From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10723958/main.jpeg
Jennifer Aguinaldo
Related Articles
  • Diriyah cancels construction contract for One Hotel

    20 November 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Diriyah Company has cancelled the main construction works contract for the One Hotel project in the Diriyah Two area of its masterplan.

    The contract was awarded to a joint venture of India’s Ashoka Buildcon for Contracting and BEC Arabia Contracting Company, as MEED reported in February.

    In a filing to the Bombay Stock Exchange, Ashoka Buildcon said: “Diriyah Company has now notified the joint venture that the said project has been cancelled due to internal reasons attributable to the employer.”

    Ashoka Buildcon holds a 49% stake in the joint venture.

    The project comprises a four-storey hospitality building with approximately 325 guest rooms, on a 31,000-square-metre plot. French engineering firm Egis was the project consultant.

    The development follows several recent tender cancellations, particularly in Saudi Arabia’s water sector. Earlier this month, MEED exclusively reported that Water Transmission Company (WTCO) had cancelled tenders for Package B and the combined Packages C1 and C3 of its New Water Pipeline to Feed Riyadh City 2 scheme.

    The packages, with a combined estimated value of about $556m, cover a long-distance potable-water transmission system intended to reinforce supplies to Riyadh. Bidders were notified of the decision in November.

    Before that, Saudi Water Authority (SWA) also cancelled the tender for a 300-million-litres-a-day seawater reverse osmosis desalination plant in Yanbu.

    India’s VA Tech Wabag announced in July 2025 that it had received the estimated $272m main contract for the project. However, on November 14, it said SWA had subsequently cancelled the tender through the Etimad government procurement platform, citing internal reasons.


    MEED’s October 2026 report on Saudi Arabia includes:

    > COMMENT: Saudi projects hold steady
    > GOVERNMENT: Riyadh looks to reset its regional defence outlook
    > ECONOMY: Conflict bolsters case for Saudi economic diversification

    > BANKING: Saudi lenders readjust to lower lending and deposit climate
    > UPSTREAM: Aramco upstream spending gathers pace
    > DOWNSTREAM: Sabic steps up Saudi petchems investment

    > POWER: Saudi Arabia’s power award activity slows
    > WATER: Saudi water sector hits sharp slowdown
    > CONSTRUCTION: Saudi construction defies the headwinds
    > TRANSPORT: Saudi infrastructure pushes forward amid conflict
    > DATABANK: Saudi data indicates project spending shift

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21612890/main.png
    Yasir Iqbal
  • Bahrain keeps moving through a difficult year

    20 November 2026

    Commentary
    Colin Foreman
    Editor

    When Formula 1 cars took to the grid at Malaysia’s Sepang International Circuit on 4 October, they were racing in the Bahrain Grand Prix. The race, originally scheduled for April, was postponed because of the regional conflict. Rather than lose its place on the calendar, Bahrain backed a one-off arrangement to stage it in Southeast Asia as the Formula 1 Gulf Air Bahrain Grand Prix in Malaysia.

    The episode captures Manama’s approach to 2026. With the Strait of Hormuz closed and the country’s airspace shut for 40 days, Bahrain has sought alternative routes to keep its economy moving.

    Gulf Air relocated its hub to Saudi Arabia’s Dammam airport during the airspace closure, taking passengers by road across the King Fahd Causeway, and expects to report higher revenues this year than in 2025. Aluminium Bahrain (Alba) is running at about 80% of capacity, with 300-350 trucks a day delivering alumina using ports in Oman and Saudi Arabia. The company has also agreed the $2.2bn acquisition of the Aluminium Dunkerque smelter in France.

    Project activity has continued. Gulf Petrochemical Industries Company has appointed Fluor and Honeywell for its planned Sitra aromatics complex. Bids for the $1.5bn Sitra independent water and power project are under evaluation. 

    Construction contract awards reached $737m by the end of October, already exceeding the total for 2025.

    In early November, Manama went ahead with the fourth edition of the Gateway Gulf investment forum, which produced more than 110 announcements valued at over $20bn.

    The cost of the regional conflict is nonetheless steep. The Washington-based IMF expects the economy to contract by 11.3% this year. Public debt reached BD20.3bn ($54bn) at the end of August, and foreign exchange reserves have been supported by a BD2bn ($5.3bn) currency swap line from the UAE.

    Lasting recovery will depend on factors that lie largely beyond Bahrain’s control. The IMF is forecasting real GDP growth of 13.9% in 2027, but this is contingent on the reopening of Gulf trade routes and a return to normal levels of energy production.

     


    MEED’s December 2026 report on Bahrain includes:

    > GOVERNMENT: Bahrain creaks under the strain of war
    > BANKING: Manama’s lenders hold out for better times
    > OIL & GAS: GPIC’s expansion project lifts Bahrain’s energy sector
    > POWER & WATER: Bahrain’s utility pipeline shows signs of progress
    > CONSTRUCTION: Bahrain construction activity remains subdued

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21389640/main.gif
    Colin Foreman
  • Gulf needs $40bn of pipelines to bypass Hormuz

    20 November 2026

    Register for MEED’s 14-day trial access 

    Gulf producers would need to spend about $40bn on new pipelines to route most of their oil exports around the Strait of Hormuz, according to the International Energy Agency (IEA).

    The estimate, published in the agency's World Energy Outlook 2026, covers 6.8 million barrels a day (b/d) of export capacity that is either under construction or proposed in Saudi Arabia, the UAE and Iraq. The IEA calculates that the investment would add about $2 to the cost of each barrel exported from the Middle East.

    The figure gives the clearest indication yet of the scale of the pipeline programme that could follow the 2026 crisis, which the IEA describes as the largest energy supply shock the world has faced. Oil volumes transiting the strait collapsed from 20 million b/d to an average of about 3 million b/d in March, April and May.

    Project pipeline

    The only scheme under construction in the IEA’s list is Abu Dhabi National Oil Company’s (Adnoc) West-East pipeline, which will add 1.8 million b/d of capacity. MEED has reported that the 520-kilometre line from Jebel Dhanna to Fujairah is being built in three sections. It is expected to double Adnoc’s crude export capacity through Fujairah when it is commissioned in 2027.

    Separately, Adnoc expects to tender the main engineering, procurement and construction (EPC) contract for a new offshore line linking its Gulf processing islands to Jebel Dhanna, which will eventually connect to the West-East pipeline, by the end of the year.

    The largest proposed project is a 3 million b/d expansion of Saudi Aramco’s East-West pipeline from Abqaiq to Yanbu on the Red Sea. Aramco president and CEO Amin Nasser has said engineering work began in the early days of the conflict. Saudi Energy Minister Prince Abdulaziz bin Salman said in October that the kingdom is looking to expand its crude export capacity by pipeline to as much as 10 million b/d.

    In Iraq, the IEA counts two 1 million b/d lines from Haditha. One would run to Baniyas in Syria. The other would run to Fishkhabur, where it would link to the Iraq-Turkiye pipeline to Ceyhan. MEED has reported that a consortium led by Qatar’s UCC, including Chevron and TotalEnergies, is discussing terms for four interconnected pipeline packages worth about $5bn, with a contract expected to be signed before year-end. Iraq and Saudi Arabia are also considering reviving the 1,568km pipeline from Zubair to Yanbu, which was halted in 1990.

    The agency says the new routes would not help all Gulf producers. Bahrain, Kuwait and Qatar would still depend on the strait for their exports.

    Bypass flows

    About 8 million b/d of bypass pipeline capacity is already available, according to the report. These lines carried about 2 million b/d in 2025 and ramped up to a peak of 6.8 million b/d during the crisis.

    In the IEA’s Stated Policies Scenario (STEPS), only the Adnoc project is completed and bypass flows return to about 3 million b/d by 2035. If every existing, under-construction and proposed route were built and used to capacity, bypass flows could reach about 14.5 million b/d. Most Saudi and UAE exports, along with more than 60% of Iraq’s, would then avoid the strait.

    The IEA’s new Low Hormuz Case adds higher output from producers outside the Gulf and demand cuts by importers. In that case, oil transit through the strait falls below 2 million b/d by 2035. Raising supply outside the strait would require about $200bn of additional upstream investment between 2025 and 2035.

    Security caveats

    The agency cautions that the pipelines would not remove the risk. Drone attacks temporarily shut the East-West pipeline in September, and any exports to the Red Sea must pass through the Bab Al-Mandab Strait. MEED has reported that Houthi attacks on Aramco’s Red Sea assets since July, including the Jizan refinery, have cost Riyadh that alternative route. Even in the Low Hormuz Case, the Middle East still exports nearly 15 million b/d in 2035, about 20% of global oil trade.

    The IEA also notes that if the strait is at least partially open, Gulf producers would have few reasons not to use it. That could weaken the commercial case for the most expensive bypass schemes.

    Execution risks are emerging in Iraq. MEED has reported that the Common Seawater Supply Project is behind schedule, largely because pipeline segments cannot easily be imported through the strait. The same problem could force contractors on new export lines to use more costly routes.

    The IEA says there is no feasible bypass for liquefied natural gas (LNG). About 110 billion cubic metres of gas passed through the strait in 2025, most of it from Qatar. Adnoc is pursuing a 4 million tonne-a-year LNG export facility at Fujairah, fed by pipeline from Abu Dhabi. MEED has reported that it has selected three teams for front-end engineering and design work.

    Cost pressures

    The wider upstream picture is less encouraging for contractors. The IEA expects global upstream oil and gas investment to rise by about 1% to $550bn in 2026, with increases elsewhere largely offset by reductions in the Middle East. Its Upstream Capital Cost Index is forecast to rise by about 8% this year, which the agency says will raise the risk of overruns and delays.

    The agency also warns that a resolution of the crisis could create a buyers’ market for oil and gas. Lower prices would test whether the security case for bypass pipelines survives once the strait reopens.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21612651/main.jpg
    Colin Foreman
  • Riyadh gives bidders more time for aviation complex

    20 November 2026

     

    Contractors have been given an extension until 31 January to submit proposals for an estimated SR3bn ($817m) contract to build an aviation complex within the King Salman International airport master development in Riyadh.

    Government-owned aviation organisation Saudi Royal Aviation (SRA) tendered the contract in August, with an initial bid submission deadline of 8 October, which was later extended to 19 November.

    Phase one of the programme comprised the concept design stage, which the design consultant has completed.

    SRA is now seeking to deliver the second phase, covering design development, detailed design, procurement, construction, testing, commissioning and close-out of the works.

    The scope covers 30 landside buildings, including 16 screening areas and gates, plus 15 airside buildings, including four gates.

    The assets include maintenance hangars, workshops, office and administrative buildings (including interior fit-out), warehouses, storage, security and catering facilities, aprons and access roads, and site utilities and civil works.

    King Salman International airport will provide primary utilities to designated tie-in points, with the contractor taking responsibility from there.

    Although the site is within King Salman International airport’s boundaries, it is classified as landside and is a greenfield development. The contractor must therefore meet airport security, safety and access requirements, in addition to SRA’s own clearance processes.

    Project scale

    The King Salman International airport project covers an area of about 57 square kilometres (sq km), allowing for six parallel runways, and will include the existing terminals at King Khalid International airport. It will also include 12 sq km of airport support facilities, residential and recreational facilities, retail outlets and other logistics real estate.

    The airport aims to accommodate up to 100 million passengers by 2030. The goal for cargo is to process 2 million tonnes a year by 2030.

    Saudi Arabia plans to invest significantly in its aviation sector. The Saudi Aviation Strategy, announced by the General Authority of Civil Aviation, aims to triple Saudi Arabia’s annual passenger traffic to 330 million travellers by 2030.

    It also aims to increase air cargo traffic to 4.5 million tonnes and raise the country’s total air connections to more than 250 destinations.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21611358/main.png
    Yasir Iqbal
  • Dar Global launches Trump project in Qatar

    20 November 2026

    London-listed developer Dar Global and The Trump Organisation have launched the QR2.5bn ($686m) Trump International Simaisma development in Qatar.

    The project combines beachfront residences, a golf course and lifestyle amenities, according to senior company officials speaking at a launch ceremony in Palm Beach, Florida.

    The residential element, Trump Residences, will comprise a gated community of three-, four- and five-bedroom branded villas. Each villa will have beach access and views of the sea and golf course.

    The development will also include the Trump International Golf Club, Simaisma, Qatar, anchored by an 18-hole championship golf course, a members-only clubhouse and a beach club.

    A private community centre will provide sports, recreation and wellness facilities for residents.

    The project forms part of Qatar’s wider Simaisma tourism development, launched by Qatar’s Ministry of Municipality in June 2024.

    The Simaisma project covers eight square kilometres and extends along seven kilometres of beachfront on Qatar’s eastern coast, north of Doha. It includes 16 tourism zones available for private sector development, with planned resorts, a theme park, an 18-hole golf course, residential villas, a yacht marina, restaurants and retail facilities.

    Qatari Diar Real Estate Investment Company is managing the wider development.

    The integrated tourism project supports the objectives of Qatar’s Third National Development Strategy 2024-30, which aims to increase the contribution of non-oil sectors to the economy.

    The launch extends the partnership between Dar Global and The Trump Organisation into Qatar.

    Dar Global develops luxury residential and hospitality projects across Europe and the Middle East.

    As of 30 June 2026, Dar Global’s portfolio had a total gross development value of $23bn, the company said.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21609076/main.jpeg
    Yasir Iqbal