UAE power sector shapes up ahead of Cop28

3 April 2023

This package on the UAE's power sector also includes:

Ewec rules out solar in desalination projects

Dewa receives K station bid

Dewa briefs 1.8GW solar bidders

Italian firms pursue energy transition roles

Majid al-Futtaim signs 36MW clean energy agreement

Abu Dhabi eyes power and water contracts extension


There will be no shortage of milestones once November’s Cop28 turns the spotlight onto the UAE’s power generation sector.

Already, Abu Dhabi-based Emirates Water & Electricity Company (Ewec) has announced that, on 10 February at 2.26 pm, it met 80 per cent of total power demand using renewable and clean energy from its solar and nuclear power plants – supplying roughly 6.2GW of its total 7.7GW system power demand.

Before this, Bruce Smith, Ewec’s executive director for strategy and planning, told MEED that the company was working towards implementing control systems to enable clean and renewable energy to meet up to 100 per cent of power demand “under specific parameters or conditions”.

As things stand, Ewec is set to become the first offtaker in the region to build a utility-scale battery energy storage system (BESS), a key tool to address the intermittency of solar energy production. The company sought advisers for the development of its first two BESS facilities earlier this year.

The two projects will have a minimum capacity of 300MW plus one-hour of reserve-optimised BESS. The facilities are expected to come on-stream by 2026.

From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy

Higher peak demand not only requires additional thermal and solar generation capacity, but also batteries to enhance system reliability, Ewec noted in a presentation in March.

Based on its latest statement of future capacity requirements, Ewec foresees a 30 per cent peak demand increase from 16.7GW in 2022 to 21.6GW by 2029.

This year’s commissioning of a new power plant in Sharjah – the 1,800MW Hamriyah independent power producer (IPP) – is expected to reduce Ewec’s electricity exports. However, this will be offset by the addition of offshore demand starting in 2026 from Abu Dhabi National Oil Company (Adnoc).

In spite of rising demand warranting expansion in installed generation capacity – and with substantial contracted thermal capacity approaching expiry – Ewec forecasts halving its total carbon dioxide (CO2) emissions from 43 million tonnes a year (t/y) in 2019 to 22 million t/y by 2035.

Ewec needs to install 7.3GW of solar capacity by 2029 and 16GW by 2036, which implies procuring roughly 1GW to 1.5GW of new capacity annually during the period.

By the end of 2023, Ewec’s solar fleet will comprise the 935MW Noor Abu Dhabi project in Sweihan and the 1.5GW Al-Dhafra solar photovoltaic (PV) plant, which is nearing completion.

The procurement process is under way for the emirate’s third utility-scale solar PV IPP, also with a capacity of 1.5GW, in Al-Ajban.

Tendering for a fourth solar PV project, likely to be located in A-Ain, is also expected to begin in the third or fourth quarter of 2023.

This ambitious programme, including an aspiration to enable Ewec’s solar fleets to produce dispatchable loads similar to conventional power plants, makes the BESS projects of paramount importance.

Dubai green story

Dubai’s long-term capacity procurement plan is less clear, although state utility Dubai Electricity & Water Authority (Dewa)  has reported a 5.5 per cent increase in demand in the emirate in 2022, to reach 53,180 gigawatt-hours (GWh).

This is half of the 10 per cent growth in 2021, which marked the emirate’s resurgence from the Covid-19 pandemic. 

As of early 2023, over 2GW of clean energy from the Mohammed bin Rashid solar park accounted for 14 per cent of Dewa’s electricity production capacity, which stood at 14.5GW.

Based on the initial plan of 5GW of capacity once the solar park is complete, and with some 1GW still under construction, Dewa is expected to procure at least 2GW more.

The 1.8GW sixth phase of the solar park, which is currently being tendered, accounts for most of the outstanding capacity.

Unlike Abu Dhabi, which plans to expand its thermal generation capacity in light of the demand increase and expansion of intermittent renewable energy, Dubai has already ruled out gas as a feedstock for future greenfield generation capacity.

“We have a relatively new and modern fleet [of thermal power generation plants] that would be operational for another 20 to 30 years,” Saeed Mohammed al-Tayer, Dewa CEO and managing director, said in a forum in Dubai in 2020.

The Dubai Economic Agenda 2033 (D33), which aims to double the size of Dubai’s economy over the next decade and consolidate its position among the top three global cities, is expected to drive power and water demand within the emirate, without compromising its carbon abatement strategy and emissions reduction targets.

Diversification

The UAE already has the GCC’s most diversified electricity production installed capacity, with fleets deriving electricity from solar PV, thermal and nuclear power plants. The region’s first hydroelectric power plant in Hatta in Dubai will further expand the country’s power sources.

The completion of the 1.5GW Al-Dhafra solar IPP in Abu Dhabi and roughly 1GW from the fourth and fifth phases of the MBR solar park in Dubai will drive solar’s share from 8 per cent at the start of the year to 12 per cent by the end 2023. This will cause the overall share of thermal power generation to retreat by three percentage points to 79 per cent, in spite of the completion of the remaining units at Hassyan in Dubai, the Hamriyah IPP in Sharjah and the Fujairah F3 facility.

The three reactors at the Barakah nuclear power plant in Abu Dhabi also contribute an estimated 4.2GW of installed capacity, or roughly 9 per cent of Abu Dhabi, Dubai and Sharjah’s combined overall capacity, and 18 per cent in Abu Dhabi alone.

From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10723958/main.jpeg
Jennifer Aguinaldo
Related Articles
  • Libya and Tunisia reschedule joint oil and gas licensing round

    19 August 2026

    The Libyan-Tunisian Joint Oil Exploration, Exploitation and Petroleum Services Company (Joint Oil) has rescheduled its planned licensing round for offshore exploration and development projects in a zone spanning the waters of both countries.

    The bidding process is now due to open on 7 September 2026, with bid submissions due by 8 January 2027.

    Previously, in May, Joint Oil said it planned to open the bid round on 1 August 2026.

    The upcoming round will offer two oil and gas packages. The first is an exploration package across the 3,000-square-kilometre Joint Oil Block, in water depths of 80-120 metres.

    Significant data are available on the geology of this area, including 6,500km of 2D and 1,900 square kilometres of 3D seismic data. Data also exists from a run of legacy wells dating to 1976.

    The second package covers development of the Zarat discovery specifically. This is a gas-condensate reservoir straddling the boundary between Tunisia’s national acreage and the jointly-held Joint Oil Block.

    Joint Oil is equally owned by Tunisia’s national oil company, ETAP, and OLA Energy Holdings, a subsidiary of the Libya Africa Investment Portfolio (LAIP).

    LAIP is a subsidiary of Libya’s sovereign wealth institution, the Libya Investment Authority.

    Joint Oil was established under a bilateral agreement between Libya and Tunisia in 1988 to explore and develop hydrocarbons in offshore areas shared by the two countries.

    The key dates from the new schedule for the licensing round are:

    • 7 September 2026: Bid round opens; qualified offshore operators can apply for access to the Virtual Data Room
    • 9 September 2026: Joint Oil presents the opportunity at the MMEA Scout Group meeting in London
    • 29-30 September 2026: Joint Oil presents at the World Energy Summit in London
    • 31 December 2026: Bid round closes
    • 8 January 2027: Bid submissions due
    • 26 February 2027: Winning bidders notified
    • 30 April 2027: Formal awards expected

    Texas-based Moyes & Co is acting as a strategic adviser on the licensing round.

    Houston-headquartered Marathon discovered the Zarat field in 1992. It is estimated to hold around 0.4 trillion cubic feet of recoverable gas and 50 million barrels of liquids.

    A previous development project concept centred on a mobile production unit, worth around $1bn, tied back to the nearby Miskar platform.

    Despite this, the field has remained undeveloped for over three decades.

    One of the key challenges to developing the reserve is its high carbon dioxide content.

    Joint Oil has run bid rounds for the acreage before without success, including as recently as late 2023.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18861047/main.jpg
    Wil Crisp
  • UAE cuts trade and financial links with Iran

    19 August 2026

    Register for MEED’s 14-day trial access 

    The UAE has halted all trade, commercial exchanges and financial transactions with Iran until further notice, the Ministry of Foreign Affairs said on 19 August.

    The suspension has been imposed in light of escalations that undermine regional and international peace and security, the ministry said. It did not specify a timeframe for any resumption.

    The ministry rejected allegations regarding the status of the economic relationship between the UAE and Iran, and restated the UAE's commitment to dialogue, cooperation and regional integration as means of advancing peace, stability and prosperity in the region.

    It said the UAE remains committed to safeguarding the integrity of the financial system, in line with international law and global standards.

    The suspension covers the full range of commercial and financial links between the two countries. The UAE has historically been one of Iran's most significant trading partners, with much of the relationship built on re-export trade routed through Dubai to Iranian ports across the Gulf.

    The ministry statement did not detail the mechanism for enforcing the halt, the sectors affected, or arrangements for existing contracts and in-transit cargo.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18857953/main0856.jpg
    Colin Foreman
  • Abu Dhabi begins Dar Al-Funoon Saadiyat construction

    19 August 2026

     

    Register for MEED’s 14-day trial access 

    Abu Dhabi-based piling contractor APCC Piling & Marine Contracting has started the enabling works on Dar Al-Funoon, a cultural development near the Saadiyat Cultural District.

    The project, commissioned by the Department of Culture & Tourism – Abu Dhabi, was designed by the late Canadian-American architect Frank Gehry.

    The venue is scheduled to open in 2030.

    MEED understands that the main contract bids are under evaluation and the project is slated for award soon.

    The complex will feature a multipurpose hall with more than 2,000 seats, a 3,500-seat open-air amphitheatre, a 400-seat studio theatre and a 250-seat jazz venue, bringing total capacity to more than 6,000 across its performance spaces.

    The venue will host leading international productions, delivering high-quality cultural experiences for audiences locally, regionally and globally.

    Upon completion, it will become one of the region’s largest performing arts venues.

    The project was announced by Sheikh Khaled Bin Mohamed Bin Zayed Al-Nahyan, Crown Prince of Abu Dhabi and Chairman of the Abu Dhabi Executive Council in June, as MEED reported.

    During a review of the plans, he was briefed on the architectural concept and the development and construction phases, as well as the venue’s advanced technical capabilities, which are being designed to meet the highest international standards for staging major global productions.

    The announcement is part of the ongoing development of Saadiyat Island, which already includes Louvre Abu Dhabi, Zayed National Museum, Natural History Museum Abu Dhabi, teamLab Phenomena Abu Dhabi and the upcoming Guggenheim Abu Dhabi.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18852155/main4145.jpg
    Yasir Iqbal
  • Contractor wins Dubai Canal drainage deal

    19 August 2026

     

    Register for MEED’s 14-day trial access 

    Local firm Detech Contracting has won an engineering, procurement and construction (EPC) contract to upgrade and rehabilitate the East Dubai Canal stormwater system.

    The project, known as TF-16-C1, is part of Dubai’s Tasreef strategic plan to improve the emirate’s stormwater network, increase flood protection and enhance the resilience of Dubai’s infrastructure.
     
    According to a source, Lebanon's Khatib & Alami has also been appointed as a consultant on the project.

    The works will focus on upgrading existing stormwater infrastructure to increase capacity and improve reliability during heavy rainfall.

    The scope includes upgrading the stormwater drainage system, laying pipelines and constructing manholes and gullies. It also includes the construction of pumping stations and diversion works, site clearance and other associated facilities.

    In February, MEED reported that the municipality had invited consultants to qualify for a contract to supervise three stormwater drainage projects (TF-16-C1, TF-15-C2 and TF-13-C1)

    China State Construction Engineering Corporation announced in July that it had won the EPC contract for the TF-15-C2 stormwater drainage network project located on Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.

    MEED understands contractor bids are still being evaluated for the TF-13-C1 project, which focuses on developing a drainage system for the Al-Marmum area.

    Detech has been awarded several packages under the Tasreef programme in the past 18 months.

    These include:

    • TF-16-C1: upgrading and rehabilitation of East Dubai Canal stormwater system
    • TF-15-C1: stormwater drainage system at Al-Wasl Road for communities west of Dubai Canal
    • TF-05-C1: stormwater drainage system in Jebel Ali 
    • TF-04: stormwater drainage system on Sheikh Mohammed Bin Zayed Road and Al-Yalayis Road
    • DS-419: Tasreef rainwater drainage network: West Deira stormwater system upgrade and rehabilitation 

    As MEED exclusively reported, the municipality recently issued a letter of award for the TF-15-C1 project, covering the construction of a stormwater drainage system on Al-Wasl Road and communities west of Dubai Canal.

    The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.

    This week, Dubai Municipality also issued three tenders for stormwater and sewerage infrastructure projects serving Hind City, Dubailand and surrounding areas.

    The projects cover drainage networks for Hind 4, connections to the stormwater network in Dubailand and a stormwater trunk line serving Hind 3, Hind 4 and Umm Al-Daman.

    All three have bid submission deadlines of 10 September.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18850438/main.jpg
    Mark Dowdall
  • Maaden and Aramco sign deal to create joint venture

    18 August 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabian Mining Company (Maaden) and Saudi Aramco have signed a shareholders’ agreement to form a joint venture (JV). Maaden will hold a 51% stake in the JV, while Aramco will own the remaining 49%.

    Before signing the shareholders’ agreement, the two Saudi state-owned companies signed a non-binding heads of agreement in January 2025 aimed at establishing the JV.

    “Combining the strengths of two leaders in their respective fields, the JV will focus on copper and other minerals critical to the energy transition,” the two parties said in a joint statement.

    The JV will focus on exploration across Zone 4, also known as the Transition Zone, within the Arabian Platform in Saudi Arabia. Spanning approximately 182,000 square kilometres – nearly 10% of the kingdom’s total land area – the expected exploration area stretches along a 100-kilometre-wide corridor running parallel to the Arabian Shield.

    “It represents a major new opportunity for mineral discovery in the kingdom,” Maaden and Aramco said.

    Copper, which is increasingly significant for electric vehicles, power networks, energy storage and renewable energy systems, will be a main focus of the JV.

    Copper accounts for more than 20% of the $1.2tn mined-metals market. The copper market is currently valued at about $250bn and is projected to grow to more than $400bn by 2035.

    The JV will also explore for other energy transition minerals, including zinc, lead and rare earth elements, “that are expected to be crucial to industries of the future”.

    “Leveraging advanced computational algorithms, [artificial intelligence] AI, and high-performance computing, the JV intends to target areas most likely to contain copper and valuable minerals, accelerating the path from regional screening to target definition and discovery. This is expected to support long-term sector development, reinforce the kingdom’s role in the global minerals value chain, and help meet rising demand for transition minerals,” the partners said.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18833329/main.jpg
    Indrajit Sen