UAE power sector shapes up ahead of Cop28
3 April 2023
This package on the UAE's power sector also includes:
> Ewec rules out solar in desalination projects
> Dewa receives K station bid
> Dewa briefs 1.8GW solar bidders
> Italian firms pursue energy transition roles
> Majid al-Futtaim signs 36MW clean energy agreement
> Abu Dhabi eyes power and water contracts extension
There will be no shortage of milestones once November’s Cop28 turns the spotlight onto the UAE’s power generation sector.
Already, Abu Dhabi-based Emirates Water & Electricity Company (Ewec) has announced that, on 10 February at 2.26 pm, it met 80 per cent of total power demand using renewable and clean energy from its solar and nuclear power plants – supplying roughly 6.2GW of its total 7.7GW system power demand.
Before this, Bruce Smith, Ewec’s executive director for strategy and planning, told MEED that the company was working towards implementing control systems to enable clean and renewable energy to meet up to 100 per cent of power demand “under specific parameters or conditions”.
As things stand, Ewec is set to become the first offtaker in the region to build a utility-scale battery energy storage system (BESS), a key tool to address the intermittency of solar energy production. The company sought advisers for the development of its first two BESS facilities earlier this year.
The two projects will have a minimum capacity of 300MW plus one-hour of reserve-optimised BESS. The facilities are expected to come on-stream by 2026.
From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy
Higher peak demand not only requires additional thermal and solar generation capacity, but also batteries to enhance system reliability, Ewec noted in a presentation in March.
Based on its latest statement of future capacity requirements, Ewec foresees a 30 per cent peak demand increase from 16.7GW in 2022 to 21.6GW by 2029.
This year’s commissioning of a new power plant in Sharjah – the 1,800MW Hamriyah independent power producer (IPP) – is expected to reduce Ewec’s electricity exports. However, this will be offset by the addition of offshore demand starting in 2026 from Abu Dhabi National Oil Company (Adnoc).
In spite of rising demand warranting expansion in installed generation capacity – and with substantial contracted thermal capacity approaching expiry – Ewec forecasts halving its total carbon dioxide (CO2) emissions from 43 million tonnes a year (t/y) in 2019 to 22 million t/y by 2035.
Ewec needs to install 7.3GW of solar capacity by 2029 and 16GW by 2036, which implies procuring roughly 1GW to 1.5GW of new capacity annually during the period.
By the end of 2023, Ewec’s solar fleet will comprise the 935MW Noor Abu Dhabi project in Sweihan and the 1.5GW Al-Dhafra solar photovoltaic (PV) plant, which is nearing completion.
The procurement process is under way for the emirate’s third utility-scale solar PV IPP, also with a capacity of 1.5GW, in Al-Ajban.
Tendering for a fourth solar PV project, likely to be located in A-Ain, is also expected to begin in the third or fourth quarter of 2023.
This ambitious programme, including an aspiration to enable Ewec’s solar fleets to produce dispatchable loads similar to conventional power plants, makes the BESS projects of paramount importance.
Dubai green story
Dubai’s long-term capacity procurement plan is less clear, although state utility Dubai Electricity & Water Authority (Dewa) has reported a 5.5 per cent increase in demand in the emirate in 2022, to reach 53,180 gigawatt-hours (GWh).
This is half of the 10 per cent growth in 2021, which marked the emirate’s resurgence from the Covid-19 pandemic.
As of early 2023, over 2GW of clean energy from the Mohammed bin Rashid solar park accounted for 14 per cent of Dewa’s electricity production capacity, which stood at 14.5GW.
Based on the initial plan of 5GW of capacity once the solar park is complete, and with some 1GW still under construction, Dewa is expected to procure at least 2GW more.
The 1.8GW sixth phase of the solar park, which is currently being tendered, accounts for most of the outstanding capacity.
Unlike Abu Dhabi, which plans to expand its thermal generation capacity in light of the demand increase and expansion of intermittent renewable energy, Dubai has already ruled out gas as a feedstock for future greenfield generation capacity.
“We have a relatively new and modern fleet [of thermal power generation plants] that would be operational for another 20 to 30 years,” Saeed Mohammed al-Tayer, Dewa CEO and managing director, said in a forum in Dubai in 2020.
The Dubai Economic Agenda 2033 (D33), which aims to double the size of Dubai’s economy over the next decade and consolidate its position among the top three global cities, is expected to drive power and water demand within the emirate, without compromising its carbon abatement strategy and emissions reduction targets.
Diversification
The UAE already has the GCC’s most diversified electricity production installed capacity, with fleets deriving electricity from solar PV, thermal and nuclear power plants. The region’s first hydroelectric power plant in Hatta in Dubai will further expand the country’s power sources.
The completion of the 1.5GW Al-Dhafra solar IPP in Abu Dhabi and roughly 1GW from the fourth and fifth phases of the MBR solar park in Dubai will drive solar’s share from 8 per cent at the start of the year to 12 per cent by the end 2023. This will cause the overall share of thermal power generation to retreat by three percentage points to 79 per cent, in spite of the completion of the remaining units at Hassyan in Dubai, the Hamriyah IPP in Sharjah and the Fujairah F3 facility.
The three reactors at the Barakah nuclear power plant in Abu Dhabi also contribute an estimated 4.2GW of installed capacity, or roughly 9 per cent of Abu Dhabi, Dubai and Sharjah’s combined overall capacity, and 18 per cent in Abu Dhabi alone.
From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy.

Exclusive from Meed
-
Chinese contractor wins Saudi power and gas contracts4 August 2026
-
Contractors submit bids for key Aramco offshore tenders4 August 2026
-
Credit ratings key to infrastructure finance4 August 2026
-
AtkinsRealis confirms Sphere Abu Dhabi role4 August 2026
-
Oman opens door to direct power sales4 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Chinese contractor wins Saudi power and gas contracts4 August 2026
Chinese contractor Ningxia Power Construction has announced it has won two contracts in Saudi Arabia covering power and gas infrastructure projects with a combined value of about RMB280m ($39m).
The awards cover the third phase of cable laying and connection works for Saudi Aramco’s Master Gas System (MGS-III) project and the first phase of a 380kV transmission line for the Red Sea Aluminium project, the company said in a statement.
The MGS gas booster station contract covers electrical, instrumentation and control, communications, pre-commissioning, commissioning and defect rectification works.
The project is located northwest of Al-Mendassah in Medina Province. Construction is scheduled to last 670 days and continue through to partial mechanical completion and mechanical completion.
The Red Sea Aluminium contract involves the first phase of a 380kV overhead transmission line project.
The scope includes eight new transmission circuits. Four incoming double-circuit lines will extend about 15.2 kilometres from the connection point to the switchyard. Four outgoing double-circuit lines will run about 0.2 kilometres from the switchyard to the aluminium plant power station. Provision has also been made for two additional outgoing circuits in the future.
The Red Sea Aluminium complex is a planned integrated aluminium production facility in Yanbu Industrial City being developed by Red Sea Aluminium Holdings (RSAH), a joint venture of Innovation Global Industries, Innovation New Materials and Shandong Innovation Group
In June, RSAH awarded China’s Shandong Electric Power Construction Corporation (Sepco) an estimated $100m engineering, procurement and construction contract for a 380kV overhead transmission line project at the Red Sea Aluminium complex.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18081852/main.jpg -
Contractors submit bids for key Aramco offshore tenders4 August 2026

Register for MEED’s 14-day trial access
Contractors in Saudi Aramco’s Long-Term Agreement (LTA) pool of offshore service providers have submitted bids for five offshore tenders covering the engineering, procurement, construction and installation (EPCI) of structures at the Abu Safah, Berri, Manifa, Marjan, Safaniya and Zuluf offshore oil and gas fields in Saudi Arabia.
The tenders are numbers 167, 168, 169, 170 and 171 on Aramco’s Contract Release and Purchase Order (CRPO) system, according to sources.
Aramco issued the five CRPOs to its offshore LTA contractors in December, setting an initial bid submission deadline of 3 February.
The Saudi energy giant has since extended the bid submission deadline several times – to 31 March, 1 June, 1 July and then 30 July – to allow LTA contractors sufficient time to prepare proposals.
At the request of certain bidders, Aramco granted a final two-day extension, with LTA contractors submitting their proposals for the five CRPOs on 1 August, sources told MEED.
The basic scope of EPCI work on the tenders is as follows:
- CRPO 167 – eight jackets at the Marjan field development
- CRPO 168 – four production deck modules (PDMs) at the Abu Safah, Berri, Manifa and Safaniya fields
- CRPO 169 – three PDMs at the Marjan field development
- CRPO 170 – three PDMs at the Marjan field development
- CRPO 171 – three PDMs at the Zuluf field development
Offshore contract awards
Aramco spent almost $11bn on offshore EPCI contracts last year, more than double its capital expenditure on offshore projects in 2024, marking another year of robust upstream project spending in Saudi Arabia.
In July, Aramco selected contractors for five CRPOs – numbers 150, 157, 158, 159 and 160 – worth over $3bn. These involve EPCI work and infrastructure upgrades at the Abu Safah, Berri, Manifa, Marjan and Zuluf offshore fields.
The Saudi energy giant then picked contractors for four more CRPOs that are part of the large-scale project to expand infrastructure at the Zuluf offshore field development. The tenders are CRPOs 145, 146, 147 and 148, and their combined value is estimated to be almost $6bn.
In late December last year, Italian contractor Saipem announced securing contracts for CRPOs 162 and 165. The scope of work on CRPO 162 covers the EPCI of two rigid pipelines – a 30-inch pipeline stretching 23.98 kilometres (km) and a 20-inch pipeline, 10.23km-long; replacement of a flexible 10-inch pipeline that spans 5.1km; and modification work on topsides at the Berri and Abu Safah field developments. The duration of this contract is 32 months, Saipem said.
The scope of work on CRPO 165, lasting 12 months, includes subsea interventions at the Marjan field development and the EPCI of 300 metres of onshore pipeline and associated tie-ins.
In early January 2026, MEED reported that Aramco had selected US-based McDermott International for CRPO 166. The scope of work is understood to have been carved out of the $15bn Marjan offshore field development project, under which Aramco issued contracts for 20 EPCI packages in 2019. McDermott won the largest share of work on the project, securing an estimated $4.5bn of contracts across two packages.
The contract for CRPO 166 was single-sourced to McDermott without a competitive tendering process and issued as a change order, sources told MEED.
Aramco then awarded its second offshore contract of the year, CRPO 156, to Saipem. The scope of work covers the EPCI of a 48-inch trunkline, spanning roughly 65km offshore and 12km onshore, from the Safaniya offshore oil field to the onshore processing facility, plus associated works such as subsea hook-ups.
CRPO 156 comprises the third package in Aramco’s latest expansion phase at Safaniya – the world’s largest offshore oil field, with a production capacity of nearly 1.2 million barrels a day (b/d). Discovered in 1951, the field is located in Gulf waters approximately 265km north of Aramco’s headquarters in Dhahran.
MEED also reported that Saipem was selected by Aramco for two more tenders as part of the Safaniya field development expansion phase – CRPOs 154 and 155. The combined contract value for CRPOs 154 and 155 is estimated at $600m, sources said.
In April, state-owned China Offshore Oil Engineering Company won CRPO 161, which covers the EPCI of four gas jackets at the Arabiyah, Hasbah and Karan offshore fields.
Healthy contract award pipeline
Looking ahead, in addition to CRPOs 167-171, which are currently under bidding, Aramco is evaluating bids submitted by its offshore LTA contractors in July and August last year for at least two additional tenders.
These are CRPOs 163 and 164, relating to the EPCI of infrastructure at the Abu Safah, Berri, Karan, Marjan and Safaniya fields.
Separately, the offshore LTA contractors are also bidding for a new tender – CRPO 176 – that was issued by Aramco in May, according to sources.
The scope of work on CRPO 176 covers the EPCI of seven flexible subsea pipelines with a combined length of 17km at the Berri and Marjan offshore field developments.
Aramco’s LTA pool of offshore service providers comprises the following entities:
- Saipem (Italy)
- McDermott International (US)
- Larsen & Toubro Energy Hydrocarbon (LTEH, India) / Subsea7 (UK)
- NMDC Energy (UAE)
- Lamprell (UAE/Saudi Arabia)
- China Offshore Oil Engineering Company (China)
- Dynamic Industries (US)
- Sapura Energy (Malaysia)
- TechnipFMC (France) / MMHE (Malaysia)
- Hyundai Heavy Industries (South Korea)
In April 2025, Aramco renewed its LTAs with the following contractors, whose contracts had either lapsed or were close to expiry:
- Saipem
- McDermott International
- Larsen & Toubro Energy Hydrocarbon / Subsea7
- NMDC Energy
- Lamprell
- China Offshore Oil Engineering Company
ALSO READ: Aramco moves apace with Jafurah unconventional gas campaign
https://image.digitalinsightresearch.in/uploads/NewsArticle/18080836/main0627.jpg -
Credit ratings key to infrastructure finance4 August 2026
A global convergence in how infrastructure is financed is creating new pools of capital for Gulf projects, but the region’s non-OECD status means credit ratings will be central to unlocking the largest of these, according to Fitch Ratings.
The ratings agency said the boundaries between project finance, corporate credit and structured finance are blurring as investors seek to optimise financing for the infrastructure required to support the digital buildout and energy transition. Rising interest from institutional investors in private credit, particularly asset-backed lending, is accelerating the adoption of tailored financing structures.
For the GCC, the shift is important because of a specific regulatory constraint. Under EU Solvency II rules, unrated infrastructure debt sourced from outside the OECD cannot be treated as qualifying infrastructure. Fitch said this means that for investors seeking to access infrastructure opportunities in Saudi Arabia, India and other non-OECD markets, a credit rating is necessary for regulatory capital treatment.
The distinction is significant for a region running one of the world’s largest project pipelines. Saudi Arabia, the UAE and their neighbours are financing large-scale projects across the power, water, transport and digital infrastructure sectors, and much of the incremental capital Fitch identifies is held by regulated institutions for which ratings determine capital charges.
Insurers pivot
Insurers and pension funds are among the most significant structural sources of infrastructure capital, with global aggregated assets of about $45tn and $40tn respectively. Fitch says their increasing involvement is directly intertwined with the role of credit ratings, as cost-of-duration mismatches within solvency regimes push insurers towards liability-driven investment strategies that better match assets with liabilities.
Insurer allocations to infrastructure have historically been low, at a global median of about 1% of investment portfolios. Fitch said this is changing rapidly. It cited a Nuveen survey conducted at the end of 2025 indicating that private market infrastructure debt is set to be the most favoured destination for fixed-income allocation for the third consecutive year, with 46% of respondents planning to grow allocations over the next two years.
Sovereign wealth funds also play a major role, with over 30% of their private market fund allocations going to infrastructure, with AI-linked infrastructure the dominant sub-theme, displacing transport and logistics for new commitments. Energy transition ranked a close second, often aligned with national strategic objectives.
Larger funds with more than $100bn in assets are deploying directly and through co-investments, bypassing fund structures to reduce fees and increase control. Fitch said such funds are increasingly price-setters in large infrastructure deals, and that their strategic national mandates mean they will absorb assets at returns that pure financial investors would reject.
Regional outlook
For the GCC specifically, Fitch said additional investment is likely to support security enhancements for core infrastructure assets in response to conflict in the region, alongside upgrades to transport and social infrastructure. It expects increased renewable power capacity and enhanced oil and gas-related infrastructure.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18079923/main.gif -
AtkinsRealis confirms Sphere Abu Dhabi role4 August 2026
AtkinsRealis has confirmed it has been appointed lead design and supervision consultant on the $1.7bn Sphere Abu Dhabi project on Yas Island.
The Canadian engineering and project management firm said it will partner with local firm Alec Engineering & Contracting on the venue, which is scheduled to open in 2029.
AtkinsRealis will be responsible for overall design coordination across architecture, structural engineering and specialist immersive technologies. Alec – appointed by Abu Dhabi’s Department of Culture & Tourism (DCT Abu Dhabi) – will oversee procurement, construction delivery and project completion.
The project is being delivered under a design-and-build framework.
Alec Holdings confirmed in May that its subsidiary, Alec Engineering & Contracting, had received a letter of award for the construction contract. MEED previously reported that Alec was the selected contractor and had been working on the project during the pre-construction phase.
Sphere Abu Dhabi will be built on Yas Island on a plot between Yas Mall and SeaWorld Abu Dhabi. It will be the first Sphere venue outside the US and is expected to echo the scale of Sphere Las Vegas, with a capacity of up to 20,000, depending on configuration.
The venue will feature a fully programmable LED exosphere and a wraparound interior display capable of delivering 16K-resolution visuals, alongside beamforming audio technology that can direct sound to individual seats.
DCT Abu Dhabi is developing Sphere Abu Dhabi with US-based Sphere Entertainment.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18079715/main.jpg -
Oman opens door to direct power sales4 August 2026
Commentary
Mark Dowdall
Power & water editorOman’s Direct Sales Framework has been in place since April, but its success will ultimately depend on whether developers and large electricity users choose to adopt it.
The framework establishes a regulated process that allows qualifying private renewable energy developers to sell electricity directly to eligible consumers, instead of through Oman’s traditional single-buyer model.
For the first time, large electricity consumers have a formal mechanism to procure renewable power directly from developers, rather than relying solely on electricity supplied through the wider grid.
The recently tendered 280MW Marsa solar independent power project could provide an early indication of how the framework will be used in practice.
The project has been identified as a potential early application of the new regime, with electricity generated near Haima expected to be supplied to the Marsa LNG facility at Sohar through Oman’s transmission network.
The framework also requires grid-connection studies, network approvals and annual capacity limits, underscoring that direct sales will continue to operate within a regulated market rather than an open one.
Developers will also need customers willing to sign long-term agreements, while large electricity users will need to see clear value in procuring renewable power directly.
The scale of electricity demand expected over the coming decade will be a key factor in driving these decisions. Large industrial consumers are expected to account for a growing share of Oman’s future electricity demand as mining, green hydrogen, metals and other energy-intensive industries expand.
Oman’s procurement of utility-scale generation through competitive tenders is not slowing down either, as evidenced by recent advisory tenders for up to 4GW of solar projects targeted for commercial operation by Q2 2030.
In the meantime, for some users, securing renewable electricity directly from developers may become an attractive alternative to relying solely on the traditional supply model.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18038648/main.jpg