UAE power sector shapes up ahead of Cop28

3 April 2023

This package on the UAE's power sector also includes:

Ewec rules out solar in desalination projects

Dewa receives K station bid

Dewa briefs 1.8GW solar bidders

Italian firms pursue energy transition roles

Majid al-Futtaim signs 36MW clean energy agreement

Abu Dhabi eyes power and water contracts extension


There will be no shortage of milestones once November’s Cop28 turns the spotlight onto the UAE’s power generation sector.

Already, Abu Dhabi-based Emirates Water & Electricity Company (Ewec) has announced that, on 10 February at 2.26 pm, it met 80 per cent of total power demand using renewable and clean energy from its solar and nuclear power plants – supplying roughly 6.2GW of its total 7.7GW system power demand.

Before this, Bruce Smith, Ewec’s executive director for strategy and planning, told MEED that the company was working towards implementing control systems to enable clean and renewable energy to meet up to 100 per cent of power demand “under specific parameters or conditions”.

As things stand, Ewec is set to become the first offtaker in the region to build a utility-scale battery energy storage system (BESS), a key tool to address the intermittency of solar energy production. The company sought advisers for the development of its first two BESS facilities earlier this year.

The two projects will have a minimum capacity of 300MW plus one-hour of reserve-optimised BESS. The facilities are expected to come on-stream by 2026.

From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy

Higher peak demand not only requires additional thermal and solar generation capacity, but also batteries to enhance system reliability, Ewec noted in a presentation in March.

Based on its latest statement of future capacity requirements, Ewec foresees a 30 per cent peak demand increase from 16.7GW in 2022 to 21.6GW by 2029.

This year’s commissioning of a new power plant in Sharjah – the 1,800MW Hamriyah independent power producer (IPP) – is expected to reduce Ewec’s electricity exports. However, this will be offset by the addition of offshore demand starting in 2026 from Abu Dhabi National Oil Company (Adnoc).

In spite of rising demand warranting expansion in installed generation capacity – and with substantial contracted thermal capacity approaching expiry – Ewec forecasts halving its total carbon dioxide (CO2) emissions from 43 million tonnes a year (t/y) in 2019 to 22 million t/y by 2035.

Ewec needs to install 7.3GW of solar capacity by 2029 and 16GW by 2036, which implies procuring roughly 1GW to 1.5GW of new capacity annually during the period.

By the end of 2023, Ewec’s solar fleet will comprise the 935MW Noor Abu Dhabi project in Sweihan and the 1.5GW Al-Dhafra solar photovoltaic (PV) plant, which is nearing completion.

The procurement process is under way for the emirate’s third utility-scale solar PV IPP, also with a capacity of 1.5GW, in Al-Ajban.

Tendering for a fourth solar PV project, likely to be located in A-Ain, is also expected to begin in the third or fourth quarter of 2023.

This ambitious programme, including an aspiration to enable Ewec’s solar fleets to produce dispatchable loads similar to conventional power plants, makes the BESS projects of paramount importance.

Dubai green story

Dubai’s long-term capacity procurement plan is less clear, although state utility Dubai Electricity & Water Authority (Dewa)  has reported a 5.5 per cent increase in demand in the emirate in 2022, to reach 53,180 gigawatt-hours (GWh).

This is half of the 10 per cent growth in 2021, which marked the emirate’s resurgence from the Covid-19 pandemic. 

As of early 2023, over 2GW of clean energy from the Mohammed bin Rashid solar park accounted for 14 per cent of Dewa’s electricity production capacity, which stood at 14.5GW.

Based on the initial plan of 5GW of capacity once the solar park is complete, and with some 1GW still under construction, Dewa is expected to procure at least 2GW more.

The 1.8GW sixth phase of the solar park, which is currently being tendered, accounts for most of the outstanding capacity.

Unlike Abu Dhabi, which plans to expand its thermal generation capacity in light of the demand increase and expansion of intermittent renewable energy, Dubai has already ruled out gas as a feedstock for future greenfield generation capacity.

“We have a relatively new and modern fleet [of thermal power generation plants] that would be operational for another 20 to 30 years,” Saeed Mohammed al-Tayer, Dewa CEO and managing director, said in a forum in Dubai in 2020.

The Dubai Economic Agenda 2033 (D33), which aims to double the size of Dubai’s economy over the next decade and consolidate its position among the top three global cities, is expected to drive power and water demand within the emirate, without compromising its carbon abatement strategy and emissions reduction targets.

Diversification

The UAE already has the GCC’s most diversified electricity production installed capacity, with fleets deriving electricity from solar PV, thermal and nuclear power plants. The region’s first hydroelectric power plant in Hatta in Dubai will further expand the country’s power sources.

The completion of the 1.5GW Al-Dhafra solar IPP in Abu Dhabi and roughly 1GW from the fourth and fifth phases of the MBR solar park in Dubai will drive solar’s share from 8 per cent at the start of the year to 12 per cent by the end 2023. This will cause the overall share of thermal power generation to retreat by three percentage points to 79 per cent, in spite of the completion of the remaining units at Hassyan in Dubai, the Hamriyah IPP in Sharjah and the Fujairah F3 facility.

The three reactors at the Barakah nuclear power plant in Abu Dhabi also contribute an estimated 4.2GW of installed capacity, or roughly 9 per cent of Abu Dhabi, Dubai and Sharjah’s combined overall capacity, and 18 per cent in Abu Dhabi alone.

From being nearly wholly dependent on thermal power generation as recently as four years ago, these developments offer compelling evidence of the UAE’s commitment to its energy diversification strategy.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10723958/main.jpeg
Jennifer Aguinaldo
Related Articles
  • Consortiums prepare bids for Al-Khairan phase one IWPP

    14 May 2026

     

    Two developer consortiums are finalising bids for the first phase of Kuwait’s Al-Khairan independent water and power producer (IWPP) project, the deadline for which has been extended to 1 June.

    The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant. 

    The project is expected to run on Low Sulphur Fuel Oil (LSFO) as the primary fuel and to accommodate crude oil, gas oil, and natural gas as backup fuels. Later phases will further expand capacity.

    The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate, with the following groups currently preparing offers:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) 
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)

    The two individual companies, Sumitomo Corporation (Japan) and Nebras Power (Qatar), are now “unlikely” to submit a bid, according to a source close to the project.

    It is also understood that the third consortium of China Power, Malakoff International (Malaysia) and Abdul Aziz Al-Ajlan Sons (Saudi Arabia) is no longer bidding for the contract.

    The project is being procured by the Kuwait Authority for Partnership Projects (Kapp) and the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The Al-Khairan IWPP project is part of Kuwait’s long-term plan to expand power and water production capacity through public-private partnerships (PPPs).

    The winning bidder will sign a set of PPP agreements covering financing, design, construction, operation and transfer of the project.

    The energy conversion and water purchase agreement is expected to cover a 25-year supply period.

    Upcoming awards

    Kuwait is also preparing to offer a contract to develop zone one of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    In January, three consortiums submitted bids for a contract to develop Kuwait’s first utility-scale solar photovoltaic (PV) plant.

    The Al-Dibdibah power and Al-Shagaya renewable energy phase three, zone one independent power project (IPP) will have a total power-generating capacity of 1,100MW.

    MEED understands that the preferred bidder announcement will happen after the bid closes for zone two of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    The PPP authority is procuring the 500MW solar photovoltaic IPP in partnership with the ministry.

    The bid deadline for this project was recently extended to 31 May.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16835649/main.jpg
    Mark Dowdall
  • Bidders compete for new Dubai Metro line project

    14 May 2026

     

    Register for MEED’s 14-day trial access 

    Dubai’s Roads & Transport Authority (RTA) has held a pre-bid meeting for the Dubai Metro Airport Express Line with consultants understood to be competing for work on the project.

    It is understood that the RTA has requested firms to form joint ventures for the project. The firms that attended the meeting include:

    • Aecom (US)
    • Arup (UK)
    • ARX (Switzerland)
    • AtkinsRealis (Canada)
    • DB (Germany)
    • Egis (France)
    • Jacobs (US)
    • Mott Macdonald (UK)
    • Parsons (US)
    • Sener (Spain)
    • Surbana Jurong (Singapore)
    • Systra (France)
    • WSP (Canada)

    The consultancy contract covers the study and design of the Airport Express Line, which will extend from the Al-Garhoud area of the city to Al-Maktoum International airport (DWC) in the Jebel Ali area. The proposed line will stretch about 55 kilometres (km) and include five stations, providing passengers with facilities such as remote airline check-in, baggage drop-off and security screening.

    Consultants have been allowed until June to submit their proposals.

    The new line will run from the Red Line metro station at Dubai International airport through Al-Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC) before continuing on to DWC.

    There will be two spur lines. The first will run from the new JVC station to the Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch out towards Business Bay, where another station will be built.

    The new line appears to follow a similar route to the Etihad Rail high-speed railway project, which is now under construction and due to be completed by 2030.

    Route 2020 extension

    The Airport Express Line scheme is the latest metro project to be tendered by the RTA this year. Tendering activity is already ongoing for the Route 2020 extension, which will start from the Expo 2020 metro station and connect to DWC’s West Terminal.

    In April, MEED exclusively reported that consultants had submitted bids for the project.

    The extension to the line will run for about 3km and will feature two stations.

    The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    The RTA awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain’s Acciona, Turkiye’s Gulermak and France’s Alstom in 2016.

    Gold Line

    Dubai’s plans for its metro network do not stop with connecting the extension of the Route 2020 metro line to DWC. There are long-term plans for further extensions.

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.

    The existing network includes the Red and Green lines of the Dubai Metro and the Dubai Tram, which connects Al-Sufouh and Dubai Marina to the metro network. The last rail project to start operations in Dubai was the Red Line extension that opened for Expo 2020.

    There are also existing and planned rail lines connecting Dubai to other emirates that are being developed and operated by Abu Dhabi-based Etihad Rail. These include passenger and freight services, as well as a high-speed rail connection.

    Blue Line

    In December 2024, the RTA awarded a AED20.5bn main contract for the Dubai Metro Blue Line project to a consortium of Turkish firms Limak Holding and Mapa Group and the Hong Kong office of China Railway Rolling Stock Corporation.

    The Blue Line consists of 14 stations, including three interchange stations at Jaddaf, Rashidiya and International City 1, as well as a station in Dubai Creek Harbour.

    By 2040, the number of daily passengers on the Blue Line is projected to reach 320,000. It will be the first Dubai Metro line to cross Dubai Creek, doing so on a 1,300-metre viaduct.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16833450/main.jpg
    Colin Foreman
  • Local firm wins $100m Kuwait substation contract

    14 May 2026

     

    The local Al-Ahleia Switchgear Company has won an engineering, procurement and construction contract for a $100m substation project in Wafra in Kuwait’s Al-Ahmadi Governorate.

    According to a source, the firm has been appointed as the contractor for the Wafra 2Z substation 400/132/33kV project, with construction scheduled for completion in January 2029.

    The contract was awarded by US-headquartered Chevron, which is undertaking its first major power project in Kuwait, according to data from MEED Projects.

    It is understood that contractor bids for the project were first submitted in 2023 by National Contracting Company (Kuwait), Al-Ahleia Switchgear (Kuwait), Imco Engineering & Construction Company (Kuwait) and Larsen & Toubro (India).

    The tender was cancelled in 2024, and a new tender was issued last year.

    In April, Al-Ahleia Switchgear won a contract to build a 400/132/11kV substation at the South Surra township for Kuwait’s Public Authority for Housing Welfare.

    The firm also recently won a separate contract in Oman for the supply, installation, execution and maintenance of a main power substation.

    The contract was awarded by Oman’s Public Authority for Social Insurance as part of its affordable housing project, known locally as Al-Masaken Al-Muyassara.

    According to MEED Projects, Chevron owns about $11.2bn-worth of operational oil and gas projects across the Middle East and Africa. It also owns four major power generation projects in Saudi Arabia, valued at $810m.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16832909/main.jpg
    Mark Dowdall
  • Al-Ain breaks ground on Four Seasons Saadiyat

    14 May 2026

    Al-Ain Asset Management has held a groundbreaking ceremony for its Four Seasons Private Residences Abu Dhabi project at Saadiyat Beach.

    Due for completion in 2029, the gated beachfront scheme will comprise 116 ultra-luxury homes with direct beach access. The unit mix includes villas, beachfront mansions, suites and penthouses, alongside a range of bespoke amenities and Four Seasons-branded services, Wam reported.

    Al-Ain Asset Management said the majority of the residences have been sold, and that AED250m ($68m) of new villa sales were recorded within one week, underlining demand for ultra-prime homes in Abu Dhabi.

    The developer added that the development set new pricing benchmarks for the emirate’s luxury coastal real estate, achieving prices above AED14,000 a square foot. Total sales have exceeded AED4bn since the project launched less than a year ago.

    The groundbreaking ceremony was attended by senior leadership and key partners, including Four Seasons, Killa Design and Mirage Leisure & Development. LW Design Group is also involved in the development.

    Al-Ain Asset Management is also developing another residential scheme on Saadiyat Island. The Vida Residences development will comprise apartment units geared towards long-stay living, supported by hotel-style facilities and operational spaces. Mimar Architecture & Engineering is working as the consultant.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16833035/main.jpeg
    Colin Foreman
  • Aldar acquires Dubai Studio City development

    14 May 2026

    Abu Dhabi-based developer Aldar has acquired a residential and community retail development in Dubai Studio City from Dubai-based developer SRG for AED1.1bn ($300m).

    The deal is part of Aldar’s long-term strategy to build a high-quality, recurring-income portfolio and to scale its presence in the city.

    Scheduled for delivery in 2028, the project comprises six mid-rise buildings with 312 homes, including one-, two- and three-bedroom apartments and duplexes. It also includes a community mall with retail, leisure and food-and-beverage offerings, as well as a 16,000-square-metre park.

    “Dubai is a priority growth market for Aldar, and this acquisition reflects our belief in the city’s residential market and the central role that institutionally owned, professionally managed rental housing plays in meeting the needs of a growing population,” said Jassem Saleh Busaibe, CEO of Aldar Investment. 

    “Dubai Studio City’s established infrastructure, vibrant community and strong connectivity make it an excellent location for a high-quality, professionally managed living environment. This transaction is the latest step in a deliberate and broadening strategy to build a diversified portfolio of income-generating assets in Dubai, one that we expect to continue growing as the city attracts increasing global interest and talent,” he added. 

    The transaction expands Aldar’s activities in Dubai across a range of property types. Aldar Investment’s recurring-income portfolio in the emirate now includes residential, commercial, logistics and mixed-use assets. Key holdings include a mixed-use joint venture with Expo City Dubai, a signature office tower in Dubai International Financial Centre, a Grade A office building on Sheikh Zayed Road, and logistics facilities in National Industries Park and Dubai South.

    On the development front, Aldar’s partnership with Dubai Holding continues to gain traction, with three master-planned residential communities already launched and a pipeline exceeding 2.3 million sq m of new gross floor area. 

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16832033/main.jpg
    Colin Foreman