UAE lenders chart a route to growth

10 April 2023

 

International markets may have been spooked by challenges in the global banking system that provide an eery reminder of past problems, but UAE lenders have little reason to fear that this year will interrupt the progress seen in 2022 as profits swelled on the back of an economy in recovery mode.  

Contagion fears may be misplaced. UAE banks had minimal exposure to the collapsed Silicon Valley Bank. Unlike Saudi Arabia and Qatar, there was no UAE exposure to Credit Suisse – the troubled Swiss lender swallowed up by its larger rival UBS last month.

Although UAE lending rates are not as vibrant as some of its neighbours, with nothing to rival the housing finance-linked boom in Saudi Arabia, the country’s banks have nonetheless shown some impressive performance metrics. Overall sector profits grew by 31 per cent in 2022, while assets grew by 10.6 per cent, according to figures collated by KPMG.

Profitability of the four largest lenders, First Abu Dhabi Bank (Fab), Emirates NBD, Abu Dhabi Commercial Bank (ADCB) and Dubai Islamic Bank (DIB), which control almost three-quarters of the banking system, exceeded pre-pandemic levels in 2022  – reflecting strong growth in interest income and normalised provisioning charges, according to Moody’s Investors Service.

Leading the pack, Emirates NBD showed a 40 per cent profit growth to AED13bn ($3.5bn), helped by a notably strong fourth-quarter performance that saw profits up by 94 per cent in year-on-year terms to AED3.9bn ($1.06bn) amid improving margins and a lower cost of risk.

DIB, the other Dubai lender of the big four UAE lenders, reported net profits up 26 per cent to AED5.5bn ($1.5bn), while ADCB reported a 23 per cent increase to AED6.4bn ($1.74bn). Fab, the UAE’s largest lender, had a more modest 7 per cent increase in net profits to AED13.4bn ($3.65bn).

Stabilising fundamentals

Banks can be confident that the prime source of their impressive profitability is unlikely to fade this year, given the global interest rate cycle. This continues last year’s picture. Net interest margins (NIMs) for UAE-listed banks grew 26 basis points (bps) in the fourth quarter of 2022, reaching 3 per cent for the first time, according to Kamco Invest Research.

“The interest rate environment reversed in 2022, driving aggregate growth of 28 per cent in the banks’ net interest income,” says Nitish Bhojnagarwala, senior credit officer at Moody’s.

“The growth reflected increasing asset yields, driven by rising interest rates, which more than offset higher funding costs.”

While the banks’ funding costs have increased, says Bhojnagarwala, they did not do so at the same rate, reflecting efforts to optimise their deposit mix and achieve strong zero or low-cost current and savings account balances, supporting margin growth.

NIMs should remain strong this year, not least given the continued cycle of rate rises emanating from the US Federal Reserve, which the UAE Central Bank tracks. The latter hiked its base rate by 25 bps to 5.5 per cent in March after the Fed hiked its base rate by a quarter per cent.

Some UAE lenders have also flagged priorities beyond fattening the bottom line. DIB said that given the rate environment and surplus liquidity, it had made a deliberate tactical move to support large corporate and public sector entities in adjusting and aligning their balance sheet in the new medium-term environment.

Elevated provisioning

Despite the strong conditions for profit growth, UAE banks will have a conservative strain in their approach to 2023, conscious of still elevated non-performing loan (NPL) ratios.

The big four banks’ NPL ratio declined to 5.3 per cent as of December 2022 from 5.9 per cent a year earlier.

“It remains high relative to the Gulf Cooperation Council region owing to the slower write-off policy of the UAE banks,” says Bhojnagarwala.

Coverage ratios have increased for the big four banks, standing at 100 per cent at year-end 2022, from 80 per cent a year earlier. Dubai’s ENDB was the standout bank here, with a coverage ratio of 145 per cent.

This reflects a broader tendency among banks to book higher provisions, with Dubai’s largest bank increasing absolute provisions in the fourth quarter of 2022 by $142.4m, reaching $517.9m.

Overall provisions booked by UAE-listed banks showed the biggest quarter-on-quarter percentage increase in the GCC of 40.2 per cent in the last quarter of 2022 to reach $1.23bn, says Kamco.

Moody’s anticipates loan loss provisions to stabilise at the current, pre-pandemic level and banks’ NPL ratio to improve modestly, driving higher coverage over the next 12-18 months.

“When we look at overall loan loss provisioning, it has fallen for two of the largest four banks, but in terms of cost of risk, fell by a collective 0.8 per cent from 1 per cent in 2021 and is now in line with pre-pandemic levels,” says Bhojnagarwala.

Evidence of faster payment settlements will bolster confidence levels among banks that credit losses will not rise this year. That may, in turn, afford more scope for lenders to scale back on provisioning at some point in the future.

Near future risk

Despite the improving conditions, analysts caution about potential economic headwinds.

Ratings agency S&P Global issued a warning earlier this year that real GDP growth could ease in 2023 and that the slowing of the non-oil sector will lower demand for credit. It sees the UAE property sector, which experienced strong demand in 2022 on the residential side, witnessing a moderation in price and rental increases this year.

UAE banks may need to countenance the prospect of higher problem loans in sectors such as construction and trade, as well as for some small and midsize enterprises. The latter is starting to feel the impact of more expensive credit in light of the higher interest rates.

Taken in context, this is unlikely to ruffle the Central Bank’s feathers. The country’s mix of elevated provisioning and strong profit performances suggest UAE banks will be suitably positioned to overcome such hurdles. And with healthy provisioning levels factored into the equation, the feeling remains that this year will continue the recovery record started in 2022.

This month's special report on the UAE also includes: UAE power sector shapes up ahead of Cop28

https://image.digitalinsightresearch.in/uploads/NewsArticle/10744976/main.gif
James Gavin
Related Articles
  • EtihadWE tenders $150m Ajman substation project

    21 July 2026

    The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.

    Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.

    The bid submission deadline is 10 August.

    According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.

    The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.

    Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.

    This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.

    EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.

    In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.” 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg
    Mark Dowdall
  • Seven seeks contractors for Dammam water park and hotel

    21 July 2026

     

    Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.

    The waterfront development sits on a 324,300-square-metre (sq m) plot.

    A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.

    Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.

    The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.

    The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.

    Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.

    Detailed design and issued-for-construction packages are complete.

    Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.

    The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.

    The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.

    Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.

    Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.

    The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.

    The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg
    Yasir Iqbal
  • Al-Ula appoints equestrian village early works contractor

    21 July 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.

    The contract was awarded to Al-Khobar-based Al-Shalawi International Company.

    Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.

    Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.

    RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.

    The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.

    These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg
    Yasir Iqbal
  • Contractors await decision on Riyadh airport sewage plant

    21 July 2026

     

    Seven contractors are awaiting a decision on a contract to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh, according to sources.

    It is understood that bids were submitted to King Salman International Airport Development Company (KSIADC) in March, following the tender’s release earlier this year.

    The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.

    The facility will have a treatment capacity of 92,000 cubic metres a day. The contract is estimated to be worth SR700m ($187m).

    The bidders (all local) are:

    • Al-Rawaf Trading & Contracting
    • Almajal Alarabi
    • Nesma Water & Energy
    • Safari Company
    • Saudi Services for Electro-Mechanic Works
    • Washnah Contracting
    • Water & Environment Technologies (Wetico)

    The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.

    US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.

    The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction contract covering potable water and fire water tanks and an associated pumping station. The same seven companies have submitted bids for that package.

    Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.

    The latest development followed KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.

    These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17709281/main.jpg
    Mark Dowdall
  • Dubai Municipality awards Tasreef drainage contract

    21 July 2026

     

    Dubai Municipality has awarded local firm Detech Contracting the engineering, procurement and construction (EPC) contract for the TF-15-C1 package of its Tasreef Rainwater Drainage Network programme.

    It is understood the municipality issued the letter of award for the contract earlier this month, covering the construction of a stormwater drainage system along Al-Wasl Road and communities west of the Dubai Canal.

    The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.

    It was tendered in February through the government’s Sewerage and Recycled Water Projects Department, with bids submitted in April.

    The package forms part of the wider Tasreef initiative, which is intended to improve Dubai’s flood resilience.

    The TF-15-C2 package was recently awarded to China State Construction Engineering Corporation for a stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.

    The project is estimated to cost $162m and includes the construction of about 20 kilometres of new stormwater pipelines. Similar to the C1 package, it is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.

    Separately, Al-Kharafi has won a drainage EPC contract (Ds207) to upgrade an existing pumping station for the municipality, a source said. The package focuses mainly on mechanical works and is valued at about $39m.

    In May, MEED reported that local firm Nael Construction & Contracting had signed a contract with Dubai Municipality to build a sewage and stormwater drainage system in Dubailand.

    The project (DS-204-C1) involves the construction of a drainage system with sewage gravity pipelines of up to 2,200mm in diameter.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17707980/main.jpg
    Mark Dowdall