UAE economy maintains robust growth
25 October 2023

UAE economic growth is largely on track as projected in 2023, with the growth estimates and forecasts remaining much as they were earlier in the year.
The latest estimates from the Washington-based IMF indicate a 3.4 per cent real GDP growth rate for the year, down only 0.1 per cent from the 3.5 per cent projected in April 2023, and still comfortably ahead of the global growth forecast of 3 per cent. The economy is then projected to pick up tempo in 2024 to a growth rate of 4 per cent.
The growth of the UAE’s non-oil economy has been higher than its oil growth over the course of 2023, with the IMF expecting the non-oil growth rate for the year to exceed 4 per cent, benefitting from strong domestic activity. It also projects a repeat of this performance in 2024.
The repeated extensions of the Opec+ production cuts have affected the country’s oil sector growth. However, the UAE’s oil output is set to accelerate next year with the UAE’s 2024 Opec+ production quota increase.
Consumer price inflation in the country is expected to have eased to an annual average of 3.1 per cent by the end of the year, compared to 4.8 per cent in 2022. This is then forecast to ease further to about 2.3 per cent in 2024, or roughly baseline levels.
Ali al-Eyd, the leader of an IMF team that visited the UAE in September, noted that “fiscal and external surpluses remain high on the back of high oil prices. The fiscal balance is expected to be around 5 per cent of GDP in 2023, driven by oil revenue and strong economic activity”.
Speaking to the broader fiscal and structural reforms under way in the UAE, Al-Eyd added: “The phased introduction of a corporate income tax that began in June 2023 will support higher non-oil revenue over the medium term.
“Public debt is projected to continue to decline, falling firmly below 30 per cent of GDP in 2023, including with the benefit of the Dubai emirate reducing its public debt by AED29bn ($7.9bn) in line with its Public Debt Sustainability Strategy. The current account surplus is expected to be notably above the medium-term level in 2023 and 2024.”
Surge in activity
In the latest assessments of business activity in the country, measured through the S&P Global purchasing managers’ index (PMI) survey, the UAE has shown an uptick in September, with the index rising to 56.7, where a value over 50 denotes growth.
This is up from 55 the previous month and is the most significant leap for the index since June, indicating a positive turn for the country’s non-oil private sector.
The index performance was driven by a rise in new orders, the sub-index for which reached 64.7 in September in a significant jump from 57.6 in the preceding month. This reflects a level of new order growth not witnessed since June 2019, and the evidence of rising demand came from across both domestic and external markets.
According to S&P, “the rate of new order growth was sharp and faster than the trend observed since the survey began in August 2009”.
The output sub-index also climbed to 62.8 in September, up from 61.9 the previous month, reflecting the influx of new orders, while there was also a knock-on boost to hiring, with non-oil firms reporting an increase in employment.

Below the country level, the PMI index for Dubai reached its highest level in three months, rising to 56.1 in September, up from 55.0 in August.
According to S&P, the index has averaged 55.5 over the first three quarters of the year, paralleling the first nine months of 2022, and this consistency aligns with a forecast of 4.0 per cent real GDP growth for Dubai in 2023.
There was a surge in new orders in Dubai, similarly to the fastest rate since mid-2019. According to Daniel Richards, senior Middle East and North Africa economist at Emirates NBD, this in turn “also boosted business confidence, which rose to the highest level since March 2020, just before the Covid-19 pandemic crisis took hold”.
Despite rising input costs, which saw the most substantial increase since July 2022, “the strong orderbook outweighed the impact of rising costs on sentiment”, notes Richards.
Growth areas
In terms of the sectors of growth, both the construction sector and wholesale and retail trade exhibited robust performances. The construction index reached a three-month high, rising to 54.5, and the wholesale and retail trade index reached 56.5, helping to lead the overall index score for Dubai.
The positive outlook in retail resulted in the fastest employment growth in that sector since May 2019.
Looking ahead, the UAE is addressing the central issues of energy transition through the lens of its UAE Energy Strategy 2050 and UAE Net Zero 2050 in the lead up to the UN Cop28 climate summit in November, while other areas of strategic focus for 2050 remain economic diversification, trade partnerships, digitalisation and green initiatives.
MEED’s November 2023 special report on the UAE includes:
> COMMENT: UAE eyes global leadership role
> POLITICS: Abu Dhabi networks on the global stage
> ECONOMY: UAE economy maintains robust growth
> BANKING: UAE banks enjoy the good times
> UPSTREAM: Hail and Ghasha galvanises UAE upstream market
> DOWNSTREAM: Adnoc spurs downstream gas expansions
> POWER: UAE closes ranks ahead of Cop28
> WATER: UAE ramps up decarbonisation of water sector
> PROJECTS: Top 10 UAE clean energy projects
> CONSTRUCTION: UAE construction sector returns to form
> TRANSPORT: UAE aviation returns to growth
Exclusive from Meed
-
Kuwait awards $381m oil project23 September 2026
-
Kuwait refinery project on track for year-end completion23 September 2026
-
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
-
UAE to develop integrated waste-to-resource pilot23 September 2026
-
Contractors prepare Oxagon Highway 55 bids23 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait awards $381m oil project23 September 2026
Register for MEED’s 14-day trial access
State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).
The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.
The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.
The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.
The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.
Meil will develop the new three-phase low-pressure wet separation facility at GC-25.
The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.
The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.
Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.
The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.
At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.
The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.
Booster and injection pumps will transfer treated effluent water to designated injection wells.
Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.
The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.
Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.
Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.
The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.
Seven companies submitted bids for the project last November.
The full list of bids was:
- Meil (India) – KD117m ($381m)
- Mechanical Engineering & Contracting Company (Kuwait) – KD130m
- Spetco (Kuwait) – KD158m
- Al-Kharafi (Kuwait) – KD164m
- China Oil HBP Science & Technology (China) – KD169m
- Alghanim International (Kuwait) – KD169m
- Jereh Oil & Gas Engineering (China) – KD191m
In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.
Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg -
Kuwait refinery project on track for year-end completion23 September 2026

A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.
The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.
One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”
The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).
Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.
The scope of the project includes:
- Construction of a substation
- Installation of transformers
- Installation of medium-voltage switchgear
- Installation of low-voltage auxiliary systems
- Installation of network protection systems
- Installation of disconnecting switches
- Installation of surge arrestors
- Installation of feeder breakers and cubicles
- Installation of low-voltage A/C and D/C equipment
- Installation of battery banks and battery chargers
- Installation of related relay and control panel boards
- Installation of fire alarm and fire protection equipment
- Installation of a SCADA system
- Installation of cables
- Civil works
- Associated facilities
The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.
On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.
The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.
Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.
He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.
Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg -
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
Register for MEED’s 14-day trial access
Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.
Saudi Arabia’s Almoosa Health Company awarded the contract.
The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.
It will be built on a 45,000-square-metre site.
A podium spanning the ninth and 10th floors will connect the two towers.
The hospital will also include parking for 1,700 cars.
BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.
In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.
In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.
Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg -
UAE to develop integrated waste-to-resource pilot23 September 2026
Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.
The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.
Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.
Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.
The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.
A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.
Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.
The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.
If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.
The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg -
Contractors prepare Oxagon Highway 55 bids23 September 2026

Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.
The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.
The project duration is 22 months.
Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.
MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.
The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.
Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.
In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”
The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg