UAE construction sector returns to form
12 October 2023
This package on the UAE’s construction sector also includes:
> Dubai starts construction of Expo Valley
> Emaar appoints contractor for Creek Harbour project
> Arada awards Jouri Hills Dubai construction contract
> Contractor appointed for Damac Hills developments
> Consultant appointed for $8.17bn Azizi Venice project
> Abu Dhabi tenders Mid Island Parkway packages

On 20 September, hundreds of people queued to buy property on Dubai’s Palm Jebel Ali. The rush to purchase units on the project, which stalled in 2008, is the latest sign of a return to form for the UAE’s construction sector.
The buoyant market conditions have prompted major UAE real estate developers to restart halted long-term projects.
In the past year, government-controlled developer Nakheel has released details of new masterplans for Palm Jebel Ali and the offshore islands it has reclaimed off the Deira Corniche, known as Dubai Islands.
Both developments are more high-end, low-rise developments that better reflect the dynamics of the post-pandemic market.
Nakheel also restarted the construction works on its Palm Beach towers project in Palm Jumeirah. Previously known as Palm Gateway, the project was rebranded and relaunched in October 2022.
Construction stopped in 2019 after structural concrete work had been completed for about 10 levels of the towers.
Indian contractor Shapoorji Pallonji will deliver the project.
Emaar Properties also announced the comeback of Dubai Creek Tower. The scheme made no significant progress after concrete pile cap works were completed in 2018.
First launched in 2015, the project was billed as the world’s tallest man-made structure, surpassing the height of Dubai’s Burj Khalifa. The project is being redesigned, which is expected to be completed by the first quarter of 2024. Construction is slated to begin in the second half of 2024.
Towering ambitions
The favourable market conditions have led another Dubai-based private developer, Azizi Developments, to restart plans to construct what it said would be the world’s second-tallest tower.
The plan to restart work on the rebranded AED3bn ($817m) 122-storey Entisar Tower project received a boost when Azizi purchased a plot of land on Sheikh Zayed Road next to World Trade Centre Metro Station 2 from Meydan.
UK-based Atkins worked on the tower's design for Azizi Developments after an original design was prepared for Meydan by Dubai-based AE7.

Demolition at the Dubai Pearl site in 2023, viewed from the MEED office in Dubai Media City
After two aborted attempts, development is expected to start again at the Dubai Pearl site, located north of Dubai Media City close to the Palm Jumeirah.
The construction work on the project stalled after the global financial crisis of 2008-09. The structures erected for the previous project have been demolished this year.
Dubai Holding, which now owns the land, has held a design competition and is in the final stages of selecting the winning architect. Local project management firm North 25 is overseeing the design competition.
Market overview
With more than $356bn-worth of private real estate developments and public building and housing programmes planned or under way, the UAE is the region’s second-biggest construction projects market, after Saudi Arabia.
After a dismal performance in 2020 due to the Covid-19 pandemic and economic downturn, the construction sector is on course for a strong comeback.
In 2021, contract awards worth about $10bn were recorded, an increase of 13.5 per cent over the previous year.
Continuing the same momentum, 2022 also grew by about 50 per cent to reach the $15bn mark, further increasing investor confidence.
According to data from regional projects tracker MEED Projects, the $17bn-worth of contract awards in 2023 has already surpassed the full-year total achieved in 2022.
The prospects for the rest of this year are promising. Nearly $8bn of contracts are already at the bid evaluation stage, and another $2bn are at the main contract bid and prequalification stages.
Projects pipeline
Renewed work opportunities for construction companies are presented by the restart of projects and new announcements in the UAE.
Real estate schemes dominate the country’s list of future projects.
In July, Emaar announced The Oasis project, which covers a total land area of more than 9.4 million square metres close to Dubai Investments Park. The $20bn project involves building over 7,000 residential units along with water canals, lakes and parks. It will also include the development of a 150,000 sq m retail area.
In October, Azizi Developments unveiled the Azizi Venice project in Dubai South. The AED30bn ($8.17bn) mixed-use development will offer over 30,000 residential units, including 100 mid-rise apartment complexes, 400 villas, two five-star hotels and an opera house.
Early this year, Mohamed Alabbar launched the $3.5bn Ramhan Island project off the coast of Abu Dhabi. The development will consist of 1,800 villas, 1,000 residences, a hotel and a marina. The project is being developed through Eagle Hills Development Company.
In July, Aldar Properties and the Abu Dhabi Housing Authority announced the AED8bn ($2.2bn) Balghaiylam Abu Dhabi residential project.
The project is scheduled to be completed by 2026 and will include 1,743 housing units. It is part of the Abu Dhabi government’s plan to employ public-private partnerships (PPPs) to provide affordable housing for its citizens through real estate schemes developed by approved developers.
Exclusive from Meed
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
-
Qatar receives bids for major power grid expansion24 August 2026
-
Maaden closes $1bn term loan and credit facility24 August 2026
-
Dubai inflation slows to 5.3% in July24 August 2026
-
Libya oil project on track for 2027 completion24 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi Arabia battery storage awards provide fresh lift24 August 2026
Commentary
Mark Dowdall
Power & water editorThe latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.
Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.
That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.
The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.
Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.
With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.
At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.
Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.
It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg -
Qatar receives bids for major power grid expansion24 August 2026

Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.
The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.
It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).
According to sources, bids were submitted for the following packages on 20 August:
- Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
- Package S3, covering new 66/11kV substations ($50m)
- Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
- Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
- Cable packages C1 and C2, covering 400kV cables ($100m)
Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.
In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.
The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.
Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.
Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.
These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.
Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg -
Maaden closes $1bn term loan and credit facility24 August 2026
Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.
The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.
The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.
The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.
ALSO READ: Maaden and Aramco sign deal to create joint venture
“The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.
“The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.
“Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg -
Dubai inflation slows to 5.3% in July24 August 2026
Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.
The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.
Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.
Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.
The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.
Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.
Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.
Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg -
Libya oil project on track for 2027 completion24 August 2026

The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.
The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.
The Libyan company was awarded the contract in February 2025.
The scope of the project includes:
- Construction of an accommodation camp
- Construction of the camp maintenance warehouse
- Construction of the camp office
- Construction of a fire brigade shelter
- Construction of a kitchen and mess hall
- Construction of a mosque
- Construction of a laundry room
- Construction of a clinic
- Construction of parking facilities
- Installation of a fire and gas system
- Installation of a power generator
- Construction of associated facilities
The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.
Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.
The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.
Libya shipped its first cargo of crude from the Erawin oil field in November 2023.
The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.
Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg