UAE closes ranks ahead of Cop28

11 October 2023

This package on the UAEs power sector also includes: 

Abu Dhabi to tap Kezad for hydrogen plan
Market expects Abu Dhabi hydrogen policy
Masdar to develop 10GW projects in Malaysia

Firms sign 60MW Sharjah captive solar plant
Masdar and Ewec sign wind power agreement
Firms submit 400MW battery storage interest


 

State-backed utility companies and off-takers in the UAE are preparing a cachet of projects to boost their green energy credentials in the weeks before the start of Cop28.

In September, Dubai Electricity & Water Authority (Dewa) signed agreements for the 1,800MW sixth phase of the Mohammed bin Rashid Solar Park.

Abu Dhabi state utility Emirates Water & Electricity Company issued the expression of interest (EoI) requests for its fourth utility-scale solar photovoltaic (PV4) project and its first two battery energy storage systems shortly after that.

Ewec is also expected to award the contract for the 1,500MW Al-Ajban solar project and inaugurate the 1,500MW Al-Dhafra solar plant prior to or during the climate summit.

The financial investment decision for the green hydrogen project in Ruwais, owned by France’s Engie, the UAE’s Fertiglobe and Abu Dhabi Future Energy Company (Masdar), is likely to be announced right before the start of Cop28.

Crucially, in early October, Adnoc Gas awarded UK-headquartered Petrofac the $615m main engineering, procurement and construction (EPC) contract for a project to develop a carbon capture facility at its Habshan gas processing complex in Abu Dhabi.

The plant will have the capacity to capture and permanently store 1.5 million tonnes a year (t/y) of carbon dioxide.

In Dubai, commercial agreements were reached on 3 October for the emirate’s first independent water project (IWP).

The Hassyan 1 seawater reverse osmosis (SWRO) project will have the capacity to treat 818,280 cubic metres of water a day (cm/d), only slightly lower than Abu Dhabi’s Taweela RO plant’s capacity of 919,000 cm/d –  the world’s largest at the time of construction.

The timing of the announcement of these milestones is critical. They help counter the massive scrutiny that the country, particularly Abu Dhabi, faces as it hosts Cop28.

A key area of focus among climate advocates, including the Pope, has been Adnoc Group’s well-documented plan to increase its oil production capacity from 4.5 million barrels a day (b/d) to 5 million b/d by 2027 as part of its “accelerated growth strategy”.

UAE ramps up decarbonisation of water sector

Not just about Cop28

The country’s renewable energy capacity build-up, in fact, began much earlier. It established the UAE Energy Strategy 2050 in 2017, four years before it set a target to achieve net-zero carbon emissions by 2050.

The 2017 strategy was intended to steer the country in a direction where the share of fossil fuels – mainly gas – in its energy mix shrank to 38 per cent, while clean energy expanded to 44 per cent.

The same year, the country put in place a water strategy to the year 2036 that aimed to reduce total demand for water resources by 21 per cent, lower the water scarcity index by three degrees and increase reuse of treated water to 95 per cent, among other goals.

Notably, the award of the second phase of Dubai’s MBR solar park, the first solar independent power producer (IPP) scheme in the GCC region, predated the 2017 strategy by two years.

A multibillion-dollar power plant project in Dubai, initially built to run on clean coal, has been converted to run on natural gas, showing the degree of compliance with the national 2050 net-zero plan.

The UAE has taken major steps to manage demand as well.

“The UAE has shown leadership in phasing out fossil fuel subsidies, having been the first country in Mena to do so back in 2015,” says Cornelius Matthes, CEO of Dubai-based Dii Desert Energy.

“It has an unparalleled track record in building some of the largest solar PV plants in the world at record low prices,” he adds.

Rounding out the country’s clean energy milestones is the completion of three units of the Barakah nuclear power plant, contributing 4,200MW of carbon emission-free electricity to the grid.

The UAE’s first utility-scale 100MW wind power projects, spread across four locations in Abu Dhabi and the northern emirate of Fujairah, were also unveiled by Ewec and Masdar in early October.

Future projects

For utility developers, investors and contractors, the UAE presents a long-term source of future opportunities.

Abu Dhabi’s Ewec aims to procure 1,500MW of solar PV capacity annually over the next 10 years at least, based on its most recent capacity planning forecast.

In addition to increasing solar capacity and battery energy storage, Ewec will also require additional thermal capacity to address an expected 30 per cent increase in gross power peak demand, from 16.7GW in 2022 to 21.6GW in 2029.

This is due to the scheduled expiry between 2025 and 2029 of offtake contracts for four integrated water and power plants with a combined power generation capacity of over 7,000MW.

While Ewec is considering a combination of either new-build, contract-extension or reconfiguration of existing assets to address the expiring capacity, it is understood to have decided to initiate the procurement of two gas-fired plants sooner rather than later.

In its latest capacity planning statement, Ewec said: “The otherwise consistent increase in peak and total energy demand from 2022 is impacted, on the one hand, by a reduction in exports to Sharjah Electricity & Water Authority (Sewa) over 2022- 2023 due to the commissioning of their new power plant, while being offset, on the other, by the addition of new Abu Dhabi National Oil Company (Adnoc) Offshore demand from 2026.”

While Dubai has not published a similar long-term capacity procurement plan, Dewa has indicated plans for multiple solar PV projects, each with a capacity of 300MW, between 2025 and 2030. 

The emirate also launched the Dubai Economic Agenda 2033 (D33) in January. The plan aspires to generate up to AED32tn ($8.7tn) over the next 10 years and double the size of Dubai’s economy, which will inevitably drive gross power peak demand over the next decade.

This creates an opportunity mainly for renewable energy developers and contractors, given that the emirate does not plan to procure additional thermal power plants in the future.

While an initial plan to build a 500MW solar power plant in the northern emirates has been scuppered, small to medium captive or distributed solar facilities present opportunities in those regions.

Sharjah National Oil Company (SNOC) and Emerge, a joint venture of France’s EDF and Masdar, have agreed to develop a 60MW solar PV project at SNOC’s Sajaa gas complex.

The plant will supply power to SNOC’s operations and be connected to the main power grid. Under the agreement, any excess solar power generated from the plant will be taken by the state utility, Sharjah Electricity & Water Authority (Sewa),  which will provide the required power for SNOC operations at night.

Photo: Noor Abu Dhabi

https://image.digitalinsightresearch.in/uploads/NewsArticle/11199493/main.jpg
Jennifer Aguinaldo
Related Articles
  • Local firm wins contract for Kuwait power project

    19 November 2025

    Local firm Alghanim International has won a contract to provide engineering services at the Subiya power and water distillation plant.

    Kuwait’s Central Agency for Public Tenders approved the award following a request from the Ministry of Electricity, Water & Renewable Energy.

    The contract, valued at $286m, covers engineering, supply, installation, operation and maintenance services to convert the 250MW second phase of the plant’s open-cycle gas turbines to combined-cycle gas turbines.

    The upgrade is intended to increase efficiency and provide additional generation capacity during periods of high demand.

    In July, MEED reported that Alghanim had submitted the lowest bid for the tender ahead of local firms Al-Daw Engineering General Trading & Contracting and Al-Zain United General Trading & Contracting.

    In 2024, US-based GE Vernova completed separate upgrades of four GE Vernova 9F.03 class gas turbines at the 2GW Sabiya combined-cycle power plant. Alghanim International acted as GE’s local engineering partner for that work.

    The Subiya power and water distillation plant is the largest power and water plant in Kuwait, with a power generation capacity of 7,046.7MW, accounting for 35% of the country’s installed capacity.

    It has a water desalination capacity of 100 million imperial gallons a day.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15116135/main.jpg
    Mark Dowdall
  • UKEF issues $3.5bn interest letter for Al-Maktoum airport

    19 November 2025

    Register for MEED’s 14-day trial access 

    The UK’s export credit agency UK Export Finance (UKEF) has issued a $3.5bn expression of interest letter to support the participation of UK businesses in the $35bn expansion of Al-Maktoum International airport, which is also known as Dubai World Central (DWC).

    Chris Bryant, UK minister for trade, handed the letter to Khalifa Al-Zaffin, executive chairman of Dubai Aviation City Corporation and Dubai Aviation Engineering Projects (DAEP), and Paul Griffiths, CEO of Dubai Airports.

    Letters of interest from UKEF, although not binding commitments, help ensure that UK exporters are given every opportunity to bid for contracts on a project. This is typically achieved by providing financial solutions in exchange for an agreed level of UK content used on the project.  

    Previous letter

    It is not the first time UKEF has issued a letter of interest for the expansion of Al-Maktoum International airport. In 2014, it issued a $2bn letter of interest. In a statement at the time, UKEF said five prime UK-based contractors were being supported, along with UK suppliers across the supply chain.

    The five prime contractors were Carillion, Kier, Balfour Beatty, Laing O’Rourke and Interserve. Of those five companies, Carillion entered liquidation in 2018 and Interserve entered administration in 2019. Balfour Beatty sold its shareholding in Dubai-based Dutco Balfour Beatty in 2017.

    Although some progress was made on the project after the UKEF offer in 2014, the scheme stalled and was revived again in April 2024, when Dubai approved new designs for the airport.

    Project progress

    Since then, the project client, DAEP, has been awarding and tendering contracts for the first construction packages. It has awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works for the terminal building are being undertaken by Abu Dhabi-based Tristar E&C.

    DAEP is also close to formally awarding a contract for the substructure works for the West Terminal and Concourse One, Concourse Two and Concourse Three.

    Tendering is also ongoing for an automated people-mover (APM) system. The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.

    The airport’s construction is planned to be undertaken in three phases. Construction works on the project’s first phase are expected to be completed by 2032.

    The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.

    Dubai has said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.


    This aviation package also includes:

    > Middle East invests in giant airports
    > Broader region upgrades its airports
    > Global air travel shifts east

     

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15115788/main.jpg
    Colin Foreman
  • Riyadh gives Expo infrastructure bidders more time

    19 November 2025

     

    Saudi Arabia’s Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, has extended the deadline for firms to submit commercial offers for the contract to undertake the initial infrastructure works at the site to 23 November.

    ERC had initially set deadlines of 26 October and 9 November for the submission of technical and commercial bids, respectively.

    The tender for the project’s initial infrastructure works was issued in September, as MEED reported.

    In October, MEED revealed that 16 firms had been invited to bid for the contract to undertake the initial infrastructure works at the Expo 2030 Riyadh site.

    The firms invited to bid include:

    • Shibh Al-Jazira Contracting (local)
    • Hassan Allam Construction (Egypt)
    • El-Seif Engineering Contracting (local)
    • Al-Ayuni Investment & Contracting (local)
    • Kolin Construction (Turkiye)
    • Al-Yamama Trading & Contracting Company (local)
    • Saudi Pan Kingdom (local)
    • Unimac (local)
    • Mapa Insaat (Turkiye)
    • Yuksel Insaat (Turkiye)
    • IC Ictas / Al-Rashid Trading & Contracting (Turkiye/local)
    • Mota-Engil / Albawani (Portugal/local)
    • Almabani / FCC Construction (local/Spain)

    The overall infrastructure works – covering the construction of the main utilities and civil works at Expo 2030 Riyadh – will be split into three packages:

    • Lot 1 covers the main utilities corridor
    • Lot 2 includes the northern cluster of the nature corridor
    • Lot 3 comprises the southern cluster of the nature corridor

    MEED previously reported that ERC was expected to issue the tender for some of the infrastructure packages in September.

    In July, US-based engineering firm Bechtel Corporation announced it had won the project management consultancy deal for the delivery of the Expo 2030 Riyadh masterplan construction works.

    The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, providing direct access to various landmarks within Riyadh.

    Countries participating in Expo 2030 Riyadh will have the option to construct permanent pavilions. This initiative is expected to create opportunities for business and investment growth in the region.

    The expo is forecast to attract more than 40 million visitors.

    The Public Investment Fund (PIF), Saudi Arabia’s sovereign wealth vehicle, launched ERC in June as a wholly owned subsidiary to build and operate facilities for Expo 2030.

    In a statement, the PIF said: “During its construction phases, Expo 2030 Riyadh and its legacy are projected to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs. Once operational, it is expected to contribute approximately $5.6bn to GDP.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15115697/main.jpg
    Yasir Iqbal
  • NHC and Turkish firm sign $266m investment deal

    19 November 2025

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s National Housing Company (NHC) has signed an investment agreement worth over SR1bn ($266m) with Turkiye’s Emlak Konut to develop new residential communities within the Mecca Gate project in Mecca.

    The agreement was signed on the sidelines of the Cityscape Global 2025 event in Riyadh.

    Emlak Konut will develop 1,000 residential villas spanning over 255,000 square metres (sq m).

    The latest agreement follows the NHC’s signing of deals worth over SR8.5bn ($2.2bn) for the development of two mixed-use and residential communities in Riyadh.

    The first agreement, worth over SR5.2bn ($1.4bn), was signed with local developer Retal Urban Development Company.

    The deal encompasses the development of 4,839 residential units in the Al-Fursan suburb of Riyadh.

    The other contract, worth over SR3.3bn ($880m), was signed with a joint venture of Egypt’s Hassan Allam Holding and local developer Tilal Real Estate for a mixed-use project in the Khozam district.

    The development will cover an area of over 228,000 sq m.

    It will be delivered through Grova Developments, the development arm of Hassan Allam Holding.

    In 2023, NHC and Saudi Arabia’s Housing Ministry signed investment agreements totalling more than SR24bn ($6.4bn) to launch the Al-Fursan residential project.

    Al‑Fursan is described as the largest scheme in terms of area and number of housing units that NHC is implementing in partnership with other real estate developers. 

    MEED reported in 2020 that Riyadh planned to oversee the development of more than 1 million homes by 2025 to meet growing demand in the kingdom.

    By 2030, the Saudi capital aims to more than double its population, from 7-8 million to 15-20 million, and become one of the 10 wealthiest cities in the world.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15115626/main.png
    Yasir Iqbal
  • Egypt announces oil discovery in Western Desert

    19 November 2025

    Register for MEED’s 14-day trial access 

    A new gas discovery has been made in Egypt’s Western Desert region, according to a statement released by the Ministry of Petroleum & Mineral Resources.

    The discovery was made by Khalda Petroleum Company, a joint venture of state-owned Egyptian General Petroleum Corporation (EGPC) and US-headquartered Apache Corporation.

    The field is expected to be brought online this week, according to the ministry.

    The reserves were discovered after drilling the exploratory well ‘Gomana-1’, the ministry said.

    It added that sensors confirmed the presence of gas reserves, and tests indicated that the well is expected to have a production rate of around 36 million standard cubic feet of gas a day.

    Further tests are ongoing, and the initial evaluation of the well’s reserves is currently being finalised.

    The ministry said that the discovery followed the introduction of new incentives designed to encourage additional gas investment within Khalda’s areas of operation.

    Earlier this month, Egypt started gas production from the West Burullus field in the Mediterranean Sea, after connecting the first wells to the national gas grid.

    The country is currently pushing to increase domestic gas production in order to meet domestic demand and reduce its import bill.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15112551/main.png
    Wil Crisp