UAE begins massive reverse osmosis buildup

11 April 2023

This package on the UAE's water sector also includes:

Dewa extends Hassyan IWP bid deadline

Adnoc resumes Project Wave negotiations

Sharjah issues first independent water tender

Ewec rules out solar in desalination projects

French/local team wins contract to build Mirfa 2 IWP

Adnoc selects Cobra-led team for PPP project


State utilities in the UAE are seeking to increase the share of seawater reverse osmosis (SWRO) technology in the overall capacity of their desalination plants in line with their carbon emission reduction targets and the UAE’s net-zero by 2050 goal.

This will end the domination of water production capacity by thermal desalination plants over the past decades.

The demand for additional SWRO capacity is especially evident in Abu Dhabi, where nearly half of the existing water desalination capacity will come out of contract between 2025 and 2029.

The power- and water-purchase agreements (P/WPA) for four major utility plants in Abu Dhabi, with a total combined water desalination capacity of 441 million imperial gallons a day (MIGD), will expire during this period.

Unlike the thermal power plant components of these independent water and power projects (IWPPs), which are subject to extension negotiations, the state utility Emirates Water & Electricity Company (Ewec) is inclined to dismantle all thermal desalination plants associated with these assets – or convert them into SWRO plants – upon the expiry of their contracts. This strategy aligns with its goal to halve its carbon emissions.

Over the next two to four years, Ewec envisages putting 290MIGD of SWRO capacity in place. This is in addition to the Taweelah SWRO plant’s remaining 100MIGD of capacity that is yet to enter commercial operation. Once this plant is at full capacity, it will plug in the capacity from Taweelah A2, the emirate’s first thermal IWPP, which was mothballed in 2021.

Recent SWRO projects in Abu Dhabi include the 120MIGD Mirfa 2 independent water producer (IWP) project, which France’s Engie is developing; the 70MIGD Shuweihat 4 IWPHudayriat and Saadiyat islands, which will each have a capacity of 50MIGD.

RELATED READ: Mirfa 2 award sends positive market signal

Both Mirfa 2 and Shuweihat 4 have a target commercial operation date of 2025, while the two Abu Dhabi Islands IWP projects are expected to provide replacement capacity for the Sas al-Nakhl plant, whose contract expires in 2027.

Longer term, Ewec will need to procure 494MIGD of SWRO capacity by 2036, under the base-case scenario of its 2023-29 Statement of Future Capacity Requirements.

Demand fluctuations

Demand for desalinated water in Abu Dhabi over the short term is anticipated to decrease from just under 800MIGD in 2022 to 764MIGD this year. This is due to reduced exports to Etihad Water & Electricity (Ewe), which is commissioning its first 150MIGD IWP in Umm al-Quwain.

Demand is expected to grow slowly between 2023 and 2029, when it is projected to reach 805MIGD. This is just slightly higher than in 2022, primarily due to recycled water replacing desalinated water as the dominant irrigation supply source.

In Dubai, the procurement process is under way for the 120MIGD Hassyan IWP. The contract for the emirate’s first IWP was tendered before and awarded in 2020, but the project stalled and Dewa relaunched the tender in 2022.

Four teams led by Engie, Saudi Arabia’s Acwa Power, Spain/South Korea’s GS Inima and Metito are understood to be among those qualified to bid for the contract.

The project has a planned capacity of 120MIGD, with an alternative proposal for an aggregate capacity of 180MIGD. Dewa expects to commission it in phases between 2025 and 2026.

The facility is part of Dewa’s plan to increase its water desalination production capacity from 490MIGD to 750MIGD by 2030. By this time, it envisages RO to account for 41 per cent of its overall desalination capacity, in support of Dubai’s 2050 Clean Energy Strategy.

Northern emirates

As previously stated, the Northern Emirates’ first 150MIGD IWP in Umm al-Quwain is undergoing commissioning. This frees up capacity for Abu Dhabi, which has been exporting both water and electricity to the smaller northern UAE emirates.

In early April, Sharjah Electricity & Water Authority also issued the request for proposals for the contract to develop Sharjah’s first IWP. Located next to an existing desalination plant in Hamriyah, the planned IWP will have a capacity of 90MIGD.

UAE power sector shapes up ahead of Cop28

Other projects

Abu Dhabi Sewerage Services Company is evaluating proposals received earlier this year for a contract to design and build a treated sewage effluent (TSE) polishing plant in Al-Wathba

The plant is expected to have a design capacity of 700,000 cubic metres a day (cm/d), with the potential to expand this capacity to 950,000 cm/d in a subsequent phase. The TSE facility will produce water for higher-end applications than the TSE produced at standard sewage treatment plants.

The largest individual projects within the sector are the two seawater treatment plants, frequently called Project Wave, being procured by Abu Dhabi National Oil Company (Adnoc).

The Mirfa and Al-Nouf nanofiltration plants and their associated utilities have budgets of between $2bn and $2.5bn each. The Mirfa package is in the advanced procurement stage, with negotiations continuing between Adnoc and the shortlisted bidders as this article is published. 


This month's special report on the UAE also includes: 

> UAE power sector shapes up ahead of Cop28

> Strategic Adnoc projects register notable progress

> UAE lenders chart a route to growth

https://image.digitalinsightresearch.in/uploads/NewsArticle/10745652/main.gif
Jennifer Aguinaldo
Related Articles
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall
  • Qatar receives bids for major power grid expansion

    24 August 2026

     

    Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.

    The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.

    It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    According to sources, bids were submitted for the following packages on 20 August:

    • Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
    • Package S3, covering new 66/11kV substations ($50m)
    • Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
    • Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
    • Cable packages C1 and C2, covering 400kV cables ($100m)

    Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.

    In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.

    The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.

    Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.

    Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg
    Mark Dowdall
  • Maaden closes $1bn term loan and credit facility

    24 August 2026

    Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.

    The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.

    The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.

    The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.

    ALSO READ: Maaden and Aramco sign deal to create joint venture

    “The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.

    “The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.

    “Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg
    Indrajit Sen
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp