UAE begins massive reverse osmosis buildup
11 April 2023
This package on the UAE's water sector also includes:
> Dewa extends Hassyan IWP bid deadline
> Adnoc resumes Project Wave negotiations
> Sharjah issues first independent water tender
> Ewec rules out solar in desalination projects
> French/local team wins contract to build Mirfa 2 IWP
> Adnoc selects Cobra-led team for PPP project
State utilities in the UAE are seeking to increase the share of seawater reverse osmosis (SWRO) technology in the overall capacity of their desalination plants in line with their carbon emission reduction targets and the UAE’s net-zero by 2050 goal.
This will end the domination of water production capacity by thermal desalination plants over the past decades.
The demand for additional SWRO capacity is especially evident in Abu Dhabi, where nearly half of the existing water desalination capacity will come out of contract between 2025 and 2029.
The power- and water-purchase agreements (P/WPA) for four major utility plants in Abu Dhabi, with a total combined water desalination capacity of 441 million imperial gallons a day (MIGD), will expire during this period.
Unlike the thermal power plant components of these independent water and power projects (IWPPs), which are subject to extension negotiations, the state utility Emirates Water & Electricity Company (Ewec) is inclined to dismantle all thermal desalination plants associated with these assets – or convert them into SWRO plants – upon the expiry of their contracts. This strategy aligns with its goal to halve its carbon emissions.
Over the next two to four years, Ewec envisages putting 290MIGD of SWRO capacity in place. This is in addition to the Taweelah SWRO plant’s remaining 100MIGD of capacity that is yet to enter commercial operation. Once this plant is at full capacity, it will plug in the capacity from Taweelah A2, the emirate’s first thermal IWPP, which was mothballed in 2021.
Recent SWRO projects in Abu Dhabi include the 120MIGD Mirfa 2 independent water producer (IWP) project, which France’s Engie is developing; the 70MIGD Shuweihat 4 IWPHudayriat and Saadiyat islands, which will each have a capacity of 50MIGD.
RELATED READ: Mirfa 2 award sends positive market signal
Both Mirfa 2 and Shuweihat 4 have a target commercial operation date of 2025, while the two Abu Dhabi Islands IWP projects are expected to provide replacement capacity for the Sas al-Nakhl plant, whose contract expires in 2027.
Longer term, Ewec will need to procure 494MIGD of SWRO capacity by 2036, under the base-case scenario of its 2023-29 Statement of Future Capacity Requirements.
Demand fluctuations
Demand for desalinated water in Abu Dhabi over the short term is anticipated to decrease from just under 800MIGD in 2022 to 764MIGD this year. This is due to reduced exports to Etihad Water & Electricity (Ewe), which is commissioning its first 150MIGD IWP in Umm al-Quwain.
Demand is expected to grow slowly between 2023 and 2029, when it is projected to reach 805MIGD. This is just slightly higher than in 2022, primarily due to recycled water replacing desalinated water as the dominant irrigation supply source.
In Dubai, the procurement process is under way for the 120MIGD Hassyan IWP. The contract for the emirate’s first IWP was tendered before and awarded in 2020, but the project stalled and Dewa relaunched the tender in 2022.
Four teams led by Engie, Saudi Arabia’s Acwa Power, Spain/South Korea’s GS Inima and Metito are understood to be among those qualified to bid for the contract.
The project has a planned capacity of 120MIGD, with an alternative proposal for an aggregate capacity of 180MIGD. Dewa expects to commission it in phases between 2025 and 2026.
The facility is part of Dewa’s plan to increase its water desalination production capacity from 490MIGD to 750MIGD by 2030. By this time, it envisages RO to account for 41 per cent of its overall desalination capacity, in support of Dubai’s 2050 Clean Energy Strategy.
Northern emirates
As previously stated, the Northern Emirates’ first 150MIGD IWP in Umm al-Quwain is undergoing commissioning. This frees up capacity for Abu Dhabi, which has been exporting both water and electricity to the smaller northern UAE emirates.
In early April, Sharjah Electricity & Water Authority also issued the request for proposals for the contract to develop Sharjah’s first IWP. Located next to an existing desalination plant in Hamriyah, the planned IWP will have a capacity of 90MIGD.
UAE power sector shapes up ahead of Cop28
Other projects
Abu Dhabi Sewerage Services Company is evaluating proposals received earlier this year for a contract to design and build a treated sewage effluent (TSE) polishing plant in Al-Wathba.
The plant is expected to have a design capacity of 700,000 cubic metres a day (cm/d), with the potential to expand this capacity to 950,000 cm/d in a subsequent phase. The TSE facility will produce water for higher-end applications than the TSE produced at standard sewage treatment plants.
The largest individual projects within the sector are the two seawater treatment plants, frequently called Project Wave, being procured by Abu Dhabi National Oil Company (Adnoc).
The Mirfa and Al-Nouf nanofiltration plants and their associated utilities have budgets of between $2bn and $2.5bn each. The Mirfa package is in the advanced procurement stage, with negotiations continuing between Adnoc and the shortlisted bidders as this article is published.
This month's special report on the UAE also includes:
> UAE power sector shapes up ahead of Cop28
> Strategic Adnoc projects register notable progress
> UAE lenders chart a route to growth
Exclusive from Meed
-
-
Algeria tenders upstream oil project contract25 June 2026
-
-
-
Chinese firm wins $265m Saudi hospital contract24 June 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Firms prepare Hudayriat East PPP tunnels advisory bids25 June 2026

Abu Dhabi’s Modon Infrastructure, formerly Gridora, has tendered a contract for technical advisory services for the construction of two underwater tunnels connecting the eastern side of Hudayriat Island with mainland Abu Dhabi.
Consultants have until 26 June to submit their proposals.
The project includes the construction of a 4.8-kilometre (km) highway, with four lanes in each direction, connecting Hudayriat Island to Mussafah 8th Street.
The project will be delivered on a public-private partnership (PPP) basis in coordination with the Abu Dhabi Department of Municipalities and Transport and the Abu Dhabi Investment Office.
The contract term is expected to be 25 years.
The latest infrastructure development in Abu Dhabi follows Modon Infrastructure’s invitation in May for firms to register for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will also be developed on a PPP basis.
Modon Infrastructure will act as the lead developer, holding the majority equity stake in the project company. It will award the engineering, procurement and construction contract, as well as the operations and maintenance services and advisory appointments.
The second phase of the MIPP involves the construction of about 11km of highways, including a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.
The scope also covers the construction of three interchanges: the E20, E10 and Dumbbell interchanges on Al-Sammaliyyah Island.
The project includes several major structures, such as the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange with cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.
Further key elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover (open) tunnel on Bilrimaid Island. The project will be completed with another tunnel connecting Bilrimaid Island to Um-Yifeenah Island.
> Be recognised among the best in the industry at the MEED Projects Awards 2026 …
https://image.digitalinsightresearch.in/uploads/NewsArticle/17410214/main.jpg -
Algeria tenders upstream oil project contract25 June 2026
Algeria’s state-owned national oil and gas company, Sonatrach, has tendered a contract for the development and rehabilitation of the central processing facility (CPF) at the Bir Berkine oil and gas field.
The scope of the contract includes the study, supply, construction and commissioning of a project to rehabilitate the CPF facilities at the field, which is located in the Hassi Mesaoud region.
Sonatrach says in the tender documents that the objective of the project is to ensure the continuity of production activities “under stable and secure operating conditions”.
It also says the project aims to improve production yields and quality.
The contract includes both initial and detailed studies as well as the supply of all equipment and materials.
It also includes the execution of works, the assembly of all equipment and materials, and the commissioning of all relevant facilities.
The tender has a two-stage submission process, with the first stage requiring technical bids to be submitted by 23 August.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17423013/main3916.jpg -
Red Sea Global tenders King Salman Bay construction work25 June 2026

Saudi gigaproject developer Red Sea Global (RSG) has tendered a contract inviting firms to undertake marine infrastructure works at King Salman Bay on the Red Sea coast, north of Jeddah.
The scope includes dredging and earthworks, as well as quay wall and edge protection works spanning about 11 kilometres.
The bid submission deadline is 31 July.
King Salman Bay is expected to be a waterfront development aimed at reshaping the city’s northern Red Sea frontage into a mixed-use destination, anchored by public-realm improvements and leisure-led development.
The update follows RSG’s award of an estimated SR100m ($27m) contract to construct a solid waste management centre at its Red Sea Project. The scope includes four buildings: a material recycling facility, a transfer station, an administration building and a vehicle maintenance building.
In October last year, MEED reported that RSG had secured a SR6.5bn ($1.7bn) credit facility to further develop Amaala, its luxury tourism destination on Saudi Arabia’s northwestern Red Sea coast.
According to an official statement, “The funding is led by Riyad Bank as the sole underwriter, along with Saudi Investment Bank and Bank Al-Bilad as mandated lead arrangers.
“The loan arrangement comprises a mix of conventional and Islamic financing and adheres to RSG’s Green Loan Framework, which was first established when it secured private funding from a consortium of four banks for the Red Sea destination in 2021,” the statement added.
The announcement followed RSG’s opening of its first properties for sale at Amaala, including branded residential communities and a five-bedroom villa on a private island.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17430045/main.jpg -
MECC submits lowest bid on three Kuwaiti oil and gas contracts25 June 2026

Kuwait-based Mechanical Engineering & Contracting Company (MECC) has submitted the lowest bid across three separate contracts tendered by the state-owned upstream operator Kuwait Oil Company (KOC).
The total value of the low bids is $427m, and all of the contracts are focused on developing substations to power industrial lift pumps and remote header manifolds
Five companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 6, 10 and 12 in southern and eastern Kuwait.
The bidders were:
- MECC: KD65,760,000 ($212m)
- Heavy Engineering Industries & Shipbuilding Company: KD70,630,000 ($228m)
- Amco Engineering & Construction: KD73,446,100 ($237m)
- Combined Group Contracting Company: KD76,186,000 ($246m)
- Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD79,332,417 ($256m)
Six companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 8 and 13 in southern and eastern Kuwait.
The bidders were:
- MECC: KD30,760,000 ($99m)
- Badr Al-Mulla & Brothers: KD32,662,040 ($106m)
- Heavy Engineering Industries & Shipbuilding Company: KD34,139,000 ($110m)
- Industrial Company for Electrical Projects: KD36,375,520 ($118m)
- Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD37,278,526 ($120m)
- Combined Group Contracting Company: KD37,790,000 ($122m)
Eight companies submitted bids for a contract focused on developing several substations to power industrial lift pumps and remote header manifolds in areas 7, 9, and 11 in southern and eastern Kuwait.
The bidders were:
- MECC: KD35,760,000 ($116m)
- Badr Al-Mulla & Brothers: KD39,447,165 ($127m)
- Amco Engineering & Construction: KD39,736,800 ($128m)
- Heavy Engineering Industries & Shipbuilding Company: KD40,105,000 ($130m)
- Industrial Company for Electrical Projects: KD43,238,265 ($140m)
- Engineering Company for Petroleum & Chemical Industries (Enppi): KD43,514,805 ($141m)
- Combined Group Contracting Company: KD43,650,000 ($141m)
- Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD43,706,826 ($141m)
Kuwait’s oil and gas sector has been in crisis in recent months due to disruption from the regional conflict that started after the US and Israel attacked Iran on 28 February 2026.
A preliminary peace agreement between the US and Iran, which was announced on 14 June, has increased optimism that disruption to the sector will decrease in the coming weeks.
Under the terms of the agreement, both sides have stated that the free flow of vessels will be permitted through the Strait of Hormuz, through which nearly all of Kuwait’s crude oil is normally exported.
READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDFGCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.
Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:
> AGENDA: Gulf races to reroute trade> EXPORT ROUTES: Regional war boosts oil and gas pipeline project activity> CURRENT AFFAIRS: UAE’s Opec departure fulfils multiple ends> MEED TOP 100: Middle East stocks recover unevenly> LEADERSHIP: Building the infrastructure that makes net zero possible> TRADE DEAL: UK-GCC trade deal talks concludeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17423009/main.jpg -
Chinese firm wins $265m Saudi hospital contract24 June 2026
Zhejiang Construction International, the local subsidiary of Chinese contractor Zhejiang Construction Investment Group, has won a $265m contract to build the Prince Mohammed Bin Fahd University Speciality Hospital in Al-Khobar.
Construction is expected to take three years from the start date.
Prince Mohammed Bin Fahd University awarded the contract.
Located in Al-Raja district, Al-Khobar, in Saudi Arabia’s Eastern Province, the hospital project will cover about 60,000 square metres.
The contract covers the construction of a 10-storey hospital building, two five-storey auxiliary buildings connected by corridors and a basement.
Work will include civil works, mechanical and electrical installation, curtain walling, landscaping, detailed design and the procurement of medical equipment.
The award is the latest in a series of contracts secured by Chinese contractors from Saudi entities in recent months.
Last week, MEED reported that Saudi Arabia’s Ministry of Municipalities & Housing awarded contracts worth more than SR1.9bn ($506m) to Chinese contractors for two residential developments in the kingdom.
China Architectural Construction Corporation won the first contract, valued at SR875m ($233m), to build 2,010 housing units at the Al-Ruba residential project in Riyadh.
China State Construction Engineering Corporation secured the other contract, valued at more than SR1bn ($266m), for the Al-Rasha Al-Faisaliah residential project in Dammam, comprising 2,426 housing units.
GlobalData expects Saudi Arabia’s construction industry to record average annual growth of 5.2% in 2025-28, supported by investments in transport, electricity, housing and tourism infrastructure, as well as the $850bn-plus gigaprojects programme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17412846/main.jpg

