Two set to bid for Aramco sulphur recovery units

28 April 2023

 

Two teams are understood to be preparing to submit proposals on 30 April for the contract to modify sulphur recovery units (SRUs) at Saudi Aramco’s key gas processing plants.

Aramco issued the main tender for the large downstream tail-gas treatment (TGT) facility in May last year, as MEED reported.

According to industry sources, the teams expected to bid for the contract are:

  • Vision Invest (Saudi Arabia) / Larsen & Toubro (India)
  • Lamar Holding (Saudi Arabia) / Hyundai Engineering (South Korea) / Korea Overseas Infrastructure & Urban Development Corporation (South Korea) / Enerflex (Canada)

Aramco expects third-party investments of up to $2bn in the desulphurisation programme, which entails building a large downstream tail-gas treatment (TGT) facility to collect and process tail gas discharged from SRUs at identified gas plants.

The facility is to be developed either on a build, own and operate (BOO) or build-own-operate-transfer (BOOT) basis. This will make it one of Aramco’s initial public-private partnership (PPP) exercises in its main oil and gas business, if not the first.

SO2 reduction campaign

The Aramco programme is in line with the regulations for emissions to air from stationary sources set out by Saudi Arabia’s Environment, Water & Agriculture Ministry. These stipulate that sulphur dioxide (SO2) emissions from stationary sources must not exceed 250 parts per million volume (dry and 0 per cent oxygen basis). They must also comply with the SO2 ambient emission limits or ground-level SO2 concentration.

The rollout of the desulphurisation scheme stems from Aramco’s goal to achieve net-zero carbon emissions by 2050 and is part of its environmental, social and governance initiatives, sources previously said.

Seven gas plants in Saudi Arabia’s Eastern Province have been identified from which tail gas needs to be treated for up to 99.9 per cent SO2 removal:

  • Berri
  • Haradh
  • Hawiyah
  • Khursaniyah
  • Shedgum
  • Uthmaniyah
  • Wasit

The scope of the scheme has been split into two packages, one source said. The first package covers gas plants in Aramco’s Zone 1 – Berri, Khursaniyah and Wasit – while the second package relates to units in Zone 2 – Haradh, Hawiyah, Shedgum and Uthmaniyah.

Along with fully financing the project, the developer will need to adopt one of the following commercial desulphurisation technologies approved by Aramco for the scheme:

  • TGT reduction absorption
  • Ammonia-based desulphurisation
  • Dry sorbent injection
  • Flue gas desulphurisation using gypsum

According to Aramco, the project will cover “the end-to-end application of the approved technologies, including but not limited to required plot space, utilities, market analysis and logistics of feedstock and byproduct, contractual arrangements, risks associated with each technology related to safety, process reliability and SO2 emissions compliance on a continuous basis”.

Aramco expects the common TGT facility to be operational by 2027.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10799701/main.jpg
Jennifer Aguinaldo
Related Articles
  • What actually slows a gigaproject down

    9 September 2026

     

    Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.

    “None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.

    For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.

    “The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.

    The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.

    “Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”

    Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.

    Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.

    Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.

    “The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”

    Integration needs to be well understood

    “Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.

    Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.

    Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.

    “The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”

    That shared view, he argues, will be what the next phase of Gulf delivery is judged on.

    Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.

    “This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.

    From reporting progress to managing risk before it lands

    Digital tools have a role here, Caldwell says, but not as a headline in themselves.

    Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.

    “The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."

    None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”

    Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.

    With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.

    “The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.

    What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.

    “The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif
    Yasir Iqbal
  • Jordan tenders advisory for wastewater treatment plant

    9 September 2026

    The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.

    The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).

    The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.

    The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.

    The submission deadline is 21 September.

    The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.

    The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.

    The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.

    WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.

    The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.

    The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg
    Mark Dowdall
  • Medina’s KEC signs real estate project development deal

    9 September 2026

    Medina’s Knowledge Economic City (KEC) has signed an agreement with Riyadh-based Kaden Investment Company to develop a mixed-use project in Medina.

    The project will have an estimated gross floor area of about 230,000 square metres (sq m).

    According to a statement filed by KEC with the Saudi Exchange (Tadawul), the project – called Multaqa Al-Madinah 2 – will be built on a 92,000 sq m plot located directly north of the first phase of the Multaqa Al-Madinah development.

    It is expected to include about 1,527 residential units across three residential zones, along with commercial and office space totalling about 31,108 sq m of net leasable area.

    It will also feature parking, recreational and service facilities, landscaping and other supporting infrastructure.

    KEC and Kaden intend to deliver the project through a closed-ended real estate investment fund regulated by Saudi Arabia’s Capital Market Authority.

    Under the proposed structure, KEC will contribute the land as an in-kind contribution and hold 75% of the fund units, while Kaden will contribute cash and hold the remaining 25%.

    Kaden will also serve as the development manager.

    KEC said the land has been initially valued at about SR692.3m ($184.6m), while the total equity required for the project is estimated at around SR833m.

    Once final agreements are signed, KEC expects to receive SR67.7m in cash and fund units valued at approximately SR624.6m.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19492407/main.png
    Yasir Iqbal
  • Morocco signs agreement for synthetic fuel complex

    9 September 2026

    Switzerland-based Synhelion has signed an agreement with the Government of Morocco with the aim of developing a large-scale commercial synthetic fuel plant in the country’s southern Tan-Tan province.

    The memorandum of understanding (MoU) relates to a facility with the capacity to produce 100,000 tonnes a year of fuel, according to a statement released by the company.

    Synhelion has secured land for the project site and established a subsidiary in Morocco to develop the fuel complex.

    Gianluca Ambrosetti, one of Synhelion’s co-chief executives, said: “Morocco’s exceptional renewable energy resources and its clear industrial strategy make it an ideal location for scaling our synthetic fuel technology.

    “With the MoU signed, the land reservation secured and our branch in place, we are moving from evaluation to execution and toward our first commercial-scale plant in the region.”

    Synhelion specialises in producing hydrocarbon fuels using renewable energy. Its products include synthetic jet fuel, gasoline and diesel.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19489903/main.jpg
    Wil Crisp
  • Iraq solar package on track to come online in December

    9 September 2026

     

    The 1,000MW solar photovoltaic project in Artawi – also called Ratawi – in southern Iraq is on track for its second phase to come online on 8 December, according to industry sources.

    This phase has a capacity of 250MW and will bring the project’s total online capacity to 500MW.

    The first phase of the project, also with a capacity of 250MW, came online in March this year.

    The third and fourth phases, each with a capacity of 250MW, are expected to be brought online next year.

    The solar project is part of the broader Gas Growth Integrated Project (GGIP), which has an estimated total value of $27bn and a first phase worth an estimated $10bn.

    The solar project’s ownership differs from the headline GGIP ownership structure, with its ownership equally divided between France’s TotalEnergies and QatarEnergy.

    The wider GGIP consortium includes TotalEnergies, Iraq’s Basra Oil Company and QatarEnergy, which hold stakes of 45%, 30% and 25%, respectively.

    China Energy Engineering Corporation is part of a consortium that is executing the main engineering, procurement and construction contract for the project.

    It announced that the first 250MW of capacity had been connected to the grid on 4 March this year.

    The consortium also includes China Energy Engineering Group Tianjin Electric Power Construction Company and Chengdu-headquartered Southwest Electric Power Design Institute Company.

    The project scope includes:

    • Construction of a substation
    • Installation of a 132kV booster station
    • Installation of solar panels
    • Installation of transformers
    • Laying of transmission lines
    • Construction of related infrastructure

    In February 2025, Basra Investment Commission director Alaa Abdul Hussein said the solar plant had an estimated total value of $820m.

    The GGIP programme is focused on developing four major projects in Iraq:

    • The Common Seawater Supply Project (CSSP)
    • The Ratawi gas processing complex
    • The 1GW solar power project for Iraq’s electricity ministry
    • A field development project at Ratawi, known as the Associated Gas Upstream Project (AGUP)

    All four of these projects are currently under execution, though there have been some delays related to the regional war that started when the US and Israel attacked Iran on 28 February.

    The conflict has caused significant disruption to shipping through the Strait of Hormuz, which Iraq uses to export crude oil and import equipment and materials for projects.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19489818/main.jpg
    Wil Crisp