Two set to bid for Aramco sulphur recovery units

28 April 2023

 

Two teams are understood to be preparing to submit proposals on 30 April for the contract to modify sulphur recovery units (SRUs) at Saudi Aramco’s key gas processing plants.

Aramco issued the main tender for the large downstream tail-gas treatment (TGT) facility in May last year, as MEED reported.

According to industry sources, the teams expected to bid for the contract are:

  • Vision Invest (Saudi Arabia) / Larsen & Toubro (India)
  • Lamar Holding (Saudi Arabia) / Hyundai Engineering (South Korea) / Korea Overseas Infrastructure & Urban Development Corporation (South Korea) / Enerflex (Canada)

Aramco expects third-party investments of up to $2bn in the desulphurisation programme, which entails building a large downstream tail-gas treatment (TGT) facility to collect and process tail gas discharged from SRUs at identified gas plants.

The facility is to be developed either on a build, own and operate (BOO) or build-own-operate-transfer (BOOT) basis. This will make it one of Aramco’s initial public-private partnership (PPP) exercises in its main oil and gas business, if not the first.

SO2 reduction campaign

The Aramco programme is in line with the regulations for emissions to air from stationary sources set out by Saudi Arabia’s Environment, Water & Agriculture Ministry. These stipulate that sulphur dioxide (SO2) emissions from stationary sources must not exceed 250 parts per million volume (dry and 0 per cent oxygen basis). They must also comply with the SO2 ambient emission limits or ground-level SO2 concentration.

The rollout of the desulphurisation scheme stems from Aramco’s goal to achieve net-zero carbon emissions by 2050 and is part of its environmental, social and governance initiatives, sources previously said.

Seven gas plants in Saudi Arabia’s Eastern Province have been identified from which tail gas needs to be treated for up to 99.9 per cent SO2 removal:

  • Berri
  • Haradh
  • Hawiyah
  • Khursaniyah
  • Shedgum
  • Uthmaniyah
  • Wasit

The scope of the scheme has been split into two packages, one source said. The first package covers gas plants in Aramco’s Zone 1 – Berri, Khursaniyah and Wasit – while the second package relates to units in Zone 2 – Haradh, Hawiyah, Shedgum and Uthmaniyah.

Along with fully financing the project, the developer will need to adopt one of the following commercial desulphurisation technologies approved by Aramco for the scheme:

  • TGT reduction absorption
  • Ammonia-based desulphurisation
  • Dry sorbent injection
  • Flue gas desulphurisation using gypsum

According to Aramco, the project will cover “the end-to-end application of the approved technologies, including but not limited to required plot space, utilities, market analysis and logistics of feedstock and byproduct, contractual arrangements, risks associated with each technology related to safety, process reliability and SO2 emissions compliance on a continuous basis”.

Aramco expects the common TGT facility to be operational by 2027.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10799701/main.jpg
Jennifer Aguinaldo
Related Articles
  • Iranian drones hit Kuwait International airport’s Terminal 1

    3 June 2026

    Kuwait International airport was struck by a fresh wave of hostile drone attacks on 3 June. The drones caused significant structural damage to Terminal 1 and wounded several individuals.

    Brigadier General Saud Abdulaziz Al-Otaibi, official spokesman for the Ministry of Defence, blamed the strikes on “criminal Iranian aggression”. He confirmed that the injured had been evacuated for medical care and stated that the armed forces remain in a state of complete readiness to secure the state.

    The incident is the third major drone strike on the hub in recent months. On 1 April, a drone strike hit fuel tanks managed by Kuwait Aviation Fuelling Company, sparking massive fires. On March 28, another multi-drone raid severely damaged the airport’s primary radar systems.

    The airport is being expanded with the construction of a new terminal, and works on the project are expected to be completed by 2027. It consists of three packages.

    These are:

    • Package 1: Main works – $4,329m
    • Package 2: Multistorey car park building, connection roads, bridges and landscaping works – $550m
    • Package 3: Aircraft parking, runways and service buildings – $950m

    Turkiye’s Limak Holding is executing the main works.

    The terminal building was designed by Foster+Partners and Gulf Consult.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17089683/main.gif
    Colin Foreman
  • Consortium signs PPA for Taweelah C power plant

    3 June 2026

    Emirates Water & Electricity Company (Ewec) has confirmed it has signed a power-purchase agreement (PPA) with a developer consortium for the Taweelah C independent power producer (IPP) project.

    The agreement, which will run through to 2050, was signed with Abu Dhabi National Energy Company (Taqa), Al-Jomaih Energy & Water Company (Saudi Arabia) and Sembcorp Industries (Singapore), the utility said in a statement.

    Taqa will own a 60% stake in the project, with the international consortium holding 40%. The ADX-listed company will also own 40% of the project’s operations and maintenance company, while the international consortium will own 60%.

    Last month, MEED exclusively revealed that the winning consortium had been selected for the project, with the PPA initially expected to be signed in mid-May.

    It is understood that China Energy Engineering Corporation (CEEC) will be the engineering, procurement and construction contractor.

    The combined-cycle gas turbine plant will have a capacity of about 2.5GW. It will be located at the Al-Taweelah power and desalination complex, about 50 kilometres northeast of Abu Dhabi city.

    Taweelah C is part of Ewec’s wider programme to support the UAE’s Net Zero by 2050 Strategic Initiative and the Abu Dhabi Department of Energy’s Clean Energy Strategic Target 2035.

    Ewec plans to raise solar power capacity to 18GW and wind capacity to 2.6GW by 2035, while reducing the carbon intensity of its power generation by more than half compared with 2019.

    The Taweelah C IPP is now expected to start commercial operations in 2029. The facility had previously been scheduled to begin commercial operations in the fourth quarter of 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17089163/main.jpg
    Mark Dowdall
  • Local contractor wins Oman water transmission contract

    3 June 2026

     

    Local contractor Al-Jesr United has won the main engineering, procurement and construction contract to reinforce Oman’s Sur water transmission system.

    The contract, awarded by state-owned utility Nama Water Services (NWS), forms part of a project to improve the reliability of potable water supply to Sur, a coastal city about 200 kilometres southeast of Muscat.

    The scheme, estimated to cost $80m, is designed to strengthen the network’s resilience during peak-demand periods and emergencies.

    The scope of work includes upgrading the pumps at the Sur DP Pump Station with variable frequency drive units and replacing ductile iron pipes and fittings within the facility. It also covers about 17km of new transmission pipelines.

    According to regional projects tracker MEED Projects, at least five local firms submitted commercial bids for the contract, which was tendered in August 2025.

    These include:

    • Al-Jesr United
    • Al-Rafaa Trading & Contracting
    • Gulf Petrochemical Services & Trading
    • Professionals Trading
    • Sarooj Construction Company

    In June 2024, NWS awarded a $1.3m contract for the project’s design and construction supervision to Muscat-headquartered Ibn Khaldun Almadaen Engineering Consultants.

    Sur is home to one of the sultanate’s key desalination plants, which supplies potable water to communities across eastern Oman. 

    The water transmission project will support network expansion in areas such as Al-Aigah and Ahiae, as the existing ductile iron pipeline serving Wilayat Sur is no longer sufficient to meet current and future demand.

    Construction is expected to start in the third quarter of 2026 and take about two years to complete.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17088454/main.jpg
    Mark Dowdall
  • Syria to tender gas plant contract

    3 June 2026

     

    Syria is preparing to tender a project to rehabilitate the Conoco gas plant in Deir ez-Zor province in the east of the country within the next 10 weeks, according to a document published by the US-Syria Business Council.

    The gas plant was reclaimed by Syria’s military during an offensive in January this year.

    It is Syria’s largest gas plant, but is severely damaged and cannot be operated in its current condition.

    Before the country’s civil war, it processed 13 million cubic metres of gas a day.

    The US-based companies ConocoPhillips and Novaterra signed a memorandum of understanding with the state-owned Syria Petroleum Company (SPC) to restore the facility in November last year.

    Syria is currently in the midst of a push to ramp up oil and gas production and establish itself as a regional energy hub.

    Earlier this year, Yousef Qiblawy, chief executive of SPC, said that his organisation was aiming to double national oil production before 2027 and boost output to 800,000 barrels a day by the end of 2029, not including offshore production.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17088320/main.jpg
    Wil Crisp
  • AD Ports enters South America with $835m Brazil deal

    3 June 2026

    Abu Dhabi-listed AD Ports Group has entered the South American market by agreeing to acquire a majority stake in Corredor Logística e Infraestrutura (CLI), Brazil’s leading independent agri-bulk port terminal operator, for an enterprise value of $835m.

    The transaction represents AD Ports’ largest acquisition to date, surpassing its $720m purchase of Spain’s Noatum in 2023, and its $510m purchase of a 51% stake in Dubai-based Global Feeder Shipping in early 2024.

    Under the terms of the agreement, AD Ports will acquire CLI from joint owners Macquarie Asset Management and IG4 Capital. CLI operates two major agri-bulk export terminals under long-term concessions: CLI Norte at the Port of Itaqui, which is 100% owned by CLI, and CLI Sul at the Port of Santos, which is 80% owned. In 2025, CLI handled 17 million tonnes of cargo, generating $178m in revenue and profits of $98m.

    The deal, expected to close in the second half of 2026, subject to regulatory approvals, aligns with AD Ports’ strategy to expand its agrifood vertical. The group has recently secured similar international assets, including a 30-year concession at Jordan’s Aqaba multipurpose port, a $30m investment in Kazakhstan’s Sarzha Grain Terminal, and a clean bulk facility development at Pakistan’s Karachi Port.

    The acquisition also reflects broader economic ties between the UAE and Brazil, where UAE investments total about $5bn. The UAE is currently negotiating a Comprehensive Economic Partnership Agreement (CEPA) with the Mercosur trading bloc, which includes Brazil.

    The major capital deployment follows a period of significant financial growth and international expansion for the Abu Dhabi operator, which is 75.42% owned by sovereign wealth fund ADQ. AD Ports reported record results for 2025, with revenue rising 20% year-on-year to AED20.77bn ($5.66bn) and net profit increasing 16% to AED2.07bn.

    According to its 2025 annual report, the group plans to invest AED2.45bn in port infrastructure development during 2026 alone, alongside AED1.3bn for liquefied petroleum gas and liquefied natural gas storage terminals between 2026 and 2028. To fund higher-return projects and optimise its balance sheet, AD Ports launched an asset monetisation programme in late 2025 targeting the recycling of AED4.6bn of capital.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17087945/main.jpg
    Colin Foreman