Transport links stitch GCC together

25 November 2024

This package also includes: Cooperation strengthens Gulf markets


Analysis
Colin Foreman
Editor

Transport projects connecting the GCC have made stuttering progress over the years, with brief periods of intense project positioning typically followed by years of little progress. 

These projects are crucial for intra-GCC trade, and, once built, should provide a catalyst for further economic activity.

Since the Al-Ula Accords were signed in January 2021, projects have started to move forwards again, with schemes including the GCC railway network, the GCC grid, and several other road and causeway links at various stages of planning and construction. 

GCC rail

For the GCC railway network, GCC leaders approved the establishment of the GCC Rail Authority in January 2022. The entity is entrusted with overall policymaking and coordination among member states to ensure the smooth delivery and operation of the scheme.

The railway will stretch over 2,177 kilometres (km), from Kuwait, through Dammam in Saudi Arabia, to Bahrain, with a causeway to be constructed between the two countries, and from Dammam to Qatar, Saudi Arabia, the UAE and finally to Muscat via Sohar in Oman.

There will be 684km of track in the UAE, 663km in Saudi Arabia, 306km in Oman, 283km in Qatar, 145km in Kuwait and 36km in Bahrain.

Passenger trains will run at 220 kilometres an hour (km/h), while freight trains will travel at 80-120km/h.

The project is expected to take a significant step forward this year with the award of the contract to prepare the operational plan study for the scheme. Speaking at the Global Rail event in Abu Dhabi on 8 October, sources told MEED that “the evaluation is in the final stages and the contract award is imminent”.

A source added that the General Secretariat of the Cooperation Council has set a deadline of 2030 for the project to be operational.

Several causeways are planned that will provide transport links between countries in the GCC. After stalling after 2010, Qatar and Bahrain have agreed to restart plans to develop the $4bn Qatar-Bahrain Causeway project. The two countries have also instructed the respective authorities to finalise plans for initiating the implementation of the project. The next step will be establishing a technical committee and appointing a consultancy to work on the designs.

The 40km-long causeway will connect the eastern coast of Bahrain to the northern region of Qatar. It will feature a dual two-lane highway and a rail link for the GCC rail network.

Once built, these transport projects should provide a catalyst for further economic activity

Construction on the project was originally scheduled to start in early 2009 after a consortium led by Vinci Construction Grands Projets signed a $3bn design-and-build contract in May 2008.

The consortium also included Qatari Diar Real Estate Investment Company, Germany’s Hochtief, Greece’s Consolidated Contractors Company and Belgium’s Deme Group.

The project was initially designed by France’s Lavigne & Cheron Architects. US-based consultant KBR was appointed as the project management consultant with support from Halcrow, which is now part of US-based Jacobs.

Further crossings

Another planned international crossing is the second causeway between Saudi Arabia and Bahrain. The $3.5bn project, which has been called the King Hamad Causeway project, was moving towards construction in 2021 when it was included in Bahrain’s $30bn Strategic Projects Plan. Since then progress has been slow, and it is understood that the authorities are re-evaluating how the project should move ahead. 

The project involves building a 25km road and rail crossing linking Saudi Arabia and Bahrain. It will follow the same alignment as the existing King Fahd Causeway. It has been earmarked for delivery on a public-private partnership basis. The King Fahd Causeway Authority appointed a consortium to provide transaction advisory services in late 2019.

The $8.9m consultancy agreement was signed with a consortium of Netherlands-headquartered KPMG, US-based Aecom and UK-based CMS. The team was tasked with working on developing the financing model, the required engineering specifications and design, as well as helping with the assessment and selection of the developers.

Canada-based SNC Lavalin and UK-based consultancy firm PwC conducted the project due diligence study in 2017.

The existing King Fahd Causeway is operating at capacity. About 11.5 million cars cross the causeway every year, and the growth has been 6% per annum over the past 10 years.

Another causeway being considered is a link connecting Abu Dhabi and Qatar. The proposed link could provide road and rail access between Qatar and the UAE, bypassing Saudi Arabia, located between the countries. 

The concept has been considered before. There were plans in 2005 that involved building a 40km causeway starting near Sila in Abu Dhabi emirate and extending to the south of Doha.

In the past, there have been difficulties with the route because it runs across Saudi Arabian territorial waters.

Road links

Overland road links have also been built. In 2021, a 725km-long road running through the Empty Quarter from Saudi Arabia to Oman opened. The Saudi section of the highway is 564km long, and the Oman section runs for 161km. The highway provides a link between the two countries bypassing the UAE.  

When it opened, the authorities added that the road would improve trade between Oman and Saudi Arabia and give Oman access to Saudi Arabia’s Red Sea Ports. Likewise, it gives Saudi Arabia access to Oman’s ports on the Arabian Sea. 

 

https://image.digitalinsightresearch.in/uploads/NewsArticle/12995564/main.jpg
Colin Foreman
Related Articles
  • Read the May 2026 MEED Business Review

    30 April 2026

    Download / Subscribe / 14-day trial access

    The regional war – and resulting disruption to oil and gas shipping – has triggered a major global energy security shock that is likely to recalibrate long-term decisions on how energy is produced and consumed.

    The effective closure of the Strait of Hormuz is exposing the vulnerability of Middle East supply chains and pushing import-dependent countries to strengthen energy security by expanding domestic fossil fuels, speeding up nuclear projects, and investing in renewables and storage.

    At the same time, higher prices are encouraging producers unencumbered by reliance on the Strait to boost output.

    Like the oil shocks of the 1970s, the conflict is likely to have lasting effects, reshaping energy policies and partnerships and accelerating diversification away from existing arrangements. Read more here

    The conflict is also undermining the business case for Middle East liquefied natural gas (LNG) projects, as prices rise, demand drops and confidence in the reliability of the region’s suppliers is eroded. 

    May’s market focus is on the UAE, where disruption from the Iran war has challenged every assumption behind the country’s non-oil model.

    This edition also includes our industry report on Gulf capital markets, as well as analysis on the region’s initial public offering market.

    In the latest issue, we explore why regional banks are feeling the strain despite strong buffers; consider why force majeure offers no shield against construction breaches; examine the Public Investment Fund’s 2026-30 strategy and talk to Estelle Brachlianoff, CEO of water infrastructure operator Veolia.   

    We hope our valued subscribers enjoy the May 2026 issue of MEED Business Review

     

    Must-read sections in the May 2026 issue of MEED Business Review include:

    AGENDA: War in the Middle East recalibrates global energy markets

    REGIONAL LNG: War undermines business case for Middle East LNG

    INDUSTRY REPORT:
    Gulf capital markets
    Damage avoidance frames debt issuance
    Regional IPO market dries up amid war

    > INTERVIEW: Desalination holds steady amid tensions, says Veolia CEO

    > LEGAL: Force majeure will not cure pre-existing construction industry breaches  

    > BANKS: GCC banks to feel the strain despite strong buffers

    > PIF STRATEGY: Public Investment Fund approves 2026-30 strategy

    > UAE MARKET FOCUS
    > COMMENT: Conflict tests UAE diversification
    > GVT &: ECONOMY: UAE economy absorbs multi-sector shock

    > BANKING: UAE banks ready to weather the storm
    > ATTACKS: UAE counts energy infrastructure costs

    > UPSTREAM: Adnoc builds long-term oil and gas production potential
    > DOWNSTREAM: Adnoc Gas to rally UAE downstream project spending
    > POWER: Large-scale IPPs drive UAE power market
    > WATER: UAE water investment broadens beyond desalination
    > CONSTRUCTION: War casts shadow over UAE construction boom
    > TRANSPORT: UAE rail momentum grows as trade routes face strain
    > DATABANK: UAE GDP projection corrects on conflict

    MEED COMMENTS: 
    War takes a rising toll on Kuwait’s oil sector

    Libya budget approval could lead to surge in oil and gas projects
    Masdar’s move abroad will not be the last
    Saudi Landbridge finds its moment in Gulf turmoil

    > GULF PROJECTS INDEX: Gulf index plateaus despite ceasefire

    > MARCH 2026 CONTRACTS: Middle East contract awards

    > ECONOMIC DATA: Data drives regional projects

    > OPINIONThe road to hell is paved with gold

    BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16623768/main.gif
    MEED Editorial
  • Algeria extends bid deadline for stalled power plant

    30 April 2026

    Algeria’s state-owned electricity and gas utility Sonelgaz has extended a deadline for contractors to submit expressions of interest for the construction of the 1.2GW Djelfa combined-cycle power plant.

    The project is being procured through Sonelgaz’s power generation subsidiary, Societe Algerienne de l’Electricite et du Gaz – Production de l’Electricite (SPE).

    In March, MEED reported that the utility was seeking contractors to complete works at the existing Djelfa plant, including the remaining construction, the supply of missing equipment and the assessment of installed equipment.

    The original bid submission deadline for prequalification was 7 April. The new deadline is 5 May.

    The tender is open to both local and international companies, and will be conducted in three phases: prequalification, preliminary technical assessment, and final technical and financial submission.

    The retender follows earlier plans to complete the project through a Chinese consortium comprising China Energy Engineering Group Company, Northwest Electric Power Design Institute and Anhui Electric Power Construction Company.

    This proposal was made after Spanish contractor Duro Felguera halted work on the project in June 2024. 

    According to MEED Projects, construction works had progressed to 72% at the time of the suspension.

    It is understood that an agreement in principle was then reached to transfer the remaining works to the Chinese group after the Spanish firm entered a pre-bankruptcy phase in December 2024.

    A company statement at the time said: “The Chinese group is committed to completing the plant construction, with commissioning scheduled to start in the ninth month following the final agreement.”

    However, in October 2025, it was revealed that the attempt to transfer the project to a consortium of Chinese companies had failed, leaving the Spanish firm with an official demand to pay €413m in compensation to Sonelgaz.

    This was revealed via a lengthy report containing a restructuring plan sent by Duro Felguera to creditors in Spain and the Madrid Financial Markets Authority.

    Gas-fired power plants

    Located in Djelfa province, the project remains a key part of Algeria’s power generation expansion plans.

    Sonelgaz has been seeking contractors to build a separate 1.2GW combined-cycle gas-fired power plant in Aldrar since last April.

    The most recent deadline extension was 29 April.

    According to recent reports, Algeria has also begun construction of a power generation plant in El-Aouinet, with a total installed capacity of 1,406MW.

    The combined-cycle gas turbine plant is being developed in partnership with China National Electric Engineering Company.

    Gas-fired combined-cycle plants continue to account for the majority of Algeria’s electricity generation capacity. Data from MEED Projects indicates that more than 5,000MW of oil- and gas-fired power capacity is currently in the execution phase.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16623787/main.jpg
    Mark Dowdall
  • Dewa announces new record for power reliability

    30 April 2026

    Dubai Electricity & Water Authority (Dewa) has announced that it set a new world record for the lowest electricity customer minutes lost (CML), at 0.82 minutes a year in 2025.

    The figure is equivalent to about 49 seconds of annual outage per customer. It improves on the utility’s previous record of 0.94 minutes in 2024, a reduction of around 13%.

    Dewa said it has reduced CML in Dubai from 6.88 minutes a year in 2012 to 0.82 minutes in 2025, significantly lower than the average of about 15 minutes recorded by leading electricity utilities in the European Union.

    The smart grid is a central component of Dewa’s strategy to improve reliability and efficiency. The programme is being implemented with total investments of AED7bn up to 2035.

    One of the key initiatives of the programme is the Automatic Smart Grid Restoration System, which enables remote, round-the-clock control and monitoring.

    Dewa currently has tenders out for several power and water infrastructure projects in the emirate. These include at least four Glass Reinforced Epoxy (GRE) water transmission pipeline projects.

    According to regional projects tracker MEED Projects, Dewa awarded $1.1bn-worth of new power and water contracts in 2025. Contract awards had previously reached $2.6bn in 2024, and $4bn in 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16623721/main.jpg
    Mark Dowdall
  • Riyadh tenders PMC deal for major sports arena

    30 April 2026

     

    Saudi Arabia’s Sports Boulevard Foundation has tendered a contract inviting firms to bid for project management consultancy (PMC) services for the Global Sports Tower in the Athletics District of the Sports Boulevard development in Riyadh.

    The tender was issued on 8 April, with a bid submission deadline of 10 May.

    The 130-metre-tall Global Sports Tower will cover an area of 84,000 square metres and will include more than 30 sports facilities. The tower will feature the world’s tallest indoor climbing wall at 98 metres and a 250-metre running track.

    Earlier this week, MEED reported that the Sports Boulevard Foundation is preparing to award the main construction contract for the Global Sports Tower. MEED understands that bid evaluation has reached an advanced stage and the contract is likely to be awarded by the end of May.

    MEED reported in May last year that design work on the tower had been completed. Saudi Arabia’s Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud approved the designs in 2024.

    The Sports Boulevard development runs across Riyadh from east to west and, once complete, is set to be the world’s longest park spanning more than 135 kilometres.

    The development will be spread across several districts, including Wadi Hanifah, Arts, Urban Wadi, Entertainment, Athletics and Eco, as well as Sands Sports Park.

    The large-scale project aims to transform central Riyadh – currently dominated by major highways – into a recreational corridor.

    Sports Boulevard, which will feature 4.4 million sq m of public realm and landmark buildings, will also be home to the Centre for Cinematic Arts and a 2,000-seat amphitheatre.

    The development will provide more than 2.3 million sq m of mixed-use commercial, residential, and retail assets, along with sports facilities around the park, known as Linear Park.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16622287/main.jpeg
    Yasir Iqbal
  • Contractors submit Saudi Arabia phosphate rail track bids

    30 April 2026

     

    Saudi Arabian Railways (SAR) received bids from contractors on 27 April for a multibillion-riyal tender to double the tracks on the existing phosphate transport railway network connecting the Waad Al-Shamal mines to Ras Al-Khair in the kingdom’s Eastern Province.

    The tender – covering the second section of the track-doubling works and spanning more than 150 kilometres (km) – was issued on 9 February.

    This follows SAR receiving bids on 1 February for the project’s first phase, which spans about 100km from the AZ1/Nariyah Yard to Ras Al-Khair.

    The scope includes track doubling, alignment modifications, new utility bridges, culvert widening and hydrological structures, as well as the conversion of the AZ1 siding into a mainline track. It also includes support for signalling and telecommunications systems.

    The tender notice was issued in late November.

    Switzerland-based engineering firm ARX is the project consultant.

    MEED understands that these two packages are the first of four that SAR is expected to tender for the phosphate railway line. Other packages anticipated to be tendered shortly include the depot and systems packages.

    In 2023, MEED reported that SAR was planning two projects to increase its freight capacity, including an estimated SR4.2bn ($1.1bn) project to install a second track along the North Train Freight Line and construct three new freight yards.

    Formerly known as the North-South Railway, the North Train is a 1,550km-long freight line running from the phosphate and bauxite mines in the far north of the kingdom to the Al-Baithah junction. There, it diverges into a line southward to Riyadh and a second line running east to downstream fertiliser production and alumina refining facilities at Ras Al-Khair on the Gulf coast.

    Adding a second track and the freight yards will significantly increase the network’s cargo-carrying capacity and facilitate increased industrial production. Project implementation is expected to take four years.

    State-owned SAR is also considering increasing the localisation of railway materials and equipment, including the construction of a cement sleeper manufacturing facility.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16622526/main.jpg
    Yasir Iqbal