Transmission and distribution sector heads for record year

3 October 2024

The GCC region’s power transmission and distribution (T&D) sector is set to experience its best year in terms of the value of awarded contracts.

Based on data from regional projects-tracking service MEED Projects, the total value of awarded contracts for substations, control centres, overhead lines and cables across the six GCC states reached an estimated $13.8bn between January and September 2024.

This figure already exceeds by 81% the total value of contracts awarded in the preceding full year.

It also exceeds by 31% the total value of awarded contracts in 2021, which registered a record-high of $10.5bn in the 10 years starting in 2014.

Project activity within the T&D sector is expected to remain buoyant over the next few years, with roughly $35.9bn-worth of planned and unawarded contracts.

Of these, some $8.5bn are in the bid evaluation stage as of early October, with a further $6.5bn under tendering.

Some $12bn of projects are in the front-end engineering and design (feed) phase.

Energy diversification 

Ambitious national energy diversification and net-zero targets across the region, which traditionally relied almost entirely on thermal power plants, will spur significant investments in T&D infrastructure in the future.

According to experts, the ongoing expansion of electricity generation capacity across the region, particularly from renewable energy sources, requires a more robust, integrated and stable electricity grid.

This is in addition to the projected increase in electricity demand as most states expand their downstream and petrochemical sectors, develop new communities and megaprojects in remote regions, and build more data centres to support smart cities, and internet-of-things (IoT) and artificial intelligence (AI) applications.

The region’s largest economy, Saudi Arabia, for instance, aims for renewable energy to account for 50% of its electricity generation capacity by 2030.

Operational renewable installed capacity in the kingdom jumped from roughly 300MW in 2020 to 3,500MW this year, with a further 16,000MW currently under construction or about to start construction, and gigawatts more under tender.

Crucially, the kingdom’s energy minister confirmed earlier this year that the kingdom has plans to procure up to 20,000MW of renewable capacity every year, subject to demand.

Saudi Arabia is also ramping up its procurement programme for new gas-fired power plants, in line with a plan to decommission fleets running on liquid fuel and at the same time secure baseload as more renewable energy enters the grid.

There is also a marked increase in terms of T&D packages or contracts interconnecting the kingdom’s various regions from central Riyadh to the eastern, northern and southern provinces.

It comes as no surprise that the kingdom accounted for 72% of the $13.8bn-worth of T&D contracts awarded in the GCC region in the first three quarters of 2024.

Oman, which awarded T&D contracts with the same value as the UAE between January and September this year, has also been working to integrate its smaller electricity grids with the sultanate’s main electricity grid to boost electricity supply in its smaller, remote regions.

Unlike the noticeable peaks and throughs in T&D capital expense in other GCC states, the UAE’s spending has remained pretty consistent since 2014, averaging roughly $1.4bn annually. The exemption was in 2021 when a team comprising South Korea’s Kepco, Japan’s Kyushu Electric Power Company (Kyuden) International and France’s EDF won the contract to develop Abu Dhabi’s first high-voltage, direct current (HVDC) subsea transmission system.

It is worth mentioning that the completion of the four units of Abu Dhabi’s 5,600MW Barakah nuclear power plant this year and the expected completion of Dubai’s first hydropower plant in Hatta mean the UAE will have the most diverse energy sources for electricity generation among its peers.   

Power links

The goal to expand electricity trade within the GCC member states and with other countries such as Egypt, Jordan and Iraq is another key driver for T&D investments.

Work is under way to increase the capacity of the GCC regional grid and enable its member-states to procure backup or emergency capacity when the need arises. Kuwait availed of this in May when it purchased 500MW from the GCC grid in anticipation of its inability to meet peak demand in the summer months.   

An HVDC network linking Saudi Arabia and Egypt is under construction, which will allow bidirectional electricity trade as well as access to the wider European and African markets.

A second GCC link with Oman and a first link with Jordan are also planned. Another HVDC transmission project linking Neom in the northern tip of the Red Sea to Yanbu, stretching 605 kilometres, is under way.

It turns out that the need to invest in T&D infrastructure to support electricity generation capacity buildout, following years of underinvestment, is a global phenomenon.

Juan Diego Zuluaga, Suncolombia CEO, told the ongoing World Green Energy Summit in Dubai that there is a major mismatch between the buildout of transmission lines and electricity generation capacity.

Experts like Zuluaga think that failing to invest in T&D can potentially lead to issues such as curtailment or wastage in renewable power, particularly in the absence of suitable energy storage systems or efficient interconnections or electricity links.

Utility companies are under pressure not only to expand their transmission capacities and coverage but to make these infrastructure and facilities more efficient, too.

New technologies, most of them driven by IoT or AI, for instance, can be used to improve demand and supply management and forecasting, leading to improved grid performance.

“In this region, in particular, consumers expect 24x7 electricity supply. In fact, it is a given,” notes a senior executive with a European technology company. “The hope is for that to continue in the future.”

 

 

https://image.digitalinsightresearch.in/uploads/NewsArticle/12646884/main.jpg
Jennifer Aguinaldo
Related Articles
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp
  • Tunisia extends bid deadline for gas pipeline project

    24 August 2026

    State-owned Tunisian Company of Electricity & Gas (Steg) has extended the bid deadline for a project to develop gas pipelines in the North African country.

    Earlier this year, the project was tendered with a bid deadline of 15 July. The new deadline is 30 September 2026.

    The scope of the project includes conducting studies, procuring equipment and materials, and performing construction work.

    Steg has received financing from the Islamic Development Bank to fund the project.

    The tender has been split into two packages.

    The first pipeline runs from the Tunisian town of Mourouj, in the suburbs of Tunis, to the town of Zriba.

    Along this route, the pipeline will be split into two sections.

    The first extends from Mourouj to the town of Fouchana, which lies to the south of the capital.

    Under existing plans, the pipeline will have a diameter of 20 inches and extend for 3.8 kilometres.

    The second section will extend for 43km to Zriba and have a diameter of 24 inches.

    The contract for package one has a 450-day completion period.

    The project’s second package focuses on a gas pipeline extending from Zriba to the town of M’saken.

    This pipeline will extend for 78km and have a diameter of 24 inches.

    The contract for this package also specifies a 450-day completion period.

    The procedure for the tender of both packages is an international call for tenders under the Islamic Development Bank guidelines for design, supply and installation.

    The Middle East and North Africa (Mena) region is currently seeing a surge in oil and gas pipeline projects as countries attempt to diversify routes through which hydrocarbons can be transported.

    The increased concerns about overreliance on a small number of transportation routes are a result of the regional conflict that started when the US and Israel attacked Iran on 28 February.

    The conflict severely disrupted oil and gas flows through the Strait of Hormuz, highlighting the importance of having a diverse range of import and export routes.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953537/main.jpg
    Wil Crisp
  • Saudi Arabia signs $1.16bn bess agreements

    21 August 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), has signed four storage service agreements for battery energy storage system (bess) projects with a combined capacity of 2,000MW.

    The projects will provide four hours of storage, equivalent to 8,000 megawatt-hours (MWh), and involve total investment of more than SR4.35bn ($1.16bn).

    The agreements cover the first group of independent storage provider (ISP) bess projects being procured by SPPC under a build, own and operate model. The projects are supervised by the Energy Ministry.

    Three projects have been awarded to a consortium comprising Saudi Energy, Acwa and Al-Sharif Contracting & Commercial Development Company.

    These comprise the Al-Muwyah and Haden bess ISPs in the Mecca region, and the Al-Kahafa bess ISP in the Hail region. Each has a capacity of 500MW for four hours.

    The fourth project, the Al-Khushaybi bess ISP in the Qassim region, has been awarded to a consortium of France's Engie and local firm Haji Abdullah Alireza & Co. This also has a capacity of 500MW for four hours. 

    In July, MEED exclusively reported that Acwa and Engie were frontrunners for the Group 1 bess contracts. SPPC launched the qualification process for the scheme in November 2024, with bids submitted last year.

    The projects form part of Saudi Arabia’s efforts to achieve an electricity generation mix comprising approximately 50% renewable energy by 2030.

    Bess 2

    As exclusively reported by MEED, SPPC issued the request for proposals for the second phase of its independent bess projects in July.

    The Group 2 programme comprises six ISP projects with a total capacity of 3GW, equivalent to 12,000MWh based on a four-hour storage duration.

    The six bess projects are:

    • Samha bess ISP: 500MW (Qassim)
    • Al-Leeth bess ISP: 500MW (Mecca)
    • Al-Henakiyah bess ISP: 500MW (Medina)
    • Khulis bess ISP: 500MW (Mecca)
    • Sadawi bess ISP: 500MW (Eastern Province)
    • Ashyrah bess ISP: 500MW (Mecca)

    According to a source, developers have since submitted a first round of clarification requests to SPPC as they prepare their bids in advance of an October deadline.

      On 1 July, MEED reported that up to 27 firms had prequalified to participate in the second phase. SPPC previously received statements of qualification on 13 May.

      It is understood that Abu Dhabi National Energy Company (Masdar, UAE), Acwa (Saudi Arabia), EDF (France), Korea Electric Power Corporation (Kepco, South Korea), International Power (Engie, France) and Marubeni Corporation (Japan) are among the companies likely to make offers for the contracts.

      Winning bidders will hold 100% equity in a special purpose vehicle (SPV), with each SPV entering into a storage services agreement with SPPC as part of the ISP structure. 

      US/India-based Synergy Consulting is advising SPPC on the energy storage Group 1 and Group 2 programmes.


      READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

      Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

      Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

      > MARKET FOCUS: Maghreb fortunes diverge
      To see previous issues of MEED Business Review, please click here
      https://image.digitalinsightresearch.in/uploads/NewsArticle/18911926/main2457.jpg
      Mark Dowdall
    • Contractors confirm $683m Oman power plant contract

      21 August 2026

      Register for MEED’s 14-day trial access 

      China-headquartered Shandong Electric Power Construction No. 3 Company (Sepco 3) and South Korea’s Doosan Enerbility have confirmed their involvement as contractors on the 1,700MW Misfah combined-cycle gas turbine (CCGT) project in Oman.

      In a statement, Sepco 3 said it signed the contract on 20 August. On 21 August, Doosan disclosed a KRW930bn ($683m) contract with Jabel Power, the project company for the Misfah plant. The contract runs from 20 August 2026 to 1 April 2029.

      The same consortium signed the engineering, procurement and construction (EPC) contract for the 890MW Duqm CCGT power plant in June. At the time, Doosan disclosed a contract worth about $350m.

      In May, MEED exclusively reported that the group had been appointed as the main contractor for the two power plants, subject to the official signing.

      State offtaker Nama Power & Water Procurement (Nama PWP) had previously signed power-purchase agreements (PPAs) for the development and operation of the plants.

      The developer’s contract was awarded to a consortium comprising Korea Western Power (Kowepo), Qatar’s Nebras Power, the UAE’s Etihad Water & Electricity (EtihadWE) and Oman’s Bhawan Infrastructure Services.

      As MEED understands, construction works have already commenced on the power plant projects. A China-based procurement listing in June shows that civil works procurement was under way for the Misfah independent power producer (IPP).

      The civil package F tender covered piling, reinforcement cages, concrete works and pile testing, with work scheduled to start in July and finish by November

      As reported in July, Germany’s Siemens Energy will supply power generation technology and long-term service agreements for the Misfah and Duqm IPP projects.

      This includes the supply of six F-class gas turbines, six generators and 20-year long-term service agreements for the equipment.

      The Misfah IPP will be led by Nebras Power and located in Wilayat Bousher in Muscat Governorate. The Duqm IPP will be led by Kowepo and located in Wilayat Duqm in Al-Wusta Governorate.

      According to Nama PWP, the total investment for the two projects is estimated at approximately RO1bn ($2.6bn).

      Synergy Consulting is the financial adviser and lead adviser to Nama PWP for these projects.

      In November, Oman’s OQ Gas Networks received final investment approval to proceed with gas supply connections for the facilities.

      The Misfah IPP will receive 8.5 million cubic metres a day (cm/d) of natural gas. The Duqm IPP will be supplied with 4.5 million cm/d of natural gas.

      In March 2025, the same Sepco 3 and Doosan Enerbility consortium signed an EPC contract with Saudi Electricity Company to expand Riyadh Power Plant 12 (PP12). Located about 150 kilometres northwest of Riyadh, the 1,863MW power plant is expected to be completed in 2028.


      READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

      Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

      Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

      > MARKET FOCUS: Maghreb fortunes diverge
      To see previous issues of MEED Business Review, please click here
      https://image.digitalinsightresearch.in/uploads/NewsArticle/18911106/main.jpg
      Mark Dowdall