Transmission and distribution sector heads for record year

3 October 2024

The GCC region’s power transmission and distribution (T&D) sector is set to experience its best year in terms of the value of awarded contracts.

Based on data from regional projects-tracking service MEED Projects, the total value of awarded contracts for substations, control centres, overhead lines and cables across the six GCC states reached an estimated $13.8bn between January and September 2024.

This figure already exceeds by 81% the total value of contracts awarded in the preceding full year.

It also exceeds by 31% the total value of awarded contracts in 2021, which registered a record-high of $10.5bn in the 10 years starting in 2014.

Project activity within the T&D sector is expected to remain buoyant over the next few years, with roughly $35.9bn-worth of planned and unawarded contracts.

Of these, some $8.5bn are in the bid evaluation stage as of early October, with a further $6.5bn under tendering.

Some $12bn of projects are in the front-end engineering and design (feed) phase.

Energy diversification 

Ambitious national energy diversification and net-zero targets across the region, which traditionally relied almost entirely on thermal power plants, will spur significant investments in T&D infrastructure in the future.

According to experts, the ongoing expansion of electricity generation capacity across the region, particularly from renewable energy sources, requires a more robust, integrated and stable electricity grid.

This is in addition to the projected increase in electricity demand as most states expand their downstream and petrochemical sectors, develop new communities and megaprojects in remote regions, and build more data centres to support smart cities, and internet-of-things (IoT) and artificial intelligence (AI) applications.

The region’s largest economy, Saudi Arabia, for instance, aims for renewable energy to account for 50% of its electricity generation capacity by 2030.

Operational renewable installed capacity in the kingdom jumped from roughly 300MW in 2020 to 3,500MW this year, with a further 16,000MW currently under construction or about to start construction, and gigawatts more under tender.

Crucially, the kingdom’s energy minister confirmed earlier this year that the kingdom has plans to procure up to 20,000MW of renewable capacity every year, subject to demand.

Saudi Arabia is also ramping up its procurement programme for new gas-fired power plants, in line with a plan to decommission fleets running on liquid fuel and at the same time secure baseload as more renewable energy enters the grid.

There is also a marked increase in terms of T&D packages or contracts interconnecting the kingdom’s various regions from central Riyadh to the eastern, northern and southern provinces.

It comes as no surprise that the kingdom accounted for 72% of the $13.8bn-worth of T&D contracts awarded in the GCC region in the first three quarters of 2024.

Oman, which awarded T&D contracts with the same value as the UAE between January and September this year, has also been working to integrate its smaller electricity grids with the sultanate’s main electricity grid to boost electricity supply in its smaller, remote regions.

Unlike the noticeable peaks and throughs in T&D capital expense in other GCC states, the UAE’s spending has remained pretty consistent since 2014, averaging roughly $1.4bn annually. The exemption was in 2021 when a team comprising South Korea’s Kepco, Japan’s Kyushu Electric Power Company (Kyuden) International and France’s EDF won the contract to develop Abu Dhabi’s first high-voltage, direct current (HVDC) subsea transmission system.

It is worth mentioning that the completion of the four units of Abu Dhabi’s 5,600MW Barakah nuclear power plant this year and the expected completion of Dubai’s first hydropower plant in Hatta mean the UAE will have the most diverse energy sources for electricity generation among its peers.   

Power links

The goal to expand electricity trade within the GCC member states and with other countries such as Egypt, Jordan and Iraq is another key driver for T&D investments.

Work is under way to increase the capacity of the GCC regional grid and enable its member-states to procure backup or emergency capacity when the need arises. Kuwait availed of this in May when it purchased 500MW from the GCC grid in anticipation of its inability to meet peak demand in the summer months.   

An HVDC network linking Saudi Arabia and Egypt is under construction, which will allow bidirectional electricity trade as well as access to the wider European and African markets.

A second GCC link with Oman and a first link with Jordan are also planned. Another HVDC transmission project linking Neom in the northern tip of the Red Sea to Yanbu, stretching 605 kilometres, is under way.

It turns out that the need to invest in T&D infrastructure to support electricity generation capacity buildout, following years of underinvestment, is a global phenomenon.

Juan Diego Zuluaga, Suncolombia CEO, told the ongoing World Green Energy Summit in Dubai that there is a major mismatch between the buildout of transmission lines and electricity generation capacity.

Experts like Zuluaga think that failing to invest in T&D can potentially lead to issues such as curtailment or wastage in renewable power, particularly in the absence of suitable energy storage systems or efficient interconnections or electricity links.

Utility companies are under pressure not only to expand their transmission capacities and coverage but to make these infrastructure and facilities more efficient, too.

New technologies, most of them driven by IoT or AI, for instance, can be used to improve demand and supply management and forecasting, leading to improved grid performance.

“In this region, in particular, consumers expect 24x7 electricity supply. In fact, it is a given,” notes a senior executive with a European technology company. “The hope is for that to continue in the future.”

 

 

https://image.digitalinsightresearch.in/uploads/NewsArticle/12646884/main.jpg
Jennifer Aguinaldo
Related Articles
  • Iranian missiles hit Qatari and Kuwaiti fuel tankers

    1 April 2026

    Iranian missiles have struck fuel tankers in Gulf waters belonging to Qatar and Kuwait, as Tehran continues to target energy, industrial and logistical assets in GCC countries.

    A fuel oil tanker chartered by QatarEnergy, named Aqua 1, was struck by missiles in Qatar’s northern territorial waters in the early hours of 1 April, the company said in a statement.

    “None of the crew members on board were injured, and there is no impact on the environment as a result of this incident,” QatarEnergy said.

    Earlier, on 31 March,  said one of its very large crude carriers, Al-Salmi, caught fire after being hit by an Iranian missile while anchored in UAE waters just outside Dubai.

    The vessel’s crew, with support from UAE authorities, extinguished the fire by 04:26 Kuwait time on 31 March, KPC said. It added that all 24 crew members were safe and that no oil spill or environmental damage occurred.

    “KPC is continuing to assess the damage in coordination with relevant authorities,” the Kuwaiti state energy conglomerate said.

    ALSO READ: Iran strikes Gulf aluminium assets after hits on its steel sector
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16217670/main4010.jpg
    Indrajit Sen
  • One killed and one injured in drone attacks on the UAE

    1 April 2026

    Debris falling from Iranian drones intercepted by the UAE’s air defence systems has killed one person in the emirate of Fujairah and injured another in Umm Al-Quwain in two separate incidents on 1 April.

    A successful interception of a drone by UAE air defence forces resulted in debris falling on a farm in Fujairah, leading to the death of a Bangladeshi national.

    The latest fatality brings the total death toll in the UAE since the start of the US-Israel-Iran war to 12. Most of the deaths have been caused by falling debris following interceptions. Among the deceased are two members of the UAE armed forces who died while performing their duties, as well as a Moroccan civilian contracted by the armed forces.

    The remaining victims were of Bangladeshi, Indian, Nepali, Pakistani and Palestinian nationalities.

    Hours after the Fujairah incident, authorities in Umm Al-Quwain confirmed that an Indian national was injured when debris from an intercepted drone fell in the emirate.

    In a statement posted on its official social media channels, the Umm Al-Quwain government media office said the incident occurred near an industrial facility in the Umm Al-Thuoob area, after air defence systems successfully intercepted an unmanned aerial vehicle (UAV).

    Meanwhile, the latest data from the UAE Ministry of Defence, released on 31 March, showed that air defence systems had engaged 36 UAVs, four cruise missiles and eight ballistic missiles in the previous 24 hours. Cumulatively, authorities said 1,977 drones, 19 cruise missiles and 433 ballistic missiles have been intercepted since the onset of the war on 28 February.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16218126/main.jpg
    Indrajit Sen
  • Contractors submit Al-Maktoum airport superstructure bids

    1 April 2026

     

    Dubai Aviation Engineering Projects (DAEP) received proposals on 31 March from contractors for three packages covering superstructure works for the first phase of the expansion of Al-Maktoum International airport.

    MEED understands that the selected contractor will undertake superstructure works on three packages:

    • West Terminal and concourse one
    • Concourse two
    • Concourse three

    Construction on these packages began in November last year, when DAEP formally selected a contractor to deliver the substructure works.

    According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000-square-metre facility with an annual capacity of 45 million passengers.

    It will be the second of three terminals at Al-Maktoum International airport, linked to the airside by a 14-station automated people-mover (APM) system.

    In August last year, MEED exclusively reported that DAEP had received bids from firms to build the APM at the airport. 

    The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.

    The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.

    Construction progress

    Construction on the first phase has already begun. In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works on the terminal are also ongoing and are being undertaken by Abu Dhabi-based Tristar E&C.

    Construction on the project’s first phase is expected to be completed by 2032.

    The government approved the updated designs and timelines for its largest construction project in April 2024.

    In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.

    The statement added that the project will create housing demand for 1 million people around the airport.

    In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.

    Project history

    The expansion of Al-Maktoum International, also known as Dubai World Central (DWC), is a long-standing project. It was officially launched in 2014, with a different design from the one approved in April 2024. At that time, it involved building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year.

    An initial phase, due to be completed in 2030, involved increasing the airport’s capacity to 130 million passengers a year. The development was to cover an area of 56 sq km.

    Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16215664/main.jpg
    Yasir Iqbal
  • Drone strikes Kuwait International airport

    1 April 2026

    Register for MEED’s 14-day trial access 

    Kuwait International airport was hit by further drone attacks on Wednesday, with strikes on fuel tanks sparking a major fire.

    Kuwait’s state news agency Kuna said the attack caused significant damage to fuel tanks belonging to Kuwait Aviation Fuelling Company. No casualties were reported.

    This was the second reported incident at the airport in recent days. Local media reported that the airport was attacked on 28 March by multiple drones, causing significant damage to its radar system.

    The airport is currently undergoing expansion works that are expected to be completed by 2027, as MEED reported previously.

    Project execution of the second terminal began in 2017, with the completion date pushed back from the original 2022 target.

    The second terminal project consists of three packages.

    These are:

    • Package 1: Main works – $4,329m
    • Package 2: Multistorey car park building, connection roads, bridges and landscaping works – $550m
    • Package 3: Aircraft parking, runways and service buildings – $950m

    Turkiye’s Limak Holding is executing the main works.

    The terminal building was designed by Foster+Partners and Gulf Consult.

    Spanish firm Ineco is providing the project management services for the new terminal building and the airfield.

    The scope of the main package includes the new terminal building, a building for cooling and electricity supply facilities, and a building for the water supply and the future Automatic People Mover (APM) connection to the satellite building.

    The terminal building will be three times the size of the original building and will have 36 boarding gates.

    The building will cover more than 700,000 square metres and have five floors, one of which will be underground.

    It will have the capacity, at maximum service level, for 25 million passengers a year once the first phase has been completed and up to 50 million passengers after further phases are completed.

    The second package of works includes a new car park with approximately 5,000 parking spaces, connected to the new passenger terminal.

    It also includes all new access roads to the airport and landscaping.

    The scope of the third package comprises the main platform, new taxiways and several tunnels, including one under the platform between the terminal building and the future cargo area of the airport.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16216797/main.png
    Yasir Iqbal
  • Saudi Arabia’s Sadara halts chemical production

    1 April 2026

    Register for MEED’s 14-day trial access 

    Sadara Chemical Company (Sadara), the Saudi Aramco-Dow Chemical joint venture producing petrochemicals and specialty chemicals, has announced a temporary shutdown of production, citing ongoing supply chain disruptions.

    Sadara operates a sprawling chemical production complex in Jubail in Saudi Arabia’s Eastern Province, with a total output capacity of more than 3 million metric tonnes a year. Aramco and Dow established the Sadara petrochemicals complex – estimated to have cost $13bn – in 2016.

    The suspension was announced in a filing on the Saudi Exchange (Tadawul) by Sadara Basic ​Services, which issues sukuk, or Islamic bonds, ​for its parent. “The shutdown was successfully completed in accordance with Sadara’s high safety standards and in a manner that safeguards operations and reduces risk,” the entity said in its filing on 31 March

    “Sadara cannot provide, at the present ‌time, ⁠an estimate for the return to production, as this is contingent on domestic and international factors,” it said, ​adding ​the shutdown ⁠is expected to impact this year’s financial results.

    The month-long war between Israel, the US and Iran has spread across the Middle East, disrupting energy supplies and threatening the global economy, as Tehran has responded to US and Israeli attacks by targeting regional energy and industrial infrastructure, as well as shipping.

    ALSO READ: Sultan Al-Jaber calls Strait of Hormuz blockade “economic terrorism”

    Separately, Sadara, in another Tadawul filing on 31 March, announced a net loss of SR5,793bn ($1.54bn) for the full year 2025, a further decline of about 40% compared to 2024. The company’s revenue in 2025 fell by about 15% year-on-year to $2.63bn.

    The chemicals producer attributed the deepening of its losses in 2025 to a reduction in sales volumes, “which resulted from unplanned operational events and extended maintenance activities that temporarily impacted production availability”.

    Sadara also pinned its augmented losses to “margin compression, and higher fixed costs associated with unplanned operational events and extended maintenance activities.

    “In addition, the company experienced lower average selling prices across certain portfolio lines, which further contributed to the overall decrease in revenue,” Sadara said in the disclosure.

    In addition, “the net loss for 2025 increased compared to 2024, mainly due to an accounting adjustment related to a debt modification that had a favourable impact on the prior year’s results,” the company added.

    ALSO READ: Sabic registers $6.87bn net loss in 2025

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16215635/main2446.jpg
    Indrajit Sen