Transmission and distribution sector heads for record year

3 October 2024

The GCC region’s power transmission and distribution (T&D) sector is set to experience its best year in terms of the value of awarded contracts.

Based on data from regional projects-tracking service MEED Projects, the total value of awarded contracts for substations, control centres, overhead lines and cables across the six GCC states reached an estimated $13.8bn between January and September 2024.

This figure already exceeds by 81% the total value of contracts awarded in the preceding full year.

It also exceeds by 31% the total value of awarded contracts in 2021, which registered a record-high of $10.5bn in the 10 years starting in 2014.

Project activity within the T&D sector is expected to remain buoyant over the next few years, with roughly $35.9bn-worth of planned and unawarded contracts.

Of these, some $8.5bn are in the bid evaluation stage as of early October, with a further $6.5bn under tendering.

Some $12bn of projects are in the front-end engineering and design (feed) phase.

Energy diversification 

Ambitious national energy diversification and net-zero targets across the region, which traditionally relied almost entirely on thermal power plants, will spur significant investments in T&D infrastructure in the future.

According to experts, the ongoing expansion of electricity generation capacity across the region, particularly from renewable energy sources, requires a more robust, integrated and stable electricity grid.

This is in addition to the projected increase in electricity demand as most states expand their downstream and petrochemical sectors, develop new communities and megaprojects in remote regions, and build more data centres to support smart cities, and internet-of-things (IoT) and artificial intelligence (AI) applications.

The region’s largest economy, Saudi Arabia, for instance, aims for renewable energy to account for 50% of its electricity generation capacity by 2030.

Operational renewable installed capacity in the kingdom jumped from roughly 300MW in 2020 to 3,500MW this year, with a further 16,000MW currently under construction or about to start construction, and gigawatts more under tender.

Crucially, the kingdom’s energy minister confirmed earlier this year that the kingdom has plans to procure up to 20,000MW of renewable capacity every year, subject to demand.

Saudi Arabia is also ramping up its procurement programme for new gas-fired power plants, in line with a plan to decommission fleets running on liquid fuel and at the same time secure baseload as more renewable energy enters the grid.

There is also a marked increase in terms of T&D packages or contracts interconnecting the kingdom’s various regions from central Riyadh to the eastern, northern and southern provinces.

It comes as no surprise that the kingdom accounted for 72% of the $13.8bn-worth of T&D contracts awarded in the GCC region in the first three quarters of 2024.

Oman, which awarded T&D contracts with the same value as the UAE between January and September this year, has also been working to integrate its smaller electricity grids with the sultanate’s main electricity grid to boost electricity supply in its smaller, remote regions.

Unlike the noticeable peaks and throughs in T&D capital expense in other GCC states, the UAE’s spending has remained pretty consistent since 2014, averaging roughly $1.4bn annually. The exemption was in 2021 when a team comprising South Korea’s Kepco, Japan’s Kyushu Electric Power Company (Kyuden) International and France’s EDF won the contract to develop Abu Dhabi’s first high-voltage, direct current (HVDC) subsea transmission system.

It is worth mentioning that the completion of the four units of Abu Dhabi’s 5,600MW Barakah nuclear power plant this year and the expected completion of Dubai’s first hydropower plant in Hatta mean the UAE will have the most diverse energy sources for electricity generation among its peers.   

Power links

The goal to expand electricity trade within the GCC member states and with other countries such as Egypt, Jordan and Iraq is another key driver for T&D investments.

Work is under way to increase the capacity of the GCC regional grid and enable its member-states to procure backup or emergency capacity when the need arises. Kuwait availed of this in May when it purchased 500MW from the GCC grid in anticipation of its inability to meet peak demand in the summer months.   

An HVDC network linking Saudi Arabia and Egypt is under construction, which will allow bidirectional electricity trade as well as access to the wider European and African markets.

A second GCC link with Oman and a first link with Jordan are also planned. Another HVDC transmission project linking Neom in the northern tip of the Red Sea to Yanbu, stretching 605 kilometres, is under way.

It turns out that the need to invest in T&D infrastructure to support electricity generation capacity buildout, following years of underinvestment, is a global phenomenon.

Juan Diego Zuluaga, Suncolombia CEO, told the ongoing World Green Energy Summit in Dubai that there is a major mismatch between the buildout of transmission lines and electricity generation capacity.

Experts like Zuluaga think that failing to invest in T&D can potentially lead to issues such as curtailment or wastage in renewable power, particularly in the absence of suitable energy storage systems or efficient interconnections or electricity links.

Utility companies are under pressure not only to expand their transmission capacities and coverage but to make these infrastructure and facilities more efficient, too.

New technologies, most of them driven by IoT or AI, for instance, can be used to improve demand and supply management and forecasting, leading to improved grid performance.

“In this region, in particular, consumers expect 24x7 electricity supply. In fact, it is a given,” notes a senior executive with a European technology company. “The hope is for that to continue in the future.”

 

 

https://image.digitalinsightresearch.in/uploads/NewsArticle/12646884/main.jpg
Jennifer Aguinaldo
Related Articles
  • Eni completes $1bn Libya gas project

    20 October 2026

    Register for MEED’s 14-day trial access 

    Libya’s Mellitah Oil & Gas Company, a joint venture of Libya’s National Oil Corporation (NOC) and Italian oil and gas company Eni, has achieved mechanical completion on its Bouri gas utilisation project (GUP).

    In a statement, Eni said that start-up procedures are currently under way, enabling the recovery of associated gas produced from the Bouri field, which is located in Libya’s western offshore area.

    The main contract for the project, worth $1bn, was awarded to Italy’s Saipem in August 2023.

    The project involved the construction and installation of the new Bouri gas recovery module and related tie-in infrastructure that enables the recovery and treatment of gas that was previously flared.

    In its statement, Eni said that the project “represents one of the most significant emissions reduction initiatives in Libya’s energy sector”.

    It also said that it would contribute to improving the environmental performance of the country’s production system by reducing greenhouse gas emissions by approximately 1.5 million tonnes of carbon dioxide a year.

    The recovered gas will be supplied to the domestic market, adding about 700 million cubic metres a year and helping meet demand from the power generation sector.

    The project will also support additional gas volumes available for export to Europe through the GreenStream pipeline.

    Eni said: “The start-up of the Bouri GUP confirms the joint commitment of Eni and NOC to the development of Libya’s energy sector through initiatives that combine production growth, operational efficiency and environmental stewardship.

    “The project is part of a broader strategy aimed at enhancing the value of the country’s gas resources while reducing the emissions intensity of upstream activities.”

    Other key projects currently under way in Libya include the A&E Structures Project, which is focused on bringing new offshore gas resources onstream for both the domestic market and exports, as well as initiatives aimed at upgrading and optimising gas production and transportation infrastructures.

    Eni has been present in Libya since 1959, and the company’s equity production in the country in 2025 amounted to approximately 162,000 barrels of oil equivalent a day.

    The Bouri offshore field is part of Libya’s Block NC-41, located 120 kilometres north of the Libyan coast in the Mediterranean Sea.

    It was first discovered in 1976 at a depth of 8,700 feet. It is estimated to contain 4.5 billion barrels in proven recoverable crude oil reserves and 3.5 trillion cubic feet of associated natural gas, with an annual production potential of 6 billion cubic metres.

    The first development phase, costing nearly $2bn, was completed in 1990.

    This was immediately followed by a second development phase, which entailed drilling 55 new wells and constructing three additional platforms. Production began from the oil platforms DP4 and DP3 in August 1998.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20770288/main3529.jpg
    Wil Crisp
  • Diriyah Company tenders East Wadi bridge

    20 October 2026

     

    Saudi Arabia’s Diriyah Company has invited contractors to bid on the construction of the DG II East Wadi Bridge, a key crossing within Riyadh’s Diriyah master development.  

    The bridge will provide an arterial road connection linking the Diriyah Gate Phase 2 (DG II) Infrastructure Package 1 and Package 2 zones.  

    The project scope involves the construction of a 100-metre clear-span, 44-metre-wide, single-span post-tensioned concrete bridge structure with integrated abutments and four architectural towers.  

    The contract also encompasses approach slabs, access roads, pavements, associated earthworks, architectural finishes and cladding, mechanical, electrical and plumbing installations, utility interfaces, bridge parapets, vehicle restraint systems, waterproofing, testing and commissioning, and associated temporary works.  

    The client will supply the detailed engineering design, and the selected contractor will develop the construction methodology.

    Diriyah Company issued the prequalification tender on 14 September, with submissions due by 10 December.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20769223/main.png
    Yasir Iqbal
  • Kuwait selects firms for power works at housing projects

    20 October 2026

     

    Kuwait’s Public Authority for Housing Welfare (PAHW) has appointed contractors for works covering the supply and installation of 132kV underground cables at South Sabah Al-Ahmad Residential City.

    The contracts relate to engineering, procurement and construction (EPC) packages for works for 28 main 132/11kV substations across four phases.

    According to sources, Egypt’s Elsewedy Cables has won contracts for phases 1 and 3, while China’s TBEA Shandong Luneng Taishan Cable Company has won contracts for phases 2 and 4 of the development.

    In April, MEED reported that PAHW had received at least five bids for each of the first two packages, with Elsewedy and TBEA offering $44m and $40.5m, respectively.

    The first contract (phase 1) covers seven substations in zones N9, N7 and N5. The second contract (phase 2) covers seven substations in zones N10 and N5.

    PAHW issued two further 132kV underground cable tenders for the South Sabah Al-Ahmad residential development at the end of May, as reported by MEED.

    This included a contract (phase 3) covering the supply, extension and maintenance of 132kV underground cables linked to seven substations serving the N5, N6, N8 and N10 districts. Egytech Cables, a subsidiary of Elsewedy, submitted an offer of $39.95m, the lowest of four bids.

    The other contract (phase 4) covers the supply, extension and maintenance of 132kV underground cables feeding eight main transformer substations serving the N1, N6 and N11 districts. 

    MEED reported in July that TBEA had submitted an offer of $44.06m for the contract.

    South Saad Al-Abdullah 

    Separately, PAHW has appointed contractors for power transmission works at the South Saad Al-Abdullah residential development.

    The local firm Sayed Hamid Behbehani & Sons has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the development’s third phase. 

    Another local firm, Al-Ahleia Switchgear, has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the project’s fourth phase. 

    As reported in August, the contractors submitted bids of $104.2m and $103.3m, respectively.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20761431/main.jpg
    Mark Dowdall
  • Taqa moves forward with Mirfa-Liwa scheme

    20 October 2026

     

    Taqa Transmission and Taqa Distribution are advancing a major water transmission and distribution scheme serving Mirfa, Madinat Zayed and Liwa in Abu Dhabi, sources told MEED.

    The project, originally estimated to cost $775m, has been in procurement for several years. According to sources, a request for proposals has been issued, with bids due on 5 January 2027.

    The initial submission deadline was 11 November, before it was extended.

    The project was previously tendered in December 2024, with contractors submitting bids for transmission and distribution packages in January 2025.  As of August, the bids were still under evaluation. It is unclear whether the latest tender represents a revised procurement process for the same scheme.

    The project comprises a water transmission system from Mirfa, alongside distribution networks serving farms and settlements in the western region.

    According to details seen by MEED, the latest scope includes a pumping station at Mirfa with a capacity of 128 million imperial gallons a day, about 125 kilometres of transmission pipelines to Muzairah, with branches to Madinat Zayed and Liwa Summit, and storage tanks at the three locations.

    The distribution network is divided into four geographic clusters covering Liwa East, Liwa West, Madinat Zayed and Seih Al-Kheir. The works include associated pipelines, pumping stations and storage facilities.

    The earlier procurement was structured as an engineering, procurement and construction scheme, divided between transmission and distribution works.

    As MEED understands, the latest tender is being pursued under a design, build and operate model, which extends the contractor’s responsibilities to operating the infrastructure after construction.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20758109/main2934.jpg
    Mark Dowdall
  • Contractors prepare prices for Adnoc Onshore field facilities project

    20 October 2026

     

    Contractors are preparing commercial bids for Adnoc Onshore’s project to build on-plot and off-plot facilities at the Rumaitha and Shanayel fields in Abu Dhabi’s North East Bab oil field cluster.

    The project will enhance and sustain crude output at Rumaitha and Shanayel at 45,000 barrels a day (b/d), supporting Adnoc’s Accelerated Integrated Programme 5 (AiP5) drive to lift capacity to 5 million b/d by 2027.

    Adnoc Onshore issued the main tender for engineering, procurement and construction (EPC) works on 19 June. Contractors submitted technical bids by 5 August, sources told MEED.

    The on-plot works include adding a crude processing train, produced water treatment and reinjection systems, surface water pumps, and multi-stage gas compression and dehydration units. Works also include utilities, safety and control systems, modifications to existing Phase 1 units and 220kV power infrastructure.

    The off-plot scope includes installing and tying in new gas-lifted producer and water-injection wells, as well as building and expanding wellhead clusters. Contractors will also lay crude-gathering, water-injection and gas-export pipelines connecting to the Adnoc Gas network and extend 33kV overhead power lines across the fields.

    The tender follows Adnoc Onshore’s shift in strategy for the wider North East Bab development – comprising the Al-Nouf, Rumaitha and Shanayel fields – after scrapping an earlier engineering, procurement and construction management (EPCm) approach. MEED reported in December that the operator had cancelled an off-plot EPCm contract awarded to China Petroleum Engineering & Construction Corporation (CPECC) in October 2024. Adnoc later cancelled a separate on-plot EPCm tender that it received bids for in the second quarter of 2025.

    In addition to the North East cluster, Adnoc Onshore continues to make progress on EPC works for another similar project to build off-plot facilities at the South East cluster of oil fields in Abu Dhabi, which is also integral to Adnoc Group’s AiP5 campaign.

    The South East cluster comprises the Asab, Mender, Qusahwira, Sahil and Shah fields and accounts for approximately a third of Adnoc Onshore’s oil production capacity.

    MEED previously reported that Adnoc Onshore awarded CPECC the EPC works for the South East off-plot facilities project, with the contract value estimated at around $1.2bn.

    CPECC is also performing EPC works on the South East on-plot facilities project in a consortium with Greece-headquartered Archirodon. Adnoc Onshore awarded an estimated $1.5bn contract for that project to the consortium in December 2024, with EPC works scheduled for completion in 2027.

    ALSO READ: Adnoc Onshore seeks bids for Bu Hasa field EOR project

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20757699/main.jpeg
    Indrajit Sen