Transmission and distribution sector heads for record year
3 October 2024
The GCC region’s power transmission and distribution (T&D) sector is set to experience its best year in terms of the value of awarded contracts.
Based on data from regional projects-tracking service MEED Projects, the total value of awarded contracts for substations, control centres, overhead lines and cables across the six GCC states reached an estimated $13.8bn between January and September 2024.
This figure already exceeds by 81% the total value of contracts awarded in the preceding full year.
It also exceeds by 31% the total value of awarded contracts in 2021, which registered a record-high of $10.5bn in the 10 years starting in 2014.
Project activity within the T&D sector is expected to remain buoyant over the next few years, with roughly $35.9bn-worth of planned and unawarded contracts.
Of these, some $8.5bn are in the bid evaluation stage as of early October, with a further $6.5bn under tendering.
Some $12bn of projects are in the front-end engineering and design (feed) phase.
Energy diversification
Ambitious national energy diversification and net-zero targets across the region, which traditionally relied almost entirely on thermal power plants, will spur significant investments in T&D infrastructure in the future.
According to experts, the ongoing expansion of electricity generation capacity across the region, particularly from renewable energy sources, requires a more robust, integrated and stable electricity grid.
This is in addition to the projected increase in electricity demand as most states expand their downstream and petrochemical sectors, develop new communities and megaprojects in remote regions, and build more data centres to support smart cities, and internet-of-things (IoT) and artificial intelligence (AI) applications.
The region’s largest economy, Saudi Arabia, for instance, aims for renewable energy to account for 50% of its electricity generation capacity by 2030.
Operational renewable installed capacity in the kingdom jumped from roughly 300MW in 2020 to 3,500MW this year, with a further 16,000MW currently under construction or about to start construction, and gigawatts more under tender.
Crucially, the kingdom’s energy minister confirmed earlier this year that the kingdom has plans to procure up to 20,000MW of renewable capacity every year, subject to demand.
Saudi Arabia is also ramping up its procurement programme for new gas-fired power plants, in line with a plan to decommission fleets running on liquid fuel and at the same time secure baseload as more renewable energy enters the grid.
There is also a marked increase in terms of T&D packages or contracts interconnecting the kingdom’s various regions from central Riyadh to the eastern, northern and southern provinces.
It comes as no surprise that the kingdom accounted for 72% of the $13.8bn-worth of T&D contracts awarded in the GCC region in the first three quarters of 2024.
Oman, which awarded T&D contracts with the same value as the UAE between January and September this year, has also been working to integrate its smaller electricity grids with the sultanate’s main electricity grid to boost electricity supply in its smaller, remote regions.
Unlike the noticeable peaks and throughs in T&D capital expense in other GCC states, the UAE’s spending has remained pretty consistent since 2014, averaging roughly $1.4bn annually. The exemption was in 2021 when a team comprising South Korea’s Kepco, Japan’s Kyushu Electric Power Company (Kyuden) International and France’s EDF won the contract to develop Abu Dhabi’s first high-voltage, direct current (HVDC) subsea transmission system.
It is worth mentioning that the completion of the four units of Abu Dhabi’s 5,600MW Barakah nuclear power plant this year and the expected completion of Dubai’s first hydropower plant in Hatta mean the UAE will have the most diverse energy sources for electricity generation among its peers.
Power links
The goal to expand electricity trade within the GCC member states and with other countries such as Egypt, Jordan and Iraq is another key driver for T&D investments.
Work is under way to increase the capacity of the GCC regional grid and enable its member-states to procure backup or emergency capacity when the need arises. Kuwait availed of this in May when it purchased 500MW from the GCC grid in anticipation of its inability to meet peak demand in the summer months.
An HVDC network linking Saudi Arabia and Egypt is under construction, which will allow bidirectional electricity trade as well as access to the wider European and African markets.
A second GCC link with Oman and a first link with Jordan are also planned. Another HVDC transmission project linking Neom in the northern tip of the Red Sea to Yanbu, stretching 605 kilometres, is under way.
It turns out that the need to invest in T&D infrastructure to support electricity generation capacity buildout, following years of underinvestment, is a global phenomenon.
Juan Diego Zuluaga, Suncolombia CEO, told the ongoing World Green Energy Summit in Dubai that there is a major mismatch between the buildout of transmission lines and electricity generation capacity.
Experts like Zuluaga think that failing to invest in T&D can potentially lead to issues such as curtailment or wastage in renewable power, particularly in the absence of suitable energy storage systems or efficient interconnections or electricity links.
Utility companies are under pressure not only to expand their transmission capacities and coverage but to make these infrastructure and facilities more efficient, too.
New technologies, most of them driven by IoT or AI, for instance, can be used to improve demand and supply management and forecasting, leading to improved grid performance.
“In this region, in particular, consumers expect 24x7 electricity supply. In fact, it is a given,” notes a senior executive with a European technology company. “The hope is for that to continue in the future.”
Exclusive from Meed
-
Local firm wins contract for Kuwait power project19 November 2025
-
UKEF issues $3.5bn interest letter for Al-Maktoum airport19 November 2025
-
Riyadh gives Expo infrastructure bidders more time19 November 2025
-
NHC and Turkish firm sign $266m investment deal19 November 2025
-
Egypt announces oil discovery in Western Desert19 November 2025
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Local firm wins contract for Kuwait power project19 November 2025
Local firm Alghanim International has won a contract to provide engineering services at the Subiya power and water distillation plant.
Kuwait’s Central Agency for Public Tenders approved the award following a request from the Ministry of Electricity, Water & Renewable Energy.
The contract, valued at $286m, covers engineering, supply, installation, operation and maintenance services to convert the 250MW second phase of the plant’s open-cycle gas turbines to combined-cycle gas turbines.
The upgrade is intended to increase efficiency and provide additional generation capacity during periods of high demand.
In July, MEED reported that Alghanim had submitted the lowest bid for the tender ahead of local firms Al-Daw Engineering General Trading & Contracting and Al-Zain United General Trading & Contracting.
In 2024, US-based GE Vernova completed separate upgrades of four GE Vernova 9F.03 class gas turbines at the 2GW Sabiya combined-cycle power plant. Alghanim International acted as GE’s local engineering partner for that work.
The Subiya power and water distillation plant is the largest power and water plant in Kuwait, with a power generation capacity of 7,046.7MW, accounting for 35% of the country’s installed capacity.
It has a water desalination capacity of 100 million imperial gallons a day.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15116135/main.jpg -
UKEF issues $3.5bn interest letter for Al-Maktoum airport19 November 2025
Register for MEED’s 14-day trial access
The UK’s export credit agency UK Export Finance (UKEF) has issued a $3.5bn expression of interest letter to support the participation of UK businesses in the $35bn expansion of Al-Maktoum International airport, which is also known as Dubai World Central (DWC).
Chris Bryant, UK minister for trade, handed the letter to Khalifa Al-Zaffin, executive chairman of Dubai Aviation City Corporation and Dubai Aviation Engineering Projects (DAEP), and Paul Griffiths, CEO of Dubai Airports.
Letters of interest from UKEF, although not binding commitments, help ensure that UK exporters are given every opportunity to bid for contracts on a project. This is typically achieved by providing financial solutions in exchange for an agreed level of UK content used on the project.
Previous letter
It is not the first time UKEF has issued a letter of interest for the expansion of Al-Maktoum International airport. In 2014, it issued a $2bn letter of interest. In a statement at the time, UKEF said five prime UK-based contractors were being supported, along with UK suppliers across the supply chain.
The five prime contractors were Carillion, Kier, Balfour Beatty, Laing O’Rourke and Interserve. Of those five companies, Carillion entered liquidation in 2018 and Interserve entered administration in 2019. Balfour Beatty sold its shareholding in Dubai-based Dutco Balfour Beatty in 2017.
Although some progress was made on the project after the UKEF offer in 2014, the scheme stalled and was revived again in April 2024, when Dubai approved new designs for the airport.
Project progress
Since then, the project client, DAEP, has been awarding and tendering contracts for the first construction packages. It has awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.
The enabling works for the terminal building are being undertaken by Abu Dhabi-based Tristar E&C.
DAEP is also close to formally awarding a contract for the substructure works for the West Terminal and Concourse One, Concourse Two and Concourse Three.
Tendering is also ongoing for an automated people-mover (APM) system. The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.
Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.
The airport’s construction is planned to be undertaken in three phases. Construction works on the project’s first phase are expected to be completed by 2032.
The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.
It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.
Dubai has said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.
This aviation package also includes:> Middle East invests in giant airports
> Broader region upgrades its airports
> Global air travel shifts easthttps://image.digitalinsightresearch.in/uploads/NewsArticle/15115788/main.jpg -
Riyadh gives Expo infrastructure bidders more time19 November 2025

Saudi Arabia’s Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, has extended the deadline for firms to submit commercial offers for the contract to undertake the initial infrastructure works at the site to 23 November.
ERC had initially set deadlines of 26 October and 9 November for the submission of technical and commercial bids, respectively.
The tender for the project’s initial infrastructure works was issued in September, as MEED reported.
In October, MEED revealed that 16 firms had been invited to bid for the contract to undertake the initial infrastructure works at the Expo 2030 Riyadh site.
The firms invited to bid include:
- Shibh Al-Jazira Contracting (local)
- Hassan Allam Construction (Egypt)
- El-Seif Engineering Contracting (local)
- Al-Ayuni Investment & Contracting (local)
- Kolin Construction (Turkiye)
- Al-Yamama Trading & Contracting Company (local)
- Saudi Pan Kingdom (local)
- Unimac (local)
- Mapa Insaat (Turkiye)
- Yuksel Insaat (Turkiye)
- IC Ictas / Al-Rashid Trading & Contracting (Turkiye/local)
- Mota-Engil / Albawani (Portugal/local)
- Almabani / FCC Construction (local/Spain)
The overall infrastructure works – covering the construction of the main utilities and civil works at Expo 2030 Riyadh – will be split into three packages:
- Lot 1 covers the main utilities corridor
- Lot 2 includes the northern cluster of the nature corridor
- Lot 3 comprises the southern cluster of the nature corridor
MEED previously reported that ERC was expected to issue the tender for some of the infrastructure packages in September.
In July, US-based engineering firm Bechtel Corporation announced it had won the project management consultancy deal for the delivery of the Expo 2030 Riyadh masterplan construction works.
The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, providing direct access to various landmarks within Riyadh.
Countries participating in Expo 2030 Riyadh will have the option to construct permanent pavilions. This initiative is expected to create opportunities for business and investment growth in the region.
The expo is forecast to attract more than 40 million visitors.
The Public Investment Fund (PIF), Saudi Arabia’s sovereign wealth vehicle, launched ERC in June as a wholly owned subsidiary to build and operate facilities for Expo 2030.
In a statement, the PIF said: “During its construction phases, Expo 2030 Riyadh and its legacy are projected to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs. Once operational, it is expected to contribute approximately $5.6bn to GDP.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/15115697/main.jpg -
NHC and Turkish firm sign $266m investment deal19 November 2025
Register for MEED’s 14-day trial access
Saudi Arabia’s National Housing Company (NHC) has signed an investment agreement worth over SR1bn ($266m) with Turkiye’s Emlak Konut to develop new residential communities within the Mecca Gate project in Mecca.
The agreement was signed on the sidelines of the Cityscape Global 2025 event in Riyadh.
Emlak Konut will develop 1,000 residential villas spanning over 255,000 square metres (sq m).
The latest agreement follows the NHC’s signing of deals worth over SR8.5bn ($2.2bn) for the development of two mixed-use and residential communities in Riyadh.
The first agreement, worth over SR5.2bn ($1.4bn), was signed with local developer Retal Urban Development Company.
The deal encompasses the development of 4,839 residential units in the Al-Fursan suburb of Riyadh.
The other contract, worth over SR3.3bn ($880m), was signed with a joint venture of Egypt’s Hassan Allam Holding and local developer Tilal Real Estate for a mixed-use project in the Khozam district.
The development will cover an area of over 228,000 sq m.
It will be delivered through Grova Developments, the development arm of Hassan Allam Holding.
In 2023, NHC and Saudi Arabia’s Housing Ministry signed investment agreements totalling more than SR24bn ($6.4bn) to launch the Al-Fursan residential project.
Al‑Fursan is described as the largest scheme in terms of area and number of housing units that NHC is implementing in partnership with other real estate developers.
MEED reported in 2020 that Riyadh planned to oversee the development of more than 1 million homes by 2025 to meet growing demand in the kingdom.
By 2030, the Saudi capital aims to more than double its population, from 7-8 million to 15-20 million, and become one of the 10 wealthiest cities in the world.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15115626/main.png -
Egypt announces oil discovery in Western Desert19 November 2025
Register for MEED’s 14-day trial access
A new gas discovery has been made in Egypt’s Western Desert region, according to a statement released by the Ministry of Petroleum & Mineral Resources.
The discovery was made by Khalda Petroleum Company, a joint venture of state-owned Egyptian General Petroleum Corporation (EGPC) and US-headquartered Apache Corporation.
The field is expected to be brought online this week, according to the ministry.
The reserves were discovered after drilling the exploratory well ‘Gomana-1’, the ministry said.
It added that sensors confirmed the presence of gas reserves, and tests indicated that the well is expected to have a production rate of around 36 million standard cubic feet of gas a day.
Further tests are ongoing, and the initial evaluation of the well’s reserves is currently being finalised.
The ministry said that the discovery followed the introduction of new incentives designed to encourage additional gas investment within Khalda’s areas of operation.
Earlier this month, Egypt started gas production from the West Burullus field in the Mediterranean Sea, after connecting the first wells to the national gas grid.
The country is currently pushing to increase domestic gas production in order to meet domestic demand and reduce its import bill.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15112551/main.png



