Traffic drives construction underground

3 April 2025

 

On 14 February, Dubai construction was thrust again onto the global stage when Elon Musk, the world’s richest man, announced plans to explore the development of an underground Dubai Loop transportation system, along the lines of the Las Vegas Convention Centre Loop project in the US.

Dubai has typically made headlines globally by constructing the world’s tallest towers. As the city becomes increasingly congested on the surface, it is taking some of its largest construction projects underground.

With Musk’s backing, the Dubai Loop scheme is the most high-profile tunnelling project launched to date. It involves carving a futuristic transport system underneath Dubai. The initial phase of the project is currently being studied by Dubai’s Roads & Transport Authority (RTA) in partnership with The Boring Company, which is owned by Musk. It will cover 17 kilometres (km) and have 11 stations, with the capacity to transport over 20,000 passengers an hour.

The project highlights the importance of expanding underground infrastructure in the Middle East region. This is mostly necessitated by the pressure that rapidly growing cities have put on existing transport and utility networks, particularly in major urban centres such as Dubai, Riyadh and Doha.

Underground opportunities

Projects that involve tunnelling, such as metro rail systems, underground highways and pedestrian walkways, are deemed key enablers in reducing congestion and optimising land use.

The recently completed metro systems in Riyadh and Doha are examples of how underground rail networks can facilitate efficient urban mobility, and more such schemes are planned. 

Without these subterranean projects, cities risk being stuck in a permanent state of gridlock, with longer commute times and decreased productivity. At the same time, tunnelling allows urban planners to integrate sustainable transport solutions, as well as large-scale utilities networks, without disturbing existing cityscapes, thereby enhancing connectivity and economic growth.

These developments signal a major shift in engineering priorities, with regional governments investing in underground transport, sewerage and metro extensions to accommodate their growing populations and infrastructure needs.

While the tower crane-dotted skylines of urban centres in the GCC attract attention, delivering major projects underground is an equally impressive engineering feat. Tunnelling under busy cities requires advanced excavation techniques, careful planning and coordination to avoid disruptions.

More tunnelling work is expected as Dubai takes another significant step forward in tackling its ongoing traffic problems [with] a new metro link

UAE tunnelling projects

Tunnelling work forms a significant portion of the Dubai Metro Blue Line extension. Awarded in December for AED20.5bn ($5.5bn), the project includes 15.5km of underground track and five subterranean stations. When operational in 2029, the Blue Line will significantly expand Dubai’s metro capacity, linking major residential and commercial hubs.

More tunnelling work is expected as Dubai takes another significant step forward in tackling its ongoing traffic problems by starting the procurement process for its next metro link: the Gold Line.

Although the technical details of the project have yet to be revealed, it is expected that tunnels will form a major component of the scheme given that the new line will run through busy urban areas where there is little space to build overground. 

The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.

As a first step, the RTA has sent a request for proposals to companies for the lead consultancy role on the multibillion-dollar project.

The UAE’s Etihad Rail also began a study of the tunnels required for the high-speed railway line connecting Abu Dhabi and Dubai in January. The survey works are ongoing on the Jaddaf and Dusup tunnels that will serve the high-speed rail link. Initial plans for the project include tunnelling works totalling 31km.

Another major tunnelling project in the UAE is the $22bn Dubai Strategic Sewerage Tunnels scheme. The client, Dubai Municipality, is preparing to tender its first packages, which include deep tunnels that will stretch 42km in Jebel Ali and 16km in Warsan.

The project will be delivered under a public-private partnership model, with international consortiums competing for contracts. Once completed, these tunnels will replace the traditional wastewater network, reducing energy consumption and enhancing long-term sustainability.

Saudi schemes

In Saudi Arabia, Riyadh is preparing to expand its metro network with the addition of a Line 7 and an extension to the existing Line 2.

The total length of Line 7 will be about 65km, of which 47km will be underground. The line will have 19 stations, 14 of which will be underground.

The project involves constructing a metro line linking the Qiddiya entertainment city development, King Abdullah International Gardens, King Salman Park, Misk City and Diriyah Gate. 

In March, the Royal Commission for Riyadh City (RCRC) gave consortiums until 15 June to submit their bids for a design-and-build contract for the construction of Line 7.

The planned Line 2 extension is 8.4km long, of which 7.1km is underground, and three out of its five stations will be built underground. The RCRC is expected to award the construction contract this year.

In January, the kingdom also completed the phased roll-out of the Riyadh Metro network. The current network comprises six lines spanning about 176km, of which 74km is constructed underground.

These numbers indicate that over 42% of the overall network is underground, highlighting the growing importance of tunnels in the kingdom’s plans to improve infrastructure in its most densely populated cities.

Tunnelling works are also a key component of the plans to improve the stormwater drainage system in Jeddah, where the municipality is preparing for the construction of the King Abdullah Road-Falasteen Road tunnel.

The three-year scheme involves constructing 5.3km of tunnels with an internal diameter of 7.2 metres using tunnel boring machines (TBMs) and another 3.4km of tunnels with a diameter of 3.5 metres driven by pipe jacking or TBMs.

At the kingdom’s Neom gigaproject, city planners are looking to find solutions to many of the problems faced in existing cities and, as a result, tunnels and large-scale underground utilities corridors are being built at the beginning of the project. For example, the development’s Delta Junction tunnels will serve as a railway junction connecting the Spine infrastructure corridor with the Neom Connector rail link to the Oxagon industrial zone. 

The project involves 26.5km of tunnelling work that will be split into a north and a south lot. The construction works are expected to begin this year as the client is evaluating the revised proposals submitted by firms in November last year.

Kuwait Metro will feature extensive tunnelling … ensuring minimal disruption to existing roads while integrating with future transport networks

Further tunnel projects

Beyond the Gulf, Egypt has a long history of tunnelling projects, as it has had to deal with crippling congestion and urban overcrowding for decades. In the 1980s, work was completed on two major projects that involved tunnelling: the first phase of the Cairo Metro system and the Greater Cairo wastewater project, which involved the construction of sewage tunnels on the east and west banks of the Nile. 

Today, Cairo’s tunnelling projects include the Cairo Metro Line 4 project. Spanning 42km with 39 stations, it involves over 20km of tunnels.

Meanwhile, in Morocco, national railway operator L’Office National des Chemins de Fer (ONCF) is constructing a tunnel project in Rabat.

In February, ONCF announced a 3.3km tunnel to be constructed under the Bou Regreg river at an estimated cost of MD1.4bn ($140m). The tunnel will connect the Sale and Agdal stations in an effort to alleviate traffic.

Similarly, the long-awaited Kuwait Metro will feature extensive tunnelling to navigate the dense urban fabric of Kuwait City, ensuring minimal disruption to existing roads while integrating with future transport networks. 

Qatar’s expansion of Doha Metro, meanwhile, requires additional underground infrastructure to connect developing areas and support the country’s vision for a comprehensive public transport system. 

Mecca Metro, already serving millions of pilgrims, is also set for further expansion, likely involving significant tunnelling to facilitate smoother access to holy sites while overcoming geographic constraints. 

In Oman, the Muscat Metro project is likewise expected to link key districts while preserving the city’s landscape and avoiding disruptions to arterial roads by introducing underground sections. 

All of these projects show that tunnels will play an important role in the region’s future as it strives to create cities with more efficient and environmentally sustainable transit and utilities systems. 

https://image.digitalinsightresearch.in/uploads/NewsArticle/13561811/main.gif
Yasir Iqbal
Related Articles
  • Oil prices rise above $100 a barrel as conflict escalates

    9 September 2026

    Register for MEED’s 14-day trial access 

    Oil prices rose above $100 a barrel on 9 September for the first time since July as the US-Iran conflict escalated and Iran-backed Houthi forces attacked Saudi energy infrastructure.

    Brent crude futures reached $100.95 a barrel, while US benchmark West Texas Intermediate (WTI) rose to $95.60. Brent had last traded above $100 on 24 July.

    The latest escalation has heightened concerns about oil supplies from the region, with shipping through both the Strait of Hormuz and the Red Sea facing disruption.

    Flows through the Strait of Hormuz had fallen below 2 million barrels a day (b/d) from about 8-9 million b/d before the latest escalation, according to Rystad Energy.

    At the same time, Houthi attacks on Saudi Arabia threaten another important route for oil exports, with the group targeting energy infrastructure and shipping in and around the Red Sea.

    US strikes on Iranian tankers

    US forces destroyed five Iranian crude oil carriers on 8 September after Iran’s Islamic Revolutionary Guard Corps (IRGC) targeted a US Navy warship with ballistic missiles.

    The US Central Command (Centcom) said the warship successfully evaded two Iranian attacks and that no US personnel were harmed.

    Four of the Iranian vessels – Kaviz, Charminar, Horizon 1 and Riesco – were struck in the Gulf of Oman, while the Derya was attacked near Kharg Island, Iran’s main crude export hub.

    The M/T Riesco subsequently sank in the Gulf of Oman, according to Centcom.

    Iran responded by launching ballistic missiles towards Jordan. Jordan’s armed forces said 18 of 20 missiles were intercepted, with the remaining two falling in unpopulated areas.

    Iran’s IRGC also said it had attacked two US naval vessels, eight oil tankers and 10 other vessels in the Gulf, although it did not identify the vessels or provide evidence of the attacks.

    The latest exchanges mark a further escalation in the US-Iran conflict, which began on 28 February.

    Houthi attacks raise supply concerns

    The conflict has also widened into a renewed confrontation between Saudi Arabia and Yemen’s Iran-backed Houthi movement.

    On 8 September, Saudi authorities said Houthi attacks had targeted civilian and economic sites in Abha, Khamis Mushait, Jazan and Najran in the south of the kingdom, injuring 73 people.

    Saudi Arabia’s Ministry of Energy said several energy sector facilities and installations had been targeted, causing fires and forcing a temporary halt to some operations.

    The Houthis said their attacks were in response to Saudi military action in Yemen, including what they described as attacks on Houthi positions and a Saudi blockade of ports and airports.

    Riyadh condemns attacks

    Saudi Arabia has strongly condemned the Houthi attacks and warned that it would take measures to defend its territory and national assets.

    In a statement on 8 September, the Ministry of Energy said authorities were working to address the impact of the attacks and ensure the safety of facilities and personnel while maintaining operations in accordance with approved plans.

    Saudi Arabia’s Ministry of Foreign Affairs also condemned the attacks and said the kingdom had the right to take measures to defend its sovereignty and protect its citizens, residents and national assets.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19505512/main0138.jpg
    Indrajit Sen
  • What actually slows a gigaproject down

    9 September 2026

     

    Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.

    “None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.

    For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.

    “The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.

    The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.

    “Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”

    Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.

    Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.

    Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.

    “The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”

    Integration needs to be well understood

    “Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.

    Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.

    Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.

    “The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”

    That shared view, he argues, will be what the next phase of Gulf delivery is judged on.

    Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.

    “This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.

    From reporting progress to managing risk before it lands

    Digital tools have a role here, Caldwell says, but not as a headline in themselves.

    Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.

    “The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."

    None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”

    Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.

    With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.

    “The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.

    What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.

    “The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif
    Yasir Iqbal
  • Qatari firm wins $221m Qiddiya stadium MEP deal

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Qatari contractor Elegancia MEP, part of Estithmar Holding, has won a SR829m ($221m) mechanical package contract for the Prince Mohammed Bin Salman Stadium in Qiddiya, Saudi Arabia.

    The contract covers full mechanical, electrical and plumbing (MEP) works for the stadium, and is Elegancia MEP’s largest award in Saudi Arabia to date.

    The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.

    The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.

    Saudi gigaproject developer Qiddiya Investment Company awarded an estimated SR15bn ($4bn) deal to build the stadium in October 2024, as MEED exclusively reported.

    The contract covered the construction of a multipurpose stadium on top of the 200-metre-high Tuwaiq cliff in the new sports and entertainment district of Qiddiya City.

    Once completed, the stadium will be the home ground for Saudi Pro League football clubs Al-Nassr and Al-Hilal.

    US-based architect Populous is the project consultant.

    The stadium is one of the venues for the kingdom’s 2034 Fifa World Cup bid and will host events such as the Saudi King Cup, the Asian Cup and the 2034 Asian Games.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19501493/main.jpg
    Yasir Iqbal
  • Jordan tenders advisory for wastewater treatment plant

    9 September 2026

    The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.

    The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).

    The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.

    The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.

    The submission deadline is 21 September.

    The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.

    The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.

    The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.

    WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.

    The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.

    The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg
    Mark Dowdall
  • Consultants bid for Abu Dhabi light rail project management

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.

    The notice was issued on 7 September, with a submission deadline of 9 November.

    The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.

    The key sections of the tram are:

    AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.

    This section covers 13km and includes 13 at-grade stations and one underground station.

    Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.

    Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.

    The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.

    The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.

    Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.

    Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.

    Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.

    The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19493532/main.jpg
    Yasir Iqbal