TotalEnergies and OQ break ground on Marsa LNG project

2 May 2025

France’s TotalEnergies and OQ Exploration & Production (OQEP), a subsidiary of Omani state energy conglomerate OQ Group, have broken ground on the Marsa liquefied natural gas (LNG) bunkering and export terminal project in Oman.

The estimated $1.6bn LNG project is being built in the sultanate’s northern port city of Sohar and will have a production capacity of 1 million tonnes a year (t/y).

TotalEnergies is the majority stakeholder in the Marsa LNG project, holding an 80% interest, with OQ Group, through OQEP, holding the remaining 20% stake.

LNG production from the facility is expected to start in the first quarter of 2028, TotalEnergies and OQ said in a joint statement.

The Marsa LNG project will primarily supply marine fuel to vessels such as container ships, tankers and large cruise ships, and is said to be the first marine LNG bunkering hub in the Middle East.

Last April, TotalEnergies awarded Technip Energies the main contract to execute engineering, procurement and construction (EPC) works on the Marsa LNG project.

US-based Chicago Bridge & Iron (CB&I) won a contract to build the main concrete LNG storage tank, which will have a capacity of 165,000 cubic metres, and to complete the associated piping upgrade. The firm described its contract as being “significant”, a term it uses to denote a value range of $100m-$250m.

In addition to awarding the EPC contracts for the project, TotalEnergies and OQ also achieved the final investment decision on the Marsa LNG project last April. Marsa LNG was formed in December 2021 through a joint-venture agreement between the two companies.

Marsa LNG infrastructure contracts

Along with the groundbreaking ceremony on 1 May, Oman’s Sohar Port & Freezone, where the Marsa LNG terminal is being built, also awarded three contracts covering infrastructure and other services related to the project.

WSP International’s Oman branch was awarded a consultancy services contract, to provide project management, back-office support, design review, site supervision and contract management services, with the contract running from November 2024 to November 2028.

The second contract was signed with the Netherlands-headquartered Boskalis International’s Oman branch for dredging works, involving the removal of approximately 3.8 million cubic metres of material to develop the access channel, berth pocket and turning circle, with completion expected in September.

Sohar Port & Freezone announced the start of dredging works on the Marsa LNG project in March, when Boskalis was contracted for the job.

The third contract was awarded to Six Construct’s Oman branch, covering the construction of the LNG jetty, shore protection and drainage systems, with a duration of 16 months.

MEED also recently reported that Technip Energies, as the main EPC contractor on the Marsa LNG project, had awarded a couple of sub-contracts to local firms.

Sarooj Construction Company won a sub-contract for temporary construction facilities at the Marsa LNG terminal project site. Industrial Technology Services (Intecs) was sub-contracted by Technip Energies to perform civil works and construct utility buildings.

LNG production

The Marsa LNG facility will consist of a single processing train that will draw up to 150,000 cubic feet a day of natural gas feedstock from the Mabrouk Northeast field, located in Oman’s onshore Block 10 concession.

TotalEnergies is part of a consortium that operates the Block 10 hydrocarbons concessions in the sultanate. Oman’s Energy & Minerals Ministry signed a concession agreement in December 2021 with a consortium led by Shell Integrated Gas Oman, the Omani subsidiary of UK-based energy major Shell, to develop and produce natural gas from Block 10.

As part of the concession agreement, Shell operates Block 10, holding a 53.45% working interest, with OQ and Marsa LNG holding 13.36% and 33.19% stakes, respectively.

TotalEnergies is also a 22.5% stakeholder in the Block 11 onshore concession, from which the Marsa LNG project could draw gas feedstock in the future. Shell Development Oman is the majority (67.5%) stakeholder in Block 11, for which the Omani government signed an exploration and production sharing agreement in September 2022.

Solar-powered LNG terminal

The Marsa LNG complex will be completely electrically driven and supplied with solar power. The project will be “one of the lowest GHG [greenhouse gas] emissions intensity LNG plants ever built worldwide”, with a GHG intensity below 3 kilogrammes of carbon dioxide per barrel of oil equivalent, the partners said in a statement.

TotalEnergies said it is in an “advanced stage of discussions” with OQ’s renewable energy branch, OQ Alternative Energy, to jointly develop a portfolio of up to 800MW, including a 300MW solar project that will supply power to the Marsa LNG facility. The two companies will form a joint venture in which OQ Alternative Energy will own 51% stake, with TotalEnergies holding the other 49%.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13803437/main5008.jpg
Indrajit Sen
Related Articles
  • EtihadWE tenders $150m Ajman substation project

    21 July 2026

    The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.

    Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.

    The bid submission deadline is 10 August.

    According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.

    The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.

    Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.

    This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.

    EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.

    In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.” 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg
    Mark Dowdall
  • Seven seeks contractors for Dammam water park and hotel

    21 July 2026

     

    Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.

    The waterfront development sits on a 324,300-square-metre (sq m) plot.

    A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.

    Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.

    The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.

    The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.

    Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.

    Detailed design and issued-for-construction packages are complete.

    Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.

    The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.

    The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.

    Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.

    Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.

    The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.

    The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg
    Yasir Iqbal
  • Al-Ula appoints equestrian village early works contractor

    21 July 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.

    The contract was awarded to Al-Khobar-based Al-Shalawi International Company.

    Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.

    Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.

    RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.

    The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.

    These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg
    Yasir Iqbal
  • Contractors await decision on Riyadh airport sewage plant

    21 July 2026

     

    Seven contractors are awaiting a decision on a contract to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh, according to sources.

    It is understood that bids were submitted to King Salman International Airport Development Company (KSIADC) in March, following the tender’s release earlier this year.

    The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.

    The facility will have a treatment capacity of 92,000 cubic metres a day. The contract is estimated to be worth SR700m ($187m).

    The bidders (all local) are:

    • Al-Rawaf Trading & Contracting
    • Almajal Alarabi
    • Nesma Water & Energy
    • Safari Company
    • Saudi Services for Electro-Mechanic Works
    • Washnah Contracting
    • Water & Environment Technologies (Wetico)

    The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.

    US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.

    The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction contract covering potable water and fire water tanks and an associated pumping station. The same seven companies have submitted bids for that package.

    Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.

    The latest development followed KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.

    These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17709281/main.jpg
    Mark Dowdall
  • Dubai Municipality awards Tasreef drainage contract

    21 July 2026

     

    Dubai Municipality has awarded local firm Detech Contracting the engineering, procurement and construction (EPC) contract for the TF-15-C1 package of its Tasreef Rainwater Drainage Network programme.

    It is understood the municipality issued the letter of award for the contract earlier this month, covering the construction of a stormwater drainage system along Al-Wasl Road and communities west of the Dubai Canal.

    The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.

    It was tendered in February through the government’s Sewerage and Recycled Water Projects Department, with bids submitted in April.

    The package forms part of the wider Tasreef initiative, which is intended to improve Dubai’s flood resilience.

    The TF-15-C2 package was recently awarded to China State Construction Engineering Corporation for a stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.

    The project is estimated to cost $162m and includes the construction of about 20 kilometres of new stormwater pipelines. Similar to the C1 package, it is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.

    Separately, Al-Kharafi has won a drainage EPC contract (Ds207) to upgrade an existing pumping station for the municipality, a source said. The package focuses mainly on mechanical works and is valued at about $39m.

    In May, MEED reported that local firm Nael Construction & Contracting had signed a contract with Dubai Municipality to build a sewage and stormwater drainage system in Dubailand.

    The project (DS-204-C1) involves the construction of a drainage system with sewage gravity pipelines of up to 2,200mm in diameter.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17707980/main.jpg
    Mark Dowdall