Top pending projects in 2024

27 December 2023

 

This report on 2024 projects also includes: Upcoming regional projects hit $270bn


$17.6bn
Neom City Development Programme

Project client: Neom

Since its launch in 2017, Saudi Arabia’s Neom has announced numerous masterplans – among them the 170-kilometre-long The Line, the partly offshore industrial city Oxagon and the Trojena mountain resort. These projects make up a large part of the $17.6bn of work currently under bid within the gigaproject.

As the $500bn gigaproject becomes a busy construction site, the construction industry has started to benefit from a sharp increase in contract awards. In 2023, Neom contract awards hit $10bn, making it a major regional market in its own right – one that is only surpassed by Saudi Arabia, the UAE and Qatar.

$3.6bn
The Line

Significant progress has been made on the construction of The Line. Work on The Line’s backbone infrastructure tunnels began in June 2022, when Neom awarded $2.7bn-worth of contracts for lots two and three of the scheme to a joint venture of Shibh al-Jazira Contracting, China State Construction Engineering Corporation and FCC Construction.

Another contract worth about $1.8bn for lots four and five was awarded to a team of Archirodon, Samsung Engineering and Hyundai Engineering.

Neom is prioritising the construction of the railway that forms part of the infrastructure corridor known as the Spine within its phased delivery plan. In August 2023, Neom awarded package A3 for the mountain railway tunnels on The Line to China Construction Third Engineering Bureau. The same month, Neom invited companies to bid for the $500m track works as part of the railway network programme along the spine of The Line. The contract award is expected in the first quarter of 2024.

$4.1bn
Oxagon

The Oxagon industrial city, launched in late 2021, is a 48 square-kilometre development that includes onshore elements as well as floating structures offshore. Its port, Duba Port, is being expanded to act as a key conduit for the delivery of materials into Tabuk Province. Construction at the site is now well under way, with a team of Boskalis, Besix and the local Modern Building Leaders delivering the $800m first phase of the Duba Port expansion project. In October 2023, Belgium’s Deme and Greece’s Archirodon were also awarded the $1bn contract to complete the next phase of the port.

Looking ahead, contractors have submitted bids for packages one and two of the Delta Junction tunnel project as part of the Neom Industrial City Connector at Oxagon. The scheme is likely to be awarded in early 2024 and is split into two packages covering 26.5km of tunnelling.

$3.7bn
Trojena

Neom is steadily advancing its plans to deliver several key components of Trojena, with Saudi Arabia set to host the 2029 Asian Winter Games at the location in 2022. It recently completed the technical evaluation of the proposals for the Trojena dams, and the client and selected contractors are now negotiating the commercial aspects of the project.

In 2023, Neom engaged three contractors on an early contractor involvement basis: a consortium of the local Al-Ayuni with Turkiye-headquartered Limak; Beijing-based PowerChina; and Italy’s WeBuild. In October, Neom awarded a $1.2bn infrastructure development contract at Trojena to a joint venture of the local Al-Ayuni Investment & Contracting and Turkish Limak Holding. In August 2023, the tender was issued for the contract to construct the shell and core components of the Vault at Trojena. 

In 2023, Neom contract awards hit $10bn, making it a major market in its own right – surpassed only by Saudi Arabia, the UAE and Qatar


$7.7bn
National Renewable Energy Programme

Project client: SPPC

In November 2023, Saudi Power Procurement Company (SPPC) kicked off the procurement process for the fifth round of Saudi Arabia’s National Renewable Energy Programme, issuing the request for qualifications for a new batch of four solar power plant projects.

Saudi Arabia has publicly tendered over 6.6GW of renewable energy capacity since 2017, of which about 4.4GW, or 66 per cent of the total tendered capacity, has been for photovoltaic solar schemes. SPPC is set to procure 30 per cent of the kingdom’s target installed renewable energy capacity of 58.7GW by 2030. 


$7bn
UZ1000 Upper Zakum Expansion

Project client: Adnoc Offshore

The UZ1000 Upper Zakum expansion will increase the oil production potential of Abu Dhabi’s largest producing oil asset – the Upper Zakum offshore field – to 1.2 million barrels a day (b/d). The $7bn contract for the development of surface facilities on the project is the largest single project package currently under bid in the region. 

Bids for the work have been submitted by the UK’s Petrofac, the local Target Engineering Construction Company and Spain’s Tecnicas Reunidas.


$6bn
Duwaiheen nuclear power plant

Project client: Duwaiheen Nuclear Energy Company

The $6bn first package of Saudi Arabia’s Duwaiheen nuclear power plant entails the construction of two 2,800MW nuclear reactors on behalf of the special purpose vehicle the Duwaiheen Nuclear Energy Company. In November, the deadline for the tendering process was extended to 31 December, two months later than the previous deadline. Expected bidders include China National Nuclear Corporation, France’s EDF, Korea Electric Power Corporation and Russia’s Rosatom.


$4.8bn
Dubai Metro Blue Line

Project client: Dubai’s Roads & Transport Authority

The Dubai Metro Blue Line is a $4.8bn project that will connect the existing Red and Green lines by means of an additional 30km of track, 15.5km underground and 14.5km above ground, together with 12 additional stations and the expansion of connecting stations. The scope of the contract also includes the supply of 28 driverless trains, the construction of the train depot and all associated works. The project was tendered by the Roads & Transport Authority after the project was greenlit in November 2023. Expressions of interest are being sought from three experienced international consortiums.


$4.5bn
Ruwais LNG Terminal

Project client: Adnoc Gas Processing

Adnoc Gas Processing is evaluating bids for a liquefied natural gas (LNG) terminal at Ruwais, UAE, worth an estimated $4.5bn. This project involves constructing a plant that will add 9.6 million tonnes a year of liquefaction capacity and will be the first electric LNG plant in the Mena region. Bids for the projects have been submitted by South Korea’s Hyundai E&C, Japan’s JGC Corporation, the US’ McDermott, local firm NPCC, Italy’s Saipem and France’s Technip Energies.


$4bn
Al-Zour North IWPP: Phases 2 and 3

Project client: Kapp

The $4bn phases two and three of Kuwait’s Al-Zour North independent water and power project (IWPP) involve constructing a 2,700MW power plant coupled with a desalination facility with a capacity of 165 million gallons a day. The Kuwait Authority for Partnership Projects (Kapp) is currently reviewing the prequalification documents for five potential bidders.


$4bn
North Field Production Sustainability: Phase 2

Project client: QatarEnergy LNG

The $4bn phase two, scope D of the North Field Production Sustainability project in Qatar involves the delivery of two large offshore gas compression complexes that will weigh between 25,000 and 35,000 tonnes as part of a total of 100,000 tonnes of fabrication. Bid submissions are due in December 2023, and the expectation is that both US’ McDermott and Italy’s Saipem will make bids.


 Upcoming regional projects hit $270bn 

https://image.digitalinsightresearch.in/uploads/NewsArticle/11381755/main.gif
John Bambridge
Related Articles
  • Local firm wins contract for Kuwait power project

    19 November 2025

    Local firm Alghanim International has won a contract to provide engineering services at the Subiya power and water distillation plant.

    Kuwait’s Central Agency for Public Tenders approved the award following a request from the Ministry of Electricity, Water & Renewable Energy.

    The contract, valued at $286m, covers engineering, supply, installation, operation and maintenance services to convert the 250MW second phase of the plant’s open-cycle gas turbines to combined-cycle gas turbines.

    The upgrade is intended to increase efficiency and provide additional generation capacity during periods of high demand.

    In July, MEED reported that Alghanim had submitted the lowest bid for the tender ahead of local firms Al-Daw Engineering General Trading & Contracting and Al-Zain United General Trading & Contracting.

    In 2024, US-based GE Vernova completed separate upgrades of four GE Vernova 9F.03 class gas turbines at the 2GW Sabiya combined-cycle power plant. Alghanim International acted as GE’s local engineering partner for that work.

    The Subiya power and water distillation plant is the largest power and water plant in Kuwait, with a power generation capacity of 7,046.7MW, accounting for 35% of the country’s installed capacity.

    It has a water desalination capacity of 100 million imperial gallons a day.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15116135/main.jpg
    Mark Dowdall
  • UKEF issues $3.5bn interest letter for Al-Maktoum airport

    19 November 2025

    Register for MEED’s 14-day trial access 

    The UK’s export credit agency UK Export Finance (UKEF) has issued a $3.5bn expression of interest letter to support the participation of UK businesses in the $35bn expansion of Al-Maktoum International airport, which is also known as Dubai World Central (DWC).

    Chris Bryant, UK minister for trade, handed the letter to Khalifa Al-Zaffin, executive chairman of Dubai Aviation City Corporation and Dubai Aviation Engineering Projects (DAEP), and Paul Griffiths, CEO of Dubai Airports.

    Letters of interest from UKEF, although not binding commitments, help ensure that UK exporters are given every opportunity to bid for contracts on a project. This is typically achieved by providing financial solutions in exchange for an agreed level of UK content used on the project.  

    Previous letter

    It is not the first time UKEF has issued a letter of interest for the expansion of Al-Maktoum International airport. In 2014, it issued a $2bn letter of interest. In a statement at the time, UKEF said five prime UK-based contractors were being supported, along with UK suppliers across the supply chain.

    The five prime contractors were Carillion, Kier, Balfour Beatty, Laing O’Rourke and Interserve. Of those five companies, Carillion entered liquidation in 2018 and Interserve entered administration in 2019. Balfour Beatty sold its shareholding in Dubai-based Dutco Balfour Beatty in 2017.

    Although some progress was made on the project after the UKEF offer in 2014, the scheme stalled and was revived again in April 2024, when Dubai approved new designs for the airport.

    Project progress

    Since then, the project client, DAEP, has been awarding and tendering contracts for the first construction packages. It has awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works for the terminal building are being undertaken by Abu Dhabi-based Tristar E&C.

    DAEP is also close to formally awarding a contract for the substructure works for the West Terminal and Concourse One, Concourse Two and Concourse Three.

    Tendering is also ongoing for an automated people-mover (APM) system. The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.

    The airport’s construction is planned to be undertaken in three phases. Construction works on the project’s first phase are expected to be completed by 2032.

    The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.

    Dubai has said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.


    This aviation package also includes:

    > Middle East invests in giant airports
    > Broader region upgrades its airports
    > Global air travel shifts east

     

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15115788/main.jpg
    Colin Foreman
  • Riyadh gives Expo infrastructure bidders more time

    19 November 2025

     

    Saudi Arabia’s Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, has extended the deadline for firms to submit commercial offers for the contract to undertake the initial infrastructure works at the site to 23 November.

    ERC had initially set deadlines of 26 October and 9 November for the submission of technical and commercial bids, respectively.

    The tender for the project’s initial infrastructure works was issued in September, as MEED reported.

    In October, MEED revealed that 16 firms had been invited to bid for the contract to undertake the initial infrastructure works at the Expo 2030 Riyadh site.

    The firms invited to bid include:

    • Shibh Al-Jazira Contracting (local)
    • Hassan Allam Construction (Egypt)
    • El-Seif Engineering Contracting (local)
    • Al-Ayuni Investment & Contracting (local)
    • Kolin Construction (Turkiye)
    • Al-Yamama Trading & Contracting Company (local)
    • Saudi Pan Kingdom (local)
    • Unimac (local)
    • Mapa Insaat (Turkiye)
    • Yuksel Insaat (Turkiye)
    • IC Ictas / Al-Rashid Trading & Contracting (Turkiye/local)
    • Mota-Engil / Albawani (Portugal/local)
    • Almabani / FCC Construction (local/Spain)

    The overall infrastructure works – covering the construction of the main utilities and civil works at Expo 2030 Riyadh – will be split into three packages:

    • Lot 1 covers the main utilities corridor
    • Lot 2 includes the northern cluster of the nature corridor
    • Lot 3 comprises the southern cluster of the nature corridor

    MEED previously reported that ERC was expected to issue the tender for some of the infrastructure packages in September.

    In July, US-based engineering firm Bechtel Corporation announced it had won the project management consultancy deal for the delivery of the Expo 2030 Riyadh masterplan construction works.

    The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, providing direct access to various landmarks within Riyadh.

    Countries participating in Expo 2030 Riyadh will have the option to construct permanent pavilions. This initiative is expected to create opportunities for business and investment growth in the region.

    The expo is forecast to attract more than 40 million visitors.

    The Public Investment Fund (PIF), Saudi Arabia’s sovereign wealth vehicle, launched ERC in June as a wholly owned subsidiary to build and operate facilities for Expo 2030.

    In a statement, the PIF said: “During its construction phases, Expo 2030 Riyadh and its legacy are projected to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs. Once operational, it is expected to contribute approximately $5.6bn to GDP.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15115697/main.jpg
    Yasir Iqbal
  • NHC and Turkish firm sign $266m investment deal

    19 November 2025

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s National Housing Company (NHC) has signed an investment agreement worth over SR1bn ($266m) with Turkiye’s Emlak Konut to develop new residential communities within the Mecca Gate project in Mecca.

    The agreement was signed on the sidelines of the Cityscape Global 2025 event in Riyadh.

    Emlak Konut will develop 1,000 residential villas spanning over 255,000 square metres (sq m).

    The latest agreement follows the NHC’s signing of deals worth over SR8.5bn ($2.2bn) for the development of two mixed-use and residential communities in Riyadh.

    The first agreement, worth over SR5.2bn ($1.4bn), was signed with local developer Retal Urban Development Company.

    The deal encompasses the development of 4,839 residential units in the Al-Fursan suburb of Riyadh.

    The other contract, worth over SR3.3bn ($880m), was signed with a joint venture of Egypt’s Hassan Allam Holding and local developer Tilal Real Estate for a mixed-use project in the Khozam district.

    The development will cover an area of over 228,000 sq m.

    It will be delivered through Grova Developments, the development arm of Hassan Allam Holding.

    In 2023, NHC and Saudi Arabia’s Housing Ministry signed investment agreements totalling more than SR24bn ($6.4bn) to launch the Al-Fursan residential project.

    Al‑Fursan is described as the largest scheme in terms of area and number of housing units that NHC is implementing in partnership with other real estate developers. 

    MEED reported in 2020 that Riyadh planned to oversee the development of more than 1 million homes by 2025 to meet growing demand in the kingdom.

    By 2030, the Saudi capital aims to more than double its population, from 7-8 million to 15-20 million, and become one of the 10 wealthiest cities in the world.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15115626/main.png
    Yasir Iqbal
  • Egypt announces oil discovery in Western Desert

    19 November 2025

    Register for MEED’s 14-day trial access 

    A new gas discovery has been made in Egypt’s Western Desert region, according to a statement released by the Ministry of Petroleum & Mineral Resources.

    The discovery was made by Khalda Petroleum Company, a joint venture of state-owned Egyptian General Petroleum Corporation (EGPC) and US-headquartered Apache Corporation.

    The field is expected to be brought online this week, according to the ministry.

    The reserves were discovered after drilling the exploratory well ‘Gomana-1’, the ministry said.

    It added that sensors confirmed the presence of gas reserves, and tests indicated that the well is expected to have a production rate of around 36 million standard cubic feet of gas a day.

    Further tests are ongoing, and the initial evaluation of the well’s reserves is currently being finalised.

    The ministry said that the discovery followed the introduction of new incentives designed to encourage additional gas investment within Khalda’s areas of operation.

    Earlier this month, Egypt started gas production from the West Burullus field in the Mediterranean Sea, after connecting the first wells to the national gas grid.

    The country is currently pushing to increase domestic gas production in order to meet domestic demand and reduce its import bill.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15112551/main.png
    Wil Crisp