Top 15 Saudi stadium projects

30 August 2024

 

Saudi Arabia formally kicked off its World Cup participation process in October last year after announcing that it planned to bid to host the event. The announcement was a culmination of Riyadh’s football-focused strategy launched two years before when a consortium led by the kingdom’s sovereign wealth vehicle, the Public Investment Fund (PIF), completed the full acquisition of UK football club Newcastle United from St James Holdings in 2021.

The move was further solidified when Saudi Arabia was effectively confirmed as the host after Australia, the only other bidder for the tournament, withdrew from the race in October last year.

This was followed by Saudi Arabia’s official bid campaign reveal and the submission of its bid to Fifa to host the World Cup 2034 event in July. The official selection of Saudi Arabia as the 2034 host is expected to be confirmed on 11 December.

Saudi Arabia will likely invest hundreds of billions of dollars in developing the required infrastructure to host the event. Experience from previous World Cups, including the most recent one in Qatar, has shown that hosting the tournament can transform a country’s economy.

The tournament brings in fans from around the world to enjoy a month-long festival of football. After the 2022 tournament, Qatar issued a statement saying that more than 1.4 million fans had visited the country during the event.

The decision to host the Fifa World Cup 2034 is a pivotal moment for Saudi Arabia as it validates much of the social and economic change that the kingdom has embarked upon since Crown Prince Mohammed Bin Salman launched Vision 2030 back in 2016.

Building stadiums is the most prominent part of the bid to host the coveted Fifa World Cup.

According to the official bid book document submitted by Saudi Arabia in July, it will construct 11 new stadiums as part of its bid to host the Fifa World Cup 2034.

Eight out of the 15 stadiums are located in the capital, Riyadh, four in Jeddah and one each in Al-Khobar, Abha and Neom. 

The event requires a minimum of 14 all-seater stadiums, of which at least four should be existing structures. The capacity must be at least 80,000 seats for the opening and final matches, and for the semi-finals, there must be at least 60,000 seats. For all other matches, at least 40,000 seats are needed.

The kingdom has recently ramped up its announcements regarding building new stadiums across the country in preparation to host the event. 

1. King Salman Stadium

The King Salman Stadium will be the showpiece venue for the tournament. The US-based architectural firm Populous-designed stadium will cover an area of about 660,000 square metres (sq m) and have a seating capacity of over 92,000 spectators.

The stadium will host the opening and final games of the Fifa World Cup 2034 tournament. The construction of the stadium is expected to be completed by 2029.

  • Location: Riyadh
  • Companies involved: Populous
  • Match category: Opening and final games
2. King Fahad Sports City Stadium

The King Fahad Sports City Stadium is expected to be the venue for the semi-final. The stadium will be refurbished to increase its seating capacity from its current 58,000 seats to 70,200 seats.

The main contract bid submission process is ongoing and the project’s expansion works are expected to begin early next year. The stadium will also be a venue for the AFC Asian Cup 2027.

  • Location: Riyadh
  • Companies involved: Populous
  • Match category: Semi-final
3. Prince Mohammed Bin Salman Stadium, Qiddiya City

The Prince Mohammed Bin Salman Stadium will be built on top of a 200-metre-high Tuwaiq cliff located in the new sports and entertainment district of Qiddiya City.

The stadium will have a capacity to accommodate 46,979 spectators and will feature a fully combined retractable pitch, roof and LED wall. The construction works are expected to begin later this year. 

  • Location: Riyadh
  • Companies involved: Qiddiya Investment Company, Populous
  • Match category: Third-place playoff
4. New Murabba Stadium

The New Murabba Stadium will have the capacity to accommodate 46,010 spectators and will be built as part of the New Murabba downtown project in Riyadh.

The construction of the stadium is expected to be completed by 2032.

  • Location: Riyadh
  • Companies involved: New Murabba Development Company
  • Match category: Round of 32
5. Roshn Stadium

The Roshn stadium will be built in the southwest of Riyadh. The planned facility will have the capacity to accommodate 46,000 spectators and will span an area of over 450,000 sq m. 

  • Location: Riyadh
  • Companies involved: Roshn
  • Match category: Round of 32
6. Prince Faisal Bin Fahad Sports City Stadium

The Prince Faisal Bin Fahad Stadium is earmarked for an expansion that aims to increase its seating capacity from its current 22,188 seats to 46,865 seats. 

The facility will also host the AFC Asian Cup in 2027.

The refurbishment works will change the geometry of the seating bowl from an athletics stadium to a football stadium.

  • Location: Riyadh
  • Companies involved: Populous
  • Match category: Round of 32

Saudi World Cup bid bucks global trend for sporting events

7. South Riyadh Stadium

The Populous-designed stadium will be located in southwest Riyadh close to the Wadi Namar. The stadium will have the capacity to host 47,060 spectators. It is expected to be ready by 2032.

  • Location: Riyadh
  • Companies involved: Populous
  • Match category: Round of 32
8. King Saud University Stadium

The King Saud University Stadium, located on the university’s campus in the west of Riyadh, is one of the venues that will undergo expansion and refurbishment to host the event.

The expansion will increase the stadium’s capacity to 46,319 spectators and the construction works are expected to be completed by 2032.

  • Location: Riyadh
  • Companies involvedPopulous
  • Match category: Round of 32
9. King Abdullah Sports City Stadium

The King Abdullah Sports City Stadium is the home ground for the Al-Ittihad and Al-Ahli football clubs. The venue will undergo expansion works that will increase its seating capacity to 58,432 people. The stadium will host the quarter-final games.

  • Location: Jeddah
  • Companies involved: Arup
  • Match category: Quarter-final
10. Qiddiya Coast Stadium, Jeddah

The Populous-designed stadium will be situated at the heart of the Qiddiya Coast development in Jeddah. The multi-purpose stadium will have a 46,096 seating capacity and will be one of the venues for the round of 16 matches.

  • Location: Jeddah
  • Companies involved: Populous
  • Match category: Round of 16
11. Jeddah Central Stadium, Jeddah

The already under-construction football stadium is part of the Jeddah Central Project in Jeddah and has a seating capacity of 45,794 spectators. The stadium is expected to be completed by 2027.

  • Location: Jeddah
  • Companies involved: Jeddah Central Development Company, Khatib & Alami, Gerkan Marg & Partner, China Railway Construction Corporation, Sama Construction for Trading & Contracting, Geoharbour
  • Match category: Round of 32
12. King Abdullah Economic City Stadium, Jeddah

The planned stadium will have a seating capacity of 45,700 and will be built in the King Abdullah Economic City on the Red Sea Coast, north of Jeddah.

  • Location: Jeddah
  • Companies involved: Populous
  • Match category: Round of 32
13. Aramco Stadium

The Aramco Stadium in Al-Khobar is under construction and is expected to be completed by 2026. The stadium will have a capacity of 46,096 seats.

  • Location: Al-Khobar
  • Companies involved: Saudi Aramco, Roshn, Foster + Partners, Populous, Besix, Albawani, Al-Osais International Holding
  • Match category: Round of 16
14. King Khalid University Stadium

The stadium will undergo expansion works that will see its capacity raised to 45,428 seats. The facility is expected to be ready by 2032.

  • Location: Abha
  • Companies involved: Populous
  • Match category: Round of 16
15. Neom Stadium

The 46,010-seat stadium in Neom is “designed to stand out among the world’s most iconic landmarks”, according to the bid book. It is planned to be built 350 metres above ground level within The Line project at Neom. 

The stadium is expected to be ready by 2032.

  • Location: Neom
  • Companies involved: Neom
  • Match category: Quarter-final
https://image.digitalinsightresearch.in/uploads/NewsArticle/12432451/main.gif
Yasir Iqbal
Related Articles
  • Kuwait awards $381m oil project

    23 September 2026

    Register for MEED’s 14-day trial access 

    State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).

    The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.

    The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.

    The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.

    The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.

    Meil will develop the new three-phase low-pressure wet separation facility at GC-25.

    The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.

    The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.

    Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.

    The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.

    At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.

    The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.

    Booster and injection pumps will transfer treated effluent water to designated injection wells.

    Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.

    The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.

    Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.

    Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.

    The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.

    Seven companies submitted bids for the project last November.

    The full list of bids was:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.

    Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg
    Wil Crisp
  • Kuwait refinery project on track for year-end completion

    23 September 2026

     

    A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.

    The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.

    One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).

    Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.

    The scope of the project includes:

    • Construction of a substation
    • Installation of transformers
    • Installation of medium-voltage switchgear
    • Installation of low-voltage auxiliary systems
    • Installation of network protection systems
    • Installation of disconnecting switches
    • Installation of surge arrestors
    • Installation of feeder breakers and cubicles
    • Installation of low-voltage A/C and D/C equipment
    • Installation of battery banks and battery chargers
    • Installation of related relay and control panel boards
    • Installation of fire alarm and fire protection equipment
    • Installation of a SCADA system
    • Installation of cables
    • Civil works
    • Associated facilities

    The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.

    On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.

    The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.

    Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.

    He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.

    Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg
    Wil Crisp
  • Contractor wins $208m Almoosa hospital MEP contract

    23 September 2026

    Register for MEED’s 14-day trial access 

    Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.

    Saudi Arabia’s Almoosa Health Company awarded the contract.

    The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.

    It will be built on a 45,000-square-metre site.

    A podium spanning the ninth and 10th floors will connect the two towers.

    The hospital will also include parking for 1,700 cars.

    BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.

    In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.

    In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.

    Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg
    Yasir Iqbal
  • UAE to develop integrated waste-to-resource pilot

    23 September 2026

    Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.

    The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.

    Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.

    Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.

    The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.

    A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.

    Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.

    The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.

    If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.

    The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg
    Mark Dowdall
  • Contractors prepare Oxagon Highway 55 bids

    23 September 2026

     

    Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.

    The project duration is 22 months.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
    Yasir Iqbal