Top 15 Saudi stadium projects
30 August 2024

Saudi Arabia formally kicked off its World Cup participation process in October last year after announcing that it planned to bid to host the event. The announcement was a culmination of Riyadh’s football-focused strategy launched two years before when a consortium led by the kingdom’s sovereign wealth vehicle, the Public Investment Fund (PIF), completed the full acquisition of UK football club Newcastle United from St James Holdings in 2021.
The move was further solidified when Saudi Arabia was effectively confirmed as the host after Australia, the only other bidder for the tournament, withdrew from the race in October last year.
This was followed by Saudi Arabia’s official bid campaign reveal and the submission of its bid to Fifa to host the World Cup 2034 event in July. The official selection of Saudi Arabia as the 2034 host is expected to be confirmed on 11 December.
Saudi Arabia will likely invest hundreds of billions of dollars in developing the required infrastructure to host the event. Experience from previous World Cups, including the most recent one in Qatar, has shown that hosting the tournament can transform a country’s economy.
The tournament brings in fans from around the world to enjoy a month-long festival of football. After the 2022 tournament, Qatar issued a statement saying that more than 1.4 million fans had visited the country during the event.
The decision to host the Fifa World Cup 2034 is a pivotal moment for Saudi Arabia as it validates much of the social and economic change that the kingdom has embarked upon since Crown Prince Mohammed Bin Salman launched Vision 2030 back in 2016.
Building stadiums is the most prominent part of the bid to host the coveted Fifa World Cup.
According to the official bid book document submitted by Saudi Arabia in July, it will construct 11 new stadiums as part of its bid to host the Fifa World Cup 2034.
Eight out of the 15 stadiums are located in the capital, Riyadh, four in Jeddah and one each in Al-Khobar, Abha and Neom.
The event requires a minimum of 14 all-seater stadiums, of which at least four should be existing structures. The capacity must be at least 80,000 seats for the opening and final matches, and for the semi-finals, there must be at least 60,000 seats. For all other matches, at least 40,000 seats are needed.
The kingdom has recently ramped up its announcements regarding building new stadiums across the country in preparation to host the event.
1. King Salman Stadium
The King Salman Stadium will be the showpiece venue for the tournament. The US-based architectural firm Populous-designed stadium will cover an area of about 660,000 square metres (sq m) and have a seating capacity of over 92,000 spectators.
The stadium will host the opening and final games of the Fifa World Cup 2034 tournament. The construction of the stadium is expected to be completed by 2029.
- Location: Riyadh
- Companies involved: Populous
- Match category: Opening and final games
2. King Fahad Sports City Stadium
The King Fahad Sports City Stadium is expected to be the venue for the semi-final. The stadium will be refurbished to increase its seating capacity from its current 58,000 seats to 70,200 seats.
The main contract bid submission process is ongoing and the project’s expansion works are expected to begin early next year. The stadium will also be a venue for the AFC Asian Cup 2027.
- Location: Riyadh
- Companies involved: Populous
- Match category: Semi-final
3. Prince Mohammed Bin Salman Stadium, Qiddiya City
The Prince Mohammed Bin Salman Stadium will be built on top of a 200-metre-high Tuwaiq cliff located in the new sports and entertainment district of Qiddiya City.
The stadium will have a capacity to accommodate 46,979 spectators and will feature a fully combined retractable pitch, roof and LED wall. The construction works are expected to begin later this year.
- Location: Riyadh
- Companies involved: Qiddiya Investment Company, Populous
- Match category: Third-place playoff
4. New Murabba Stadium
The New Murabba Stadium will have the capacity to accommodate 46,010 spectators and will be built as part of the New Murabba downtown project in Riyadh.
The construction of the stadium is expected to be completed by 2032.
- Location: Riyadh
- Companies involved: New Murabba Development Company
- Match category: Round of 32
5. Roshn Stadium
The Roshn stadium will be built in the southwest of Riyadh. The planned facility will have the capacity to accommodate 46,000 spectators and will span an area of over 450,000 sq m.
- Location: Riyadh
- Companies involved: Roshn
- Match category: Round of 32
6. Prince Faisal Bin Fahad Sports City Stadium
The Prince Faisal Bin Fahad Stadium is earmarked for an expansion that aims to increase its seating capacity from its current 22,188 seats to 46,865 seats.
The facility will also host the AFC Asian Cup in 2027.
The refurbishment works will change the geometry of the seating bowl from an athletics stadium to a football stadium.
- Location: Riyadh
- Companies involved: Populous
- Match category: Round of 32
Saudi World Cup bid bucks global trend for sporting events
7. South Riyadh Stadium
The Populous-designed stadium will be located in southwest Riyadh close to the Wadi Namar. The stadium will have the capacity to host 47,060 spectators. It is expected to be ready by 2032.
- Location: Riyadh
- Companies involved: Populous
- Match category: Round of 32
8. King Saud University Stadium
The King Saud University Stadium, located on the university’s campus in the west of Riyadh, is one of the venues that will undergo expansion and refurbishment to host the event.
The expansion will increase the stadium’s capacity to 46,319 spectators and the construction works are expected to be completed by 2032.
- Location: Riyadh
- Companies involved: Populous
- Match category: Round of 32
9. King Abdullah Sports City Stadium
The King Abdullah Sports City Stadium is the home ground for the Al-Ittihad and Al-Ahli football clubs. The venue will undergo expansion works that will increase its seating capacity to 58,432 people. The stadium will host the quarter-final games.
- Location: Jeddah
- Companies involved: Arup
- Match category: Quarter-final
10. Qiddiya Coast Stadium, Jeddah
The Populous-designed stadium will be situated at the heart of the Qiddiya Coast development in Jeddah. The multi-purpose stadium will have a 46,096 seating capacity and will be one of the venues for the round of 16 matches.
- Location: Jeddah
- Companies involved: Populous
- Match category: Round of 16
11. Jeddah Central Stadium, Jeddah
The already under-construction football stadium is part of the Jeddah Central Project in Jeddah and has a seating capacity of 45,794 spectators. The stadium is expected to be completed by 2027.
- Location: Jeddah
- Companies involved: Jeddah Central Development Company, Khatib & Alami, Gerkan Marg & Partner, China Railway Construction Corporation, Sama Construction for Trading & Contracting, Geoharbour
- Match category: Round of 32
12. King Abdullah Economic City Stadium, Jeddah
The planned stadium will have a seating capacity of 45,700 and will be built in the King Abdullah Economic City on the Red Sea Coast, north of Jeddah.
- Location: Jeddah
- Companies involved: Populous
- Match category: Round of 32
13. Aramco Stadium
The Aramco Stadium in Al-Khobar is under construction and is expected to be completed by 2026. The stadium will have a capacity of 46,096 seats.
- Location: Al-Khobar
- Companies involved: Saudi Aramco, Roshn, Foster + Partners, Populous, Besix, Albawani, Al-Osais International Holding
- Match category: Round of 16
14. King Khalid University Stadium
The stadium will undergo expansion works that will see its capacity raised to 45,428 seats. The facility is expected to be ready by 2032.
- Location: Abha
- Companies involved: Populous
- Match category: Round of 16
15. Neom Stadium
The 46,010-seat stadium in Neom is “designed to stand out among the world’s most iconic landmarks”, according to the bid book. It is planned to be built 350 metres above ground level within The Line project at Neom.
The stadium is expected to be ready by 2032.
- Location: Neom
- Companies involved: Neom
- Match category: Quarter-final
Exclusive from Meed
-
Lessons learnt from a power plant decommissioning26 February 2026
-
Abu Dhabi’s Enersol charts acquisitions path26 February 2026
-
Dubai plans EPC tender for Warsan sewage treatment plant25 February 2026
-
Aramco firm and Arcapita sign logistics facility deal25 February 2026
-
Algeria gives bidders more time for 1.2GW plant25 February 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Lessons learnt from a power plant decommissioning26 February 2026

Al-Kamil power plant, a 280MW, gas-fired power plant in the Sharqiya region of Oman, was recently decommissioned following nearly 20 years of operations as the country’s second independent power plant.
The plant reached commercial operation in 2002, at which time it started to supply electricity to Nama Power & Water Procurement Company under a 15-year power purchase agreement that was later extended to the end of 2021. No further extension was granted so, in 2022, the decommissioning process was initiated.
Al-Kamil power plant was one of the first privately owned power plants in Oman to be decommissioned. The entire process took significantly longer than planned – three years compared to an initial target of 12 months. This was not unexpected, however, as there were not yet any standard processes to follow. Everything was being done for the first time, and proper procedures had to be established.
Starting decommissioning
The decommissioning of a power plant is a complex process and can take as much time to complete as it takes to build a plant. It involves environmental considerations, health and safety protocols, detailed surveys, de-energisation, dismantling, demolition, waste management and the segregation and storage of secondary valuables.
Careful planning and management are essential to ensure that decommissioning is accomplished safely, cost-effectively and in accordance with all government environmental standards.Consulting on the decommissioning of Al-Kamil were Dubai’s Golden Sands Marketing Consulting (GSMC), appointed in 2021, alongside Abu Dhabi’s Sustainable Water & Power Company (SWPC) and Dubai’s Tractebel Engineering Company (TEC).
One of the first steps that GSMC undertook was to prepare a master plan covering the entire decommissioning process (see right).
A site investigation was undertaken by GSMC and SWPC early in the process to determine the condition of the power assets and the overall site.
The Al-Kamil power plant was found to have been well maintained, with no major health, safety, security and environment (HSSE) issues.
SWPC prepared the dismantling guidelines covering all plant equipment, and these were reviewed by TEC. The guidelines covered three main phases: the shut down and isolation of all assets; the de-
energisation process; and the dismantling of the plant equipment, its removal from site and the demolition of all remaining civil works.GSMC designed a sales strategy for the plant equipment, taking into consideration the secondary market for power-related equipment, as well as the scrap market in Oman. A competitive procurement process was also followed in an effort to maximise sales revenues from plant equipment.
A separate tender was issued to appoint a demolition contractor to remove the remaining civil works, and once this work was complete, a local environmental engineering company undertook a final environmental report to demonstrate that the site was properly cleared and ready for handover to the original owner, the Housing & Urban Planning Ministry.
Final results
The decommissioning project went well in terms of HSSE considerations, with no fatalities, no lost-time injuries and no first aid injuries over the more than 243,000 total workhours at the site.
There were no material environmental spills or incidents to report, and all above- and below-ground structures were demolished and safely removed from the site in accordance with local requirements.
The final environmental report, completed just before handover, showed that the site was effectively in the same condition as it was when originally taken over at the start of construction.
The decommissioning was also successful from a financial perspective, as revenues from the sale of plant equipment and diesel fuel were beyond what was required to cover the costs associated with the decommissioning process.
Lessons learnt
Many lessons were learnt during the process that can benefit future power plant decommissioning efforts in the region.
> Notify key stakeholders early: Key stakeholders are those that have a vested interest in the project, either through ownership of certain assets on site, such as grid connection assets, or via regulation, such as the environmental authority. Many of these stakeholders take time to respond, so notifying key stakeholders early in the process can ensure that unnecessary delays are avoided.
> Prioritise HSSE: For any future decommissioning project, HSSE must be a top priority, and this should be the focus throughout the entire decommissioning process – at all levels of work and management.
The site manager at Al-Kamil installed a 24/7 closed-circuit television camera, which proved to be extremely effective in terms of monitoring progress and identifying potential HSSE issues before they became an incident. This simple and cost-effective practice should be replicated for all future decommissioning projects.
> Appoint the environmental consultant early in the process: It is advisable to appoint an environmental consultant early in the process. The consultant is needed to coordinate activities with the local environmental authority and obtain a no-objection letter or certificate, complete an environmental management report and an update of the environmental impact assessment, which includes an environmental baseline.
Ideally, these reports and environmental authority approvals should be completed well before any work is under way at the site. This information is also useful to potential bidders for the sale of equipment, or to contractors involved in the dismantling and demolition process.
> Submit an environmental management plan for approval: It is unlikely that any environmental authority will provide a no-objection letter or certificate without reviewing the environmental plan. It is therefore necessary to complete the plan early, prior to informing the environmental authority. This can minimise potential delays in starting the decommissioning process.
As a general practice, an environmental consultant should be brought on board early in the process, ideally once the overall master plan is approved by the company.
> Establish a proactive steering committee: This was done at Al-Kamil and proved to be effective when it came to overseeing project progress and dealing with issues as they arose. Certain members of the steering committee visited the site regularly and undertook spot HSSE inspections.
At Al-Kamil, the overall decommissioning was relatively straightforward as the plant was in a remote area. However, decommissioning a power plant in a busier location, or when part of the power plant remains in operation, is more challenging. Under these circumstances, a steering committee is vital.
> Set realistic delivery and completion timelines: Decommissioning a power plant is a complex process. The initial timeline to complete the process for Al-Kamil was one year, which was the best estimate at the time as there were no benchmarks or references in Oman. However, the actual completion time turned out to be three years – longer than the approximately 2.5 years it took to build the plant, from the start of construction in early 2001 to full commercial operation in July 2003.
Realistic delivery dates should be set for contractors, suppliers and others involved in the decommissioning process. This is likely to result in better pricing, as bidders tend to factor in higher contingencies with shorter or fast-track delivery dates. More realistic delivery dates also help management to allocate staff resources and manage the decommissioning budget.
Finally, realistic delivery dates help to manage owner and shareholder expectations regarding project completion.
Given the experience with Al-Kamil, a reasonable decommissioning timeline for a power plant is probably close to the actual construction timeline for the plant involved.
> Allow time to maximise revenues from the sale of assets: The market value for Al-Kamil’s power assets was estimated at a value significantly higher than the prevailing scrap value. This was based in part on the value of similar gas turbine units, after adjusting for age, usage and other factors that affect the net market value. However, the company realised a much lower value, even after retendering the equipment sales in an effort to get a better price.
It appears that prices close to the market rate are only achievable if there is time to find a suitable buyer. This can take many months or even years – typically a longer time than the owners of power plants wish to take.
Moreover, as renewables continue to penetrate the market, there is less worldwide demand for used gas turbine units. Prevailing market supply and demand conditions also have a bearing on the sale price for secondary equipment, and this factor needs to be considered.
If time is of the essence, then power plant owners need to accept the fact that the expected revenues will likely be on the low side, although still higher than the scrap value of the assets.
Main image: Picture 1: Al-Kamil power plant as constructed; Picture 2: Post decommissioning
https://image.digitalinsightresearch.in/uploads/NewsArticle/15780944/main.gif -
Abu Dhabi’s Enersol charts acquisitions path26 February 2026

With about half of its $1.5bn seed capital still available to deploy, Abu Dhabi- based oil and gas drilling services firm Enersol is firmly on a growth trajectory driven by acquisitions. Since its establishment in November 2023 as a 51:49 joint venture of Adnoc Drilling – a subsidiary of Abu Dhabi National Oil Company (Adnoc Group) – and holding company Alpha Dhabi, Enersol has pursued inorganic growth as its core expansion strategy.
Having completed four key acquisitions to date, Enersol is now targeting opportunities that will not only expand its portfolio but also enhance the value of its offerings to customers, says the company’s CEO, Dean Watson.“The unifying theme that we want to focus on is around the production side of what we call the well lifecycle. Why is that important? For investors it is super important because that’s where we get to the opex [operating expenditure] side, moving away from capex [capital expenditure], achieving completions and recurring revenues. So, with the potential target acquisitions, that’s where we’re focused on,” Watson explains.
“We think that they [future acquisitions] are going to unify and anchor our current portfolio,” he tells MEED in an interview.
“We have a lot of dry powder to spend. We have identified targets that we want to go after. We are pursuing a few targets,” Watson says, without revealing details. “With the targets we are after, we want to make sure that they’ve got a presence here in the UAE and Mena. We’re also looking for a global footprint.”
Completed acquisitions
Enersol became the majority shareholder in US oil and gas drilling firm Gordon Technologies in 2024, acquiring a 67.2% stake through two transactions with a combined value of $387m.
Louisiana-based Gordon Technologies provides measurement while drilling (MWD) technology. MWD technology captures critical data near the drill bit and transmits it to the surface in real time without interrupting normal drilling operations.
“Gordon Technologies are number one in North America, by a long way, in terms of market share percentage. It’s quite amazing how big that difference is in terms of how much they dominate [in] North America,” Watson says about the rationale behind Enersol acquiring the majority stake.
Enersol then initiated a $58m transaction in July 2024 to acquire a 51% majority stake in UAE-based oil and gas services provider NTS Amega from Alpha Dhabi.
“NTS Amega is a manufacturing business with a rental component,” Watson explains. “It manufactures a product and rents out a portion of it. What excites us about NTS Amega is its potential to serve as our manufacturing backbone, helping to strengthen and promote our in-country value, as it is based and originated in the UAE.”
In August of the same year, Enersol started a transaction to fully acquire US-headquartered EV Holdings Limited, paying $45m to UK-based private equity firm Dunedin for 100% of the company’s shares.
EV Holdings has a significant technology portfolio, with more than 100 pieces of intellectual property, primarily patents. It is a highly technical company that generates vast amounts of data, Watson explains.
Aligned with Enersol’s focus on technology leadership, EV is the number one provider of downhole camera technology in oil field services. It therefore meets what Watson calls “the key investment criteria we are looking for”.
In November 2024, Enersol entered into a $223m deal to acquire a 95% equity stake in US-based Deep Well Services (DWS).
The acquisition, which was completed in the first quarter of 2025, gives Enersol access to DWS’s hydraulic completion units, complemented by its data analytics software, BoreSite, as well as accredited training programmes designed to enhance operational safety and efficiency.
We have a lot of dry powder to spend. We have identified targets that we want to go after. We are pursuing a few targets
Dean Watson, EnersolSecuring contracts
Enersol is seeking to leverage the suite of capabilities and technologies it has acquired to secure oil field services contracts in the UAE and the wider regional market, Watson says.
“We’re very excited about being part of the Adnoc ecosystem. Gordon Technologies, through Turnwell, has just completed its first batch of wells and is currently working on the Turnwell project,” the Enersol CEO says, adding: “Gordon is the MWD provider on that project.”
Adnoc Drilling signed a term sheet in 2024 to enter into a partnership with the Middle East arm of US oil field services provider SLB and US firm Patterson-UTI International Holdings to form a new company called Turnwell Industries.
In May of that year, Adnoc Drilling was awarded a major contract, worth about $1.7bn, by its parent Adnoc Group, to provide drilling and associated services for the recovery of unconventional oil and gas resources. Work on this contract is being executed by Turnwell. The broad scope of work on the contract covers drilling and appraisal of 144 unconventional oil and gas wells.
Separately, DWS won its first contract from Malaysia’s state energy company Petronas last November for deploying its hydraulic completion units and BoreSite systems to support a 12-well unconventional programme in Abu Dhabi.
Watson is optimistic about Enersol securing additional work in Abu Dhabi from Adnoc Drilling. Beyond its home market, the company is “in active discussions and negotiations with our Saudi joint-venture partner on a major scope of work with Saudi Aramco,” he says.
Enersol’s growing portfolio and its push to secure contracts across the region also place the company in competition with established oil field services majors. On that subject, Watson concludes: “I believe our offering is unique and does not necessarily compete directly with companies such as SLB or Weatherford.
“We will identify a niche that fits between the major players and deliver parallel value through our differentiated offering.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/15780622/main.gif -
Dubai plans EPC tender for Warsan sewage treatment plant25 February 2026

Register for MEED’s 14-day trial access
Dubai Municipality is preparing to tender the main construction package for the Warsan sewage treatment plant (STP) by the end of the year, according to sources close to the project.
The scheme is linked to the deep sewerage tunnels infrastructure programme being implemented by the municipality’s sewerage and recycled water projects department.
As MEED understands, the Warsan STP had previously been expected to be procured as a public-private partnership (PPP) scheme.
However, sources confirmed that the main construction package will now be procured as an engineering, procurement and construction (EPC) contract.
The project involves the construction of a sewage treatment plant with a capacity of about 175,000 cubic metres a day (cm/d), including treatment units, sludge handling systems and associated infrastructure.
The plant, estimated to cost about $326m, will be developed at the existing Warsan complex, where the municipality is also progressing separate expansion and rehabilitation packages.
These include Warsan STP Phase 1 (DS-355/1), which involves sewerage and stormwater network upgrades, and Stage 2 of the Al-Warsan sewage treatment plant (DS-203/2), comprising new treatment units
Kuwait-headquartered Mohammed Abdulmohsin Al-Kharafi & Sons is the main EPC contractor for both projects.
Separately, the municipality is also progressing the expansion and upgrade of the first and second phases of the Jebel Ali STP.
The upgraded facility will be capable of treating an additional sewage flow of 100,000 cm/d.
Earlier this month, contractors were invited to prequalify for the contract.
The bid submission deadline is 2 April.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15765751/main.jpg -
Aramco firm and Arcapita sign logistics facility deal25 February 2026
Asmo, the logistics joint venture of Saudi Aramco and DHL Supply Chain, has signed an agreement with Bahrain‑headquartered Arcapita Group Holdings to deliver a 1.4-million-square-metre (sq m) built-to-suit logistics complex at King Salman Energy Park (Spark).
The project will feature a 43,000 sq m temperature-controlled, Grade A warehouse, more than 3,000 sq m of office and staff amenities, 5,300 sq m dedicated to chemical storage, and an open yard spanning about 1.2 million sq m.
Planned for large-scale industrial use, the site is expected to incorporate advanced warehouse and building management systems, end-to-end digital connectivity, automation and robotics.
It will also be developed in line with internationally recognised sustainability standards, featuring solar (photovoltaic) readiness, EV charging infrastructure and a target of LEED Gold certification.
The development is aimed at supporting the next stage of Saudi Arabia’s logistics and supply chain expansion.
Under the deal structure, Arcapita will provide funding and retain ownership of the asset, while Asmo will develop the facility and then lease and operate it under a 22-year occupational lease.
According to a statement, “the scheme will be executed via a forward-funding model, underscoring a long-term commitment to national infrastructure”.
Asmo added that this will be its first purpose-built logistics centre and one of four strategic locations planned to anchor its nationwide logistics network, aligned with the National Transport and Logistics Strategy (NTLS) under Saudi Vision 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15765085/main.gif -
Algeria gives bidders more time for 1.2GW plant25 February 2026
Algeria’s state-owned electricity and gas utility Sonelgaz has extended the bid submission deadline for a contract to build a 1,200MW combined-cycle gas-fired power plant in Adrar.
The project is being procured through Sonelgaz’s power generation subsidiary, Societe Algerienne de l’Electricite et du Gaz – Production de l’Electricite (SPE).
The new bid submission deadline is 29 April. The main contract was first tendered in April last year, and the deadline has been extended several times since.
The latest deadline was 26 February.
The tender is open to local and international companies with experience in delivering large-scale power generation projects and with sufficient technical and financial capacity.
Algeria’s wider power sector has experienced periods of limited contract activity in recent years. Between 2018 and 2022, virtually no new solar or wind farm contracts were awarded, according to available data from the regional projects tracker MEED Projects.
In 2023, Sonelgaz Energie Renouvelables, a subsidiary of Algeria’s state-owned utility, awarded 14 of the 15 solar photovoltaic (PV) packages it tendered that year.
At the time, MEED reported that the 15 packages had a total combined capacity of 2,000MW, requiring at least AD172bn ($1.2bn) of investment.
However, publicly available data suggests that progress has been slow with several schemes yet to reach full construction or commercial stages.
Gas-fired combined-cycle plants continue to account for the majority of Algeria’s electricity generation capacity. Data from MEED Projects indicates that more than 5,000MW of oil- and gas-fired power capacity is currently under construction.
Despite this, new contract awards in 2025 came from three solar schemes.
This included the construction of a 154MW solar PV plant in Bechar, for which China Power was appointed main contractor in August.
https://image.digitalinsightresearch.in/uploads/NewsArticle/15765079/main.jpg
