Top 10 UAE clean energy projects

18 October 2023

 

Register for MEED's guest programme 

The UAE is expected to showcase its growing green credentials at the Cop28 climate summit, which starts on 30 November in Dubai.

In addition to gradually phasing out fossil fuel subsidies and eliminating methane flaring, UAE-based energy and utility companies have mobilised multibillion-dollar public and private investments in utility-scale clean and renewable energy plants, reverse osmosis technology-based water desalination plants and carbon capture, utilisation and storage (CCUS) projects.   

These projects aim to reduce harmful emissions – mainly carbon dioxide – offsetting the environmental impact of the country’s oil industry while it aims to meet its nationally determined contributions (NDCs) for the Paris Agreement, its energy diversification agenda set in 2017, as well as its 2050 net-zero target.

Barakah nuclear power plant

Three of the four reactors at the $29bn Barakah nuclear power plant, located close to the UAE’s border with Saudi Arabia, are operational. Each unit can produce 1,400MW of electricity. The UAE is also looking for opportunities to export its nuclear expertise by investing in and developing nuclear power plants overseas.

Mohammed bin Rashid al-Maktoum Solar Park

The UAE’s first and largest solar photovoltaic (PV) installation is located 50 kilometres away from the Cop28 venue. Nearly all the first five phases of the solar park are operational, with a total combined installed capacity of more than 2.4GW. The project’s fourth phase, probably the world’s largest hybrid solar PV and concentrated solar power plant, is nearing completion. The contract to develop the project’s sixth phase, which is designed to have an installed capacity of 1.8GW, has been awarded this year.

Sweihan and Al-Dhafra solar power plants

Abu Dhabi’s first solar PV plant, the 935MW Sweihan independent power project (IPP), began operating in 2019. The UAE capital’s second utility-scale solar PV IPP in Al-Dhafra, which has a capacity of 1.5GW, is expected to be inaugurated imminently. Emirates Water & Electricity Company (Ewec) received world-record-low tariffs, as has Dubai Electricity & Water Authority (Dewa), for these projects.

Taweelah reverse osmosis facility

With a capacity of 200 million imperial gallons a day, the plant is the world’s largest reverse osmosis-based water desalination facility. Half of the plant’s capacity was completed in 2022, with the other half now in the final commissioning stage. Taweelah is the country’s first independent water producer project, which resulted from the drive to decouple water and power production as a key initiative to decarbonise both sectors.

Reyadah CCUS

Abu Dhabi National Oil Company (Adnoc) and Abu Dhabi Future Energy Company (Masdar) have been operating the Al-Reyadah carbon capture, utilisation and storage (CCUS) facility since 2016. It can capture up to 800,000 tonnes a year (t/y) of carbon dioxide. About 240,000 tonnes of carbon dioxide (CO2), collected by Al-Reyadah from Emirates Steel Industries, has been injected into Adnoc's reservoirs at its Rumaitha and Bab oil fields to bolster oil recovery.

The project is in line with Adnoc’s commitment to decarbonise its operations, reduce its carbon intensity by 25 per cent by 2030, and deliver on its net zero by 2045 goal. Adnoc estimates the volume of CO2 being locked away underground daily through CCUS deployment across its reservoirs is equivalent to the emissions of more than 1 million vehicles.

Habshan CCUS

Adnoc Gas recently awarded UK-headquartered Petrofac the main contract for a project to develop a $615m carbon capture facility at its Habshan gas processing complex in Abu Dhabi. The Habshan CCUS facility will have the capacity to capture and permanently store 1.5 million t/y of CO2 within geological formations deep underground.

The Habshan CO2 recovery project will be built, operated and maintained by Adnoc Gas and is expected to be commissioned in 2026. The proposed facility will feature carbon capture units at the Habshan gas processing plant, pipeline infrastructure and a network of wells for CO2 injection into oil and gas fields in Abu Dhabi.

Captured CO2 will be permanently stored in reservoirs deep in the sub-surface by deploying closed-loop CO2 capture and reinjection technology at the well site at Adnoc Onshore’s Bab Far North Field, located about 240 kilometres southwest of Abu Dhabi city.

Street lighting PPP

Abu Dhabi awarded two public-private partnership (PPP) contracts in 2020 and 2022 to replace over 176,000 street lights with LED lights. The first phase of the 12-year PPP project is designed to save the municipality AED264m ($71.9m), while the larger second phase is designed to result in cost savings amounting to close to $200m. The project's phase two aims to reduce power consumption by 74 per cent over the 12-year concession period, equivalent to almost 2,400 million kilowatt hours of electricity savings.

Green data centre

Work is progressing on the first phase of the 100MW data centre powered by solar energy at Mohammed bin Rashid al-Maktoum Solar Park in Dubai. Hub Integrated Solutions (Moro Hub), a Dewa subsidiary, is the project client. The data centre is envisaged to become the largest solar-powered Uptime Tier 3-certified data centre in the Middle East and Africa, offering digital products and services based on fourth industrial revolution technologies, such as cloud services. The project supports the emirate’s goal of achieving net-zero carbon emissions by 2050 and the UAE 2031 Artificial Intelligence Strategy.

Hydrogen pilot site

Dewa, in partnership with Expo 2020 Dubai and Germany’s Siemens Energy, inaugurated the AED50m ($14m) green hydrogen plant at Dubai’s Mohammed bin Rashid al-Maktoum Solar Park in 2021. The integrated facility was developed with electrolysis, storage and re-electrification capabilities. Daylight solar power from the solar park will enable the pilot project to produce about 20.5 kilograms an hour of hydrogen at 1.25MW of peak power.

Large green hydrogen projects

There is an expectation that the Abu Dhabi Department of Energy will issue the UAE capital's green hydrogen policy before the start of, or during, the Cop28 climate summit. If this happens, planned green hydrogen projects worth at least $12bn could see rapid progress.

These projects include the 150MW green hydrogen-based ammonia production plant in Ruwais being developed by France's Engie and Abu Dhabi's Fertiglobe and Masdar; the $1bn green ammonia facility being planned by a South Korean-led consortium in Khalifa Economic Zones Abu Dhabi (Kezad); and the Masdar City green hydrogen and sustainable aviation fuel project being developed by Masdar, France's Total Energies, Germany’s Siemens Energy and Japan's Marubeni Corporation.

Other projects that are likely to be highlighted include the planned 400MW battery energy storage system in Abu Dhabi and the seawater reverse osmosis facilities that are under construction or in the bid phase across the UAE. 

Projects to retrofit public buildings to improve their sustainability, and the adoption of district cooling and electric vehicle policies, among others, will also likely share the spotlight as the UAE prepares to host its most important event of 2023.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11228094/main1001.jpg
Jennifer Aguinaldo
Related Articles
  • Oil prices rise above $100 a barrel as conflict escalates

    9 September 2026

    Register for MEED’s 14-day trial access 

    Oil prices rose above $100 a barrel on 9 September for the first time since July as the US-Iran conflict escalated and Iran-backed Houthi forces attacked Saudi energy infrastructure.

    Brent crude futures reached $100.95 a barrel, while US benchmark West Texas Intermediate (WTI) rose to $95.60. Brent had last traded above $100 on 24 July.

    The latest escalation has heightened concerns about oil supplies from the region, with shipping through both the Strait of Hormuz and the Red Sea facing disruption.

    Flows through the Strait of Hormuz had fallen below 2 million barrels a day (b/d) from about 8-9 million b/d before the latest escalation, according to Rystad Energy.

    At the same time, Houthi attacks on Saudi Arabia threaten another important route for oil exports, with the group targeting energy infrastructure and shipping in and around the Red Sea.

    US strikes on Iranian tankers

    US forces destroyed five Iranian crude oil carriers on 8 September after Iran’s Islamic Revolutionary Guard Corps (IRGC) targeted a US Navy warship with ballistic missiles.

    The US Central Command (Centcom) said the warship successfully evaded two Iranian attacks and that no US personnel were harmed.

    Four of the Iranian vessels – Kaviz, Charminar, Horizon 1 and Riesco – were struck in the Gulf of Oman, while the Derya was attacked near Kharg Island, Iran’s main crude export hub.

    The M/T Riesco subsequently sank in the Gulf of Oman, according to Centcom.

    Iran responded by launching ballistic missiles towards Jordan. Jordan’s armed forces said 18 of 20 missiles were intercepted, with the remaining two falling in unpopulated areas.

    Iran’s IRGC also said it had attacked two US naval vessels, eight oil tankers and 10 other vessels in the Gulf, although it did not identify the vessels or provide evidence of the attacks.

    The latest exchanges mark a further escalation in the US-Iran conflict, which began on 28 February.

    Houthi attacks raise supply concerns

    The conflict has also widened into a renewed confrontation between Saudi Arabia and Yemen’s Iran-backed Houthi movement.

    On 8 September, Saudi authorities said Houthi attacks had targeted civilian and economic sites in Abha, Khamis Mushait, Jazan and Najran in the south of the kingdom, injuring 73 people.

    Saudi Arabia’s Ministry of Energy said several energy sector facilities and installations had been targeted, causing fires and forcing a temporary halt to some operations.

    The Houthis said their attacks were in response to Saudi military action in Yemen, including what they described as attacks on Houthi positions and a Saudi blockade of ports and airports.

    Riyadh condemns attacks

    Saudi Arabia has strongly condemned the Houthi attacks and warned that it would take measures to defend its territory and national assets.

    In a statement on 8 September, the Ministry of Energy said authorities were working to address the impact of the attacks and ensure the safety of facilities and personnel while maintaining operations in accordance with approved plans.

    Saudi Arabia’s Ministry of Foreign Affairs also condemned the attacks and said the kingdom had the right to take measures to defend its sovereignty and protect its citizens, residents and national assets.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19505512/main0138.jpg
    Indrajit Sen
  • What actually slows a gigaproject down

    9 September 2026

     

    Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.

    “None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.

    For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.

    “The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.

    The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.

    “Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”

    Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.

    Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.

    Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.

    “The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”

    Integration needs to be well understood

    “Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.

    Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.

    Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.

    “The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”

    That shared view, he argues, will be what the next phase of Gulf delivery is judged on.

    Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.

    “This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.

    From reporting progress to managing risk before it lands

    Digital tools have a role here, Caldwell says, but not as a headline in themselves.

    Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.

    “The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."

    None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”

    Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.

    With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.

    “The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.

    What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.

    “The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif
    Yasir Iqbal
  • Qatari firm wins $221m Qiddiya stadium MEP deal

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Qatari contractor Elegancia MEP, part of Estithmar Holding, has won a SR829m ($221m) mechanical package contract for the Prince Mohammed Bin Salman Stadium in Qiddiya, Saudi Arabia.

    The contract covers full mechanical, electrical and plumbing (MEP) works for the stadium, and is Elegancia MEP’s largest award in Saudi Arabia to date.

    The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.

    The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.

    Saudi gigaproject developer Qiddiya Investment Company awarded an estimated SR15bn ($4bn) deal to build the stadium in October 2024, as MEED exclusively reported.

    The contract covered the construction of a multipurpose stadium on top of the 200-metre-high Tuwaiq cliff in the new sports and entertainment district of Qiddiya City.

    Once completed, the stadium will be the home ground for Saudi Pro League football clubs Al-Nassr and Al-Hilal.

    US-based architect Populous is the project consultant.

    The stadium is one of the venues for the kingdom’s 2034 Fifa World Cup bid and will host events such as the Saudi King Cup, the Asian Cup and the 2034 Asian Games.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19501493/main.jpg
    Yasir Iqbal
  • Jordan tenders advisory for wastewater treatment plant

    9 September 2026

    The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.

    The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).

    The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.

    The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.

    The submission deadline is 21 September.

    The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.

    The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.

    The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.

    WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.

    The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.

    The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg
    Mark Dowdall
  • Consultants bid for Abu Dhabi light rail project management

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.

    The notice was issued on 7 September, with a submission deadline of 9 November.

    The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.

    The key sections of the tram are:

    AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.

    This section covers 13km and includes 13 at-grade stations and one underground station.

    Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.

    Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.

    The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.

    The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.

    Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.

    Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.

    Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.

    The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19493532/main.jpg
    Yasir Iqbal