Top 10 tallest towers in the region
2 October 2023

> This package also includes: Saudi’s Jeddah Tower reaches for new heights
1. Burj Khalifa, UAE
The construction of the world’s tallest skyscraper, Burj Khalifa, began in 2006 and reached its pinnacle in 2009.
The 829.8-metre-tall tower was developed by Dubai’s Emaar Properties and designed by US-based Skidmore Owings & Merrill and Adrian Smith + Gordon Gill Architecture.
Construction was led by a consortium of South Korea’s Samsung C&T, the local/Belgian Bel Hasa Six Construct and the local Arabtec Construction. The $875m main construction contract was awarded in December 2004.
The 163-storey tower took 22 million man-hours to build. Overall, the project cost about $1.5bn to complete.
2. Mecca Royal Clock Tower, Saudi Arabia
The 601-metre-tall Mecca Royal Clock Tower is the landmark feature of the Abraj al-Bayt complex.
The development comprises seven towers overlooking the holy site of Kaaba, with a total built-up area of more than 1.4 million square metres and 15,000 apartments.
Saudi Binladin Group was the main contractor for the project.
The $800m contract for the clock tower was awarded in 2003 and the complex completed in 2012.
3. Marina 101, UAE
Marina 101 is the second-tallest building in Dubai.
Construction began in 2007 when Turkish contractor TAV was awarded the estimated AED800m ($218m) main contract.
The project involved building a 101-floor tower with a height of 425 metres and a total built-up area of 144,000 sq m.
The project has witnessed several setbacks over the years and remains unoccupied. The construction works were partially completed in 2017.
4. Princess Tower, UAE
Princess Tower is the second-tallest residential building in the world.
The 107-storey tower stands 413 metres tall and is located in Dubai Marina.
The project was announced in 2005 and the foundation works were completed in 2007.
The main contractor for the project was the Lebanese Arabian Construction Company.
The Princess Tower was the world’s tallest residential building from 2012 to 2015, when it was overtaken by 432 Park Avenue in New York City.
5. Al-Hamra Tower, Kuwait
The 80-floor Al-Hamra Tower is the tallest building in Kuwait and the 36th tallest in the world, at 412 metres. It was built by the local Ahmadiah Contracting & Trading Company. Construction works started in 2005 and were completed in 2011. The project was designed by US-based architectural firms Skidmore, Owings & Merrill, Callison and the local Al-Jazirah Engineers & Consultants.
6. 23 Marina, UAE
The 392-metre-tall 23 Marina is the fourth-tallest building in the UAE and the 40th tallest in the world. Dubai Civil Engineering constructed the 88-floor tower. The construction works started in 2005 and the project was completed in 2012. US-based KEO International and Indian Architect Hafeez Contractor designed the tower.
Jeddah Tower restart is watershed moment
7. PIF Tower, Saudi Arabia
The Public Investment Fund (PIF) Tower is located within Riyadh’s King Abdullah Financial District. US-based HOK Architects, Canadian WSP, Hyder Consulting and the local Omrania Associates designed the 385-metre-tall, 80-storey tower. The construction works began in 2009 and were finally completed in 2022. Saudi Binladin Group was the main project contractor.
8. Iconic Tower, Egypt
The 385-metre-tall Iconic Tower is the centrepiece among the 20 buildings of the Central Business District in Egypt’s New Administrative Capital. The construction of this 80-storey tower started in 2019 when China State Construction Engineering Corporation was appointed as the main contractor. The construction works on Africa’s tallest skyscraper were completed in 2022. Lebanese engineering company Dar al-Handasah was the project consultant.
9. Burj Mohammed bin Rashid, UAE
Completed in 2014, Abu Dhabi’s tallest building measures 381 metres and consists of 88 floors. The tower, part of the Abu Dhabi World Trade Centre, was announced in 2004. The construction works started in 2007 under the government’s redevelopment plan. The consultants involved in the development included Arup, Mott MacDonald, Foster & Partners, AtkinsRealis and Callison. Lebanese contractor Arabian Construction Company undertook the construction works.
10. Elite Residence, UAE
Dubai Marina’s Elite Residence, a 91-storey residential building, is the sixth-tallest building in the UAE. The 380-metre-tall tower was announced in 2006 and designed by Lebanese Khatib & Alami. The construction works began in 2007 when Arabian Construction Company was awarded the main construction contract. The tower has been operational since 2012.
|
SOON TO JOIN GCC countries’ quest to build tall towers is not over yet. Several upcoming developments are likely to overthrow some of the tall towers on our list. These schemes include:
|
Tallest towers in the world


Jeddah Tower image (top): Jeddah Economic Company
Exclusive from Meed
-
Dubai scales up its metro ambitions23 April 2026
-
Sports Boulevard tenders Wadi Hanifa road works23 April 2026
-
Masdar to develop renewables projects in Montenegro23 April 2026
-
Qiddiya sets new deadline for infrastructure package23 April 2026
-
Detailed design progressing for major Iraqi oil project23 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Dubai scales up its metro ambitions23 April 2026

Dubai’s rail sector has rarely seen such a concentrated burst of procurement activity as it has in the past year.
Within the space of a few months, Dubai’s Roads & Transport Authority (RTA) has moved simultaneously on three distinct fronts: tendering design consultancy for the Route 2020 extension that will connect the Expo 2020 metro station to Al-Maktoum International airport; inviting study-and-design bids for a 55-kilometre Airport Express Line linking Dubai International airport to Al-Maktoum International airport; and culminating in Dubai Ruler Sheikh Mohammed Bin Rashid Al-Maktoum’s approval of the AED34bn ($9.2bn) Gold Line, a 42km fully underground route that the emirate is calling the largest transportation project in its history.
These projects form a key part of the Dubai Rail Network Plan 2032, which outlines the development of six public transportation schemes comprising a mix of metro, passenger and high-speed rail lines.
The most prominent feature of the plan is the addition of new lines to Dubai Metro’s existing network, representing a systematic effort to support the shift of Dubai’s economic centre of gravity towards Dubai South and the vast development corridors in between.
The city is also seeking to stay ahead of the curve by investing heavily in infrastructure. Data from regional projects tracker MEED Projects shows that the emirate has awarded over $14bn-worth of transport projects in the past two years alone, with several other multibillion-dollar schemes still moving through the planning stages.
All of this work is being carried out in line with the Dubai 2040 Urban Master Plan, which forecasts the emirate’s population will reach 5.8 million by 2040 – a clear indication of the scale of daily movement the city must accommodate.
Project progress
Dubai Metro Gold Line
On 21 April, Sheikh Mohammed officially announced the launch of the new AED34bn ($9.2bn) Gold Line project.
The line will be a fully underground network spanning over 42 kilometres, with 18 stations.
It will run from Al-Ghubaiba in Bur Dubai to Jumeirah Golf Estates.
The Gold Line will connect with Dubai Metro’s existing Red and Green lines and integrate with the Etihad Rail passenger network.
In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the project.
Stage one covers concept design; stage two, preliminary design; stage three, preparation of tender documents; stage four, construction supervision; and stage five, the defects liability period.
Airport Express Line
Procurement has started for another metro line extending from Dubai International airport (DXB) in Al-Garhoud to Al-Maktoum International airport (DWC) in Jebel Ali.
Earlier this month, the RTA invited consultants to bid for a contract to study and design what is referred to as the Airport Express Line.
The proposed line will stretch about 55km and include five stations that will provide passengers with facilities such as remote airline check-in, baggage drop-off and security screening.
The new line will run from the Red Line metro station at DXB through Al-Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC), before continuing on to DWC.
There will be two spur lines. The first will run from the new JVC station to Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch toward Business Bay, where another station will be built.
Expo 2020 route extension
Dubai is also undertaking the Route 2020 extension of its metro system, which will start from the Expo 2020 metro station and connect with Al-Maktoum International airport’s West Terminal.
Consultants submitted their bids earlier this month for the design contract.
The extension will run for about 3km and feature two stations.
The existing Route 2020 metro link is a 15km line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.
Dubai Metro Blue Line extension
Construction progress on the Dubai Metro Blue Line extension is expected to reach 30% by the end of 2026, according to official accounts.
In December 2024, the RTA awarded a AED20.5bn ($5.5bn) main contract for the construction of the project.
The contract was awarded to a consortium of Turkiye’s Limak Holding, Mapa Group, also of Turkiye, and the Hong Kong office of China Railway Rolling Stock Corporation (CRRC).
The Blue Line will connect the existing Red and Green lines. It will be 30km long, with 15.5km underground and 14.5km above ground.
The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.
The project is scheduled for completion in September 2029.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16534887/main.png -
Sports Boulevard tenders Wadi Hanifa road works23 April 2026

Register for MEED’s 14-day trial access
Saudi Arabia’s Sports Boulevard Foundation has issued a tender inviting firms to bid for a contract to build a road and associated infrastructure in the Wadi Hanifa area of Riyadh.
The bid submission deadline is 27 April.
The scope includes construction of an 11.4-kilometre road and associated infrastructure, including public realm works, utilities and security systems.
The scheme is the latest package to progress on Riyadh’s Sports Boulevard project.
The Sports Boulevard Foundation is also evaluating bids for its Global Sports Tower in the development’s Athletics District.
The 130-metre-tall Global Sports Tower will have a gross floor area of 84,000 square metres (sq m) and will include more than 30 sports facilities. The tower will feature what is billed as the world’s tallest indoor climbing wall, at 98 metres, and a 250-metre running track.
Sports Boulevard will run across Riyadh from east to west. Once complete, it is intended to be the world’s longest park, stretching more than 135 kilometres.
The project is divided into multiple districts, including the Wadi Hanifah, Arts, Urban Wadi, Entertainment, Athletics and Eco districts, as well as Sands Sports Park.
The large-scale development aims to transform central Riyadh – currently dominated by major highways – into a recreational corridor.
Sports Boulevard will include 4.4 million sq m of public realm and landmark buildings. Along with the Global Sports Tower, there will be a Centre for Cinematic Arts and a 2,000-seat amphitheatre.
It will also deliver more than 2.3 million sq m of mixed-use commercial, residential and retail space, alongside sports facilities, around the park, known as the Linear Park.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16534345/main.jpg -
Masdar to develop renewables projects in Montenegro23 April 2026
Abu Dhabi Future Energy Company (Masdar) and Elektroprivreda Crne Gore (EPCG) have agreed to establish a 50:50 joint venture to develop and operate renewable energy projects in Montenegro.
The planned projects include solar photovoltaic (PV), wind, hydropower, pumped-hydro storage and battery energy storage systems.
The joint venture will be headquartered in Niksic in western Montenegro and is intended to support Montenegro’s domestic energy needs while also enabling the export of renewable electricity to the Western Balkans and Southern Europe, Masdar said in a statement.
The companies plan to leverage an existing sub-sea interconnection with Italy. Montenegro is connected to Italy via a 600MW HVDC submarine cable, enabling electricity exports to the Italian market.
Masdar has an existing presence in Montenegro through its investment in the 72MW Krnovo wind farm.
The developer has recently accelerated foreign investment plans as part of its broader expansion. In April, it signed a binding agreement with France’s TotalEnergies to establish a $2.2bn joint venture to develop, build and operate renewable energy projects across Asia.
The combined business will have 3GW of operational capacity and 6GW of projects in advanced development, targeted for commissioning by 2030.
Masdar is targeting a global renewable energy portfolio of 100GW by 2030. It recently reached 65GW, two-thirds of the way to that target.
The company plans to deploy an additional $30bn-$35bn in equity and project finance by 2030, adding an average of 10GW of new capacity each year.
This expansion will be funded through a mix of equity, green bonds and long-term project financing.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16534112/main.jpg -
Qiddiya sets new deadline for infrastructure package23 April 2026

Saudi gigaproject developer Qiddiya Investment Company (QIC) has set a 13 May deadline for bids for a contract covering new infrastructure works at Qiddiya Entertainment City.
The scope comprises two infrastructure development packages for District 0 of Qiddiya Entertainment City, including the construction of four event park-and-ride facilities.
The tender was issued on 11 March, with an initial bid submission deadline of 22 April.
Lebanese firm Dar Al-Handasah and Saudi-based Sets International are serving as project consultants.
QIC is accelerating plans to develop additional assets at Qiddiya City. Earlier this month, the company received prequalification statements from firms for the engineering, procurement, construction and finance package for the Qiddiya high-speed rail project.
MEED has also reported that QIC received bids from contractors on 23 February for a SR980m ($261m) contract covering the construction of staff accommodation at Qiddiya Entertainment City.
The project will cover an area of more than 105,000 square metres (sq m).
Also in February, QIC started the main construction works on its performing arts centre at the entertainment hub.
The Qiddiya City performing arts centre is one of several major projects within the greater Qiddiya development. Other projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a motorsports track, the Dragon Ball and Six Flags theme parks, and Aquarabia.
QIC officially opened the Six Flags theme park to the public in December last year.
The park covers 320,000 sq m and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.
The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to UK analytics firm GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.
Saudi Arabia’s tourism sector posted record figures last year, with more than 130 million domestic and international visitors – a 6% increase on 2024.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16533776/main.jpg -
Detailed design progressing for major Iraqi oil project23 April 2026

Detailed design work is progressing on Iraq’s 950-kilometre seawater pipeline network under the Common Seawater Supply Project (CSSP), according to industry sources.
They added that on-site construction would begin only after the detailed design is complete.
Iraq’s state-owned Basra Oil Company (BOC) and China Petroleum Pipeline Engineering (CPP) signed a $2.5bn contract for the pipeline package in September last year.
The project is being supervised by Austria’s ILF Consulting Engineers.
The pipeline package is one of two main CSSP packages.
The second focuses on a seawater treatment facility, expected to have a capacity of 5 million barrels a day (b/d), potentially rising to 7-8 million b/d in later phases.
Processed water will be injected into some of Iraq’s largest oil fields – Rumaila, Zubair, West Qurna 1, West Qurna 2 and Majnoon – and also used in the Maysan and Dhi Qar fields.
Iraq’s Oil Ministry said the injected water will help maintain reservoir pressure and sustain crude production.
CPP is a subsidiary of state-owned China National Petroleum Corporation.
TotalEnergies is responsible for the CSSP as part of the larger $27bn Gas Growth Integrated Project.
Iraq approved a $2.45bn contract with South Korea’s Hyundai Engineering & Construction (Hyundai E&C) in August last year for the engineering, procurement and construction of the seawater treatment plant.
Over recent weeks, Iraq’s oil exports have collapsed by about 80% due to fallout from the US and Israel’s war with Iran.
READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDFEconomic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.
Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:
> AGENDA: Gulf economies under fire> GCC CONTRACTOR RANKING: Construction guard undergoes a shift> MARKET FOCUS: Risk accelerates Saudi spending shift> QATAR LNG: Qatar’s new $8bn investment heats up global LNG race> LEADERSHIP: Shaping the future of passenger rail in the Middle EastTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/16527404/main.jpg
