Top 10 GCC contractors by country
29 March 2023

This article is part two of MEED's 2023 construction contractor ranking. The first part, MEED's 2023 top 10 GCC contractors, can be accessed here. Key points include:
> Sentiment runs ahead of construction activity
> Improved outlook for the Gulf region’s construction market is not reflected in the 2023 contractor ranking
> Nesma & Partners retains its position as the most active GCC contractor, but its total value of work this year is down 22 per cent on 2022
PPP progress spurs Bahrain real estate
Bahrain is traditionally the smallest construction market in the GCC, a position that reflects the island kingdom’s small population and land area, combined with energy exports that are limited when compared to its neighbours.
China Machinery Engineering Corporation continues to lead the ranking in 2023 with $689m-worth of work at the execution phase thanks to its contract to build the East Sitra development for the Housing Ministry.
In second position is Sharjah-based Al-Hamad Building Contracting, which is working on $560m-worth of projects. The contractor was the third-ranked contractor last year.
In third position this year is the local Kooheji Contractors with $449m of projects. Its rise from eighth position in the ranking reflects the resurgent property market in Bahrain. The firm is part of the Kooheji group, which is developing new real estate projects in Manama, including the Onyx Sky View project that was launched at the end of last year.
Turkey’s Tav Construction – which was ranked fifth last year as it completed work at the airport – has now left the top 10. Its position in the ranking since 2016 demonstrated the importance of major projects to the Bahrain market.
While there has been a lull in construction activity in Bahrain over the past two years, major new projects are planned, including the Bahrain Metro and a second causeway bridge to Saudi Arabia.
The Transport & Communications Ministry has prequalified companies for the metro, which will be developed as a public-private partnership (PPP). Similarly, the King Fahd Causeway Authority has approached contractors about working on the causeway, which is also being developed as a PPP.
Airport contractor still leads in Kuwait
Kuwait’s ranking continues to be led by Limak with $5bn-worth of work at the execution stage. The Turkish contractor remains active on the expansion of Kuwait International airport. It could be the last year that Limak heads the Kuwait ranking, however, as the airport work is due for completion this year.
The rest of the contractors below Limak have endured a significant drop in the value of the projects they are engaged on. The average total value of projects being worked on for the top 10 in 2023 is $1.1bn, down from $1.7bn in 2022.
Occupying the second and third places in this year’s ranking are two of Kuwait’s largest contracting companies. Ahmadiah Contracting & Trading Company is in second place with $1.1bn of work, followed by Mohammed Abdulmohsin al-Kharafi & Sons with $900m.
With Limak’s work at the airport coming to a close, these two companies are likely to return to the top of the Kuwait ranking in 2024.
The only other international companies in the Kuwait top 10 are Italy’s Impresa Pizarotti in sixth place with $730m of work and India’s Shapoorji Pallonji in seventh place with $687m of work at the execution stage.
Little change in Oman as big projects loom
Oman’s contractor ranking has remained largely static this year. The local Galfar Engineering & Contracting tops the list again with $1.05bn of work, down slightly on the $1.1bn of projects it was working on in 2022.
Last year’s second- and third-ranked contractors have switched places. The local Al-Adrak Trading & Contracting Company is now ranked second with $800m of work and the local Al-Tasnim Enterprises is ranked third with $770m.
India’s Larsen & Toubro is the only international company that makes the top 10 this year. It is ranked number five with projects worth $280m at the execution stage.
International companies could figure more prominently in the ranking in future. Oman-Etihad Rail Company is expected to tender construction contracts connecting Oman and the UAE later this year, and it is likely that international contractors will be involved in delivering that project.
Similarly, tentative steps have been taken on the proposed Muscat Metro project. This scheme is unlikely to move into construction by next year, but if it goes ahead, it will offer more significant opportunities for international players.
Qatar numbers drop in post-World Cup lull
After years of doubt and criticism, Qatar’s construction market successfully delivered the infrastructure, stadiums and hotels needed to host the Fifa World Cup last year.
The problem is, with that 10-year building programme now complete, there are few projects left for contractors to work on. This is most clearly shown in the 2023 contractor ranking by the local Urbacon Trading & Contracting Company’s numbers.
This year, the firm has $1.8bn-worth of projects at the execution stage, which is significantly less than the $4.9bn it was working on in 2022.
To counter the decline in the domestic market, Urbacon is pursing opportunities internationally. The company recently secured two major contracts in Saudi Arabia for the construction of entertainment complexes.
Other contractors are likely to pursue a similar strategy as they face fewer new Qatari projects moving into the construction phase in the near term.
There is a hope that major schemes such as the Doha Bay Crossing and extensions to the metro will move ahead, however. If these schemes do progress, then they are likely to spend the next year in the design and tendering phases before they move into construction.
Gigaprojects shake up Saudi ranking
Saudi Arabia is the region’s most exciting construction market in 2023. After six years of planning, construction work is now well under way on the kingdom’s five gigaprojects – Neom, Qiddiya, The Red Sea, Roshn and Diriyah Gate – as well as on a host of other masterplan projects such as Sports Boulevard and King Salman Park.
As construction ramps up, logic would dictate that the value of projects that contractors are working on would also increase. Somewhat surprisingly, this has not been the case, and in the 2023 ranking, most of the top 10 are working on a lower value of projects than they were in 2022.
This could be explained by the fact that several legacy projects in the kingdom have been completed in the past year, but it also suggests that while there is an expectation of a significant ramp-up in construction activity, it has not quite happened yet.
The top-ranked contractor, Nesma & Partners, shows this trend clearly. In 2022 it was working on $6.8bn of projects. In 2023 it is working on $5.3bn.
The second-ranked Saudi Binladin Group has experienced a similar decline, with its total value falling from $6.5bn to $4bn.
There are several explanations for this trend. Some say projects are moving into construction more slowly than expected as they get bogged down in the design phase, and that decision making at the senior level is hampering design and procurement decisions. Others say that the market is already operating at full capacity and can not take on more work.
Some respite for the market is in sight. This year, the Public Investment Fund invested in four contractors: Almabani, Nesma, El-Seif Engineering & Construction and Al-Bawani. These firms are expected to grow rapidly and take a leading role in delivering projects for Vision 2030.
Other companies are also expanding. One is the local Modern Building Leaders, which has entered the top 10 this year at number eight, with $2.3bn of work at the execution stage. Its main project wins have been the Royal Arts Complex in Riyadh and the expansion of Duba Port.
With so many large projects expected to move into construction in the next year, there will be plenty of opportunities for contractors in Saudi Arabia to build up their order books. This should mean that the kingdom’s ranking will be a dynamic one in the years ahead.
All change in the UAE construction market
The top 10 contractor ranking for the UAE shows a shift in the order of companies and the growing dominance of Abu Dhabi-based contractors, as well as a general decline in the value of projects being worked on.
National Marine Dredging Company (NMDC) has taken the top spot with projects worth $2.3bn. The Abu Dhabi-listed contractor has moved up from fourth position in the 2022 ranking.
NMDC replaces Beijing-based China State Construction Engineering Corporation, which was at the top of the 2022 ranking with project values worth $2.6bn. The Chinese firm has dropped to third place this year with projects worth $1.6bn. Its fall from the top of the ranking can largely be explained by it completing a series of real estate projects in Dubai in the past year.
China State’s orderbooks are expected to swell this year as Dubai’s property market remains buoyant and major projects start moving into construction. An example is Wasl’s Island project, which involves the construction of several high-end hotels on a man-made island close to Marsa al-Arab.
Abu Dhabi-based Trojan General Contracting has moved up from the sixth position in 2022 to the second position in 2023, with project values worth $1.7bn.
Another Abu Dhabi-based firm, Al-Amry Transport & General Contracting, has moved into the top 10 to occupy the fourth position in the 2023 raking, with $1.2bn of projects at the execution phase.
In fifth position is iBuild, which is working on $1.2bn of projects. The company is part of Innovo Holding UK, a London-registered firm with ownership links to ASGC, which occupied 10th position in the 2023 ranking with $774m of projects at the executions stage.
Although they are separate companies, if iBuild and ASGC were taken together they would be working on $2bn-worth of projects and would occupy the second position in the ranking.
Another contractor in the ranking that has gone through corporate change is Dubai-based Alec. Ranked seventh with $919m of work, it completed the acquisition of Abu Dhabi-based Target Engineering last year, giving it a foothold in the oil and gas market. Both Alec and Target now aim to double their turnover in the next five years, mostly with work from the UAE and Saudi Arabia.
MEED's 2023 top 10 GCC contractors
Exclusive from Meed
-
Kuwait utilities investment shifts towards water11 August 2026
-
Syrian court gives death penalty to Bashar Al-Assad11 August 2026
-
Oman extends deadline for $150m water transmission project11 August 2026
-
Medina invites bids for major stormwater project11 August 2026
-
Adnoc Gas expects Habshan to hit full capacity in 202711 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait utilities investment shifts towards water11 August 2026

China State Construction Engineering Corporation recently signed a contract for Kuwait’s North Kabd wastewater treatment plant, the country’s largest wastewater infrastructure project to date.
The award, following more than a decade of planning, propelled Kuwait’s water sector contract awards to more than $4bn as of early August, according to regional project tracker MEED Projects.
The facility will have a treatment capacity of up to 1 million cubic metres a day (cm/d), with the $3.3bn contract covering the design, construction, operation and maintenance of the plant over a 10-year period.
It marks a significant recovery for the sector after several years of subdued activity and the first time since 2020 that annual water awards have exceeded $1bn.
North Kabd is the largest of several major water projects awarded this year, alongside contracts covering desalination and the expansion and rehabilitation of water distribution infrastructure.
Desalination and distribution
These include a $316m contract awarded to local firm United Gulf Construction (UGC) by the Ministry of Electricity, Water & Renewable Energy (MEWRE) for the rehabilitation and expansion of the Doha water distribution complex.
The five-year project includes a new pump station and will add about 130 million imperial gallons of storage capacity, while increasing pumping capacity to 220 million imperial gallons a day (MIGD).
UGC was also selected in February to upgrade the Hawally water distribution complex in Kuwait’s Hawalli Governorate. The facility serves one of Kuwait’s most densely populated governorates, with the project intended to address chronic low water pressure, particularly during peak summer demand, and improve continuity of supply.
The upgrade will increase freshwater storage capacity by 66 million gallons and raise potable-water pumping capacity to 54.5 million gallons a day.
In April, Kuwait’s Central Agency for Public Tenders approved MEWRE’s recommendation to award a $371m contract for phase two of the Doha seawater reverse osmosis (SWRO) desalination plant.
A joint venture of Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco) and India’s VA Tech Wabag will carry out the project, which will have a capacity of about 272,000 cm/d.
Upcoming water awards
Meanwhile, Kuwait’s Ministry of Public Works (MPW) has been progressing several tenders for major water infrastructure projects covering rainwater drainage and treated water systems in the country’s southern and northern regions.
In July, local Combined Group Contracting submitted the lowest bid for a contract to develop a major treated water system in the southern region. The contractor submitted a price of about $515m for the scheme, according to a company disclosure.
For the smaller northern treated water system, Contractor General Trading & Contracting submitted the lowest bid of $169m.
In what is already a standout year for Kuwait’s water sector, further awards could push activity significantly higher. More than $1bn of water projects are currently under bid evaluation, indicating further evidence of a sustained recovery in the months ahead.
Power sector activity
Kuwait’s power sector recorded just $271m of contract awards by early August, according to MEED Projects, putting activity well below recent annual levels.
This compares with a record full-year total of $5.5bn in 2025 and $2.7bn in both 2024 and 2023.
Several large-scale generation projects have been slow to advance, with deadline extensions a notable feature in recent months. The outlook is stronger, however, with these projects now progressing through procurement and significant awards expected in the months ahead.
Kuwait is advancing the 1,800MW Al-Khairan phase one independent water and power project (IWPP), for which two developer consortiums led by Abu Dhabi National Energy Company (Taqa) and Saudi Arabia’s Acwa submitted bids in June.
The project will also include a desalination plant with a capacity of 125 MIGD. A second phase of the Al-Khairan IWPP, estimated at $750m, is understood to include a further 1,800MW of generation capacity through a combined-cycle gas-fired power plant. The project remains in the early development stages, with tendering not expected until at least 2027.
Renewable energy programme
The Kuwait Authority for Partnership Projects (Kapp) is also progressing the Al-Dibdibah power and Al-Shagaya renewable energy programme in partnership with Kuwait’s MEWRE.
The contract to develop the 1,100MW phase three, zone one solar photovoltaic (PV) project is expected to be confirmed soon, with a consortium led by Abu Dhabi Future Energy Company (Masdar) previously reported to be the frontrunner.
A separate 500MW solar PV project is also being procured under phase three, zone two of the same programme, with bids submitted on 26 July. If the contract is awarded by the end of the year, the two Shagaya contracts would add about $2bn to the value of power sector awards.
Another notable development was the 25-year energy conversion and water purchase agreement signed in February for the Al-Zour North IWPP phases two and three. The signing marked a key step towards financial close on the estimated $4bn project. Once completed, the facility will add 2,700MW of power and 120 MIGD of desalinated water to Kuwait’s supply network
The Shagaya, Khairan and Zour North projects form a key part of Kuwait’s generation portfolio. The country is aiming to reach 22,100MW of installed renewable energy capacity by 2030, under a 20-year strategy announced in March 2025 that extends to 2050.
Kuwait is also continuing to invest in existing generation plants. MEWRE is evaluating bids for the $1.7bn upgrade of the Subiya power and water plant, including the conversion of units from open-cycle to combined-cycle operation and the modernisation of existing facilities.
Battery energy storage systems
In the near to medium term, more than $10bn-worth of power projects are under bid evaluation. This includes several battery energy storage system projects with a planned total storage capacity of 1.5GW.
In June, Kuwait approved sites in Al-Mutlaa and Jaber Al-Ahmad cities for the development of the projects. The projects will be implemented in phases, with the first phase providing 500MW of storage capacity. The first facilities are expected to be operational by summer 2027 and will supply stored energy to the electricity grid during periods of peak demand.
Elsewhere, MEWRE continues to evaluate offers from Shanghai Electric Group and local firm Heavy Engineering Industries & Shipbuilding Company (Heisco) for the estimated $400m engineering, procurement and construction contract to rehabilitate and modernise eight boilers at the Subiya power generation and water distillation station. The bid bond validity has been extended to 23 August, indicating that the procurement process remains ongoing.
MEED’s September 2026 report on Kuwait also includes:
> ECONOMY: Kuwait shows tentative signs of economic development
> BANKING: Necessity is the mother of invention for Kuwaiti lenders
> OIL & GAS: Regional war to have lasting impact on Kuwaiti oil sector
> CONSTRUCTION: Kuwait construction holds up despite regional strifehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18333042/main.gif -
Syrian court gives death penalty to Bashar Al-Assad11 August 2026
A Syrian court has sentenced former president Bashar Al-Assad to death after trying him in absentia, convicting him of crimes committed during the country’s nearly 14 years of civil war.
It is the first such ruling under Syria’s transitional authorities, who ousted Al-Assad in December 2024 and vowed justice and accountability for crimes committed under his rule.
Al-Assad fled to Moscow as Islamist-led forces closed in on Damascus after a lightning offensive.
In a Damascus court, Judge Fakhr Al-Din Al-Aryan convicted Al-Assad of crimes including “premeditated murder, the intentional killing of more than one person, the intentional killing of children under 15 years … torture, torture leading to death, and deprivation of liberty on multiple occasions” — acts the court classified as crimes against humanity and war crimes.
“He is therefore sentenced to death,” the judge said in his ruling.
The court also sentenced six former military and security officials to death in absentia, including Al-Assad’s brother Maher, who ran the army’s elite Fourth Division and also fled the country.
Those convicted included former defence minister Fahd Al-Freij and Louay Al-Ali, who headed military intelligence in Daraa province in 2011.
ALSO READ: Syria charts post-war reconstruction course
The officials were convicted of crimes including murder, incitement to murder, torture leading to death and repeated deprivation of liberty, also classified as crimes against humanity and war crimes.
Former security official Atif Najib – the only defendant tried in person – was also sentenced to death for crimes against humanity committed while he headed political security in Daraa province, the cradle of the country’s 2011 uprising.
Najib, a cousin of Al-Assad who was arrested in January last year, was convicted of crimes including murder, the intentional killing of children under 15 and torture leading to death.
The acts attributed to him are “crimes against humanity”, the court said as it handed down “the harshest punishment … which is the death penalty”.
ALSO READ: US lifts sanctions on Syria after the EU takes similar action
Syria began proceedings in April against Al-Assad and other officials, accused both in person and in absentia of atrocities during the civil war, which erupted after the former authorities’ brutal repression of pro-democracy protesters.
More than half a million people were killed and millions displaced, while tens of thousands disappeared, many into the country’s brutal prison system.
The uprising began in Daraa in March 2011 after 15 students were arrested for allegedly writing anti-government slogans on the city’s walls.
Residents said the students were tortured, prompting protests demanding their release that ended in bloodshed.
Security forces suppressed demonstrations and fired live ammunition to disperse sit-ins at several locations.
Najib was dismissed after the crackdown as protests spread to other provinces.
Judge Al-Aryan said Najib had denied the charges and shown “no remorse”.
Al-Assad took power in Syria in 2000 in an unopposed election following the death of his father, Hafez Al-Assad, who was president from 1971.
ALSO READ: Syria exports first crude oil batch in 14 years
https://image.digitalinsightresearch.in/uploads/NewsArticle/18331541/main.gif -
Oman extends deadline for $150m water transmission project11 August 2026

State-owned Nama Water Services (NWS) has extended the bid submission deadline for a contract to build a $150m water distribution network project in Jalan Bani Bu Ali Wilayat in Oman’s South Sharqiyah Governorate.
The new deadline is 24 August. The original deadline was 17 August.
The engineering, procurement and construction (EPC) contract covers the development of water distribution infrastructure in the JBBA North and JBBA Coastal areas.
The scope includes new water storage reservoirs, elevated tanks, booster pump stations and transmission and distribution pipelines.
The project includes two reservoirs in the JBBA North area with a capacity of 40,000 cubic metres, along with about 58 kilometres of ductile iron distribution pipelines and 343km of high-density polyethylene (HDPE) pipelines.
The JBBA Coastal works include reservoirs at Asilah, Ashkarah, Wadi Sal and Khabbah, as well as elevated tanks and pump stations. The scope also includes about 38.5km of 400mm-diameter ductile iron transmission pipeline.
NWS issued the main contract tender on 4 June. UK-headquartered Mott MacDonald is the main consultant on the project.
The project is one of three water distribution schemes being tendered under a wider $350m masterplan covering Jalan Bani Bu Hassan, Jalan Bani Bu Ali, and Al-Kamil and Al-Wafi wilayats.
The Jalan Bani Bu Hassan scheme includes a new 40,000-cubic-metre ground reservoir at Al-Sayah Al-Sharqi 4, a pump station and associated transmission and distribution pipelines. It will also include a pump station serving the Industrial Area and an inline booster pump station supplying Al-Mintajjah and Sariq Haryah.
The projects covering Jalan Bani Bu Ali and Al-Kamil and Al-Wafi wilayats are estimated to cost £100m each. The bid submission deadline for both projects is 17 August.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18326851/main.jpg -
Medina invites bids for major stormwater project11 August 2026

Saudi Arabia’s Madinah Municipality has issued a tender for an engineering, procurement and construction (EPC) contract to upgrade the city’s rainwater drainage network.
According to regional project tracker MEED Projects, it is the first main contract tender the municipality has issued for a major water infrastructure project since 2022.
The $30m project covers the construction of rainwater drainage networks and the repair of existing stormwater pipelines across major roads and corridors within the urban area of Medina.
It aims to improve the performance of the city’s stormwater drainage system, reduce surface flooding, and protect roads and nearby assets during heavy rainfall.
The bid submission deadline is 5 September.
According to MEED Projects data, Madinah Municipality completed two rainwater drainage network projects in Medina in 2024.
The local Al-Ayuni Investment & Contracting was the EPC contractor for both Phase 1 and Phase 2 projects. Saudi contractor Azmeel Contracting also previously submitted bids for both projects.
The municipality is also understood to be nearing completion of a separate Phase 1 rainwater drainage network project in Al-Rawabi in Al-Madinah province. This project was tendered in 2022 and awarded to Al-Naeim Contracting (Saudi Arabia) in 2023.
Meanwhile, Madinah Municipality received prequalification documents at the beginning of the year for two stormwater drainage projects in Yanbu. It is unclear if the main contract tender will be issued this year.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18325305/main.jpg -
Adnoc Gas expects Habshan to hit full capacity in 202711 August 2026
Adnoc Gas hopes to restore full output capacity at its Habshan gas processing facility in Abu Dhabi by the second quarter of next year, following attacks on the facility in March and April during the US-Iran conflict.
Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), said it has already restored 85% of the Habshan facility’s capacity, surpassing the year-end target set in May.
The Habshan complex is one of the largest gas processing facilities in the UAE and the wider Middle East and North Africa region. It has a processing capacity of 6.1 billion cubic feet a day. The complex comprises five trains and 14 processing units that receive gas feedstock from onshore and offshore fields in Abu Dhabi.
The Habshan facility was struck at least three times in March and April by Iranian drones and missiles. On 19 March, UAE authorities suspended operations at Habshan after it was affected by debris falling from Iranian missiles intercepted by the country’s air defence systems.
Adnoc Gas then announced on 23 March that operations were continuing safely across its asset base, after similar missile and drone attacks by Iran on facilities owned by its parent, Adnoc Group, although it did not specifically mention the Habshan plant.
The worst of the attacks on Habshan took place on 3 April, when Iranian drones intercepted by the UAE’s air defence systems caused damage at the site, resulting in the death of an engineer working at the facility for Egyptian contractor Petrojet during an evacuation. Four other contractors sustained minor injuries, but were later discharged from hospital after receiving treatment.
ALSO READ: Adnoc Gas to move prudently on Bab Gas Cap project
On 8 April, Abu Dhabi authorities said three people – two Emiratis and an Indian national – sustained minor injuries after debris fell at the Habshan gas complex following a successful interception by the UAE’s air defence systems.
The debris also sparked several fires at the facility, prompting a temporary suspension of operations as safety and response teams assessed the situation.
“Adnoc Gas responded swiftly to the security-related incidents at the Habshan site on 3 and 8 April, prioritising safety and minimising disruptions to customers,” the company said on 10 August.
“The company has concluded its technical assessment of the impact from these incidents and recovery has progressed ahead of schedule, with gas supply already restored to 85%,” Adnoc Gas said as part of its announcement of financial results for the second quarter of 2026.
During a press conference to discuss Adnoc Gas’ Q2 2026 results, Peter Van Driel, the company’s chief financial officer, said: “At the moment, we have progressed to 85% of supply being reinstated, so the balance will be reinstated between now and the first half of 2027.
“If I look at the cost impact, we are still firming up our estimates. There are uncertainties around the pricing of certain items that we need to install as part of the final reinstatement.
“If we look at the key driver for our results in the second half, the 85% reinstatement of supply is definitely important. We’re encouraged by the fact that the 85% was delivered ahead of schedule,” Van Driel told journalists.
Fatema Al-Nuaimi, Adnoc Gas’ CEO and board member, said: “If I may add one point: it might be 85%, but in reality, today we are supplying 100% of our customers’ requirements locally.”
She added: “On exports, of course, we try our best to satisfy requirements and work closely with customers. But in terms of gas supply to the UAE, we are at 100%.”
Role of robotics and AI
Responding to a question about the deployment of robotics and artificial intelligence (AI) to carry out damage assessment and repair work at the Habshan gas processing facility, Al-Nuaimi said: “One of the technical challenges in restoring the facilities quickly was that we had to inspect a significant part of our assets – some 600 kilometres of piping of different sizes across the facilities.
“If we had done this in the conventional way, we would have spent around 100 additional days putting up scaffolding and sending people to conduct manual and visual inspections.”
The CEO continued: “Instead, we used robotics supported by AI-driven software, which enabled us to shorten the inspection and response time and carry out repairs faster.
“It was not just about time; it was also about safety. It spared us from sending our people into critical areas that might not yet have been safe.”
She added: “We also used robotics in responding to fires and accessing certain parts of the assets.
“When we talk about AI, it is not a headline. It is real work and real value that we see every day in our business,” Al-Nuaimi further remarked.
ALSO READ: Adnoc announces FID on $6.2bn Umm Shaif gas cap project
https://image.digitalinsightresearch.in/uploads/NewsArticle/18324488/main.jpg