The region’s most ambitious causeway projects
8 February 2023

The submission of feedback questionnaires and meetings with contractors for the planned second causeway connecting Saudi Arabia and Bahrain is the latest sign of potential progress on one of the region’s largest infrastructure projects.
Causeways have a chequered history in the region. The first causeway connecting Saudi Arabia and Bahrain was completed during the 1980s, and since then, it has had a transformative impact on the Bahraini economy.
The project’s success has inspired other causeways. But while these schemes remain ambitions for many in the region, construction progress has been limited. The hope is that a successful second causeway linking Saudi Arabia and Bahrain will foster the delivery of other longstanding causeway plans.
These are the most ambitious causeway schemes that the region has planned:
| Second Saudi Arabia-Bahrain causeway |
The second causeway between Saudi Arabia and Bahrain is the most likely to proceed. Planned by the King Fahd Causeway Authority, the $3.5bn project, which has been called the King Hamad Causeway project, is moving towards construction.
In 2021, senior government officials in Bahrain told MEED that the project was progressing towards tendering as financial studies had been completed.
The project was included in Bahrain’s $30bn Strategic Projects Plan that was announced later in 2021. As well as the causeway, the plan includes building new urban areas on five reclaimed islands to increase the country’s total land area by 60 per cent. It also comprises plans for a new airport.
The second causeway involves building a 25-kilometre road and rail crossing linking Saudi Arabia and Bahrain. It will follow the same alignment as the existing King Fahd Causeway.
It has been earmarked for delivery on a public-private partnership (PPP) basis. The King Fahd Causeway Authority appointed a consortium to provide transaction advisory services in late 2019.
The $8.9m consultancy agreement was signed with a consortium of Netherlands-headquartered KPMG, US-based Aecom and UK-based CMS. The team was tasked with working on developing the financing model, the required engineering specifications and design, as well as helping with the assessment and selection of the project’s developers.
Canada-based SNC Lavalin and UK-based consultancy firm PwC conducted the project due diligence study in 2017.
The existing King Fahd Causeway is operating at capacity. About 11.5 million cars cross the causeway every year, and the growth has been 6 per cent per annum over the past 10 years.

| Qatar-Bahrain causeway |
There have also been suggestions that the proposed causeway bridging Bahrain and Qatar may be revived. In March 2022, Manama called for work to restart on the causeway joining the two countries.
“We in the Kingdom of Bahrain renew the call for the start of bilateral talks between the two sides in accordance with the mechanisms agreed upon in the Al-Ula statement,” said Bahrain’s undersecretary for land transportation and post in an official statement published by the official Bahrain News Agency.
The estimated $4bn Qatar-Bahrain causeway project was put on hold and the contracting consortium demobilised in 2010.
A joint venture of state-owned developer Qatari Diar Real Estate Investment Company and French contractor Vinci Construction Grand Projets led the consortium. The other consortium members were Germany’s Hochtief, Athens-based Consolidated Contractors Company (CCC), Dredging International from Belgium and the local Middle East Dredging Company (Medco).
The planned 40km bridge includes a four-lane motor crossing scheduled for completion in 2013 and two railway lines forming part of the GCC rail network.
The project also comprises 22km of bridges and viaducts, 18km of embankments and two 400-metre cable-stayed bridges. The causeway connects Ras Ashairij on the west coast of Qatar to Askar on the east coast of Bahrain.
The project was also known as the Friendship Bridge and was to be jointly funded by the Qatari and Bahraini governments, which intended to recover some of the construction costs by implementing a toll system on the bridge.
The crossing would cut the journey time between the two countries, which currently involves a detour through Saudi Arabia, from five hours to just 30 minutes.
| Saudi Arabia-Egypt causeway |
The prospects for the causeway connecting the $500bn Neom project in Saudi Arabia and Egypt’s Sinai Peninsula across the Straits of Tiran improved last year after US President Joe Biden’s visit to Saudi Arabia.
After the visit, a joint communique issued by Washington and Riyadh referred to the development of Tiran Island.
“President Biden welcomed the arrangements by Saudi Arabia to remove the Multinational Force & Observers (MFO) from the Island of Tiran, including the removal of US troops there as part of the MFO mission, while preserving and continuing all existing commitments and procedures in the area,” it said.
“This area of the Red Sea will now be developed for tourism and economic purposes, contributing to a more secure, peaceful and prosperous region.”
The US-Egyptian-Israeli-backed MFO was founded in 1981 to oversee the terms of the 1978 Camp David Accords, which included the full Israeli withdrawal from the Sinai Peninsula.
In 2016, Egypt and Saudi Arabia agreed during a state visit to Cairo by King Salman bin Abdulaziz al-Saud to develop a causeway linking the two countries across the Red Sea.
The agreement was made as part of a broader deal that would also involve Egypt ceding the sovereignty of the two Tiran islands to Saudi Arabia.
While details of the proposed crossing were never revealed at the time, it was understood to be a revival of a $4bn project announced in 2011. That scheme involved building a 32km crossing stretching over the Straits of Tiran from Ras Humaid in Tabuk, in the northern region of Saudi Arabia, to Ras Nasrani, close to the Egyptian resort of Sharm el-Sheikh.
Plans to link Saudi Arabia and Egypt are far from new. The development of a causeway was first mooted as far back as 1988. However, the idea has received additional focus in recent years following the launch of the Neom development in northwestern Saudi Arabia, which includes Ras Humaid. Part of the Neom scheme, the 170km-long linear city known as The Line, will extend from the promontory inland to the city of Tabuk.
UK-based Arup was reported to have been selected in 2019 for the next stage of the feasibility study for the causeway.
Saudi Arabia was understood to be considering using a public-private partnership (PPP) model for the scheme, similar to other transport projects planned in and around the kingdom.
| Yemen-Djibouti causeway |
A 28.5km causeway was planned to connect Yemen and Djibouti before the scheme was put on hold in 2010 until the governments of both countries signed the framework agreement for the project. The civil war in Yemen means it is unlikely the scheme will make any progress soon.
The estimated $20bn first phase involved building the link between the Yemeni mainland to the island of Perim in the Red Sea. Phase two would have then connected Perim with Djibouti.
The wider project also involves building two cities at each end of the link. The total investment required to construct the cities and the bridge is $200bn.
Dubai-based Al-Noor Holding Investment Company was developing the project.
In 2009, the company said it expected to award a build-operate-transfer contract for the first phase of the bridge and that three companies had expressed interest in funding and building the road and rail link. Denmark’s Cowi prepared the preliminary design for the crossing.
| UAE-Qatar causeway |
In 2005, Abu Dhabi and Doha were reported to have been setting up a joint company to oversee the implementation of the proposed UAE/Qatar causeway.
The 40km causeway was expected to start near Sila in Abu Dhabi emirate and extend to the south of Doha.
The estimated $13bn crossing would have significantly cut journey times. At present, traffic between Qatar and the UAE has to pass through 125km of Saudi Arabian territory.
The scheme stalled shortly afterwards. Problems included difficulties with the route, which ran through Saudi Arabian territorial waters.
Exclusive from Meed
-
Qiddiya plans $7bn theme park hub near Paris25 August 2026
-
Masdar shelves Abu Dhabi green hydrogen project25 August 2026
-
Oman invites bids for Musandam renewables study25 August 2026
-
US launches sanctions campaign against Iran25 August 2026
-
Kuwait tenders $3.3bn gas processing facility25 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Qiddiya plans $7bn theme park hub near Paris25 August 2026
Saudi Arabia’s Qiddiya Investment Company plans to develop a mixed-use leisure destination worth about €6bn ($7bn) at Cergy-Pontoise in the Ile-de-France region, in one of the largest Saudi investments in French tourism infrastructure to date.
The plan was set out in a joint statement issued on 24 August at the close of a state visit to France by Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud. France and Saudi Arabia signed a memorandum of understanding (MoU) covering the project during the two-day visit.
The destination will bring together entertainment, leisure, hospitality, culture and sport, according to the joint statement. Current plans envisage up to three major entertainment anchors, hotels and complementary leisure experiences, with the €6bn figure covering the full development lifecycle.
One of the three parks is expected to be manga-themed, according to the French presidency. The themes of the other two have not been disclosed. The parks will be built and opened in stages, with construction expected to take several years. No opening date has been given.
The parks are expected to create about 22,000 direct jobs, according to the French presidency, compared with about 20,000 at Disneyland Paris. Cergy-Pontoise lies about 30 kilometres northwest of Paris.
Qiddiya is a subsidiary of the Public Investment Fund, Saudi Arabia’s sovereign wealth fund. Its flagship project is a giga-scale entertainment, sports and cultural city on the outskirts of Riyadh, one of several gigaprojects under Vision 2030.
The theme park plan was among a wider set of agreements reached during the visit. Both sides welcomed the announcement of 21 agreements and MoUs at a French-Saudi investment roundtable, spanning energy, industry, financial services, transport and logistics, health, culture, tourism and artificial intelligence. Bilateral trade reached about $11.8bn in 2025.
It is not the first time Saudi capital has backed a French theme park. Kingdom Holding Company was a longstanding investor in the operator of Disneyland Paris, first taking a stake in 1994 and participating in successive recapitalisations before Walt Disney Company moved to near-full ownership in 2017.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18987274/main.png -
Masdar shelves Abu Dhabi green hydrogen project25 August 2026

Abu Dhabi Future Energy Company (Masdar) has decided to cancel a planned project to build a green hydrogen plant in Abu Dhabi that would have supplied up to 100MW of renewable hydrogen to local steelmaker Emsteel for green steel production.
After contractors submitted bids for the project last year, Masdar asked bidders in the first quarter of this year to extend the validity of their proposals until the end of August to allow “more time to study and evaluate bids”, according to one source.
However, Masdar issued a notification to all bidders on 1 August stating that it had decided to cancel the project, sources told MEED.
Contractors that submitted bids for the Masdar green hydrogen project included:
- Envision (China)
- Larsen & Toubro (India)
- PowerChina (China)
- Samsung E&A (South Korea)
- Sinopec (China)
Masdar did not respond to MEED’s request for comment on the information.
In its current steelmaking process, Emsteel uses hydrogen produced by steam reforming of natural gas as a reducing agent to extract iron from iron ore. The core objective of Masdar’s planned project was to install a 100MW electrolyser at Emsteel’s main manufacturing hub in Musaffah, Abu Dhabi, to supply green hydrogen for future clean steel production.
Masdar initiated work on the project in 2024 by awarding a front-end engineering and design (feed) contract to locally based NT Energies, a joint venture of Abu Dhabi’s NMDC Energy and France-based Technip Energies.
Masdar then sought proposals last year for engineering, procurement, construction, demolition (if needed for brownfield activities), pre-commissioning, commissioning, start-up, and two years of operations and maintenance (extendable up to 20 years) at the planned facility.
Contractors submitted bids by the end of the year, according to sources.
The project involved green hydrogen production using alkaline water electrolysis, with a total installed electrolyser capacity of 100MW.
The scope of work involved building electrolyser stacks and modules, hydrogen separation and compression units, associated utilities and storage systems, and electrical, instrumentation and control systems.
It also included tie-ins to pre-defined interface points, including (but not limited to):
- a grid power supply connection to the MOSF substation in Musaffah that exists within the Emsteel complex and is operated by Taqa Transmission
- a water supply connection to a nearby Taqa Distribution network
Supporting infrastructure included a substation, a motor control centre, and ancillary plant buildings and facilities.
Masdar’s planned 100MW electrolyser project at the Emsteel facility would have represented a step up from a previous pilot project by the two Abu Dhabi-owned companies.
The partners inaugurated a pilot green hydrogen plant at Emsteel’s manufacturing complex in Musaffah in October 2024. It incorporates a 2.1MW electrolyser and is designed to support the production of up to 5,000 tonnes of green steel a year.
This made Emsteel the only steelmaker in the Middle East to use green hydrogen to produce green steel on a pilot basis.
“Sustainability is central to Emsteel’s innovation, competitiveness and long-term growth. Today, approximately 89% of our steel business electricity consumption comes from clean sources, and our steel carbon emissions intensity is around 40% lower than the World Steel Association global average,” Michael Rion, chief commercial officer of Emirates Steel, part of Emsteel Group, told MEED in a recent interview.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18911651/main0611.jpg -
Oman invites bids for Musandam renewables study25 August 2026
Oman’s Nama Power & Water Procurement Company (PWP) has issued a request for proposals (RFP) for techno-economic consultancy services to assess the feasibility of renewable energy options in Musandam Governorate.
The study will examine solar photovoltaic (PV), wind and hybrid renewable energy configurations. It will also assess battery energy storage systems (bess) and other renewable energy and energy storage technologies.
The consultant will be required to determine which technologies are technically and economically justified for the governorate.
The bid submission deadline is 24 September.
The Musandam power system is served primarily by the 123MW Musandam independent power plant (IPP), which began operating in 2017. The governorate has historically relied on small diesel-fired units, but has been seeking to move away from diesel-fired power generation for several years.
Nama PWP has previously said it was exploring renewable energy options in Musandam to meet future additional capacity requirements.
Its latest seven-year statement, released in March, forecasts peak electricity demand in Musandam to rise from 91MW in 2024 to 130MW in 2031, an average annual increase of 5%. Average demand is forecast to rise from 52MW to 73MW over the same period.
The plan says demand growth is being driven by distribution-level load and projects aimed at boosting tourism, economic and commercial activity.
Separately, the utility recently invited bids for financial and commercial consultancy services covering three 1GW solar IPPs targeted for commercial operation by the second quarter of 2030.
The bid submissions deadline is 10 September.
The three projects covered by the financial and commercial consultancy tender are understood to also be part of the 4GW programme, for which a technical advisory tender was issued on 15 July.
Bidding for this tender closes on 26 August.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18983679/main.jpg -
US launches sanctions campaign against Iran25 August 2026
The US has launched a sweeping sanctions campaign against Iran and the entities that trade with it, imposing measures on almost 60 individuals, companies and vessels while expanding the reach of secondary sanctions across five sectors of the Iranian economy.
The campaign, named Operation Economic Outcast, was announced on 24 August by US treasury secretary Scott Bessent, who described it as an economic D-Day for Iran. He said Washington’s objective was to sever every economic lifeline sustaining the Iranian regime.
The treasury’s Office of Foreign Assets Control (Ofac) issued five sectoral sanctions determinations under Executive Order 13902, covering digital assets, technology, gold, aviation and shipping. The determinations allow Ofac to sanction any person operating in those sectors, regardless of location. Washington said Iran uses cryptocurrency for sanctions evasion, seeks advanced technology for its weapons programmes, uses gold to stabilise the rial, and relies on commercial aviation and shipping networks to move fighters, weapons and oil revenue.
The measures build on earlier determinations targeting Iran’s financial, petroleum and petrochemical sectors.
Ofac also sanctioned close to 60 entities, individuals and vessels across multiple jurisdictions, including UAE-based entities, over alleged involvement in nuclear and missile procurement, cyber operations and oil revenue networks. The designations named a network of brokers, companies and shadow fleet vessels operating across the UAE, Hong Kong, China, Singapore, Switzerland and other regions to transport Iranian oil and channel revenue to the Islamic Revolutionary Guard Corps.
Among those designated were shipping brokers and bunkering firms based in the UAE that Washington said facilitated Iranian oil shipments and provided services to sanctioned vessels. The treasury also identified several shadow fleet tankers as blocked property, saying they had moved millions of barrels of Iranian crude and petroleum products, mainly to China.
Separately, the treasury targeted a procurement network spanning the Middle East and East Asia that it said supported Iran’s acquisition of proliferation-sensitive equipment, along with a cyber group directed by Iran’s Ministry of Intelligence & Security.
Bessent said Washington was pressing governments to shut down Iran-related activity within defined timelines, warning that entities facilitating money laundering or sanctions evasion for Iran risked being cut off from the US financial system. He declined to name specific countries.
The campaign follows the UAE’s own move against Tehran. On 19 August, the UAE suspended all trade, commercial exchanges and financial transactions with Iran with immediate effect, citing regional escalation. The UAE has historically been one of Iran’s most significant trading partners, with much of the relationship built on re-export trade routed through Dubai.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18983152/main.jpg -
Kuwait tenders $3.3bn gas processing facility25 August 2026

State-owned Kuwait Gulf Oil Company (KGOC) has issued the tender for the development of an onshore gas plant next to the Al-Zour refinery, according to industry sources.
The project budget is estimated at $3.3bn, and the bid deadline is 29 December, with a meeting for contractors scheduled for 14 September.
The tender was issued on 23 August.
The proposed plant will have the capacity to process up to 632 million cubic feet a day of gas and 88.9 million barrels a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.
In February, MEED reported that at least seven companies had shown interest in participating in the tender.
Contractors that sent representatives to previous meetings to discuss the project include:
- Samsung E&A (South Korea)
- Larsen & Toubro (India)
- Tecnicas Reunidas (Spain)
- Saipem (Italy)
- Hyundai Engineering & Construction (South Korea)
- Hyundai Engineering Company (South Korea)
- JGC (Japan)
The tender process is using a fast-track model, which means that Kuwait’s Central Agency for Public Tenders (Capt) will not be involved in the tender process.
Capt typically reviews the technical and commercial evaluations of bids and verifies that the bidding process is competitive.
It is understood that not requiring Capt to approve this tender is expected to speed up the tender process.
Iran disputes ownership of the field, referring to it as Arash.
Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.
The Dorra field’s close proximity to Iran could make development difficult due to current security concerns.
The offshore elements of the wider Dorra field development project are expected to be especially difficult to protect from attacks from Iran.
Earlier this month, MEED revealed that Al-Khafji Joint Operations (KJO) had selected contractors for two major offshore packages under the Dorra field facilities development project.
KJO, which is jointly owned by Aramco subsidiary Aramco Gulf Operations Company and Kuwait Petroleum Corporation subsidiary KGOC, has divided the engineering, procurement and construction (EPC) scope for the Dorra gas production project into four packages: three offshore and one onshore.
US-based McDermott International has secured offshore package 2A, valued at about $1.5bn, according to sources.
A consortium of India’s Larsen & Toubro Energy Hydrocarbon (LTEH) and Italian contractor Saipem has secured package 2B, sources told MEED.
Estimated at about $3.7bn, package 2B is the largest of the three offshore EPC packages under the Dorra field facilities project.
MEED reported in March that the LTEH/Saipem consortium had emerged as the lowest bidder for offshore package 2B.
Contractors submitted bids for offshore packages 2A and 2B by the 9 March deadline, MEED previously reported. Bid validity was understood to expire on 15 August, prompting KJO to issue letters of intent to the selected contractors earlier this month, sources said.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18964461/main.png
