Risks remain for GCC railway project

28 August 2023

 

Register for MEED's guest programme 

When the GCC secretariat agreed to restart the GCC Railway Project in 2021, it set the tone for one of the region’s most ambitious transnational projects.

The endeavour aims to connect the six Gulf nations with a sprawling railway network that will be a game-changer for the region’s infrastructure. The potential to boost trade, connectivity and regional economic development is enormous. 

But risks and challenges also lie ahead, including cost overruns and technical risks related to the project design, engineering and complexity that must be assessed, managed and monitored to ensure the project’s successful delivery.

Political risks

Political factors play a significant role in the development and operation of the GCC railway. Given that the network will traverse multiple geographies, one of its biggest tests is manoeuvring through the regional political landscape.

First and foremost among political considerations is the level of cooperation and diplomatic relations between the member states. The railway’s seamless operation relies on harmonised regulations, standard operating procedures and open communication between nations, as well as geopolitical stability. 

In this respect, the Al-Alu agreement of 2021 is key, as it laid the strong foundations for a more robust mechanism to ensure better cooperation between the GCC countries.

“The Qatar blockade was a big challenge to manage and the GCC countries have seen the consequences of the situation,” Alexandre Busson (right), director of rail, Hill International, tells MEED.

“They realised that there was no benefit in it for the region. So the Al-Ula declaration is really important.”

But while the agreement mitigates the political risk related to the GCC railway project to some extent, the potential for geopolitical tensions or disputes between the involved states remains and could impede the project’s progress by delaying decisions, complicating negotiations and disrupting work.

The GCC countries' wide-ranging economic interests and priorities could also impact their commitment to the railway project. Member states will need to consider their existing investments in other forms of transportation infrastructure, such as ports and highways. Balancing these interests requires careful negotiations and alignment of economic visions.

PPP contracts are more complex to negotiate and manage. But it [will be] very interesting to see how it goes because a successful PPP project could lead to the opening up of the market
Alexandre Busson, Hill International

Financial risks

The enormity of the GCC Railway Project becomes apparent when considering the huge costs involved. Laying tracks spanning six countries and crossing diverse terrains and urban areas, building stations, installing signalling systems and ensuring the safety of the network demands billions of dollars’ worth of investment.

With the financial stability of GCC nations closely tied to the global oil market, fluctuations in oil prices could significantly impact the ability and political will of governments to allocate funds to the GCC Railway Project.

“When GCC countries budget for infrastructure projects, they are very conservative with regards to the oil price in their budget,” says Busson. “And in terms of projects financing, they realise [the need] to diversify the economy and not be too dependent on oil prices.” 

Nevertheless, economic diversification plans mean each GCC nation faces its own set of budget constraints and priorities. Regional governments must juggle allocating limited funds to sectors such as healthcare, education, defence and infrastructure. The GCC Railway Project’s financial demands could strain these budgets, potentially diverting resources away from critical sectors.

To bridge the financial gap, governments are likely to explore a combination of public financing and private investment. Public-private partnerships (PPPs) have attracted interest from large-scale infrastructure projects in the region and the GCC railway will be no different. Luring private investors, however, requires a stable and attractive investment environment, coupled with clear revenue-generation models and risk-sharing agreements.

“The PPP model is quite new in the GCC. Even more so in transport,” says Busson. “Those kinds of contracts are more complex to negotiate and manage. But it [will be] very interesting to see how it goes because a successful PPP project could lead to the opening up of the market.”

You need to look at the consortium members and say, do we have the right balance within that particular consortium to be able to manage this project
Christopher Harding, Hill International

Technical risks

The technical risks of rail systems running across international borders are well documented. Examples include the Tan-Zam railway between Tanzania and Zambia and the rail link connecting Spain and France, where the adoption of different gauges meant construction was fraught with technical difficulties when joining the networks to each other.

“Inaccurate or complex specifications sometimes lead to extra efforts [needing] to be put into the interface management and getting interface agreements between the contractors,” explains Christopher Harding (right), a senior project management professional currently working on the Cairo Metro project for US-based consultant Hill International.

“That leads to claims from contractors and hence may lead to cost overruns.”

The complexity of the GCC Railway Project raises the stakes when it comes to technical risks. Meticulous planning and implementation will be required to ensure seamless connectivity across deserts, mountains and coastal areas, while the need for bridges, tunnels and viaducts to overcome geographical obstacles demands robust engineering solutions. 

Addressing these engineering risks requires a comprehensive understanding of the local environment, as well as innovative and consistent engineering techniques.

“There needs to be a common policy on the control systems for each country and how they talk to each other,” says Harding.

The involvement of multiple contractors will bring contractor-related risks too. Coordination between these entities will be key, as delays in one segment could cascade through the entire network, causing misalignments and operational bottlenecks.

“You need to look at the consortium members and say, do we have the right balance within that particular consortium to be able to manage this project,” says Harding.

Another significant challenge will be maintaining uniform quality standards across the contractors working on the GCC Railway Project to prevent differing construction techniques, materials and safety practices from potentially compromising the railway’s overall integrity and efficiency. 

“The rules around aspects like recruitment localisation, In-country Value (ICV), In-Kingdom Total Value Add (IKTVA) and regional headquarters requirement could be a challenge for new companies,” adds Busson.

The establishment of the GCC Railway Authority to oversee the overall implementation of the project will go some way towards resolving the technical issues outlined here. The authority is tasked with ensuring common standards and specifications, and supervising the railway’s interoperability and regional integration.

For the project to succeed, the authority must develop robust risk management strategies, effective communication channels among contractors, stringent quality control measures and transparent procurement processes.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11099328/main.jpg
Yasir Iqbal
Related Articles
  • Abu Dhabi seeks firms for Mid Island Parkway PPP

    15 May 2026

     

    Register for MEED’s 14-day trial access 

    Modon Infrastructure, formerly known as Gridora, has invited firms to submit their registrations for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will be developed on a public-private partnership (PPP) basis.

    The request for qualifications (RFQ) is expected to be issued to interested parties soon.

    Modon Infrastructure will act as the lead developer with the majority of the equity in the project company. It will award the engineering, procurement, and construction contractor, the operations and maintenance providers, and the advisers.

    The second phase of the MIPP involves the construction of about 11 kilometres (km) of highways, including a mix of three-, four- and five-lane highways. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also covers the construction of three interchanges: the E20, E10 and Dumbbell interchanges on Al-Sammaliyyah Island.

    The project includes several major structures, such as the E20 interchange featuring cast-in-place box girder and void slab bridges, and the E10 interchange with cast-in-place box girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further key elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island, a tunnel between Al-Sammaliyyah Island and Bilrimaid Island, and a cut-and-cover (open) tunnel on Bilrimaid Island. The project is completed with another tunnel connecting Bilrimaid Island to Um-Yifeenah Island.

    Abu Dhabi awarded three packages for phase one of the MIPP in 2024. The contract for package 1A was awarded to a joint venture of Turkish contractor Dogus Construction and UAE firm Gulf Contractors. Package 1B was awarded to a joint venture of Yas Projects (Alpha Dhabi Holding) and China Railway International Group. Beijing-headquartered China Harbour Engineering Company and the UAE’s Agility Engineering & Contracting Company won the contract for package 1C.

    Phase one starts at the existing Saadiyat interchange, connecting the E12 to the MIPP, and ends at the recently constructed Um-Yifeenah highway. 

    It comprises a dual main road with a total length of 8km, including four traffic lanes in each direction, two interchanges, a tunnel and associated infrastructure works.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16858325/main.jpg
    Colin Foreman
  • Oman seeks adviser for gas-fired IPPs

    15 May 2026

    Oman’s Nama Power & Water Procurement Company (PWP) has issued a request for proposals for technical consultancy services for the development of new gas-fired independent power projects (IPPs) in the sultanate.

    The state offtaker said the projects will have a total capacity of up to 2,800MW.

    The bid submission deadline is 17 June.

    While Oman is accelerating investment in renewable energy and battery storage, gas-fired thermal generation is expected to remain a core part of the country’s power mix over the coming decade.

    The Misfah and Duqm combined-cycle gas turbine power plants are advancing towards construction following the appointment of China-headquartered Shandong Electric Power Construction No. 3 Company (Sepco 3) and South Korea’s Doosan Enerbility as contractors.

    According to Nama PWP’s 2025 annual report, the Duqm IPP will have a total capacity of 877MW, including 555MW of early power capacity, which is scheduled to commence in Q2 2028.

    The Misfah IPP will have a total capacity of 1,700MW, including 1,203MW of early power capacity, which is scheduled to commence in the same quarter.

    Nama PWP has also recently awarded new power-purchase agreements (PPAs) to three IPPs to extend the operating life of existing gas-fired power plants beyond the expiry of their current contracts.

    The new agreements for the 750MW Sohar 2 IPP and 750MW Barka 3 IPP will take effect on 1 April 2028 and run until 31 March 2043. The agreement for the 200MW Sur IPP will commence on 1 April 2029 and run until 31 March 2044.

    The awards form part of Nama PWP’s 2028-29 procurement programme. The programme aims to secure firm generation capacity from existing assets whose current PPAs are due to expire during that period.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16857037/main4750.jpg
    Mark Dowdall
  • Alghanim submits lowest offer for Kuwait oil refinery project

    15 May 2026

    Kuwait’s Alghanim International General Trading & Contracting has submitted the lowest bid for a contract to upgrade the country’s Mina Al-Ahmadi (MAA) refinery.

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC). The project scope covers upgrades to water transmission and storage infrastructure at the refinery.

    The contract will be delivered under an engineering, procurement and construction (EPC) model. The tender was issued in October 2025 with an initial bid deadline of 4 January 2026, which was later extended several times. The most recent rescheduling moved the deadline from 19 April to 10 May.

    Alghanim submitted a bid of KD37.0m ($120m), significantly lower than the other two bidders, both Kuwait-based: Heavy Engineering Industries & Shipbuilding Company (Heisco) at KD60.6m ($197m) and Gulf Spic General Trading & Contracting at KD63.9m ($207m).

    The project is expected to take two years to complete and will expand water storage capacity at the facility by extending existing tanks or constructing new ones. The contractor will also develop associated infrastructure and upgrade systems that transport desalinated water to the refinery, including pipelines and related equipment.

    In its 2024-25 annual report, KNPC said the project will help meet water demand for the facility’s refining and gas production units.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16852744/main.jpg
    Wil Crisp
  • Civil and piping work starts on Iraq field development

    15 May 2026

     

    Civil works and piping work have started for the project to develop a second central processing facility (CPF) at Iraq’s Ratawi oil and gas field, according to industry sources.

    The project is part of the $27bn Gas Growth Integrated Project (GGIP), which is being developed by TotalEnergies along with its partners Basra Oil Company (BOC) and Qatar Energy.

    Phase one of the GGIP is expected to be worth about $10bn.

    Work is progressing on the project despite logistical problems related to the regional conflict that broke out after the US and Israel attacked Iran on 28 February.

    While early works are ongoing, equipment needed for later stages of the project is being delayed as it was due to be transported to the project site using ships that would have travelled through the Strait of Hormuz.

    Shipping through the Strait is still severely disrupted due to the regional conflict.

    In September, Turkiye’s Enka signed a contract to develop the second CPF at Iraq’s Ratawi field as part of the second phase of the field’s development.

    Enka did not give a value for the contract, but it is believed to be worth more than $1bn.

    In November, US-based KBR was selected by Enka to provide detailed design services for the project.

    Enka’s contract covers the engineering, procurement, supply, construction and commissioning of the CPF for the project known as the Associated Gas Upstream Project Phase 2 (AGUP2).

    The aim of the AGUP2 project is to process oil and associated gas from the Ratawi oil field to increase production capacity to 210,000 barrels a day of oil and 154 million standard cubic feet a day of gas.

    GGIP masterplan

    The GGIP programme is being led by TotalEnergies, the operator, which holds a 45% stake.

    Basra Oil Company and QatarEnergy hold 30% and 25% stakes, respectively. The consortium formalised the investment agreement with the Iraqi government in September 2021.

    The four projects that comprise the GGIP are:

    • The Common Seawater Supply Project (CSSP)
    • The Ratawi gas processing complex
    • A 1GW solar power project for Iraq’s electricity ministry
    • A field development project at Ratawi, known as the Associated Gas Upstream Project (AGUP)

    The CSSP is designed to support oil production in Iraq’s southern oil and gas fields – mainly Zubair, Rumaila, Majnoon, West Qurna and Ratawi – by delivering treated seawater for injection, a method used to boost crude recovery rates and improve long-term reservoir performance.

    China Petroleum Engineering & Construction Corporation (CPECC) won a $1.61bn contract in May to execute EPC work for the gas processing complex at the Ratawi field development.

    CPECC’s project team based in its Dubai office is performing detailed engineering work on the project.

    In August last year, TotalEnergies awarded China Energy Engineering International Group the engineering, procurement and construction (EPC) contract for the 1GW solar project at the Ratawi field. A month later, QatarEnergy signed an agreement with TotalEnergies to acquire a 50% interest in the project.

    The 1GW Ratawi solar scheme will be developed in phases, with each phase coming online between 2025 and 2027. It will have the capacity to provide electricity to about 350,000 homes in Iraq’s Basra region.

    The project, consisting of 2 million bifacial solar panels mounted on single-axis trackers, will include the design, procurement, construction and commissioning of the photovoltaic power station site and 132kV booster station.

    Separately, in June, TotalEnergies awarded China Petroleum Pipeline Engineering an EPC contract worth $294m to build a pipeline as part of a package known as the Ratawi Gas Midstream Pipeline.

    Also, TotalEnergies awarded UK-based consultant Wood Group a pair of engineering framework agreements in April, worth a combined $11m, under the GGIP scheme.

    The agreements have a three-year term under which Wood will support TotalEnergies in advancing the AGUP.

    One of the aims of the AGUP is to debottleneck and upgrade existing facilities to increase production capacity to 120,000 b/d of oil on completion of the first phase, according to a statement by Wood.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16852654/main.png
    Wil Crisp
  • Abu Dhabi selects Yas Island site for $1.7bn Sphere venue

    14 May 2026

    Abu Dhabi’s Department of Culture & Tourism (DCT Abu Dhabi) and US-based Sphere Entertainment have selected Yas Island as the location for the $1.7bn Sphere Abu Dhabi project.

    The venue will be built on a plot between Yas Mall and SeaWorld Abu Dhabi, close to Yas Island’s theme parks and attractions. Construction is expected to be completed by the end of 2029. Dubai-listed Alec is understood to be the selected contractor and has been working on the project’s pre-construction phase.

    The project will be the first Sphere venue outside the US. It is expected to echo the scale of Sphere Las Vegas, with a capacity of up to 20,000 depending on configuration.

    DCT Abu Dhabi said it will coordinate enabling and infrastructure works with Abu Dhabi entities, including the Department of Municipalities & Transport and its Integrated Transport Centre, the Department of Energy, Taqa, Etihad Rail and Aldar. The scope includes road enhancements, site access and site-wide infrastructure integrated with surrounding Yas Island assets.

    Sphere Abu Dhabi is the latest addition to Abu Dhabi’s integrated tourism and destination-development pipeline on Yas Island, alongside major attractions and the Disney theme park resort that was announced in 2025.

    DCT and Sphere Entertainment finalised an agreement last year related to the construction, development and operation of the Sphere entertainment venue in Abu Dhabi. According to the agreement, Sphere Entertainment granted DCT the exclusive rights to build and operate the Sphere Abu Dhabi entertainment venue.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16837302/main.gif
    Colin Foreman