Risks remain for GCC railway project
28 August 2023

Register for MEED's guest programme
When the GCC secretariat agreed to restart the GCC Railway Project in 2021, it set the tone for one of the region’s most ambitious transnational projects.
The endeavour aims to connect the six Gulf nations with a sprawling railway network that will be a game-changer for the region’s infrastructure. The potential to boost trade, connectivity and regional economic development is enormous.
But risks and challenges also lie ahead, including cost overruns and technical risks related to the project design, engineering and complexity that must be assessed, managed and monitored to ensure the project’s successful delivery.
Political risks
Political factors play a significant role in the development and operation of the GCC railway. Given that the network will traverse multiple geographies, one of its biggest tests is manoeuvring through the regional political landscape.
First and foremost among political considerations is the level of cooperation and diplomatic relations between the member states. The railway’s seamless operation relies on harmonised regulations, standard operating procedures and open communication between nations, as well as geopolitical stability.
In this respect, the Al-Alu agreement of 2021 is key, as it laid the strong foundations for a more robust mechanism to ensure better cooperation between the GCC countries.
“The Qatar blockade was a big challenge to manage and the GCC countries have seen the consequences of the situation,” Alexandre Busson (right), director of rail, Hill International, tells MEED.
“They realised that there was no benefit in it for the region. So the Al-Ula declaration is really important.”
But while the agreement mitigates the political risk related to the GCC railway project to some extent, the potential for geopolitical tensions or disputes between the involved states remains and could impede the project’s progress by delaying decisions, complicating negotiations and disrupting work.
The GCC countries' wide-ranging economic interests and priorities could also impact their commitment to the railway project. Member states will need to consider their existing investments in other forms of transportation infrastructure, such as ports and highways. Balancing these interests requires careful negotiations and alignment of economic visions.
PPP contracts are more complex to negotiate and manage. But it [will be] very interesting to see how it goes because a successful PPP project could lead to the opening up of the market
Alexandre Busson, Hill International
Financial risks
The enormity of the GCC Railway Project becomes apparent when considering the huge costs involved. Laying tracks spanning six countries and crossing diverse terrains and urban areas, building stations, installing signalling systems and ensuring the safety of the network demands billions of dollars’ worth of investment.
With the financial stability of GCC nations closely tied to the global oil market, fluctuations in oil prices could significantly impact the ability and political will of governments to allocate funds to the GCC Railway Project.
“When GCC countries budget for infrastructure projects, they are very conservative with regards to the oil price in their budget,” says Busson. “And in terms of projects financing, they realise [the need] to diversify the economy and not be too dependent on oil prices.”
Nevertheless, economic diversification plans mean each GCC nation faces its own set of budget constraints and priorities. Regional governments must juggle allocating limited funds to sectors such as healthcare, education, defence and infrastructure. The GCC Railway Project’s financial demands could strain these budgets, potentially diverting resources away from critical sectors.
To bridge the financial gap, governments are likely to explore a combination of public financing and private investment. Public-private partnerships (PPPs) have attracted interest from large-scale infrastructure projects in the region and the GCC railway will be no different. Luring private investors, however, requires a stable and attractive investment environment, coupled with clear revenue-generation models and risk-sharing agreements.
“The PPP model is quite new in the GCC. Even more so in transport,” says Busson. “Those kinds of contracts are more complex to negotiate and manage. But it [will be] very interesting to see how it goes because a successful PPP project could lead to the opening up of the market.”
You need to look at the consortium members and say, do we have the right balance within that particular consortium to be able to manage this project
Christopher Harding, Hill International
Technical risks
The technical risks of rail systems running across international borders are well documented. Examples include the Tan-Zam railway between Tanzania and Zambia and the rail link connecting Spain and France, where the adoption of different gauges meant construction was fraught with technical difficulties when joining the networks to each other.
“Inaccurate or complex specifications sometimes lead to extra efforts [needing] to be put into the interface management and getting interface agreements between the contractors,” explains Christopher Harding (right), a senior project management professional currently working on the Cairo Metro project for US-based consultant Hill International.
“That leads to claims from contractors and hence may lead to cost overruns.”
The complexity of the GCC Railway Project raises the stakes when it comes to technical risks. Meticulous planning and implementation will be required to ensure seamless connectivity across deserts, mountains and coastal areas, while the need for bridges, tunnels and viaducts to overcome geographical obstacles demands robust engineering solutions.
Addressing these engineering risks requires a comprehensive understanding of the local environment, as well as innovative and consistent engineering techniques.
“There needs to be a common policy on the control systems for each country and how they talk to each other,” says Harding.
The involvement of multiple contractors will bring contractor-related risks too. Coordination between these entities will be key, as delays in one segment could cascade through the entire network, causing misalignments and operational bottlenecks.
“You need to look at the consortium members and say, do we have the right balance within that particular consortium to be able to manage this project,” says Harding.
Another significant challenge will be maintaining uniform quality standards across the contractors working on the GCC Railway Project to prevent differing construction techniques, materials and safety practices from potentially compromising the railway’s overall integrity and efficiency.
“The rules around aspects like recruitment localisation, In-country Value (ICV), In-Kingdom Total Value Add (IKTVA) and regional headquarters requirement could be a challenge for new companies,” adds Busson.
The establishment of the GCC Railway Authority to oversee the overall implementation of the project will go some way towards resolving the technical issues outlined here. The authority is tasked with ensuring common standards and specifications, and supervising the railway’s interoperability and regional integration.
For the project to succeed, the authority must develop robust risk management strategies, effective communication channels among contractors, stringent quality control measures and transparent procurement processes.
Exclusive from Meed
-
Kuwait halves drilling contractor pool22 September 2026
-
Abu Dhabi expects 45% emissions cut as electricity demand rises21 September 2026
-
Seven bid for Bahrain highway upgrade21 September 2026
-
Teams prepare bids for Oman PPP wastewater project21 September 2026
-
Oman reveals Sohar airport and Salalah Thumrait Road plans21 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait halves drilling contractor pool22 September 2026

State-owned upstream operator Kuwait Oil Company (KOC) has reduced the number of approved contractors for onshore drilling and shallow-well maintenance from 51 to 24.
Firms that are no longer qualified include major contractors such as Italy’s Saipem, Oklahoma-based Helmerich & Payne and Houston-based Patterson-UTI Energy.
The latest list still includes a wide range of Kuwaiti, regional and international companies, according to the latest update on its electronic system, published on 21 September 2026.
The full list of contractors that are now qualified to participate in tenders is:
- Burgan Company for Well Drilling, Trading & Maintenance (Kuwait)
- Kuwait Drilling Company (Kuwait)
- Sun Drilling Kuwait (Kuwait)
- TDL Kuwait for Oil Rigs & Natural Gas Extraction Activities, Services and Facilities (Kuwait)
- United Precision Drilling (Kuwait)
- Abraj Energy Services (Oman)
- Adnoc Drilling Company (UAE)
- Arabian Drilling Company (Saudi Arabia)
- Anton Oilfield Services (China)
- China Oilfield Services (China)
- Egyptian Drilling Company (Egypt)
- CNPC Bohai Drilling Engineering Company (China)
- Great Wall Drilling Company (China)
- John Energy (India)
- Kerui Oilfield Service (China)
- KCA Deutag Drilling (Germany)
- Mohammed Al-Barwani Petroleum Services (Oman)
- Nabors Drilling International (US)
- National Drilling & Services Company (Oman)
- Sea & Land Drilling Contractors (Oman)
- Sinopec International Petroleum Service Corporation (China)
- Karamay Jianye Energy (China)
- Modern Drilling Company (Egypt)
- Grey Wolf Drilling International (US)
An earlier list, which was published on 11 February, included 51 qualified companies.
The reduction in qualified drilling contractors follows KOC’s notice on 27 April this year, informing existing qualified contractors that they would need to reapply.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19863744/main3435.jpg -
Abu Dhabi expects 45% emissions cut as electricity demand rises21 September 2026
Register for MEED’s 14-day trial access
Abu Dhabi-based Emirates Water & Electricity Company (Ewec) expects carbon emissions from power and water production to fall by more than 45% by 2035 as the UAE expands renewable energy and reverse osmosis (RO) desalination.
The state offtaker's latest long-term system planning forecasts emissions will decline from about 42 million tonnes in 2019 to approximately 23 million tonnes in 2035.
The reduction is expected despite annual electricity demand that is forecast to rise by about 70% in 2026-33.
Ewec said the expansion of renewable energy and the shift towards RO desalination will be the principal drivers of the reduction.
The company plans to increase Abu Dhabi's solar capacity to 14GW by 2030 and more than 35GW by 2035. This will be supported by up to 15GW of battery storage capacity.
According to regional project tracker MEED Projects, Ewec has over $16bn-worth of power and water projects in the execution stage as part of its long-term procurement programme to increase renewable energy and low-carbon water production capacity.
This includes a 5.2GW Abu Dhabi solar and battery energy storage system (bess) round-the-clock renewable energy project, as well as three 1.5GW solar photovoltaic independent power projects (IPP): Al-Ajban, Al-Khazna and Al-Zarraf.
It also comprises the 1GW Al-Dhafra open-cycle gas turbine power plant, the 2.5GW Taweelah C combined-cycle gas turbine (CCGT) plant and a separate 400MW bess IPP.
As previously reported, it is expected that the developer's agreement for the 3.3GW Al-Nouf 1 CCGT IPP will be signed by the end of the year, while contractors are preparing to submit bids for a separate 2.6GW power plant project in Ajman.
The expansion of solar and battery storage is expected to reduce the system's reliance on gas-fired generation. However, gas-fired generation will continue to provide flexibility to support the system and balance intermittent renewable power output, according to Ewec.
The offtaker also expects RO desalination to account for more than 95% of total water production by 2035, with the procurement programme supporting the Abu Dhabi Department of Energy's Clean Energy Strategic Target 2035 for electricity production and the UAE Net Zero by 2050 Strategy.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19849749/main.jpg -
Seven bid for Bahrain highway upgrade21 September 2026
Register for MEED’s 14-day trial access
Seven contractors have submitted bids for the next phase of the Sheikh Jaber Al-Ahmed Al-Sabah Highway upgrade project.
According to results published by the Bahrain Tender Board, the firms that have submitted bids include:
- Nass Contracting Company
- Haji Hassan Group
- Almoayyed Contracting Group
- Mohammed Abdulmohsen Al-Kharafi & Sons
- Eastern Asphalt & Concrete Production
- Cebarco Bahrain
- Kingdom Asphalt
The contract scope includes expansion works on 2 kilometres of the highway. It consists of a four-lane dual carriageway with service roads on both sides.
The scope of works also includes excavation and backfill work, construction of stormwater drainage networks, a pumping station, installation of ducts for future utilities, upgraded street lighting, traffic signs and directional signage.
The project aims to improve traffic capacity, reduce congestion and enhance safety along the transport corridor linking Manama with industrial zones.
In April, MEED reported that Bahrain had approved a financing agreement framework to fund the construction of the next phase of the Sheikh Jaber Al-Ahmed Al-Sabah Highway upgrade.
In March last year, the Kuwait Fund for Arab Economic Development and the Bahraini government signed a KD10m ($32.4m) loan agreement to fund the second phase of the project, which is expected to cost about $404m.
This was followed in September 2025 by the appointment of US-based Parsons Corporation on a $1.5m contract to provide pre-contract engineering consultancy services for the project.
According to data from regional project tracker MEED Projects, construction of the first phase was completed in 2020.
A joint venture of local firm Nass Contracting and Kuwait’s KCC Engineering & Contracting undertook the main construction works.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19847073/main.png -
Teams prepare bids for Oman PPP wastewater project21 September 2026

At least three consortiums are preparing bids for a contract to develop and operate two major sewage treatment plants (STPs) in Oman.
The public-private partnership (PPP) project covers expanding two Muscat-based plants: the Al-Ansab STP (phase three) and the Al-Amerat STP (phase two). It will be delivered under a build-own-operate-transfer model.
At Al-Ansab, capacity will increase from 125,000 cubic metres a day (cm/d) to 207,000 cm/d. At Al-Amerat, capacity will rise from 18,000 cm/d to 54,000 cm/d.
According to sources, the bidders for the project include:
- Etihad Water & Electricity (UAE) / Metito (UAE)
- Lamar Holding (Bahrain) / Tawzea (Saudi Arabia)
- Civil Works Company (CWC, Saudi Arabia) / Suez (France)
The bid submission deadline is 5 January 2027.
State-owned Nama Water Services (NWS) issued a request for proposals for the project in July, as exclusively reported by MEED.
It is understood that Veolia (France), Miahona (Saudi Arabia) and Samsung E&A (South Korea) are also among the firms that prequalified for the project after the request for qualifications was issued last November.
The project scope includes the design, financing, construction, operation and maintenance of the new facilities, alongside the long-term operation of the existing facilities.
It has been over a decade since the Al-Ansab STP first entered full operation at a capacity of about 54,000 cm/d. In 2015, South Korea’s Doosan Ennerbility, formerly Doosan Heavy Industries, was awarded the main engineering, procurement, and construction contract for the phase two expansion, which increased the facility’s maximum flow capacity to 125,000 cm/d. This phase was completed in 2017.
Phase one of the Al-Amerat STP was awarded to a joint venture of France’s Degremont (Suez) and local contractor Al-Ansari Trading Enterprise under a design, build and short-term operation contract valued at about €50m ($58.1m). The plant was developed for Haya Water and commissioned in 2019 as part of the Muscat wastewater scheme.
Haya Water, the former wastewater utility, was later incorporated into NWS following a government restructuring programme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19794912/main.jpg -
Oman reveals Sohar airport and Salalah Thumrait Road plans21 September 2026
Oman is planning a new passenger terminal at Sohar Airport to expand regional air connectivity and strengthen the airport’s role in the national aviation network.
According to Said Bin Hamoud Al-Maawali, Oman’s minister of transport, communications and information technology, new routes are expected to be announced before the end of the year. Potential destinations include Dammam in Saudi Arabia, Gwadar in Pakistan, and southern Iran.
The planned terminal and additional routes will give residents of northern Oman more travel options.
Al-Maawali also provided an update on the long-delayed Salalah-Thumrait truck road, saying the project will be procured through a conventional tendering model rather than a public-private partnership (PPP).
In August 2023, Oman shortlisted five of eight prequalified teams to compete for the Salalah-Thumrait truck road project, which was set to be the sultanate’s first PPP road project.
The 67-kilometre road project is specially designed for heavy vehicles.
The road is a key link in Dhofar’s transport network, connecting Thumrait with Salalah and supporting movement between the interior and the governorate’s main urban and economic centre.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19794881/main.jpg