Ten projects that will shape Dubai’s future
5 September 2023

Register for MEED's guest programme
Dubai is back with major projects after several years of subdued activity following Expo 2020 and the Covid-19 pandemic.
Over the past year, plans have emerged for 10 projects across various sectors that will help shape the emirate’s development over the coming decade.
Many of these projects have been planned for years. After stalling during the low-oil-price era of 2015-20, positive economic tailwinds mean many of these schemes are now being revisited by their owners and relaunched.
| 1. Tower at Creek Harbour |
The most recent relaunch announcement came at the end of August, when Emaar Properties founder Mohammad Alabbar revealed plans to redesign and relaunch the Tower at Dubai Creek Harbour.
The design works are expected to be completed by the first quarter of 2024, and construction slated to begin in the second half of 2024.
Details of the redesigned tower have not been launched, but sources close to the project say it will be tall and feature high-end residential units. This reflects Dubai’s buoyant property market and will stand in sharp contrast to the original design that involved building a 1,000-metre-tall observation tower.
Construction on that project stalled in 2019 after work on the foundations was completed. Two bidders were competing for the estimated $5.5bn contract to build the tower. They were Beijing-based China State Construction Engineering Corporation and a joint venture of the local/Belgian Belhasa Six Construct and Tishman, which US-based Aecom owns.
Belhasa Six Construct completed the raft foundations for the tower in May 2018. France’s Soletanche Bachy finished the piling.
Spanish/Swiss architect and engineer Santiago Calatrava Valls was the main consultant on the project, with the local office of Aurecon, supported by the UK’s RMJM and Dubai-based DEC, acting as local engineer and architect of record. The project manager for the tower was US-based Parsons.
| 2. Dubai Metro Blue Line |
The Dubai Creek Harbour development in Ras al-Khor will connect to Dubai’s Metro network via the planned Blue Line, which will serve as an extension to the existing Red and Green lines.
Dubai’s Roads & Transport Authority (RTA) is preparing to issue tender documents for the Blue Line.
The Green Line extension will commence from its current terminus at Creek station in the Jadaf area. It will cross over to the Dubai Creek Harbour development and continue through Ras al-Khor, International City, Dubai Silicon Oasis and Academic City, before concluding near the Desert Rose project. The line will have 11 stations.
The Red Line extension will connect its existing terminus in Rashidiya to Mirdif City Centre and continue through Mirdif and Warqaa, before joining the Green Line extension in International City.
The project was put on hold during the Covid-19 pandemic and reactivated in early 2022, when UK-based Atkins and Grimshaw, US-based Parsons and France’s Egis restarted design work.
The last metro project to be completed in Dubai was Route 2020, which connected the Red Line to the Dubai Expo site. The AED10.6bn ($2.9bn) contract to design and build the line was awarded to a consortium of Alstom, Spain’s Acciona and Turkiye’s Gulermak.
| 3. Deep Tunnels Portfolio |
Another major infrastructure scheme is the Deep Tunnels Portfolio, which involves developing deep-gravity sewage tunnels and treatment plants across the emirate.
In August, Dubai Municipality began the process of appointing a project management consultant to oversee the scheme, which will be developed as a public-private partnership (PPP).
Two sets of deep tunnels will be constructed, terminating at two terminal pump stations at sewerage treatment plants (STPs) in Warsan and Jebel Ali. A conventional sewage and drainage collection system and STPs will be built in Hatta.
The scheme also includes recycled water distribution systems connected to the STPs.
Dubai’s Executive Council approved the project in June and said it would require an investment of about AED80bn ($22bn). It added that the project has been designed to serve the needs of the Dubai population for the next 100 years in alignment with the Dubai Economic Agenda D33 and Dubai Urban Plan 2040.
| 4. DWTC/Candy tower |
Dubai World Trade Centre (DWTC) and UK-based Candy Capital have formed a joint venture to develop three towers in Dubai’s One Central commercial district.
The mixed-use towers will have two branded residences, two hotels and office space. The construction work involves building three towers. The two taller towers will be connected by a sky bridge containing one of the hotels.
Dubai-based Killa Design has been appointed as the architect for the project.
Candy Capital is a privately held family office established by British entrepreneur and businessman Nick Candy. His best-known property development is One Hyde Park in London, which he developed with his brother Christian. It comprises 86 apartments and three retail units and is considered one of the wealthiest residences in the world.
| 5. Al-Maktoum International airport |
Dubai plans to restart the emirate’s largest construction project, the AED120bn ($33bn) expansion of Al-Maktoum International airport, also known as Dubai World Central (DWC).
The expansion was officially launched in 2014. It involves building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year. An initial phase, which was due to be completed in 2030, aims to take the airport’s capacity to 130 million passengers a year.
Altogether, the development will cover an area of 56 square kilometres.
Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.
Firms were competing for the estimated $2.7bn substructure contract for Concourse 1 and the West Terminal building – the largest contract tendered for the project.
The contract covers the delivery of more than 1.7 million square metres of connected basement footprint, housing the people-mover tunnels, baggage handling systems, ground services road network and other back-of-house technical and support facilities.
| 6. Palm Jebel Ali |
Dubai released details of the new masterplan for Palm Jebel Ali, an artificial island located south of Jebel Ali Freezone, in June.
Double the size of Palm Jumeirah, Palm Jebel Ali will have 110 kilometres of shoreline and extensive green spaces. The development will feature over 80 hotels and resorts and a diverse range of entertainment and leisure facilities.
It includes seven connected islands, catering to approximately 35,000 families. The development also emphasises sustainability, with 30 per cent of public facilities powered by renewable energy.
MEED reported in January that local developer Nakheel had approached contractors to complete the reclamation works for Palm Jebel Ali.
As with Palm Jumeirah, it is estimated that it could take around 20 years for Palm Jebel Ali to reach its full development potential. Nakheel has previously secured AED17bn ($4.6bn) in funding to expedite the development of various projects, including the Dubai Islands and other waterfront schemes.
The upcoming dredging contract for Palm Jebel Ali is anticipated to involve 5-6 million cubic metres of material, contributing to the completion of the man-made offshore island.
While reclamation work for Palm Jebel Ali is mostly finished, the project was put on hold in 2009. Nakheel had made some progress with infrastructure development, including the construction of bridges on the island by Samsung C+T.
| 7. The Oasis by Emaar |
Another major masterplanned development was launched by Emaar Properties in June. The $20bn Oasis by Emaar covers a total land area of more than 9.4 million square metres, close to Dubai Investments Park. The project involves building over 7,000 residential units along with water canals, lakes and parks. It will also include the development of a 150,000 sq m retail area.
| 8. The Island |
Another project that has been restarted in recent years is The Island, which Wasl is developing.
Located off the coast of Umm Suqeim, near the Jumeirah public beach, it is expected to feature 1,400 hotel rooms and apartments, in addition to retail, food and beverage and entertainment options. The 10.5-hectare island will include properties featuring the MGM, Bellagio and Aria hotel brands.
The developer is close to appointing a contractor to build the development after bids were submitted earlier this year.
Tender documents for the contract were previously issued in 2020, when the project was being delivered with a consultancy team led by South Africa’s Mirage.
Germany’s Kling Consult is now the project manager.
| 9. Al-Habtoor Tower |
The $1bn Al-Habtoor Tower project is located at Al-Habtoor City, next to Dubai Water Canal, on a 7,500 sq m plot. The tower, which the developer describes as one of the largest buildings in the world, will have three basement levels, a seven-storey podium and 73 floors of residences. The built-up area will be 350,000 sq m.
Its construction is technically challenging because the tower will be built above an existing parking basement that serves the already completed buildings at Al-Habtoor City.
Al-Habtoor had the option of demolishing the basement. Instead, it decided to employ a top-down approach to the construction that involves piling down through the basement, while at the same time starting construction above ground.
The top-down approach is expected to reduce the construction time by about one year, meaning the tower will be completed in 1,000 days or roughly three years.
China Railway 18th Bureau Group was appointed as the main contractor in May.
| 10. Dubai Pearl |
After two aborted attempts, development is expected to start again at the Dubai Pearl site, located north of Dubai Media City close to the Palm Jumeirah.
The structures erected for the previous project have been demolished this year. Dubai Holding, which now owns the land, has held a design competition and is in the final stages of selecting the winning architect.
Local project management firm North 25 is overseeing the design competition.
Exclusive from Meed
-
Kuwait selects firms for power works at housing projects20 October 2026
-
Taqa moves forward with Mirfa-Liwa scheme20 October 2026
-
-
Lowest bidder emerges for Kuwait Airport Terminal 2 operations19 October 2026
-
Dubai tenders Al-Maktoum-Dubai South drainage scheme19 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait selects firms for power works at housing projects20 October 2026

Kuwait’s Public Authority for Housing Welfare (PAHW) has appointed contractors for works covering the supply and installation of 132kV underground cables at South Sabah Al-Ahmad Residential City.
The contracts relate to engineering, procurement and construction (EPC) packages for works for 28 main 132/11kV substations across four phases.
According to sources, Egypt’s Elsewedy Cables has won contracts for phases 1 and 3, while China’s TBEA Shandong Luneng Taishan Cable Company has won contracts for phases 2 and 4 of the development.
In April, MEED reported that PAHW had received at least five bids for each of the first two packages, with Elsewedy and TBEA offering $44m and $40.5m, respectively.
The first contract (phase 1) covers seven substations in zones N9, N7 and N5. The second contract (phase 2) covers seven substations in zones N10 and N5.
PAHW issued two further 132kV underground cable tenders for the South Sabah Al-Ahmad residential development at the end of May, as reported by MEED.
This included a contract (phase 3) covering the supply, extension and maintenance of 132kV underground cables linked to seven substations serving the N5, N6, N8 and N10 districts. Egytech Cables, a subsidiary of Elsewedy, submitted an offer of $39.95m, the lowest of four bids.
The other contract (phase 4) covers the supply, extension and maintenance of 132kV underground cables feeding eight main transformer substations serving the N1, N6 and N11 districts.
MEED reported in July that TBEA had submitted an offer of $44.06m for the contract.
South Saad Al-Abdullah
Separately, PAHW has appointed contractors for power transmission works at the South Saad Al-Abdullah residential development.
The local firm Sayed Hamid Behbehani & Sons has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the development’s third phase.
Another local firm, Al-Ahleia Switchgear, has won a contract to supply, install and maintain 10 main 132/11kV transformer substations for the project’s fourth phase.
As reported in August, the contractors submitted bids of $104.2m and $103.3m, respectively.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20761431/main.jpg -
Taqa moves forward with Mirfa-Liwa scheme20 October 2026

Taqa Transmission and Taqa Distribution are advancing a major water transmission and distribution scheme serving Mirfa, Madinat Zayed and Liwa in Abu Dhabi, sources told MEED.
The project, originally estimated to cost $775m, has been in procurement for several years. According to sources, a request for proposals has been issued, with bids due on 5 January 2027.
The initial submission deadline was 11 November, before it was extended.
The project was previously tendered in December 2024, with contractors submitting bids for transmission and distribution packages in January 2025. As of August, the bids were still under evaluation. It is unclear whether the latest tender represents a revised procurement process for the same scheme.
The project comprises a water transmission system from Mirfa, alongside distribution networks serving farms and settlements in the western region.
According to details seen by MEED, the latest scope includes a pumping station at Mirfa with a capacity of 128 million imperial gallons a day, about 125 kilometres of transmission pipelines to Muzairah, with branches to Madinat Zayed and Liwa Summit, and storage tanks at the three locations.
The distribution network is divided into four geographic clusters covering Liwa East, Liwa West, Madinat Zayed and Seih Al-Kheir. The works include associated pipelines, pumping stations and storage facilities.
The earlier procurement was structured as an engineering, procurement and construction scheme, divided between transmission and distribution works.
As MEED understands, the latest tender is being pursued under a design, build and operate model, which extends the contractor’s responsibilities to operating the infrastructure after construction.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20758109/main2934.jpg -
Contractors prepare prices for Adnoc Onshore field facilities project20 October 2026

Contractors are preparing commercial bids for Adnoc Onshore’s project to build on-plot and off-plot facilities at the Rumaitha and Shanayel fields in Abu Dhabi’s North East Bab oil field cluster.
The project will enhance and sustain crude output at Rumaitha and Shanayel at 45,000 barrels a day (b/d), supporting Adnoc’s Accelerated Integrated Programme 5 (AiP5) drive to lift capacity to 5 million b/d by 2027.
Adnoc Onshore issued the main tender for engineering, procurement and construction (EPC) works on 19 June. Contractors submitted technical bids by 5 August, sources told MEED.
The on-plot works include adding a crude processing train, produced water treatment and reinjection systems, surface water pumps, and multi-stage gas compression and dehydration units. Works also include utilities, safety and control systems, modifications to existing Phase 1 units and 220kV power infrastructure.
The off-plot scope includes installing and tying in new gas-lifted producer and water-injection wells, as well as building and expanding wellhead clusters. Contractors will also lay crude-gathering, water-injection and gas-export pipelines connecting to the Adnoc Gas network and extend 33kV overhead power lines across the fields.
The tender follows Adnoc Onshore’s shift in strategy for the wider North East Bab development – comprising the Al-Nouf, Rumaitha and Shanayel fields – after scrapping an earlier engineering, procurement and construction management (EPCm) approach. MEED reported in December that the operator had cancelled an off-plot EPCm contract awarded to China Petroleum Engineering & Construction Corporation (CPECC) in October 2024. Adnoc later cancelled a separate on-plot EPCm tender that it received bids for in the second quarter of 2025.
In addition to the North East cluster, Adnoc Onshore continues to make progress on EPC works for another similar project to build off-plot facilities at the South East cluster of oil fields in Abu Dhabi, which is also integral to Adnoc Group’s AiP5 campaign.
The South East cluster comprises the Asab, Mender, Qusahwira, Sahil and Shah fields and accounts for approximately a third of Adnoc Onshore’s oil production capacity.
MEED previously reported that Adnoc Onshore awarded CPECC the EPC works for the South East off-plot facilities project, with the contract value estimated at around $1.2bn.
CPECC is also performing EPC works on the South East on-plot facilities project in a consortium with Greece-headquartered Archirodon. Adnoc Onshore awarded an estimated $1.5bn contract for that project to the consortium in December 2024, with EPC works scheduled for completion in 2027.
ALSO READ: Adnoc Onshore seeks bids for Bu Hasa field EOR project
https://image.digitalinsightresearch.in/uploads/NewsArticle/20757699/main.jpeg -
Lowest bidder emerges for Kuwait Airport Terminal 2 operations19 October 2026

Ireland’s DAA International has emerged as the lowest bidder for the contract to operate, manage and maintain the new passenger Terminal 2 (T2) at Kuwait International airport, submitting an offer of KD419m ($1.35bn).
Official price-opening records released by Kuwait’s Central Agency for Public Tenders on behalf of the Directorate General of Civil Aviation show three international airport operators submitted commercial bids for the tender.
DAA International’s proposal undercut its nearest rival by about 45%. Turkiye’s TAV Airports Holding submitted the second-lowest offer at KD764.15m ($2.46bn), while South Korea’s Incheon International Airport Corporation bid KD959.48m ($3.1bn).
All three proposals were marked as approved in the tender committee’s price disclosure.
The contract entails the operation, management and improvement of training, maintenance and development services across Terminal 2 and its associated aircraft parking aprons.
The remit also includes corporate management of centralised operation and maintenance across the broader Kuwait International airport model, centralising operational procedures, systems integration and service delivery across the aviation hub.
Technical documents indicate the winning operator will oversee facility management, terminal operational readiness, passenger processing systems, apron operations and staff development programmes before and after the complex’s commercial launch.
MEED reported in June 2023 that six airport operators had initially been invited to bid for the Terminal 2 operating concession.
Terminal 2 is the centrepiece of Kuwait International airport’s multibillion-dollar expansion, aimed at boosting total handling capacity to 25 million passengers a year.
Turkish contractor Limak Insaat is executing the main terminal building under an estimated $4.34bn contract awarded in 2016.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20747061/main.png -
Dubai tenders Al-Maktoum-Dubai South drainage scheme19 October 2026
Dubai Municipality has invited contractors to submit bids by 5 November for the construction of a stormwater drainage system connecting Al-Maktoum Airport and Dubai South
The project, designated TF-06-C2, involves approximately 20 kilometres of pipelines with diameters ranging from 400mm to 3,000mm. The works will use deep trenchless construction and conventional open-cut methods.
The scheme is one of four projects, for which a project management consultancy (PMC) tender was issued earlier this month.
The tender for TF-06-S1 Supervision of Stormwater Drainage System Projects – Package 4 was issued on 6 October.
The consultancy covers the following projects:
- TF-06-C1: Construction of a stormwater pond connecting Al-Maktoum Airport and Dubai South
- TF-06-C2: Construction of a stormwater drainage system connecting Al-Maktoum Airport and Dubai South
- TF-07-C1: Construction of a stormwater drainage system on Sheikh Zayed Bin Hamdan Road connecting developers
- TF-24-C1: Connecting developers’ areas to the stormwater networks in Dubailand
The projects are part of Dubai Municipality’s wider Tasreef programme, intended to increase Dubai’s rainwater drainage capacity by 700% by 2033 and provide capacity for the emirate’s needs for the next 100 years.
Investment in the UAE water sector has been dominated by stormwater drainage and network resilience schemes this year, as Dubai Municipality advances procurement under its AED30bn ($8.1bn) Tasreef programme.
TF-07-C1
As previously reported, contractors are preparing to submit bids on 22 October for the main construction contract for TF-07-C1.
The project covers more than 100 million square metres between Sheikh Mohammed Bin Zayed Road and Emirates Road, and from Expo Road to Dubailand.
It will provide stormwater infrastructure and service connections for more than 20 private developers and Al-Yalayis 5, as well as supporting major roads in the Jebel Ali area. The construction scope includes a major gravity drainage system with pipeline diameters of up to 3,000mm.
TF-24-C1
Bids for TF-24-C1 were submitted on 1 October, with Nael Construction & Contracting, Al-Nasr Contracting Company and Al-Kharafi & Sons understood to be among the bidders.
The project will connect developers’ areas in Dubailand to the stormwater network. It includes 18km of stormwater drainage pipelines with diameters of up to 1,800mm and 3.5km of gravity sewer pipelines with diameters of up to 1,000mm.
As MEED understands, the main contract tender for TF-06-C1 has yet to be released.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20746611/main.jpg