Ten projects that will shape Dubai’s future

5 September 2023

 

Register for MEED's guest programme 

Dubai is back with major projects after several years of subdued activity following Expo 2020 and the Covid-19 pandemic.

Over the past year, plans have emerged for 10 projects across various sectors that will help shape the emirate’s development over the coming decade. 

Many of these projects have been planned for years. After stalling during the low-oil-price era of 2015-20, positive economic tailwinds mean many of these schemes are now being revisited by their owners and relaunched.

1. Tower at Creek Harbour

The most recent relaunch announcement came at the end of August, when Emaar Properties founder Mohammad Alabbar revealed plans to redesign and relaunch the Tower at Dubai Creek Harbour.

The design works are expected to be completed by the first quarter of 2024, and construction slated to begin in the second half of 2024.

Details of the redesigned tower have not been launched, but sources close to the project say it will be tall and feature high-end residential units. This reflects Dubai’s buoyant property market and will stand in sharp contrast to the original design that involved building a 1,000-metre-tall observation tower.

Construction on that project stalled in 2019 after work on the foundations was completed. Two bidders were competing for the estimated $5.5bn contract to build the tower. They were Beijing-based China State Construction Engineering Corporation and a joint venture of the local/Belgian Belhasa Six Construct and Tishman, which US-based Aecom owns.

Belhasa Six Construct completed the raft foundations for the tower in May 2018. France’s Soletanche Bachy finished the piling.

Spanish/Swiss architect and engineer Santiago Calatrava Valls was the main consultant on the project, with the local office of Aurecon, supported by the UK’s RMJM and Dubai-based DEC, acting as local engineer and architect of record. The project manager for the tower was US-based Parsons.

2. Dubai Metro Blue Line

The Dubai Creek Harbour development in Ras al-Khor will connect to Dubai’s Metro network via the planned Blue Line, which will serve as an extension to the existing Red and Green lines.

Dubai’s Roads & Transport Authority (RTA) is preparing to issue tender documents for the Blue Line.

The Green Line extension will commence from its current terminus at Creek station in the Jadaf area. It will cross over to the Dubai Creek Harbour development and continue through Ras al-Khor, International City, Dubai Silicon Oasis and Academic City, before concluding near the Desert Rose project. The line will have 11 stations.

The Red Line extension will connect its existing terminus in Rashidiya to Mirdif City Centre and continue through Mirdif and Warqaa, before joining the Green Line extension in International City.

The project was put on hold during the Covid-19 pandemic and reactivated in early 2022, when UK-based Atkins and Grimshaw, US-based Parsons and France’s Egis restarted design work.

The last metro project to be completed in Dubai was Route 2020, which connected the Red Line to the Dubai Expo site. The AED10.6bn ($2.9bn) contract to design and build the line was awarded to a consortium of Alstom, Spain’s Acciona and Turkiye’s Gulermak.

3. Deep Tunnels Portfolio

Another major infrastructure scheme is the Deep Tunnels Portfolio, which involves developing deep-gravity sewage tunnels and treatment plants across the emirate.

In August, Dubai Municipality began the process of appointing a project management consultant to oversee the scheme, which will be developed as a public-private partnership (PPP).

Two sets of deep tunnels will be constructed, terminating at two terminal pump stations at sewerage treatment plants (STPs) in Warsan and Jebel Ali. A conventional sewage and drainage collection system and STPs will be built in Hatta.

The scheme also includes recycled water distribution systems connected to the STPs.

Dubai’s Executive Council approved the project in June and said it would require an investment of about AED80bn ($22bn). It added that the project has been designed to serve the needs of the Dubai population for the next 100 years in alignment with the Dubai Economic Agenda D33 and Dubai Urban Plan 2040.

4. DWTC/Candy tower

Dubai World Trade Centre (DWTC) and UK-based Candy Capital have formed a joint venture to develop three towers in Dubai’s One Central commercial district.

The mixed-use towers will have two branded residences, two hotels and office space. The construction work involves building three towers. The two taller towers will be connected by a sky bridge containing one of the hotels.

Dubai-based Killa Design has been appointed as the architect for the project.

Candy Capital is a privately held family office established by British entrepreneur and businessman Nick Candy. His best-known property development is One Hyde Park in London, which he developed with his brother Christian. It comprises 86 apartments and three retail units and is considered one of the wealthiest residences in the world.

5. Al-Maktoum International airport

Dubai plans to restart the emirate’s largest construction project, the AED120bn ($33bn) expansion of Al-Maktoum International airport, also known as Dubai World Central (DWC). 

The expansion was officially launched in 2014. It involves building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year. An initial phase, which was due to be completed in 2030, aims to take the airport’s capacity to 130 million passengers a year.

Altogether, the development will cover an area of 56 square kilometres.

Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.

Firms were competing for the estimated $2.7bn substructure contract for Concourse 1 and the West Terminal building – the largest contract tendered for the project.

The contract covers the delivery of more than 1.7 million square metres of connected basement footprint, housing the people-mover tunnels, baggage handling systems, ground services road network and other back-of-house technical and support facilities.

6. Palm Jebel Ali

Dubai released details of the new masterplan for Palm Jebel Ali, an artificial island located south of Jebel Ali Freezone, in June.

Double the size of Palm Jumeirah, Palm Jebel Ali will have 110 kilometres of shoreline and extensive green spaces. The development will feature over 80 hotels and resorts and a diverse range of entertainment and leisure facilities.

It includes seven connected islands, catering to approximately 35,000 families. The development also emphasises sustainability, with 30 per cent of public facilities powered by renewable energy.

MEED reported in January that local developer Nakheel had approached contractors to complete the reclamation works for Palm Jebel Ali.

As with Palm Jumeirah, it is estimated that it could take around 20 years for Palm Jebel Ali to reach its full development potential. Nakheel has previously secured AED17bn ($4.6bn) in funding to expedite the development of various projects, including the Dubai Islands and other waterfront schemes.

The upcoming dredging contract for Palm Jebel Ali is anticipated to involve 5-6 million cubic metres of material, contributing to the completion of the man-made offshore island.

While reclamation work for Palm Jebel Ali is mostly finished, the project was put on hold in 2009. Nakheel had made some progress with infrastructure development, including the construction of bridges on the island by Samsung C+T.

7. The Oasis by Emaar

Another major masterplanned development was launched by Emaar Properties in June. The $20bn Oasis by Emaar covers a total land area of more than 9.4 million square metres, close to Dubai Investments Park. The project involves building over 7,000 residential units along with water canals, lakes and parks. It will also include the development of a 150,000 sq m retail area.

8. The Island

Another project that has been restarted in recent years is The Island, which Wasl is developing.

Located off the coast of Umm Suqeim, near the Jumeirah public beach, it is expected to feature 1,400 hotel rooms and apartments, in addition to retail, food and beverage and entertainment options. The 10.5-hectare island will include properties featuring the MGM, Bellagio and Aria hotel brands.

The developer is close to appointing a contractor to build the development after bids were submitted earlier this year.

Tender documents for the contract were previously issued in 2020, when the project was being delivered with a consultancy team led by South Africa’s Mirage.

Germany’s Kling Consult is now the project manager.

9. Al-Habtoor Tower

The $1bn Al-Habtoor Tower project is located at Al-Habtoor City, next to Dubai Water Canal, on a 7,500 sq m plot. The tower, which the developer describes as one of the largest buildings in the world, will have three basement levels, a seven-storey podium and 73 floors of residences. The built-up area will be 350,000 sq m.

Its construction is technically challenging because the tower will be built above an existing parking basement that serves the already completed buildings at Al-Habtoor City.

Al-Habtoor had the option of demolishing the basement. Instead, it decided to employ a top-down approach to the construction that involves piling down through the basement, while at the same time starting construction above ground.

The top-down approach is expected to reduce the construction time by about one year, meaning the tower will be completed in 1,000 days or roughly three years.

China Railway 18th Bureau Group was appointed as the main contractor in May.

10. Dubai Pearl

After two aborted attempts, development is expected to start again at the Dubai Pearl site, located north of Dubai Media City close to the Palm Jumeirah.

The structures erected for the previous project have been demolished this year. Dubai Holding, which now owns the land, has held a design competition and is in the final stages of selecting the winning architect.

Local project management firm North 25 is overseeing the design competition.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11121967/main.gif
Colin Foreman
Related Articles
  • Borouge puts butene-1 expansion project on hold

    16 November 2026

     

    Abu Dhabi petrochemicals producer Borouge, now part of Austria-headquartered Borouge International, is said to have put on hold a project to increase butene-1 production from the olefins conversion unit (OCU) at its Borouge 2 facility in Ruwais Industrial City.

    Under the proposed project, Borouge planned to produce 60,000 tonnes a year (t/y) of butene-1 from the existing fractionator column while limiting propylene production from the OCU to 500,000 t/y.

    The company intended to achieve this by adding co-monomer production technology and selective hydrogenation units, while retaining the capability to run the unit at its original design capacity of 752,000 t/y of propylene and 39,000 t/y of butene-1. The scope also entailed expanding butene-1 storage capacity by converting existing N1 mixed-butane spheres into dedicated butene-1 units.

    According to sources, Borouge informed contractors in the weeks after receiving bids that it had decided to shelve the tender.

    Contractors submitted technical bids for the engineering, procurement and construction (EPC) package by 1 September 2025, following several extensions to the original 23 June deadline. Borouge had initially released an advanced tender notice in May last year, followed by the main EPC tender on 4 June, and hosted a site visit for bidders on 25 June.

    Contractors understood to have submitted bids include:

    • Galfar Emirates (UAE subsidiary of Oman’s Galfar Engineering & Construction)
    • Target Engineering Construction (UAE)

    US-based Lummus Technology was previously awarded the contract to provide the process design package for the new co-monomer production unit as the OCU licensor. Lummus sub-contracted the extended process design package and basic engineering works to South Korea’s Samsung E&A. Borouge had targeted an EPC contract award in the first quarter of 2026.

    Butene-1 is a colourless gas primarily used as a co-monomer in the production of high-grade polyethylenes and poly(1-butene), serving end markets such as specialty films, bags and food packaging.

    ALSO READ: Borouge prepares to tender construction works for ethane cracker expansion

    Borouge International was formed through the combination of Adnoc Group and OMV’s shareholdings in Borouge and Austria-based Borealis, alongside the acquisition of Canada-based Nova Chemicals. In July, Adnoc announced it would transfer its holding in Borouge International to its global investment arm, XRG.

    Borouge began operations in 2001 with 450,000 t/y of polyethylene capacity. The Borouge 2 and Borouge 3 expansions raised overall capacity to 2 million t/y in 2010 and 4.5 million t/y in 2014, respectively. Once the Borouge 4 expansion is commissioned, total production capacity will increase from 5 million t/y to 6.4 million t/y, creating the world’s largest single-site polyolefins facility.

    Borouge 4 will add two polyethylene units with a combined capacity of 1.4 million t/y (700,000 t/y each) based on Borealis’s third-generation Borstar technology, supplied by a 1.5 million t/y ethane cracker and associated derivative units.

    ALSO READ: Borouge restores Ruwais complex after Iranian attacks
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21443754/main.jpg
    Indrajit Sen
  • Contractor wins Saudi Energy substation deal

    16 November 2026

     

    Local firm Alfanar Projects has signed a contract with Saudi Energy, formerly Saudi Electricity Company, to build a 115/13.8kV substation in Al-Aqiq, Al-Bahah province, a source confirmed to MEED.

    The station will receive electricity at 115kV and step it down to 13.8kV for local distribution. The scope of work includes site preparation, civil works, substation buildings and foundations, and the supply and installation of power transformers and associated electrical equipment.

    Seventeen firms submitted bids for the project in May. The bidders included:

    • Al-Babtain Contracting 
    • Al-Gihaz Holding 
    • Al-Haider Company
    • Alfanar Projects 
    • Cepco 
    • Energy & Infrastructure Company (Eico)
    • Expertise Contracting 
    • Haif Company 
    • JAL International 
    • Maetel Saudi Arabia Construction Company 
    • Mohammed Al-Ojaimi Group 
    • Nesma Infrastructure & Technology
    • Nour Energy Company 
    • PA Cost International 
    • Sama Energy 
    • Saudi Projects & Supplies Company 
    • Tareg Al-Jaafari Contracting Establishment 

    According to regional project tracker MEED Projects, AlFanar Projects had won up to eight awards for substation projects this year, prior to the Al-Aqiq award.

    The largest is a contract worth more than SR122m ($32.5m) to construct a 132/13.8kV substation for the Expo 2030 Riyadh site.

    The firm was one of four contractors selected by Saudi Energy to deliver electricity infrastructure for the site, MEED reported in August.

    Recent contracts include the 380kV Tumair PV substation (#9127), the Busita-C 132/33kV substation, the 132/13.8kV substation north of Al-Kharj (#8721) and the Al-Sahafa 132/13.8kV new substation (#8316).

    Saudi Energy has tendered several other 380kV substations and associated transmission lines this year, including projects serving planned solar and wind developments in the kingdom’s central, western and southern regions.

    Earlier, in November, MEED exclusively reported that China’s TBEA Shandong Luneng Taishan Cable Company (TBEA) and Egypt’s Elsewedy had submitted the lowest bids for two substation projects in Riyadh Province, estimated to cost a combined $100m.

    The tenders for the Thadeq PV and Qiddiya 2 bulk supply points were issued earlier this year, with bids submitted in August and November, respectively.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21443095/main.jpg
    Mark Dowdall
  • WEBINAR: End-of-Year Mena Market Review

    13 November 2026

    Webinar: The big questions shaping the Gulf market. You decide what gets debated.
    Tuesday 24 November 2026  | 11:00 AM GST  |  Register now


    What makes this session particularly interesting is that the audience gets to decide the agenda. Registrants can vote for the topics they’d like Ed and Colin to debate, with the most popular questions forming the final shortlist for the live session.

    Topics in the ballot:

    • Is the Gulf trying to build too much, too quickly?
    • Saudi Arabia or the UAE: where would you place your next big bet?
    • Are gigaprojects the best use of public money?
    • Who is really responsible when projects go wrong?
    • Should the lowest-price tender become a thing of the past?
    • Can private capital take over from the government in financing infrastructure and diversification?
    • Is the Gulf’s AI and data centre boom a smart bet or the next overbuilding risk?
    • Should the Gulf double down on hydrocarbons to fund diversification?
    • Is localisation strengthening the economy or making delivery harder?
    • Are Gulf countries building complementary economies or competing for the same customers?

    The session will also feature live audience polling and Q&A, giving attendees an opportunity to share their views.

    Hosted by: 

    Edward James, head of content and analysis at MEED

    A well-known and respected thought leader in Mena affairs, Edward James has been with MEED for more than 19 years, working as a researcher, consultant and content director. Today, he heads up all content and research produced by the MEED group. His specific areas of expertise are construction, hydrocarbons, power and water, and the petrochemicals market. He is considered one of the world’s foremost experts on the Mena projects market. He is a regular guest commentator on Middle East issues for news channels such as the BBC, CNN and ABC News and is a regular speaker at events in the region. 


    Colin Foreman, editor of MEED 

    Colin Foreman is editor and a specialist construction journalist for news and analysis on MEED.com and the MEED Business Review magazine. He has been reporting on the region since 2003, specialising in the construction sector and its impact on the broader economy. He has reported exclusively on a wide range of projects across the region including Dubai Metro, the Burj Khalifa, Jeddah Airport, Doha Metro, Hamad International airport and Yas Island. Before joining MEED, Colin reported on the construction sector in Hong Kong.

    Click here to register

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21380319/main.gif
    MEED Editorial
  • Saudi Arabia tenders World Cup stadiums upgrade works

    13 November 2026

     

    Saudi Arabia's Sport Ministry has tendered contracts for upgrade works on two stadiums that will host games for Fifa World Cup 2034.

    The two tenders cover upgrade works on Prince Faisal bin Fahad (PFBF) Stadium, located in Riyadh, and King Khalid University Stadium in Abha.

    The deadline for bid submissions is 22 November.

    PFBF Stadium is located in the northern section of King Abdullah Park in the Al-Malaz area of Riyadh. It will have a seating capacity of about 47,000 spectators.

    It will host the Round of 32 games for the Fifa World Cup in 2034.

    The project was floated as a public-private partnership under a design, build, finance, operate and maintain model last year, but will proceed on a conventional engineering, procurement and construction basis.

    King Khalid University Stadium is expected to be upgraded to have over 45,400 seats. It will host the tournament's Round of 16 games.

    The stadium is located in the southeast of the city of Abha, in Asir Province.

    Saudi stadium plans

    In August 2024, MEED reported that Saudi Arabia planned to build 11 stadiums and refurbish four existing venues for the 2034 tournament. Eight venues will be located in Riyadh, four in Jeddah, and one each in Al-Khobar, Abha and Neom.

    An additional 10 cities will host team base camps: Al-Baha, Jazan, Taif, Medina, AlUla, Umluj, Tabuk, Hail, Al-Ahsa and Buraidah. Across the kingdom, organisers plan to deploy 134 training sites, comprising 61 existing facilities and 73 new builds.

    Saudi Arabia was officially selected to host the Fifa World Cup 2034 tournament during an online convention of member associations at the Fifa Congress on 11 December 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21379026/main.jpg
    Yasir Iqbal
  • Syntys breaks ground on 20MW Qatar data centre

    13 November 2026

    Register for MEED’s 14-day trial access 

    Qatari data centre developer Syntys has broken ground on a 20MW facility to support hyperscale, cloud, artificial intelligence (AI) and advanced computing deployments.

    The groundbreaking ceremony took place on 12 November. It was attended by Qatar’s Communications & Information Technology Minister, Mohammed bin Ali bin Mohammed Al-Mannai, along with representatives from Ooredoo Group, Microsoft, Google, Kahramaa, the National Cyber Security Agency, Qatar Free Zones Authority and local banks.

    Syntys said the facility is being developed on an existing company campus, where power, fibre connectivity and an operational team are already in place. The company has yet to disclose the project value or planned completion date.

    The facility is designed to meet Tier 3 requirements and accommodate a range of rack densities, including higher-density configurations for graphics processing unit (GPU)-based AI and high-performance computing workloads.

    It will operate as a carrier-neutral facility, allowing customers to select connectivity providers and establish network resilience in line with their own technical and operational requirements.

    The project forms part of Syntys’ strategy to expand its Qatar platform through acquisitions and new development. Earlier this year, the company acquired QData QFZ, adding two operational, Tier 3-compliant, carrier-neutral facilities to its portfolio.

    Syntys now owns and operates four campuses in Qatar, allowing customers to establish primary and disaster-recovery environments at separate in-country locations.

    The company also designs and operates the facilities supporting Ooredoo’s sovereign AI cloud, which uses Nvidia Hopper GPUs.

    The development comes as Qatar implements its Digital Agenda 2030, which identifies digital infrastructure as one of six strategic pillars and targets about QR40bn ($11bn) in economic impact by 2030.

    The data centre is expected to support the growth of in-country digital services and enable sensitive workloads to remain within Qatar’s national borders.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21378257/main1028.png
    Yasir Iqbal