Ten projects that will shape Dubai’s future

5 September 2023

 

Register for MEED's guest programme 

Dubai is back with major projects after several years of subdued activity following Expo 2020 and the Covid-19 pandemic.

Over the past year, plans have emerged for 10 projects across various sectors that will help shape the emirate’s development over the coming decade. 

Many of these projects have been planned for years. After stalling during the low-oil-price era of 2015-20, positive economic tailwinds mean many of these schemes are now being revisited by their owners and relaunched.

1. Tower at Creek Harbour

The most recent relaunch announcement came at the end of August, when Emaar Properties founder Mohammad Alabbar revealed plans to redesign and relaunch the Tower at Dubai Creek Harbour.

The design works are expected to be completed by the first quarter of 2024, and construction slated to begin in the second half of 2024.

Details of the redesigned tower have not been launched, but sources close to the project say it will be tall and feature high-end residential units. This reflects Dubai’s buoyant property market and will stand in sharp contrast to the original design that involved building a 1,000-metre-tall observation tower.

Construction on that project stalled in 2019 after work on the foundations was completed. Two bidders were competing for the estimated $5.5bn contract to build the tower. They were Beijing-based China State Construction Engineering Corporation and a joint venture of the local/Belgian Belhasa Six Construct and Tishman, which US-based Aecom owns.

Belhasa Six Construct completed the raft foundations for the tower in May 2018. France’s Soletanche Bachy finished the piling.

Spanish/Swiss architect and engineer Santiago Calatrava Valls was the main consultant on the project, with the local office of Aurecon, supported by the UK’s RMJM and Dubai-based DEC, acting as local engineer and architect of record. The project manager for the tower was US-based Parsons.

2. Dubai Metro Blue Line

The Dubai Creek Harbour development in Ras al-Khor will connect to Dubai’s Metro network via the planned Blue Line, which will serve as an extension to the existing Red and Green lines.

Dubai’s Roads & Transport Authority (RTA) is preparing to issue tender documents for the Blue Line.

The Green Line extension will commence from its current terminus at Creek station in the Jadaf area. It will cross over to the Dubai Creek Harbour development and continue through Ras al-Khor, International City, Dubai Silicon Oasis and Academic City, before concluding near the Desert Rose project. The line will have 11 stations.

The Red Line extension will connect its existing terminus in Rashidiya to Mirdif City Centre and continue through Mirdif and Warqaa, before joining the Green Line extension in International City.

The project was put on hold during the Covid-19 pandemic and reactivated in early 2022, when UK-based Atkins and Grimshaw, US-based Parsons and France’s Egis restarted design work.

The last metro project to be completed in Dubai was Route 2020, which connected the Red Line to the Dubai Expo site. The AED10.6bn ($2.9bn) contract to design and build the line was awarded to a consortium of Alstom, Spain’s Acciona and Turkiye’s Gulermak.

3. Deep Tunnels Portfolio

Another major infrastructure scheme is the Deep Tunnels Portfolio, which involves developing deep-gravity sewage tunnels and treatment plants across the emirate.

In August, Dubai Municipality began the process of appointing a project management consultant to oversee the scheme, which will be developed as a public-private partnership (PPP).

Two sets of deep tunnels will be constructed, terminating at two terminal pump stations at sewerage treatment plants (STPs) in Warsan and Jebel Ali. A conventional sewage and drainage collection system and STPs will be built in Hatta.

The scheme also includes recycled water distribution systems connected to the STPs.

Dubai’s Executive Council approved the project in June and said it would require an investment of about AED80bn ($22bn). It added that the project has been designed to serve the needs of the Dubai population for the next 100 years in alignment with the Dubai Economic Agenda D33 and Dubai Urban Plan 2040.

4. DWTC/Candy tower

Dubai World Trade Centre (DWTC) and UK-based Candy Capital have formed a joint venture to develop three towers in Dubai’s One Central commercial district.

The mixed-use towers will have two branded residences, two hotels and office space. The construction work involves building three towers. The two taller towers will be connected by a sky bridge containing one of the hotels.

Dubai-based Killa Design has been appointed as the architect for the project.

Candy Capital is a privately held family office established by British entrepreneur and businessman Nick Candy. His best-known property development is One Hyde Park in London, which he developed with his brother Christian. It comprises 86 apartments and three retail units and is considered one of the wealthiest residences in the world.

5. Al-Maktoum International airport

Dubai plans to restart the emirate’s largest construction project, the AED120bn ($33bn) expansion of Al-Maktoum International airport, also known as Dubai World Central (DWC). 

The expansion was officially launched in 2014. It involves building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year. An initial phase, which was due to be completed in 2030, aims to take the airport’s capacity to 130 million passengers a year.

Altogether, the development will cover an area of 56 square kilometres.

Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.

Firms were competing for the estimated $2.7bn substructure contract for Concourse 1 and the West Terminal building – the largest contract tendered for the project.

The contract covers the delivery of more than 1.7 million square metres of connected basement footprint, housing the people-mover tunnels, baggage handling systems, ground services road network and other back-of-house technical and support facilities.

6. Palm Jebel Ali

Dubai released details of the new masterplan for Palm Jebel Ali, an artificial island located south of Jebel Ali Freezone, in June.

Double the size of Palm Jumeirah, Palm Jebel Ali will have 110 kilometres of shoreline and extensive green spaces. The development will feature over 80 hotels and resorts and a diverse range of entertainment and leisure facilities.

It includes seven connected islands, catering to approximately 35,000 families. The development also emphasises sustainability, with 30 per cent of public facilities powered by renewable energy.

MEED reported in January that local developer Nakheel had approached contractors to complete the reclamation works for Palm Jebel Ali.

As with Palm Jumeirah, it is estimated that it could take around 20 years for Palm Jebel Ali to reach its full development potential. Nakheel has previously secured AED17bn ($4.6bn) in funding to expedite the development of various projects, including the Dubai Islands and other waterfront schemes.

The upcoming dredging contract for Palm Jebel Ali is anticipated to involve 5-6 million cubic metres of material, contributing to the completion of the man-made offshore island.

While reclamation work for Palm Jebel Ali is mostly finished, the project was put on hold in 2009. Nakheel had made some progress with infrastructure development, including the construction of bridges on the island by Samsung C+T.

7. The Oasis by Emaar

Another major masterplanned development was launched by Emaar Properties in June. The $20bn Oasis by Emaar covers a total land area of more than 9.4 million square metres, close to Dubai Investments Park. The project involves building over 7,000 residential units along with water canals, lakes and parks. It will also include the development of a 150,000 sq m retail area.

8. The Island

Another project that has been restarted in recent years is The Island, which Wasl is developing.

Located off the coast of Umm Suqeim, near the Jumeirah public beach, it is expected to feature 1,400 hotel rooms and apartments, in addition to retail, food and beverage and entertainment options. The 10.5-hectare island will include properties featuring the MGM, Bellagio and Aria hotel brands.

The developer is close to appointing a contractor to build the development after bids were submitted earlier this year.

Tender documents for the contract were previously issued in 2020, when the project was being delivered with a consultancy team led by South Africa’s Mirage.

Germany’s Kling Consult is now the project manager.

9. Al-Habtoor Tower

The $1bn Al-Habtoor Tower project is located at Al-Habtoor City, next to Dubai Water Canal, on a 7,500 sq m plot. The tower, which the developer describes as one of the largest buildings in the world, will have three basement levels, a seven-storey podium and 73 floors of residences. The built-up area will be 350,000 sq m.

Its construction is technically challenging because the tower will be built above an existing parking basement that serves the already completed buildings at Al-Habtoor City.

Al-Habtoor had the option of demolishing the basement. Instead, it decided to employ a top-down approach to the construction that involves piling down through the basement, while at the same time starting construction above ground.

The top-down approach is expected to reduce the construction time by about one year, meaning the tower will be completed in 1,000 days or roughly three years.

China Railway 18th Bureau Group was appointed as the main contractor in May.

10. Dubai Pearl

After two aborted attempts, development is expected to start again at the Dubai Pearl site, located north of Dubai Media City close to the Palm Jumeirah.

The structures erected for the previous project have been demolished this year. Dubai Holding, which now owns the land, has held a design competition and is in the final stages of selecting the winning architect.

Local project management firm North 25 is overseeing the design competition.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11121967/main.gif
Colin Foreman
Related Articles
  • Qiddiya plans $7bn theme park hub near Paris

    25 August 2026

    Saudi Arabia’s Qiddiya Investment Company plans to develop a mixed-use leisure destination worth about €6bn ($7bn) at Cergy-Pontoise in the Ile-de-France region, in one of the largest Saudi investments in French tourism infrastructure to date.

    The plan was set out in a joint statement issued on 24 August at the close of a state visit to France by Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud. France and Saudi Arabia signed a memorandum of understanding (MoU) covering the project during the two-day visit.

    The destination will bring together entertainment, leisure, hospitality, culture and sport, according to the joint statement. Current plans envisage up to three major entertainment anchors, hotels and complementary leisure experiences, with the €6bn figure covering the full development lifecycle.

    One of the three parks is expected to be manga-themed, according to the French presidency. The themes of the other two have not been disclosed. The parks will be built and opened in stages, with construction expected to take several years. No opening date has been given.

    The parks are expected to create about 22,000 direct jobs, according to the French presidency, compared with about 20,000 at Disneyland Paris. Cergy-Pontoise lies about 30 kilometres northwest of Paris.

    Qiddiya is a subsidiary of the Public Investment Fund, Saudi Arabia’s sovereign wealth fund. Its flagship project is a giga-scale entertainment, sports and cultural city on the outskirts of Riyadh, one of several gigaprojects under Vision 2030.

    The theme park plan was among a wider set of agreements reached during the visit. Both sides welcomed the announcement of 21 agreements and MoUs at a French-Saudi investment roundtable, spanning energy, industry, financial services, transport and logistics, health, culture, tourism and artificial intelligence. Bilateral trade reached about $11.8bn in 2025.

    It is not the first time Saudi capital has backed a French theme park. Kingdom Holding Company was a longstanding investor in the operator of Disneyland Paris, first taking a stake in 1994 and participating in successive recapitalisations before Walt Disney Company moved to near-full ownership in 2017.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18987274/main.png
    Colin Foreman
  • Masdar shelves Abu Dhabi green hydrogen project

    25 August 2026

     

    Abu Dhabi Future Energy Company (Masdar) has decided to cancel a planned project to build a green hydrogen plant in Abu Dhabi that would have supplied up to 100MW of renewable hydrogen to local steelmaker Emsteel for green steel production.

    After contractors submitted bids for the project last year, Masdar asked bidders in the first quarter of this year to extend the validity of their proposals until the end of August to allow “more time to study and evaluate bids”, according to one source.

    However, Masdar issued a notification to all bidders on 1 August stating that it had decided to cancel the project, sources told MEED.

    Contractors that submitted bids for the Masdar green hydrogen project included:

    • Envision (China)
    • Larsen & Toubro (India)
    • PowerChina (China)
    • Samsung E&A (South Korea)
    • Sinopec (China)

    Masdar did not respond to MEED’s request for comment on the information.

    In its current steelmaking process, Emsteel uses hydrogen produced by steam reforming of natural gas as a reducing agent to extract iron from iron ore. The core objective of Masdar’s planned project was to install a 100MW electrolyser at Emsteel’s main manufacturing hub in Musaffah, Abu Dhabi, to supply green hydrogen for future clean steel production.

    Masdar initiated work on the project in 2024 by awarding a front-end engineering and design (feed) contract to locally based NT Energies, a joint venture of Abu Dhabi’s NMDC Energy and France-based Technip Energies.

    Masdar then sought proposals last year for engineering, procurement, construction, demolition (if needed for brownfield activities), pre-commissioning, commissioning, start-up, and two years of operations and maintenance (extendable up to 20 years) at the planned facility.

    Contractors submitted bids by the end of the year, according to sources.

    The project involved green hydrogen production using alkaline water electrolysis, with a total installed electrolyser capacity of 100MW.

    The scope of work involved building electrolyser stacks and modules, hydrogen separation and compression units, associated utilities and storage systems, and electrical, instrumentation and control systems.

    It also included tie-ins to pre-defined interface points, including (but not limited to):

    • a grid power supply connection to the MOSF substation in Musaffah that exists within the Emsteel complex and is operated by Taqa Transmission
    • a water supply connection to a nearby Taqa Distribution network

    Supporting infrastructure included a substation, a motor control centre, and ancillary plant buildings and facilities.

    Masdar’s planned 100MW electrolyser project at the Emsteel facility would have represented a step up from a previous pilot project by the two Abu Dhabi-owned companies.

    The partners inaugurated a pilot green hydrogen plant at Emsteel’s manufacturing complex in Musaffah in October 2024. It incorporates a 2.1MW electrolyser and is designed to support the production of up to 5,000 tonnes of green steel a year.

    This made Emsteel the only steelmaker in the Middle East to use green hydrogen to produce green steel on a pilot basis.

    “Sustainability is central to Emsteel’s innovation, competitiveness and long-term growth. Today, approximately 89% of our steel business electricity consumption comes from clean sources, and our steel carbon emissions intensity is around 40% lower than the World Steel Association global average,” Michael Rion, chief commercial officer of Emirates Steel, part of Emsteel Group, told MEED in a recent interview.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18911651/main0611.jpg
    Indrajit Sen
  • Oman invites bids for Musandam renewables study

    25 August 2026

    Oman’s Nama Power & Water Procurement Company (PWP) has issued a request for proposals (RFP) for techno-economic consultancy services to assess the feasibility of renewable energy options in Musandam Governorate.

    The study will examine solar photovoltaic (PV), wind and hybrid renewable energy configurations. It will also assess battery energy storage systems (bess) and other renewable energy and energy storage technologies.

    The consultant will be required to determine which technologies are technically and economically justified for the governorate.

    The bid submission deadline is 24 September.

    The Musandam power system is served primarily by the 123MW Musandam independent power plant (IPP), which began operating in 2017. The governorate has historically relied on small diesel-fired units, but has been seeking to move away from diesel-fired power generation for several years.

    Nama PWP has previously said it was exploring renewable energy options in Musandam to meet future additional capacity requirements.

    Its latest seven-year statement, released in March, forecasts peak electricity demand in Musandam to rise from 91MW in 2024 to 130MW in 2031, an average annual increase of 5%. Average demand is forecast to rise from 52MW to 73MW over the same period.

    The plan says demand growth is being driven by distribution-level load and projects aimed at boosting tourism, economic and commercial activity. 

    Separately, the utility recently invited bids for financial and commercial consultancy services covering three 1GW solar IPPs targeted for commercial operation by the second quarter of 2030.

    The bid submissions deadline is 10 September.

    The three projects covered by the financial and commercial consultancy tender are understood to also be part of the 4GW programme, for which a technical advisory tender was issued on 15 July.

    Bidding for this tender closes on 26 August.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18983679/main.jpg
    Mark Dowdall
  • US launches sanctions campaign against Iran

    25 August 2026

    The US has launched a sweeping sanctions campaign against Iran and the entities that trade with it, imposing measures on almost 60 individuals, companies and vessels while expanding the reach of secondary sanctions across five sectors of the Iranian economy.

    The campaign, named Operation Economic Outcast, was announced on 24 August by US treasury secretary Scott Bessent, who described it as an economic D-Day for Iran. He said Washington’s objective was to sever every economic lifeline sustaining the Iranian regime.

    The treasury’s Office of Foreign Assets Control (Ofac) issued five sectoral sanctions determinations under Executive Order 13902, covering digital assets, technology, gold, aviation and shipping. The determinations allow Ofac to sanction any person operating in those sectors, regardless of location. Washington said Iran uses cryptocurrency for sanctions evasion, seeks advanced technology for its weapons programmes, uses gold to stabilise the rial, and relies on commercial aviation and shipping networks to move fighters, weapons and oil revenue.

    The measures build on earlier determinations targeting Iran’s financial, petroleum and petrochemical sectors.

    Ofac also sanctioned close to 60 entities, individuals and vessels across multiple jurisdictions, including UAE-based entities, over alleged involvement in nuclear and missile procurement, cyber operations and oil revenue networks. The designations named a network of brokers, companies and shadow fleet vessels operating across the UAE, Hong Kong, China, Singapore, Switzerland and other regions to transport Iranian oil and channel revenue to the Islamic Revolutionary Guard Corps.

    Among those designated were shipping brokers and bunkering firms based in the UAE that Washington said facilitated Iranian oil shipments and provided services to sanctioned vessels. The treasury also identified several shadow fleet tankers as blocked property, saying they had moved millions of barrels of Iranian crude and petroleum products, mainly to China.

    Separately, the treasury targeted a procurement network spanning the Middle East and East Asia that it said supported Iran’s acquisition of proliferation-sensitive equipment, along with a cyber group directed by Iran’s Ministry of Intelligence & Security.

    Bessent said Washington was pressing governments to shut down Iran-related activity within defined timelines, warning that entities facilitating money laundering or sanctions evasion for Iran risked being cut off from the US financial system. He declined to name specific countries.

    The campaign follows the UAE’s own move against Tehran. On 19 August, the UAE suspended all trade, commercial exchanges and financial transactions with Iran with immediate effect, citing regional escalation. The UAE has historically been one of Iran’s most significant trading partners, with much of the relationship built on re-export trade routed through Dubai.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18983152/main.jpg
    Colin Foreman
  • Kuwait tenders $3.3bn gas processing facility

    25 August 2026

     

    State-owned Kuwait Gulf Oil Company (KGOC) has issued the tender for the development of an onshore gas plant next to the Al-Zour refinery, according to industry sources.

    The project budget is estimated at $3.3bn, and the bid deadline is 29 December, with a meeting for contractors scheduled for 14 September.

    The tender was issued on 23 August.

    The proposed plant will have the capacity to process up to 632 million cubic feet a day of gas and 60,000 b/d a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.

    In February, MEED reported that at least seven companies had shown interest in participating in the tender.

    Contractors that sent representatives to previous meetings to discuss the project include:

    • Samsung E&A (South Korea)
    • Larsen & Toubro (India)
    • Tecnicas Reunidas (Spain)
    • Saipem (Italy)
    • Hyundai Engineering & Construction (South Korea)
    • Hyundai Engineering Company (South Korea)
    • JGC (Japan)

    The tender process is using a fast-track model, which means that Kuwait’s Central Agency for Public Tenders (Capt) will not be involved in the tender process.

    Capt typically reviews the technical and commercial evaluations of bids and verifies that the bidding process is competitive.

    It is understood that not requiring Capt to approve this tender is expected to speed up the tender process.

    Iran disputes ownership of the field, referring to it as Arash.

    Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.

    The Dorra field’s close proximity to Iran could make development difficult due to current security concerns.

    The offshore elements of the wider Dorra field development project are expected to be especially difficult to protect from attacks from Iran.

    Earlier this month, MEED revealed that Al-Khafji Joint Operations (KJO) had selected contractors for two major offshore packages under the Dorra field facilities development project.

    KJO, which is jointly owned by Aramco subsidiary Aramco Gulf Operations Company and Kuwait Petroleum Corporation subsidiary KGOC, has divided the engineering, procurement and construction (EPC) scope for the Dorra gas production project into four packages: three offshore and one onshore.

    US-based McDermott International has secured offshore package 2A, valued at about $1.5bn, according to sources.

    A consortium of India’s Larsen & Toubro Energy Hydrocarbon (LTEH) and Italian contractor Saipem has secured package 2B, sources told MEED.

    Estimated at about $3.7bn, package 2B is the largest of the three offshore EPC packages under the Dorra field facilities project.

    MEED reported in March that the LTEH/Saipem consortium had emerged as the lowest bidder for offshore package 2B.

    Contractors submitted bids for offshore packages 2A and 2B by the 9 March deadline, MEED previously reported. Bid validity was understood to expire on 15 August, prompting KJO to issue letters of intent to the selected contractors earlier this month, sources said.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18964461/main.png
    Wil Crisp