Ten projects that will shape Dubai’s future

5 September 2023

 

Register for MEED's guest programme 

Dubai is back with major projects after several years of subdued activity following Expo 2020 and the Covid-19 pandemic.

Over the past year, plans have emerged for 10 projects across various sectors that will help shape the emirate’s development over the coming decade. 

Many of these projects have been planned for years. After stalling during the low-oil-price era of 2015-20, positive economic tailwinds mean many of these schemes are now being revisited by their owners and relaunched.

1. Tower at Creek Harbour

The most recent relaunch announcement came at the end of August, when Emaar Properties founder Mohammad Alabbar revealed plans to redesign and relaunch the Tower at Dubai Creek Harbour.

The design works are expected to be completed by the first quarter of 2024, and construction slated to begin in the second half of 2024.

Details of the redesigned tower have not been launched, but sources close to the project say it will be tall and feature high-end residential units. This reflects Dubai’s buoyant property market and will stand in sharp contrast to the original design that involved building a 1,000-metre-tall observation tower.

Construction on that project stalled in 2019 after work on the foundations was completed. Two bidders were competing for the estimated $5.5bn contract to build the tower. They were Beijing-based China State Construction Engineering Corporation and a joint venture of the local/Belgian Belhasa Six Construct and Tishman, which US-based Aecom owns.

Belhasa Six Construct completed the raft foundations for the tower in May 2018. France’s Soletanche Bachy finished the piling.

Spanish/Swiss architect and engineer Santiago Calatrava Valls was the main consultant on the project, with the local office of Aurecon, supported by the UK’s RMJM and Dubai-based DEC, acting as local engineer and architect of record. The project manager for the tower was US-based Parsons.

2. Dubai Metro Blue Line

The Dubai Creek Harbour development in Ras al-Khor will connect to Dubai’s Metro network via the planned Blue Line, which will serve as an extension to the existing Red and Green lines.

Dubai’s Roads & Transport Authority (RTA) is preparing to issue tender documents for the Blue Line.

The Green Line extension will commence from its current terminus at Creek station in the Jadaf area. It will cross over to the Dubai Creek Harbour development and continue through Ras al-Khor, International City, Dubai Silicon Oasis and Academic City, before concluding near the Desert Rose project. The line will have 11 stations.

The Red Line extension will connect its existing terminus in Rashidiya to Mirdif City Centre and continue through Mirdif and Warqaa, before joining the Green Line extension in International City.

The project was put on hold during the Covid-19 pandemic and reactivated in early 2022, when UK-based Atkins and Grimshaw, US-based Parsons and France’s Egis restarted design work.

The last metro project to be completed in Dubai was Route 2020, which connected the Red Line to the Dubai Expo site. The AED10.6bn ($2.9bn) contract to design and build the line was awarded to a consortium of Alstom, Spain’s Acciona and Turkiye’s Gulermak.

3. Deep Tunnels Portfolio

Another major infrastructure scheme is the Deep Tunnels Portfolio, which involves developing deep-gravity sewage tunnels and treatment plants across the emirate.

In August, Dubai Municipality began the process of appointing a project management consultant to oversee the scheme, which will be developed as a public-private partnership (PPP).

Two sets of deep tunnels will be constructed, terminating at two terminal pump stations at sewerage treatment plants (STPs) in Warsan and Jebel Ali. A conventional sewage and drainage collection system and STPs will be built in Hatta.

The scheme also includes recycled water distribution systems connected to the STPs.

Dubai’s Executive Council approved the project in June and said it would require an investment of about AED80bn ($22bn). It added that the project has been designed to serve the needs of the Dubai population for the next 100 years in alignment with the Dubai Economic Agenda D33 and Dubai Urban Plan 2040.

4. DWTC/Candy tower

Dubai World Trade Centre (DWTC) and UK-based Candy Capital have formed a joint venture to develop three towers in Dubai’s One Central commercial district.

The mixed-use towers will have two branded residences, two hotels and office space. The construction work involves building three towers. The two taller towers will be connected by a sky bridge containing one of the hotels.

Dubai-based Killa Design has been appointed as the architect for the project.

Candy Capital is a privately held family office established by British entrepreneur and businessman Nick Candy. His best-known property development is One Hyde Park in London, which he developed with his brother Christian. It comprises 86 apartments and three retail units and is considered one of the wealthiest residences in the world.

5. Al-Maktoum International airport

Dubai plans to restart the emirate’s largest construction project, the AED120bn ($33bn) expansion of Al-Maktoum International airport, also known as Dubai World Central (DWC). 

The expansion was officially launched in 2014. It involves building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year. An initial phase, which was due to be completed in 2030, aims to take the airport’s capacity to 130 million passengers a year.

Altogether, the development will cover an area of 56 square kilometres.

Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.

Firms were competing for the estimated $2.7bn substructure contract for Concourse 1 and the West Terminal building – the largest contract tendered for the project.

The contract covers the delivery of more than 1.7 million square metres of connected basement footprint, housing the people-mover tunnels, baggage handling systems, ground services road network and other back-of-house technical and support facilities.

6. Palm Jebel Ali

Dubai released details of the new masterplan for Palm Jebel Ali, an artificial island located south of Jebel Ali Freezone, in June.

Double the size of Palm Jumeirah, Palm Jebel Ali will have 110 kilometres of shoreline and extensive green spaces. The development will feature over 80 hotels and resorts and a diverse range of entertainment and leisure facilities.

It includes seven connected islands, catering to approximately 35,000 families. The development also emphasises sustainability, with 30 per cent of public facilities powered by renewable energy.

MEED reported in January that local developer Nakheel had approached contractors to complete the reclamation works for Palm Jebel Ali.

As with Palm Jumeirah, it is estimated that it could take around 20 years for Palm Jebel Ali to reach its full development potential. Nakheel has previously secured AED17bn ($4.6bn) in funding to expedite the development of various projects, including the Dubai Islands and other waterfront schemes.

The upcoming dredging contract for Palm Jebel Ali is anticipated to involve 5-6 million cubic metres of material, contributing to the completion of the man-made offshore island.

While reclamation work for Palm Jebel Ali is mostly finished, the project was put on hold in 2009. Nakheel had made some progress with infrastructure development, including the construction of bridges on the island by Samsung C+T.

7. The Oasis by Emaar

Another major masterplanned development was launched by Emaar Properties in June. The $20bn Oasis by Emaar covers a total land area of more than 9.4 million square metres, close to Dubai Investments Park. The project involves building over 7,000 residential units along with water canals, lakes and parks. It will also include the development of a 150,000 sq m retail area.

8. The Island

Another project that has been restarted in recent years is The Island, which Wasl is developing.

Located off the coast of Umm Suqeim, near the Jumeirah public beach, it is expected to feature 1,400 hotel rooms and apartments, in addition to retail, food and beverage and entertainment options. The 10.5-hectare island will include properties featuring the MGM, Bellagio and Aria hotel brands.

The developer is close to appointing a contractor to build the development after bids were submitted earlier this year.

Tender documents for the contract were previously issued in 2020, when the project was being delivered with a consultancy team led by South Africa’s Mirage.

Germany’s Kling Consult is now the project manager.

9. Al-Habtoor Tower

The $1bn Al-Habtoor Tower project is located at Al-Habtoor City, next to Dubai Water Canal, on a 7,500 sq m plot. The tower, which the developer describes as one of the largest buildings in the world, will have three basement levels, a seven-storey podium and 73 floors of residences. The built-up area will be 350,000 sq m.

Its construction is technically challenging because the tower will be built above an existing parking basement that serves the already completed buildings at Al-Habtoor City.

Al-Habtoor had the option of demolishing the basement. Instead, it decided to employ a top-down approach to the construction that involves piling down through the basement, while at the same time starting construction above ground.

The top-down approach is expected to reduce the construction time by about one year, meaning the tower will be completed in 1,000 days or roughly three years.

China Railway 18th Bureau Group was appointed as the main contractor in May.

10. Dubai Pearl

After two aborted attempts, development is expected to start again at the Dubai Pearl site, located north of Dubai Media City close to the Palm Jumeirah.

The structures erected for the previous project have been demolished this year. Dubai Holding, which now owns the land, has held a design competition and is in the final stages of selecting the winning architect.

Local project management firm North 25 is overseeing the design competition.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11121967/main.gif
Colin Foreman
Related Articles
  • Parsons wins role on Elon Musk-backed Dubai Loop project

    4 May 2026

    US-based Parsons Corporation has been appointed to deliver programme management services for the Dubai Loop transportation system.

    The contract was awarded by Elon Musk-backed firm The Boring Company, which signed a construction agreement with Dubai’s Roads & Transport Authority (RTA) in February.

    Parsons’ scope of work includes independent design verification, stakeholder management, permitting and no-objection certificate (NOC) support, and multidisciplinary design reviews for the project’s first phase.

    The first phase comprises a 6.4-kilometre route with four stations, linking the Dubai International Financial Centre (DIFC) and Dubai Mall.

    Stations will be located at DIFC 2, ICD Brookfield Place, Dubai Mall Zabeel Parking and Burj Khalifa.

    The first phase is expected to cost about AED565m ($154m) and to be delivered within one year after design work and other preparations are completed. Tunnelling is expected to begin in the second half of this year.

    Next phase

    The second phase will connect Dubai World Trade Centre and DIFC with Business Bay.

    The tunnels will extend up to 22km and include 19 stations.

    The total cost across both phases is expected to be around AED2bn ($545m), with completion scheduled within three years.

    The pilot route is expected to serve around 13,000 passengers a day, while the full route is projected to have a capacity of about 30,000 passengers a day.

    The RTA and The Boring Company signed a memorandum of understanding on the sidelines of the World Governments Summit in Dubai in February last year to explore the development of the Dubai Loop transportation system.

    The Dubai Loop is expected to be similar to The Boring Company’s Las Vegas Convention Centre (LVCC) Loop project. The LVCC Loop is a 2.7km underground tunnel system that connects different convention centre halls, reducing walking time across the site to about two minutes.

    The LVCC Loop has been in operation since 2021. It uses Tesla Model 3 cars to carry passengers between five stations. The Boring Company began construction in November 2019 at an estimated cost of $49m.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16672074/main.jpg
    Yasir Iqbal
  • Humain tenders infrastructure for 6GW data centre campus

    4 May 2026

    Saudi artificial intelligence (AI) infrastructure company Humain, owned by the Public Investment Fund (PIF), has issued a tender inviting firms to develop infrastructure for its planned 6GW hyperscale AI data centre campus in Riyadh.

    The project will be delivered on an early contractor involvement (ECI) basis. Under the ECI process, selected contractors are required to submit methodologies and design proposals, after which one team will be selected to deliver the construction works.

    Firms have until 8 May to submit proposals.

    The development will be built on a 24-square-kilometre site in the Al-Saad area in east Riyadh. It will be delivered in two phases across six plots, each with a capacity of 1GW.

    The scope of infrastructure work covers:

    • Construction of 380kV/132kV/33kV electrical distribution network, two substations with a capacity of 500MVA and 200MVA, bulk supply point (2,000MVA)
    • Water network and fire protection systems
    • Sewage treatment plant and wastewater network
    • Stormwater systems
    • Roads
    • Underground cable and fibre optic networks
    • Landscaping works

    The client is being supported by Canadian engineering firm Hatch, France’s Egis and US-based firm JLL.

    Humain was launched in May last year to operate and invest across the AI value chain.

    Humain is building full-stack AI capabilities across four core areas: next-generation data centres, hyper-performance infrastructure and cloud platforms, and advanced AI models, including Allam.

    Also in May 2025, Humain signed preliminary deals with US chipmakers AMD and Nvidia to build multibillion-dollar advanced digital infrastructure in the kingdom.

    AMD said it will invest up to $10bn to deploy 500MW of AI compute capacity in Saudi Arabia over the next five years.

    In October, PIF and Saudi Aramco signed a non-binding term sheet setting out key terms under which Aramco would acquire a minority stake in Humain, with PIF retaining majority ownership.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16671267/main.jpg
    Yasir Iqbal
  • Abu Dhabi selects consortium for 2.5GW Taweelah C IPP

    4 May 2026

     

    Register for MEED’s 14-day trial access 

    A consortium of Al-Jomaih Energy & Water Company (Saudi Arabia) and Sembcorp Industries (Singapore) has been selected to develop the Taweelah C independent power producer (IPP) project in Abu Dhabi.

    The consortium will sign a power purchase agreement (PPA) in mid-May, a source told MEED.

    The combined-cycle gas turbine (CCGT) plant will have a capacity of 2.5GW. It will be located at the Al-Taweelah power and desalination complex, about 50 kilometres northeast of Abu Dhabi city.

    It is understood that China Energy Engineering Corporation (CEEC) will be the engineering, procurement and construction (EPC) contractor.

    Last September, MEED reported that state offtaker Emirates Water & Electricity Company (Ewec) had received three bids for the facility.

    The bidders included:

    • Al-Jomaih Energy & Water Company / Sembcorp Industries
    • Sumitomo Corporation (Japan) / Korea Overseas Infrastructure & Urban Development Corporation / Korean Midland Power
    • Korea Western Power Company / Etihad Water & Electricity (UAE) / Kyuden International (Japan)

    At the time, Mohamed Al-Marzooqi, chief asset development and management officer at Ewec, said the bids would make Taweelah C “one of the lowest tariff CCGT projects in the region”.

    The carbon-capture-ready facility had been scheduled to begin commercial operations in the fourth quarter of 2028.

    This was based on the initial timeline for a PPA to be signed in the fourth quarter of 2025.

    Taweelah C is part of Ewec’s wider programme to support the UAE’s Net Zero by 2050 Strategic Initiative and the Abu Dhabi Department of Energy’s Clean Energy Strategic Target 2035.

    Ewec plans to raise solar power capacity to 18GW and wind capacity to 2.6GW by 2035, while reducing the carbon intensity of its power generation by more than half compared to 2019.

    Ewec is also expanding its low-carbon water desalination capacity, with the Taweelah reverse osmosis (RO) plant already operating as the world’s largest RO facility and additional projects, such as the Mirfa 2 RO and Shuweihat 4 RO, under way.

    By 2030, it expects 95% of Abu Dhabi’s installed water capacity to come from RO technology.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16670622/main0858.jpg
    Mark Dowdall
  • Dubai launches Blue Line metro tunnelling works

    4 May 2026

    Dubai has announced the launch of tunnelling works for the Dubai Metro Blue Line extension project.

    In a post on X, Sheikh Mohammed Bin Rashid Al-Maktoum, UAE Vice President, Prime Minister and Ruler of Dubai, announced the start of operations of the tunnel boring machine (TBM), which the Roads & Transport Authority (RTA) has named ‘Al-Wugeisha’.

    The TBM is 163 metres long, weighs more than 2,000 tonnes and will operate around the clock. The post added that its average excavation rate ranges from 13 to 17 metres a day.

    The Blue Line will connect the existing Red and Green lines. It will be 30 kilometres (km) long, with 15.5km underground and 14.5km above ground.

    The line will have 14 stations, seven of which will be elevated. There will be five underground stations, including one interchange station, and two elevated transfer stations connected to the existing Centrepoint and Creek stations.

    In December 2024, the RTA awarded a AED20.5bn ($5.5bn) main contract for the construction of the project to a consortium comprising Turkiye’s Limak Holding and Mapa Group, along with the Hong Kong office of China Railway Rolling Stock Corporation (CRRC).

    The consortium is responsible for all civil works, electromechanical works, rolling stock and rail systems. After completing the project, it will assist with maintenance and operations for an initial three-year period.

    According to an official statement, the Blue Line will have a capacity of 46,000 passengers an hour in both directions.

    The project is scheduled for completion in September 2029.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16670584/main.jpeg
    Yasir Iqbal
  • Firms submit Jeddah distribution centre bids

    4 May 2026

     

    Contractors submitted bids on 26 April for an estimated SR140m ($37m) contract to build a distribution centre in Jeddah.

    Saudi Logistics Services Company (SAL) launched the tender on 11 March, as previously reported by MEED. The project will cover an area of about 37,000 square metres. Egyptian firm Cosmos-E Engineers & Consultants has been appointed as the project consultant.

    This tender follows the start of construction by Egyptian contractor Rowad Modern Engineering, a subsidiary of Elsewedy Electric Group, on the expansion of SAL’s facilities at King Khalid International airport in Riyadh. The scope of work includes rehabilitating and upgrading existing infrastructure, as well as constructing new supporting facilities and services.

    SAL also launched the tendering process in September last year for its SR4.2bn ($1bn) logistics zone in northern Riyadh, MEED previously reported. UAE-based Global Engineering Consultants is the consultant for that development.

    The logistics hub aims to meet demand for customised warehouses near King Khalid International airport and the Riyadh Metro. The project aligns with Vision 2030 and the National Transport & Logistics Strategy, which aims to strengthen the kingdom’s logistics sector and enhance Saudi Arabia’s position as a global logistics hub.