Technip Energies leapfrogs the field
23 November 2023

There has been a surge in market activity for the oil, gas and petrochemicals sector in the Middle East and North Africa (Mena) over the past year, with engineering, procurement and construction (EPC) contractors securing $77.6bn-worth of deals between October 2022 and September 2023.
This pace of contract award activity represents a more than doubling of the $37.6bn in awards that were let in the preceding four quarters. It is also reflected in a swelling of the award value that was booked by the top 10 most successful contractors during the period.
These companies secured contract awards totalling $47.2bn in the past four quarters – also more than double the $21.4bn secured by the top 10 contractors by contract value in the period prior.
This surge in activity has also resulted in a significant amount of reshuffling of the regional leaders in terms of recently awarded contract values.
Regional leaders
Topping the ranking is France’s Technip Energies, which clinched pole position with a contract value of $7.6bn over the past four quarters – made up principally by its 70 per cent share in the $10bn contract to deliver two new liquefied natural gas (LNG) trains as part of QatarEnergy’s North Field South expansion programme. This was the second-largest single contract in the Mena oil and gas industry to date.
The remarkable win is a huge boost for the French company, which in the preceding period sat in only 10th place, with awards totalling $922m.
France’s Technip Energies clinched the top position with a contract value of $7.6bn over the past four quarters
Second in this year’s ranking is Hyundai Engineering & Construction from South Korea, with $7.4bn in contract awards, having risen from sixth position the preceding year with just $1.4bn in awards. The firm notably secured two packages worth $2.5bn each from Satorp – the joint venture of Saudi Aramco and TotalEnergies – for the development of the Amiral complex in Jubail.
Hyundai E&C also secured a $2.4bn contract with Saudi Aramco for the phase two, package two utilities and off-site facilities at the Jafurah unconventional gas field in the kingdom’s Eastern Province.
India’s Larsen & Toubro Energy Hydrocarbon (LTEH) has maintained a consistent foothold in the ranking, retaining the third spot for the second year running. It did so with a significantly elevated contract award value, however, at $6.9bn over the past four quarters, as compared to $2.4bn in the preceding period.
LTEH bookings included two more contracts as part of phase two of Aramco’s development of its Jafurah unconventional gas field – a $2.9bn contract for package one, a gas treatment facility, and a $1bn contract for package three, a gas compression plant. LTEH also secured a $1.2bn deal in Algeria for a hydrocracking unit as part of Sonatrach’s Skikda refinery expansion.
Italy’s Saipem has climbed to fourth place with $6.1bn of awards, where previously it came in seventh place with $1.3bn in awards. Its major contracts included the $4.5bn contract for phase two, scope B of the QatarEnergy LNG North Field Production Sustainability programme, and a $1bn contract for the Bouri gas utilisation project with Libya’s Mellitah Oil & Gas Company.
Spain’s Tecnicas Reunidas follows in fifth place, with contracts valued at $5.6bn, rising from ninth place in the previous period, when it secured $1.1bn in awards. The major contract wins in the current period included the $3.6bn contract for Abu Dhabi National Oil Company’s (Adnoc) Maximising Ethane Recovery and Monetisation (Meram) project in a 50:50 joint venture with the local NMDC Energy, formerly National Petroleum Construction Company.
Tecnicas Reunidas also secured two contracts with Aramco for work on the Riyas natural gas liquids fractionation plant, which is part of the second expansion phase of Jafurah: a $2.2bn award for package two and a $1bn award for package one.
Rounding out the top 10
Italy’s Maire Tecnimont claims sixth place with contracts totalling $3.6bn, maintaining its presence in the top ranks with an increased award value, but still down from third position in the previous period, when the firm secured contracts worth $2.6bn.
The contractor’s wins included a $1.3bn deal from a joint venture of QatarEnergy and US firm Chevron Phillips Chemical for the Ras Laffan petrochemicals project and several packages within Satorp’s Amiral complex, totalling $1.92bn. It also secured a $380m contract with Sonatrach for a liquefied petroleum gas extraction plant in Rhourde el-Bagel.
Lebanon’s Consolidated Contractors Company has meanwhile secured the seventh position with contracts valued at $3bn. This was led by its 30 per cent share of the $10bn contract for the QatarEnergy LNG North Field South development and a $400m deal for pipelines as part of Satorp’s Amiral project package 5B.
NMDC Energy has landed in eighth position with contracts worth just under $3bn. Its wins included a 50 per cent share of the $3.6bn contract for Adnoc’s Meram project, working alongside Tecnicas Reunidas, as well as a $614m contract for a pipeline as part of Adnoc’s Estidama project and a $600m contract from Saudi Aramco to lay a pipeline from Zuluf to Safaniya.
The contractor’s position is nevertheless down from last year, when it ranked first with $4.9bn-worth of awards.
China Petroleum Engineering & Construction Corporation secured contracts totalling $2.4bn, earning it ninth place in this year’s ranking. Its wins included a $500m contract for Basra Oil Company’s West Qurna-1 oil field development and a $386m contract for Basra Energy Company’s Mishrif Qurainat oil field development.
UK-based Petrofac rounds off the top 10 with contracts valued at $1.7bn. Wins included a $1bn share of the $1.5bn contract for the Sonatrach Total Entreprise Polymeres joint venture’s propane dehydrogenation polypropylene plant in Arzew, Algeria, and a $700m award for a compressor plant at Habshan as part of Adnoc’s Estidama programme.
Several contractors that were present in last year’s ranking are noticeably absent from this year’s list. These include Japan’s JGC Corporation, which secured no new contracts in the period after posting in second place last year with $4bn in awards.
US firm McDermott secured $1bn in contract awards this year after placing fourth in the ranking last year with $2.6bn in awards. South Korea’s Samsung Engineering meanwhile secured $1.3bn in awards, slightly up from $1.2bn in the previous period, but not enough to remain in the ranking this year.
Sector and country breakdown
The gas sector emerged as the most lucrative sector in the past four quarters, representing contract awards totalling $33.3bn. This was followed by the chemicals sector, which saw $23.3bn in contract awards, and the oil sector, which recorded $21bn.
In terms of the country of origin for contract awards over the past four quarters, Saudi Arabia led the way, representing awards totalling $23.4bn. This was followed closely by Qatar, with awards worth $20.6bn.
Iran also witnessed contracts totalling $11.2bn, but this was split between several local contractors in such a way that it prevented any individual EPC contractor from making its mark at a regional level.
The UAE oil, gas and chemicals market meanwhile recorded $9.2bn in contract awards, with several contracts from Adnoc playing a key role in this year’s ranking.
Algeria, Jordan and Iraq saw total contract awards values of $3.3bn, $3bn and $2.9bn, respectively. Other countries in the region accounted for a further $4bn-worth of EPC contract awards.
Exclusive from Meed
-
Kuwait awards $381m oil project23 September 2026
-
Kuwait refinery project on track for year-end completion23 September 2026
-
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
-
UAE to develop integrated waste-to-resource pilot23 September 2026
-
Contractors prepare Oxagon Highway 55 bids23 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Kuwait awards $381m oil project23 September 2026
Register for MEED’s 14-day trial access
State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).
The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.
The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.
The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.
The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.
Meil will develop the new three-phase low-pressure wet separation facility at GC-25.
The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.
The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.
Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.
The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.
At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.
The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.
Booster and injection pumps will transfer treated effluent water to designated injection wells.
Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.
The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.
Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.
Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.
The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.
Seven companies submitted bids for the project last November.
The full list of bids was:
- Meil (India) – KD117m ($381m)
- Mechanical Engineering & Contracting Company (Kuwait) – KD130m
- Spetco (Kuwait) – KD158m
- Al-Kharafi (Kuwait) – KD164m
- China Oil HBP Science & Technology (China) – KD169m
- Alghanim International (Kuwait) – KD169m
- Jereh Oil & Gas Engineering (China) – KD191m
In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.
Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg -
Kuwait refinery project on track for year-end completion23 September 2026

A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.
The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.
One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”
The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).
Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.
The scope of the project includes:
- Construction of a substation
- Installation of transformers
- Installation of medium-voltage switchgear
- Installation of low-voltage auxiliary systems
- Installation of network protection systems
- Installation of disconnecting switches
- Installation of surge arrestors
- Installation of feeder breakers and cubicles
- Installation of low-voltage A/C and D/C equipment
- Installation of battery banks and battery chargers
- Installation of related relay and control panel boards
- Installation of fire alarm and fire protection equipment
- Installation of a SCADA system
- Installation of cables
- Civil works
- Associated facilities
The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.
On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.
The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.
Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.
He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.
Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg -
Contractor wins $208m Almoosa hospital MEP contract23 September 2026
Register for MEED’s 14-day trial access
Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.
Saudi Arabia’s Almoosa Health Company awarded the contract.
The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.
It will be built on a 45,000-square-metre site.
A podium spanning the ninth and 10th floors will connect the two towers.
The hospital will also include parking for 1,700 cars.
BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.
In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.
In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.
Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg -
UAE to develop integrated waste-to-resource pilot23 September 2026
Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.
The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.
Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.
Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.
The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.
A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.
Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.
The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.
If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.
The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg -
Contractors prepare Oxagon Highway 55 bids23 September 2026

Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.
The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.
The project duration is 22 months.
Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.
MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.
The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.
Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.
In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”
The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg