Technip Energies leapfrogs the field

23 November 2023

 

There has been a surge in market activity for the oil, gas and petrochemicals sector in the Middle East and North Africa (Mena) over the past year, with engineering, procurement and construction (EPC) contractors securing $77.6bn-worth of deals between October 2022 and September 2023.

This pace of contract award activity represents a more than doubling of the $37.6bn in awards that were let in the preceding four quarters. It is also reflected in a swelling of the award value that was booked by the top 10 most successful contractors during the period. 

These companies secured contract awards totalling $47.2bn in the past four quarters – also more than double the $21.4bn secured by the top 10 contractors by contract value in the period prior. 

This surge in activity has also resulted in a significant amount of reshuffling of the regional leaders in terms of recently awarded contract values.

Regional leaders

Topping the ranking is France’s Technip Energies, which clinched pole position with a contract value of $7.6bn over the past four quarters – made up principally by its 70 per cent share in the $10bn contract to deliver two new liquefied natural gas (LNG) trains as part of QatarEnergy’s North Field South expansion programme. This was the second-largest single contract in the Mena oil and gas industry to date. 

The remarkable win is a huge boost for the French company, which in the preceding period sat in only 10th place, with awards totalling $922m. 

France’s Technip Energies clinched the top position with a contract value of $7.6bn over the past four quarters

Second in this year’s ranking is Hyundai Engineering & Construction from South Korea, with $7.4bn in contract awards, having risen from sixth position the preceding year with just $1.4bn in awards. The firm notably secured two packages worth $2.5bn each from Satorp – the joint venture of Saudi Aramco and TotalEnergies – for the development of the Amiral complex in Jubail. 

Hyundai E&C also secured a $2.4bn contract with Saudi Aramco for the phase two, package two utilities and off-site facilities at the Jafurah unconventional gas field in the kingdom’s Eastern Province.

India’s Larsen & Toubro Energy Hydrocarbon (LTEH) has maintained a consistent foothold in the ranking, retaining the third spot for the second year running. It did so with a significantly elevated contract award value, however, at $6.9bn over the past four quarters, as compared to $2.4bn in the preceding period. 

LTEH bookings included two more contracts as part of phase two of Aramco’s development of its Jafurah unconventional gas field –  a $2.9bn contract for package one, a gas treatment facility, and a $1bn contract for package three, a gas compression plant. LTEH also secured a $1.2bn deal in Algeria for a hydrocracking unit as part of Sonatrach’s Skikda refinery expansion.

Italy’s Saipem has climbed to fourth place with $6.1bn of awards, where previously it came in seventh place with $1.3bn in awards. Its major contracts included the $4.5bn contract for phase two, scope B of the QatarEnergy LNG North Field Production Sustainability programme, and a $1bn contract for the Bouri gas utilisation project with Libya’s Mellitah Oil & Gas Company.

Spain’s Tecnicas Reunidas follows in fifth place, with contracts valued at $5.6bn, rising from ninth place in the previous period, when it secured $1.1bn in awards. The major contract wins in the current period included the $3.6bn contract for Abu Dhabi National Oil Company’s (Adnoc) Maximising Ethane Recovery and Monetisation (Meram) project in a 50:50 joint venture with the local NMDC Energy, formerly National Petroleum Construction Company. 

Tecnicas Reunidas also secured two contracts with Aramco for work on the Riyas natural gas liquids fractionation plant, which is part of the second expansion phase of Jafurah: a $2.2bn award for package two and a $1bn award for package one.

Rounding out the top 10

Italy’s Maire Tecnimont claims sixth place with contracts totalling $3.6bn, maintaining its presence in the top ranks with an increased award value, but still down from third position in the previous period, when the firm secured contracts worth $2.6bn. 

The contractor’s wins included a $1.3bn deal from a joint venture of QatarEnergy and US firm Chevron Phillips Chemical for the Ras Laffan petrochemicals project and several packages within Satorp’s Amiral complex, totalling $1.92bn. It also secured a $380m contract with Sonatrach for a liquefied petroleum gas extraction plant in Rhourde el-Bagel.

Lebanon’s Consolidated Contractors Company has meanwhile secured the seventh position with contracts valued at $3bn. This was led by its 30 per cent share of the $10bn contract for the QatarEnergy LNG North Field South development and a $400m deal for pipelines as part of Satorp’s Amiral project package 5B.

NMDC Energy has landed in eighth position with contracts worth just under $3bn. Its wins included a 50 per cent share of the $3.6bn contract for Adnoc’s Meram project, working alongside Tecnicas Reunidas, as well as a $614m contract for a pipeline as part of Adnoc’s Estidama project and a $600m contract from Saudi Aramco to lay a pipeline from Zuluf to Safaniya. 

The contractor’s position is nevertheless down from last year, when it ranked first with $4.9bn-worth of awards.

China Petroleum Engineering & Construction Corporation secured contracts totalling $2.4bn, earning it ninth place in this year’s ranking. Its wins included a $500m contract for Basra Oil Company’s West Qurna-1 oil field development and a $386m contract for Basra Energy Company’s Mishrif Qurainat oil field development.

UK-based Petrofac rounds off the top 10 with contracts valued at $1.7bn. Wins included a $1bn share of the $1.5bn contract for the Sonatrach Total Entreprise Polymeres joint venture’s propane dehydrogenation polypropylene plant in Arzew, Algeria, and a $700m award for a compressor plant at Habshan as part of Adnoc’s Estidama programme.

Several contractors that were present in last year’s ranking are noticeably absent from this year’s list. These include Japan’s JGC Corporation, which secured no new contracts in the period after posting in second place last year with $4bn in awards. 

US firm McDermott secured $1bn in contract awards this year after placing fourth in the ranking last year with $2.6bn in awards. South Korea’s Samsung Engineering meanwhile secured $1.3bn in awards, slightly up from $1.2bn in the previous period, but not enough to remain in the ranking this year.

Sector and country breakdown

The gas sector emerged as the most lucrative sector in the past four quarters, representing contract awards totalling $33.3bn. This was followed by the chemicals sector, which saw $23.3bn in contract awards, and the oil sector, which recorded $21bn.

In terms of the country of origin for contract awards over the past four quarters, Saudi Arabia led the way, representing awards totalling $23.4bn. This was followed closely by Qatar, with awards worth $20.6bn. 

Iran also witnessed contracts totalling $11.2bn, but this was split between several local contractors in such a way that it prevented any individual EPC contractor from making its mark at a regional level.

The UAE oil, gas and chemicals market meanwhile recorded $9.2bn in contract awards, with several contracts from Adnoc playing a key role in this year’s ranking. 

Algeria, Jordan and Iraq saw total contract awards values of $3.3bn, $3bn and $2.9bn, respectively. Other countries in the region accounted for a further $4bn-worth of EPC contract awards.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11318386/main.gif
John Bambridge
Related Articles
  • Oil prices rise above $100 a barrel as conflict escalates

    9 September 2026

    Register for MEED’s 14-day trial access 

    Oil prices rose above $100 a barrel on 9 September for the first time since July as the US-Iran conflict escalated and Iran-backed Houthi forces attacked Saudi energy infrastructure.

    Brent crude futures reached $100.95 a barrel, while US benchmark West Texas Intermediate (WTI) rose to $95.60. Brent had last traded above $100 on 24 July.

    The latest escalation has heightened concerns about oil supplies from the region, with shipping through both the Strait of Hormuz and the Red Sea facing disruption.

    Flows through the Strait of Hormuz had fallen below 2 million barrels a day (b/d) from about 8-9 million b/d before the latest escalation, according to Rystad Energy.

    At the same time, Houthi attacks on Saudi Arabia threaten another important route for oil exports, with the group targeting energy infrastructure and shipping in and around the Red Sea.

    US strikes on Iranian tankers

    US forces destroyed five Iranian crude oil carriers on 8 September after Iran’s Islamic Revolutionary Guard Corps (IRGC) targeted a US Navy warship with ballistic missiles.

    The US Central Command (Centcom) said the warship successfully evaded two Iranian attacks and that no US personnel were harmed.

    Four of the Iranian vessels – Kaviz, Charminar, Horizon 1 and Riesco – were struck in the Gulf of Oman, while the Derya was attacked near Kharg Island, Iran’s main crude export hub.

    The M/T Riesco subsequently sank in the Gulf of Oman, according to Centcom.

    Iran responded by launching ballistic missiles towards Jordan. Jordan’s armed forces said 18 of 20 missiles were intercepted, with the remaining two falling in unpopulated areas.

    Iran’s IRGC also said it had attacked two US naval vessels, eight oil tankers and 10 other vessels in the Gulf, although it did not identify the vessels or provide evidence of the attacks.

    The latest exchanges mark a further escalation in the US-Iran conflict, which began on 28 February.

    Houthi attacks raise supply concerns

    The conflict has also widened into a renewed confrontation between Saudi Arabia and Yemen’s Iran-backed Houthi movement.

    On 8 September, Saudi authorities said Houthi attacks had targeted civilian and economic sites in Abha, Khamis Mushait, Jazan and Najran in the south of the kingdom, injuring 73 people.

    Saudi Arabia’s Ministry of Energy said several energy sector facilities and installations had been targeted, causing fires and forcing a temporary halt to some operations.

    The Houthis said their attacks were in response to Saudi military action in Yemen, including what they described as attacks on Houthi positions and a Saudi blockade of ports and airports.

    Riyadh condemns attacks

    Saudi Arabia has strongly condemned the Houthi attacks and warned that it would take measures to defend its territory and national assets.

    In a statement on 8 September, the Ministry of Energy said authorities were working to address the impact of the attacks and ensure the safety of facilities and personnel while maintaining operations in accordance with approved plans.

    Saudi Arabia’s Ministry of Foreign Affairs also condemned the attacks and said the kingdom had the right to take measures to defend its sovereignty and protect its citizens, residents and national assets.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19505512/main0138.jpg
    Indrajit Sen
  • What actually slows a gigaproject down

    9 September 2026

     

    Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.

    “None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.

    For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.

    “The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.

    The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.

    “Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”

    Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.

    Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.

    Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.

    “The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”

    Integration needs to be well understood

    “Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.

    Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.

    Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.

    “The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”

    That shared view, he argues, will be what the next phase of Gulf delivery is judged on.

    Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.

    “This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.

    From reporting progress to managing risk before it lands

    Digital tools have a role here, Caldwell says, but not as a headline in themselves.

    Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.

    “The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."

    None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”

    Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.

    With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.

    “The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.

    What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.

    “The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif
    Yasir Iqbal
  • Qatari firm wins $221m Qiddiya stadium MEP deal

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Qatari contractor Elegancia MEP, part of Estithmar Holding, has won a SR829m ($221m) mechanical package contract for the Prince Mohammed Bin Salman Stadium in Qiddiya, Saudi Arabia.

    The contract covers full mechanical, electrical and plumbing (MEP) works for the stadium, and is Elegancia MEP’s largest award in Saudi Arabia to date.

    The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.

    The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.

    Saudi gigaproject developer Qiddiya Investment Company awarded an estimated SR15bn ($4bn) deal to build the stadium in October 2024, as MEED exclusively reported.

    The contract covered the construction of a multipurpose stadium on top of the 200-metre-high Tuwaiq cliff in the new sports and entertainment district of Qiddiya City.

    Once completed, the stadium will be the home ground for Saudi Pro League football clubs Al-Nassr and Al-Hilal.

    US-based architect Populous is the project consultant.

    The stadium is one of the venues for the kingdom’s 2034 Fifa World Cup bid and will host events such as the Saudi King Cup, the Asian Cup and the 2034 Asian Games.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19501493/main.jpg
    Yasir Iqbal
  • Jordan tenders advisory for wastewater treatment plant

    9 September 2026

    The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.

    The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).

    The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.

    The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.

    The submission deadline is 21 September.

    The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.

    The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.

    The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.

    WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.

    The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.

    The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg
    Mark Dowdall
  • Consultants bid for Abu Dhabi light rail project management

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.

    The notice was issued on 7 September, with a submission deadline of 9 November.

    The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.

    The key sections of the tram are:

    AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.

    This section covers 13km and includes 13 at-grade stations and one underground station.

    Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.

    Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.

    The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.

    The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.

    Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.

    Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.

    Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.

    The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19493532/main.jpg
    Yasir Iqbal