Taziz awards $1.99bn contract for chemical plants complex

5 November 2025

Register for MEED’s 14-day trial access 

Abu Dhabi’s Taziz has awarded the main engineering, procurement and construction (EPC) contract to build a complex of specialty chemical plants in the Taziz Industrial Chemicals Zone at Ruwais Industrial City.

China National Chemical Engineering & Construction Corporation Seven (CC7) has won the EPC contract, valued at $1.99bn, to build the chemicals cluster known as Project Salt.

In late September, MEED reported that CC7 was the frontrunner to win the EPC contract for Project Salt.

The facility will produce 1.9 million tonnes a year of marketable polyvinyl chloride (PVC), ethylene dichloride (EDC), vinyl chloride monomer (VCM) and caustic soda.

EPC works on the project are expected to be completed by Q4 2028.

The contract award was announced at the Abu Dhabi International Petroleum Exhibition and Conference (Adipec), taking place from 3 to 6 November in Abu Dhabi.

Project Salt’s contract award “marks a major step forward in delivering Taziz’s strategic mandate to drive industrial growth, localise supply chains, and enable new value chains in the UAE”, Taziz said in a statement.

“These chemicals are critical to serving growing demand in sectors such as construction, infrastructure, packaging and healthcare, both in the UAE and internationally,” it added.

Project Salt tendering phase

South Korean contractor Samsung E&A was understood to be the only other bidder for Project Salt.

MEED previously reported that contractors had submitted technical bids for EPC works on Project Salt by the deadline of 15 July.

Adnoc received commercial bids from contractors for Project Salt by the deadline of 15 August, according to sources.

Adnoc had initially set deadlines of 15 June and 23 July for contractors to submit technical and commercial bids for the project, respectively.

Taziz first announced the EDC, chlor alkali and PVC plants in December 2021. India’s Reliance Industries was named as the main investor in the chemicals plants at the time.

Reliance is understood to have pulled out of Project Salt and has been replaced by France-based Kem One, MEED previously reported.

MEED reported in June last year on the award of front-end engineering and design (feed) contracts for the three chemicals production plants.

Germany-headquartered Thyssenkrupp Uhde won feed contracts for the EDC and chlor alkali plants, while France-based Technip Energies won the deal for the PVC facility.

The planned EDC plant will utilise chlorine from the associated chlor alkali plant as its main feedstock and will have a production capacity of up to 1.2 million tonnes a year (t/y).

Part of the EDC output will, in turn, be used as feedstock by the PVC plant, which is planned to have a production capacity of 350,000 t/y.

Surplus quantities of EDC and caustic soda from the chlor alkali plant are intended to be exported.

Taziz chemicals zone

Since 2021, Taziz has attracted investments from several foreign investors for its planned chemicals projects in the under-construction Taziz Industrial Chemicals Zone in Ruwais.

Taziz has planned seven chemicals derivatives projects as part of the first phase of its zone.

UK-headquartered Wood Group has performed the feed works on the seven projects, which are:

Anchor product

End use

Chlor alkali

Water treatment, metallurgy and textiles

Ethylene dichloride

Housing, infrastructure and consumer goods

Maleic anhydride

Piping, construction and heavy transport

Methanol

Energy, consumer goods and pharmaceuticals

Blue ammonia

Agriculture, apparel and energy

Isopropyl alcohol

Healthcare and cosmetics

Elastomers

Automobiles, adhesives, food production and storage

Chemicals production is a priority sector for Operation 300bn, the UAE’s industrial growth strategy.

The strategy is being overseen by the Industry & Advanced Technology Ministry, which aims to raise the UAE industrial sector’s contribution to the national GDP to AED300bn ($81.7bn) by 2031.

In December 2021, Taziz secured agreements from eight UAE-based entities for investments in its planned chemicals projects in Ruwais. The agreements marked the first domestic public-private partnership in Abu Dhabi’s downstream oil, gas and petrochemicals sector.

ALSO READ: Local firms invest in Taziz industrial complex

In addition to the three chemicals plants planned under Project Salt, a joint venture of UAE-based Fertiglobe, South Korea’s GS Energy Corporation and Japanese investment firm Mitsui & Company has invested in a “world-scale” blue ammonia production facility in the Ruwais petrochemicals derivatives complex.

The Fertiglobe/GS Energy/Mitsui joint venture awarded Italian contractor Tecnimont the EPC contract for the project in May 2024. Construction on the facility started in June last year.

Separately, in February, Taziz awarded Samsung E&A the main EPC contract to build the UAE’s first methanol plant in the Taziz Industrial Chemicals Zone. The value of the EPC contract is $1.7bn and the duration of works is 44 months.

The nameplate production capacity of the planned methanol complex is 5,000 metric tonnes a day, or 1.8 million metric t/y. Switzerland-based energy and chemicals company Proman is a joint investor in the project.

Supporting infrastructure

Regarding infrastructure to support the various projects, Taziz awarded three EPC contracts totalling $2bn in November.

Abu Dhabi government-owned NMDC Group was awarded the EPC contract to build a chemicals port. Once complete, the port will facilitate the export of chemicals and fuels.

Singapore-based Rotary Engineering won the EPC contract for a chemicals terminal known as Project Landing. The contract includes developing storage facilities, tank-to-jetty pipelines, jetty-to-tank pipelines, inter-site pipelines and liquid product storage. Taziz is building the chemicals-handling terminal in partnership with Netherlands-based midstream energy company Advario.

Abu Dhabi-based Al-Geemi Contracting was awarded the EPC contract to develop essential infrastructure for the 17-square-kilometre Taziz chemicals production site, including internal roads, security fencing and buildings.

Contracts have also been awarded for the development of a centralised utilities facility for the Taziz Industrial Chemicals Zone, which will include power transmission, steam, cooling water and water units.

Adnoc signed an agreement with Abu Dhabi National Energy Company (Taqa) in June 2021 to develop a cogeneration power facility in Ruwais. In December, the partners awarded a $1bn contract to Kuwait-based Alghanim International for the project, and the contractor started construction of the facility in February this year.

Alghanim International, in turn, awarded a $67m sub-contract to Riyadh-based water utility developer Water & Environment Technologies Company (Wetico) for the comprehensive water facilities package of the cogeneration power facility, which includes the construction of a seawater desalination plant, demineralisation plant, condensate polishing unit and effluent treatment plant.

ALSO READ: Fertiglobe delays final investment decision on Project Rabdan

https://image.digitalinsightresearch.in/uploads/NewsArticle/15023358/main2813.jpeg
Indrajit Sen
Related Articles
  • UAE company wins Muscat cultural complex deal

    28 January 2026

    UAE-based steel structure manufacturer Emirates Building Systems, a wholly owned subsidiary of Dubai Investments, has won a contract to deliver the complete structural steel package for Sayyid Tarik Bin Taimur Cultural Complex in Oman.

    The scope of works covers the structural steel works, including detailed engineering, specialised fabrication, on-site erection and advanced fireproofing.

    The package also includes complex long-span steel components for theatre halls, public atria and other spaces.

    The complex will comprise three buildings and is located next to the Labour Ministry, to the south of Sultan Qaboos Highway and opposite the Muscat International airport development.

    The buildings will include a national library large enough to hold 5 million volumes; the national archives, which will act as a four-storey exhibition and public event area and a research and administration wing; and the national theatre, which will accommodate more than 1,000 people.

    There will also be four smaller buildings for a children’s library, a cinema, a gallery and workshop, literary society headquarters and a lecture hall and retail areas.

    The total built-up area will be about 73,000 square metres (sq m) and the project’s land area is 400,000 sq m.

    In October 2023, Oman’s Culture, Sports & Youth Ministry awarded a design-and-build construction contract for the cultural complex to a joint venture of the local Saif Salim Issa Al-Harrasi and Turkiye's Sembol Construction, MEED reported.


    READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds

    Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:

    > ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15527017/main.jpeg
    Yasir Iqbal
  • Adnoc allows extra time for Umm Shaif gas cap project prices

    28 January 2026

     

    The offshore oil and gas business of Abu Dhabi National Oil Company (Adnoc Offshore) has allowed contractors extra time to prepare commercial bids for a project to increase gas and condensate production from the Umm Shaif hydrocarbons field.

    The primary objective of Adnoc Offshore’s Umm Shaif gas cap and surface pressure boosting project is to increase gas production by 550 million cubic feet a day (cf/d) and raise associated condensate output by 50 million barrels a day (b/d).

    Adnoc Offshore intends to feed about 520 million cf/d of the additional produced gas volumes into the sales gas grid of its parent company, Adnoc Group.

    Contractors now have until 2 February to submit commercial bids for the project, according to sources. The previous deadlines for the submission of prices were 26 January and 5 January.

    Adnoc Offshore has divided the engineering, procurement and construction (EPC) scope of the project’s first phase into three packages. The broad scopes of the two offshore packages and one onshore package are as follows:

    • Offshore package 1 – fabrication of a 30,000-tonne gas compression system
    • Offshore package 2 – fabrication of a 30,000-tonne gas compression system
    • Onshore package – EPC of gas inlet and processing systems on Das Island

    Contractors submitted technical bids for the three EPC packages of the Umm Shaif gas cap and surface pressure boosting project by the deadline of 30 October.

    The previous technical bid submission deadlines were 31 July, 1 September and 10 October, MEED previously reported.

    The following contractors are among those that are understood to be bidding for the three EPC packages of the project:

    Offshore package 1:

    • Saipem (Italy) / Seatrium (Singapore)
    • Larsen & Toubro Energy Hydrocarbon (India) / Lamprell (Saudi Arabia/UAE)
    • NMDC Energy (UAE) / Hyundai Heavy Industries (South Korea)

    Offshore package 2:

    • China Offshore Oil Engineering Company (COOEC)
    • McDermott (US)
    • Larsen & Toubro Energy Hydrocarbon (India) / Lamprell (Saudi Arabia/UAE)
    • NMDC Energy (UAE) / Hyundai Heavy Industries (South Korea)

    Onshore package:

    • Archirodon (Greece)
    • China Petroleum Engineering & Construction Company (CPECC)
    • Engineering for the Petroleum & Process Industries (Enppi; Egypt)
    • Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
    • Target Engineering Construction Company (UAE)

    Adnoc Offshore is understood to have issued the main EPC tender for the Umm Shaif gas cap and surface pressure boosting project in the first quarter of 2025.

    Australian firm Worley has performed front-end engineering and design (feed) work on the project.

    Umm Shaif gas production

    Adnoc Offshore operates the Umm Shaif hydrocarbons development, which is located 150 kilometres (km) northwest of the city of Abu Dhabi. The field is located in Abu Dhabi’s offshore Umm Shaif and Nasr hydrocarbons concession, previously operated by former Adnoc Group companies Adma-Opco and Zadco.

    Between March and April 2018, Adnoc awarded a 10% stake in the Umm Shaif and Nasr offshore block to Italy’s Eni, 20% to France’s TotalEnergies and 10% to China National Petroleum Corporation. Adnoc Group retained the majority 60% interest. The operators produce a total of about 460,000 b/d of oil from the Umm Shaif and Nasr block.

    Gas is produced from the Umm Shaif Khuff and Uweinat reservoirs, as well as from the Arab C and Arab D Early Production Scheme 2. The Umm Shaif Khuff reservoir is a formation that consists of dry gas volumetric reservoirs located in the Umm Shaif field.

    Khuff reservoirs have been in production in Abu Dhabi since August 1989. Umm Shaif Khuff gas is currently produced from 28 active wells within the Umm Shaif field. A majority of these wells supply gas to Adnoc Group subsidiaries Adnoc LNG and Adnoc Gas Processing, with the rest supporting oil reservoirs at the Umm Shaif field through gas injection.

    The Umm Shaif Super Complex (USSC) processes and transports oil, condensates and natural gas in separate pipelines to Das Island for further processing and export. The condensates collected from the USSC are transported to Das Island through an 18-inch pipeline stretching 34.4km, or are spiked into the 36-inch Adnoc main oil line.

    The gas collected from the USSC is transported to Das Island through two 46-inch pipelines, which also run 34.4km.

    Pressure at the Umm Shaif Khuff gas reservoirs will start to decline by the end of 2028. The flowing wellhead pressures at some of the Khuff gas wellhead towers are likely to reduce, so boosting well deliverability and increasing the flowrates is necessary.

    Therefore, new Khuff surface pressure boosting facilities are required to maintain the plateau – with a goal of achieving a 90% gas recovery factor – and increase production beyond the end of the plateau by lowering pressure at the Khuff reservoirs.

    Project tendering exercise

    Adnoc Offshore has been making attempts to advance the Umm Shaif gas cap project since at least 2019, and has experimented with several project execution models.

    According to the original schedule, the project was due to be commissioned in 2023, but progress slowed down, primarily due to the Covid-19 pandemic.

    Adnoc Offshore launched a feed-to-engineering, procurement, construction and installation (EPCI) competition for the project in May 2019 and selected the following three entities based on their feed submissions:

    • McDermott (US)
    • National Petroleum Construction Company (UAE) / TechnipFMC (France)
    • Saipem (Italy) / Petrofac (UK)

    Technical bids for the EPCI works on the estimated $1.5bn project were submitted in January 2020 and commercial bids were submitted by August of that year.

    The Saipem/Petrofac consortium emerged as the lowest bidder for the project in September 2020, MEED reported.

    Petrofac is understood to have eventually pulled out of the consortium and was replaced by state-owned China Petroleum Engineering & Construction Company (CPECC).

    In 2022, the Saipem/CPECC consortium is understood to have been the lone bidder remaining on the Umm Shaif gas cap project. Adnoc Offshore engaged the consortium for a revised feed exercise, and went on to receive commercial offers on a single-source basis.

    In 2023, Adnoc Offshore cancelled the tendering process for the project and later decided to proceed with a conventional EPC-based project execution model.

    Last year, the operator appointed Worley to undertake feed works on the renewed Umm Shaif gas cap project. Worley has a legacy of involvement in the Umm Shaif hydrocarbons development.


    READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds

    Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:

    > ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15526816/main.jpg
    Indrajit Sen
  • Kuwait receives bids for Shagaya solar plant

    28 January 2026

     

    Three consortiums have submitted bids for a contract to develop Kuwait's first utility-scale solar photovoltaic (PV) plant.

    The Al-Dibdibah power and Al-Shagaya renewable energy phase three, zone one independent power project (IPP) will have a total power generating capacity of 1,100MW.

    It is being prcoured by Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEWRE), through the Kuwait Authority for Partnership Projects (Kapp), which issued the request for proposals in June 2025.

    The three bidding consortiums are:

    • Acwa Power (Saudi Arabia) / Alternative Energy Projects Company (Kuwait)
    • EDF Renewables (France) / Abdulla Al-Hamad Al-Sagar & Bros (Kuwait) / Korea Western Power Company (South Korea)
    • Abu Dhabi Future Energy Company (Masdar, UAE) / Fouad AlGhanim & Sons (Kuwait)

    Kapp issued the request for qualifications for the contract in January 2024, with six prequalified companies and consortiums announced that August. 

    The request for proposals was issued in June 2025 with an initial deadline of 14 September.

    Bidding for the project closed on 15 January following a deadline extension.

    The selected developer will sign a 30-year power purchase agreement with the MEWRE to export its electricity output. The contract also calls for the construction of an associated 400kV transmission substation. 

    London-headquartered consultancy firm EY is the lead and financial transaction adviser. The UK's DLA Piper is the legal adviser, while Norwegian engineering services firm DNV is the client’s technical and environmental adviser.

    2030-50 strategy

    Kuwait aims to have a renewable energy installed capacity of 22,100MW by 2030 as part of the 20-year strategy announced in March 2025 and ending in 2050.

    In September last year, Kapp opened bidding for its Al-Dibdibah power and Al-Shagaya renewable energy phase three, zone two IPP, which will have a capacity of 500MW. 

    The main contract bid submission deadline is 16 February.

    The selected developer or developer consortium will design, finance, construct and maintain the project.

    In October, MEED reported that the following consortiums and companies had prequalified to bid for the contract:

    • Acwa Power (Saudi Arabia) / Arabian Engineering Projects Contracting Company (Kuwait)
    • EDF Renewables (France) / Al-Kharafi & Sons (Kuwait) / Korea Western Power Company 
    • Masdar (UAE) / Al-Ghanim International (Kuwait)
    • Jinko Power (China) / Combined Group Contracting (Kuwait)
    • Swift Current Energy (US) / Arizona National (Kuwait)
    • Limak (Turkiye)
    • Kalyon Enerji (Turkiye)
    • TotalEnergies (France)
    • TCL Zhonghuan (China)
    • Sinotec (China)

    The zone two scheme is the fourth renewable energy project to be developed under Kuwait’s public-private partnership programme.

    Similar to the 1,100MW zone one project, EY and DLA Piper, together with DNV, are advising the client on the zone two solar IPP.


    READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds

    Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:

    > ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15526799/main.jpg
    Mark Dowdall
  • New Murabba approaches contractors for Mukaab towers

    28 January 2026

     

    Saudi Arabia's New Murabba Development Company (NMDC), a wholly owned subsidiary of sovereign wealth vehicle the Public Investment Fund, has issued a request for information notice to test the market for modular and offsite fit-out solutions for its Mukaab development.

    The notice was issued on 26 January with a submission deadline of 11 February.

    NMDC has scheduled a market engagement meeting with prospective companies in the first week of February to discuss the solutions further.

    "NMDC is seeking experienced suppliers and contractors to advise on the feasibility, constraints and execution strategy for using non-load-bearing modular systems for the four corner towers encompassing the Mukaab structure," sources directly associated with the project told MEED.

    "The feedback will be incorporated to shape later design and procurement decisions," the sources added.

    The towers will frame the Mukaab and are an integral part of the structure. There will be North and South towers, marked for residential use, and mixed-use East and West towers.

    The towers will be about 375 metres tall and more than 80 storeys high. 

    The core modular elements under consideration include bathroom pods, kitchen pods, dressing room modules, panelised steel partition systems and other offsite manufactured fit-out solutions.

    The Najdi-inspired Mukaab building – the name of which is the Arabic word for cube – will be the centrepiece of New Murabba. Measuring 400 metres in height, width and length, the building will rank among the largest structures ever constructed.

    The early works on the Mukaab were completed last year, and the client was preparing to award the estimated $1bn contract for the main raft works on the structure, according to a presentation delivered by NMDC's chief project delivery officer on 9 September at the Future Projects Forum in Riyadh.

    Project agreements

    Earlier in January, US-based engineering firm Parsons Corporation was awarded a contract by NMDC to provide design and construction technical support.

    Parsons will serve as the lead design consultant for infrastructure, delivering design and engineering services covering infrastructure, public buildings, landscaping and the public realm at the New Murabba development. 

    Parsons will also support the creation of the project’s downtown experience, spanning 14 million square metres of residential, workplace and entertainment space.

    The latest deal with Parsons follows NMDC’s signing in October last year of agreements with three other US-based engineering firms to undertake design work on assets at New Murabba.

    NMDC signed an agreement with New York-headquartered firm Kohn Pedersen Fox to lead early design work for the first residential community within the New Murabba development.

    The other agreements were signed with Aecom and Jacobs, both of which were appointed lead design consultants for the Mukaab district.

    In August last year, NMDC signed a memorandum of understanding with another US-based firm, Falcons Creative Group, to develop the creative vision and immersive experiences for the Mukaab project.

    Beijing-headquartered China Harbour Engineering Company completed the Mukaab excavation works.

    The foundation works for the Mukaab were executed by UAE-headquartered HSSG Foundation Contracting.


    READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds

    Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:

    > ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15526521/main.jpg
    Yasir Iqbal
  • Dubai announces $27bn DIFC expansion

    28 January 2026

    Sheikh Mohammed Bin Rashid Al-Maktoum, Ruler of Dubai and Vice President and Prime Minister of the UAE, has announced a AED100bn ($27bn) expansion of Dubai International Financial Centre (DIFC) through the creation of the DIFC Zabeel District.

    According to a statement from the Government of Dubai Media Office, the DIFC Zabeel District will add over 7 million square feet (sq ft), with a total gross floor area of 17.7 million sq ft.

    The new district is expected to more than double DIFC’s capacity to over 42,000 businesses, support a workforce exceeding 125,000 and allocate more than 1 million sq ft for future technologies and artificial intelligence (AI).

    Planned in six phases, the expansion is scheduled to open to the public in 2030, with the masterplan due for completion in 2040.

    Cnstruction works on the first phase are already under way.

    The project will include an innovation hub of more than 1 million sq ft, featuring an AI campus designed to support more than 6,000 businesses and 30,000 technology specialists.

    It will also house a gaming hub, aimed at positioning Dubai as a leader in next-generation gaming, simulation and digital content creation.

    Aligned with Dubai’s Education 33 (E33) strategy, the DIFC expansion will also seek to attract top universities, becoming an international destination for higher education.

    The DIFC Academy is also set to expand 10-fold, to 370,000 sq ft.

    In addition, the expansion will introduce an art pavilion, strengthening DIFC’s cultural footprint, alongside a mix of commercial and residential spaces centred around a main boulevard.

    The masterplan also includes conference facilities, hotels and retail outlets.

    The DIFC Zabeel District will be linked to the existing DIFC Gate District by a bridge.


    READ THE JANUARY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia courts real estate investment; EVs and battery production are key regional tech themes; Muscat holds a steady growth course despite headwinds

    Distributed to senior decision-makers in the region and around the world, the January 2026 edition of MEED Business Review includes:

    > ECONOMIC ACTIVITY INDEX: UAE and Qatar emerge as markets to watch
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15525807/main.gif
    Yasir Iqbal