Syria makes progress towards reunification

24 April 2025

 

Following the ousting of Bashar Al-Assad in late 2024, President Ahmed Al-Sharaa has rapidly consolidated power in Syria. He has transitioned from a militant and political outsider into a credible leader increasingly recognised in the region and on the world stage.

Within Syria, Al-Sharaa faces political, economic, military and civil challenges in pulling the country back together again. In recent weeks, a prominent focus has been the reunification of Syria’s fractured security landscape through the negotiated dissolution and integration of smaller rebel factions into a centralised military structure under the Ministry of Defence.

Rebel disbandment

Most recently, the new government brokered the dissolution of the Eighth Brigade, a 3,000-strong rebel group based in the southern city of Daraa that had waged an insurgency against the government of Bashar Al-Assad since 2018.

That outcome proved a relief to the government after its trustworthiness in talks was thrown into doubt by the chaos that erupted in Syria’s coastal region on 6 March as Islamist groups committed massacres against Alawite civilians in revenge over attacks by Assad loyalists.

On 9 March, Al-Sharaa appointed a committee to report on the violence, determine its perpetrators and theoretically hold them to account. That move caused some murmurings within his own ranks, but externally it showed the president’s commitment, in principle, to justice.

It also appeared to serve the political imperatives of the moment. Just a day later, on 10 March, the reassured Kurdish- led Syrian Democratic Forces (SDF) – representing tens of thousands of trained soldiers – signed a deal to integrate its forces into the national army.

The deal marked perhaps the most significant step towards national reunification so far, promising to restore to government control a swathe of northeastern Syria and its oil fields that has been largely lost to Damascus since the 2014 invasion by the Islamic State.

The integration of the SDF into the national military also appears to have been accepted by the US, which had been supporting the SDF military as an independent force in the northeast of the country, but has now announced the planned staggered withdrawal of its stationed troops.

Al-Sharaa has been making his rounds of the region in a diplomatic blitz aimed at shoring up regional support for his new government

Broader priorities

Alongside reconsolidating and restructuring the country’s military and security apparatus, Al-Sharaa’s main priorities are foreign affairs and economic policy. These two areas go hand in hand, given that removing international sanctions is key to reviving Syria’s economy.

In late March, Al-Sharaa entrenched his authority by enacting a new constitutional declaration, announcing a new transitional government and granting himself sweeping executive powers, including the right to appoint a third of the legislature and select judges for the constitutional court.

The cabinet was also broadened and reshuffled to address concerns over the lack of representation from minority communities. Individuals from the Alawite, Druze and Christian communities, as well as one woman, were appointed to ministerial positions.

The move further witnessed the replacement of the formerly appointed justice minister Shadi Al-Waisi, whose elevation embarrassed the government after 2015 videos surfaced of him presiding over street executions by morality police as part of the then Nusra Front. His removal was another reassuring step for observers that the government is attuned and reactive to constructive criticism.

With the right signals sent, Al-Sharaa has been making his rounds of the region in a diplomatic blitz aimed at shoring up regional support for his new government. He is likely also aiming to put the right words in the right ears, in the hope that they filter through the Gulf’s power lobbying system to the US.

Already on 30 January, just a day after Al-Sharaa became president, Qatar’s Emir Sheikh Tamim Bin Hamad Al-Thani flew to greet the man who displaced Al-Assad – a goal also long pursued by Doha. On 2 February, Al-Sharaa then took his first trip abroad to meet Saudi Crown Prince Mohammed bin Salman.

Some other regional governments have been more reticent to launch into renewed relations, but have increasingly come on board.

This includes Iraq, which, hesitant over Al-Sharaa’s past militant activity against Baghdad, only arranged a meeting between the Syrian president and Prime Minister Mohammed Shia Al-Sudani on 17 April in Doha – ultimately driven by shared security imperatives. Al-Sudani also invited Al-Sharaa to attend the upcoming Arab summit in Baghdad in May.

On 14 April, the equally green Lebanese Prime Minister Nawaf Salam also met with Al-Sharaa in Damascus – no doubt keen to address the recent border clashes between the two countries. A day earlier, Al-Sharaa was in Abu Dhabi to meet Sheikh Mohamed Bin Zayed Al-Nahyan, rounding out his visits to the key power brokers and budget holders in the Gulf.

Between all of these meetings, Al-Sharaa appears to have ingratiated himself with the region’s other leaders with remarkable rapidity and ease. A year after the Arab League reaccepted him in May 2023, Al-Assad had made little comparable progress.

For world leaders weary from years of dithering by Al-Assad’s government, which was unable or unwilling to even acquiesce to the Gulf’s most basic request – to stem the flow of the drug captagon from within Syria’s borders – Al-Sharaa is at least a partner who can do that and achieve far more besides. 

For years, it has been the case that a reunified Syria and a rebuilt Syrian economy would lift the entire Levant region and any Gulf investors with it. The appetite in the region to see it succeed has been there. All that has been missing is a suitable partner in Damascus to move forward with.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13747658/main.gif
John Bambridge
Related Articles
  • Kuwait awards $381m oil project

    23 September 2026

    Register for MEED’s 14-day trial access 

    State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).

    The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.

    The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.

    The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.

    The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.

    Meil will develop the new three-phase low-pressure wet separation facility at GC-25.

    The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.

    The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.

    Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.

    The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.

    At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.

    The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.

    Booster and injection pumps will transfer treated effluent water to designated injection wells.

    Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.

    The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.

    Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.

    Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.

    The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.

    Seven companies submitted bids for the project last November.

    The full list of bids was:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.

    Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg
    Wil Crisp
  • Kuwait refinery project on track for year-end completion

    23 September 2026

     

    A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.

    The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.

    One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).

    Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.

    The scope of the project includes:

    • Construction of a substation
    • Installation of transformers
    • Installation of medium-voltage switchgear
    • Installation of low-voltage auxiliary systems
    • Installation of network protection systems
    • Installation of disconnecting switches
    • Installation of surge arrestors
    • Installation of feeder breakers and cubicles
    • Installation of low-voltage A/C and D/C equipment
    • Installation of battery banks and battery chargers
    • Installation of related relay and control panel boards
    • Installation of fire alarm and fire protection equipment
    • Installation of a SCADA system
    • Installation of cables
    • Civil works
    • Associated facilities

    The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.

    On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.

    The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.

    Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.

    He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.

    Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg
    Wil Crisp
  • Contractor wins $208m Almoosa hospital MEP contract

    23 September 2026

    Register for MEED’s 14-day trial access 

    Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.

    Saudi Arabia’s Almoosa Health Company awarded the contract.

    The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.

    It will be built on a 45,000-square-metre site.

    A podium spanning the ninth and 10th floors will connect the two towers.

    The hospital will also include parking for 1,700 cars.

    BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.

    In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.

    In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.

    Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg
    Yasir Iqbal
  • UAE to develop integrated waste-to-resource pilot

    23 September 2026

    Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.

    The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.

    Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.

    Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.

    The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.

    A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.

    Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.

    The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.

    If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.

    The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg
    Mark Dowdall
  • Contractors prepare Oxagon Highway 55 bids

    23 September 2026

     

    Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.

    The project duration is 22 months.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
    Yasir Iqbal