SWPC focuses on desalination and sewage plants

30 September 2024

 

The latest seven-year statement of Saudi Water Partnership Company (SWPC), the kingdom’s main water offtaker, has significantly fewer projects compared to the previous statement covering the years 2022-28.

MEED understands the streamlined projects pipeline is due in part to SWPC now splitting the responsibility to procure water transmission pipeline and reservoir projects in particular with the Water Transmission & Technologies Company (WTTCO), and Saudi Water Authority (SWA) having resumed the tendering of major water desalination projects.

Ouf of 50 projects in five sub-sectors in the previous capacity procurement plan, the latest statement specifies over a dozen future projects, in addition to about six that are in the tendering process and several others that were awarded during the intervening period.

Of the four or five sub-sectors, the independent water projects (IWPs) appear less susceptible to the changes, with SWPC’s Seven-Year Statement covering the years 2024-30 indicating procurement plans for seven IWPs, consistent with the previous statement’s capacity procurement plan.

These schemes have a total combined capacity of about 2.75 million cubic metres a day (cm/d) and are expected to reach commercial operations between 2028 and 2032.

This is in addition to two projects in the bid evaluation stage: the 300,000 cm/d Ras Mohaisen IWP and the 600,000 cm/d Jubail 4 and 6 projects.

“Our goal is to achieve 100% private-sector participation in the production of desalinated water by 2030,” the statement quoted Khaled AlQureshi, SWPC chief executive, as saying.

A similar number of independent sewage treatment plant (ISTP) projects – seven in total – are included in SWPC’s latest seven-year statement, which is down by six compared to the previous plan, and inclusive of the Al-Haer ISTP project, which has since been awarded.

The total planned treated sewage capacity is about 370,000 cm/d, exclusive of the yet-to-be-announced capacity for the Arar ISTP project. These sewage treatment plants are expected to come online between 2027 and 2029.

A plan to procure small sewage treatment plants remains, but the latest SWPC Seven-Year Statement is silent on which of the planned seven clusters it will implement or procure.

The latest statement is equally silent on future independent water transmission pipeline (IWTP) projects, apart from the one that is under construction and two that are in the bidding stage.

The $2bn Rayis-Rabigh IWTP is under construction, bid evaluation is under way for the Jubail-Buraydah IWTP, while SWPC expects to receive bids in February next year for the Riyadh-Qassim IWTP project.

From a pipeline of 14 independent strategic water reservoir (ISWR) projects two years earlier, inclusive of the under-construction Juranah ISWR, the Seven-Year Statement mentions only three future IWTP projects, including one in Al-Ahsa, which has a capacity of 1.39 million cubic metres, and the Dammam ISWR with a capacity of 3.13 million cubic metres.

According to an industry expert, the drive to improve energy efficiency, reuse treated water and improve storage capacity, while keeping up with increasing demand, implies that the kingdom needs to tap both public-private partnerships (PPPs) and engineering, procurement and construction (EPC) models for additional water capacity in the future.

Sharing responsibilities

MEED reported in March that the responsibility for procuring several water transmission pipeline projects in Saudi Arabia had been transferred from SWPC to WTTCO, a spin-off of the Saline Water Conversion Company, which is now called SWA.

Formed in 2019, WTTCO is responsible for "managing, operating and maintaining water transmission, storage and dispatch systems across the kingdom".

It was reported that the procurement model for the following water transmission pipeline projects has also shifted from build-operate-transfer to EPC:

  • Jizan-Al Shuqaiq
  • Tabuk-Ula
  • Rabigh-Jeddah
  • Ras Al Kahir-Hafar
IWP and ISTP focus

SWPC announced in May the start of the prequalification process for companies keen to participate in developing five desalination IWPs and seven ISTP projects in the kingdom.

Developers and investors expressed interest in bidding for the projects last July. SWPC also requested that companies submit separate expressions of interest for the IWPs and ISTP projects. 

The programme "will provide local and international developers the opportunity to obtain prequalification approval and receive the request for proposal documents for its future projects ... without the need to submit a separate qualification application for each project".

The five IWPs have a total combined capacity of 1.7 million cm/d. The seven ISTP projects have a total combined capacity of 700,000 cm/d.

The tenders for these projects are expected to launch between 2024 and 2026.

In June, MEED reported that SWPC is in the process of appointing a transaction advisory team for this batch of IWP and ISTP projects.

Restructuring

The kingdom's water sector has been undergoing a restructuring programme, with the capacity procurement process linked to the 2030 National Water Strategy being undertaken by three other clients: SWA, WTTCO and the National Water Company.

SWA, for its part, has received bids in the past few months for EPC contracts for four reverse osmosis technology-based water desalination plants, which have a total combined capacity of about 2 million cm/d. The contract to design and build one of the four projects, the 300,000 cm/d Yanbu seawater reverse osmosis plant, was awarded earlier in September.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12624812/main.gif
Jennifer Aguinaldo
Related Articles
  • Chinese and Saudi partners set up Hithium Manat

    17 October 2024

    Register for MEED's 14-day trial access 

    Chinese energy storage solutions firm Hithium Energy Storage Technology Company (Hithium) and the local Nabilah AlTunisi have formed a joint venture that will manufacture battery energy storage systems (bess) in Saudi Arabia.

    The joint venture is called Hithium Manat. The planned manufacturing facility has an annual production capacity target of 5 gigawatt-hours (GWh), according to an official statement.

    Hithium launched energy storage solutions designed for the region's harsh environment during a solar and storage conference held in Riyadh.

    According to Hithium, "These systems feature advanced sandstorm protection and robust high and low-temperature designs, supporting ultra-long discharge cycles of 12+ hours."

    It added that the new product line is "customised to meet the unique demands of the Middle East and Africa region".

    Nabilah AlTunisi is the founder and owner of Hithium Manat's local partner.

    "This strategic alliance will not only provide access to world-class energy storage technology but also generate local employment opportunities, stimulate technological innovation and actively contribute to realising the kingdom's Vision 2030 objectives," AlTunisi said.

    Battery energy storage market

    In August, National Grid Saudi Arabia, a subsidiary of state utility Saudi Electricity Company, awarded the engineering, procurement and construction (EPC) contracts for three energy storage systems to Riyadh-based investment group Algihaz Holding. The estimated $800m projects are located in Najran, Madaya and Khamis Mushait.

    National Grid also recently tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW across the kingdom.

    The planned facilities, each with a capacity of 500MW or roughly 2,000 megawatt-hours, are located in or within proximity of the following key cities and load centres:

    • Riyadh
    • Qaisumah
    • Dawadmi
    • Al-Jouf
    • Rabigh

    Every utility in the region is procuring or planning to procure bess capacity in light of growing intermittent renewable power in their grids. 

    The overall capacity of deployed bess globally is expected to reach 127GW by 2027, up from an estimated cumulative deployment of 36.7GW at the end of 2023, a GlobalData report issued in June said.

    The report cited Chinese companies BYD and CATL and South Korean companies LG Energy Solutions and Samsung SDI among the top battery technology providers globally.

    Related read: Battery storage gains foothold

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12742375/main.jpg
    Jennifer Aguinaldo
  • Kahramaa invites Ras Laffan substation bids

    17 October 2024

    Qatar state utility General Electricity & Water Corporation (Kahramaa) has tendered a contract to upgrade the Ras Laffan C substation.

    The scope of work covers the upgrade of existing 220-kilovolt (kV) and 400kV substations and the addition of 220kV gas-insulated switchgear bays and an 800-megavolt amps transformer.

    Kahramaa issued the tender on 15 October and expects to receive bids by 28 November.

    The project bid bond is valued at QR1.5m ($410,000).

    Separately, Kahramaa invited firms to submit their proposals for a contract to supply and install power transmission and distribution equipment, including providing and connecting substation main earth and equipment earthing, commissioning fitted substations and pre-commissioning protection testing for 11kV switchgear panels.

    Kahramaa expects to receive bids for this contract, with a bid bond of QR3m, by 14 November.

    Kahramaa is expanding its power generation capacity. Negotiations are under way with the sole bidder led by Japan's Sumitomo Corporation for a contract to develop and operate Qatar’s Facility E independent water and power producer (IWPP) project.

    The Facility E IWPP scheme will have a power generation capacity of 2,300MW and a water desalination capacity of 100 million imperial gallons a day.

    Earlier this month, Qatar Electricity & Water Company announced plans to develop a 500MW peak power unit in Qatar's Ras Abu Fontas area.

    Construction is also under way for two solar farms with a total combined capacity of 875MW in Mesaieed and Ras Laffan.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12742343/main.jpg
    Jennifer Aguinaldo
  • Neom starts Tabuk highway prequalifications

    17 October 2024

     

    Saudi Arabian gigaproject developer Neom expects firms to submit their prequalification applications for a project to build a mountain road near Tabuk later this month.

    The 11.5-kilometre (km) Tabuk mountain road project comprises a 4km tunnel and 7.5km dualisation of an existing road, according to an industry source.

    Neom expects to receive statements of qualifications from interested engineering, procurement and construction contractors by 29 October.

    The tender proceedings for Neom's transport infrastructure projects are gathering momentum.

    Neom received expressions of interest for a contract to build a coastal highway and infrastructure project catering to the Magna development on the Gulf of Aqaba on 15 October.

    The project, called Magna Infrastructure Packages, is split into three. Package one is 13km, package two is 42km and package three is 41km. The packages cater to the development’s north, central and south areas.

    The design-and-build project covers utilities for water, power, mobility, sewer, buildings and highways, in addition to the coastal highway. The project is expected to be completed by 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12738632/main.gif
    Jennifer Aguinaldo
  • Adnoc completes Fertiglobe stake acquisition

    16 October 2024

    Register for MEED's 14-day trial access 

    Abu Dhabi National Oil Company (Adnoc) has completed the transaction to acquire a majority stake in UAE-headquartered Fertiglobe, the largest nitrogen-based fertiliser producer in the Middle East and North Africa region.

    Adnoc has increased its shareholding in Fertiglobe to 86.2% through the acquisition of 50% + 1 share held by Netherlands-based OCI Global, which is backed by Egyptian billionaire Nassef Sawiris. The Abu Dhabi energy giant previously held a 36.2% stake in Fertiglobe.

    The remaining 13.8% of Fertiglobe’s shares trade on the Abu Dhabi Securities Exchange following the company's stock listing in October 2022.

    Adnoc announced the transaction to become the majority shareholder in Fertiglobe last December. Fertiglobe’s shares were priced at AED3.2 ($0.87) a share, valuing the deal at $3.62bn.

    Following the completion of the majority acquisition, “Fertiglobe’s current management team will stay in place”, including Ahmed El-Hoshy in his role as CEO, Adnoc said in a statement on 15 October.

    “Ahmed El-Hoshy spent 15 years growing OCI’s US and European business in ammonia and methanol via greenfields, brownfields and acquisitions, generating significant value for shareholders by leading recent divestments,” Adnoc said.

    Growing chemicals business

    Fertiglobe is the world’s largest seaborne exporter of urea and ammonia combined, exporting to 53 countries with a collective market share of about 10% of global trade in these products.

    “The acquisition represents … the expansion of Adnoc’s low-carbon fuels business, and supports its goal to become a top-five global chemicals player,” Adnoc said.

    “Fertiglobe will become the platform for Adnoc’s growth in fertiliser and low-carbon ammonia,” Adnoc said in its statement.

    Adnoc added it will transfer its stakes in existing and future low-carbon ammonia projects to Fertiglobe “at cost and when ready for startup”, including its two projects in Abu Dhabi and other projects in its global portfolio. Adnoc has yet to specify the low-carbon ammonia and blue ammonia production projects.

    MEED understands that the first Abu Dhabi project in question is the blue ammonia facility in the Taziz Industrial Chemicals Zone in Ruwais. Fertiglobe has partnered with South Korea’s GS Energy Corporation and Japanese investment firm Mitsui & Company to build the complex, which will have a production capacity of 1 million tonnes a year (t/y).

    In February last year, the joint venture awarded Italian firm Tecnimont the main contract for executing the engineering, procurement and construction works on the Taziz blue ammonia project.

    The second Abu Dhabi blue ammonia project that Adnoc could be referring to in its statement is a proposed scheme for which it signed a joint feasibility study agreement with British energy producer BP in May 2022.

    Adnoc further said that the two projects in Abu Dhabi will add 2 million t/y of output potential, more than doubling Fertiglobe’s current commercial ammonia capacity of 1.6 million t/y and increasing its total sellable capacity to 8.6 million t/y of net ammonia and urea combined, in addition to other announced global projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12735570/main1542.jpg
    Indrajit Sen
  • Neom receives interest for Magna coastal highway

    16 October 2024

     

    Saudi Arabia’s gigaproject developer Neom has received interest from firms for the contract to build a coastal highway and infrastructure project linking Neom to the Magna development on the Gulf of Aqaba.

    The project, called Magna Infrastructure Packages, is split into three. 

    Package 1 is 13 kilometres, package 2 is 42km and package 3 is 41km.

    The packages cater to the development’s north, central and south areas.

    According to an industry source, the design-and-build project covers utilities for water, power, mobility, sewer, buildings and highways. It could cost between $250m and $500m.

    Local and international engineering, procurement and construction (EPC) contractors are understood to have submitted their expressions of interest to participate in the tender on 15 October.

    The coastal highway and infrastructure project is expected to be completed by 2027, the source said.

    Magna consists of 12 developments featuring 15 hotels that offer 1,600 hotel rooms, suites and apartments and over 2,500 residences.

    The development will span a 120km-long coastal strip with an average width of 3.5km. The total land area is about 430 square kilometres.

    The Magna infrastructure is divided into six districts, as follows:

    • District 1 – Northern Gateway: includes 13 bridges and underpasses with a length of 1.9km, 18 wadi culverts and five drainage culverts
    • District 2 – Romantic Bay and the Cube: includes two bridges and underpasses spanning 360 metres, 40 wadi culverts and 24 drainage culverts
    • District 3 – Wadi Tayyib: includes two bridges and underpasses, 26 wadi culverts and nine drainage culverts
    • District 4 – Jungle Club: includes three bridges and underpasses and 17 wadi culverts
    • District 5 – Magna: includes two bridges and underpasses, 14 wadi culverts and two drainage culverts
    • District 6 – Southern Gateway: includes three bridges and underpasses, 31 wadi culverts and one drainage culvert
    https://image.digitalinsightresearch.in/uploads/NewsArticle/12735899/main.jpg
    Jennifer Aguinaldo