Sustainability drives water investments

29 December 2023

 

Growing water scarcity that could imperil long-term economic expansion plans in much of the Middle East and North Africa region continues to drive investments in improving the sector’s capacity and efficiency.

This spending covers projects to increase water desalination and water treatment capacity to meet growing demand more sustainably, as well as water transmission pipeline projects to reduce water loss and improve sanitation.

Other projects, such as reservoirs and district cooling, are also picking up as national and municipal governments work to improve water security and reduce the carbon footprint of buildings. 

Across the five sub-sectors, an estimated $22bn-worth of contracts were awarded between January and November 2023. This is nearly twice the previous year’s figure, according to data from regional projects tracker MEED Projects.

Saudi Arabia accounted for 43 per cent of the total contracts awarded, followed by the UAE at 23 per cent.

Key awards

Recent months have seen the award of several pioneering projects.

Abu Dhabi National Oil Company (Adnoc) and Abu Dhabi National Energy Company (Taqa) awarded a 30-year build-own-operate-transfer (BOOT) contract for the first phase of Project Wave to a team of Egypt’s Orascom Construction and Metito in May this year. The scheme will replace the current aquifer water injection systems used to maintain reservoir pressure in all onshore oil fields in Abu Dhabi. It is expected to reduce the water injection-related energy consumption of the oil fields by up to 30 per cent.

The same month, a consortium including the local Alkhorayef Water & Power Technologies Company won a contract worth SR7.78bn ($2bn) to develop and operate the first independent water transmission pipeline (IWTP) project in Saudi Arabia. The Rayis-Rabigh scheme will be 150 kilometres (km) long and transmit 500,000 cubic metres a day (cm/d) of drinking water between the two municipalities.

Morocco’s National Office of Electricity & Drinking Water (Onee) also awarded a contract to develop and operate the first phase of a seawater reverse osmosis (SWRO) desalination plant in Grand Casablanca – the first major independent water producer (IWP) scheme in the country. A team of Spain’s Acciona and the local Afriquia Gaz and Green of Africa won the 30-year build-operate-transfer contract for the scheme, which will require a total investment of $875m.

State utility Dubai Electricity & Water Authority (Dewa) awarded the contract for its first IWP to Saudi-based utility developer Acwa Power. The Hassyan 1 IWP, which has a capacity of 180 million imperial gallons a day (MIGD), will require an investment of AED3.36bn ($914m).

Neom and its subsidiary Enowa have also awarded over $900m-worth of water utility contracts in the first 11 months of 2023, while Saudi Aramco awarded the $750m Jafurah water desalination project to a local consortium of Al-Bawani, Mowah Company and Lamar Holding.  

While the majority of the contracts awarded in 2023 were procured on an engineering, procurement and construction (EPC) basis, the largest individual contracts are schemes that are being implemented using the public-private partnership (PPP) model.

Saudi Arabia accounted for 43 per cent of the total water contracts awarded, followed by the UAE at 23 per cent

Future projects

Data from MEED Projects shows that close to $75bn of projects are in the pre-execution phase, with a third of this total already in the bidding stage.

Water transmission and pipeline projects account for about 35 per cent of the planned and unawarded projects, followed by water desalination and water treatment plants, which each have a share of approximately 25 per cent.

With its population expected to reach 50 million by 2030, Saudi Arabia accounted for more than 43 per cent of the planned and unawarded water projects in the Mena region.

Water offtaker Saudi Water Partnership Company (SWPC) plans to procure 50 independent water infrastructure projects, according to its latest Seven-Year Statement covering the years 2022-28.

In terms of water desalination capacity, SWPC plans to procure  3.5 million cm/d of capacity based on its 2022-28 plan, exclusive of the Ras Mohaisen IWP which is under bid. The Saline Water Conversion Corporation (SWCC) has also initiated several SWRO projects that are being procured using an EPC model.

Together, SWCC and SWPC, in addition to the National Water Company and its spin-off Water Transmission & Technologies Company, account for a projects pipeline of more than $20bn, or more than a quarter of the total.

Neom and Enowa are emerging as major water project clients, with each having planned projects valued at about $3bn. Enowa is the client for the planned zero liquid discharge SWRO plant in Neom, which will be developed by a team of Japan’s Itochu and France’s Veolia. The project has an estimated budget of $1.5bn.

Going forward, the largest potential client is Dubai Municipality, which has restarted a major project known as the Deep Tunnels Portfolio. The estimated $22bn scheme will be developed as a public-private partnership (PPP) initiative and will involve developing assets across the city of Dubai and Hatta.

The scheme involves the construction of two sets of deep tunnels terminating at two terminal pump stations located at sewerage treatment plants (STPs) in Warsan and Jebel Ali. A conventional sewage and drainage collection system and STPs will be built in Hatta. The scheme also includes recycled water distribution systems connected to the STPs.

Qatar is also expected to resume projects activity in 2024.  In addition to the water desalination component of the Facility E independent water and power project, Qatar’s Public Works Authority (Ashghal) is expected to issue the request for proposals for four contracts that make up the South of Wakrah and New District of Doha pumping station and outfall scheme in the first quarter of 2024.

In the UAE, Adnoc and Taqa are also expected to start the procurement process for the second phase of Project Wave in 2024. As with the Mirfa seawater treatment plant, the Al-Nouf facility will be developed and maintained as a BOOT project. 

Egypt’s plan to procure renewable energy-powered water desalination plants will provide investors and local contractors with opportunities in the coming months or years. In May, the Sovereign Fund of Egypt disclosed that 17 teams and companies had been qualified to bid for the contracts to develop up to 8.85 million cm/d of renewable energy-powered desalination capacity in the country. The tender for the first phase of these projects is expected to be issued soon.

Mena power rides high into 2024

https://image.digitalinsightresearch.in/uploads/NewsArticle/11339767/main.gif
Jennifer Aguinaldo
Related Articles
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall
  • Qatar receives bids for major power grid expansion

    24 August 2026

     

    Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.

    The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.

    It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    According to sources, bids were submitted for the following packages on 20 August:

    • Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
    • Package S3, covering new 66/11kV substations ($50m)
    • Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
    • Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
    • Cable packages C1 and C2, covering 400kV cables ($100m)

    Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.

    In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.

    The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.

    Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.

    Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg
    Mark Dowdall
  • Maaden closes $1bn term loan and credit facility

    24 August 2026

    Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.

    The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.

    The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.

    The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.

    ALSO READ: Maaden and Aramco sign deal to create joint venture

    “The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.

    “The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.

    “Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg
    Indrajit Sen
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp