Sustainability drives water investments
29 December 2023

Growing water scarcity that could imperil long-term economic expansion plans in much of the Middle East and North Africa region continues to drive investments in improving the sector’s capacity and efficiency.
This spending covers projects to increase water desalination and water treatment capacity to meet growing demand more sustainably, as well as water transmission pipeline projects to reduce water loss and improve sanitation.
Other projects, such as reservoirs and district cooling, are also picking up as national and municipal governments work to improve water security and reduce the carbon footprint of buildings.
Across the five sub-sectors, an estimated $22bn-worth of contracts were awarded between January and November 2023. This is nearly twice the previous year’s figure, according to data from regional projects tracker MEED Projects.
Saudi Arabia accounted for 43 per cent of the total contracts awarded, followed by the UAE at 23 per cent.
Key awards
Recent months have seen the award of several pioneering projects.
Abu Dhabi National Oil Company (Adnoc) and Abu Dhabi National Energy Company (Taqa) awarded a 30-year build-own-operate-transfer (BOOT) contract for the first phase of Project Wave to a team of Egypt’s Orascom Construction and Metito in May this year. The scheme will replace the current aquifer water injection systems used to maintain reservoir pressure in all onshore oil fields in Abu Dhabi. It is expected to reduce the water injection-related energy consumption of the oil fields by up to 30 per cent.
The same month, a consortium including the local Alkhorayef Water & Power Technologies Company won a contract worth SR7.78bn ($2bn) to develop and operate the first independent water transmission pipeline (IWTP) project in Saudi Arabia. The Rayis-Rabigh scheme will be 150 kilometres (km) long and transmit 500,000 cubic metres a day (cm/d) of drinking water between the two municipalities.
Morocco’s National Office of Electricity & Drinking Water (Onee) also awarded a contract to develop and operate the first phase of a seawater reverse osmosis (SWRO) desalination plant in Grand Casablanca – the first major independent water producer (IWP) scheme in the country. A team of Spain’s Acciona and the local Afriquia Gaz and Green of Africa won the 30-year build-operate-transfer contract for the scheme, which will require a total investment of $875m.
State utility Dubai Electricity & Water Authority (Dewa) awarded the contract for its first IWP to Saudi-based utility developer Acwa Power. The Hassyan 1 IWP, which has a capacity of 180 million imperial gallons a day (MIGD), will require an investment of AED3.36bn ($914m).
Neom and its subsidiary Enowa have also awarded over $900m-worth of water utility contracts in the first 11 months of 2023, while Saudi Aramco awarded the $750m Jafurah water desalination project to a local consortium of Al-Bawani, Mowah Company and Lamar Holding.
While the majority of the contracts awarded in 2023 were procured on an engineering, procurement and construction (EPC) basis, the largest individual contracts are schemes that are being implemented using the public-private partnership (PPP) model.
Saudi Arabia accounted for 43 per cent of the total water contracts awarded, followed by the UAE at 23 per cent
Future projects
Data from MEED Projects shows that close to $75bn of projects are in the pre-execution phase, with a third of this total already in the bidding stage.
Water transmission and pipeline projects account for about 35 per cent of the planned and unawarded projects, followed by water desalination and water treatment plants, which each have a share of approximately 25 per cent.
With its population expected to reach 50 million by 2030, Saudi Arabia accounted for more than 43 per cent of the planned and unawarded water projects in the Mena region.
Water offtaker Saudi Water Partnership Company (SWPC) plans to procure 50 independent water infrastructure projects, according to its latest Seven-Year Statement covering the years 2022-28.
In terms of water desalination capacity, SWPC plans to procure 3.5 million cm/d of capacity based on its 2022-28 plan, exclusive of the Ras Mohaisen IWP which is under bid. The Saline Water Conversion Corporation (SWCC) has also initiated several SWRO projects that are being procured using an EPC model.
Together, SWCC and SWPC, in addition to the National Water Company and its spin-off Water Transmission & Technologies Company, account for a projects pipeline of more than $20bn, or more than a quarter of the total.
Neom and Enowa are emerging as major water project clients, with each having planned projects valued at about $3bn. Enowa is the client for the planned zero liquid discharge SWRO plant in Neom, which will be developed by a team of Japan’s Itochu and France’s Veolia. The project has an estimated budget of $1.5bn.
Going forward, the largest potential client is Dubai Municipality, which has restarted a major project known as the Deep Tunnels Portfolio. The estimated $22bn scheme will be developed as a public-private partnership (PPP) initiative and will involve developing assets across the city of Dubai and Hatta.
The scheme involves the construction of two sets of deep tunnels terminating at two terminal pump stations located at sewerage treatment plants (STPs) in Warsan and Jebel Ali. A conventional sewage and drainage collection system and STPs will be built in Hatta. The scheme also includes recycled water distribution systems connected to the STPs.
Qatar is also expected to resume projects activity in 2024. In addition to the water desalination component of the Facility E independent water and power project, Qatar’s Public Works Authority (Ashghal) is expected to issue the request for proposals for four contracts that make up the South of Wakrah and New District of Doha pumping station and outfall scheme in the first quarter of 2024.
In the UAE, Adnoc and Taqa are also expected to start the procurement process for the second phase of Project Wave in 2024. As with the Mirfa seawater treatment plant, the Al-Nouf facility will be developed and maintained as a BOOT project.
Egypt’s plan to procure renewable energy-powered water desalination plants will provide investors and local contractors with opportunities in the coming months or years. In May, the Sovereign Fund of Egypt disclosed that 17 teams and companies had been qualified to bid for the contracts to develop up to 8.85 million cm/d of renewable energy-powered desalination capacity in the country. The tender for the first phase of these projects is expected to be issued soon.
Exclusive from Meed
-
EtihadWE tenders $150m Ajman substation project21 July 2026
-
-
-
-
Dubai Municipality awards Tasreef drainage contract21 July 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
EtihadWE tenders $150m Ajman substation project21 July 2026
The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.
Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.
The bid submission deadline is 10 August.
According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.
The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.
Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.
This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.
EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.
In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg -
Seven seeks contractors for Dammam water park and hotel21 July 2026

Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.
The waterfront development sits on a 324,300-square-metre (sq m) plot.
A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.
Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.
The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.
The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.
Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.
Detailed design and issued-for-construction packages are complete.
Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.
The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.
The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.
Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.
Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.
The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.
The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg -
Al-Ula appoints equestrian village early works contractor21 July 2026

Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.
The contract was awarded to Al-Khobar-based Al-Shalawi International Company.
Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.
Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.
RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.
The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.
These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg -
Contractors await decision on Riyadh airport sewage plant21 July 2026

Seven contractors are awaiting a decision on a contract to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh, according to sources.
It is understood that bids were submitted to King Salman International Airport Development Company (KSIADC) in March, following the tender’s release earlier this year.
The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.
The facility will have a treatment capacity of 92,000 cubic metres a day. The contract is estimated to be worth SR700m ($187m).
The bidders (all local) are:
- Al-Rawaf Trading & Contracting
- Almajal Alarabi
- Nesma Water & Energy
- Safari Company
- Saudi Services for Electro-Mechanic Works
- Washnah Contracting
- Water & Environment Technologies (Wetico)
The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.
US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.
The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction contract covering potable water and fire water tanks and an associated pumping station. The same seven companies have submitted bids for that package.
Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.
The latest development followed KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.
These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17709281/main.jpg -
Dubai Municipality awards Tasreef drainage contract21 July 2026

Dubai Municipality has awarded local firm Detech Contracting the engineering, procurement and construction (EPC) contract for the TF-15-C1 package of its Tasreef Rainwater Drainage Network programme.
It is understood the municipality issued the letter of award for the contract earlier this month, covering the construction of a stormwater drainage system along Al-Wasl Road and communities west of the Dubai Canal.
The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.
It was tendered in February through the government’s Sewerage and Recycled Water Projects Department, with bids submitted in April.
The package forms part of the wider Tasreef initiative, which is intended to improve Dubai’s flood resilience.
The TF-15-C2 package was recently awarded to China State Construction Engineering Corporation for a stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.
The project is estimated to cost $162m and includes the construction of about 20 kilometres of new stormwater pipelines. Similar to the C1 package, it is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.
Separately, Al-Kharafi has won a drainage EPC contract (Ds207) to upgrade an existing pumping station for the municipality, a source said. The package focuses mainly on mechanical works and is valued at about $39m.
In May, MEED reported that local firm Nael Construction & Contracting had signed a contract with Dubai Municipality to build a sewage and stormwater drainage system in Dubailand.
The project (DS-204-C1) involves the construction of a drainage system with sewage gravity pipelines of up to 2,200mm in diameter.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17707980/main.jpg
Mena power rides high into 2024