Small reactors top nuclear agenda

25 August 2023

This package also includes: Mena pushes for nuclear future

 


Small modular reactor (SMR) solutions could offset concerns about capital expenditure, construction delays and spent-fuel reprocessing that large-scale nuclear power plants present.

SMRs are advanced nuclear reactors that have a power capacity of up to 300MW a unit, which is about one-third of the generating capacity of traditional nuclear power reactors, according to the International Atomic Energy Agency.

They can be factory-assembled, transported and installed in locations not suitable for larger nuclear power plants, such as industrial zones or remote areas with limited grid capacity. This makes them more affordable and easier to build than large reactors.

So far, there are only two advanced SMR installations globally, one in China and the other in Russia. The US’ NuScale is also working towards deploying its first modules in Idaho.

Saudi Arabia and Jordan have been considering deploying SMR solutions as part of their nuclear power programmes.

In 2020, King Abdullah City for Atomic & Renewable Energy (KA-Care) and South Korea’s Science & ICT (Information & Communication Technology) Ministry set up a joint venture to undertake the commercialisation and construction of South Korea’s system-integrated modular advanced reactor technology in the kingdom with the help of Korea Hydro & Nuclear Power.

Nuclear energy is having a revival moment as a recognised part of climate mitigation
Karen Young, Centre on Global Energy Policy, Columbia University

Seeking partners

Jordan, for its part, signed an agreement with Russia for the construction of two 1,000MW reactors in 2015, but the project was cancelled three years later.

Jordan is now considering small nuclear reactors and is talking to potential partners including Russia, South Korea, France and the UK to determine the optimal technical specifications and how to adapt the reactors to the Jordanian environment, Khaled Toukan, chairman of the Jordan Atomic Energy Commission, said in April.

Jordan hopes to use small nuclear reactors for water desalination and power production.

“We have done all the studies,” Toukan said at the time. “The infrastructure is in place, and studies on site selection and the provision of cooling water are in place. Now, we are comparing technologies and we want to get the go-ahead from the government.”

According to Karen Young, a senior research scholar at the Centre on Global Energy Policy at Columbia University in the US, “nuclear energy is having a revival moment as a recognised part of climate mitigation”. 

She says: “We simply do not have other ways of ramping up non-carbon energy production as easily. Technology innovations in SMRs, among others, make this look like a more viable option.”

However, SMRs are as yet unproven, points out Paddy Padmanathan, co-founder and vice-chairman of green hydrogen firm Zhero. He adds that solar and wind projects with battery energy storage systems cost significantly less, despite the subsidies some governments allocate to nuclear power plant projects.

We simply do not have other ways of ramping up non-carbon energy production as easily

Spent fuel

Regardless of a nuclear plant’s size, the storage or reprocessing of the resulting highly radioactive solid waste is a key safety and environmental concern. 

Nuclear reactors require ceramic pellets of low-enriched uranium oxide. These are stacked vertically and encased in metallic cladding to form a fuel rod. The fuel rods are bundled into fuel assemblies that are placed into the reactor. 

The fuel pellets remain in the reactors for five or six years of operation, or until the fission process uses up the uranium fuel. 

The US, which generates about 2,000 tonnes of spent fuel a year, stores the solid waste across 70 reactor sites in the country. Research and development into how to recycle spent fuel, or to design advanced reactors that could consume it, is also under way.

With 58 nuclear power plants generating over 70 per cent of its electricity, France produces nearly 1,150 tonnes of spent fuel a year. Unlike the US, France recycles spent fuel through a process that converts spent plutonium – formed in nuclear power reactors as a by-product of burning uranium fuel – and uranium into a mixed oxide that can be reused in nuclear plants to produce more electricity.

In Iran, meanwhile, the policy at the 1,000MW Bushehr reactor entails cooling down spent fuel in an onsite pool, a process that takes at least five years. It is then transported in steel cylinders that are welded closed to a central storage location in the country’s Anarak region.

UAE policy

The UAE government is developing a long-term storage policy for spent fuel from its Barakah nuclear power plant, the first reactor of which began producing electricity in 2021. The current plan involves placing the fuel assemblies in concrete and steel-lined cooling pools located at the Barakah plant, after which they will be stored in dry casks either on site or at a long-term storage facility.

According to Emirates Nuclear Energy Corporation, the UAE still has plenty of time to make decisions about spent-fuel management, as the first batch of nuclear fuel will be stored for 20-30 years in the spent-fuel pool.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11020048/main.gif
Jennifer Aguinaldo
Related Articles
  • Consultants submit bids for Saudi Arabia’s GCC rail link

    20 July 2026

     

    Consultants submitted proposals on 14 July for a contract to provide design consultancy services for the Saudi Arabian section of the GCC railway network, which is intended to link all six member states.

    Saudi Arabia Railways (SAR) issued the tender on 7 May, MEED previously reported.

    The tender covers the concept, preliminary and issued for construction design stages. SAR requires the selected consultant to review, update and complete the existing preliminary design.

    The consultants who submitted bids include: 

    • Atkins with Khatib & Alami
    • DeutscheBahn with ARX
    • Egis with Sener
    • Idom with Dal al-Handasah
    • Systra

    Saudi Arabia’s section of the railway will start at Al-Khafji in the Eastern Province, near the border with Kuwait, and end at Al-Batha, on Saudi Arabia’s border with the UAE. The route length in Saudi Arabia will be about 672 kilometres (km).

    The railway will interface with the Kuwait National Rail Road (KNRR) project on the Kuwaiti side. Last year, MEED exclusively reported that the KNRR design contract was awarded to Turkiye’s Proyapi Muhendislik ve Musavirlik Anonim Sirketi.

    The KNRR forms part of the wider GCC rail network. GCC railway projects have gained renewed momentum since the six member states signed the Al-Ula Declaration in January 2021.

    In October last year, Qatar’s cabinet approved a draft agreement paving the way for a railway link between Qatar and Saudi Arabia as part of the GCC railway network.

    GCC railway line

    Under the overall plan, the railway will run from Kuwait, pass through Dammam in Saudi Arabia, reach Bahrain via a planned causeway, and continue from Dammam to Qatar, the UAE and, ultimately, Muscat via Sohar in Oman. The railway is reported to span about 2,186km in total.

    The route length within each member state is as follows: 684km in the UAE, 672km in Saudi Arabia, 306km in Oman, 283km in Qatar, 145km in Kuwait and 36km in Bahrain.

    The railway is designed for passenger trains travelling at 220km/h and freight trains operating at 80-120km/h.

    With high levels of project activity, governments in spending mode and renewed cooperation under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If completed, the railway could prove transformational for a region that is globally connected but still divided by national borders.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17705320/main.gif
    Yasir Iqbal
  • Chinese firm wins Dubai drainage contract

    20 July 2026

    China State Construction Engineering Corporation (CSCEC) has announced it has won a contract to deliver a stormwater drainage pipeline package under Dubai Municipality’s Tasreef programme.

    The contract is for the TF-15-C2 stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai. 

    MEED exclusively revealed in May that the contractor had been selected for the engineering, procurement and construction (EPC) contract. The project is estimated to cost $162m.

    The scope of work includes the construction of about 20 kilometres of new stormwater pipelines, together with associated inspection and intake manholes. The project is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.

    It is being delivered as part of Dubai’s Tasreef strategic plan, which supports the Dubai 2040 Urban Master Plan. Once completed, the new drainage infrastructure is expected to improve the emirate’s stormwater network, increase flood protection and enhance the resilience of Dubai’s infrastructure.

    In February, the municipality confirmed it had awarded contracts for five new projects under phase two of the programme to expand and strengthen Dubai’s stormwater drainage network.

    These include a separate contract awarded to CSCEC for the TF-11-C1 stormwater drainage project in the Dubailand area.

    Also in February, Dubai Municipality invited consultants to qualify for a contract to supervise construction on the TF-15-C2 stormwater drainage projects along with two other projects (TF-13-C1 and TF-16-C1) under the Tasreef programme.

    According to a source, a consultant has yet to be appointed.

    TF-16-C1 involves upgrading and rehabilitating the stormwater system east of the Dubai Canal, while TF-13-C1 involves building a water pipeline stormwater drainage system at Al-Marmoum, Al-Qudra and Al-Yalayis 2 & 3.

    Bids are currently under evaluation for the EPC contracts for both projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17705058/main.jpg
    Mark Dowdall
  • Dubai receives eight bids for Hassyan SWRO pipeline contract

    20 July 2026

    Register for MEED’s 14-day trial access 

    Eight contractors have made offers for a contract to supply, install, test and commission glass-reinforced epoxy (GRE) water transmission pipelines and associated works for the Hassyan seawater reverse osmosis (SWRO) phase two network in Dubai.

    The contract relates to project one of the Hassyan pipeline network expansion being undertaken by state utility Dubai Electricity & Water Authority (Dewa).

    Local firm Binladin Contracting Group submitted the lowest offer of AED335.92m ($91.5m), according to results published by the utility.

    The other bids were:

    • Green Oasis General Contracting (UAE) – AED345.00m ($93.9m)
    • Al-Nasr Contracting (UAE) – AED391.54m ($106.6m)
    • Wade Adams Contracting (UAE) – AED393.80m ($107.2m)
    • RMB Contracting (UAE) – AED437.96m ($119.3m) 
    • Tristar Engineering & Construction (UAE) – AED441.55m ($120.2m)
    • Shapoorji Pallonji Mideast (UAE/India) – AED451.47m ($122.9m)
    • Gulf Petrochemical Services Trading (UAE) – AED495.20m ($134.8m)

    RMB also submitted a conditional discounted offer of AED427.02m ($116.3m). Three companies submitted regret notices, while one offer was rejected after no valid commercial offer was received. 

    In January, Dewa announced that construction of the 180-million-imperial-gallon-a-day phase one of the Hassyan SWRO independent water project was 90% complete.

    Dewa has two other contracts out for tender for GRE water transmission pipeline work related to the Hassyan SWRO phase two network.

    Project two was tendered on 22 January and has a bid submission deadline of 21 July. Project three was tendered on 26 January and has a bid submission deadline of 29 July.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17704940/main.jpg
    Mark Dowdall
  • Abu Dhabi launches E20 highway expansion project

    20 July 2026

    Abu Dhabi’s Department of Municipalities and Transport (DMT) has announced the E20 highway expansion project.

    The scheme covers widening the main carriageway from three to five lanes, constructing more than 10 kilometres (km) of new ramps and loops, and building four bridges.

    Works also include 1.5km of internal roads and the addition of eight signalised junctions across Khalifa City and the Zayed International airport precinct.

    The project includes utility works, comprising 62km of stormwater drainage, 37km of irrigation networks and the installation of 485 streetlights.

    The E20 expansion is one of the major infrastructure schemes being overseen by DMT in Abu Dhabi.

    Separately, DMT is evaluating bids for a design-and-build contract to construct two bridges serving Hudayriyat Island in Abu Dhabi.

    The scope includes a two-lane bridge connecting 32nd Street to Shakhbout Bin Sultan Street, and a single-lane bridge on 8th Street. It also includes upgrades to signalised intersections.

    Shakhbout Bin Sultan Street is a two-way road with three lanes in each direction, providing access to and from Hudayriyat Island.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17704696/main.jpg
    Yasir Iqbal
  • Firms given more time for Mid Island Parkway prequalifications

    20 July 2026

     

    Abu Dhabi’s Modon Infrastructure has extended the deadline to 31 July for firms to submit expressions of interest and prequalification statements for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will be developed as a public-private partnership (PPP).

    The previous deadline was 15 July. MEED understands the prequalification notice was issued in June, following Modon Infrastructure’s invitation in May for firms to register their interest.

    Modon Infrastructure will act as the lead developer and will hold a majority equity stake in the project company. It will award contracts for engineering, procurement and construction; operations and maintenance; and project advisory services.

    Phase two of the MIPP involves the construction of about 11 kilometres (km) of highways, comprising a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also includes the construction of three interchanges – E20, E10 and Dumbbell – on Al-Sammaliyyah Island.

    The project includes several major structures, including the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange, which will feature cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover (open) tunnel on Bilrimaid Island. Another tunnel will connect Bilrimaid Island to Um-Yifeenah Island.

    Abu Dhabi awarded three packages for phase one of the MIPP in 2024. The contract for Package 1A was awarded to a joint venture of Turkish contractor Dogus Construction and UAE firm Gulf Contractors. Package 1B was awarded to a joint venture of Yas Projects (Alpha Dhabi Holding) and China Railway International Group. Beijing-headquartered China Harbour Engineering Company and the UAE’s Agility Engineering & Contracting Company won the contract for Package 1C.

    Phase one starts at the existing Saadiyat Interchange, connecting the E12 to the MIPP, and ends at the recently constructed Um-Yifeenah Highway.

    It comprises a dual main road with a total length of 8km, including four traffic lanes in each direction, two interchanges, a tunnel and associated infrastructure works.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17704765/main.jpg
    Yasir Iqbal