Small reactors top nuclear agenda
25 August 2023
This package also includes: Mena pushes for nuclear future

Small modular reactor (SMR) solutions could offset concerns about capital expenditure, construction delays and spent-fuel reprocessing that large-scale nuclear power plants present.
SMRs are advanced nuclear reactors that have a power capacity of up to 300MW a unit, which is about one-third of the generating capacity of traditional nuclear power reactors, according to the International Atomic Energy Agency.
They can be factory-assembled, transported and installed in locations not suitable for larger nuclear power plants, such as industrial zones or remote areas with limited grid capacity. This makes them more affordable and easier to build than large reactors.
So far, there are only two advanced SMR installations globally, one in China and the other in Russia. The US’ NuScale is also working towards deploying its first modules in Idaho.
Saudi Arabia and Jordan have been considering deploying SMR solutions as part of their nuclear power programmes.
In 2020, King Abdullah City for Atomic & Renewable Energy (KA-Care) and South Korea’s Science & ICT (Information & Communication Technology) Ministry set up a joint venture to undertake the commercialisation and construction of South Korea’s system-integrated modular advanced reactor technology in the kingdom with the help of Korea Hydro & Nuclear Power.
Nuclear energy is having a revival moment as a recognised part of climate mitigation
Karen Young, Centre on Global Energy Policy, Columbia University
Seeking partners
Jordan, for its part, signed an agreement with Russia for the construction of two 1,000MW reactors in 2015, but the project was cancelled three years later.
Jordan is now considering small nuclear reactors and is talking to potential partners including Russia, South Korea, France and the UK to determine the optimal technical specifications and how to adapt the reactors to the Jordanian environment, Khaled Toukan, chairman of the Jordan Atomic Energy Commission, said in April.
Jordan hopes to use small nuclear reactors for water desalination and power production.
“We have done all the studies,” Toukan said at the time. “The infrastructure is in place, and studies on site selection and the provision of cooling water are in place. Now, we are comparing technologies and we want to get the go-ahead from the government.”
According to Karen Young, a senior research scholar at the Centre on Global Energy Policy at Columbia University in the US, “nuclear energy is having a revival moment as a recognised part of climate mitigation”.
She says: “We simply do not have other ways of ramping up non-carbon energy production as easily. Technology innovations in SMRs, among others, make this look like a more viable option.”
However, SMRs are as yet unproven, points out Paddy Padmanathan, co-founder and vice-chairman of green hydrogen firm Zhero. He adds that solar and wind projects with battery energy storage systems cost significantly less, despite the subsidies some governments allocate to nuclear power plant projects.
We simply do not have other ways of ramping up non-carbon energy production as easily
Spent fuel
Regardless of a nuclear plant’s size, the storage or reprocessing of the resulting highly radioactive solid waste is a key safety and environmental concern.
Nuclear reactors require ceramic pellets of low-enriched uranium oxide. These are stacked vertically and encased in metallic cladding to form a fuel rod. The fuel rods are bundled into fuel assemblies that are placed into the reactor.
The fuel pellets remain in the reactors for five or six years of operation, or until the fission process uses up the uranium fuel.
The US, which generates about 2,000 tonnes of spent fuel a year, stores the solid waste across 70 reactor sites in the country. Research and development into how to recycle spent fuel, or to design advanced reactors that could consume it, is also under way.
With 58 nuclear power plants generating over 70 per cent of its electricity, France produces nearly 1,150 tonnes of spent fuel a year. Unlike the US, France recycles spent fuel through a process that converts spent plutonium – formed in nuclear power reactors as a by-product of burning uranium fuel – and uranium into a mixed oxide that can be reused in nuclear plants to produce more electricity.
In Iran, meanwhile, the policy at the 1,000MW Bushehr reactor entails cooling down spent fuel in an onsite pool, a process that takes at least five years. It is then transported in steel cylinders that are welded closed to a central storage location in the country’s Anarak region.
UAE policy
The UAE government is developing a long-term storage policy for spent fuel from its Barakah nuclear power plant, the first reactor of which began producing electricity in 2021. The current plan involves placing the fuel assemblies in concrete and steel-lined cooling pools located at the Barakah plant, after which they will be stored in dry casks either on site or at a long-term storage facility.
According to Emirates Nuclear Energy Corporation, the UAE still has plenty of time to make decisions about spent-fuel management, as the first batch of nuclear fuel will be stored for 20-30 years in the spent-fuel pool.
Exclusive from Meed
-
EtihadWE tenders $150m Ajman substation project21 July 2026
-
-
-
-
Dubai Municipality awards Tasreef drainage contract21 July 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
EtihadWE tenders $150m Ajman substation project21 July 2026
The UAE’s Etihad Water & Electricity (EtihadWE) has tendered a contract to build three new substations in Ajman.
Estimated to cost $150m, the project involves the construction of three new 132/11kV substations in the Bahya, Rumaila and Liwara districts. It also includes associated 132kV underground cabling works to connect the substations to the existing transmission network.
The bid submission deadline is 10 August.
According to tender documents, the project will add distribution capacity to support load growth and improve the security of electricity supply in the emirate.
The scope of work includes site preparation, construction of three substation buildings and foundations, installation of 132kV GIS/AIS switchgear, 132/11kV power transformers and 11kV switchgear, as well as protection, control, Scada and telecommunications systems.
Etihad WE is responsible for electricity and water services in Ajman, Umm Al-Quwain, Ras Al-Khaimah, Fujairah and parts of Sharjah. The utility has been investing in new substations and transmission infrastructure as electricity demand continues to increase across the Northern Emirates.
This includes a 132/33/11kV substation project on Al-Marjan Island in Ras Al-Khaimah. Construction work is ongoing on the project, with Maetal Dubai serving as the main contractor.
EtihadWE is also finalising a new masterplan that will cover network capacity requirements and expansion priorities for the next 10 to 15 years.
In June, Abdulla Al-Khemeiri, chief operations officer, told MEED: “We are currently reviewing it, and we need to obtain shareholder approval first. Once it is approved, it will be released, hopefully by the end of the year.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710661/main.jpg -
Seven seeks contractors for Dammam water park and hotel21 July 2026

Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, is preparing to shortlist general contractors for the main construction package of its Dammam Water Park & Hotel project in the Al-Hamra district.
The waterfront development sits on a 324,300-square-metre (sq m) plot.
A notice was issued to contractors in July, and the client is expected to finalise the shortlist by the end of this month.
Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.
The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.
The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.
Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.
Detailed design and issued-for-construction packages are complete.
Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.
The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.
The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.
Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.
Construction of Seven’s Dammam entertainment complex is currently under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the Kingdom’s Eastern Province.
The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.
The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710096/main.jpg -
Al-Ula appoints equestrian village early works contractor21 July 2026

Saudi Arabia’s Royal Commission for Al-Ula (RCU) has awarded a contract for early construction works at the Al-Muatadil Equestrian Village.
The contract was awarded to Al-Khobar-based Al-Shalawi International Company.
Canadian engineering firm AtkinsRealis is the project management consultant. UK-headquartered Baker Wilkins & Smith and local firm Al-Hoty Company are the cost consultants.
Dubai-based SSH is the supervision consultant, and UK-based Hopkins Architects is the lead design consultant.
RCU announced the project plans in March 2023, including the development of an equestrian hub with two arenas that can accommodate 5,000 and 1,400 spectators, respectively.
The venue will also include grass polo, sand polo and endurance facilities, with capacities of 600, 400 and 600 seats, respectively.
These facilities will be complemented by visitor amenities, two stable compounds with capacity for 740 horses, and accommodation and retail outlets for event participants and workers.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17710170/main.jpeg -
Contractors await decision on Riyadh airport sewage plant21 July 2026

Seven contractors are awaiting a decision on a contract to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh, according to sources.
It is understood that bids were submitted to King Salman International Airport Development Company (KSIADC) in March, following the tender’s release earlier this year.
The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.
The facility will have a treatment capacity of 92,000 cubic metres a day. The contract is estimated to be worth SR700m ($187m).
The bidders (all local) are:
- Al-Rawaf Trading & Contracting
- Almajal Alarabi
- Nesma Water & Energy
- Safari Company
- Saudi Services for Electro-Mechanic Works
- Washnah Contracting
- Water & Environment Technologies (Wetico)
The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.
US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.
The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction contract covering potable water and fire water tanks and an associated pumping station. The same seven companies have submitted bids for that package.
Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.
The latest development followed KSIADC’s receipt of prequalification statements from contractors on 1 July for two new packages at KSIA.
These include the construction of a permanent East-West corridor and landside access roads serving the North and South terminals.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17709281/main.jpg -
Dubai Municipality awards Tasreef drainage contract21 July 2026

Dubai Municipality has awarded local firm Detech Contracting the engineering, procurement and construction (EPC) contract for the TF-15-C1 package of its Tasreef Rainwater Drainage Network programme.
It is understood the municipality issued the letter of award for the contract earlier this month, covering the construction of a stormwater drainage system along Al-Wasl Road and communities west of the Dubai Canal.
The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.
It was tendered in February through the government’s Sewerage and Recycled Water Projects Department, with bids submitted in April.
The package forms part of the wider Tasreef initiative, which is intended to improve Dubai’s flood resilience.
The TF-15-C2 package was recently awarded to China State Construction Engineering Corporation for a stormwater drainage network project located along Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.
The project is estimated to cost $162m and includes the construction of about 20 kilometres of new stormwater pipelines. Similar to the C1 package, it is located west of the Dubai Canal and will connect the Al-Quoz 3 and Al-Quoz 4 industrial areas with Al-Quoz 1.
Separately, Al-Kharafi has won a drainage EPC contract (Ds207) to upgrade an existing pumping station for the municipality, a source said. The package focuses mainly on mechanical works and is valued at about $39m.
In May, MEED reported that local firm Nael Construction & Contracting had signed a contract with Dubai Municipality to build a sewage and stormwater drainage system in Dubailand.
The project (DS-204-C1) involves the construction of a drainage system with sewage gravity pipelines of up to 2,200mm in diameter.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17707980/main.jpg