Securing Bahrain’s hydrocarbons potential
3 April 2025
Bahrain, which has access to modest hydrocarbons reserves in comparison to its Gulf peers, has been in constant pursuit of additional resources to grow its oil and gas production levels.
The country took a leap towards this goal in 2018, when it announced the discovery of the Khalij Al-Bahrain offshore hydrocarbons basin, which is estimated to contain 80 billion barrels of oil and 10-20 trillion cubic feet of gas. Almost seven years on, however, Manama is not known to have made any notable progress on the commercial appraisal of that oil and gas resource base.
State enterprise Bapco Energies has, therefore, devised a multi-pronged strategy to secure Bahrain’s energy future. The first objective is to maintain the country’s present oil and gas output levels, according to group CEO Mark Thomas.
“Objective number one is to stabilise oil and gas production from the existing reservoirs at the Awali field and stem the decline. These are very mature reservoirs, which, without intervention, will decline quite quickly,” Thomas tells MEED.
Bahrain’s primary oil and gas production comes from the Awali field, where the first oil in the Gulf region was discovered in 1932. Bapco Upstream, a subsidiary of Bapco Energies, is the sole operator of the onshore field. It produces an average of 42,400 barrels a day (b/d) of crude oil and 1.67 billion cubic feet a day of non-associated gas from the Awali field, which is also known as the Bahrain field.
In addition, Bapco Energies draws in about half of the 300,000 b/d production capacity of the Abu Safah offshore field, which is shared by Bahrain and Saudi Arabia.
“Objective number two is to develop new opportunities for us,” Thomas says, adding: “We’ve been looking at appraising pre-Unayzah gas from the Al-Jawf and Al-Juba reservoirs,” which Bapco Energies announced discovering in 2022.
“These are deep gas reservoirs, so we call them unconventional. They’re tight rock, need to be fracked and require the drilling of horizontal wells for production. We’ve gone through an appraisal programme on that. We’ll start a development programme in 2025 around those [discoveries].”
Exploration campaign
Bapco Energies is progressing with a “very big three-dimensional (3D) seismic programme” to hunt for offshore hydrocarbons resources, Thomas says.
“We’re running an extensive campaign covering about 4,500 square kilometres of surface area, where we will be shooting 3D seismic. That is basically around the entirety of [Bahrain]. We will carry on through 2025 and into 2026.
“We hope to be able to identify some structures and then invite companies to come, share the information with them and hopefully do some exploration drilling,” he adds.
“It’s logical that there will be [a licensing round in the future], assuming that we are successful with the 3D seismic and can identify some structures. But it needs to wait until we have some quality data.
“This has always been the hindrance for us in attracting international oil companies to come to Bahrain,” he notes.
“The quality of the data that we had for offshore was not good and, quite frankly, for a company entering a new country, the risk was too high.”
Italian energy producer Eni is the only international player that has been evaluating exploration and production opportunities in Bahrain in recent years.
“By using the latest technology with 3D seismic seabed nodes, and by shooting deeper, we will absolutely have the best data that we can. And, if there are structures offshore, we will definitely find them,” Thomas says.
By using the latest technology with 3D seismic seabed nodes … we will absolutely have the best data
Business expansion
Bapco Energies has set its sights on growing its presence in overseas markets by identifying and exploiting promising opportunities in the upstream sector, similar to the path that has been adopted by some of the other Gulf national oil companies in this decade.
“We have traditionally been a national oil and gas company, and what we’re looking at now is international expansion,” Thomas says.
“We’ve got 90 years of experience in exploring for, and developing, oil and gas fields. We want to take that capability, that experience, and apply it internationally.”
He continues: “We’ve taken that proposal through our governance structure and received approval for that.
So now, we’re looking at potential opportunities where we could invest outside of Bahrain, using our capability and experience.
“We are not necessarily [looking at] being an operator, and certainly not [aiming to be] in exploration plays, but more into already-producing fields, or fields in a late stage of development, where the risk is low. These are the types of opportunities that we’re now looking at. They are small in nature, but they’re out there and so we’re searching for them right now.”
Bapco Energies took a stride towards its goal of international expansion in July, with the launch of its venture capital arm, BeVentures.
“BeVentures is a new company for us. It’s something that a lot of the major energy companies are doing, and that is to set up a separate company to look at opportunities for investment in new services and new technologies that can both help their existing business, as well as prepare their businesses for the future, for the energy transition,” Thomas says.
“We are looking at smaller, direct investments in companies that have a commercial product. What they’re looking for is capital and [ways to] scale [up].
“We’re looking at opportunities principally within our existing businesses around oil and gas production, refining and petrochemicals. But we’re also looking at elements that will prepare us for the future, more into renewables.”
Exclusive from Meed
-
-
-
-
Firms bag $850m Qatar substation contracts
8 May 2025
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends

Related Articles
-
Dubai awards $272m Al-Maktoum airport runway deal Yasir Iqbal
9 May 2025
Dubai Aviation Engineering Projects (DAEP) has awarded a AED1bn ($272m) deal to local firm Binladin Contracting Group to construct the second runway as part of the expansion of Dubai’s Al-Maktoum International airport.
MEED understands that the contract was finalised in Q1 of this year, and the construction works have started.
The airport, which will cover an area of 70 square kilometres south of Dubai, will have five parallel runways, five terminal buildings and 400 aircraft gates.
It will be five times the size of the existing Dubai International airport and have the world’s largest passenger handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.
The construction works on the first phase of the project are expected to be completed by 2032.
Dubai approved the updated designs and timelines for its largest construction project in April last year.
The government of Dubai said that the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International airport within 10 years.
The government statement added that the project will create housing demand for 1 million people around the airport.
In September last year, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead master planning and design consultants on the expansion of Dubai’s Al-Maktoum International airport.
Project history
The expansion of Al-Maktoum International airport is a long-standing project. Also known as Dubai World Central (DWC), it was officially launched in 2014 with a different design from the one approved in April 2024. Back then, it involved building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year.
An initial phase, due to be completed in 2030, involved increasing the airport’s capacity to 130 million passengers a year. The development was to cover an area of 56 square kilometres.
Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.
MEED’s May 2025 report on the UAE includes:
> COMMENT: UAE is poised to weather the storm
> GOVERNMENT & ECONOMY: UAE looks to economic longevity
> BANKING: UAE banks dig in for new era
> UPSTREAM: Adnoc in cruise control with oil and gas targets
> DOWNSTREAM: Abu Dhabi chemicals sector sees relentless growth
> POWER: AI accelerates UAE power generation projects sector
> CONSTRUCTION: Dubai construction continues to lead region
> TRANSPORT: UAE accelerates its $60bn transport push
> DATABANK: UAE growth prospects head northhttps://image.digitalinsightresearch.in/uploads/NewsArticle/13847301/main.jpg -
Siemens Energy signs preliminary 14GW Iraq pact Jennifer Aguinaldo
9 May 2025
Register for MEED’s 14-day trial access
Germany’s Siemens Energy and Iraq’s Electricity Ministry have signed a preliminary agreement to add 14GW of electricity generation capacity to Iraq’s grid.
The firms also signed two long-term service contracts for the Dibis and Al-Mussaib gas-fired power plants.
The contract for the Dibis power plant covers two generating units with a combined capacity of 340MW.
The five-year maintenance contract for the Al-Mussaib power station includes rehabilitating units with a capacity of 750MW and an additional 150MW, along with support for safe operations and performance optimisation.
The announcement was made following a meeting between Siemens Energy CEO Christian Bruch and Iraqi Prime Minister Mohammed Al-Sudani, local media reported.
The deals were signed a few weeks after US-headquartered GE Vernova signed a memorandum of understanding (MoU) with the Iraqi government to establish 24GW of combined-cycle gas turbine (CCGT) power plants in the country.
In late April, Iraq and Siemens Energy also announced breaking ground on a project to build a new CCGT power generation plant in Nasiriyah in Iraq’s southern Dhi Qar governorate.
The project is part of a $1.68bn development package that Al-Sudani recently launched.
In addition to the CCGT plant, the other projects include the Nasiriyah Integrated Medical City, a 700-bed hospital complex and infrastructure works in the Suq Al-Shuyukh district.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13847219/main.jpg -
Abu Dhabi hopes bigger is better with Disney theme park Colin Foreman
8 May 2025
Commentary
Colin Foreman
EditorEver since Aldar Properties first launched the Yas Island project with its Yas Marina Circuit for the Abu Dhabi Grand Prix in 2006, Abu Dhabi has been steadily adding theme parks to the island’s roster of attractions. First, there was the Ferrari theme park, then came a water park, a Warner Bros theme park and, most recently, SeaWorld.
The theory with theme park development is bigger is better.
A destination needs a series of parks to create a critical mass to attract visitors who can stay and enjoy multiple parks in one visit. The example always cited is Florida, which is home to many of the world’s largest theme parks, including Disney World.
The theory gained particular traction in the region when Dubai Parks and Resorts opened. The company, which was public until it was acquired by Meraas in 2021, reported significant losses as it struggled to attract enough visitors.
Although it opened with Legoland, Legoland Waterpark, Motiongate and Bollywood theme parks, insiders said that the problem with the development was that it did not have enough attractions to turn it into a successful theme park destination.
The financial performance of theme parks on Yas Island has not been publicly disclosed. While it is accepted that they have been more successful than their counterparts in Dubai, some say that the island still does not have the critical mass required to establish itself as a global destination for theme park visitors.
Miral has developed a series of theme parks and other entertainment-related attractions on Yas Island
Enter Disney
Disney changes that. It is the largest brand in the theme park space and will be a major attraction, but with limited information released on the project so far, it is difficult to fully gauge how significant the project will be.
The official release said that the project will be developed and operated by Abu Dhabi developer Miral, adding that Disney’s in-house design and engineering unit, Walt Disney Imagineering, will lead creative design and operational oversight to provide a world-class experience. It did not give any details on the ownership of the project.
In Hong Kong, for example, a company, Hong Kong International Theme Parks, was established as a joint venture, with the Government of Hong Kong holding 57% and The Walt Disney Company holding 43%.
In Japan, the structure is different. The Tokyo Disney Resort is owned and operated by Oriental Land, and the company pays licences and royalties to The Walt Disney Company.
In interviews following the launch announcement, Miral CEO Mohamed Abdalla Al-Zaabi confirmed the arrangement will be like Tokyo.
Waterfront location
The official release for the Abu Dhabi launch also said that the project is on Yas Island, which only has limited areas of land to develop. The release also said that the land is waterfront, and imagery in the launch video shows the Abu Dhabi skyline in the background, suggesting the land is on the northern waterfront of Yas Island.
There is a substantial tract of undeveloped land on the north shore of the island, which measures about 2 square kilometres (sq km). This is larger than the site that Hong Kong Disneyland occupies, and much smaller than Disney World in Florida, which spans an area of 111 sq km – nearly five times the size of the whole of Yas Island and nearly double the size of Abu Dhabi Island.
The hope is that Yas Island will become a leading global theme park destination and attract large numbers of visitors wanting a holiday with multiple theme park visits
Exclusivity clause
Another area of interest will be whether Abu Dhabi has an exclusivity agreement with Disney for the region. No exclusivity was mentioned at the launch, but in Hong Kong, the issue became contentious when Disney announced plans to build a park shortly after Disneyland Hong Kong opened. Local politicians criticised the Hong Kong government for not including an exclusivity clause in its deal with Disney.
Tourism gateway
Like Hong Kong, Abu Dhabi is a smaller economy sitting next to a larger regional player. With Saudi Arabia’s ambitious Vision 2030 strategy and its existing roster of theme park developments at Qiddiya, which includes a Six Flags, a water park and a Dragon Ball Z theme park, developers in Riyadh would likely be keen to have a Disney theme park, too.
For now, with Disney on board in Abu Dhabi, the hope is that Yas Island will become a leading global theme park destination and attract large numbers of visitors wanting a holiday with multiple theme park visits.
The potential is certainly there. During the project launch, Disney highlighted that the UAE is located within a four-hour flight of one-third of the world’s population, making it a significant gateway for tourism. It is also home to the largest global airline hub in the world, with 120 million passengers travelling through Abu Dhabi and Dubai each year.
If that potential is realised, then the bigger is better theory will be proved right. If the park’s performance disappoints, then it will suggest the region is not such a great destination for theme parks after all.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13840555/main.gif -
Firms bag $850m Qatar substation contracts Jennifer Aguinaldo
8 May 2025
Four local and international firms have won contracts for the construction of seven high-voltage substations in Qatar.
State-backed Qatar General Electricity & Water Corporation (Kahramaa) signed the contracts, which have a total combined value of approximately QR3.1bn ($850m), with the following firms:
- Elsewedy Cables Qatar Company (local/Egypt)
- Voltage Engineering (local)
- Best/Betas Consortium (Turkey)
- Taihan Cable & Solution (South Korea)
Kahramaa said the projects aim to “meet electrical network demand in light of the country's fast-growing …urban development”.
The contracts include the provision and installation of underground cables and overhead lines extending around 212 kilometres to connect these substations.
Qatari companies won the largest share, equivalent to 58.4% or QR1.8bn, of the total contract value.
This reflects “our great confidence in the capabilities of the local private sector and its pivotal role in achieving our development vision and achieving Qatar National Vision 2030”, said Kahramaa president Abdulla Bin Ali Al-Theyab.
Qatar Minister of State for Energy Affairs, Saad Sherida Al-Kaabi, and senior executives from Kahramaa and the contracting firms signed the deals at a ceremony held in Doha.
Al-Kaabi said the projects will help “ensure our networks' continued and sustainable ability to accommodate the unprecedented growth of the power sector and meet the increasing electricity demand”.
Kahramaa said the contractors will undertake the construction of electrical substations and the connection of cables and overhead lines, as well as the development of some existing substations to increase their capacity.
Qatar has been ramping up its power generation capacity in recent years.
Qatar's Emir, Sheikh Tamim Bin Hamad Al-Thani, inaugurated the Ras Laffan and Mesaieed solar photovoltaic (PV) power plants on 28 April.
The two plants have a combined capacity of 875MW and will more than double Qatar’s solar energy production to 1,675MW.
In February, Qatar Electricity & Water Company (QEWC) and Kahramaa signed a power-purchase agreement for a 511MW peak electricity generation plant at Ras Abu Fontas, which will have a total cost of approximately QR1.6bn. The peak power plant is scheduled to become operational by January 2027.
A consortium led by South Korea's Doosan Enerbility, and that includes Beijing-headquartered PowerChina, will undertake the Ras Abu Fontas peak power plant's engineering, procurement and construction contract, with Germany's Siemens Energy supplying the plant's gas turbines.
Photo credit: Kahramaa
https://image.digitalinsightresearch.in/uploads/NewsArticle/13838850/main.jpg -
OQ to take interest in Oman renewable projects Jennifer Aguinaldo
8 May 2025
OQ Alternative Energy (OQAE), part of Oman’s state-backed energy group OQ, will be taking shares in Oman’s renewable energy independent power projects (IPP), starting with the Ibri 3 solar scheme.
“The direction seems to be for OQ Alternative Energy to own up to 25% shares in the upcoming solar and wind IPP projects in the sultanate,” says a source familiar with the plans.
Before this development, private developers and investors owned the total shares in such projects, similar to the existing structure in Saudi Arabia.
With this policy change, Oman will now be more closely aligned with the existing project structure in the UAE, where either Abu Dhabi National Energy Company (Taqa), Abu Dhabi Future Energy Company (Masdar) or the state utility, Dubai Electricity & Water Authority (Dewa), owns stakes in these projects.
However, OQAE’s planned 25% ownership share will be slightly lower than the typical 40% to 60% shares that Taqa, Masdar or Dewa owns in the UAE’s renewable energy IPP projects.
Currently, OQAE owns a 51% share in three renewable energy projects being developed in partnership with France’s TotalEnergies for the state-backed firm, Petroleum Development Oman (PDO).
The Riyah-1 and Riyah-2 wind power plants will be located in the Amin and West Nimr fields in southern Oman, while the North Solar project will be situated in northern Oman.
Each plant will have a capacity of 100MW, Total Energies announced in December.
PDO will purchase the electricity from the plants through long-term power-purchase agreements with the developer team, whose 49% shares are owned by TotalEnergies.
OQAE is also part of Hyport Coordination Company, a consortium comprising Belgium’s Deme Concessions and BP Oman. The consortium plans to develop a green hydrogen project in Duqm that can produce more than 50 tonnes a year of green hydrogen in its first phase by 2029.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13838800/main.jpg