Saudi’s Jeddah Tower reaches for new heights

27 September 2023

 

A landmark moment came for Saudi Arabia’s construction sector in mid-September when Jeddah Economic Company (JEC) invited firms to bid for a contract to complete the world’s tallest tower project, the 1,000-metre-plus Jeddah Tower.

Work on the tower “is back in full [swing]”, a source close to the project told MEED.

When completed, Jeddah Tower will be the first structure in history to exceed 1 kilometre in height. It will also be taller than the current world’s tallest building, Dubai’s Burj Khalifa, by more than 172 metres. 

When contacted by MEED, Talal Ibrahim Almaiman, CEO of Kingdom Holding Company, confirmed that the tender to complete the record-breaking tower had been officially issued.

The companies that have been invited to bid for the contract include:

  • Almabani (local)
  • Bawani (local)
  • China Harbour (China)
  • China State Construction Engineering Corporation (China)
  • Consolidated Contractors Company (CCC – Lebanon)
  • El-Seif Engineering Contracting (local)
  • Hyundai Engineering Construction (South Korea)
  • Mohammed Abdulmohsin al-Kharafi & Sons (Kuwait)
  • Nesma & Partners (local)
  • Powerchina (China)
  • Samsung C+T (South Korea)
  • Saudi Freyssinet (local)
  • Skanska (Sweden)
  • Strabag (Europe)

The contractors have been given three months to prepare their bids, and are expected to form joint ventures comprising local and international partners. It is understood that contractors have visited the site.

When completed, Jeddah Tower will be the first structure in history to exceed 1 kilometre in height

Restarting construction

One important question for the potential bidders is the condition of the tower’s existing structure. JEC commissioned an independent assessment of the structure before the tender was issued. Sources close to the project have told MEED that the report concluded that building work can restart.

The construction work for the superstructure of the tower, which began in the early 2010s with the local Saudi Binladin Group (SBG) as the contractor, is one-third complete.

SBG stopped working on the project in February 2018. In September this year, JEC called in the performance guarantees or bonds provided by SBG. A source close to the project said that the value of the bonds totals SR653m ($174m).

Almaiman confirmed that the developer has exercised its rights under the contract after having given SBG five years to re-engage.

While SBG is no longer working as the contractor on the project, the consultancy team remains the same. The architect is US-based Adrian Smith & Gordon Gill, and the engineering consultant is Lebanon’s Dar al-Handasah (Shair & Partners).

Project stakeholders 

The shareholders in JEC are Kingdom Holding Company with a 40 per cent stake, Bakhsh Group with a 40 per cent stake, and Sharbatly Group with a 20 per cent share.

In 2015, JEC and Saudi Arabia’s Alinma Investment established a $2.24bn fund to finance the first phase of the Jeddah Economic City project and Jeddah Tower. The Alinma Jeddah Economic City Fund is a sharia-compliant fund that will operate under the Saudi Arabian Capital Market Authority. 

Alinma Bank agreed to finance the fund, which is managed by Alinma Investment. Prince Alwaleed bin Talal bin Abdulaziz al-Saud, chairman of Kingdom Holding Company, was appointed as chair of the fund’s board. 


The 170-storey Jeddah Tower will have a variety of revenue streams and will
feature the world’s highest observation deck. Credit: Jeddah Economic Company

Development plans

Jeddah Tower is the centrepiece of the Jeddah Economic City development in the Obhur district, north of Jeddah. The project’s first phase, which includes Jeddah Tower, covers an area of 1.5 square kilometres.

The mixed-use tower will have 170 storeys, seven of which will be allocated to a five-star, 200-room Four Seasons Hotel. There will also be 11 storeys housing 121 serviced apartments, and seven storeys of offices. 

A further 61 storeys of the tower will comprise 318 residential units, a gym, spa, cafes and restaurants. Plans also include several sky lobbies and the world’s highest observation deck, located on the top floors of the tower, 660 metres above the ground. 

Development work on the project began in 2006. Building the world’s tallest tower requires state-of-the-art technologies and construction methods. 

The piling and foundations work for the tower was completed in 2014. Germany’s Bauer was the piling contractor, and 270 piles were cast, reaching 105 metres below ground. The raft sitting on top of the piles is one of the world’s largest reinforced steel foundations, with a thickness of between 4.5 and 5 metres. 

Cranage is a major challenge when constructing megatall towers. In early 2015, JEC took delivery of custom-made cranes, supplied by Germany’s Liebherr & WolffKran.

For elevators, Finland’s Kone was appointed to supply the fastest and highest double- decker elevator system in the world. The planned system will travel at a speed of more than 10 metres a second, rising to 660 metres. 


MEED's October 2023 special report on Saudi Arabia includes: 

> POLITICS: Saudi Arabia looks both east and west
> SPORTSaudi Arabia’s football vision goes global
> ECONOMY: Riyadh prioritises stability over headline growth
BANKSSaudi banks track more modest growth path
> UPSTREAMAramco focuses on upstream capacity building

> DOWNSTREAMSaudi chemical and downstream projects in motion
> POWERRiyadh rides power projects surge
> WATERSaudi water projects momentum holds steady
> GIGAPROJECTSGigaproject activity enters full swing
> TRANSPORTInfrastructure projects support Riyadh’s logistics ambitions
> JEDDAH TOWERJeddah developer restarts world’s tallest tower

https://image.digitalinsightresearch.in/uploads/NewsArticle/11177248/main.gif
Colin Foreman
Related Articles
  • Saudi Arabia battery storage awards provide fresh lift

    24 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The latest battery storage awards provide a welcome injection of investment into Saudi Arabia’s power market, which has seen a sharp slowdown in contract awards this year.

    Saudi Power Procurement Company’s four Group 1 storage service agreements, announced last week, are worth more than $1.16bn and cover 2,000MW of capacity.

    That is significant against the wider market. According to regional project tracker MEED Projects, Saudi Arabia recorded $19.7bn in power sector contract awards in the first seven months of 2025, compared with just $2.5bn in new awards in the same period this year.

    The battery energy storage system (bess) awards therefore account for a sizeable share of the activity recorded so far this year and provide a much-needed source of new contracting activity.

    Importantly, this is not a one-off. SPPC issued the request for proposal (RFP) for its second group of bess projects in July, covering six projects with a combined capacity of 3,000MW and 12,000MWh.

    With the Group 1 tender taking around 18 months from RFP to contract award, it is reasonable to expect Group 2 contracts to be signed in 2027.

    At the same time, the awards for six independent renewable plants under Round 7 of Saudi Arabia’s National Renewable Energy Programme (NREP), with a combined capacity of 5,300MW, are also likely to move into next year, with the latest bid deadlines now extending into September.

    Although a substantial pipeline remains in procurement, it is only once these projects move from tender to award and into construction that this pipeline translates into market activity.

    It is important that these tenders continue to progress at the pace established by the early rounds of Saudi Arabia’s renewable energy programme and now also SPPC’s independent storage provider bess scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962923/main.jpg
    Mark Dowdall
  • Qatar receives bids for major power grid expansion

    24 August 2026

     

    Qatar General Electricity & Water Corporation (Kahramaa) has received bids for several packages under a major power transmission expansion project tendered in April.

    The project covers new substations at multiple voltage levels, as well as the supply and installation of 400kV extra-high-voltage power cables. The overall scheme is estimated to cost $650m.

    It is being tendered as part of Kahramaa’s 2026 procurement plan, which includes 198 tenders with a total estimated value of QR21.4bn ($5.9bn).

    According to sources, bids were submitted for the following packages on 20 August:

    • Substation packages S1 and S2, covering new 132/11kV substations (estimated cost: $200m)
    • Package S3, covering new 66/11kV substations ($50m)
    • Package S4, including a new 400/220/132kV substation, as well as upgrades and modifications to existing 400kV and 220kV substations ($200m)
    • Package S5, covering new 132/11kV substations and upgrades to existing 132kV and 66kV substations ($100m)
    • Cable packages C1 and C2, covering 400kV cables ($100m)

    Kahramaa previously stated that foreign companies not registered in Qatar would be allowed to participate in the bidding, subject to meeting specified conditions, including registration and certification requirements.

    In June, the electricity and water utility awarded contracts worth more than QR2.2bn ($604m) to expand the electricity transmission network in the country’s western region.

    The engineering, procurement and construction (EPC) works will support the integration of the 2GW Dukhan solar power project into Qatar’s national electricity grid. The scope includes new and upgraded substations, as well as the installation of underground cables and overhead transmission lines.

    Kahramaa said contracts were awarded to local firm Voltage Engineering, Turkiye’s Best & Betas Consortium, India’s Larsen & Toubro and South Korea’s LS Cable.

    Of Kahramaa’s 2026 procurement plan, electricity transmission projects account for QR8.9bn ($2.4bn) and include the construction of new 400/132kV substations in Al-Wukair and Al-Mashaf, as well as the expansion of 400kV substations at Ras Laffan.

    These also cover the installation of 132kV underground cables between Al-Sailiya and Al-Rayyan over a 24-kilometre route, as well as upgrades to the 400kV and 220kV networks.

    Additionally, there are 64 planned electricity distribution projects managed by the Electricity Distribution Department that cover the medium-voltage and low-voltage networks throughout Doha and the regional municipalities. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962223/main.jpg
    Mark Dowdall
  • Maaden closes $1bn term loan and credit facility

    24 August 2026

    Saudi Arabian Mining Company (Maaden) has announced the closing of its inaugural international syndicated term loan and revolving credit facilities, worth a total of $1bn.

    The $500m international term loan facility will support Maaden’s growth agenda and general corporate purposes, including funding growth projects across its portfolio.

    The $500m international revolving credit facility, which is expected to remain undrawn, provides additional committed funding capacity “as Maaden continues to scale its business and execute its long-term growth strategy”.

    The transaction “was met with strong support from the international banking market, attracting participation from a diverse group of leading international banks across key global financial markets”, including the US, Canada, Europe, China and Japan. The facilities were oversubscribed, Maaden said.

    ALSO READ: Maaden and Aramco sign deal to create joint venture

    “The level of demand reflects the global banking community’s confidence in Maaden’s financial strength, strategic direction and ambitious growth plans,” the Saudi state miner said in its statement.

    “The facilities mark another significant milestone in Maaden’s funding journey – further diversifying its sources of funding and broadening its access to global capital providers as the company continues to advance its long-term growth ambitions.

    “Maaden continues to make significant progress across its growth pipeline, expanding production, advancing major projects and accelerating exploration as it builds a world-class mining company at the heart of Saudi Arabia’s economic transformation.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18962086/main4516.jpg
    Indrajit Sen
  • Dubai inflation slows to 5.3% in July

    24 August 2026

    Dubai’s annual inflation rate slowed to 5.3% in July, down from 5.7% in June, as a decline in transport costs eased pressure on consumer prices, according to Emirates NBD.

    The bank said the slowdown supported its view that price growth peaked at mid-year, and it expects inflation to continue easing through the rest of 2026. Monthly price growth slowed to 0.1% in July, from 0.4% in June, the weakest pace since February.

    Transport was the clearest sign of the moderation. Annual price growth in the category slowed to 11.9% in July, from 18.1% in June, as transport costs fell 3.7% over the month. Fuel and lubricant inflation eased to 24.1% year on year, from 48.3%, tracking a decline in local petrol prices.

    Petrol remains the main swing factor in the emirate’s inflation. Transport contributed 1.1 percentage points to headline inflation in July, down from 1.7 percentage points in June. Emirates NBD said the relief may prove temporary, with Super 98 petrol prices climbing 5.9% in August to leave them 33.8% higher than a year earlier. The bank expects headline inflation to edge higher in the August figures before easing again later in the year.

    The UAE deregulated petrol and diesel prices in 2015 and reviews them monthly against global prices, meaning changes in global fuel costs pass through to consumers quickly. Transport, which includes fuel, accounts for 9% of Dubai’s consumer price index basket.

    Housing remained the largest contributor to inflation even as its impulse faded. Housing and utilities, which account for about two-fifths of the basket, added 2.8 percentage points to headline inflation. Annual price growth in the category slowed to 7.0%, from 7.4% in January.

    Food inflation edged up to 7.8% year on year, from 7.6% in June, which the bank attributed to lingering supply-chain disruption from the regional conflict. Inflation in restaurants and hotels accelerated to 4.5% year on year, from 1.7% in June.

    Emirates NBD forecasts inflation of 2.9% by year-end but said risks to that projection were tilted to the upside, given lingering pressures in food and housing.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18961735/main1839.jpg
    Colin Foreman
  • Libya oil project on track for 2027 completion

    24 August 2026

     

    The project to develop a workers’ camp at Libya’s Erawin oil field is on track for completion next year, according to industry sources.

    The project, estimated to be worth about $50m, is being executed by the Libyan oil services company Al-Saraya Al-Hamara, headquartered in the city of Sebha.

    The Libyan company was awarded the contract in February 2025.

    The scope of the project includes:

    • Construction of an accommodation camp
    • Construction of the camp maintenance warehouse
    • Construction of the camp office
    • Construction of a fire brigade shelter
    • Construction of a kitchen and mess hall
    • Construction of a mosque
    • Construction of a laundry room
    • Construction of a clinic
    • Construction of parking facilities
    • Installation of a fire and gas system
    • Installation of a power generator
    • Construction of associated facilities

    The client on the project is Zallaf Libya Oil & Gas Exploration & Production Company.

    Zallaf Libya Oil & Gas Exploration & Production Company was established in Libya in 2013 and is wholly owned by Libya’s state-owned National Oil Corporation.

    The Erawin field development project is located about 800 kilometres south of Tripoli and 100km southwest of the El-Sharara field.

    Libya shipped its first cargo of crude from the Erawin oil field in November 2023.

    The shipment departed from Libya’s Zawiyah port and consisted of 600,000 barrels of crude.

    Australia-based Worley Parsons was appointed as the front-end engineering and design (feed) contractor for the early production facility project in 2019.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18953632/main.jpg
    Wil Crisp