Saudi’s Jeddah Tower reaches for new heights

27 September 2023

 

A landmark moment came for Saudi Arabia’s construction sector in mid-September when Jeddah Economic Company (JEC) invited firms to bid for a contract to complete the world’s tallest tower project, the 1,000-metre-plus Jeddah Tower.

Work on the tower “is back in full [swing]”, a source close to the project told MEED.

When completed, Jeddah Tower will be the first structure in history to exceed 1 kilometre in height. It will also be taller than the current world’s tallest building, Dubai’s Burj Khalifa, by more than 172 metres. 

When contacted by MEED, Talal Ibrahim Almaiman, CEO of Kingdom Holding Company, confirmed that the tender to complete the record-breaking tower had been officially issued.

The companies that have been invited to bid for the contract include:

  • Almabani (local)
  • Bawani (local)
  • China Harbour (China)
  • China State Construction Engineering Corporation (China)
  • Consolidated Contractors Company (CCC – Lebanon)
  • El-Seif Engineering Contracting (local)
  • Hyundai Engineering Construction (South Korea)
  • Mohammed Abdulmohsin al-Kharafi & Sons (Kuwait)
  • Nesma & Partners (local)
  • Powerchina (China)
  • Samsung C+T (South Korea)
  • Saudi Freyssinet (local)
  • Skanska (Sweden)
  • Strabag (Europe)

The contractors have been given three months to prepare their bids, and are expected to form joint ventures comprising local and international partners. It is understood that contractors have visited the site.

When completed, Jeddah Tower will be the first structure in history to exceed 1 kilometre in height

Restarting construction

One important question for the potential bidders is the condition of the tower’s existing structure. JEC commissioned an independent assessment of the structure before the tender was issued. Sources close to the project have told MEED that the report concluded that building work can restart.

The construction work for the superstructure of the tower, which began in the early 2010s with the local Saudi Binladin Group (SBG) as the contractor, is one-third complete.

SBG stopped working on the project in February 2018. In September this year, JEC called in the performance guarantees or bonds provided by SBG. A source close to the project said that the value of the bonds totals SR653m ($174m).

Almaiman confirmed that the developer has exercised its rights under the contract after having given SBG five years to re-engage.

While SBG is no longer working as the contractor on the project, the consultancy team remains the same. The architect is US-based Adrian Smith & Gordon Gill, and the engineering consultant is Lebanon’s Dar al-Handasah (Shair & Partners).

Project stakeholders 

The shareholders in JEC are Kingdom Holding Company with a 40 per cent stake, Bakhsh Group with a 40 per cent stake, and Sharbatly Group with a 20 per cent share.

In 2015, JEC and Saudi Arabia’s Alinma Investment established a $2.24bn fund to finance the first phase of the Jeddah Economic City project and Jeddah Tower. The Alinma Jeddah Economic City Fund is a sharia-compliant fund that will operate under the Saudi Arabian Capital Market Authority. 

Alinma Bank agreed to finance the fund, which is managed by Alinma Investment. Prince Alwaleed bin Talal bin Abdulaziz al-Saud, chairman of Kingdom Holding Company, was appointed as chair of the fund’s board. 


The 170-storey Jeddah Tower will have a variety of revenue streams and will
feature the world’s highest observation deck. Credit: Jeddah Economic Company

Development plans

Jeddah Tower is the centrepiece of the Jeddah Economic City development in the Obhur district, north of Jeddah. The project’s first phase, which includes Jeddah Tower, covers an area of 1.5 square kilometres.

The mixed-use tower will have 170 storeys, seven of which will be allocated to a five-star, 200-room Four Seasons Hotel. There will also be 11 storeys housing 121 serviced apartments, and seven storeys of offices. 

A further 61 storeys of the tower will comprise 318 residential units, a gym, spa, cafes and restaurants. Plans also include several sky lobbies and the world’s highest observation deck, located on the top floors of the tower, 660 metres above the ground. 

Development work on the project began in 2006. Building the world’s tallest tower requires state-of-the-art technologies and construction methods. 

The piling and foundations work for the tower was completed in 2014. Germany’s Bauer was the piling contractor, and 270 piles were cast, reaching 105 metres below ground. The raft sitting on top of the piles is one of the world’s largest reinforced steel foundations, with a thickness of between 4.5 and 5 metres. 

Cranage is a major challenge when constructing megatall towers. In early 2015, JEC took delivery of custom-made cranes, supplied by Germany’s Liebherr & WolffKran.

For elevators, Finland’s Kone was appointed to supply the fastest and highest double- decker elevator system in the world. The planned system will travel at a speed of more than 10 metres a second, rising to 660 metres. 


MEED's October 2023 special report on Saudi Arabia includes: 

> POLITICS: Saudi Arabia looks both east and west
> SPORTSaudi Arabia’s football vision goes global
> ECONOMY: Riyadh prioritises stability over headline growth
BANKSSaudi banks track more modest growth path
> UPSTREAMAramco focuses on upstream capacity building

> DOWNSTREAMSaudi chemical and downstream projects in motion
> POWERRiyadh rides power projects surge
> WATERSaudi water projects momentum holds steady
> GIGAPROJECTSGigaproject activity enters full swing
> TRANSPORTInfrastructure projects support Riyadh’s logistics ambitions
> JEDDAH TOWERJeddah developer restarts world’s tallest tower

https://image.digitalinsightresearch.in/uploads/NewsArticle/11177248/main.gif
Colin Foreman
Related Articles
  • Firms prepare Hudayriat East PPP tunnels advisory bids

    25 June 2026

     

    Abu Dhabi’s Modon Infrastructure, formerly Gridora, has tendered a contract for technical advisory services for the construction of two underwater tunnels connecting the eastern side of Hudayriat Island with mainland Abu Dhabi.

    Consultants have until 26 June to submit their proposals.

    The project includes the construction of a 4.8-kilometre (km) highway, with four lanes in each direction, connecting Hudayriat Island to Mussafah 8th Street.

    The project will be delivered on a public-private partnership (PPP) basis in coordination with the Abu Dhabi Department of Municipalities and Transport and the Abu Dhabi Investment Office.

    The contract term is expected to be 25 years.

    The latest infrastructure development in Abu Dhabi follows Modon Infrastructure’s invitation in May for firms to register for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will also be developed on a PPP basis.

    Modon Infrastructure will act as the lead developer, holding the majority equity stake in the project company. It will award the engineering, procurement and construction contract, as well as the operations and maintenance services and advisory appointments.

    The second phase of the MIPP involves the construction of about 11km of highways, including a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also covers the construction of three interchanges: the E20, E10 and Dumbbell interchanges on Al-Sammaliyyah Island.

    The project includes several major structures, such as the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange with cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further key elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover (open) tunnel on Bilrimaid Island. The project will be completed with another tunnel connecting Bilrimaid Island to Um-Yifeenah Island.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17410214/main.jpg
    Yasir Iqbal
  • Algeria tenders upstream oil project contract

    25 June 2026

    Algeria’s state-owned national oil and gas company, Sonatrach, has tendered a contract for the development and rehabilitation of the central processing facility (CPF) at the Bir Berkine oil and gas field.

    The scope of the contract includes the study, supply, construction and commissioning of a project to rehabilitate the CPF facilities at the field, which is located in the Hassi Mesaoud region.

    Sonatrach says in the tender documents that the objective of the project is to ensure the continuity of production activities “under stable and secure operating conditions”.

    It also says the project aims to improve production yields and quality.

    The contract includes both initial and detailed studies as well as the supply of all equipment and materials.

    It also includes the execution of works, the assembly of all equipment and materials, and the commissioning of all relevant facilities.

    The tender has a two-stage submission process, with the first stage requiring technical bids to be submitted by 23 August.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17423013/main3916.jpg
    Wil Crisp
  • Red Sea Global tenders King Salman Bay construction work

    25 June 2026

     

    Saudi gigaproject developer Red Sea Global (RSG) has tendered a contract inviting firms to undertake marine infrastructure works at King Salman Bay on the Red Sea coast, north of Jeddah.

    The scope includes dredging and earthworks, as well as quay wall and edge protection works spanning about 11 kilometres.

    The bid submission deadline is 31 July.

    King Salman Bay is expected to be a waterfront development aimed at reshaping the city’s northern Red Sea frontage into a mixed-use destination, anchored by public-realm improvements and leisure-led development.

    The update follows RSG’s award of an estimated SR100m ($27m) contract to construct a solid waste management centre at its Red Sea Project. The scope includes four buildings: a material recycling facility, a transfer station, an administration building and a vehicle maintenance building.

    In October last year, MEED reported that RSG had secured a SR6.5bn ($1.7bn) credit facility to further develop Amaala, its luxury tourism destination on Saudi Arabia’s northwestern Red Sea coast.

    According to an official statement, “The funding is led by Riyad Bank as the sole underwriter, along with Saudi Investment Bank and Bank Al-Bilad as mandated lead arrangers.

    “The loan arrangement comprises a mix of conventional and Islamic financing and adheres to RSG’s Green Loan Framework, which was first established when it secured private funding from a consortium of four banks for the Red Sea destination in 2021,” the statement added.

    The announcement followed RSG’s opening of its first properties for sale at Amaala, including branded residential communities and a five-bedroom villa on a private island.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17430045/main.jpg
    Yasir Iqbal
  • MECC submits lowest bid on three Kuwaiti oil and gas contracts

    25 June 2026

     

    Kuwait-based Mechanical Engineering & Contracting Company (MECC) has submitted the lowest bid across three separate contracts tendered by the state-owned upstream operator Kuwait Oil Company (KOC).

    The total value of the low bids is $427m, and all of the contracts are focused on developing substations to power industrial lift pumps and remote header manifolds

    Five companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 6, 10 and 12 in southern and eastern Kuwait.

    The bidders were:

    • MECC: KD65,760,000 ($212m)
    • Heavy Engineering Industries & Shipbuilding Company: KD70,630,000 ($228m)
    • Amco Engineering & Construction: KD73,446,100 ($237m)
    • Combined Group Contracting Company: KD76,186,000 ($246m)
    • Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD79,332,417 ($256m)

    Six companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 8 and 13 in southern and eastern Kuwait.

    The bidders were:

    • MECC: KD30,760,000 ($99m)
    • Badr Al-Mulla & Brothers: KD32,662,040 ($106m)
    • Heavy Engineering Industries & Shipbuilding Company: KD34,139,000 ($110m)
    • Industrial Company for Electrical Projects: KD36,375,520 ($118m)
    • Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD37,278,526 ($120m)
    • Combined Group Contracting Company: KD37,790,000 ($122m)

    Eight companies submitted bids for a contract focused on developing several substations to power industrial lift pumps and remote header manifolds in areas 7, 9, and 11 in southern and eastern Kuwait.

    The bidders were:

    • MECC: KD35,760,000 ($116m)
    • Badr Al-Mulla & Brothers: KD39,447,165 ($127m)
    • Amco Engineering & Construction: KD39,736,800 ($128m)
    • Heavy Engineering Industries & Shipbuilding Company: KD40,105,000 ($130m)
    • Industrial Company for Electrical Projects: KD43,238,265 ($140m)
    • Engineering Company for Petroleum & Chemical Industries (Enppi): KD43,514,805 ($141m)
    • Combined Group Contracting Company: KD43,650,000 ($141m)
    • Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD43,706,826 ($141m)

    Kuwait’s oil and gas sector has been in crisis in recent months due to disruption from the regional conflict that started after the US and Israel attacked Iran on 28 February 2026.

    A preliminary peace agreement between the US and Iran, which was announced on 14 June, has increased optimism that disruption to the sector will decrease in the coming weeks.

    Under the terms of the agreement, both sides have stated that the free flow of vessels will be permitted through the Strait of Hormuz, through which nearly all of Kuwait’s crude oil is normally exported.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17423009/main.jpg
    Wil Crisp
  • Chinese firm wins $265m Saudi hospital contract

    24 June 2026

    Zhejiang Construction International, the local subsidiary of Chinese contractor Zhejiang Construction Investment Group, has won a $265m contract to build the Prince Mohammed Bin Fahd University Speciality Hospital in Al-Khobar.

    Construction is expected to take three years from the start date.

    Prince Mohammed Bin Fahd University awarded the contract.

    Located in Al-Raja district, Al-Khobar, in Saudi Arabia’s Eastern Province, the hospital project will cover about 60,000 square metres.

    The contract covers the construction of a 10-storey hospital building, two five-storey auxiliary buildings connected by corridors and a basement.

    Work will include civil works, mechanical and electrical installation, curtain walling, landscaping, detailed design and the procurement of medical equipment.

    The award is the latest in a series of contracts secured by Chinese contractors from Saudi entities in recent months.

    Last week, MEED reported that Saudi Arabia’s Ministry of Municipalities & Housing awarded contracts worth more than SR1.9bn ($506m) to Chinese contractors for two residential developments in the kingdom.

    China Architectural Construction Corporation won the first contract, valued at SR875m ($233m), to build 2,010 housing units at the Al-Ruba residential project in Riyadh.

    China State Construction Engineering Corporation secured the other contract, valued at more than SR1bn ($266m), for the Al-Rasha Al-Faisaliah residential project in Dammam, comprising 2,426 housing units.

    GlobalData expects Saudi Arabia’s construction industry to record average annual growth of 5.2% in 2025-28, supported by investments in transport, electricity, housing and tourism infrastructure, as well as the $850bn-plus gigaprojects programme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17412846/main.jpg
    Yasir Iqbal