Saudi’s Jeddah Tower reaches for new heights
27 September 2023
A landmark moment came for Saudi Arabia’s construction sector in mid-September when Jeddah Economic Company (JEC) invited firms to bid for a contract to complete the world’s tallest tower project, the 1,000-metre-plus Jeddah Tower.
Work on the tower “is back in full [swing]”, a source close to the project told MEED.
When completed, Jeddah Tower will be the first structure in history to exceed 1 kilometre in height. It will also be taller than the current world’s tallest building, Dubai’s Burj Khalifa, by more than 172 metres.
When contacted by MEED, Talal Ibrahim Almaiman, CEO of Kingdom Holding Company, confirmed that the tender to complete the record-breaking tower had been officially issued.
The companies that have been invited to bid for the contract include:
- Almabani (local)
- Bawani (local)
- China Harbour (China)
- China State Construction Engineering Corporation (China)
- Consolidated Contractors Company (CCC – Lebanon)
- El-Seif Engineering Contracting (local)
- Hyundai Engineering Construction (South Korea)
- Mohammed Abdulmohsin al-Kharafi & Sons (Kuwait)
- Nesma & Partners (local)
- Powerchina (China)
- Samsung C+T (South Korea)
- Saudi Freyssinet (local)
- Skanska (Sweden)
- Strabag (Europe)
The contractors have been given three months to prepare their bids, and are expected to form joint ventures comprising local and international partners. It is understood that contractors have visited the site.
When completed, Jeddah Tower will be the first structure in history to exceed 1 kilometre in height
Restarting construction
One important question for the potential bidders is the condition of the tower’s existing structure. JEC commissioned an independent assessment of the structure before the tender was issued. Sources close to the project have told MEED that the report concluded that building work can restart.
The construction work for the superstructure of the tower, which began in the early 2010s with the local Saudi Binladin Group (SBG) as the contractor, is one-third complete.
SBG stopped working on the project in February 2018. In September this year, JEC called in the performance guarantees or bonds provided by SBG. A source close to the project said that the value of the bonds totals SR653m ($174m).
Almaiman confirmed that the developer has exercised its rights under the contract after having given SBG five years to re-engage.
While SBG is no longer working as the contractor on the project, the consultancy team remains the same. The architect is US-based Adrian Smith & Gordon Gill, and the engineering consultant is Lebanon’s Dar al-Handasah (Shair & Partners).
Project stakeholders
The shareholders in JEC are Kingdom Holding Company with a 40 per cent stake, Bakhsh Group with a 40 per cent stake, and Sharbatly Group with a 20 per cent share.
In 2015, JEC and Saudi Arabia’s Alinma Investment established a $2.24bn fund to finance the first phase of the Jeddah Economic City project and Jeddah Tower. The Alinma Jeddah Economic City Fund is a sharia-compliant fund that will operate under the Saudi Arabian Capital Market Authority.
Alinma Bank agreed to finance the fund, which is managed by Alinma Investment. Prince Alwaleed bin Talal bin Abdulaziz al-Saud, chairman of Kingdom Holding Company, was appointed as chair of the fund’s board.
The 170-storey Jeddah Tower will have a variety of revenue streams and will
feature the world’s highest observation deck. Credit: Jeddah Economic Company
Development plans
Jeddah Tower is the centrepiece of the Jeddah Economic City development in the Obhur district, north of Jeddah. The project’s first phase, which includes Jeddah Tower, covers an area of 1.5 square kilometres.
The mixed-use tower will have 170 storeys, seven of which will be allocated to a five-star, 200-room Four Seasons Hotel. There will also be 11 storeys housing 121 serviced apartments, and seven storeys of offices.
A further 61 storeys of the tower will comprise 318 residential units, a gym, spa, cafes and restaurants. Plans also include several sky lobbies and the world’s highest observation deck, located on the top floors of the tower, 660 metres above the ground.
Development work on the project began in 2006. Building the world’s tallest tower requires state-of-the-art technologies and construction methods.
The piling and foundations work for the tower was completed in 2014. Germany’s Bauer was the piling contractor, and 270 piles were cast, reaching 105 metres below ground. The raft sitting on top of the piles is one of the world’s largest reinforced steel foundations, with a thickness of between 4.5 and 5 metres.
Cranage is a major challenge when constructing megatall towers. In early 2015, JEC took delivery of custom-made cranes, supplied by Germany’s Liebherr & WolffKran.
For elevators, Finland’s Kone was appointed to supply the fastest and highest double- decker elevator system in the world. The planned system will travel at a speed of more than 10 metres a second, rising to 660 metres.
MEED's October 2023 special report on Saudi Arabia includes:
> POLITICS: Saudi Arabia looks both east and west
> SPORT: Saudi Arabia’s football vision goes global
> ECONOMY: Riyadh prioritises stability over headline growth
> BANKS: Saudi banks track more modest growth path
> UPSTREAM: Aramco focuses on upstream capacity building
> DOWNSTREAM: Saudi chemical and downstream projects in motion
> POWER: Riyadh rides power projects surge
> WATER: Saudi water projects momentum holds steady
> GIGAPROJECTS: Gigaproject activity enters full swing
> TRANSPORT: Infrastructure projects support Riyadh’s logistics ambitions
> JEDDAH TOWER: Jeddah developer restarts world’s tallest tower
Exclusive from Meed
-
Jordan 2025 country profile and databank
30 December 2024
-
Iraq 2025 country profile and databank
30 December 2024
-
Regional downstream sector prepares for consolidation
30 December 2024
-
Oman 2025 country profile and databank
30 December 2024
-
Morocco 2025 country profile and databank
30 December 2024
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Jordan 2025 country profile and databank
30 December 2024
https://image.digitalinsightresearch.in/uploads/NewsArticle/13175149/main.gif -
Iraq 2025 country profile and databank
30 December 2024
https://image.digitalinsightresearch.in/uploads/NewsArticle/13175051/main.gif -
Regional downstream sector prepares for consolidation
30 December 2024
The Middle East and North Africa (Mena) region’s midstream and downstream oil, gas and petrochemicals sectors together had one of their best years on record in 2024, with state-owned companies and private players collectively spending close to $38bn on projects.
Saudi Arabia emerged as the biggest regional spender on midstream and downstream projects. To address incremental volumes of gas entering the grid as Saudi Aramco increases its conventional and unconventional gas production, the state enterprise has spent more than $17bn on gas processing and transportation projects this year.
In April 2024, Aramco awarded $7.7bn in engineering, procurement and construction (EPC) contracts for a project to expand the Fadhili gas plant in the Eastern Province of Saudi Arabia. The project is expected to increase the plant’s processing capacity from 2.5 billion cubic feet a day (cf/d) to up to 4 billion cf/d.
On 30 June, Aramco awarded 15 lump-sum turnkey contracts for the third expansion phase of the Master Gas System (MGS-3), worth $8.8bn. Then, in August, the company awarded contracts for the remaining two packages of the MGS-3 project, which were worth $1bn.
Saudi Aramco divided EPC works on the MGS-3 project into 17 packages. The first two packages involve upgrading existing gas compression systems and installing new gas compressors. The 15 other packages relate to laying gas transport pipelines at various locations in the kingdom.
The Master Gas System expansion will increase the size of the network and raise its total capacity by an additional 3.15 billion cf/d by 2028 with the installation of about 4,000 kilometres
of pipelines and 17 new gas compression trains.Abu Dhabi capex
The UAE has been the second-largest spender on midstream, downstream and chemicals projects in 2024, led by investments from Abu Dhabi National Oil Company (Adnoc) and Taziz – its 60:40 joint venture with industrial holding entity ADQ.
Adnoc’s biggest capital expenditure (capex) was in the form of a $5.5bn EPC contract that it awarded to a consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy to develop a greenfield liquefied natural gas (LNG) terminal complex in Ruwais.
The upcoming Ruwais LNG export terminal will have the capacity to produce about 9.6 million tonnes a year (t/y) of LNG from two processing trains, each of which has a capacity of 4.8 million t/y. When the project is commissioned, Adnoc’s LNG production capacity will more than double to about 15 million t/y.
Adnoc Group subsidiary Adnoc Gas has also advanced a project to expand its sales gas pipeline network across the UAE, which is known as Estidama. The Abu Dhabi-listed company has awarded two EPC packages of the project this year, which together were worth more than $500m.
Adnoc Gas is expected to award the contract for another Estidama package before the end of 2024 that covers the construction of a pipeline that will provide feedstock from its Habshan gas processing plant to the upcoming Ruwais LNG complex.
Taziz, meanwhile, awarded three EPC contracts totalling $2bn for infrastructure works at the industrial chemicals zone that it is developing in Ruwais Industrial City.
Spending to plateau
Having reached a peak in spending, and with EPC contracts awarded for strategic midstream, downstream and chemicals projects in 2024, the Mena region is set to enter a period of more pragmatic project spending in 2025. However, this does not imply that a slump in project capex is likely, and the region could once again equal the level of contract awards made in 2024.
One of the largest projects that may be awarded in 2025 is the main contract for the North Field West LNG project – the third phase of QatarEnergy’s LNG expansion programme.
The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme.
The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore
gas reserve.Taziz is also on course to make progress with the second expansion phase of its derivatives complex, which will more than double the number of chemicals produced at the industrial hub. The expansion’s centrepiece will be a large-scale steam cracker that will supply feedstocks to the several new chemical plants earmarked for third-party investments.
In Saudi Arabia, there has been speculation that Aramco may be revisiting its investment strategy and execution approach for its strategic liquids-to-chemicals programme.
The aim of the programme is to derive greater economic value from every barrel of crude produced in the kingdom by converting 4 million barrels a day (b/d) of Aramco’s oil production into high-value petrochemicals and chemicals feedstocks by 2030.
Aramco has divided its liquids-to-chemicals programme into four main projects. It took a major step forward
in September 2023 by selecting US firm KBR, France’s Technip Energies, UK-based Wood Group and Australia- headquartered Worley to provide project management consultancy services for the four different segments of the scheme.Progress on a programme as big as the liquids-to-chemicals scheme is expected to be measured and laboured.
While day-to-day the advancement might appear sluggish, Amin Nasser, Aramco’s president and CEO, said earlier in 2024 that the Saudi energy giant is on track to achieve its crude oil-to-chemicals conversion goal by 2030.
“We are on track to achieve our target of 4 million b/d liquids-to-chemicals [conversion capacity] by 2030,” he said.
Meanwhile, Kuwait is in a similar situation with its planned Al-Zour integrated complex upgrade programme (Zicup), which has suffered significant delays in recent years. However, state-owned Kuwait Integrated Petroleum Industries Company (Kipic), the project’s operator, recently appointed a team to look into the logistics of developing a benzine pipeline as part of the estimated $10bn Zicup scheme.
Although this may be a small step, it does indicate that Kuwait remains determined to achieve its ambition of developing a large-scale petrochemicals facility, which, when integrated with its $16bn Al-Zour refinery, could become one of the biggest integrated refining and petrochemicals complexes in the Mena region.
https://image.digitalinsightresearch.in/uploads/NewsArticle/13145202/main.gif -
Morocco 2025 country profile and databank
30 December 2024
https://image.digitalinsightresearch.in/uploads/NewsArticle/13175213/main.gif -
Oman 2025 country profile and databank
30 December 2024
https://image.digitalinsightresearch.in/uploads/NewsArticle/13175226/main.gif