Saudi water capacity procurement takes new turn

20 December 2024

Commentary
Jennifer Aguinaldo
Energy & technology editor

The better part of 2024 saw Saudi Water Authority (SWA), formerly Saline Water Conversion Corporation (SWCC), the world’s largest water desalinator, tender and award several contracts to build new seawater reverse osmosis (SWRO) plants in Saudi Arabia.

The four projects have a total combined capacity of over 2 million cubic metres a day (cm/d) and cost about $2bn.

Unlike the independent water projects (IWPs) being procured by Saudi Water Partnership Company (SWPC), SWA’s projects were being procured using an engineering, procurement, construction and commissioning (EPCC) model.

The urgency of additional water desalination capacity, and the need to lower the carbon intensity of the kingdom’s existing water desalination fleet, underpinned SWA’s decision to take the EPCC route, which typically takes less time compared with the build, own and operate (BOO) model, the preferred model for SWPC’s projects.

SWA, however, cancelled two of the four SWRO contract awards towards the end of 2024 while reassuring the bidders that the contracts would be rendered “over the coming weeks”, most likely with recalibrated or lower capacity than the initial plans.

The cancellation has put the bidders in an awkward situation. For example, the value of shares of India’s VA Tech Wabag – the winning bidder for the Yanbu SWRO contract – plunged by 16% following the cancellation announcement.

Notably, SWPC did not officially sign new water-purchase agreements in the first 11 months of 2024 despite naming the preferred bidders for the Ras Mohaisen IWP, which has a capacity of 300,000 cm/d, and the Jubail 4 and 6 IWP, which together have a capacity of 600,000 cm/d.

These contracts are expected to be awarded in early 2025, coinciding with the release of new tenders for future IWP and independent sewage treatment plant projects.

SWPC is also expected to finalise the award of the contract to develop the kingdom’s second independent water transmission pipeline that links Jubail and Buraydah shortly, after naming a team comprising Aljomaih Energy & Water, Nesma Company and Buhur for Investment Company as the preferred bidder.

A third entity, Water Transmission Company (WTCO), has motored ahead by tendering water transmission pipeline projects using a hybrid approach comprising engineering, procurement and construction (EPC) and public-private partnership (PPP) models for different projects.

Despite the SWA contract cancellations, Saudi Arabia’s water sector has performed relatively well. The value of awarded contracts over the past 11 months reached roughly $14bn, closely matching the previous year’s record-high figure.

The $4.7bn contract to construct dams at Trojena, which Neom awarded to the Italian contractor Webuild in January, helped the kingdom’s water sector avoid a downturn this year.

The kingdom’s various water stakeholders are expected to foster closer coordination of their procurement programmes in the future to enable more streamlined tendering procedures.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13153186/main.jpg
Jennifer Aguinaldo
Related Articles
  • Fuel storage facility attacked in Bahrain

    13 March 2026

    Register for MEED’s 14-day trial access 

    Fuel storage tanks at a facility on Bahrain’s Muharraq Island were targeted in an attack attributed to Iran, according to a statement from Bahrain’s Interior Ministry.

    The ministry put out an alert for people in surrounding neighbourhoods “to remain in their homes, close windows and ventilation openings, as a precautionary measure against possible exposure to smoke”.

    Videos of the incident, which took place on 12 March, showed a large fire emitting black smoke. The fire was later extinguished by teams of firefighters.

    Bahrain’s international airport is also located on Muharraq Island.

    Iran has been firing missiles at a range of targets in nearby countries since it was attacked by the US and Israel on 28 February.

    On 11 March, a similar attack on fuel storage tanks in Oman led to the closure of some terminals at the port of Salalah.

    Footage recorded by vessel crews at the port, which is the largest in the country, showed explosions and a large fire.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15963333/main.png
    Wil Crisp
  • Bahrain contacts engineering companies over Sitra refinery damage

    13 March 2026

    Register for MEED’s 14-day trial access 

    Bahrain’s national oil and gas company Bapco Energies is in touch with international engineering companies about damage done to the Sitra refinery by Iranian strikes, according to industry sources.

    In a statement on 9 March, Bapco Energies said its decision to issue the force majeure notice followed “the recent attack on its refinery complex”, without providing details.

    Bapco Energies is yet to share full details about the extent of the damage caused to the refinery, sources said.

    One source said: “Bapco has been corresponding with several companies with regard to the damage. It is being careful not to share confidential information, but it has reached out.”

    Prior to Bapco’s 9 March statement, the Sitra refinery was hit by a strike earlier in the day.

    That strike on the Sitra refinery was the second strike on the complex in days.

    Iranian missiles hit the facility on 5 March, resulting in parts of the refinery being engulfed in flames.

    Iran has been firing missiles at a range of targets in nearby countries since it was attacked by the US and Israel on 28 February.

    In November last year, MEED reported that Bapco Energies was in the final stages of ramping up volumes processed by new units that were installed as part of the Bapco Modernisation Programme (BMP).

    The project at the Sitra refinery in Bahrain is estimated to have been worth $7bn and was inaugurated by Bahrain’s King Hamad Bin Isa Al-Khalifa in December 2024.

    At the time, the companies involved in the engineering, procurement and construction (EPC) contract for the project were still working on the site to assist with efforts to increase volumes.

    Bapco Energies awarded the main $4.2bn contract to perform EPC works on the BMP to a consortium led by France’s Technip Energies in February 2018.

    The consortium also included Spain’s Tecnicas Reunidas and South Korea’s Samsung E&A.

    Technip Energies also performed the project’s front-end engineering and design work. US oil and gas producer Chevron acted as a consultant on the BMP, while Australia-based Worley was the project management consultant.

    In March 2024, after a series of setbacks and delays, France’s Total Energies was brought in to support Bapco in “optimising” the project.

    The BMP is central to Bahrain’s Vision 2030 economic development strategy, and Bapco has said that it is crucial to boosting the country’s long-term downstream potential.

    The BMP was originally expected to reach mechanical completion in 2023, with operations set to begin in 2024.

    The core objective of the BMP was to upgrade the Sitra refinery – Bahrain’s only oil refining asset, which is 90 years old.

    One of the key units to be built as part of the BMP was a residual hydrocracking unit (RHCU) powered by technology licensed from US-based Chevron Lummus Global. The BMP team has built a two-train RHCU with a capacity of 65,000 barrels a day.

    The Sitra refinery includes seven crude distillation units (CDUs) and vacuum distillation units (VDUs) as part of the BMP.

    The new 225,000 b/d integrated crude and vacuum unit replaced CDUs 1, 2 and 3 and VDUs 1 and 3, which had served Bapco Energies for over 80 years.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15963329/main.jpg
    Wil Crisp
  • Italian consultant wins Egypt battery storage contract

    13 March 2026

    Italy-headquartered consultancy Rina has announced its appointment as owner’s engineer for the 1 gigawatt-hour Nefertiti battery energy storage system (bess) project in Egypt.

    The project is being developed by Dubai-based firm Amea Power and is located in the Benban Photovoltaic Industrial Park in Aswan.

    The scheme will deploy a 500MW/1,000 megawatt-hour (MWh) utility-scale bess, making it the largest independent energy storage project in Africa.

    In March, a group comprising China Energy Engineering International Group, Zhejiang Thermal Power Construction and Southwest Electric Power Design & Research Institute was appointed as the main engineering, procurement and construction contractor.

    The $250m project also includes the construction of a 220kV substation, upgrades to an adjacent substation and development of grid network connection infrastructure.

    Under the owner’s engineer scope, Rina will deliver engineering design review, construction monitoring and commissioning support. The company will also undertake performance verification.

    Egypt’s utilities sector had its strongest year in over a decade in 2025, hitting $5bn in contract awards for the first time since 2015. 

    Last July, Amea Power commissioned Egypt’s first-ever utility-scale bess.

    The 300MWh project had previously reached financial close in June.

    The bess project is an extension of Amea Power’s operational 500MW solar photovoltaic plant in Aswan Governorate, which was commissioned in December 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15954234/main.jpg
    Mark Dowdall
  • Oil tankers attacked in Iraqi waters

    12 March 2026

    Register for MEED’s 14-day trial access 

    Two tankers carrying Iraqi oil products were set on fire after being attacked in Iraq’s territorial waters near the country’s southern export terminals, increasing concerns about global energy supplies.

    After the attack, the country’s Oil Ministry said that it saw the attacks as “a worrying indicator of escalating tensions in a vital area of the global economy and energy supply”.

    It added that “the safety and safety of navigation in international sea corridors and energy supply routes should be kept away from regional conflicts”.

    The Oil Ministry said the attacks had a direct impact on the stability of the global economy and energy markets, as well as putting the lives of civilians and workers in the maritime transport sector at risk.

    Farhan Al-Fartousi, from Iraq’s General Company for Ports, told state television that one crew member had been killed in the attack and that 38 crew members had been rescued.

    Iraq’s state-owned oil marketing company Somo said that the Maltese-flagged oil tanker Zefyros was attacked as it was preparing to enter the port of Khor Al-Zoubair, where it would have taken on board an additional 30,000 tonnes of liquid naphtha.

    The second targeted vessel, Safesea Vishnu, was sailing under the Marshall Islands flag and was chartered by an Iraqi company, according to Somo.

    Iraq’s oil production has fallen steeply since the conflict began, from 3.3 million barrels a day (b/d) to less than 1 million b/d.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15951323/main.png
    Wil Crisp
  • Chevron yet to agree terms for Iraq oil field takeover

    12 March 2026

     

    US-based oil company Chevron is yet to agree terms with Iraqi state-owned Basra Oil Company (BOC) for its potential takeover of Iraq’s West Qurna-2 oil field, according to industry sources.

    Last month, Chevron signed a preliminary agreement with BOC to explore taking control of the West Qurna-2 oil field.

    Until recently, West Qurna-2 was operated by Russia’s Lukoil, which faces a 28 February deadline to divest its assets in Iraq under sanctions.

    One industry source said: “Chevron is yet to agree terms, and it has made it clear that it wants different terms to the contract that Lukoil had.”

    In January, Iraq’s cabinet approved temporarily nationalising petroleum operations at the West Qurna-2 oil field until a new operator was found.

    Lukoil declared force majeure at the West Qurna-2 oil field in November, after sanctions by the UK, EU and US were announced in October.

    The Russian company had a 75% stake in the asset.      

    Prior to Russia’s Lukoil declaring force majeure, Iraq’s state oil authorities froze all cash and crude payments to Lukoil in compliance with the sanctions.

    In a statement released on 1 December 2025, Iraq’s Oil Ministry said that it had extended “direct and exclusive invitations to a number of major American oil companies”.

    Awarded to Lukoil in 2009, West Qurna-2 lies about 65 kilometres northwest of Basra in southern Iraq and produces about 480,000 barrels a day (b/d) of oil, accounting for roughly 10% of the country’s total oil output.

    At the same meeting on 23 February, Chevron also signed a deal relating to the development of the Nasiriyah field, four exploration sites in the province of Dhi Qar and a field in the province of Salahaddin.

    Chevron signed an agreement in principle with Iraq in August 2025 to develop the Nasiriyah oil project in the province of Dhi Qar.

    At the time, Iraq said it expected the Nasiriyah project to reach a production capacity of 600,000 b/d within seven years.


    READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDF

    Riyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.

    Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15944830/main.png
    Wil Crisp