Saudi water begins next growth phase

10 March 2023

 

Saudi Arabia’s National Water Strategy 2030 continues to drive investments in the kingdom’s water desalination, treatment and distribution sector.

The strategy aims to reduce the water demand-supply gap and ensure desalinated water accounts for 90 per cent of the national urban supply to reduce reliance on non-renewable ground sources.

The need to boost the security of supply amid rising demand, volatile costs and increased compliance with sustainability goals is also driving project activity – particularly in terms of using more energy-efficient technologies to convert seawater into potable water – as well as improving storage capacity.

As of March, an estimated 2.66 million cubic metres a day (cm/d) of water desalination capacity is under construction by the main water utility provider Saline Water Conversion Corporation (SWCC) and state water offtaker Saudi Water Partnership Company (SWPC). 

At least a further 2.4 million cm/d of capacity is under procurement using both the independent water producer (IWP) model, mainly through SWPC, and the engineering, procurement and construction (EPC) model, primarily via SWCC. 

Following the award of successive IWP contracts in 2019-20, SWPC paced the award of new contracts and also tendered new jobs in 2021-22.

As in most sectors and geographies, the Covid-19 pandemic and war in Ukraine impacted project finance costs and inflation in Saudi Arabia, both particularly relevant to IWP projects.

New developments in the latter part of last year and the first few months of 2023, including the imminent award of the contract to develop the Rabigh 4 IWP, indicate that SWPC is reestablishing its projects momentum.

Similarly, there has been increased activity in water desalination EPC projects being procured by SWCC, such as the proposed seawater reverse osmosis (SWRO) facilities in Shuaibah and Yanbu, which have a combined capacity of over 1 million cm/d.

These are in addition to the under-construction Jubail 2 SWRO plant, with a capacity of 1 million cm/d, and the 400,000 cm/d Shuqaiq 1 SWRO facility, whose main contracts were awarded in 2021 and 2020, respectively.

Along with meeting rising demand, these projects address the decarbonisation requirements of Saudi Arabia’s water sector, which the kingdom’s pledge last year to reach net-zero carbon emissions by 2060 has made more urgent.

This drive is highlighted by the Shuaibah 3 IWP project, for which a team led by Riyadh-headquartered utility developer Acwa Power won the directly-negotiated contract in 2022.

The 600,000 cm/d SWRO plant will replace the existing multi-stage flash (MSF)-based desalination unit that is being decommissioned in 2025 at the existing Shuaibah 3 independent water and power project (IWPP).

The Shuaibah 3 project was the lone IWP contract awarded by SWPC last year.

The same carbon emissions reduction incentive is driving the Yanbu 2 SWRO project. According to SWCC, the project aligns with improving the environmental impact of the desalination water unit of Yanbu phase 2.

Power & Water Utility Company for Jubail & Yanbu (Marafiq) owns the Yanbu 2 integrated water and power desalination plant, which came onstream in 2015. Like the Shuaibah 3 IWPP, the facility’s desalination unit utilises the older, energy-intensive MSF technology.

Saudi Arabia reinvigorates power sector

Other water PPP projects 

The procurement processes are proceeding simultaneously for several independent sewage treatment plants (ISTP), water transmission pipelines and water reservoir facilities being overseen by SWPC across Saudi Arabia.

SWPC tendered the first scheme under the third round of its ISTP programme in November. The Al-Haer ISTP will have a design capacity of 200,000 cm/d.

The tender is also expected in the first half of the year for the two other schemes under batch three, the Riyadh East and Khamis Mushait ISTP schemes.

At least five other ISTP projects are in the planning stage. 

In November, the Taif ISTP scheme, one of the first-round ISTP projects awarded in 2019, entered commercial operation. 

SWPC has received three bids for its first water transmission pipeline public-private partnership (PPP) project, which links Rayis in Medina to Rabigh in Mecca, with prequalification under way for three similar schemes.

Bids are due in April for the contract to develop the kingdom’s first independent strategic water reservoir (ISWR) project. The Juranah ISWR project will be implemented in Mecca, using a build, own, operate and transfer model. The project includes a water reservoir and associated infrastructure and facilities.

It supports Saudi Arabia’s goal to increase municipal water storage capacity to an average of seven days by 2030. In addition, the government aims to increase water storage capacity to an equivalent of 20 days of Hajj demand in Mecca and 40 days of Hajj demand in Medina by 2022. 

Two other IWTP schemes are planned for Mecca under SWPC’s 2020 seven-year planning statement.

Wastewater treatment

Over the past year, the kingdom’s chief wastewater collection and treatment firm, National Water Company (NWC), has tendered a series of contracts across governorates and provinces.

They include contracts for the construction of networks and pumping stations in Aziziyah in Mecca and other areas in Al-Khobar; three lifting stations and ejection lines with diameters of up to 700mm serving different areas in Jubail; and a sewage project in the King Fahd suburb in the Eastern Province and adjacent schemes west of Abu Hadriya Road in Dammam.

Requests for proposals (RFPs) have also been issued to complete sewage facilities in Al-Khafji governorate, West Safwa and Fayhaa.

These projects are part of NWC’s five-year, SR108bn ($29bn) investment plan for the kingdom’s water infrastructure. The latest five-year plan allocates an estimated SR39bn to Mecca, SR16bn to the Eastern Province and SR14.2bn to Riyadh.

The privatisation of NWC’s sewage treatment plant network is also being undertaken in parallel with improving its underlying infrastructure.

Under long-term operation and management (LTOM) agreements, private sector companies can bid to operate and upgrade water treatment plants.

The first package, for Mecca, was awarded in September 2022 to a team of the local Miahona and Thabat Construction Company. The rehabilitate-operate-transfer scheme is for 10 years and is valued at SR392m. Eight other packages are expected to be tendered under the LTOM programme.   


MEED's April 2023 special report on Saudi Arabia also includes:

> CONSTRUCTION: Saudi construction project ramp-up accelerates

> UPSTREAM: Aramco slated to escalate upstream spending

> DOWNSTREAM: Petchems ambitions define Saudi downstream

> POWER: Saudi Arabia reinvigorates power sector

> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10660701/main.jpg
Jennifer Aguinaldo
Related Articles
  • Aramco turns attention to strategic projects

    12 September 2025

     

    In the second quarter of 2025, Saudi Aramco’s capital expenditure (capex) stood at $12.3bn, marking a marginal year-on-year increase of 1.46%. For the first half of the year, the company recorded capex of $24.85bn, up 9.5% compared to the same period last year.

    The company had earlier issued capital investment guidance of $52bn to $58bn for 2025, excluding approximately $4bn in project financing.

    Concerns grew in Saudi Arabia’s offshore oil and gas projects market earlier this year as engineering, procurement, construction and installation (EPCI) contract awards stalled.

    Aramco spent a record $5bn on offshore EPCI contracts in 2024 and was expected to surpass that in 2025. However, it awarded no Contract Release Purchase Orders (CRPOs) in the first half of the year, fuelling apprehension among contractors and suppliers.

    In July, Aramco dispelled speculation by awarding five tenders worth over $3bn. The CRPOs are numbers 150, 157, 158, 159 and 160, and involve EPCI work and infrastructure upgrades at the Abu Safah, Berri, Manifa, Marjan and Zuluf offshore oil fields.

    Aramco also awarded four additional CRPOs as part of a large-scale infrastructure expansion at the Zuluf offshore field. These are CRPOs 145, 146, 147 and 148, with a combined estimated value of nearly $6bn.

    With these contract awards, Aramco has nearly doubled its offshore capex this year compared to 2024, marking another year of robust upstream investment.

    Looking ahead, Aramco is evaluating bids received for seven key tenders in July and August.

    These tenders include CRPOs 154, 155 and 156, representing the next phase of infrastructure expansion at the Safaniya offshore oil field; CRPO 161, which covers the EPCI of four gas jackets at the Arabiyah, Hasbah and Karan fields; and CRPOs 162, 163 and 164, relating to the EPCI of key infrastructure at the Abu Safah, Berri, Karan, Marjan and Safaniya fields.

    Onshore projects advance

    In parallel with the Safaniya offshore expansion, Aramco is tendering a separate project to build onshore surface and processing facilities to handle additional volumes of oil and associated gas generated by the expanded offshore infrastructure.

    The scope of the Safaniya onshore facilities project has been divided into two main EPC packages: the first covering water treatment and injection units, and the second focused on produced water utilities. Contractors have been given deadlines of 24 October and 7 November to submit technical and commercial bids.

    Aramco is also understood to be close to awarding the main EPC contracts for the expansion of the Haradh gas-oil separation plant 3 (Gosp 3) in Saudi Arabia. Located within the Haradh hydrocarbons development in the Eastern Province, the project will increase output of the Arab Light crude grade from 300,000 barrels a day (b/d) to 420,000 b/d. It will also raise sour gas production to 32 million cubic feet a day (cf/d).

    Ramping up gas production

    In line with its goal of increasing gas production, Aramco is progressing its Jafurah unconventional gas programme. Situated in Saudi Arabia’s Eastern Province, the Jafurah Basin contains the largest liquid-rich shale gas play in the Middle East, with an estimated 200 trillion cubic feet of gas in place. The shale play spans approximately 17,000 square kilometres.

    The Jafurah programme is a cornerstone of Aramco’s long-term gas strategy, with total lifecycle investment expected to exceed $100bn. In February 2020, Aramco received a capex allocation of $110bn from the Saudi government to support the long-term phased development of the unconventional gas resource base.

    Aramco is estimated to have spent $25bn across the first three phases of Jafurah’s development. In November 2021, the company awarded $10bn in subsurface and EPC contracts for phase one of the programme.

    On 30 June 2024, Aramco awarded 16 contracts worth approximately $12.4bn for phase two. The scope includes the construction of gas compression facilities, associated pipelines and the expansion of the Jafurah gas plant – covering gas processing trains, utilities, sulphur handling and export infrastructure.

    In July 2024, a consortium of Spain’s Tecnicas Reunidas and China’s Sinopec was awarded a $2.24bn EPC contract by Aramco for phase three of the expansion.

    Phase four of the Jafurah expansion is estimated at $2.5bn. The scope includes EPC works for three gas compression plants, each with a capacity of 200 million cf/d. Bids were submitted in mid-January, remain valid through September, and are under evaluation, with a contract award expected in Q4 2025.

    Aramco is also tendering a major project to boost gas compression capacity at the Shedgum and Uthmaniya plants in the Eastern Province.

    The facilities currently receive approximately 870 million cf/d and 1.2 billion cf/d of Khuff raw gas, respectively. The project aims to increase compression and processing capacity and to construct new pipelines to enhance gas transport.

    Contractors are preparing bids for several EPC packages under the Shedgum and Uthmaniya gas compression project.


    MEED’s October 2025 special report on Saudi Arabia also includes:

    > ECONOMY: Riyadh looks to adjust investment approach
    > BANKING: New funding sources solve Saudi liquidity challenge
    > GAS: Saudi Arabia and Kuwait accelerate Dorra gas field development
    > POWER: Saudi Arabia accelerates power transformation
    > CONSTRUCTION: Saudi construction pivots from gigaprojects to events
    > TRANSPORT: Infrastructure takes centre stage in Saudi strategy

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14656451/main.png
    Indrajit Sen
  • GCCIA signs $500m deal for Oman power link

    12 September 2025

    The GCC Interconnection Authority (GCCIA) has signed a $500m interim financing agreement with Sohar International Bank to support the planned direct electricity interconnection between Oman and the GCC grid.

    The project will involve building a 400-kilovolt double-circuit transmission line linking the Al-Sila station in the UAE with a new Ibri station in Oman. The line will span 530km.

    The Al-Sila station, located in Abu Dhabi near the border with Saudi Arabia, is owned and operated by GCCIA. It is a key node in the existing Gulf power grid, enabling the transfer of electricity between the UAE, Saudi Arabia and other GCC states.

    The Ibri station will be newly developed by GCCIA as part of the interconnection project. Situated in Oman’s Al-Dhahirah governorate, the facility will act as the entry point for linking Oman’s national grid to the wider GCC network. Oman is currently connected via the UAE grid.

    The link will provide a transmission capacity of 1,700MW and a net transfer capacity of 1,200MW.

    In February, MEED reported that the interconnection project would require around $700m of investment.

    It had previously been estimated that the project could cost around $1bn.

    The Qatar Fund for Development (QFFD) signed an agreement with the GCCIA in the same month to finance part of the electricity transmission network that will form Oman’s second link with the GCCIA network.

    Local media reports suggested that QFFD would provide around $100m for the project.

    Although a contract has yet to be awarded, it is understood that Bahwan Engineering Company is among the firms that have submitted bids for the project.

    In June, Abu Dhabi Fund for Development (ADFD) signed a financing agreement with the GCCIA to support a $205m project linking the Al-Sila substation to Saudi Arabia’s Salwa substation.

    This involves the construction of a 400kV double-circuit overhead transmission line extending 96km and includes the expansion of three key substations in Gonan, Al-Sila and Salwa.

    Oman’s first link with the GCCIA became operational in November 2011.

    It comprises a 200kV line connecting the Mahadha grid station in Al-Wasit, Oman, to the Al-Oha grid station in Al-Ain, UAE.

    Projects are also under way for interconnection with Kuwait, as well as with Iraq, as part of a major investment.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14656220/main.jpg
    Mark Dowdall
  • Qatar’s Ashghal awards $101m construction contracts

    12 September 2025

    Qatar’s Public Works Authority (Ashghal) has awarded two contracts worth over QR368m ($101m) for the construction of projects across various locations in the country.

    The first contract, worth QR228m ($62m), was awarded to the local firm Bo Jamhoor Trading & Contracting Company. The scope of the contract encompasses the construction of three new schools at different sites in Qatar.

    The other QR140m ($38m) contract was awarded for the repair and renovation works at the Al-Zubara horse breeding farm, located about 60 kilometres (km) from Doha.

    The contract was awarded to the local firm Generic Engineering Technologies & Contracting.

    The latest award follows Ashghal’s issuance of a tender inviting firms to bid for the construction of roads and infrastructure in Wadi Al-Banat North, Zone 70.

    The tender was floated on 3 September, with a bid submission date of 30 September.

    The contract duration is three years from the start of construction.

    Market overview

    After 2019, there was a consistent year-on-year decline in contract awards in Qatar’s construction and transport sectors. The total value of awards in that year was $13.5bn, but by 2023 it had fallen to just over $1.2bn.

    In 2024, the value of project contract awards increased to $1.7bn, bucking the downward trend in the market in the preceding four years.

    Of last year’s figure, the construction sector accounted for contract awards of over $1.2bn, while transport contract awards were about $200m.

    There are strategic projects worth more than $5bn in the bidding phase, and these are expected to provide renewed impetus to the construction and transportation market, presenting opportunities for contractors in the near term.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14656436/main.gif
    Yasir Iqbal
  • Saudi Arabia seeks consultants for Riyadh rail link

    12 September 2025

     

    Register for MEED’s 14-day trial access 

    Saudi Arabia Railways (SAR) has floated a tender notice inviting consultants to bid by 28 September for a contract covering the design review and construction supervision for the Riyadh rail link project.

    The 35-kilometre-long double-track rail line will run from the north of Riyadh to the south, connecting SAR's North-South railway network with the Eastern Railway network.

    Last week, MEED exclusively reported that SAR had asked contractors to prequalify for a contract covering the construction of the Riyadh rail link.

    The contract also includes the procurement, construction and installation of associated infrastructure, including viaduct construction, civil works, utility installations, signalling systems and other associated works.

    The project is expected to become a key component of the Saudi Landbridge railway.

    The Saudi Landbridge is an estimated $7bn project comprising more than 1,500km of new track. Its core component is a 900km new railway between Riyadh and Jeddah, which will provide direct freight access to the capital from King Abdullah Port on the Red Sea.

    Other key sections include upgrades to the existing Riyadh-Dammam line and a link between King Abdullah Port and Yanbu.

    The start of the tendering activity for the Riyadh rail link project makes the construction of the Saudi Landbridge project even more likely. 

    The project is one of the kingdom’s most anticipated infrastructure programmes. Plans to develop it were first announced in 2004, but the project was put on hold in 2010 before being revived a year later.

    Key stumbling blocks were rights-of-way issues, route alignment and its high cost.

    In December 2023, MEED reported that a team of US-based Hill International, Italy’s Italferr and Spain’s Sener had been awarded the contract to provide project management services for the programme.

    If it proceeds, the Landbridge will be one of the largest railway projects ever undertaken in the Middle East – and among the biggest globally.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14655581/main.jpg
    Yasir Iqbal
  • Petrofac agrees restructuring deal with Samsung and Saipem

    12 September 2025

    The UK-based engineering company Petrofac has announced that it has reached an agreement in principle with South Korea’s Samsung E&A and Italy’s Saipem that will allow the company to restructure.

    The announcement comes more than two months after an appeals court in the UK ruled against Petrofac’s restructuring plans and in favour of Samsung E&A and Saipem.

    The dispute between the three firms, which all have a significant presence in Middle East oil and gas projects, is centred on Petrofac’s participation in the $4bn Thai Oil clean fuels project.

    Petrofac said that the commercial terms of the new agreement between the three companies have been supported by an “Ad Hoc Group” of bondholders.

    This refers to a group of senior secured creditors that backstopped the original restructuring plan earlier this year.

    Petrofac has said that it will now “work to conclude discussions with key stakeholders on next steps towards implementation of the restructuring”.

    It added that, “subject to receipt of all requisite approvals and satisfaction of conditions”, it expects its restructuring to be completed by the end of November 2025.

    Petrofac did not give any details about what commercial terms had been agreed with Samsung E&A and Saipem.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14655445/main.jpg