Saudi water begins next growth phase

10 March 2023

 

Saudi Arabia’s National Water Strategy 2030 continues to drive investments in the kingdom’s water desalination, treatment and distribution sector.

The strategy aims to reduce the water demand-supply gap and ensure desalinated water accounts for 90 per cent of the national urban supply to reduce reliance on non-renewable ground sources.

The need to boost the security of supply amid rising demand, volatile costs and increased compliance with sustainability goals is also driving project activity – particularly in terms of using more energy-efficient technologies to convert seawater into potable water – as well as improving storage capacity.

As of March, an estimated 2.66 million cubic metres a day (cm/d) of water desalination capacity is under construction by the main water utility provider Saline Water Conversion Corporation (SWCC) and state water offtaker Saudi Water Partnership Company (SWPC). 

At least a further 2.4 million cm/d of capacity is under procurement using both the independent water producer (IWP) model, mainly through SWPC, and the engineering, procurement and construction (EPC) model, primarily via SWCC. 

Following the award of successive IWP contracts in 2019-20, SWPC paced the award of new contracts and also tendered new jobs in 2021-22.

As in most sectors and geographies, the Covid-19 pandemic and war in Ukraine impacted project finance costs and inflation in Saudi Arabia, both particularly relevant to IWP projects.

New developments in the latter part of last year and the first few months of 2023, including the imminent award of the contract to develop the Rabigh 4 IWP, indicate that SWPC is reestablishing its projects momentum.

Similarly, there has been increased activity in water desalination EPC projects being procured by SWCC, such as the proposed seawater reverse osmosis (SWRO) facilities in Shuaibah and Yanbu, which have a combined capacity of over 1 million cm/d.

These are in addition to the under-construction Jubail 2 SWRO plant, with a capacity of 1 million cm/d, and the 400,000 cm/d Shuqaiq 1 SWRO facility, whose main contracts were awarded in 2021 and 2020, respectively.

Along with meeting rising demand, these projects address the decarbonisation requirements of Saudi Arabia’s water sector, which the kingdom’s pledge last year to reach net-zero carbon emissions by 2060 has made more urgent.

This drive is highlighted by the Shuaibah 3 IWP project, for which a team led by Riyadh-headquartered utility developer Acwa Power won the directly-negotiated contract in 2022.

The 600,000 cm/d SWRO plant will replace the existing multi-stage flash (MSF)-based desalination unit that is being decommissioned in 2025 at the existing Shuaibah 3 independent water and power project (IWPP).

The Shuaibah 3 project was the lone IWP contract awarded by SWPC last year.

The same carbon emissions reduction incentive is driving the Yanbu 2 SWRO project. According to SWCC, the project aligns with improving the environmental impact of the desalination water unit of Yanbu phase 2.

Power & Water Utility Company for Jubail & Yanbu (Marafiq) owns the Yanbu 2 integrated water and power desalination plant, which came onstream in 2015. Like the Shuaibah 3 IWPP, the facility’s desalination unit utilises the older, energy-intensive MSF technology.

Saudi Arabia reinvigorates power sector

Other water PPP projects 

The procurement processes are proceeding simultaneously for several independent sewage treatment plants (ISTP), water transmission pipelines and water reservoir facilities being overseen by SWPC across Saudi Arabia.

SWPC tendered the first scheme under the third round of its ISTP programme in November. The Al-Haer ISTP will have a design capacity of 200,000 cm/d.

The tender is also expected in the first half of the year for the two other schemes under batch three, the Riyadh East and Khamis Mushait ISTP schemes.

At least five other ISTP projects are in the planning stage. 

In November, the Taif ISTP scheme, one of the first-round ISTP projects awarded in 2019, entered commercial operation. 

SWPC has received three bids for its first water transmission pipeline public-private partnership (PPP) project, which links Rayis in Medina to Rabigh in Mecca, with prequalification under way for three similar schemes.

Bids are due in April for the contract to develop the kingdom’s first independent strategic water reservoir (ISWR) project. The Juranah ISWR project will be implemented in Mecca, using a build, own, operate and transfer model. The project includes a water reservoir and associated infrastructure and facilities.

It supports Saudi Arabia’s goal to increase municipal water storage capacity to an average of seven days by 2030. In addition, the government aims to increase water storage capacity to an equivalent of 20 days of Hajj demand in Mecca and 40 days of Hajj demand in Medina by 2022. 

Two other IWTP schemes are planned for Mecca under SWPC’s 2020 seven-year planning statement.

Wastewater treatment

Over the past year, the kingdom’s chief wastewater collection and treatment firm, National Water Company (NWC), has tendered a series of contracts across governorates and provinces.

They include contracts for the construction of networks and pumping stations in Aziziyah in Mecca and other areas in Al-Khobar; three lifting stations and ejection lines with diameters of up to 700mm serving different areas in Jubail; and a sewage project in the King Fahd suburb in the Eastern Province and adjacent schemes west of Abu Hadriya Road in Dammam.

Requests for proposals (RFPs) have also been issued to complete sewage facilities in Al-Khafji governorate, West Safwa and Fayhaa.

These projects are part of NWC’s five-year, SR108bn ($29bn) investment plan for the kingdom’s water infrastructure. The latest five-year plan allocates an estimated SR39bn to Mecca, SR16bn to the Eastern Province and SR14.2bn to Riyadh.

The privatisation of NWC’s sewage treatment plant network is also being undertaken in parallel with improving its underlying infrastructure.

Under long-term operation and management (LTOM) agreements, private sector companies can bid to operate and upgrade water treatment plants.

The first package, for Mecca, was awarded in September 2022 to a team of the local Miahona and Thabat Construction Company. The rehabilitate-operate-transfer scheme is for 10 years and is valued at SR392m. Eight other packages are expected to be tendered under the LTOM programme.   


MEED's April 2023 special report on Saudi Arabia also includes:

> CONSTRUCTION: Saudi construction project ramp-up accelerates

> UPSTREAM: Aramco slated to escalate upstream spending

> DOWNSTREAM: Petchems ambitions define Saudi downstream

> POWER: Saudi Arabia reinvigorates power sector

> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10660701/main.jpg
Jennifer Aguinaldo
Related Articles
  • Chinese firm signs deals for 5GW Saudi projects

    13 October 2025

    China Energy Engineering Corporation has signed engineering, procurement and construction (EPC) contracts for three major renewable energy projects in Saudi Arabia with a total capacity of 5GW.

    The agreements cover the 1GW Shaqra wind power project, the 2GW Starah wind power project and the 2GW Khulis solar photovoltaic (PV) project.

    A consortium of three China Energy subsidiaries – China Energy International Group, Guangdong Thermal Power and the Northwest Electric Power Design Institute – signed the contracts.

    All three projects were allocated directly under Saudi Arabia’s Public Investment Fund's (PIF) 15GW package announced in July, with Acwa Power, Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco).

    The package included five large-scale solar PV plants with a total capacity of 12,000MW and two large-scale wind energy plants with a total capacity of 3,000MW.

    The total contract value is $2.75bn with a construction period of 26 months for Shaqra and Khulis, and 30 months for Starah.

    The Shaqra and Starah wind projects are located northwest and south of Riyadh, while the Khulis solar project is located north of Jeddah in Mecca province.

    According to China Energy Engineering, the signing represents a major expansion of its Middle East wind market presence.

    The company has been involved in previous Saudi renewable developments, including the 2.6GW Al-Shubakh solar project and 2GW Hadden solar project, both developed under PIF's direct renewable energy programme.

    PIF has committed to developing 70% of Saudi Arabia’s renewable energy target capacity by 2030. 

    The projects under the 15GW package are scheduled to start operating in the second half of 2027 and the first half of 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14856443/main.jpg
    Mark Dowdall
  • Adnoc strives to build long-term upstream potential

    13 October 2025

     

    Between 2023 and 2024, Abu Dhabi National Oil Company (Adnoc Group) spent an estimated $37bn on projects considered vital to achieving its upstream goals: reaching an oil production capacity of 5 million barrels a day (b/d) by 2027 and attaining gas self-sufficiency by the end of the decade.

    The state energy enterprise spent more than $22.5bn in 2023 alone, making it the biggest year on record for oil and gas project spending in the UAE. The Hail and Ghasha sour gas development project, which accounted for approximately $17bn, holds the distinction of being the single-largest contract award in history in the country’s hydrocarbons industry.

    A decline in capital expenditure (capex) in 2025, following two years of prolific project spending, is therefore in line with expectations. While there has been a noticeable dip in capex on engineering, procurement and construction (EPC) contract awards for upstream projects this year, Adnoc has still spent over $8bn year-to-date.

    This year, Adnoc’s upstream spending appears to be focused on surpassing its immediate oil and gas production targets – which are already considered within reach – and on building long-term output capacity beyond 2030.

    Adnoc Group subsidiary Adnoc Offshore awarded contracts totalling $7.5bn for three main EPC packages under a project to boost oil production at the Lower Zakum offshore concession in Abu Dhabi. Spanish contractor Tecnicas Reunidas and Abu Dhabi-based firms NMDC Energy and Target Engineering Construction Company were selected in February to execute EPC works on the three main packages of the Lower Zakum Long-Term Development Plan (LTDP-1) project.

    The Lower Zakum hydrocarbons zone is located 65 kilometres northwest of Abu Dhabi in the Gulf’s waters. Adnoc Offshore holds the majority 60% stake in the Lower Zakum asset. Other stakeholders in the concession include an Indian consortium led by ONGC Videsh (10%), Japan’s Inpex Corporation (10%), China National Petroleum Corporation (10%), Italy’s Eni (5%) and France’s TotalEnergies (5%).

    Adnoc Offshore’s broader long-term objective is to raise the asset’s production capacity to 520,000 b/d by 2027 and sustain that level through 2034.

    Vital projects in queue

    Looking ahead, another Adnoc Group subsidiary, Adnoc Sour Gas, has entered the decision-making phase for its project to increase the Shah gas plant’s sour gas processing capacity to 1.85 billion cubic feet a day (cf/d), following the receipt of commercial bids from contractors in July.

    Based on an initial evaluation of bids, China Petroleum Engineering & Construction Company (CPECC) has emerged as the lowest bidder for the Shah gas plant expansion project.

    Meanwhile, Adnoc Offshore is progressing with three additional key projects aimed at further expanding its oil and gas production capacity.

    The first is a major project to increase oil production from the Satah Al-Razboot (Sarb) field, located within the Sarb and Umm Lulu concession in the Gulf.

    Contractors including US-based McDermott, China Offshore Oil Engineering Company (COOEC), UAE/Saudi-based Lamprell and Abu Dhabi’s NMDC Energy submitted bids for the two main EPC packages of the Sarb field development in September. Adnoc Offshore is believed to be nearing a decision, with the contract award expected by year-end.

    Adnoc Offshore is also advancing a project to boost gas and condensate production from the Umm Shaif field. The primary goal of the Umm Shaif gas cap and surface pressure boosting project is to increase gas production by 550 million cf/d and raise associated condensate output by 50 million b/d. Adnoc Offshore plans to feed approximately 520 million cf/d of the additional gas output into Adnoc Group’s sales gas network.

    Adnoc Offshore is in the tendering phase for three EPC packages of the Umm Shaif gas cap development project – two offshore packages and one onshore – with contractors currently preparing technical bids.

    After awarding EPC contracts worth over $1.3bn last year for two key projects as part of its campaign to increase oil production capacity at the Upper Zakum offshore field to 1.2 million b/d, Adnoc Offshore is now moving forward with the next expansion phase, which will boost the asset’s capacity to 1.5 million b/d.

    Located 84 kilometres offshore from Abu Dhabi, Upper Zakum is the world’s second-largest offshore oil field and the fourth-largest overall. Contractors are currently preparing technical bids for the UZ1.5MMBD project, with the EPC scope reportedly divided into three packages.

    Separately, Adnoc Gas – the natural gas processing arm of Adnoc Group – is working towards a final investment decision (FID) on a project to process gas from the Bab onshore field in Abu Dhabi in 2026.

    Adnoc Gas is nearing the issuance of the main tender for the Bab gas cap development project, having completed early engagement with interested contractors.

    Adnoc Gas is close to issuing the main tender for the Bab gas cap development project, having completed an early engagement process with contractors interested in participating. EPC works on the Bab gas cap project – which will add 1.85 billion cf/d of gas output – are scheduled for completion in 2029.


    MEED's November 2025 special report on the UAE also includes:

    > GOVERNMENT: Public spending ties the UAE closer together
    > ECONOMY: UAE growth expansion beats expectations
    > BANKING: Stability is the watchword for UAE lenders
    > DOWNSTREAM: Taziz fulfils Abu Dhabi’s chemical ambitions at pace
    > POWER: UAE power sector hits record $8.9bn in contracts
    > CONSTRUCTION: UAE construction faces delivery pressures
    > TRANSPORT: $70bn infrastructure schemes underpin UAE economic expansion

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14855366/main.jpg
    Indrajit Sen
  • Global renewable capacity to double by 2030

    13 October 2025

    Register for MEED’s 14-day trial access 

    Global renewable power capacity is expected to more than double by 2030, led by a surge in solar photovoltaic (PV) deployment, according to the International Energy Agency’s (IEA) latest medium-term forecast.

    The Renewables 2025 report projects an additional 4,600GW of capacity, equivalent to the combined power generation of China, the EU and Japan.

    Solar PV will account for around 80% of this increase, driven by declining costs and faster permitting timelines. Growth in wind, hydropower, bioenergy and geothermal will also contribute, with geothermal installations on track to reach record levels in key markets such as the US, Japan and Indonesia.

    The IEA notes that emerging economies in Asia, the Middle East and Africa are accelerating renewable energy deployment through stronger policy support and new auction programmes. India is set to become the second-largest growth market after China and is expected to meet its 2030 target comfortably.

    “The growth in global renewable capacity in the coming years will be dominated by solar PV – but with wind, hydropower, bioenergy and geothermal all contributing, too,” said IEA executive director Fatih Birol.

    “Solar PV is on course to account for some 80% of the increase in the world’s renewable capacity over the next five years,” he added.

    While overall forecasts remain strong, the outlook has been revised slightly downward compared with last year due to policy shifts in China and the US.

    The early phase-out of federal tax incentives and regulatory changes in the US have lowered growth expectations by almost 50%. China’s move from fixed tariffs to auctions has also reduced projected capacity growth.

    This has been partly offset by higher growth projections in India, Europe and other emerging markets, supported by expanded auctions, faster permitting and rising rooftop solar installations. Corporate power purchase agreements and merchant projects are expected to drive 30% of total capacity additions by 2030, double last year’s forecast.

    The report also highlights supply chain risks, with more than 90% of key solar PV and wind turbine components concentrated in China. Grid congestion and curtailment are increasing as variable renewables rise, prompting several countries to launch new capacity and storage auctions to strengthen grid integration.

    Renewables’ share in transport and heating will grow modestly, from 4% to 6% in transport and from 14% to 18% in heat supply by 2030.

    The shift will be driven by the electrification of transport in China and Europe and the expanded use of biofuels in emerging economies.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14855484/main.jpg
    Mark Dowdall
  • Neom to retender Trojena Ski Village

    13 October 2025

     

    Trojena will retender the main construction contract for the multibillion-riyal Trojena Ski Village project in Saudi Arabia.

    The client plans to reissue the tender for the package – estimated at SR12bn-SR15bn ($3.2bn-$4bn) – “in a couple of months”, according to a source.

    In May, MEED exclusively reported that Trojena had received final offers from contractors for the Ski Village project.

    Neom requested a new round of offers after issuing an addendum in early January. Contractors submitted revised proposals on 17 May.

    The Ski Village is a superstructure consisting of five zones, from ground floor to roof, designed to mimic a ski slope and align with the surrounding mountain. The village will also include hotels, residences and retail facilities.

    Designed by Hong Kong-based architecture firm Aedas, Trojena Ski Village will be the Middle East’s first outdoor ski resort.

    The project is the centrepiece of the 2029 Asian Winter Games, which Saudi Arabia is scheduled to host in Neom.

    In August, MEED reported that high-level discussions had begun regarding a potential shift of the 2029 Asian Winter Games venue from Saudi Arabia to South Korea.

    A senior official from the Korean Sport and Olympic Committee was recently quoted by South Korean media as saying they had been contacted by the Olympic Council of Asia about the possibility of hosting the event.

    Officials from the Olympic Council of Asia and the Korean Sport and Olympic Committee met in Singapore in September for further discussions on the potential hosting of the 2029 event.

    South Korean media also reported that the Olympic Council of Asia sent an official letter to the Korean Sport and Olympic Committee following the Singapore meeting.

    The Trojena development in Neom, located in northwest Saudi Arabia, was selected in October 2022 to host the 10th Asian Winter Games in 2029.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14855072/main.jpg
    Yasir Iqbal
  • Qatari cabinet approves GCC rail link to Saudi Arabia

    13 October 2025

    The Qatari cabinet has approved a draft agreement that paves the way for constructing a railway link between Qatar and Saudi Arabia, as part of the GCC railway network.

    The draft was approved on 8 October during a cabinet session chaired by Qatari Prime Minister Sheikh Mohammed Bin Abdulrahman Bin Jassim Al-Thani.

    The GCC railway project has progressed steadily since the GCC Secretariat’s official announcement in January 2021, which effectively relaunched the initiative.

    A string of recent announcements and commitments means that all six GCC states have either declared or signalled plans for their sections of the rail network.

    GCC leaders approved the establishment of the GCC Rail Authority in January 2022. It was tasked with policymaking and coordinating efforts among member states to ensure smooth project delivery and operation.

    The latest development follows MEED's report earlier in October that the authority had received technical bids for an asset management contract covering the overall scheme.

    In August, MEED exclusively reported that the authority awarded a contract to develop the GCC railway’s operational plan to a joint venture of German consultancy Dornier and India’s Balaji Railroad Systems.

    GCC railway line

    According to the overall plan, the railway will span 2,177 kilometres, beginning in Kuwait, passing through Dammam in Saudi Arabia, reaching Bahrain via a planned causeway, and continuing from Dammam to Qatar, the UAE, and ultimately Muscat via Sohar in Oman.

    The network’s route length within each member state is as follows: 684km in the UAE, 663km in Saudi Arabia, 306km in Oman, 283km in Qatar, 145km in Kuwait and 36km in Bahrain.

    The railway is designed for passenger trains travelling at 220km an hour (km/h) and freight trains operating between 80 and 120km/h.

    With high levels of project activity, governments in spending mode and the agreements under the Al-Ula Declaration, the latest efforts to restart the GCC railway project may make more progress than previous attempts. If the railway is finally completed, it could prove transformational for a region that feels connected to the world but divided between its constituent parts.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14855094/main.gif
    Yasir Iqbal