Saudi water begins next growth phase

10 March 2023

 

Saudi Arabia’s National Water Strategy 2030 continues to drive investments in the kingdom’s water desalination, treatment and distribution sector.

The strategy aims to reduce the water demand-supply gap and ensure desalinated water accounts for 90 per cent of the national urban supply to reduce reliance on non-renewable ground sources.

The need to boost the security of supply amid rising demand, volatile costs and increased compliance with sustainability goals is also driving project activity – particularly in terms of using more energy-efficient technologies to convert seawater into potable water – as well as improving storage capacity.

As of March, an estimated 2.66 million cubic metres a day (cm/d) of water desalination capacity is under construction by the main water utility provider Saline Water Conversion Corporation (SWCC) and state water offtaker Saudi Water Partnership Company (SWPC). 

At least a further 2.4 million cm/d of capacity is under procurement using both the independent water producer (IWP) model, mainly through SWPC, and the engineering, procurement and construction (EPC) model, primarily via SWCC. 

Following the award of successive IWP contracts in 2019-20, SWPC paced the award of new contracts and also tendered new jobs in 2021-22.

As in most sectors and geographies, the Covid-19 pandemic and war in Ukraine impacted project finance costs and inflation in Saudi Arabia, both particularly relevant to IWP projects.

New developments in the latter part of last year and the first few months of 2023, including the imminent award of the contract to develop the Rabigh 4 IWP, indicate that SWPC is reestablishing its projects momentum.

Similarly, there has been increased activity in water desalination EPC projects being procured by SWCC, such as the proposed seawater reverse osmosis (SWRO) facilities in Shuaibah and Yanbu, which have a combined capacity of over 1 million cm/d.

These are in addition to the under-construction Jubail 2 SWRO plant, with a capacity of 1 million cm/d, and the 400,000 cm/d Shuqaiq 1 SWRO facility, whose main contracts were awarded in 2021 and 2020, respectively.

Along with meeting rising demand, these projects address the decarbonisation requirements of Saudi Arabia’s water sector, which the kingdom’s pledge last year to reach net-zero carbon emissions by 2060 has made more urgent.

This drive is highlighted by the Shuaibah 3 IWP project, for which a team led by Riyadh-headquartered utility developer Acwa Power won the directly-negotiated contract in 2022.

The 600,000 cm/d SWRO plant will replace the existing multi-stage flash (MSF)-based desalination unit that is being decommissioned in 2025 at the existing Shuaibah 3 independent water and power project (IWPP).

The Shuaibah 3 project was the lone IWP contract awarded by SWPC last year.

The same carbon emissions reduction incentive is driving the Yanbu 2 SWRO project. According to SWCC, the project aligns with improving the environmental impact of the desalination water unit of Yanbu phase 2.

Power & Water Utility Company for Jubail & Yanbu (Marafiq) owns the Yanbu 2 integrated water and power desalination plant, which came onstream in 2015. Like the Shuaibah 3 IWPP, the facility’s desalination unit utilises the older, energy-intensive MSF technology.

Saudi Arabia reinvigorates power sector

Other water PPP projects 

The procurement processes are proceeding simultaneously for several independent sewage treatment plants (ISTP), water transmission pipelines and water reservoir facilities being overseen by SWPC across Saudi Arabia.

SWPC tendered the first scheme under the third round of its ISTP programme in November. The Al-Haer ISTP will have a design capacity of 200,000 cm/d.

The tender is also expected in the first half of the year for the two other schemes under batch three, the Riyadh East and Khamis Mushait ISTP schemes.

At least five other ISTP projects are in the planning stage. 

In November, the Taif ISTP scheme, one of the first-round ISTP projects awarded in 2019, entered commercial operation. 

SWPC has received three bids for its first water transmission pipeline public-private partnership (PPP) project, which links Rayis in Medina to Rabigh in Mecca, with prequalification under way for three similar schemes.

Bids are due in April for the contract to develop the kingdom’s first independent strategic water reservoir (ISWR) project. The Juranah ISWR project will be implemented in Mecca, using a build, own, operate and transfer model. The project includes a water reservoir and associated infrastructure and facilities.

It supports Saudi Arabia’s goal to increase municipal water storage capacity to an average of seven days by 2030. In addition, the government aims to increase water storage capacity to an equivalent of 20 days of Hajj demand in Mecca and 40 days of Hajj demand in Medina by 2022. 

Two other IWTP schemes are planned for Mecca under SWPC’s 2020 seven-year planning statement.

Wastewater treatment

Over the past year, the kingdom’s chief wastewater collection and treatment firm, National Water Company (NWC), has tendered a series of contracts across governorates and provinces.

They include contracts for the construction of networks and pumping stations in Aziziyah in Mecca and other areas in Al-Khobar; three lifting stations and ejection lines with diameters of up to 700mm serving different areas in Jubail; and a sewage project in the King Fahd suburb in the Eastern Province and adjacent schemes west of Abu Hadriya Road in Dammam.

Requests for proposals (RFPs) have also been issued to complete sewage facilities in Al-Khafji governorate, West Safwa and Fayhaa.

These projects are part of NWC’s five-year, SR108bn ($29bn) investment plan for the kingdom’s water infrastructure. The latest five-year plan allocates an estimated SR39bn to Mecca, SR16bn to the Eastern Province and SR14.2bn to Riyadh.

The privatisation of NWC’s sewage treatment plant network is also being undertaken in parallel with improving its underlying infrastructure.

Under long-term operation and management (LTOM) agreements, private sector companies can bid to operate and upgrade water treatment plants.

The first package, for Mecca, was awarded in September 2022 to a team of the local Miahona and Thabat Construction Company. The rehabilitate-operate-transfer scheme is for 10 years and is valued at SR392m. Eight other packages are expected to be tendered under the LTOM programme.   


MEED's April 2023 special report on Saudi Arabia also includes:

> CONSTRUCTION: Saudi construction project ramp-up accelerates

> UPSTREAM: Aramco slated to escalate upstream spending

> DOWNSTREAM: Petchems ambitions define Saudi downstream

> POWER: Saudi Arabia reinvigorates power sector

> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10660701/main.jpg
Jennifer Aguinaldo
Related Articles
  • Al-Maktoum airport is key to Dubai’s aviation hub status

    27 November 2026

    Commentary
    Colin Foreman
    Editor

    Dubai’s position as a global aviation hub is central to its economy, and the expansion of Al-Maktoum International airport is critical to maintaining that role.

    On 26 November, Dubai awarded AED56.5bn ($15bn) of contracts for the airport expansion, taking the total value of contracts awarded to more than AED80bn ($21.8bn). A workforce of 14,000 is working on the project, which will provide capacity for more than 260 million passengers a year when complete.

    The economic stakes are high. A study published by Emirates Group and Dubai Airports in October 2024 found that aviation accounted for 27% of Dubai’s GDP in 2023. The sector contributed AED137bn ($37.3bn) in gross value added and supported 631,000 jobs – about one in five jobs in the emirate. The study forecast that aviation’s share of GDP would rise to 32% by 2030, contributing AED196bn in gross value added and supporting 816,000 jobs.

    This year has demonstrated both the vulnerability and resilience of Dubai’s aviation model. Regional conflict has disrupted commercial air traffic across the Gulf since 28 February. Emirates Group’s profit before tax fell 66% year on year to AED4.1bn in the six months to 30 September, while Emirates carried 21.8 million passengers, down 22% on the prior-year period.

    However, the network recovered quickly. By 30 September, Emirates was operating 91% of its pre-disruption network, serving 150 airports in 78 countries and territories. Emirates SkyCargo revenue rose 52%, the fleet increased to 289 aircraft, and the airline broke ground in May on a $5.1bn maintenance facility at Al-Maktoum International airport.

    Maintaining that connectivity will require additional capacity. If aviation accounts for almost one-third of Dubai’s economy by 2030, as Emirates Group and Dubai Airports forecast, Al-Maktoum International airport will be central to the emirate’s ability to retain its position in global air travel.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21894329/main.jfif
    Colin Foreman
  • Emaar tenders Dubai Creek Harbour mall

    27 November 2026

     

    Register for MEED’s 14-day trial access 

    Dubai developer Emaar Properties has invited contractors to submit bids by 9 December for the main construction package of the Dubai Creek Harbour mall, known as Dubai Square.

    The development covers a total retail, hospitality and commercial area of 2.6 million square metres, and is scheduled to open within three years.

    Emaar unveiled Dubai Square in December 2025 as the anchor of its AED180bn ($49bn) Dubai Creek Harbour development.

    The scheme has undergone several redesigns. MEED first reported on Emaar’s plans for a major retail centre at Dubai Creek Harbour in 2016. At the time, the project was envisioned to surpass Dubai Mall as the world’s largest retail destination, though its scale and layout have since evolved.

    The mall will connect directly to the planned Dubai Creek Tower at the centre of the development.

    UK-headquartered Brewer Smith Brewer Group is the project’s lead consultant, executive architect, architect of record and structural engineer. It is also the construction supervision consultant.

    Dubai-based contractor Dutco Construction began mobilising last year for early site works.

    In March last year, MEED reported that Emaar was preparing to relaunch development of both the tower and the mall. The developer had earmarked roughly AED14bn ($3.81bn) for the two assets as part of a wider AED65bn ($18bn), five-year capital expenditure programme.

    Progress on the tower has been slower. First launched in 2015, it was promoted as the world’s tallest structure, designed to exceed the 828-metre Burj Khalifa. The original design was led by Spanish architect Santiago Calatrava and UK-based RMJM. The project stalled after concrete pile-cap works were completed in 2018.

    In 2023, Emaar founder Mohamed Alabbar confirmed design works were continuing following an international design competition. In January 2026, Alabbar stated that a tender for the redesigned tower would be issued within three months. He later said the tender would be deferred until regional geopolitical tensions ease.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21892263/main.jpg
    Yasir Iqbal
  • Contractor wins Arabian Beauty Horses Village in Qatar

    27 November 2026

     

    Qatar’s Culture Village Foundation (Katara) has awarded Qatar Trading & Contracting Group a QR574m ($158m) contract to build the Arabian Beauty Horses Village in Al-Uqdah Zone 74, in the Al-Khor area.

    The project will include supporting infrastructure and public facilities designed for Arabian show horses and equestrian operations in the Al-Uqdah district.

    Zone 74 is already an important centre for Qatar’s equestrian sector, anchored by the Al-Uqdah Equestrian Complex. The Qatar Racing & Equestrian Club began operating the complex in 2020 in coordination with Qatar’s Ministry of Culture and Sports.

    The Arabian Beauty Horses Village is part of a broader, multistage state strategy to develop Al-Uqdah, on the outskirts of Al-Khor, as Qatar’s second major equestrian hub, alongside Al-Rayyan and Al-Shaqab in Doha.

    According to UK analytics firm GlobalData, Qatar’s commercial construction sector is expected to grow at an average annual rate of 4.5% between 2025 and 2028, supported by investment in hotels, logistics facilities and data centres.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21890026/main.jpg
    Yasir Iqbal
  • King Salman airport sets new infrastructure bid deadline

    27 November 2026

     

    Saudi Arabia’s King Salman International Airport Development Company (KSIADC) has set a 10 January deadline for bids for the Zone C1+C2 roads, bridges and utility networks package for King Salman International airport (KSIA) in Riyadh.

    The tender was issued on 26 October, with an initial bid-submission deadline of 6 December.

    The request for proposals covers the procurement, construction, testing and commissioning of civil infrastructure supporting Terminal 6, alongside the existing Terminals 1-5.

    The scope includes upgrades to Airport Road 539, which runs west of Terminals 1-5, and part of Mohamed bin Faraj Road 5333, west of Junction 6.

    It also includes new roads, ramps, service roads and signalised at-grade junctions. An additional access road will connect the Terminal 6 site offices to Road 5333.

    Structures will include the Junction 6 and Terminal 6 bridges, retaining walls and reinforced-soil structures.

    The contractor will also construct the central ground services equipment (GSE) bridge. Before construction begins, the contractor must validate the design, complete any outstanding elements – including mechanically stabilised earth walls, approach slabs, drainage and lighting – and secure the required authority approvals.

    Dry utilities will comprise high- and extra-high-voltage containment, a 13.8kV medium-voltage network with package substations, low-voltage distribution and street lighting, and security-surveillance systems.

    Wet utilities will include potable water, fire water, irrigation water, treated sewage effluent, district cooling and wastewater networks. Wastewater pipes will range from 200mm u-PVC gravity lines to 1,700mm glass-reinforced plastic mains.

    The stormwater network will include channels, culverts, ponds and pipes ranging from 400mm to 1,400mm in diameter. Crossings will be constructed using open-cut excavation, horizontal directional drilling or microtunneling.

    Utilities serving the operational terminals will be diverted on a design-and-build basis. Enabling works will include earthworks and the relocation of the security fence and trees. The contractor will also demolish a temporary car park, existing bridges and a sewage pumping station.

    Optional works comprise two design-and-build elements that will proceed only at the client’s instruction.

    The first is the south GSE bridge. The second is an approximately 1,400-metre, multi-lane access road to the Terminal 6 Transportation Hub, including bridges, underpasses, ramps and tunnels, as well as provisions for future Wadi Loop utilities and structures.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21887157/main3955.png
    Yasir Iqbal
  • PIF secures inaugural A+ rating from S&P

    26 November 2026

    Saudi Arabia’s Public Investment Fund (PIF) has received an inaugural A+ long-term foreign and local currency issuer credit rating from S&P Global Ratings, with a stable outlook.

    The fund’s existing A-1 short-term rating from S&P is unchanged. PIF said its ratings are in line with those of Saudi Arabia.

    PIF said S&P’s assessment cited its diversified funding profile, moderate leverage and its focus on value realisation under its 2026-30 strategy. The agency also pointed to the fund’s role in driving the kingdom’s economic transformation.

    “The inaugural A+ long-term rating from S&P marks an important milestone in the continued development of PIF’s credit profile and our long-term funding plan,” said Ziyad Alfawzan, head of capital finance strategy at PIF.

    The new rating makes PIF one of a small number of sovereign wealth funds with long-term credit ratings from all three leading agencies.

    Moody’s Ratings confirmed PIF’s Aa3 long-term issuer rating and aa3 baseline credit assessment in September after a periodic review, with a stable outlook. In October, Fitch Ratings affirmed the fund’s long-term foreign and local currency issuer default ratings at A+, also with a stable outlook.

    The Moody’s rating is one notch higher than the A+ grades from S&P and Fitch.

    Debt is an increasingly important source of funding for PIF as it pays for domestic investment programmes and gigaprojects.

    The fund raised $2bn in January from a 10-year sukuk, its first debt sale of 2026. In May, it raised $7bn from a three-tranche bond, its first hard-currency public issuance since the Iran conflict disrupted regional capital markets.

    A full set of long-term ratings is likely to widen PIF’s investor base for future bond and sukuk issuance. The fund also borrows through loans and other debt instruments as part of its funding mix.

    PIF is entering what it calls the value realisation phase of its strategy, covering 2026 to 2030. Over this period, it aims to deliver sustainable financial returns while continuing to drive the diversification of the Saudi economy.


    MEED’s latest report on Saudi Arabia includes:

    > COMMENT: Saudi projects hold steady
    > GOVERNMENT: Riyadh looks to reset its regional defence outlook
    > ECONOMY: Conflict bolsters case for Saudi economic diversification

    > BANKING: Saudi lenders readjust to lower lending and deposit climate
    > UPSTREAM: Aramco upstream spending gathers pace
    > DOWNSTREAM: Sabic steps up Saudi petchems investment

    > POWER: Saudi Arabia’s power award activity slows
    > WATER: Saudi water sector hits sharp slowdown
    > CONSTRUCTION: Saudi construction defies the headwinds
    > TRANSPORT: Saudi infrastructure pushes forward amid conflict
    > DATABANK: Saudi data indicates project spending shift

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21868102/main.gif
    Colin Foreman