Saudi power sector enters busiest year

10 March 2025

 

Contracts worth more than $90bn are under execution in Saudi Arabia’s power sector, making 2025 the busiest year ever for generation and transmission capacity buildout in the kingdom.

The construction of conventional and renewable power generation plants accounts for two-thirds, or 66%, of the contracts under execution, while transmission and distribution projects account for the rest, based on the latest available data from regional project tracker MEED Projects.

In addition to gas-fired and renewable energy generation plant projects, the kingdom has awarded several contracts in the past two years to modernise and expand its domestic grids in light of the solar photovoltaic (PV) and wind power plants, and industrial complexes, which are being built in remote areas – as well as Riyadh's plan to trade electricity beyond the kingdom's GCC partners and with countries such as Egypt.

In the past 12 months, the kingdom also awarded the first contracts to build on-grid battery energy storage system (bess) facilities, in line with fostering greater grid flexibility and countering the intermittency of renewable power.

“It has been a very, very busy year, despite some projects – particularly those catering to Neom – being re-scoped,” notes a Dubai-based senior executive with a transaction advisory firm.

The $500bn Neom gigaproject in southwestern Saudi Arabia aims to be powered 100% by renewable energy, which it initially expected to generate independently.

However, ongoing discussions are understood to include an option to meet future demand through renewable power sourced from the grid.

Overall, combined-cycle gas turbine (CCGT) projects – procured on either an independent power project (IPP) or engineering, procurement and construction (EPC) model – account for 56% of the total power generation contracts under execution in Saudi Arabia, with solar and wind accounting for the remaining 44%.

The principal buyer, Saudi Power Procurement Company (SPPC), awarded contracts for two pairs of CCGT plants – projects one and two of the Rumah and Nairiyah schemes – last year.

SPPC also signed the offtake agreements for four solar PV IPPs, which were tendered under the fifth round of the National Renewable Energy Programme (NREP). These were contracts for the 2GW Al-Sadawi, 1.25GW Al-Masaa, 500MW Al-Henakiyah 2 and 300MW Rabigh 2 solar IPPs.

An EPC contract for a high-voltage, direct current transmission network connecting the kingdom’s central and southern electricity grids was also one of the largest deals signed last year in the kingdom.

In the second half of 2024, the developer arm of Saudi Electricity Company (SEC) selected the preferred bidders for several greenfield CCGT expansion plants: Ghazlan 1 and 2, Riyadh PP12 and Marjan.

SEC subsidiary National Grid also awarded the second phase of its bess projects that are being procured on an EPC basis to local firm AlGihaz Holding last year. The three battery energy storage facilities, each with a capacity of 800MW, or about 2,600 megawatt-hours, are to be located in Najran, Khamis Mushait and Madaya.

The extent of work on hand is exerting pressure on contractor capacity, according to some experts.

"I think the Chinese EPC contractors are already at capacity, so SEC has started tapping Egyptian and Spanish EPC contractors," an industry source told MEED, referring to Tecnicas Reunidas, Orascom and Elsewedy, which are understood to have been selected last year to undertake the EPC contracts for several CCGT plants that SEC is developing.

South Korean EPC contractors are also executing several cogeneration and generation power plants in the kingdom.

Outlook

The need to expand, connect and stabilise the kingdom’s electricity grid will be a primary preoccupation for Saudi utility stakeholders in the short to medium term.

This is crucial given the large capacity of renewable energy power generation plants that are scheduled to come on stream, and as the kingdom deploys new gas-fired plants in line with its need to displace liquid fuel in some of its ageing fleet.

Oil fuel still accounted for 36% of Saudi Arabia's total electricity generation in 2023, at 422.9 terawatt-hours, according to the Energy Institute.

Data from MEED Projects suggests that at least $68bn-worth of power generation and transmission contracts are in the pre-execution phase as of March 2025.

Clean energy fuel-powered plants, using solar, wind, hydro and nuclear, dominate the $47bn-worth of planned power generation units, with thermal plants accounting for just 13% of the total.

This signals a shift to clean energy, despite the overall figure excluding a significant volume of renewable energy projects that are still in the concept stage. This is in line with a plan by the Energy Ministry to procure up to 20GW of renewable energy capacity annually until 2030, subject to demand growth.

Planned transmission and distribution projects, including several independent battery energy storage projects, together account for about $21bn of contracts that have yet to be awarded.

Local developers

Local companies are increasingly visible in the procurement proceedings for new power generation and transmission plants in the kingdom.

The decisions made by several European and Japanese developers to retreat from thermal power plant tenders that do not offer a clear carbon capture, utilisation and storage (CCUS) path – which would be necessary for them to meet their 2045 or 2050 net-zero targets – has contributed to this trend.

The exclusion of dominant utility developer Acwa Power in the prequalification process for the NREP’s fifth and sixth procurement rounds has also opened up opportunities for other international and local developers that are keen to win more contracts in Saudi Arabia.

Aljomaih Energy & Water, Ajlan & Brothers, Alfanar, Algihaz and SEC’s developer arm have been pursuing new contracts, usually in cooperation with an international developer.

Battery energy storage

Large-scale solar PV projects and limited wind capacity in the kingdom create a major market for battery energy storage going forwards.

Independent battery energy storage projects, in particular, offer neutral opportunities for both international and local developers, and are expected to attract more bidders compared to conventional thermal or standalone solar PV projects.

“We are definitely interested,” says a senior executive with a European utility developer, referring to the first phase of the kingdom’s independent storage provider (ISP) programme.

In addition to its net-zero merits, the ISPs will follow the same model as an IPP project, where the successful bidders will hold 100% equity in the special purpose vehicles set up to develop and operate the project.

While such strong interest is expected to benefit the principal buyer, which can expect to receive competitive prices from bidders, an over-competitive or crowded landscape could also be off-putting to developers and investors that are keen to maintain their internal rate of return, or which are shifting their global focus to other geographies.

“We prefer to wait and see,” one source tells MEED, indicating that their company does not intend to participate in upcoming battery tenders, not only in Saudi Arabia but also in other GCC states.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13466191/main.gif
Jennifer Aguinaldo
Related Articles
  • Dubai real estate buys time

    17 March 2026

    Register for MEED’s 14-day trial access 

    The outbreak of the Iran-US-Israel war has injected a powerful dose of uncertainty into Dubai’s residential real estate market, a sector already bracing for a cyclical cooldown.

    A new report from S&P Global Ratings, published on 16 March, outlines the parameters of the risk.

    The core argument is that while Dubai is not facing an immediate 2008-style collapse, the market’s resilience is now a function of time. If the conflict intensifies beyond a one-month horizon, the strains on prices, investor confidence and developer balance sheets could become severe.

    Momentum stalls as caution takes hold

    The most immediate impact of the conflict has been psychological. According to S&P, official sources are already reporting lower transaction volumes since the war began. The prolonged war could mark the end of the post-pandemic boom, shifting the market into a phase of guarded caution.

    The luxury segment, which has driven much of the recent growth, is seen as the most vulnerable. High-net-worth individuals who relocated to Dubai for its perceived safety and tax advantages may now reconsider their positions, given that the city’s ‘safe haven’ status is being tested.

    S&P’s baseline forecast assumes the most intense phase of fighting will last up to four weeks. Under this scenario, the market will likely experience a slowdown in both volumes and prices, with the declines being more pronounced the longer the uncertainty drags on.

    The report notes a flight to liquidity, predicting that secondary market transactions will become more prevalent as investors seek to offload properties, further suppressing values.

    Apartments are expected to suffer steeper price drops than villas due to a robust supply pipeline.

    Regulatory shields and the threat of a prolonged conflict

    One of the central tenets of the report is that Dubai’s post-2008 regulatory framework provides a crucial buffer. Escrow accounts and stringent payment plans mean that for projects already under way, developers should be able to complete construction, barring a wave of mass investor defaults.

    The rules offer significant protection: developers can retain up to 40% of the property value if construction is on schedule, refund the remainder, and repossess the unit for resale.

    However, this protection has limits. S&P warns that a prolonged war scenario would test these regulations. If the Strait of Hormuz remains closed, supply chains for construction materials could bottleneck, driving up input costs. More critically, the rules that protect developers would only be effective up to a point.

    In a deep and lasting downturn, project cancellations would become likely, particularly for newly launched developments that have not secured substantial presales.

    The analysis suggests that while top-tier developers weathered past downturns with delinquency rates of just 3-10%, the figure for newer, less experienced players could be much higher.

    Rated developers have headroom, but it is not infinite

    The four major developers rated by S&P with exposure to Dubai are Emaar Properties, Damac Properties, PNC Investments and Omniyat Holdings. All of these players enter the period of uncertainty from a position of relative strength.

    The report highlights that years of strong sales have created significant revenue backlogs covering several years.

    Emaar leads with the revenue backlog of about $37bn, equivalent to 2.7 years, while Damac holds about $22bn of backlog, representing 2.3 years.

    Their leverage is low, and cash positions are meaningful. As of 31 December 2025, Emaar held $7.5bn in cash and liquid investments, with $11.7bn as escrow cash balance.

    Damac holds $1.7bn in total cash, including $6bn in escrow, while PNCI and Omniyat hold more modest balances of $600m and $600m, respectively.

    S&P has built “substantial headroom” into their credit ratings to absorb sudden shocks.

    The liquidity assessments for all four companies are adequate, with manageable debt maturities in 2026.

    The critical question is duration. If the conflict grinds on, the buffers will narrow.

    S&P states that in a prolonged scenario, its reassessment will focus on construction progress, cash collection and working capital.

    The financial policies of management teams, specifically their willingness to maintain low leverage and cut dividends, will be key to preserving creditworthiness.

    Capex and dividends under review

    The war will also force a recalibration of corporate strategy. The report notes that investment decisions are likely to be postponed or cancelled. While commitments for projects nearing completion will proceed, companies will prioritise liquidity over new land purchases.

    This is most pronounced for Emaar, which has sizeable capital expenditure plans of AED10bn-AED11bn ($2.7bn-$3bn) annually in 2026-27 for projects such as Dubai Creek Tower, Dubai Creek Mall and the expansion of Dubai Mall. S&P believes a significant portion of this spending is flexible and can be delayed if needed.

    Dividend policies will also be tested. The report expects dividend distributions to remain substantial but potentially adjustable. 

    S&P’s analysis paints a picture of a market that is braced for impact but not yet broken. The fundamentals are stronger than they were in 2008, thanks to tighter regulations and well-capitalised developers with $10bn in combined cash reserves.

    However, the market’s fate is now externally determined. If the conflict remains contained and short-lived, Dubai’s real estate sector should absorb the shock with manageable declines.

    But if the war becomes a protracted regional crisis, the meaningful correction that S&P flags as a possibility will move from the realm of the theoretical to the probable, testing the resilience of both the developers and the regulatory framework designed to protect them.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16012971/main.gif
    Yasir Iqbal
  • Saudi Energy pushes back deadlines for power projects

    17 March 2026

    Saudi Energy, formerly Saudi Electricity Company (SEC), has extended bid submission deadlines for three substation projects in Riyadh Province.

    The utility has pushed back the deadline for the estimated $50m King Khalid International airport 132/13.8kV substation project to 9 April.

    The contract was originally tendered in December, and the deadline had previously been extended to 9 March.

    Local firms Al-Babtain Contracting and Al-Haider are understood to have prequalified to bid for the scheme. 

    The company has also extended the deadline for a $40m engineering, procurement and construction (EPC) contract for a 132kV underground cable project in Al-Kharj, Riyadh Province.

    The new bid submission date is 26 March.

    The project covers the installation of underground cable circuits linking a proposed substation (S/S #8721) north of Al-Kharj to BSP #9028. The scope also includes associated civil works and infrastructure.

    Prequalified bidders include Saudi Services for Electro Mechanic Works, Al-Babtain Contracting and Al-Haider, according to regional project tracker MEED Projects.

    In addition, the utility has extended the deadline for a $50m contract to replace the existing 132/13.8kV substation (S/S #8044) with the new Al-Sharafiyah-2 substation (S/S #8407) in Riyadh.

    The revised submission date is 9 April.

    The scope includes construction of the new substation, installation of switchgear and conductors, and associated infrastructure works.

    Saudi Services for Electro Mechanic Works, Al-Babtain Contracting and Al-Haider are expected to submit bids for the project.

    Riyadh Expo substations

    Separately, Saudi Energy is understood to be moving forward with procurement for a project to develop three 132/13.8kV substations in Riyadh to support Expo 2030.

    The utility is said to have invited bids for the engineering, procurement and construction (EPC) contract to deliver the three substations along with associated works to connect the facilities to the national grid.

    The project forms part of wider infrastructure preparations for Expo 2030 Riyadh, scheduled to take place from October 2030 to March 2031

    No bid submission deadline has been publicly disclosed.

    Last September, Saudi Energy outlined plans to invest $58.7bn in power projects between 2025 and 2030.

    This includes $36bn and $22.7bn for transmission and distribution, respectively, and is part of long-term plans to meet growing electricity demand while improving grid efficiency and reliability.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16012147/main.jpg
    Mark Dowdall
  • Fujairah oil hub targeted in fresh drone strike

    17 March 2026

    Register for MEED’s 14-day trial access 

    The Fujairah Oil Industry Zone (FOIZ) was hit by another drone attack early on 17 March, causing a fire, authorities in Fujairah said.

    No injuries have been reported in the attack, and the emirate’s civil defence teams are dealing with the situation and trying to control the fire, the official Emirates News Agency (Wam) reported, citing the media office of the Government of Fujairah.

    This is understood to be the fifth attack since the start of March that FOIZ has suffered from drone or debris resulting from interceptions by the UAE’s air defence systems, as Iran continues to hit energy and industrial facilities in the UAE.

    Fujairah benefits from its strategic geopolitical location outside the Strait of Hormuz, which Iran has blockaded in its ongoing conflict with Israel and the US, choking about a fifth of the world’s oil and gas supplies.

    Consequently, oil prices have soared since the start of the conflict on 28 February. Global benchmark Brent broke the $100 mark on 9 March, for the first time since Russia’s invasion of Ukraine in February 2022, rising to a high of $119 a barrel on that day. Prices have dropped since, but it is still trading well above the $100 mark, with Brent recorded at $103.87 a barrel as of 12pm GST on 17 March.

    Major midstream oil and gas companies operate key storage and export hubs for oil and refined products in Fujairah, including Abu Dhabi National Oil Company (Adnoc Group), Saudi Aramco – through its subsidiary Aramco Trading – Vopak Horizon, VTTI, Shell, Fujairah Oil Terminal, Brooge Petroleum & Gas Investment Company (BPGIC), Emirates National Oil Company (Enoc), Ecomar, Mount Row and GPS Chemoil.

    ALSO READ: Iran sees economic pressure as key to ending war

    Fujairah is crucial to the operations of Adnoc Group subsidiary Adnoc Onshore, which operates a main oil terminal (MOT) there. Located approximately 300 kilometres north of Abu Dhabi, the terminal facilitates the import and export of various crude oil grades, particularly Murban, from the company’s onshore and offshore fields.

    Meanwhile, the Abu Dhabi Crude Oil Pipeline (Adcop) connects milestone pole (MP) 21 at the Habshan oil facility in Abu Dhabi, where stabilised crude produced from Adnoc Onshore fields is gathered for dispatch, to the Fujairah MOT.

    BPGIC is an oil storage and services firm that was established in 2013 in Fujairah and started operations with a capacity of 400,000 cubic metres spanning 14 tanks. In March 2022, it announced its intention to increase the storage capacity of four of those storage tanks in the first phase complex.

    Separately, in September 2021, BPGIC began operations at the second phase of its Fujairah oil storage complex, adding 600,000 cubic metres of storage capacity across eight tanks. As a result of that expansion, BPGIC’s storage capacity more than doubled to 1 million cubic metres, or 6.3 million barrels, from 400,000 cubic metres.

    BPGIC then undertook a third expansion phase of its oil storage facility, which is understood to have been commissioned in 2023.

    The third phase increased BPGIC’s oil storage capacity by 3.5 times, raising it to 3.5 million cubic metres, or 22 million barrels, and making the firm the largest oil storage services provider in the UAE emirate of Fujairah.

    The third-phase expansion project consists of an oil storage facility with a capacity of 2.5 million cubic metres, a modular 25,000-barrel-a-day (b/d) refinery, and a larger 180,000-b/d conventional refinery.

    BPGIC also co-owns a topping refinery in Fujairah with Nigeria-based Sahara Energy Resources, which produces low-sulphur bunker fuel for ships and vessels. It is understood that the new naphtha upgradation unit could be integrated with the existing topping refinery unit.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16011988/main.jpg
    Indrajit Sen
  • Oman signs $2bn real estate deals at Mipim 2026

    17 March 2026

    Oman has signed 17 international investment and development agreements worth over RO762m ($1.98bn) at the Mipim 2026 event held in Cannes, France.

    The deals were concluded through the Ministry of Housing & Urban Planning (MHUP) and partners at the Oman pavilion, and span mixed-use real estate, healthcare, agri-investment and digital planning tools.

    A key agreement was a memorandum of understanding with Turkiye’s Artas Holding for the Al-Khuwair Downtown project, with planned investments exceeding RO150m ($390m).

    In Sultan Haitham City, an agreement was signed with Saudi Arabia’s Retal Development to develop neighbourhoods 3, 15 and 17, covering more than 1.39 million square metres, with a combined investment of over RO320m ($832m).

    Other agreements include Vogue Homes Portugal investing more than RO25m ($65m) in the Al-Thuraya City project, and another residential scheme led by international firms including Avant Garde Properties, F&M International, Metrogramma and The One Atelier, with an investment of about RO50m ($130m).

    MoHUP also signed agreements covering smart planning and project delivery, including advanced 3D digital modelling, with investment exceeding RO408,000 ($1m).

    Healthcare-related agreements include a partnership between local Al-Daham Real Estate and Kubba to develop hospital and stem-cell treatment facilities, valued at RO11.5m ($30m), and a deal between local firm Al-Abrar Real Estate Group and Vienna Hospital & University to operate Ibn Al-Haitham Hospital in Sultan Haitham City, with an investment of more than RO40m ($104m).

    In Dhofar, investments will be made in planting one million olive trees under a usufruct arrangement, valued at RO15m ($39m), as part of agriculture sustainability plans.

    The programme also includes architectural and branding collaborations involving international firms such as Chapman Taylor Architects, 3DTouch Studio, Hawk & Impact Communication and Atelier Entropic, alongside luxury brands including Pagani, Armani and Elie Saab for branded residential concepts.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16011061/main.jpg
    Yasir Iqbal
  • Ashghal tenders northern Smaisma infrastructure

    17 March 2026

     

    Qatar’s Public Works Authority (Ashghal) has issued a tender covering infrastructure development in the northern Smaisma area.

    The tender was floated on 14 March, with a bid submission closing date of 12 May.

    The scope includes the airstrip road, coastal road and connections to the existing Al-Khor Expressway, spanning an area of about 18.5 kilometres.

    The contract duration is four years from the start of construction works.

    The latest tender follows Ashghal’s announcement of contract awards for 12 new projects, with a total value exceeding QR4.5bn ($1.2bn).

    According to a notice published on its website, these include six building projects, most notably the redevelopment of Hamad General Hospital, with a contract value of about QR1.1bn ($301m).

    The other projects awarded include the construction of a post office building in Al-Thumama, the renovation of the Qatar Racing & Equestrian Club and the Qatar Equestrian Federation, as well as the implementation of phase four of the Al-Uqda Equestrian Complex development.

    In the roads and infrastructure sector, four projects have been awarded, led by packages one and two of the road and infrastructure development works in Izghawa and Al-Thumaid.

    The awards also include a project covering landscaping and an air-conditioned walkway at Qatar University, as part of broader public facilities improvement initiatives.

    According to UK analytics firm GlobalData, Qatar’s construction industry is expected to expand by 4.3% in 2026, supported by investments in renewable energy and transportation infrastructure.

    According to the Planning & Statistics Authority, Qatar’s construction value-add grew by 6.6% year-on-year in the first half of 2025. 

    GlobalData expects the industry to grow at an annual average growth rate of 4.6% in 2027-29, supported by investments in construction, energy and infrastructure projects.


    READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDF

    Riyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.

    Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16010960/main.gif
    Yasir Iqbal