Saudi power sector enters busiest year
10 March 2025

Contracts worth more than $90bn are under execution in Saudi Arabia’s power sector, making 2025 the busiest year ever for generation and transmission capacity buildout in the kingdom.
The construction of conventional and renewable power generation plants accounts for two-thirds, or 66%, of the contracts under execution, while transmission and distribution projects account for the rest, based on the latest available data from regional project tracker MEED Projects.
In addition to gas-fired and renewable energy generation plant projects, the kingdom has awarded several contracts in the past two years to modernise and expand its domestic grids in light of the solar photovoltaic (PV) and wind power plants, and industrial complexes, which are being built in remote areas – as well as Riyadh's plan to trade electricity beyond the kingdom's GCC partners and with countries such as Egypt.
In the past 12 months, the kingdom also awarded the first contracts to build on-grid battery energy storage system (bess) facilities, in line with fostering greater grid flexibility and countering the intermittency of renewable power.
“It has been a very, very busy year, despite some projects – particularly those catering to Neom – being re-scoped,” notes a Dubai-based senior executive with a transaction advisory firm.
The $500bn Neom gigaproject in southwestern Saudi Arabia aims to be powered 100% by renewable energy, which it initially expected to generate independently.
However, ongoing discussions are understood to include an option to meet future demand through renewable power sourced from the grid.
Overall, combined-cycle gas turbine (CCGT) projects – procured on either an independent power project (IPP) or engineering, procurement and construction (EPC) model – account for 56% of the total power generation contracts under execution in Saudi Arabia, with solar and wind accounting for the remaining 44%.
The principal buyer, Saudi Power Procurement Company (SPPC), awarded contracts for two pairs of CCGT plants – projects one and two of the Rumah and Nairiyah schemes – last year.
SPPC also signed the offtake agreements for four solar PV IPPs, which were tendered under the fifth round of the National Renewable Energy Programme (NREP). These were contracts for the 2GW Al-Sadawi, 1.25GW Al-Masaa, 500MW Al-Henakiyah 2 and 300MW Rabigh 2 solar IPPs.
An EPC contract for a high-voltage, direct current transmission network connecting the kingdom’s central and southern electricity grids was also one of the largest deals signed last year in the kingdom.
In the second half of 2024, the developer arm of Saudi Electricity Company (SEC) selected the preferred bidders for several greenfield CCGT expansion plants: Ghazlan 1 and 2, Riyadh PP12 and Marjan.
SEC subsidiary National Grid also awarded the second phase of its bess projects that are being procured on an EPC basis to local firm AlGihaz Holding last year. The three battery energy storage facilities, each with a capacity of 800MW, or about 2,600 megawatt-hours, are to be located in Najran, Khamis Mushait and Madaya.
The extent of work on hand is exerting pressure on contractor capacity, according to some experts.
"I think the Chinese EPC contractors are already at capacity, so SEC has started tapping Egyptian and Spanish EPC contractors," an industry source told MEED, referring to Tecnicas Reunidas, Orascom and Elsewedy, which are understood to have been selected last year to undertake the EPC contracts for several CCGT plants that SEC is developing.
South Korean EPC contractors are also executing several cogeneration and generation power plants in the kingdom.
Outlook
The need to expand, connect and stabilise the kingdom’s electricity grid will be a primary preoccupation for Saudi utility stakeholders in the short to medium term.
This is crucial given the large capacity of renewable energy power generation plants that are scheduled to come on stream, and as the kingdom deploys new gas-fired plants in line with its need to displace liquid fuel in some of its ageing fleet.
Oil fuel still accounted for 36% of Saudi Arabia's total electricity generation in 2023, at 422.9 terawatt-hours, according to the Energy Institute.
Data from MEED Projects suggests that at least $68bn-worth of power generation and transmission contracts are in the pre-execution phase as of March 2025.
Clean energy fuel-powered plants, using solar, wind, hydro and nuclear, dominate the $47bn-worth of planned power generation units, with thermal plants accounting for just 13% of the total.
This signals a shift to clean energy, despite the overall figure excluding a significant volume of renewable energy projects that are still in the concept stage. This is in line with a plan by the Energy Ministry to procure up to 20GW of renewable energy capacity annually until 2030, subject to demand growth.
Planned transmission and distribution projects, including several independent battery energy storage projects, together account for about $21bn of contracts that have yet to be awarded.
Local developers
Local companies are increasingly visible in the procurement proceedings for new power generation and transmission plants in the kingdom.
The decisions made by several European and Japanese developers to retreat from thermal power plant tenders that do not offer a clear carbon capture, utilisation and storage (CCUS) path – which would be necessary for them to meet their 2045 or 2050 net-zero targets – has contributed to this trend.
The exclusion of dominant utility developer Acwa Power in the prequalification process for the NREP’s fifth and sixth procurement rounds has also opened up opportunities for other international and local developers that are keen to win more contracts in Saudi Arabia.
Aljomaih Energy & Water, Ajlan & Brothers, Alfanar, Algihaz and SEC’s developer arm have been pursuing new contracts, usually in cooperation with an international developer.
Battery energy storage
Large-scale solar PV projects and limited wind capacity in the kingdom create a major market for battery energy storage going forwards.
Independent battery energy storage projects, in particular, offer neutral opportunities for both international and local developers, and are expected to attract more bidders compared to conventional thermal or standalone solar PV projects.
“We are definitely interested,” says a senior executive with a European utility developer, referring to the first phase of the kingdom’s independent storage provider (ISP) programme.
In addition to its net-zero merits, the ISPs will follow the same model as an IPP project, where the successful bidders will hold 100% equity in the special purpose vehicles set up to develop and operate the project.
While such strong interest is expected to benefit the principal buyer, which can expect to receive competitive prices from bidders, an over-competitive or crowded landscape could also be off-putting to developers and investors that are keen to maintain their internal rate of return, or which are shifting their global focus to other geographies.
“We prefer to wait and see,” one source tells MEED, indicating that their company does not intend to participate in upcoming battery tenders, not only in Saudi Arabia but also in other GCC states.
Exclusive from Meed
-
Former emir of Qatar Sheikh Hamad dies aged 7413 July 2026
-
-
AtkinsRealis wins Expo 2030 Riyadh design deal13 July 2026
-
Conflict fails to dent Saudi Arabia’s A+ rating13 July 2026
-
KBR re-evaluates design for Libya oil project10 July 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Former emir of Qatar Sheikh Hamad dies aged 7413 July 2026
Sheikh Hamad Bin Khalifa Al-Thani, the former emir who presided over Qatar's transformation into one of the world's richest states and its largest exporter of liquefied natural gas (LNG), has died at the age of 74.
The Amiri Diwan, Qatar's official administrative office, announced his death on the morning of 12 July, describing him as a great leader and mourning the loss to the nation. The country declared a four-day period of public mourning, with work suspended across ministries, government agencies and public institutions from Monday 13 July until employees resume on Sunday 19 July. Flags are to be flown at half-mast throughout the mourning period. Funeral prayers were held after Maghrib prayer on 12 July at the Imam Muhammad Bin Abdul Wahab Mosque, after which his body was laid to rest in Lusail Cemetery.
Sheikh Hamad ruled Qatar from 1995 to 2013 and led its modern economic development. When he took power from his father, the country's finances were strained and its oil reserves were declining. Over the following 18 years, he oversaw an era of rapid economic, social and cultural change that established Qatar as a significant global player in energy, finance and diplomacy.
Gas foundations
Central to that transformation was the development of Qatar's North Field gas reserves, one of the largest single accumulations of natural gas in the world. Through a series of international partnerships and investments, Sheikh Hamad's government built the infrastructure that turned the country into the world's largest exporter of LNG, a position that underpinned decades of budget surpluses and funded an expansive development programme across construction, infrastructure and social services.
The wealth generated by gas exports allowed Qatar to invest heavily both at home and abroad. Sheikh Hamad founded the Qatar Investment Authority (QIA), the sovereign wealth fund that acquired stakes in assets ranging from the London department store Harrods to the football club Paris Saint-Germain. The QIA remains one of the most active sovereign investors in the world and a cornerstone of Qatar's economic strategy.
Born in Doha in 1952, Sheikh Hamad studied at the UK's Royal Military Academy Sandhurst before joining the Qatar Armed Forces and later serving as defence minister. He was named heir apparent in the late 1970s and took power in 1995 while his father was abroad.
Global profile
Sheikh Hamad used Qatar's growing wealth to raise its international standing well beyond its size. In 1996, he backed the launch of the Al-Jazeera television network, which grew into one of the most influential media organisations in the region and further afield. His government also pursued an active diplomatic role, hosting negotiations and international events that positioned Doha as a mediation hub.
The most prominent, and most contested, achievement of his tenure came in 2010, when Qatar won the right to host the 2022 Fifa World Cup. The tournament prompted a multibillion-dollar construction programme, spanning stadiums, transport networks, hotels and wider urban infrastructure, and accelerated the build-out of projects across the country. The bid and the subsequent preparations drew scrutiny over labour conditions and allegations of corruption, of which Qatar was later cleared.
Sheikh Hamad's rule also brought institutional change, including the promulgation of Qatar's first permanent constitution in 2004 and the introduction of municipal elections in which women were permitted to vote and stand as candidates.
In 2013, he handed power to his son and heir apparent, Sheikh Tamim Bin Hamad Al-Thani, then 33, in a rare voluntary abdication by a hereditary Gulf ruler. The transition allowed for a managed handover of a state that had been reshaped over the previous two decades.
Tributes were offered by leaders across the Gulf and beyond, including UAE President Mohamed Bin Zayed Al-Nahyan, Egyptian President Abdel Fattah El-Sisi and the UK's King Charles III, who said Sheikh Hamad had dedicated many years of distinguished service to Qatar.
Qatar was a British protectorate until 1971, with the Al-Thani family having ruled since 1851. Sheikh Hamad leaves a state whose economic weight, built largely on the gas reserves developed during his reign, continues to shape the wider Gulf economy.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17651433/main.jpg -
Contractors submit bids for Ras Tanura refinery gas pipeline13 July 2026

Register for MEED’s 14-day trial access
Contractors have submitted bids to Saudi Aramco for a tender to replace a pipeline in the Gas Line Abqaiq-Ras Tanura (GART) transmission network.
The GART grid transports associated gas and natural gas liquids (NGL) from the Abqaiq oil processing complex as feedstock, northwards to the Ras Tanura refinery in Saudi Arabia’s Eastern Province.
The aim of the project is to replace the GART-22 pipeline that connects the Juaymah export terminal on the Gulf coast in the Eastern Province to the Ras Tanura refinery, to ensure reliable fuel gas supply and meet ongoing demand.
The basic scope of work for the project is to install a new 24-inch pipeline system to replace the GART-22 line and the abandoned GART-24 line. It will cover a distance of 18 kilometres between Juaymah and the Ras Tanura terminal.
The scope also includes the installation of associated scraper trap facilities (launcher and receiver), pressure control valves, motor-operated valves and gas detection and sampling systems.
Aramco issued the tender for the project in May, setting an initial deadline of 30 June for contractors to submit proposals, MEED previously reported.
The Saudi energy giant then extended the deadline until 10 July, and then allowed bidders until 12 July. Contractors submitted their proposals by that final deadline, according to sources.
The following contractors, among others, are understood to be bidding for the project:
- ACE Pipeline Arabia
- Combined Group Contracting Company
- Gas Arabian Services Company
- Max Streicher Saudi Arabia
- National Basics Company
- Saad Ali Alessa Group
- Sicim
- Sinopec Engineering Group Saudi
- Tecton Engineering & Construction
Ras Tanura refinery complex
The Ras Tanura refinery is the oldest, and one of the largest, crude oil refineries in Saudi Arabia. The complex has a refining capacity of 550,000 barrels a day (b/d).
The facility also has a 305,000 b/d NGL processing facility, a 960,000 b/d crude stabilisation facility, combined steam and gas turbine electrical power generation plants with a summer capacity of 145MW and a winter capacity of 158MW, and a combined 150-pound and 600-pound steam capacity of 6,217 million pounds an hour.
It has 75 crude oil and products storage tanks with a combined capacity of 5.8 million barrels.
The Ras Tanura refinery’s major facilities include a 325,000 b/d crude distillation unit, a 225,000 b/d gas condensate distillation unit, a 50,000 b/d hydrocracker and 107,000 b/d of catalytic reforming capacity.
The facility is Aramco’s only refinery to contain a Visbreaker processing unit, which has a 60,000 b/d capacity.
The Visbreaker reduces the quantity of residual oil produced in the distillation of crude oil and increases the yield of more valuable middle distillates, heating oil and diesel.
The refinery complex also produces 17,000 b/d of asphalt, more than any other refinery in Saudi Arabia.
Ras Tanura receives crude feedstock from the Abqaiq, Safaniya and Manifa oil field developments.
Crude is typically transferred to Ras Tanura through a pipeline and can also be supplied by ship.
Most of Ras Tanura’s production is transferred to the Dhahran bulk plant for domestic use, while some products are exported from the nearby Ras Tanura shipping terminal.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17649169/main2152.jpg -
AtkinsRealis wins Expo 2030 Riyadh design deal13 July 2026
Canadian engineering firm AtkinsRealis has won a contract to deliver lead design services for the Place & Planet Pavilion at the Expo 2030 Riyadh site.
The contract was awarded by Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue.
AtkinsRealis will deliver the full architectural and engineering design for the pavilion, coordinate all relevant design disciplines and embed sustainable design principles throughout.
The Place & Planet Pavilion is anticipated to be a key attraction at Expo 2030 Riyadh.
The latest development follows ERC tendering a contract to build the Saudi Arabia pavilion at the site.
The pavilion is a major asset located within the KSA District on the eastern side of the Expo 2030 Riyadh masterplan, within the Loop of Nations district.
The tendering of the pavilion structure followed swift progress on the site’s infrastructure development works.
In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Al-Yamama Company.
The scope covers the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.
These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners. That scope covers about 50 kilometres of integrated infrastructure networks, including internal roads and utilities such as water, sewage, electrical and communication systems and electric vehicle charging stations.
The overall infrastructure works – covering the construction of main utilities and civil works at Expo 2030 Riyadh – are split into three packages:
- Lot 1 covers the main utilities corridor
- Lot 2 includes the northern cluster of the nature corridor
- Lot 3 comprises the southern cluster of the nature corridor
The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport, and will provide direct access to various landmarks within Riyadh.
The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17642053/main.jpg -
Conflict fails to dent Saudi Arabia’s A+ rating13 July 2026
Ratings agency Fitch has affirmed Saudi Arabia's long-term foreign-currency issuer default rating at A+ with a stable outlook, citing fiscal and external balance sheets that remain significantly stronger than those of similarly rated peers.
In a rating action published on 10 July, Fitch said the kingdom's economy and public finances had proved resilient to the US-Iran war, supported by significant fiscal buffers in the form of deposits and other public-sector assets. Oil dependence and governance scores had improved but remained weaknesses, while geopolitical risk stayed high.
A deal allowing a ceasefire and the reopening of the Strait of Hormuz is broadly in place, although Fitch warns that flare-ups highlight risks to its near-term sustainability. The agency says further US or Israeli military action against Iran remains quite likely. It expects the reopening of the strait to return the oil market to oversupply, pulling Brent down to an average of $60 a barrel in 2028 from $87 a barrel in 2026.
Fitch forecasts real GDP growth will slow to 0.6% in 2026, hit by disruption to trade during the closure of the strait. Flows through the East-West pipeline support oil production during the war, but output at an annual average of 9 million barrels a day will sit below the 2025 level.
Growth is expected to rebound in 2027 as flows normalise, before easing to 2.9% in 2028, supported by the phased opening of gigaprojects and guidance that sovereign wealth vehicle the Public Investment Fund will keep domestic spending largely unchanged.
The fiscal deficit is projected to narrow in 2026 as higher oil prices offset lower volumes, before widening to 4.7% in 2027 on a fiscal breakeven oil price of $94 a barrel. Fitch projects government debt will rise to 41.3% of GDP by the end of 2028, from 31.8% at the end of 2025, above the government's guidance of a 40% ceiling.
The agency describes the external balance sheet as healthy, with sovereign net foreign assets of 38.5% of GDP by the end of 2028. Banks have been resilient to the war, with non-performing loans at 1.1% and a Tier 1 capital ratio of 19.2% at the end of the first quarter of 2026.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17644782/main.gif -
KBR re-evaluates design for Libya oil project10 July 2026

US-headquartered KBR is responsible for re-evaluating the front-end engineering and design (feed) for the project to develop the J6 North Gialo field in Libya, according to industry sources.
In June, MEED reported that Libya’s Waha Oil Company (WOC), a subsidiary of the state-owned National Oil Corporation (NOC), had launched a review into the tender process for the J6 North Gialo oil field development project, and that this would include re-evaluating the feed work.
The Waha concessions are held by a consortium of Libya’s NOC, which holds 59.16%; TotalEnergies, holding 20.42%; and US-based ConocoPhillips, with 20.42%.
They are operated by WOC, which is 100% owned by NOC.
KBR has previously provided engineering services for major national projects in Libya, such as the Great Man-Made River project, which is widely recognised as the largest irrigation project in the world.
In March, KBR was awarded a contract by Zallaf Exploration, Production & Refining of Oil & Gas Company to provide project management and technical services for the South Refinery project in Libya’s southern city of Ubari.
Under the terms of the contract, KBR will provide contract management, project management and supporting technical services throughout the engineering, procurement and construction (EPC) phases of the project.
The EPC work is expected to be executed over a 50-month period.
In its statement, KBR said that the project is aligned with its “long-standing commitment to advancing vital oil and gas infrastructure in Libya”.
In March, MEED reported that South Korea’s Daewoo had pulled out of the tender process for Libya’s J6 North Gialo oil field development project.
Daewoo had formed a partnership with Egypt’s Petrojet to participate in the tender process.
The only other company to submit a bid for the project was UK-based Petrofac, which filed for administration in October last year.
In January, TotalEnergies signed an agreement extending the Waha concessions agreement up to 31 December 2050.
This agreement set new fiscal terms, allowing an increase in the production of these concessions that were, at the time, producing about 370,000 barrels of oil equivalent a day (boe/d).
In January, TotalEnergies said that the deal paved the way for “a new phase of investments, including the development of the North Gialo field, which is expected to add 100,000 boe/d of production”.
The J6 North Gialo project is the first of three field development projects that WOC has prioritised.
The other two are known as NC98 and Gialo 3.
Together, the three projects are expected to double Waha’s production from about 300,000 barrels a day (b/d) of oil to 600,000 b/d.
The Waha concession covers 13 million acres.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17621475/main.jpg