Saudi power sector enters busiest year

10 March 2025

 

Contracts worth more than $90bn are under execution in Saudi Arabia’s power sector, making 2025 the busiest year ever for generation and transmission capacity buildout in the kingdom.

The construction of conventional and renewable power generation plants accounts for two-thirds, or 66%, of the contracts under execution, while transmission and distribution projects account for the rest, based on the latest available data from regional project tracker MEED Projects.

In addition to gas-fired and renewable energy generation plant projects, the kingdom has awarded several contracts in the past two years to modernise and expand its domestic grids in light of the solar photovoltaic (PV) and wind power plants, and industrial complexes, which are being built in remote areas – as well as Riyadh's plan to trade electricity beyond the kingdom's GCC partners and with countries such as Egypt.

In the past 12 months, the kingdom also awarded the first contracts to build on-grid battery energy storage system (bess) facilities, in line with fostering greater grid flexibility and countering the intermittency of renewable power.

“It has been a very, very busy year, despite some projects – particularly those catering to Neom – being re-scoped,” notes a Dubai-based senior executive with a transaction advisory firm.

The $500bn Neom gigaproject in southwestern Saudi Arabia aims to be powered 100% by renewable energy, which it initially expected to generate independently.

However, ongoing discussions are understood to include an option to meet future demand through renewable power sourced from the grid.

Overall, combined-cycle gas turbine (CCGT) projects – procured on either an independent power project (IPP) or engineering, procurement and construction (EPC) model – account for 56% of the total power generation contracts under execution in Saudi Arabia, with solar and wind accounting for the remaining 44%.

The principal buyer, Saudi Power Procurement Company (SPPC), awarded contracts for two pairs of CCGT plants – projects one and two of the Rumah and Nairiyah schemes – last year.

SPPC also signed the offtake agreements for four solar PV IPPs, which were tendered under the fifth round of the National Renewable Energy Programme (NREP). These were contracts for the 2GW Al-Sadawi, 1.25GW Al-Masaa, 500MW Al-Henakiyah 2 and 300MW Rabigh 2 solar IPPs.

An EPC contract for a high-voltage, direct current transmission network connecting the kingdom’s central and southern electricity grids was also one of the largest deals signed last year in the kingdom.

In the second half of 2024, the developer arm of Saudi Electricity Company (SEC) selected the preferred bidders for several greenfield CCGT expansion plants: Ghazlan 1 and 2, Riyadh PP12 and Marjan.

SEC subsidiary National Grid also awarded the second phase of its bess projects that are being procured on an EPC basis to local firm AlGihaz Holding last year. The three battery energy storage facilities, each with a capacity of 800MW, or about 2,600 megawatt-hours, are to be located in Najran, Khamis Mushait and Madaya.

The extent of work on hand is exerting pressure on contractor capacity, according to some experts.

"I think the Chinese EPC contractors are already at capacity, so SEC has started tapping Egyptian and Spanish EPC contractors," an industry source told MEED, referring to Tecnicas Reunidas, Orascom and Elsewedy, which are understood to have been selected last year to undertake the EPC contracts for several CCGT plants that SEC is developing.

South Korean EPC contractors are also executing several cogeneration and generation power plants in the kingdom.

Outlook

The need to expand, connect and stabilise the kingdom’s electricity grid will be a primary preoccupation for Saudi utility stakeholders in the short to medium term.

This is crucial given the large capacity of renewable energy power generation plants that are scheduled to come on stream, and as the kingdom deploys new gas-fired plants in line with its need to displace liquid fuel in some of its ageing fleet.

Oil fuel still accounted for 36% of Saudi Arabia's total electricity generation in 2023, at 422.9 terawatt-hours, according to the Energy Institute.

Data from MEED Projects suggests that at least $68bn-worth of power generation and transmission contracts are in the pre-execution phase as of March 2025.

Clean energy fuel-powered plants, using solar, wind, hydro and nuclear, dominate the $47bn-worth of planned power generation units, with thermal plants accounting for just 13% of the total.

This signals a shift to clean energy, despite the overall figure excluding a significant volume of renewable energy projects that are still in the concept stage. This is in line with a plan by the Energy Ministry to procure up to 20GW of renewable energy capacity annually until 2030, subject to demand growth.

Planned transmission and distribution projects, including several independent battery energy storage projects, together account for about $21bn of contracts that have yet to be awarded.

Local developers

Local companies are increasingly visible in the procurement proceedings for new power generation and transmission plants in the kingdom.

The decisions made by several European and Japanese developers to retreat from thermal power plant tenders that do not offer a clear carbon capture, utilisation and storage (CCUS) path – which would be necessary for them to meet their 2045 or 2050 net-zero targets – has contributed to this trend.

The exclusion of dominant utility developer Acwa Power in the prequalification process for the NREP’s fifth and sixth procurement rounds has also opened up opportunities for other international and local developers that are keen to win more contracts in Saudi Arabia.

Aljomaih Energy & Water, Ajlan & Brothers, Alfanar, Algihaz and SEC’s developer arm have been pursuing new contracts, usually in cooperation with an international developer.

Battery energy storage

Large-scale solar PV projects and limited wind capacity in the kingdom create a major market for battery energy storage going forwards.

Independent battery energy storage projects, in particular, offer neutral opportunities for both international and local developers, and are expected to attract more bidders compared to conventional thermal or standalone solar PV projects.

“We are definitely interested,” says a senior executive with a European utility developer, referring to the first phase of the kingdom’s independent storage provider (ISP) programme.

In addition to its net-zero merits, the ISPs will follow the same model as an IPP project, where the successful bidders will hold 100% equity in the special purpose vehicles set up to develop and operate the project.

While such strong interest is expected to benefit the principal buyer, which can expect to receive competitive prices from bidders, an over-competitive or crowded landscape could also be off-putting to developers and investors that are keen to maintain their internal rate of return, or which are shifting their global focus to other geographies.

“We prefer to wait and see,” one source tells MEED, indicating that their company does not intend to participate in upcoming battery tenders, not only in Saudi Arabia but also in other GCC states.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13466191/main.gif
Jennifer Aguinaldo
Related Articles
  • Oman prepares for wave of IPP awards

    3 December 2025

     

    Contract activity in Oman’s power sector slowed in 2025, yet the sultanate is entering the new year with its diversification plans advancing and procurement for independent power projects (IPPs) gathering pace.

    In the renewables segment, progress continued in September with the award of the sultanate’s fourth large-scale solar IPP. The 500MW Ibri 3 solar IPP was awarded to a consortium of Abu Dhabi Future Energy Company (Masdar), Korea Midland Power and local firms Al-Khadra Partners and OQ Alternative Energy.

    The project also incorporates a 100MWh battery system, making it Oman’s first utility-scale solar-and-storage development.

    Ibri 3 accounted for almost 60% of the power contract awards in 2025. While this reflects a quieter year for investment, it also highlights the transition taking place in the market, with attention shifting towards grid reinforcement and preparations for a series of IPPs expected to advance over the coming period.

    The inauguration of the 500MW Manah 1 and Manah 2 solar IPPs earlier in the year added further capacity, building on the operational Ibri 2 plant, which came online in 2021.

    Wind procurement also continues to advance. In November, Nama Power & Water Procurement Company (Nama PWP) signed a 20-year power purchase agreement with a joint venture of Singapore’s Sembcorp Utilities and OQ Alternative Energy for the Dhofar 2 wind IPP.

    The 125MW plant is scheduled to begin operations in the third quarter of 2027 and will add capacity to the Dhofar Power System (DPS), where Oman’s first commercial wind farm, the 50MW Dhofar project, already operates.

    In the DPS, peak demand is anticipated to grow by 5% a year, from 612MW in 2022 to 837MW in 2029. The Sadah wind IPP, which will add around 99MW to the system once operational, is expected to move forward in the coming months.

    Overall, the direction of the sector remains aligned with national plans to increase renewable energy’s share of electricity generation to 30% by 2030 and expand steadily thereafter.

    Oman’s renewable energy programme is expected to expand considerably by 2030, with about 4.5GW of solar IPPs and around 1GW of wind farms planned across multiple sites.

    Increasing wind power

    The wider wind programme includes the Duqm and Mahoot wind IPPs, which are moving forward and will have a combined generation capacity of more than 600MW. In October, Nama PWP issued a supervisory consultancy services tender for the Duqm project.

    Several awards are expected in the near term. Jalan Bani Bu Ali, a wind IPP of about 100MW, and the 280MW Al-Kamil Wal Wafi solar photovoltaic IPP are among four IPPs currently under bid evaluation.

    While Oman continues to scale up renewable capacity, the need for firm generation remains. Peak demand in Oman’s Main Interconnection System (MIS) is expected to grow at an average of 3.4% a year over the current planning period, reaching about 8,350MW in 2029, up from 6,628MW in 2022. 

    Demand in the MIS is likely to continue rising through the decade, supported by industrial growth, population increases and development in economic zones such as Duqm.

    Nama PWP aims to meet this requirement with two major thermal schemes: the $1.53bn gas-fired Misfah IPP and the $753m Duqm IPP. The state offtaker has received three bids for the development and operation of the plants, which together will supply 2,400MW and are scheduled to begin delivering early power by April 2028.

    Developing the grid

    Similar to previous planning cycles, grid development remains a priority. In September, the GCC Interconnection Authority signed a $500m interim financing agreement with Sohar International Bank to support the development of the direct Oman-GCC electricity interconnection.

    The project involves constructing a 400-kilovolt double-circuit line stretching approximately 530km between the Al-Sila station in the UAE and a new Ibra substation in Oman.

    Once completed, the link will enhance regional power exchange capability, improve reserve margins and support the integration of intermittent renewable power.

    These regional works complement domestic transmission upgrades, including the continued expansion of the Rabt North-South Interconnection. The first phase, completed in 2023, connected the MIS with the Duqm Power System.

    Construction works are ongoing on the second phase, which is expected to reinforce the 400kV backbone southwards toward Dhofar.

    New technologies are also emerging in Oman’s power programme. Ibri 3 represents the first deployment of utility-scale battery storage in the sultanate, setting a precedent for integrating storage with future renewable projects. 

    In parallel, Nama PWP and Oman Environmental Services Holding Company (Beah) are preparing to tender the main contract for a 100MW waste-to-energy (WTE) project in Barka.

    Estimated to cost almost $1bn, the scheme would be Oman’s first major WTE facility and reflects broader efforts to embed circular-economy principles into the national infrastructure programme.

    Water sector

    The water sector recorded a solid year, with about $1bn in contract awards, although activity remained below 2024 levels.

    In March, China National Electric Engineering Corporation (CNEEC) won the main contract for a $200m deep-sea desalination project, heading a list of smaller wastewater and transmission packages awarded across 2025.

    Following the commissioning of the Barka 5 independent water project (IWP) and continued construction on the Ghubrah 3 IWP, planning attention has shifted to the next cycle of capacity.

    The next major scheme expected to move forward is a $150m desalination plant in Dhofar, with a planned capacity of 22 million imperial gallons a day.

    Rising water demand in Sharqiyah and Dhofar continues to guide long-term planning with more than $800m-worth of water transmission and treatment schemes set to be awarded in the near to medium terms.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15196122/main.gif
    Mark Dowdall
  • Local contractor wins Saudi substation deal

    3 December 2025

    Saudi Arabia-based Nesma Infrastructure & Technology has signed a contract with state-owned utility Saudi Electricity Company (SEC) to replace the Jubail Southeast 230/115/34.5kV substation.

    The project includes overhead transmission line (OHTL) works and is valued at more than SR840m ($224m). It is scheduled to be delivered within 20 months.

    The award forms part of SEC’s ongoing programme to upgrade ageing substations and reinforce network capacity in the Jubail industrial area.

    In September, local contractor Al-Fanar Projects was appointed to replace the Jubail Southwest 230/115KV substation, one of several transmission assets in the region undergoing phased renewal.

    As MEED recently reported, SEC has plans to invest SR220bn ($58.7bn) in power projects by 2030. This includes SR135bn ($36bn) and SR85bn ($22.7bn) for transmission and distribution, respectively.

    According to the utility, its planned upgrades will cover 130 high-voltage substations, 135,000 MVA of capacity, 12,900 kilometres of overhead transmission lines and 1,100km of underground cables.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15195824/main.jpg
    Mark Dowdall
  • SEC signs $347m power works deal for Soudah Peaks

    3 December 2025

    Register for MEED’s 14-day trial access 

    Saudi Electricity Company (SEC) has announced that its transmission subsidiary, National Grid, has signed a SR1.3bn ($347m) agreement with Soudah Development to deliver the electrical infrastructure for Saudi Arabia’s Soudah Peaks project.

    Soudah Peaks is a major high-altitude tourism and real estate development in the Asir mountains, led by Soudah Development, a wholly owned Public Investment Fund (PIF) company.

    The $7.7bn project includes hotels, resorts, residential units, entertainment facilities and outdoor activity zones at elevations of up to 3,000 metres. It will be developed over three phases, with full completion scheduled for 2033.

    Under the agreement, National Grid will develop a full integrated electrical network to support the project’s phased construction.

    The scope includes a central 380/132kV transmission substation with a capacity of 500MVA and two 13.8/132kV substations. The company will also build the electrical interconnection needed to supply all stages of the development.

    The first phase of the initiative will see the development of 454 residential units, 1,010 hotel keys and retail space with a gross leasable area of 20,625 square metres by 2027.

    The overall project includes the development of six main areas: Red Rock Mountain, Tahlal gateway to Soudah Peaks, Sahab, Sabrah, Jareen and Rijal.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15194632/main.jpg
    Mark Dowdall
  • Jeddah Economic Company appoints new CEO

    3 December 2025

    Register for MEED’s 14-day trial access 

    Jeddah Economic Company (JEC), the developer of the world’s tallest tower project, has appointed Fabian Toscano as its new CEO.

    In an official statement, JEC said: “Toscano will lead the next phase of development for Jeddah Economic City and the Jeddah Tower. His focus will include accelerating development activity, strengthening global collaborations, and shaping a world-class destination aligned with the ambitions of Saudi Vision 2030.”

    Toscano has previously served as the CEO of AlUla Development Company.

    Last year, JEC signed an estimated SR8bn, 42-month contract with SBG to resume construction work on the tower. SBG then began engaging with the supply chain to work on the project. SBG awarded Beijing-headquartered Jangho Group a facade works contract that involves engineering design and technical services for the project’s structural glass and adhesive curtain walls. 

    At the time, Jeddah Tower’s superstructure was about one-third complete, with 63 floors out of a total 157. SBG was the main contractor on the project in the early and mid-2010s. Germany’s Bauer completed the tower’s piling work.

    The architect is US-based Adrian Smith & Gordon Gill, and the engineering consultant is Lebanon’s Dar Al-Handasah (Shair & Partners).

    Jeddah Tower is the centrepiece of the Jeddah Economic City development. The project’s first phase, which includes the main tower, covers an area of 1.5 million square metres.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15194477/main.gif
    Yasir Iqbal
  • Saudi Arabia approves 2026 state budget

    3 December 2025

    Saudi Arabia has approved a SR1.313tn ($349bn) state budget for fiscal year 2026, maintaining an expansionary spending stance as it pursues its Vision 2030 economic transformation agenda.

    The Ministry of Finance’s Final Budget Statement, released on 2 December, projects revenues of SR1.147tn, leaving an estimated deficit of SR165bn, equivalent to about 3.3% of GDP. The figures are broadly in line with the projections set out in October’s pre-budget statement.

    Finance Minister Mohammed Aljadaan said the 2026 budget underlines Riyadh’s commitment to sustaining economic diversification and social development while preserving fiscal sustainability over the medium term. He stressed that citizens remain the core focus of spending plans, with continued allocations for education, health and social services, alongside investments in infrastructure and quality-of-life improvements across the kingdom’s regions.

    Non-oil activities are expected to remain the main engine of growth. Initial estimates for 2025 point to a 5% expansion in non-oil GDP, supported by higher investment and consumption, while real GDP is forecast to grow by 4.6% in 2026, driven primarily by non-oil sectors.

    Public debt is projected to rise to SR1.457tn in 2025 (31.7% of GDP) and SR1.622tn in 2026 (32.7% of GDP). Aljadaan said the debt profile remains sustainable by international standards and confirmed that the government will continue to tap local and international debt markets and alternative financing channels to cover the deficit and refinance maturing obligations.

    Government reserves held at the Saudi Central Bank are expected to remain stable at around SR390bn through the end of 2026, supporting the kingdom’s capacity to absorb external shocks. The minister said ongoing structural and fiscal reforms have strengthened public finance management and enhanced the resilience of the Saudi economy amid a challenging and uncertain global environment.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15194673/main.gif
    Colin Foreman