Saudi power sector enters busiest year
10 March 2025

Contracts worth more than $90bn are under execution in Saudi Arabia’s power sector, making 2025 the busiest year ever for generation and transmission capacity buildout in the kingdom.
The construction of conventional and renewable power generation plants accounts for two-thirds, or 66%, of the contracts under execution, while transmission and distribution projects account for the rest, based on the latest available data from regional project tracker MEED Projects.
In addition to gas-fired and renewable energy generation plant projects, the kingdom has awarded several contracts in the past two years to modernise and expand its domestic grids in light of the solar photovoltaic (PV) and wind power plants, and industrial complexes, which are being built in remote areas – as well as Riyadh's plan to trade electricity beyond the kingdom's GCC partners and with countries such as Egypt.
In the past 12 months, the kingdom also awarded the first contracts to build on-grid battery energy storage system (bess) facilities, in line with fostering greater grid flexibility and countering the intermittency of renewable power.
“It has been a very, very busy year, despite some projects – particularly those catering to Neom – being re-scoped,” notes a Dubai-based senior executive with a transaction advisory firm.
The $500bn Neom gigaproject in southwestern Saudi Arabia aims to be powered 100% by renewable energy, which it initially expected to generate independently.
However, ongoing discussions are understood to include an option to meet future demand through renewable power sourced from the grid.
Overall, combined-cycle gas turbine (CCGT) projects – procured on either an independent power project (IPP) or engineering, procurement and construction (EPC) model – account for 56% of the total power generation contracts under execution in Saudi Arabia, with solar and wind accounting for the remaining 44%.
The principal buyer, Saudi Power Procurement Company (SPPC), awarded contracts for two pairs of CCGT plants – projects one and two of the Rumah and Nairiyah schemes – last year.
SPPC also signed the offtake agreements for four solar PV IPPs, which were tendered under the fifth round of the National Renewable Energy Programme (NREP). These were contracts for the 2GW Al-Sadawi, 1.25GW Al-Masaa, 500MW Al-Henakiyah 2 and 300MW Rabigh 2 solar IPPs.
An EPC contract for a high-voltage, direct current transmission network connecting the kingdom’s central and southern electricity grids was also one of the largest deals signed last year in the kingdom.
In the second half of 2024, the developer arm of Saudi Electricity Company (SEC) selected the preferred bidders for several greenfield CCGT expansion plants: Ghazlan 1 and 2, Riyadh PP12 and Marjan.
SEC subsidiary National Grid also awarded the second phase of its bess projects that are being procured on an EPC basis to local firm AlGihaz Holding last year. The three battery energy storage facilities, each with a capacity of 800MW, or about 2,600 megawatt-hours, are to be located in Najran, Khamis Mushait and Madaya.
The extent of work on hand is exerting pressure on contractor capacity, according to some experts.
"I think the Chinese EPC contractors are already at capacity, so SEC has started tapping Egyptian and Spanish EPC contractors," an industry source told MEED, referring to Tecnicas Reunidas, Orascom and Elsewedy, which are understood to have been selected last year to undertake the EPC contracts for several CCGT plants that SEC is developing.
South Korean EPC contractors are also executing several cogeneration and generation power plants in the kingdom.
Outlook
The need to expand, connect and stabilise the kingdom’s electricity grid will be a primary preoccupation for Saudi utility stakeholders in the short to medium term.
This is crucial given the large capacity of renewable energy power generation plants that are scheduled to come on stream, and as the kingdom deploys new gas-fired plants in line with its need to displace liquid fuel in some of its ageing fleet.
Oil fuel still accounted for 36% of Saudi Arabia's total electricity generation in 2023, at 422.9 terawatt-hours, according to the Energy Institute.
Data from MEED Projects suggests that at least $68bn-worth of power generation and transmission contracts are in the pre-execution phase as of March 2025.
Clean energy fuel-powered plants, using solar, wind, hydro and nuclear, dominate the $47bn-worth of planned power generation units, with thermal plants accounting for just 13% of the total.
This signals a shift to clean energy, despite the overall figure excluding a significant volume of renewable energy projects that are still in the concept stage. This is in line with a plan by the Energy Ministry to procure up to 20GW of renewable energy capacity annually until 2030, subject to demand growth.
Planned transmission and distribution projects, including several independent battery energy storage projects, together account for about $21bn of contracts that have yet to be awarded.
Local developers
Local companies are increasingly visible in the procurement proceedings for new power generation and transmission plants in the kingdom.
The decisions made by several European and Japanese developers to retreat from thermal power plant tenders that do not offer a clear carbon capture, utilisation and storage (CCUS) path – which would be necessary for them to meet their 2045 or 2050 net-zero targets – has contributed to this trend.
The exclusion of dominant utility developer Acwa Power in the prequalification process for the NREP’s fifth and sixth procurement rounds has also opened up opportunities for other international and local developers that are keen to win more contracts in Saudi Arabia.
Aljomaih Energy & Water, Ajlan & Brothers, Alfanar, Algihaz and SEC’s developer arm have been pursuing new contracts, usually in cooperation with an international developer.
Battery energy storage
Large-scale solar PV projects and limited wind capacity in the kingdom create a major market for battery energy storage going forwards.
Independent battery energy storage projects, in particular, offer neutral opportunities for both international and local developers, and are expected to attract more bidders compared to conventional thermal or standalone solar PV projects.
“We are definitely interested,” says a senior executive with a European utility developer, referring to the first phase of the kingdom’s independent storage provider (ISP) programme.
In addition to its net-zero merits, the ISPs will follow the same model as an IPP project, where the successful bidders will hold 100% equity in the special purpose vehicles set up to develop and operate the project.
While such strong interest is expected to benefit the principal buyer, which can expect to receive competitive prices from bidders, an over-competitive or crowded landscape could also be off-putting to developers and investors that are keen to maintain their internal rate of return, or which are shifting their global focus to other geographies.
“We prefer to wait and see,” one source tells MEED, indicating that their company does not intend to participate in upcoming battery tenders, not only in Saudi Arabia but also in other GCC states.
Exclusive from Meed
-
Saudi water sector hits sharp slowdown8 September 2026
-
Kuwait grants loan for GCC grid extension study8 September 2026
-
Chinese firm to set up $300m anode facility in the UAE8 September 2026
-
Riyadh tenders Expo 2030 Souq areas package8 September 2026
-
Powering the next chapter with nuclear energy8 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Saudi water sector hits sharp slowdown8 September 2026

Saudi Arabia’s water sector has recorded a sharp slowdown in contract awards this year, with $3.94bn of new contracts awarded as of early September.
According to regional project tracker MEED Projects, this is well below the $10.7bn recorded in 2025, $13bn in 2024 and a record $15.3bn in 2023.
The slowdown comes as several major projects remain in the procurement process, with some yet to reach financial close or contract award, while tender deadlines for other schemes have been pushed back.
Among the largest is the estimated $2bn Riyadh-Qassim independent water transmission pipeline. The 859-kilometre project will have a transmission capacity of 685,000 cubic metres a day (cm/d). Vision Invest was selected as the preferred bidder last December; however, more than eight months later, an official developer’s agreement has not yet been signed.
Similarly, the Arana and Hadda independent sewage treatment plant (ISTP) projects have yet to reach the financial close originally targeted for the second quarter. The two schemes will provide a combined treatment capacity of 350,000 cm/d.
Delays extend further down the procurement pipeline. The latest developer bid deadline for the estimated $150m Riyadh East ISTP is 29 September, almost a year after the request for proposals (RFP) was issued in October 2025.
Procurement for the main contracts for the Jubail-Buraidah and Ras Mohaisen-Baha-Mecca independent water transmission system projects could also slip into 2027, amid delivery-model changes by Water Transmission Company.
New awards
The market received a boost in September when Saudi Arabia’s National Water Company (NWC) announced it had signed a SR1.3bn ($347m) deal with a Saudi-Chinese consortium for package 10 of its long-term operations and maintenance programme.
The consortium – comprising China’s Jiangsu United Water Technology and Saudi-based Armada Holding – will rehabilitate, operate and maintain nine sewage treatment plants (STPs) with a combined design capacity of more than 337,000 cm/d. Based on the latest procurement timeline, it is unclear whether the selected consortium for package 11 will be formally announced this year. Packages 12 and 14 remain under tender while package 16 is next in line, with its RFP not expected to be issued before November.
NWC is the second-largest awarding entity by value in 2026, accounting for $1.09bn, or about 28% of the total. Saudi Aramco is the largest, with $2.15bn, meaning the two organisations account for more than 82% of awards so far this year.
Aramco’s activity has been led by two major oil field developments. In June, it awarded the $1.5bn Safaniya onshore surface facilities project: package 1 to a joint venture of Tecnimont and Consolidated Contractors Company. The package includes a water treatment and injection plant supporting upstream production.
It also awarded the second phase of its Zuluf water treatment project to a joint venture of Almar Water Solutions and AlJomaih Energy & Water. The project will add a 308,000-cm/d treatment facility at Tanajib in the Eastern Province, supplying water for injection at the offshore Zuluf oil field.
The concentration of awards in industrial projects this year has been notable. Against the slowdown in municipal water infrastructure procurement, much of the value awarded so far has been linked to the water requirements of oil and gas and mining developments.
The third-largest award is the $350m Taif Ar Rjum water pipeline project, being developed by Saudi Arabian Mining Company (Maaden) in Mecca. The project will support the Ar Rjum gold mining and processing facility and is being developed under a build-own-operate-transfer model.
By project type, treatment projects make up the largest share of awards, at $2.85bn or about 72% of the total. Transmission projects account for $980m and cooling projects for a further $110m, while no major desalination or water storage contracts have been awarded so far this year.
Project pipeline
The slowdown in awards appears to reflect the timing of projects moving through procurement rather than a fundamental weakening in demand for water infrastructure.
Saudi Arabia continues to face rising demand for desalination, wastewater treatment and water transmission as population growth and industrial expansion drive demand for water.
Sharakat, formerly Saudi Water Partnership Company, set out the next phase of the kingdom’s water investment programme in its latest seven-year statement, published in March.
The plan points to a significant expansion in desalination capacity. Capacity from Sharakat-procured projects is expected to increase from about 3.88 million cm/d in 2025 to roughly 7.18 million cm/d by 2031.
The increase will be supported by seven new independent water plants (IWPs) with a combined capacity of about 2.8 million cm/d, in addition to projects already operating, under construction or in procurement.
However, several of the planned projects have yet to move into active procurement, while others have seen their expected timelines pushed back.
Among the schemes affected are the Ras Al-Khair, Tabuk, Shuqaiq and Jizan IWPs, which have all progressed through prequalification, but have seen changes to their expected procurement schedules.
The largest is phase two of the Ras Al-Khair IWP, a 600,000-cm/d reverse osmosis desalination plant that has been in development for more than a decade.
The revised schedule indicates that the $400m Al-Shuqaiq 4 IWP is expected to be the first of the seven new plants to reach commercial operation. Its main contract had been expected to be tendered later this year, but it is now understood that the first RFP will not be issued until early 2027.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19466739/main.gif -
Kuwait grants loan for GCC grid extension study8 September 2026
The Kuwait Fund for Arab Economic Development has signed a KD200,000 ($647,000) grant agreement with the GCC Interconnection Authority (GCCIA) to finance a feasibility study on extending the Gulf power grid to electricity networks outside the GCC.
The agreement was signed on 3 September by Ahmed Bin Ali Al-Ibrahim, CEO of the GCCIA, and Kuwait Fund acting director general Rashid Al-Bader.
The study will assess opportunities to expand the GCC power interconnection system to neighbouring countries. It will examine their electricity requirements and the technical and economic feasibility of connecting their national grids to the Gulf network.
The Kuwait Fund did not identify the countries or potential interconnection routes. However, it is understood that the study will identify potential phases for future expansion, determine priority projects and assess the most appropriate interconnection options based on technical and economic criteria.
It will cover the proposed project’s main components, costs, implementation arrangements and expected timeframe. The study will also assess the potential economic and social benefits for GCC member states and connected countries, as well as how the GCC network would operate alongside neighbouring national grids.
A preliminary assessment of the project’s potential environmental and social impacts will also be carried out, together with proposed mitigation measures.
The Kuwait Fund has previously provided three loans worth a combined KD78m ($252m) to GCCIA to support expansion of the GCC power interconnection system and its connection to southern Iraq’s electricity grid.
In August 2025, the fund announced two loans worth KD70m ($224m) for the expansion of the Gulf Power Interconnection Project. The financing included support for the Al-Wafra 400kV substation and infrastructure connecting Kuwait’s grid with Iraq.
The Al-Wafra substation facilitates electricity exchanges and enables Kuwait to access surplus power available through the GCC interconnection system.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19461053/main.jpg -
Chinese firm to set up $300m anode facility in the UAE8 September 2026
Beijing-headquartered Sunstone Development has signed a memorandum of understanding (MoU) with the UAE Ministry of Investment to develop an anode production facility in the UAE, with an estimated investment of about $300m.
The MoU follows Sunstone’s December 2025 joint-venture agreement with Emirates Global Aluminium (EGA) to build the project.
Upon completion, the plant is expected to replace most of EGA’s current anode imports and support the UAE’s ambition to become one of a limited number of global anode-exporting countries, aligning with the Make It In The Emirates initiative and Operation 300bn.
The ministry said the agreement reflects its role in helping strategic investors navigate the UAE’s investment ecosystem and convert commitments into long-term operations, in line with the National Investment Strategy 2031.
By localising a key stage in the aluminium value chain, the facility will reduce reliance on imported anodes, enhance the competitiveness of the UAE aluminium sector and support wider economic diversification.
The Ministry of Investment and Sunstone will establish a joint working group, chaired by the ministry, to oversee project delivery.
The project is expected to create skilled employment opportunities for UAE nationals and residents, while strengthening domestic manufacturing capacity and industrial capabilities.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19461120/main.jpg -
Riyadh tenders Expo 2030 Souq areas package8 September 2026

Expo 2030 Riyadh Company (ERC), responsible for delivering the Expo 2030 Riyadh venue, has tendered a contract to deliver the Souq areas within the Expo site.
The tender was floated on 30 July, with a submission deadline of 9 October.
The Souq areas are divided into five distinct precincts, with a total development area of about 300,000 square metres (sq m).
The scope includes the five precincts and their associated vertical elements, infrastructure and public realm works.
The precincts comprise:
- Precinct 1 – The Icon: 41,417 sq m
- Precinct 2 – Place & Planet: 62,306 sq m
- Precinct 3 – Culture of Wisdom: 67,112 sq m
- Precinct 4 – Kingdom of Saudi Arabia: 45,967 sq m
- Precinct 5 – Adaptation & Innovation: 82,358 sq m
The package will interface with three public parks. It will also tie into the Natural Corridor, including bridges.
The Souq areas will form a mixed-use destination at the centre of Expo 2030 Riyadh, providing a central connection between the site’s iconic and thematic assets.
The development will include rented and partnership pavilions, alongside a range of food and beverage, retail and visitor-experience offerings.
Site progress
Construction activity at the Expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.
Earlier this month, Saudi Arabia’s Royal Commission for Riyadh City (RCRC) awarded a design-and-build contract for the construction of a new metro station catering to the Expo 2030 site.
In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Alyamama Company.
The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.
These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.
That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.
The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.
The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19457171/main.jpg -
Powering the next chapter with nuclear energy8 September 2026
Commentary
Colin Foreman
EditorNuclear energy is increasingly being viewed as essential around the world. It offers a non-CO2-emitting, steady baseload at a time when governments have made net-zero commitments.
In the Gulf, the UAE has spent the past 15 years building the Middle East’s first commercial nuclear plant, now supplying about a quarter of the country’s electricity. What is new is the breadth of ambition beyond Abu Dhabi. The civil nuclear cooperation deal signed between Saudi Arabia and the US in July is the most significant step in the kingdom’s nuclear programme for several years, and it lands as the region moves decisively towards atomic power.
The logic is clear. Electricity demand from industry, desalination and digital infrastructure is climbing, and governments want reliable low-carbon supply to meet it. Saudi Arabia is targeting up to 17GW of nuclear capacity by 2040. Its first plant at Khor Duwaiheen, comprising two 1.4GW reactors, represents only about a sixth of that goal, which points to a programme rather than a one-off.
What is new is the breadth of ambition beyond Abu Dhabi
The opportunity extends well beyond reactors. The UAE’s nuclear programme shows the scale of the economic impact. More than 2,000 local firms secured contracts worth over $6.7bn supporting construction, operations and maintenance.
Saudi Arabia’s ambitions reach further still, into small modular reactors, domestic uranium and elements of the fuel cycle. At the same time, Bahrain is studying a modular plant to power its industrial base, and Egypt’s 4.8GW El-Dabaa project is already under construction, with first generation expected in 2028.
For contractors, engineers and financiers, this is the beginning of a projects market that will unfold over decades. The reactor awards will grab the headlines, but the supporting ecosystem, from regulation and fuel supply to workforce development, is where much of the value lies.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19461185/main.gif