Saudi power sector enters busiest year

10 March 2025

 

Contracts worth more than $90bn are under execution in Saudi Arabia’s power sector, making 2025 the busiest year ever for generation and transmission capacity buildout in the kingdom.

The construction of conventional and renewable power generation plants accounts for two-thirds, or 66%, of the contracts under execution, while transmission and distribution projects account for the rest, based on the latest available data from regional project tracker MEED Projects.

In addition to gas-fired and renewable energy generation plant projects, the kingdom has awarded several contracts in the past two years to modernise and expand its domestic grids in light of the solar photovoltaic (PV) and wind power plants, and industrial complexes, which are being built in remote areas – as well as Riyadh's plan to trade electricity beyond the kingdom's GCC partners and with countries such as Egypt.

In the past 12 months, the kingdom also awarded the first contracts to build on-grid battery energy storage system (bess) facilities, in line with fostering greater grid flexibility and countering the intermittency of renewable power.

“It has been a very, very busy year, despite some projects – particularly those catering to Neom – being re-scoped,” notes a Dubai-based senior executive with a transaction advisory firm.

The $500bn Neom gigaproject in southwestern Saudi Arabia aims to be powered 100% by renewable energy, which it initially expected to generate independently.

However, ongoing discussions are understood to include an option to meet future demand through renewable power sourced from the grid.

Overall, combined-cycle gas turbine (CCGT) projects – procured on either an independent power project (IPP) or engineering, procurement and construction (EPC) model – account for 56% of the total power generation contracts under execution in Saudi Arabia, with solar and wind accounting for the remaining 44%.

The principal buyer, Saudi Power Procurement Company (SPPC), awarded contracts for two pairs of CCGT plants – projects one and two of the Rumah and Nairiyah schemes – last year.

SPPC also signed the offtake agreements for four solar PV IPPs, which were tendered under the fifth round of the National Renewable Energy Programme (NREP). These were contracts for the 2GW Al-Sadawi, 1.25GW Al-Masaa, 500MW Al-Henakiyah 2 and 300MW Rabigh 2 solar IPPs.

An EPC contract for a high-voltage, direct current transmission network connecting the kingdom’s central and southern electricity grids was also one of the largest deals signed last year in the kingdom.

In the second half of 2024, the developer arm of Saudi Electricity Company (SEC) selected the preferred bidders for several greenfield CCGT expansion plants: Ghazlan 1 and 2, Riyadh PP12 and Marjan.

SEC subsidiary National Grid also awarded the second phase of its bess projects that are being procured on an EPC basis to local firm AlGihaz Holding last year. The three battery energy storage facilities, each with a capacity of 800MW, or about 2,600 megawatt-hours, are to be located in Najran, Khamis Mushait and Madaya.

The extent of work on hand is exerting pressure on contractor capacity, according to some experts.

"I think the Chinese EPC contractors are already at capacity, so SEC has started tapping Egyptian and Spanish EPC contractors," an industry source told MEED, referring to Tecnicas Reunidas, Orascom and Elsewedy, which are understood to have been selected last year to undertake the EPC contracts for several CCGT plants that SEC is developing.

South Korean EPC contractors are also executing several cogeneration and generation power plants in the kingdom.

Outlook

The need to expand, connect and stabilise the kingdom’s electricity grid will be a primary preoccupation for Saudi utility stakeholders in the short to medium term.

This is crucial given the large capacity of renewable energy power generation plants that are scheduled to come on stream, and as the kingdom deploys new gas-fired plants in line with its need to displace liquid fuel in some of its ageing fleet.

Oil fuel still accounted for 36% of Saudi Arabia's total electricity generation in 2023, at 422.9 terawatt-hours, according to the Energy Institute.

Data from MEED Projects suggests that at least $68bn-worth of power generation and transmission contracts are in the pre-execution phase as of March 2025.

Clean energy fuel-powered plants, using solar, wind, hydro and nuclear, dominate the $47bn-worth of planned power generation units, with thermal plants accounting for just 13% of the total.

This signals a shift to clean energy, despite the overall figure excluding a significant volume of renewable energy projects that are still in the concept stage. This is in line with a plan by the Energy Ministry to procure up to 20GW of renewable energy capacity annually until 2030, subject to demand growth.

Planned transmission and distribution projects, including several independent battery energy storage projects, together account for about $21bn of contracts that have yet to be awarded.

Local developers

Local companies are increasingly visible in the procurement proceedings for new power generation and transmission plants in the kingdom.

The decisions made by several European and Japanese developers to retreat from thermal power plant tenders that do not offer a clear carbon capture, utilisation and storage (CCUS) path – which would be necessary for them to meet their 2045 or 2050 net-zero targets – has contributed to this trend.

The exclusion of dominant utility developer Acwa Power in the prequalification process for the NREP’s fifth and sixth procurement rounds has also opened up opportunities for other international and local developers that are keen to win more contracts in Saudi Arabia.

Aljomaih Energy & Water, Ajlan & Brothers, Alfanar, Algihaz and SEC’s developer arm have been pursuing new contracts, usually in cooperation with an international developer.

Battery energy storage

Large-scale solar PV projects and limited wind capacity in the kingdom create a major market for battery energy storage going forwards.

Independent battery energy storage projects, in particular, offer neutral opportunities for both international and local developers, and are expected to attract more bidders compared to conventional thermal or standalone solar PV projects.

“We are definitely interested,” says a senior executive with a European utility developer, referring to the first phase of the kingdom’s independent storage provider (ISP) programme.

In addition to its net-zero merits, the ISPs will follow the same model as an IPP project, where the successful bidders will hold 100% equity in the special purpose vehicles set up to develop and operate the project.

While such strong interest is expected to benefit the principal buyer, which can expect to receive competitive prices from bidders, an over-competitive or crowded landscape could also be off-putting to developers and investors that are keen to maintain their internal rate of return, or which are shifting their global focus to other geographies.

“We prefer to wait and see,” one source tells MEED, indicating that their company does not intend to participate in upcoming battery tenders, not only in Saudi Arabia but also in other GCC states.

https://image.digitalinsightresearch.in/uploads/NewsArticle/13466191/main.gif
Jennifer Aguinaldo
Related Articles
  • Adnoc builds long-term oil and gas production potential

    7 April 2026

     

    Between 2023 and 2024, Abu Dhabi National Oil Company (Adnoc Group) spent an estimated $37bn on projects critical to achieving its upstream targets: increasing oil production capacity to 5 million barrels a day (b/d) by 2027 and attaining gas self-sufficiency by the end of the decade.

    The state energy company spent more than $22.5bn in 2023 alone, marking the highest annual oil and gas project spending on record in the UAE. The Hail and Ghasha sour gas development – accounting for approximately $17bn – remains the single-largest contract award in the country’s hydrocarbons sector.

    A slowdown in capital expenditure (capex) following two years of elevated spending is therefore in line with expectations. While engineering, procurement and construction (EPC) contract awards for upstream projects declined in 2025 and into this year, Adnoc has still committed close to $10bn over the past 15 months.

    The largest award during this period came from Adnoc Offshore, which let contracts worth $7.5bn for three EPC packages under the Lower Zakum Long-Term Development Plan (LTDP-1). Spain’s Tecnicas Reunidas and Abu Dhabi-based NMDC Energy and Target Engineering Construction Company were selected last February to execute the works.

    The Lower Zakum field, located 65 kilometres northwest of Abu Dhabi, is majority-owned by Adnoc Offshore (60%). Other stakeholders include an Indian consortium led by ONGC Videsh (10%), Japan’s Inpex (10%), China National Petroleum Corporation (10%), Italy’s Eni (5%) and France’s TotalEnergies (5%).

    Adnoc Offshore aims to increase production capacity at Lower Zakum to 520,000 b/d by 2027 and sustain that level through 2034.

    Offshore contracts in 2026

    So far this year, Adnoc Offshore has awarded contracts for two key projects: the Satah Al-Razboot (Sarb) deep gas development and the expansion of the Nasr oil field.

    Adnoc achieved final investment decision (FID) on the Sarb project in January and awarded the main EPC contract to US-based McDermott International. The contract is estimated to be worth around $500m, sources told MEED.

    The project is expected to deliver 200 million cubic feet a day (cf/d) of gas by the end of the decade – enough to power more than 300,000 homes.

    The scope includes the EPC of an offshore wellhead tower with four gas production wells, which will be connected to Das Island for processing through Adnoc Gas facilities. Works also include the installation of pipelines and intra-field connections linking the Sarb field to Das Island.

    Also in January, Adnoc Offshore awarded McDermott a $942m contract for the Nasr-115 project, which will increase production capacity at the Nasr offshore field to 115,000 b/d. The field is located about 130km northwest of Abu Dhabi.

    McDermott’s scope covers full EPCI services for two topside structures, a new manifold tower, a jacket, a bridge, associated pipelines, subsea cables and brownfield modifications.

    Strategic projects in queue

    Over the next 12-18 months, Adnoc’s upstream spending is expected to shift from meeting near-term production targets –now largely within reach – to building longer-term capacity beyond 2030.

    Following $1.3bn in EPC awards in 2024 for the Upper Zakum expansion to 1.2 million b/d, Adnoc Offshore is advancing the next phase, which will increase capacity to 1.5 million b/d.

    Located 84km offshore, Upper Zakum is the world’s second-largest offshore oil field. Adnoc Offshore has divided the EPC scope into three packages, with contractors submitting commercial bids for the UZ1.5MMBD project in February.

    Adnoc Offshore is also progressing the Umm Shaif gas cap and surface pressure boosting project, aimed at increasing gas production by 550 million cubic feet a day (cf/d) and condensate output by 50,000 b/d. About 520 million cf/d of additional gas is expected to be fed into Adnoc’s sales gas network.

    The first phase of the project has been split into three EPC packages:

    • Offshore package 1: fabrication of a 30,000-tonne gas compression system
    • Offshore package 2: fabrication of a 30,000-tonne gas compression system
    • Onshore package: EPC of gas inlet and processing systems at Das Island

    Adnoc Offshore is currently evaluating commercial bids submitted in February for these packages.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16285814/main.gif
    Indrajit Sen
  • Contractor wins Oman housing substation contract

    7 April 2026

    Oman’s Public Authority for Social Insurance has awarded a contract for the supply, installation, execution and maintenance of a main power substation for its affordable housing project.

    The contract was awarded to Kuwait-based Al-Ahleia Switchgear Company.

    The project comprises a 400/132/11kV main substation for the Affordable Housing Project, known locally as Al-Masaken Al-Muyassara.

    The tender was announced last November, with the bid envelopes opened on 16 December 2025.

    Al-Ahleia Switchgear submitted another bid in March for a contract to build three 132/11kV main transformer stations for Kuwait’s Public Authority for Housing Welfare (PAHW).

    As reported by MEED, the company’s price of KD10.5m ($34.1m) was the lowest of two offers for the engineering, procurement and construction (EPC) contract.

    Separately, in December, Al-Ahleia Switchgear submitted the lowest bid of KD33.9m ($110.3m) for a contract to build a 400/132/11 kV substation at the South Surra township for Kuwait’s PAHW.

    The bid was marginally lower than the two other offers submitted by Saudi Arabia’s National Contracting Company (NCC) and India’s Larsen & Toubro.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16285335/main5555.jpg
    Mark Dowdall
  • UAE reviews $1.63bn fourth federal road project

    7 April 2026

    UAE authorities on 6 April unveiled details of the AED6bn ($1.63bn) fourth federal corridor scheme, a major highway programme aimed at boosting inter-emirate connectivity, increasing road capacity and easing congestion.

    The project comprises a 68-kilometre corridor with 10 major interchanges, four flyovers and six to eight lanes in each direction.

    Officials provided technical updates on the corridor, including revised connection points and coordination with local authorities to finalise route alignments in line with broader development plans.

    Suhail Mohamed Al-Mazrouei, minister of energy and infrastructure, said the programme underscores the central role of infrastructure in the UAE’s development agenda and competitiveness. He was speaking while chairing the first meeting of the UAE Infrastructure and Housing Council this year.

    The council also reviewed progress on federal infrastructure initiatives aimed at improving transport efficiency and strengthening coordination between federal and local authorities.

    Al-Mazrouei said the next phase will focus on accelerating the delivery of high-impact projects to enhance transport system performance and support the shift towards smart and sustainable mobility in line with population growth and urban expansion.

    The council also assessed progress on linking Ajman to the third and fourth federal corridors, which is expected to provide alternative routes, improve traffic flow and further enhance mobility between the emirates.

    On public transport, the council reviewed a study on transport links between Dubai, Sharjah and Ajman to address rising commuting demand.

    The proposed plan includes 10 priority routes incorporating bus rapid transit and dedicated lanes, with connections to key hubs such as the Dubai Metro and city centres.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16285296/main.jpg
    Yasir Iqbal
  • Kingdom Holding Company signs Riyadh project deal

    7 April 2026

    Saudi Arabia’s Kingdom Holding Company has signed an agreement with Sumou Real Estate Company under which Sumou will manage the development, marketing and sale of a 3-million-square-metre land plot in Riyadh.

    The scheme is expected to generate about SR4bn ($1bn) in total sales.

    In a Tadawul disclosure, Kingdom Holding Company said its subsidiaries, Kingdom Real Estate Development Company and Trade Centre Company, have appointed Sumou as the exclusive development manager for the site.

    The project is scheduled to be implemented over 36 months, starting once the masterplans are approved by the relevant authorities.

    In a separate stock exchange statement, Sumou said it will be paid 6.5% of total infrastructure development costs and 2.5% of project sales, in addition to the brokerage commission paid by buyers.

    Kingdom Holding Company said the agreement aligns with its long-term strategy for its Riyadh landbank, which originally totalled around 20 million sq m and is being developed in phases.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16284668/main.jpg
    Yasir Iqbal
  • Saudi Arabia’s Jubail industrial city hit by missile debris

    7 April 2026

    Explosions were reported in Saudi Arabia’s Jubail industrial city on 7 April. Saudi authorities said the country’s air defence systems intercepted seven ballistic missiles targeting the Eastern Province, with debris landing near energy facilities, primarily in Jubail.

    Jubail is one of the world’s largest petrochemical production hubs, with an annual output of about 60 million tonnes, accounting for an estimated 6% to 8% of global supply.

    The incident places renewed focus on the kingdom’s flagship petrochemical cluster, where majority state-owned Saudi Basic Industries Corporation (Sabic) is a key investor.

    Jubail also hosts major downstream oil, gas and petrochemical assets operated by Saudi Aramco, US-based Dow and France’s TotalEnergies, underscoring the industrial zone’s international significance.

    Saudi officials said damage assessments are ongoing.

    The developments follow an Israeli strike on 6 April targeting a major petrochemical complex in Iran’s southern Asaluyeh region, described as the country’s largest industrial hub.

    Separately, authorities closed the King Fahd Causeway – the main bridge linking Saudi Arabia and Bahrain – early on 7 April as a precaution amid heightened security concerns.

    The King Fahd Causeway Authority said in a post on X that vehicle movement had been “suspended as a precautionary measure” due to Iranian attacks targeting Saudi Arabia’s Eastern Province.

    The 25-kilometre bridge is Bahrain’s only road link to the Arabian Peninsula.

    US President Donald Trump has issued an ultimatum for Iran to reopen the Strait of Hormuz and threatened to bomb Iranian power plants and bridges if Tehran does not comply by 8pm EDT on 7 April.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16283711/main2424.jpg
    Indrajit Sen