Saudi Binladin Group makes a comeback

8 November 2024

 

Register for MEED's 14-day trial access 

The Saudi Binladin Group (SBG) has undergone a dramatic revival over the past year with the award of high-profile construction contracts and financial support from the Saudi government.

Founded in 1931 by Muhammad Bin Ladin, SBG grew to become Saudi Arabia’s largest construction company with a reputation for delivering large programmes of work for the government and leading figures within Saudi Arabia.

SBG’s fortunes declined following the oil price crash of 2014-15 and the collapse of an SBG crane at the Grand Mosque of Mecca, which resulted in a temporary ban on the contractor taking on new projects.

As its finances deteriorated, SBG hired US-headquartered Houlihan Lokey as the adviser for its SR56.4bn ($15bn) debt restructuring programme in April 2020.

These challenges combined meant the contractor was unable to regain its position as the go-to contractor for the Saudi Arabian government.

Financial support

Financially, the big turning point came in late October when Saudi Arabia’s National Debt Management Centre (NDMC) announced that it had completed arranging a syndicated loan facility for the Ministry of Finance to support SBG.

In an official statement, NDMC said that the loan facility amounting to SR23.3bn ($6bn) has been secured with several local and international banks.

The support includes a series of arrangements to settle the firm’s outstanding amount with banks, provide loans to the firm and potentially increase the government’s stake in the company.

The move to announce financial support follows the Ministry of Finance’s announcement in July, which outlined an intention to improve SBG’s financial capacity. The injection of cash into the firm will also enable it to improve its financing for various other projects in the kingdom.

The government has a vested interest in SBG’s fortunes. In 2019, a parent company known as Binladin International Holding Group (BIHG) was formed. That entity is owned by Istidama, an investment arm of the Ministry of Finance. The remaining 63.78% is owned by the Binladin Company for Development & Commercial Investment. Its subsidiaries include SBG.

In addition to SBG’s finances being shored up, over the past year the contractor’s orderbook has grown with several high-profile awards.

Jeddah Tower

While the financial turning point came at the end of October, the key moment symbolically came on 2 October, when SBG was appointed to complete the world’s tallest tower, the 1,000-metre-plus Jeddah Tower.

SBG was the original contractor on the project before construction work stalled in 2018. This left the tower’s superstructure about one-third complete, with 63 floors built out of 157.

The SR7.2bn ($2bn) contract award to complete the record-breaking structure took many in the market by surprise after it was reported that a joint venture of China State Construction Engineering Corporation and the local El-Seif Engineering Contracting was the frontrunner for the contract.

The Ministry of Finance’s support was crucial for the project client, giving the contract financial credibility. This allowed it to put together a winning proposal to complete the tower with a reduced programme and a more competitive price.

There were also practical reasons for selecting the original contractor on the project, according to Kingdom Holding’s CEO Talal Ibrahim Almaiman. SBG already has offices established on-site and, as a Jeddah-based company with a long history of delivering major projects in Saudi Arabia, it has well-established connections with the local supply chain.

The Jeddah Tower award followed important contract awards a year earlier. In October 2023, SBG won contracts totalling about $1.3bn from Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund (PIF).

The contracts were awarded to build Seven’s two entertainment destinations in the Dammam and Alkhobar regions in the kingdom’s eastern province.

The entertainment complex in Alkhobar will be built on reclaimed land on the waterfront. It will span around 300,000 square metres (sq m) and is also known as “The Waves”.

The Dammam entertainment complex spans 360,000 sq m and will also be built on reclaimed land on the Dammam waterfront.

SBG also has historical work. It is delivering the third Mecca Grand Mosque expansion programme after resuming construction activities at the project site following this year’s Hajj pilgrimage.

The first section is understood to include expansion works for the main building, with the second and third sections of the programme covering ancillary, security, media, hotel and hospital buildings, among others.

The programme to expand the Mecca Grand Mosque was reportedly launched in 2011 by the late King Abdullah Bin Abdulaziz. It faced delays following the crane collapse at the mosque in September 2015, with work resuming in late 2019.

King Salman Bin Abdulaziz Al-Saud launched five projects in July 2015 as part of the third expansion programme. These projects covered an estimated built-up area of 1.47 million sq m.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12878436/main.jpg
Colin Foreman
Related Articles
  • Municipality seeks consultants for Dubailand drainage project

    10 December 2025

    Register for MEED’s 14-day trial access 

    Dubai Municipality has invited consultants to prequalify for a contract to provide supervision services on a major drainage infrastructure project serving developed communities in Dubailand.

    The sewerage and stormwater drainage project, listed under the code DS-204-S1, is being procured through the government’s Sewerage and Recycled Water Projects Department (SRPD).

    The bid submission deadline is 8 January.

    The consultancy contract follows the issuance in November of the related construction package, DS-204-C1, for which the municipality invited contractors to prequalify.

    The scope includes sewage gravity pipelines with diameters of up to 2,200mm, a sewage lift station with a capacity of three cubic metres a second, and a 1,400mm-diameter sewage rising main that will take pumped sewage from the lift station to the main sewer network.

    The bid submission deadline for the construction package is also 8 January 2026.

    The tenders form part of Dubai’s wider investment in sewerage expansion, including the $8bn Tasreef programme, for which several projects have moved into the execution phase in recent months.

    Once completed, the Tasreef system is expected to increase Dubai’s overall drainage capacity by about 700% and provide daily stormwater treatment capacity exceeding 20 million cubic metres.


    READ THE DECEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF

    Prospects widen as Middle East rail projects are delivered; India’s L&T storms up MEED’s EPC contractor ranking; Manama balances growth with fiscal challenges

    Distributed to senior decision-makers in the region and around the world, the December 2025 edition of MEED Business Review includes:

    > BAHRAIN MARKET FOCUS: Manama pursues reform amid strain
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/15218750/main.jpg
    Mark Dowdall
  • Riyadh prepares Qiddiya National Athletics Stadium tender

    9 December 2025

     

    Register for MEED’s 14-day trial access 

    Saudi gigaproject developer Qiddiya Investment Company (QIC) is expected to float a tender soon for the construction of the estimated SR7bn ($1.8bn) National Athletics Stadium at its Qiddiya entertainment city development.

    MEED understands that the prequalification process has reached an advanced stage and the tender for the main contract is likely to be issued within a few weeks.

    The multipurpose stadium will cover an area of approximately 182,000 square metres and its design is inspired by the London Olympic Stadium.

    In September, MEED exclusively reported that QIC had begun the procurement process for the kingdom’s next major sporting destination, having received expressions of interest from contractors for the project.

    UK-based HOK is the project’s lead design consultant. It is supported by Canadian engineering firm WSP and Germany’s Schlaich Bergermann Partner.

    UK-headquartered WT Partnership is serving as the project’s cost consultant.

    The stadium will be located within the Qiddiya Sports Park cluster and is expected to be completed by 2030.

    In December 2020, Saudi Arabia was selected to host the 2034 Asian Games. The 22nd edition of the event will be held in Riyadh from 29 November to 14 December 2034.

    Saudi Arabia is also set to host the Asian Winter Games in 2029. In October 2022, the Trojena development at Neom, in the northwest of the country, was selected to host the ninth edition of the event.

    The National Athletics Stadium is one of several major projects within the wider Qiddiya development. Others include an e-games arena, Prince Mohammed Bin Salman Stadium, a performing arts centre, a motorsports track, Dragon Ball and Six Flags theme parks and Aquarabia waterpark.

    The project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom. According to UK analytics firm GlobalData, leisure tourism in Saudi Arabia has experienced significant growth in recent years.

    Domestic leisure tourism trips increased to 33.76 million in 2023, up from 16.74 million in 2018. International tourist arrivals for recreational purposes increased by 600% from 2018 to 2023.

    Image: Buro Happold

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15217660/main.jpg
    Yasir Iqbal
  • Contractors submit prices to Adnoc Gas for Ruwais NGL project

    9 December 2025

     

    Register for MEED’s 14-day trial access 

    Contractors have submitted commercial proposals to Adnoc Gas for engineering, procurement and construction (EPC) work as part of a design‑update competition for a project to install a fifth natural gas liquids (NGL) fractionation train at its Ruwais gas processing facility in Abu Dhabi.

    The fifth NGL fractionation train will have an output capacity of 22,000 tonnes a day (t/d), or about 8 million tonnes a year.

    Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), has adopted the design-update competition model to deliver the Ruwais NGL Train 5 project, MEED previously reported.

    The design-update competition model involves the project operator selecting contractors to execute front-end engineering design (feed) work on the project. The operator selects the contractor with the most competitive feed proposal to execute EPC works on the project, while also compensating the other contestants for their work.

    According to sources, contractors participating in the design-update competition for the Ruwais NGL Train 5 project submitted commercial bids for EPC works by the deadline of 8 December.

    The previous deadline for price submissions was 30 November, sources said.

    Adnoc Gas previously asked contractors to submit their feed technical proposals for the project in September.

    In January, MEED reported that Adnoc Gas had selected the following contractors to participate in the design-update competition for the Ruwais NGL Train 5 project:

    • JGC Corporation (Japan)
    • Technip Energies (France)
    • Tecnimont (Italy)

    MEED previously reported that participants had submitted technical proposals for feed work on 6 October.

    The scope of work on the Ruwais NGL Train 5 project covers the EPC of the following units:

    • NGL fractionation plant with a capacity of 22,000 t/d, including NGL fractionation facilities, downstream treatment units, sulphur recovery units, products storage, loading facilities and associated utilities, flares and interconnection pipelines with existing facilities
    • Two propane liquefied petroleum gas storage tanks and one paraffinic naphtha storage tank
    • Buildings – a central control building, outstations, substations and plant amenities
    • Electrical power connections. Power is to be sourced from the nearby Transco substation via a direct underground cable to the plot location.

    Adnoc Gas requires the feed on the project to be updated based on the design of Ruwais NGL Train 4, which has an output capacity of 27,000 t/d and was commissioned in 2014.

    In December 2021, MEED reported that Adnoc Gas, then operating as Adnoc Gas Processing, had awarded Indian contractor Larsen & Toubro Hydrocarbon Engineering the main contract for a project to enhance the capacity of its NGL trains 1-4 at the Ruwais complex.

    ALSO READ: Adnoc Gas capex budget to rise to $28bn by 2029

    Adnoc Gas business

    Adnoc Group announced the creation of Adnoc Gas through the merger of its subsidiaries Adnoc Gas Processing and Adnoc LNG in November 2022. Adnoc Gas began operating as a commercial entity on 1 January 2023.

    The consolidation of Adnoc’s gas processing and liquefied natural gas (LNG) operations into Adnoc Gas has created one of the world’s largest gas-processing entities, with a processing capacity of about 10 billion standard cubic feet of gas a day across eight onshore and offshore sites, which include its Asab, Bab, Bu Hasa, Habshan and Ruwais plants.

    The company also owns a 3,250-kilometre (km) gas pipeline network to supply feedstock to its customers in the UAE. This sales gas pipeline network is being expanded to over 3,500km through the estimated $3bn Estidama project.

    The company will also acquire its parent Adnoc Group’s 60% share in the Ruwais LNG terminal project at cost in the second half of 2028. UK energy producer BP, Japan’s Mitsui & Co, UK-based Shell and French energy producer TotalEnergies are the other shareholders in the project, holding 10% stakes each.

    Adnoc Gas share sale

    In February 2025, Adnoc Group completed a marketed offering of approximately 3.1 billion shares in Adnoc Gas, raising $2.8bn from the exercise.

    The offering consisted of 3,070,056,880 shares, representing 4% of the issued and outstanding share capital of Adnoc Gas.

    Following the marketed offering of shares, Adnoc Group continues to hold the majority 86% of shares in Adnoc Gas.

    The parent entity listed 5% of Adnoc Gas’ shares on the Abu Dhabi Securities Exchange in March 2023, in an initial public offering from which it raised about $2.5bn.

    Abu Dhabi National Energy Company (Taqa) owns the remaining 5% shares in Adnoc Gas.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15217598/main2533.jpg
    Indrajit Sen
  • Saudi Arabia and Qatar sign high-speed rail link agreement

    9 December 2025

    Register for MEED’s 14-day trial access 

    Saudi Arabia and Qatar have signed an agreement to build a proposed high-speed rail line connecting Riyadh and Doha.

    The agreement was signed by Saudi Arabia's Transport & Logistics Services Minister, Saleh Al-Jasser, and Qatar's Transport Minister, Sheikh Mohammed Bin Abdulla Bin Mohammed Al-Thani.

    The high-speed railway line will cover 785 kilometres (km) and will pass through Hofuf and Dammam, while also linking King Salman International airport and Hamad International airport.

    The train's speed will exceed 300 kilometres an hour, reducing travel time between the two capitals to about two hours.

    The project is slated for completion in six years. The project is expected to serve over 10 million passengers annually and create more than 30,000 direct and indirect jobs.

    Riyadh and Doha relaunched a proposed rail link connecting the two countries in 2022, after agreeing to set a date to begin studying the connection. 

    In July of that year, France’s Systra was selected to conduct a feasibility study on the proposed scheme, as MEED reported.

    A rail link connecting Saudi Arabia and Qatar was planned before the diplomatic dispute that froze relations between Riyadh and Doha from 2017 until the Al-Ula Declaration was signed in January 2021.

    In 2016, Qatar Railways Company (Qatar Rail) was planning to tender the design-and-build contract for the construction of regional railways in Qatar, including the link connecting to the Saudi border.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15217463/main.gif
    Yasir Iqbal
  • Oman green hydrogen projects cancelled

    8 December 2025

    Hydrogen Oman (Hydrom), France’s Engie and South Korea’s Pohang Iron & Steel Company (Posco) have cancelled plans to move forward with the $6.7bn HyDuqm green hydrogen project.

    In a joint statement, the firms said they had reached a decision to end the scheme by mutual consent following an “in-depth assessment” of global renewable hydrogen offtake dynamics and investment frameworks.

    The HyDuqm scheme was one of the largest green hydrogen projects awarded under Oman’s first auction round in 2023.

    The proposed development included around 5GW of combined solar and wind capacity, supported by battery energy storage, to power an electrolysis plant producing hydrogen for conversion into green ammonia.

    The facility was expected to deliver up to 1.2 million tonnes of green ammonia a year by 2030, with Posco as the main offtaker to support the decarbonisation of its steel operations.

    The consortium, led by Posco (28%) and Engie (25%), had secured a 47-year concession with the state-owned Hydrom to develop a 320-square-kilometre site near the Port of Duqm.

    Samsung Engineering, Korea Southern Power and Korea East-West Power had a 12% stake, with Thailand’s PTTEP holding the remaining 11%.

    As recently as May, the partners were still targeting a final investment decision in 2027, subject to detailed economic and technical feasibility assessments.

    Separately, a second Hydrogen project in the same area, owned by the UK’s BP, has also been cancelled. BP withdrew its plans for the Duqm green hydrogen project, which had secured land rights for the 1.5GW facility.

    Hydrom managing director, Abdulaziz Al-Shidhani, told the 2025 Green Hydrogen Summit in Oman last week that only seven of the nine original projects that won land tenders were progressing.

    Wider slowdown

    The cancellations come amid a broader slowdown in green hydrogen development globally. Several major schemes have been postponed, scaled back or withdrawn as project economics have tightened.

    In Europe, more than one-fifth of planned hydrogen projects had been stalled or cancelled by the end of 2024, according to research and consultancy firm Westwood Global Energy, largely due to high costs, uncertain demand and slow progress securing long-term offtake.

    A similar trend has emerged in the GCC, where Saudi Arabia’s flagship Neom green hydrogen project has also faced offtake and market pressures despite reaching an $8.4bn financial close in 2023.

    The 4GW scheme, designed to produce about 1.2 million tonnes a year of green ammonia, has reportedly struggled to secure multiple international buyers, with only limited offtake confirmed to date.

    Hydrogen production costs

    Global green hydrogen production costs also remain significantly higher than conventional alternatives, typically in the range of $3-$8 a kilogram compared with roughly $0.5-$2/kg for hydrogen produced from fossil fuels, leaving large export-oriented projects exposed to pricing and demand uncertainty.

    The combination of elevated capital costs, slow offtake development and evolving policy frameworks has created headwinds for investment decisions across the sector.

    In the joint statement, however, Hydrom said it is committed to “developing a competitive hydrogen-centric economy” aligned with Oman’s Vision 2040.

    It added that projects awarded in the first two auction rounds are progressing on schedule towards the country’s target of producing more than one million tonnes a year of green hydrogen by 2030.

    The company also highlighted continued international interest in the sector, noting that the third auction round is under way with strong foreign participation.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15214080/main.jpg
    Mark Dowdall