Saudi Arabia’s power sector motors on

11 September 2024

 

Saudi Arabia’s power sector has sustained its project activity momentum over the past six months.

The principal buyer, Saudi Power Procurement Company (SPPC), awarded the contracts to develop two publicly-tendered wind independent power producer (IPP) projects, with a total combined capacity of 1,100MW, under the fourth round of the kingdom’s National Renewable Energy Programme (NREP).

The Public Investment Fund (PIF), responsible for procuring through direct negotiations 70% of the kingdom’s 2030 target renewable energy capacity, let three large-scale solar photovoltaic (PV) projects with a total combined capacity of around 5,500MW.

State majority-owned Saudi Aramco also awarded a contract to develop an independent cogeneration project with an electricity generation capacity of 475MW.

During the same period, SPPC began the tendering process for two combined-cycle gas turbine (CCGT) projects, the Remah and Nairiyah IPPs, each with a capacity of 3,600MW, and for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round.

“It has been a very busy summer,” notes a senior executive with an international utility developer, referring to the submission of bids in August for the contracts to develop the Remah 1 & 2, Nairiyah 1 & 2, and the NREP round-five solar PV schemes.

Notably, the principal buyer has initiated the selection process for consultants who will advise on its next pair of independent CCGT power plants – the 2,400MW Al-Rais and the 3,600MW Riyadh 16 projects.

Saudi Electricity Company (SEC) and SPPC are also understood to be conducting bilateral talks for the development of five CCGT power plants, which, along with those currently being built or tendered, support the kingdom’s mandate to replace fleets running on liquid fuel.

Essentially, the reported SEC projects, each with a capacity of 1,500MW-2,000MW, bear some similarities to PIF’s directly negotiated renewable energy schemes.

These projects help substantiate previous reports that SEC has been seeking to lock in gas turbine equipment deals with a total capacity of 30GW, in line with an overall capacity expansion plan within and outside Saudi Arabia.

The next few years can only get busier, with Saudi Arabia's Energy Minister, Prince Abdulaziz Bin Salman Bin Abdulaziz Al-Saud, confirming in June plans to tender 20,000MW of renewable energy projects annually starting this year, in line with reaching 100GW-130GW of installed capacity by 2030, "depending on electricity demand growth".

This represents a major upward revision to the official 2030 renewable energy capacity target of 58,700MW.

However, it is unclear if this new target considers the renewable capacity that will be installed to power Neom, Saudi Arabia’s largest gigaproject, as well as the requirement of green hydrogen projects that the PIF plans to codevelop.

Wind IPPs

In May, SPPC awarded a team led by Japanese utility developer Marubeni Corporation the contracts to develop the 600MW Al-Ghat wind and 700MW Waad Al-Shamal wind IPPs.

The team of Marubeni and its partner, the local Alajlan Brothers, is also expected to win the contract to develop the 700MW Yanbu wind IPP, the final wind scheme included in NREP’s round four.

These are important awards for Marubeni, which last won an IPP contract in Saudi Arabia in 2021 for the 300MW Rabigh solar scheme.

Notably, the Al-Ghat and Waad Al-Shamal wind IPPs will be developed at world-record-low levelised electricity costs of $c1.565 a kilowatt-hour (kWh), or roughly 5.87094 halalas/kWh, and $c1.70187/kWh or 6.38201 halalas/kWh.

PIF projects

In June, three Saudi utility developers and investors signed power-purchase agreements (PPAs) with SPPC to develop and operate three solar PV projects with a combined capacity of 5,500MW.

The Haden and Muwayh solar PVs, located in Mecca, will each have a capacity of 2,000MW, while the Al-Khushaybi solar PV power plant in Qassim will be able to generate 1,500MW of electricity.

The team that will develop the three projects consists of Acwa Power, PIF-backed Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco), a subsidiary of the state majority-owned oil giant.

The project companies formed for each solar IPP have since signed financing documents for the projects, which will require a total investment of SR12.3bn ($3.3bn). The financing sought was $2.6bn.

These projects comprise round four of PIF’s Price Discovery Scheme, with Acwa Power as the preferred developer partner.

Energy storage systems

The scale of new conventional and renewable energy capacity being developed in the kingdom – some 3,500MW of solar PV and wind capacity is now online, with over 10,500MW under construction – has increased the urgency to build energy storage systems to balance the kingdom’s energy system and stabilise its grid.

SPPC has signalled plans to procure gigawatt-sized battery energy storage systems (bess) using an IPP model. The tendering process for the first bess IPP package is expected to begin by the year-end or early 2025.

In parallel, National Grid Saudi Arabia, an SEC subsidiary, has started awarding contracts to build energy storage systems capacity using an engineering, procurement and construction (EPC) model. The local Algihaz Holding is understood to have won the contracts to build four energy storage systems in Najran, Madaya and Khamis Mushait, which will have a total combined capacity of 7.8 gigawatt-hours (GWh).

Also in August, SEC tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW, or roughly 10GWh.

The planned facilities, each with a capacity of 500MW or roughly 2GWh, are located in or within the proximity of the following key cities and load centres:

  • Riyadh
  • Qaisumah
  • Dawadmi
  • Al-Jouf
  • Rabigh

Saudi Arabia’s plan to build its first large-scale nuclear power plant in Duwaiheen, which appeared to be making progress before October last year, has faced delays following shifting geopolitics involving stakeholders that include the US and Israel. The tender bid deadline for nuclear technology providers is understood to have been postponed and no new date has been set.

As it is, Saudi Arabia’s ever-expanding power projects pipeline, particularly for renewables and bess, will require investors, contractors and lenders to allocate sizeable resources, perhaps more than they have historically done in the past, over the next several years as various stakeholders endeavour to meet Vision 2030-tied peak demand scenarios.

This applies less to CCGT projects, which, pending a clear carbon-capture strategy from the offtaker or the Energy Ministry, appear to attract a decreasing number of developers and investors.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12496716/main.jpg
Jennifer Aguinaldo
Related Articles
  • Riyadh looks to boost FDI

    3 October 2024

    Commentary
    Colin Foreman
    Editor

    Read the October 2024 issue of MEED Business Review

    This year and next will be pivotal years for the Saudi economy. After years of heavy investment in projects by the state and its related entities – most notably the Public Investment Fund (PIF) – the economy is now shifting towards one that is more reliant on foreign investment. 

    This is partly due to the kingdom running a budget deficit due to oil production cuts and oil prices, but also because creating business opportunities and attracting foreign direct investment (FDI) was a key part of Vision 2030. 

    There are early signs of success, although the largest deals in terms of dollar value have been concentrated on sectors that Saudi Arabia is already well known for, such as oil and gas and, to a lesser extent, industry. 

    Other sectors have so far needed more convincing. The new ambitious development projects, including the gigaprojects, follow a business model that involves state actors developing the first phases of a project. The private sector then takes over once the concept or business model has been proven. 

    This is a tried-and-tested strategy. The best example in the region in recent decades was in the UAE, with Emaar building the first towers at Dubai Marina before the private sector developed many of the remaining towers.

    Many of Saudi Arabia’s projects are nearing that point today as initial phases start to be completed. Over the next few years, the hope is that the development companies leading Saudi Arabia’s projects will be ready to take a slight step sideways and allow the private sector to step in and shoulder more of the investment. 

    For that to happen, Saudi Arabia must successfully deliver the initial phases of its projects. If projects fail to meet their stated ambitions, they may risk scaring off FDI rather than attracting it.


    Must-read sections in the October 2024 issue of MEED Business Review include:

    AGENDA: 
    Riyadh redoubles efforts to boost inward investment
    Foreign investment trends align with Vision 2030

    > CURRENT AFFAIRS:
    Iran benefits from energy disruption in Iraqi Kurdistan
    Jordan election results in Islamist gains

    INDUSTRY REPORT:
    MEED's 2024 GCC Power Developer Ranking
    > Local firms rise in GCC Power Developer Ranking
    Brisk pace of IPP awards set to continue

    > IRAQ-CHINA: Chinese companies win 95% of all Iraqi energy projects

    > PROJECT SERVICES: Bringing scale to project delivery

    > HIGH-SPEED RAIL: UAE’s high-speed rail moves ahead

    INTERVIEW: Ducab undaunted by global market headwinds

    > SAUDI ARABIA MARKET REPORT: 

    > COMMENT: Riyadh modifies its narrative
    > GOVERNMENT: Riyadh is forced to reassess its spending priorities
    > BANKING: Saudi banks continue to lend, lend, lend
    > UPSTREAM: Aramco spending lifts Saudi upstream market
    > DOWNSTREAM: Saudi downstream programmes gain traction
    > UTILITIES: Saudi Arabia’s power sector motors on
    > CONSTRUCTION: Companies confirm Saudi gigaproject slowdown
    > TRANSPORT: Infrastructure schemes support Riyadh’s ambitions

    MEED COMMENTS: 
    > More scrutiny for highly paid expatriates in Saudi Arabia
    > Economic change is inevitable for major projects

    UAE bucks the trend of rising construction risk
    Riyadh AI goals require colossal mindset and capital shift

    > GULF PROJECTS INDEX: Gulf projects index halts its decline

    > AUGUST 2024 CONTRACTS: Value of deals signed drops in August

    > ECONOMIC DATA: Data drives regional projects

    > OPINIONDesperate days drag on

    BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/12649026/main.gif
    Colin Foreman
  • Transmission and distribution sector heads for record year

    3 October 2024

    The GCC region’s power transmission and distribution (T&D) sector is set to experience its best year in terms of the value of awarded contracts.

    Based on data from regional projects-tracking service MEED Projects, the total value of awarded contracts for substations, control centres, overhead lines and cables across the six GCC states reached an estimated $13.8bn between January and September 2024.

    This figure already exceeds by 81% the total value of contracts awarded in the preceding full year.

    It also exceeds by 31% the total value of awarded contracts in 2021, which registered a record-high of $10.5bn in the 10 years starting in 2014.

    Project activity within the T&D sector is expected to remain buoyant over the next few years, with roughly $35.9bn-worth of planned and unawarded contracts.

    Of these, some $8.5bn are in the bid evaluation stage as of early October, with a further $6.5bn under tendering.

    Some $12bn of projects are in the front-end engineering and design (feed) phase.

    Energy diversification 

    Ambitious national energy diversification and net-zero targets across the region, which traditionally relied almost entirely on thermal power plants, will spur significant investments in T&D infrastructure in the future.

    According to experts, the ongoing expansion of electricity generation capacity across the region, particularly from renewable energy sources, requires a more robust, integrated and stable electricity grid.

    This is in addition to the projected increase in electricity demand as most states expand their downstream and petrochemical sectors, develop new communities and megaprojects in remote regions, and build more data centres to support smart cities, and internet-of-things (IoT) and artificial intelligence (AI) applications.

    The region’s largest economy, Saudi Arabia, for instance, aims for renewable energy to account for 50% of its electricity generation capacity by 2030.

    Operational renewable installed capacity in the kingdom jumped from roughly 300MW in 2020 to 3,500MW this year, with a further 16,000MW currently under construction or about to start construction, and gigawatts more under tender.

    Crucially, the kingdom’s energy minister confirmed earlier this year that the kingdom has plans to procure up to 20,000MW of renewable capacity every year, subject to demand.

    Saudi Arabia is also ramping up its procurement programme for new gas-fired power plants, in line with a plan to decommission fleets running on liquid fuel and at the same time secure baseload as more renewable energy enters the grid.

    There is also a marked increase in terms of T&D packages or contracts interconnecting the kingdom’s various regions from central Riyadh to the eastern, northern and southern provinces.

    It comes as no surprise that the kingdom accounted for 72% of the $13.8bn-worth of T&D contracts awarded in the GCC region in the first three quarters of 2024.

    Oman, which awarded T&D contracts with the same value as the UAE between January and September this year, has also been working to integrate its smaller electricity grids with the sultanate’s main electricity grid to boost electricity supply in its smaller, remote regions.

    Unlike the noticeable peaks and throughs in T&D capital expense in other GCC states, the UAE’s spending has remained pretty consistent since 2014, averaging roughly $1.4bn annually. The exemption was in 2021 when a team comprising South Korea’s Kepco, Japan’s Kyushu Electric Power Company (Kyuden) International and France’s EDF won the contract to develop Abu Dhabi’s first high-voltage, direct current (HVDC) subsea transmission system.

    It is worth mentioning that the completion of the four units of Abu Dhabi’s 5,600MW Barakah nuclear power plant this year and the expected completion of Dubai’s first hydropower plant in Hatta mean the UAE will have the most diverse energy sources for electricity generation among its peers.   

    Power links

    The goal to expand electricity trade within the GCC member states and with other countries such as Egypt, Jordan and Iraq is another key driver for T&D investments.

    Work is under way to increase the capacity of the GCC regional grid and enable its member-states to procure backup or emergency capacity when the need arises. Kuwait availed of this in May when it purchased 500MW from the GCC grid in anticipation of its inability to meet peak demand in the summer months.   

    An HVDC network linking Saudi Arabia and Egypt is under construction, which will allow bidirectional electricity trade as well as access to the wider European and African markets.

    A second GCC link with Oman and a first link with Jordan are also planned. Another HVDC transmission project linking Neom in the northern tip of the Red Sea to Yanbu, stretching 605 kilometres, is under way.

    It turns out that the need to invest in T&D infrastructure to support electricity generation capacity buildout, following years of underinvestment, is a global phenomenon.

    Juan Diego Zuluaga, Suncolombia CEO, told the ongoing World Green Energy Summit in Dubai that there is a major mismatch between the buildout of transmission lines and electricity generation capacity.

    Experts like Zuluaga think that failing to invest in T&D can potentially lead to issues such as curtailment or wastage in renewable power, particularly in the absence of suitable energy storage systems or efficient interconnections or electricity links.

    Utility companies are under pressure not only to expand their transmission capacities and coverage but to make these infrastructure and facilities more efficient, too.

    New technologies, most of them driven by IoT or AI, for instance, can be used to improve demand and supply management and forecasting, leading to improved grid performance.

    “In this region, in particular, consumers expect 24x7 electricity supply. In fact, it is a given,” notes a senior executive with a European technology company. “The hope is for that to continue in the future.”

     

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12646884/main.jpg
    Jennifer Aguinaldo
  • FDI trends align with Vision 2030

    3 October 2024

     

    This package also includes: Riyadh redoubles efforts to boost inward investment


    Foreign direct investment (FDI) trends are typically volatile and impacted by economic and political factors.

    According to a report on FDI by GlobalData, there was a decline in both project numbers and capital investment in 2023 after a strong year in 2022. 

    While the overall numbers were down, the report highlighted global trends that include a strong investor focus on the Middle East and elsewhere in Asia, outside of China, with Saudi Arabia and the UAE identified specifically as markets that offer strong potential. 

    According to a GlobalData poll, the Middle East ranked as the fourth most attractive region for FDI in 2024 by investor sentiment.

    Middle East deals 

    In terms of deals, the Middle East experienced annual growth in both project activity and inbound capital investment from FDI in 2023. Companies announced 1,848 projects worth an estimated $88.3bn. Geopolitics, strategic partnerships, digitalisation, emissions reductions and artificial intelligence are the key themes causing investors to expand in the region. 

    The UAE was the largest destination country in the region with $23bn of deals across 1,277 projects, which also made it the third-largest FDI market in the world in 2023 based on project activity. 

    Saudi Arabia was the second-largest destination country in the region based on project activity. According to GlobalData, the kingdom attracted inward investment of $17.3bn from 305 FDI projects, which represents a growth of 23% in inward FDI investment in 2022-23. 

    Core sectors

    A detailed analysis of the Saudi FDI data shows that some sectors have been more successful than others. The numbers show that the core sectors of Vision 2030 have been best placed when it comes to attracting FDI.

    The most successful sector in terms of value is metals and minerals. There have been $9.5bn of metals and minerals projects announced in the kingdom, which is significantly more than the second-largest sector, renewables and alternative power, which has attracted $5.4bn of deals. 

    Metals and minerals are an increasingly important sector for Saudi Arabia. The kingdom says its natural resources are worth $2.5tn – an increase of more than 90% compared with 2016 estimates.

    To help monetise these reserves, Riyadh enacted a new mining investment law in 2021, and since then the Ministry of Industry & Mineral Resources (MIMR) has awarded more than 2,000 mining permits to local and foreign firms under its accelerated exploration initiative.

    Renewables and alternative power is also an important sector for FDI, with foreign players investing in power generation projects that are delivered on a public-private partnership basis. 

    Not all projects are announced with a value. Based on the number of FDI projects rather than the aggregate of their announced value, the best-performing sector is tourism, with 271 projects, followed closely by business and professional services, with 270 projects. 

    Tourism is another key pillar of Vision 2030. It has been identified as a focal point for Saudi Arabia’s economic transformation because it opens up the kingdom to foreign visitors, while at the same time creating jobs and investment opportunities.

    When analysed based on business function, manufacturing is the leading sector based on deal value, while construction is the largest sector when measured by the number of projects. Both of these sectors are playing a key role in delivering the objectives of Vision 2030. 

    Manufacturing investments are helping develop jobs and investment opportunities in Saudi Arabia, while also keeping Saudi spending within the kingdom and securing supply chains. This is highlighted clearly by the kingdom’s various moves into the automotive manufacturing space, which aims to establish Saudi Arabia as a key supplier of vehicles for both the local and international markets. 

    Construction underpins many of the other sectors being developed in Saudi Arabia as much of the new economic activity that is planned needs new facilities. Whether it be hotels for tourism, factories for manufacturing or office buildings for professional services, there is a wide range of construction projects planned and underway in the kingdom. 

    FDI landmarks

    Notable breakthroughs in FDI in Saudi Arabia this year highlight these trends shown by the data. The first major deal involves manufacturing and was reported in January when Turkish steelmaker Tosyali Holding revealed plans to invest up to $5bn in a new steel plant in the kingdom.

    Another manufacturing deal came when The Saudi Arabian Industrial Investments Company (Dussur) divested its 55% ownership in General Electric Saudi Advanced Turbines (Gesat) to GE Vernova, giving the US-headquartered firm full ownership of the manufacturer.

    For construction, the National Housing Company (NHC) has signed several major deals with foreign investors. In April, NHC and Urbas Middle East Real Estate Company, a subsidiary of Spain’s Urbas Group, signed an agreement to develop over 589 residential units in NHC’s Al-Fursan suburb of Riyadh.

    In March, NHC signed another deal with Egyptian real estate developer Talaat Moustafa Group (TMG) to develop over 27,000 residential units at NHC’s Banan City project, which is also in the Al-Fursan suburb of Riyadh. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12604344/main.jpg
    Colin Foreman
  • Bringing scale to project delivery

    3 October 2024

     

    A US-based project services company has quietly grown over the past seven years into a global entity with $15bn of revenue and operations in over 100 countries, including key Middle East markets.

    That company is Global Infrastructure Solutions Inc (GISI). It was founded in 2017 by a group of industry veterans, including Dick Newman and John Dinisio, who previously founded another industry giant, Aecom. 

    “The founders are legends in the industry. Dick Newman, in many respects, shaped the modern engineering and consulting business. John Dinisio is another key leader, and so is Jeff Kissel. They are a group of highly experienced, very accomplished leaders that got together in 2017 and founded the business, and in that short period built a business of over 15,000 staff,“ says Derek Amidon, chief operating officer of GISI.

    Business structure

    The business is structured into four broad segments: infrastructure, earth and environment, international development and infrastructure in Asia. 

    The main business for infrastructure is Hill International, which merged with GISI in December 2022. Hill has a strong track record of delivering major projects in the Middle East, including the Palm Jumeirah, Abu Dhabi Airport and Riyadh Metro. 

    The Middle East is also an important region for GISI and, having grown up in the region as a child, one that holds a special place for Amidon. “I have always been interested in the Middle East, and it is a key area of focus for us. We are strengthening our presence and serving important clients. Hill International has worked on some of the most transformative projects that have helped define the modern Middle East,” he says. 

    Global spending on infrastructure right now is at record levels” 
    Derek Amidon, GISI

    The Middle East is just one global market offering strong promise for GISI. “Global spending on infrastructure right now is at record levels, and the demands from clients for our services are very high,” says Amidon. 

    Using a sporting reference, Amidon highlights GISI’s scale and the ability to call upon the experience of its global network of staff as a key differentiator. “We are a firm with a very deep bench of capability. Our global footprint has positioned us well to support our clients and their projects.” 

    People are crucial for successfully delivering projects. “In the Middle East, we are becoming a valuable resource for clients. We are working on key programmes and that will continue to fuel our growth. Our growth has been phenomenal up until now, and that is tied to our ability to attract the best talent in the industry,” says Amidon.

    Looking ahead, GISI is committed to the region and is mindful that it will have to negotiate challenges along the way. “Clearly, there are tensions in the Middle East, but I think we are experienced enough to roll with those tensions. Challenges do not daunt us. We seek to make smart decisions and have good collaborative relationships with our clients,” says Amidon. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12604313/main.gif
    Colin Foreman
  • UAE’s high-speed rail moves ahead

    3 October 2024

    Etihad Rail asked contractors over the summer to submit prequalification forms by October for a contract to design and build the civil works packages for the high-speed rail (HSR) line connecting Abu Dhabi and Dubai.

    The design speed of the trains running on the network will be 350 kilometres an hour (km/h) and the operating speed will be 320km/h.

    The proposed HSR programme will be constructed in four phases, gradually adding further connectivity to other areas within the UAE.

    The first phase involves the construction of a railway line connecting Abu Dhabi and Dubai, which is estimated to be operational by 2030.

    The second phase will involve the development of an inner-city railway network with 10 stations within Abu Dhabi city.

    The third phase of the railway network involves the construction of a connection between Abu Dhabi and Al-Ain.

    The fourth phase involves the development of an inter-emirate connection between Dubai and Sharjah.

    The 150-kilometre (km) first phase of the HSR line will stretch from the Al-Zahiyah area in Abu Dhabi to Al-Jaddaf
    in Dubai.

    The project’s civil works have been split into two packages comprising four sections, the scope of which includes:

    • Phase 1A: Al-Zahiyah to Yas Island in Abu Dhabi (23.5km)
    • Phase 1B: Yas Island to the border of Abu Dhabi/Dubai (64.2km)
    • Phase 1C: Abu Dhabi/Dubai border to Al-Jaddaf in Dubai (52.1km)
    • Phase 1D: Abu Dhabi airport delta junction and connection with Abu Dhabi airport station (9.2km)

    The HSR project is also expected to include significant tunnelling works totalling 31km.

    Five stations

    The rail line will have five stations. These will be in Al-Zahiyah (ADT), Saadiyat Island (ADS), Yas Island (YAS), Abu Dhabi airport (AUH) and the Al-Jaddaf (DJD) area of Dubai.

    The ADT, AUH and DJD stations will be underground, while ADS will be an elevated station and YAS will be at grade.

    The overall HSR package also includes provisions for the rolling stock, railway systems and two maintenance depots.

    The high-speed project will slash journey times between the UAE’s two largest cities and economic centres. The journey time between the YAS and DJD stations will be 30 minutes.

    Dubai-based Matcon Testing Laboratory and Abu Dhabi’s Engineering & Research International are conducting drilling tests to ascertain the ground conditions in areas through which the HSR line will pass.

    Spanish engineering companies Sener and Ineco are the project’s engineering consultants. French engineering firm Systra has been confirmed as the project management consultant for the first phase of the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12598662/main.jpg
    Yasir Iqbal