Saudi Arabia’s power sector motors on

11 September 2024

 

Saudi Arabia’s power sector has sustained its project activity momentum over the past six months.

The principal buyer, Saudi Power Procurement Company (SPPC), awarded the contracts to develop two publicly-tendered wind independent power producer (IPP) projects, with a total combined capacity of 1,100MW, under the fourth round of the kingdom’s National Renewable Energy Programme (NREP).

The Public Investment Fund (PIF), responsible for procuring through direct negotiations 70% of the kingdom’s 2030 target renewable energy capacity, let three large-scale solar photovoltaic (PV) projects with a total combined capacity of around 5,500MW.

State majority-owned Saudi Aramco also awarded a contract to develop an independent cogeneration project with an electricity generation capacity of 475MW.

During the same period, SPPC began the tendering process for two combined-cycle gas turbine (CCGT) projects, the Remah and Nairiyah IPPs, each with a capacity of 3,600MW, and for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round.

“It has been a very busy summer,” notes a senior executive with an international utility developer, referring to the submission of bids in August for the contracts to develop the Remah 1 & 2, Nairiyah 1 & 2, and the NREP round-five solar PV schemes.

Notably, the principal buyer has initiated the selection process for consultants who will advise on its next pair of independent CCGT power plants – the 2,400MW Al-Rais and the 3,600MW Riyadh 16 projects.

Saudi Electricity Company (SEC) and SPPC are also understood to be conducting bilateral talks for the development of five CCGT power plants, which, along with those currently being built or tendered, support the kingdom’s mandate to replace fleets running on liquid fuel.

Essentially, the reported SEC projects, each with a capacity of 1,500MW-2,000MW, bear some similarities to PIF’s directly negotiated renewable energy schemes.

These projects help substantiate previous reports that SEC has been seeking to lock in gas turbine equipment deals with a total capacity of 30GW, in line with an overall capacity expansion plan within and outside Saudi Arabia.

The next few years can only get busier, with Saudi Arabia's Energy Minister, Prince Abdulaziz Bin Salman Bin Abdulaziz Al-Saud, confirming in June plans to tender 20,000MW of renewable energy projects annually starting this year, in line with reaching 100GW-130GW of installed capacity by 2030, "depending on electricity demand growth".

This represents a major upward revision to the official 2030 renewable energy capacity target of 58,700MW.

However, it is unclear if this new target considers the renewable capacity that will be installed to power Neom, Saudi Arabia’s largest gigaproject, as well as the requirement of green hydrogen projects that the PIF plans to codevelop.

Wind IPPs

In May, SPPC awarded a team led by Japanese utility developer Marubeni Corporation the contracts to develop the 600MW Al-Ghat wind and 700MW Waad Al-Shamal wind IPPs.

The team of Marubeni and its partner, the local Alajlan Brothers, is also expected to win the contract to develop the 700MW Yanbu wind IPP, the final wind scheme included in NREP’s round four.

These are important awards for Marubeni, which last won an IPP contract in Saudi Arabia in 2021 for the 300MW Rabigh solar scheme.

Notably, the Al-Ghat and Waad Al-Shamal wind IPPs will be developed at world-record-low levelised electricity costs of $c1.565 a kilowatt-hour (kWh), or roughly 5.87094 halalas/kWh, and $c1.70187/kWh or 6.38201 halalas/kWh.

PIF projects

In June, three Saudi utility developers and investors signed power-purchase agreements (PPAs) with SPPC to develop and operate three solar PV projects with a combined capacity of 5,500MW.

The Haden and Muwayh solar PVs, located in Mecca, will each have a capacity of 2,000MW, while the Al-Khushaybi solar PV power plant in Qassim will be able to generate 1,500MW of electricity.

The team that will develop the three projects consists of Acwa Power, PIF-backed Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco), a subsidiary of the state majority-owned oil giant.

The project companies formed for each solar IPP have since signed financing documents for the projects, which will require a total investment of SR12.3bn ($3.3bn). The financing sought was $2.6bn.

These projects comprise round four of PIF’s Price Discovery Scheme, with Acwa Power as the preferred developer partner.

Energy storage systems

The scale of new conventional and renewable energy capacity being developed in the kingdom – some 3,500MW of solar PV and wind capacity is now online, with over 10,500MW under construction – has increased the urgency to build energy storage systems to balance the kingdom’s energy system and stabilise its grid.

SPPC has signalled plans to procure gigawatt-sized battery energy storage systems (bess) using an IPP model. The tendering process for the first bess IPP package is expected to begin by the year-end or early 2025.

In parallel, National Grid Saudi Arabia, an SEC subsidiary, has started awarding contracts to build energy storage systems capacity using an engineering, procurement and construction (EPC) model. The local Algihaz Holding is understood to have won the contracts to build four energy storage systems in Najran, Madaya and Khamis Mushait, which will have a total combined capacity of 7.8 gigawatt-hours (GWh).

Also in August, SEC tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW, or roughly 10GWh.

The planned facilities, each with a capacity of 500MW or roughly 2GWh, are located in or within the proximity of the following key cities and load centres:

  • Riyadh
  • Qaisumah
  • Dawadmi
  • Al-Jouf
  • Rabigh

Saudi Arabia’s plan to build its first large-scale nuclear power plant in Duwaiheen, which appeared to be making progress before October last year, has faced delays following shifting geopolitics involving stakeholders that include the US and Israel. The tender bid deadline for nuclear technology providers is understood to have been postponed and no new date has been set.

As it is, Saudi Arabia’s ever-expanding power projects pipeline, particularly for renewables and bess, will require investors, contractors and lenders to allocate sizeable resources, perhaps more than they have historically done in the past, over the next several years as various stakeholders endeavour to meet Vision 2030-tied peak demand scenarios.

This applies less to CCGT projects, which, pending a clear carbon-capture strategy from the offtaker or the Energy Ministry, appear to attract a decreasing number of developers and investors.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12496716/main.jpg
Jennifer Aguinaldo
Related Articles
  • Adnoc builds long-term oil and gas production potential

    7 April 2026

     

    Between 2023 and 2024, Abu Dhabi National Oil Company (Adnoc Group) spent an estimated $37bn on projects critical to achieving its upstream targets: increasing oil production capacity to 5 million barrels a day (b/d) by 2027 and attaining gas self-sufficiency by the end of the decade.

    The state energy company spent more than $22.5bn in 2023 alone, marking the highest annual oil and gas project spending on record in the UAE. The Hail and Ghasha sour gas development – accounting for approximately $17bn – remains the single-largest contract award in the country’s hydrocarbons sector.

    A slowdown in capital expenditure (capex) following two years of elevated spending is therefore in line with expectations. While engineering, procurement and construction (EPC) contract awards for upstream projects declined in 2025 and into this year, Adnoc has still committed close to $10bn over the past 15 months.

    The largest award during this period came from Adnoc Offshore, which let contracts worth $7.5bn for three EPC packages under the Lower Zakum Long-Term Development Plan (LTDP-1). Spain’s Tecnicas Reunidas and Abu Dhabi-based NMDC Energy and Target Engineering Construction Company were selected last February to execute the works.

    The Lower Zakum field, located 65 kilometres northwest of Abu Dhabi, is majority-owned by Adnoc Offshore (60%). Other stakeholders include an Indian consortium led by ONGC Videsh (10%), Japan’s Inpex (10%), China National Petroleum Corporation (10%), Italy’s Eni (5%) and France’s TotalEnergies (5%).

    Adnoc Offshore aims to increase production capacity at Lower Zakum to 520,000 b/d by 2027 and sustain that level through 2034.

    Offshore contracts in 2026

    So far this year, Adnoc Offshore has awarded contracts for two key projects: the Satah Al-Razboot (Sarb) deep gas development and the expansion of the Nasr oil field.

    Adnoc achieved final investment decision (FID) on the Sarb project in January and awarded the main EPC contract to US-based McDermott International. The contract is estimated to be worth around $500m, sources told MEED.

    The project is expected to deliver 200 million cubic feet a day (cf/d) of gas by the end of the decade – enough to power more than 300,000 homes.

    The scope includes the EPC of an offshore wellhead tower with four gas production wells, which will be connected to Das Island for processing through Adnoc Gas facilities. Works also include the installation of pipelines and intra-field connections linking the Sarb field to Das Island.

    Also in January, Adnoc Offshore awarded McDermott a $942m contract for the Nasr-115 project, which will increase production capacity at the Nasr offshore field to 115,000 b/d. The field is located about 130km northwest of Abu Dhabi.

    McDermott’s scope covers full EPCI services for two topside structures, a new manifold tower, a jacket, a bridge, associated pipelines, subsea cables and brownfield modifications.

    Strategic projects in queue

    Over the next 12-18 months, Adnoc’s upstream spending is expected to shift from meeting near-term production targets –now largely within reach – to building longer-term capacity beyond 2030.

    Following $1.3bn in EPC awards in 2024 for the Upper Zakum expansion to 1.2 million b/d, Adnoc Offshore is advancing the next phase, which will increase capacity to 1.5 million b/d.

    Located 84km offshore, Upper Zakum is the world’s second-largest offshore oil field. Adnoc Offshore has divided the EPC scope into three packages, with contractors submitting commercial bids for the UZ1.5MMBD project in February.

    Adnoc Offshore is also progressing the Umm Shaif gas cap and surface pressure boosting project, aimed at increasing gas production by 550 million cubic feet a day (cf/d) and condensate output by 50,000 b/d. About 520 million cf/d of additional gas is expected to be fed into Adnoc’s sales gas network.

    The first phase of the project has been split into three EPC packages:

    • Offshore package 1: fabrication of a 30,000-tonne gas compression system
    • Offshore package 2: fabrication of a 30,000-tonne gas compression system
    • Onshore package: EPC of gas inlet and processing systems at Das Island

    Adnoc Offshore is currently evaluating commercial bids submitted in February for these packages.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16285814/main.gif
    Indrajit Sen
  • Contractor wins Oman housing substation contract

    7 April 2026

    Oman’s Public Authority for Social Insurance has awarded a contract for the supply, installation, execution and maintenance of a main power substation for its affordable housing project.

    The contract was awarded to Kuwait-based Al-Ahleia Switchgear Company.

    The project comprises a 400/132/11kV main substation for the Affordable Housing Project, known locally as Al-Masaken Al-Muyassara.

    The tender was announced last November, with the bid envelopes opened on 16 December 2025.

    Al-Ahleia Switchgear submitted another bid in March for a contract to build three 132/11kV main transformer stations for Kuwait’s Public Authority for Housing Welfare (PAHW).

    As reported by MEED, the company’s price of KD10.5m ($34.1m) was the lowest of two offers for the engineering, procurement and construction (EPC) contract.

    Separately, in December, Al-Ahleia Switchgear submitted the lowest bid of KD33.9m ($110.3m) for a contract to build a 400/132/11 kV substation at the South Surra township for Kuwait’s PAHW.

    The bid was marginally lower than the two other offers submitted by Saudi Arabia’s National Contracting Company (NCC) and India’s Larsen & Toubro.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16285335/main5555.jpg
    Mark Dowdall
  • UAE reviews $1.63bn fourth federal road project

    7 April 2026

    UAE authorities on 6 April unveiled details of the AED6bn ($1.63bn) fourth federal corridor scheme, a major highway programme aimed at boosting inter-emirate connectivity, increasing road capacity and easing congestion.

    The project comprises a 68-kilometre corridor with 10 major interchanges, four flyovers and six to eight lanes in each direction.

    Officials provided technical updates on the corridor, including revised connection points and coordination with local authorities to finalise route alignments in line with broader development plans.

    Suhail Mohamed Al-Mazrouei, minister of energy and infrastructure, said the programme underscores the central role of infrastructure in the UAE’s development agenda and competitiveness. He was speaking while chairing the first meeting of the UAE Infrastructure and Housing Council this year.

    The council also reviewed progress on federal infrastructure initiatives aimed at improving transport efficiency and strengthening coordination between federal and local authorities.

    Al-Mazrouei said the next phase will focus on accelerating the delivery of high-impact projects to enhance transport system performance and support the shift towards smart and sustainable mobility in line with population growth and urban expansion.

    The council also assessed progress on linking Ajman to the third and fourth federal corridors, which is expected to provide alternative routes, improve traffic flow and further enhance mobility between the emirates.

    On public transport, the council reviewed a study on transport links between Dubai, Sharjah and Ajman to address rising commuting demand.

    The proposed plan includes 10 priority routes incorporating bus rapid transit and dedicated lanes, with connections to key hubs such as the Dubai Metro and city centres.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16285296/main.jpg
    Yasir Iqbal
  • Kingdom Holding Company signs Riyadh project deal

    7 April 2026

    Saudi Arabia’s Kingdom Holding Company has signed an agreement with Sumou Real Estate Company under which Sumou will manage the development, marketing and sale of a 3-million-square-metre land plot in Riyadh.

    The scheme is expected to generate about SR4bn ($1bn) in total sales.

    In a Tadawul disclosure, Kingdom Holding Company said its subsidiaries, Kingdom Real Estate Development Company and Trade Centre Company, have appointed Sumou as the exclusive development manager for the site.

    The project is scheduled to be implemented over 36 months, starting once the masterplans are approved by the relevant authorities.

    In a separate stock exchange statement, Sumou said it will be paid 6.5% of total infrastructure development costs and 2.5% of project sales, in addition to the brokerage commission paid by buyers.

    Kingdom Holding Company said the agreement aligns with its long-term strategy for its Riyadh landbank, which originally totalled around 20 million sq m and is being developed in phases.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16284668/main.jpg
    Yasir Iqbal
  • Saudi Arabia’s Jubail industrial city hit by missile debris

    7 April 2026

    Explosions were reported in Saudi Arabia’s Jubail industrial city on 7 April. Saudi authorities said the country’s air defence systems intercepted seven ballistic missiles targeting the Eastern Province, with debris landing near energy facilities, primarily in Jubail.

    Jubail is one of the world’s largest petrochemical production hubs, with an annual output of about 60 million tonnes, accounting for an estimated 6% to 8% of global supply.

    The incident places renewed focus on the kingdom’s flagship petrochemical cluster, where majority state-owned Saudi Basic Industries Corporation (Sabic) is a key investor.

    Jubail also hosts major downstream oil, gas and petrochemical assets operated by Saudi Aramco, US-based Dow and France’s TotalEnergies, underscoring the industrial zone’s international significance.

    Saudi officials said damage assessments are ongoing.

    The developments follow an Israeli strike on 6 April targeting a major petrochemical complex in Iran’s southern Asaluyeh region, described as the country’s largest industrial hub.

    Separately, authorities closed the King Fahd Causeway – the main bridge linking Saudi Arabia and Bahrain – early on 7 April as a precaution amid heightened security concerns.

    The King Fahd Causeway Authority said in a post on X that vehicle movement had been “suspended as a precautionary measure” due to Iranian attacks targeting Saudi Arabia’s Eastern Province.

    The 25-kilometre bridge is Bahrain’s only road link to the Arabian Peninsula.

    US President Donald Trump has issued an ultimatum for Iran to reopen the Strait of Hormuz and threatened to bomb Iranian power plants and bridges if Tehran does not comply by 8pm EDT on 7 April.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16283711/main2424.jpg
    Indrajit Sen