Saudi Arabia’s power sector motors on

11 September 2024

 

Saudi Arabia’s power sector has sustained its project activity momentum over the past six months.

The principal buyer, Saudi Power Procurement Company (SPPC), awarded the contracts to develop two publicly-tendered wind independent power producer (IPP) projects, with a total combined capacity of 1,100MW, under the fourth round of the kingdom’s National Renewable Energy Programme (NREP).

The Public Investment Fund (PIF), responsible for procuring through direct negotiations 70% of the kingdom’s 2030 target renewable energy capacity, let three large-scale solar photovoltaic (PV) projects with a total combined capacity of around 5,500MW.

State majority-owned Saudi Aramco also awarded a contract to develop an independent cogeneration project with an electricity generation capacity of 475MW.

During the same period, SPPC began the tendering process for two combined-cycle gas turbine (CCGT) projects, the Remah and Nairiyah IPPs, each with a capacity of 3,600MW, and for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round.

“It has been a very busy summer,” notes a senior executive with an international utility developer, referring to the submission of bids in August for the contracts to develop the Remah 1 & 2, Nairiyah 1 & 2, and the NREP round-five solar PV schemes.

Notably, the principal buyer has initiated the selection process for consultants who will advise on its next pair of independent CCGT power plants – the 2,400MW Al-Rais and the 3,600MW Riyadh 16 projects.

Saudi Electricity Company (SEC) and SPPC are also understood to be conducting bilateral talks for the development of five CCGT power plants, which, along with those currently being built or tendered, support the kingdom’s mandate to replace fleets running on liquid fuel.

Essentially, the reported SEC projects, each with a capacity of 1,500MW-2,000MW, bear some similarities to PIF’s directly negotiated renewable energy schemes.

These projects help substantiate previous reports that SEC has been seeking to lock in gas turbine equipment deals with a total capacity of 30GW, in line with an overall capacity expansion plan within and outside Saudi Arabia.

The next few years can only get busier, with Saudi Arabia's Energy Minister, Prince Abdulaziz Bin Salman Bin Abdulaziz Al-Saud, confirming in June plans to tender 20,000MW of renewable energy projects annually starting this year, in line with reaching 100GW-130GW of installed capacity by 2030, "depending on electricity demand growth".

This represents a major upward revision to the official 2030 renewable energy capacity target of 58,700MW.

However, it is unclear if this new target considers the renewable capacity that will be installed to power Neom, Saudi Arabia’s largest gigaproject, as well as the requirement of green hydrogen projects that the PIF plans to codevelop.

Wind IPPs

In May, SPPC awarded a team led by Japanese utility developer Marubeni Corporation the contracts to develop the 600MW Al-Ghat wind and 700MW Waad Al-Shamal wind IPPs.

The team of Marubeni and its partner, the local Alajlan Brothers, is also expected to win the contract to develop the 700MW Yanbu wind IPP, the final wind scheme included in NREP’s round four.

These are important awards for Marubeni, which last won an IPP contract in Saudi Arabia in 2021 for the 300MW Rabigh solar scheme.

Notably, the Al-Ghat and Waad Al-Shamal wind IPPs will be developed at world-record-low levelised electricity costs of $c1.565 a kilowatt-hour (kWh), or roughly 5.87094 halalas/kWh, and $c1.70187/kWh or 6.38201 halalas/kWh.

PIF projects

In June, three Saudi utility developers and investors signed power-purchase agreements (PPAs) with SPPC to develop and operate three solar PV projects with a combined capacity of 5,500MW.

The Haden and Muwayh solar PVs, located in Mecca, will each have a capacity of 2,000MW, while the Al-Khushaybi solar PV power plant in Qassim will be able to generate 1,500MW of electricity.

The team that will develop the three projects consists of Acwa Power, PIF-backed Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco), a subsidiary of the state majority-owned oil giant.

The project companies formed for each solar IPP have since signed financing documents for the projects, which will require a total investment of SR12.3bn ($3.3bn). The financing sought was $2.6bn.

These projects comprise round four of PIF’s Price Discovery Scheme, with Acwa Power as the preferred developer partner.

Energy storage systems

The scale of new conventional and renewable energy capacity being developed in the kingdom – some 3,500MW of solar PV and wind capacity is now online, with over 10,500MW under construction – has increased the urgency to build energy storage systems to balance the kingdom’s energy system and stabilise its grid.

SPPC has signalled plans to procure gigawatt-sized battery energy storage systems (bess) using an IPP model. The tendering process for the first bess IPP package is expected to begin by the year-end or early 2025.

In parallel, National Grid Saudi Arabia, an SEC subsidiary, has started awarding contracts to build energy storage systems capacity using an engineering, procurement and construction (EPC) model. The local Algihaz Holding is understood to have won the contracts to build four energy storage systems in Najran, Madaya and Khamis Mushait, which will have a total combined capacity of 7.8 gigawatt-hours (GWh).

Also in August, SEC tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW, or roughly 10GWh.

The planned facilities, each with a capacity of 500MW or roughly 2GWh, are located in or within the proximity of the following key cities and load centres:

  • Riyadh
  • Qaisumah
  • Dawadmi
  • Al-Jouf
  • Rabigh

Saudi Arabia’s plan to build its first large-scale nuclear power plant in Duwaiheen, which appeared to be making progress before October last year, has faced delays following shifting geopolitics involving stakeholders that include the US and Israel. The tender bid deadline for nuclear technology providers is understood to have been postponed and no new date has been set.

As it is, Saudi Arabia’s ever-expanding power projects pipeline, particularly for renewables and bess, will require investors, contractors and lenders to allocate sizeable resources, perhaps more than they have historically done in the past, over the next several years as various stakeholders endeavour to meet Vision 2030-tied peak demand scenarios.

This applies less to CCGT projects, which, pending a clear carbon-capture strategy from the offtaker or the Energy Ministry, appear to attract a decreasing number of developers and investors.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12496716/main.jpg
Jennifer Aguinaldo
Related Articles
  • Firms submit Mid Island Parkway prequalifications

    18 August 2026

     

    Abu Dhabi’s Modon Infrastructure has received expressions of interest and prequalification statements for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will be developed as a public-private partnership.

    Modon Infrastructure will act as the lead developer and will hold a majority equity stake in the project company. It will award contracts for engineering, procurement and construction; operations and maintenance; and project advisory services.

    Phase two of the MIPP involves constructing about 11 kilometres (km) of highways, comprising a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also includes the construction of three interchanges – E20, E10 and Dumbbell – on Al-Sammaliyyah Island.

    The project includes several major structures, including the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange, which will feature cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover tunnel on Bilrimaid Island. Another tunnel will connect Bilrimaid Island to Um-Yifeenah Island.

    Abu Dhabi awarded three packages for phase one of the MIPP in 2024. The contract for Package 1A was awarded to a joint venture of Turkish contractor Dogus Construction and UAE firm Gulf Contractors. Package 1B was awarded to a joint venture of Yas Projects (Alpha Dhabi Holding) and China Railway International Group. Beijing-headquartered China Harbour Engineering Company and the UAE’s Agility Engineering & Contracting Company won the contract for Package 1C.

    Phase one starts at the existing Saadiyat Interchange, connecting the E12 to the MIPP, and ends at the recently constructed Um-Yifeenah Highway.

    It comprises a dual main road with a total length of 8km, including four traffic lanes in each direction, two interchanges, a tunnel and associated infrastructure works.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18830452/main.png
    Yasir Iqbal
  • Adnoc selects contractors for new LNG project in the UAE

    18 August 2026

     

    Abu Dhabi National Oil Company (Adnoc) has selected contractors for a design competition it is overseeing for a major project to build a new liquefied natural gas (LNG) export facility along the UAE’s eastern coast.

    The proposed onshore LNG liquefaction facility – whose precise location Adnoc has yet to reveal – will have a nameplate output capacity of 4 million tonnes a year (t/y) and will mainly serve export purposes, MEED reported in June. The facility will receive sales-gas-quality feedstock via pipelines from Adnoc’s gas processing facilities in Abu Dhabi and will export LNG via a loading jetty.

    MEED previously reported on Adnoc’s intention to execute work on the project through a design competition or front-end engineering and design (feed)-to-engineering, procurement and construction (EPC) contest.

    Under this model, the project operator selects contractors to carry out feed work. The operator then awards the EPC contract to the contractor with the most competitive feed proposal, while compensating the other contestants for their work.

    The Abu Dhabi energy giant has selected the following three entities to undertake feed work on the planned onshore LNG liquefaction facility, according to sources:

    • Saipem (Italy) / Larsen & Toubro Energy Hydrocarbon (India)
    • Technip Energies (France) / JGC Corporation (Japan)
    • Tecnimont (Italy)

    Adnoc issued draft letters of award to the selected contractors between 11 and 12 August, the sources added.

    In addition to the contractors picked by Adnoc, MEED previously reported that the following contractors were shortlisted for the feed-to-EPC contest:

    • McDermott (US)
    • Samsung E&A (South Korea)
    • Wison (China)

    MEED reported that Adnoc issued the expression of interest (EoI) document for the planned LNG facility project on 2 June, with contractors submitting responses by 5 June.

    Given the strategic importance of the project, Adnoc is understood to be fast-tracking the tendering exercise, issuing the main tender for the feed-to-EPC contest within days of the EoI submission. The company sought proposals from participating contractors by 1 July, sources said.

    In its EoI document, Adnoc said it intends to award the main EPC contract in the third quarter of this year.

    Adnoc has yet to specify where it plans to build the LNG complex, stating only in the EoI document that it will be located at a coastal site in the UAE.

    MEED understands Adnoc may be considering a site near one of the UAE’s eastern port facilities in the emirate of Fujairah. The blockade of the Strait of Hormuz in recent months has increased interest in prioritising exports and maritime trade through ports on the Gulf of Oman.

    The scope of work on the planned LNG facility covers the following units:

    LNG facilities:

    • An onshore LNG liquefaction facility in a coastal location, with a nominal output capacity of 4 million t/y;
    • Process units necessary to bring sales feed to a liquefaction-quality feed gas (i.e. carbon dioxide removal, dehydration, mercury removal and total sulphur reduction);
    • Common facilities including inlet receiving facilities, refrigerant storage and flares;
    • Utilities to support the facility, allowing it to be self-sufficient, including but not limited to local power generation and any necessary tie-ins;
    • LNG export facilities, including a jetty and berth;
    • Structures including control buildings, amenities, a laboratory, a warehouse, workshops and administration buildings, to fully support the plant operation.

    LNG storage facilities:

    • LNG storage tanks, handling of boil-off gases (BOG) and potentially a BOG reliquefaction unit to facilitate major shutdown operations for bidders opting to compete with a single liquefaction train option.

    Feed gas supply:

    • Supplying and installing an additional identical gas compressor to be located at an existing compression station near Adnoc Gas’ Habshan complex in Abu Dhabi, to provide additional capacity in an existing gas pipeline system;
    • A new feed gas pipeline, approximately 160 kilometres long, to route sales gas quality feed gas from an existing pipeline network to the LNG facility.

    Modifications to upstream facilities (alternative scope):

    • Installation of sulphur removal beds in Habshan to bring feed gas to required LNG quality at the upstream gas conditioning facility, rather than at the LNG facility. This may be selected by bidders to avoid additional investment for processing the regeneration gas.

    Construction facilities:

    • Temporary construction facilities, laydown area and material offloading facility, to support EPC execution requirements;
    • Construction labour accommodation camp.
    Adnoc LNG output capacity

    Adnoc has an LNG liquefaction capacity of 6 million t/y, which is set to more than double to 15 million t/y when its under-construction LNG terminal complex in Abu Dhabi’s Ruwais enters operations in 2028.

    The upcoming LNG export terminal in Ruwais will have the capacity to produce about 9.6 million t/y of LNG from two processing trains, each with a capacity of 4.8 million t/y.

    Adnoc awarded the full EPC contract and reached the final investment decision for the Ruwais LNG terminal project in June 2024. A consortium of France’s Technip Energies, Japan-based JGC Corporation and Abu Dhabi-owned NMDC Energy – a subsidiary of NMDC Group – was awarded the $5.5bn EPC contract. In March of that year, Adnoc issued a limited notice to proceed to the consortium of contractors led by Technip Energies for early EPC works on the Ruwais LNG terminal project.

    The complex will feature process units, storage tanks and an export jetty for loading cargoes and LNG bunkering, as well as utilities, flare handling systems and associated buildings.

    The planned LNG facility will run on electric-powered rotary equipment and compressors instead of gas-fired units. Adnoc awarded a $400m contract in October 2023 to US-based Baker Hughes for the supply of all-electric compression systems for the project. The LNG trains will run on energy-efficient Baker Hughes technology, including compressors driven by 75MW electric motors.

    Adnoc has also signed agreements with international energy companies to divest a total stake of 40% in the Ruwais LNG project. UK energy producer BP, Mitsui & Co, Shell and French energy producer TotalEnergies will each hold 10% stakes in the Ruwais LNG terminal project, with Adnoc retaining the majority 60% stake in the facility.

    Adnoc Group subsidiary Adnoc Gas will acquire its parent company’s 60% stake in the Ruwais LNG facility at cost in the second half of 2028, when first production from the complex is due.

    To date, Adnoc has secured offtake agreements totalling 8 million t/y, representing approximately 90% of the Ruwais LNG project’s output capacity.

    Photo for illustration only

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18829520/main.jpg
    Indrajit Sen
  • Saudi Arabia extends bid deadline for Round 7 solar projects

    18 August 2026

     

    Saudi Arabia’s principal buyer, Saudi Power Procurement Company (SPPC), has extended the deadline for developers bidding for four solar projects under the seventh round of the National Renewable Energy Programme (NREP).

    Round seven of the NREP comprises solar photovoltaic (PV) and wind independent power producer (IPP) projects with a combined capacity of 5,300MW. The renewables programme is being led and supervised by the Ministry of Energy.

    The four solar PV projects comprise:

    • 1,400MW Tabjal 2 solar PV IPP (Tabrijal, Al-Jouf province)
    • 600MW Mawqqaq solar PV IPP (Mawqqaq, Hail province)
    • 600MW Tathleeth solar PV IPP (Tathleeth, Aseer province)
    • 500MW South Al-Ula solar PV IPP (Al-Ula, Medina province)

    The projects were tendered in January, with submissions previously expected by 30 August. The new deadline is 13 September.

    The programme also includes the 1,300MW Bilgah and 900MW Shagra wind IPPs. The bid submission deadline for these projects is 14 September.

    As previously reported by MEED, procurement for the seventh round of the NREP opened in August 2025 when SPPC issued a request for qualification. 

    In January, MEED reported that 16 developers qualified to bid as both managing and technical members for the four solar PV projects. A further six companies qualified to bid as a managing member only.

    For the wind IPPs, SPPC qualified 13 developers in the managing and technical members category, and a further six companies in the managing member category only. The request for proposals for both wind and solar IPPs was issued that same month. 

    The renewable energy programme aims to supply 50% of the kingdom’s electricity from renewable energy by 2030.

    Earlier rounds under the NREP have already put in place large capacities. Last October, SPPC awarded contracts to develop and operate five renewable energy projects under round six of the NREP.

    These comprise four solar PV IPP projects and one wind IPP project with a total combined capacity of 4,500MW.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18828963/main.jpg
    Mark Dowdall
  • Construction begins on phase two of Cairo Metro Line 4

    18 August 2026

    Egypt’s National Authority for Tunnels (NAT) has begun implementing the second phase of Cairo Metro’s Line 4, spanning about 27 kilometres.

    The main construction works contract was awarded to a joint venture of local firms, including Arab Contractors, Hassan Allam, Petrojet and Concord Engineering & Contracting.

    Cairo Metro Line 4 will stretch from Fustat station to Zahraa Nasr City station in New Cairo. The line will comprise 21 stations, 15 underground and six elevated.

    According to data from regional projects tracker MEED Projects, the scope also covers:

    • Construction of a tunnel route starting from Al-Fustat station, following Salah Salem Road, and intersecting with the sixth metro line at Sayeda Aisha station
    • An extension along Hafez Ibrahim Street, intersecting the Shinzo Abe Axis and linking Ahmed Al-Zomor and Al-Mithaq streets
    • A section running via Nasr Road and Nasr City to Anwar Al-Mufti Street, with an interchange with the East Nile Monorail at Aviation station
    • Construction of a depot at the Omra El-Gasima site
    • Integration of interchange stations with existing lines, including Line 1 and Line 2
    • Construction of structures over and under major roadways, including the Ring Road and Cairo-Suez Road
    • Earthworks and site preparation, including elevated foundations and underground excavations
    • Construction of all other associated infrastructure

    Local media reports said construction work on the first phase of Line 4 is expected to be completed in 2028.

    The joint venture of Arab Contractors, Hassan Allam, Petrojet and Concord Engineering & Contracting is also undertaking the main works on the first phase.

    The Japan International Cooperation Agency (Jica) provided half of the $4bn funding required for Line 4’s first phase.

    The media reports added that NAT is currently studying the third and fourth phases of Line 4.

    The third phase aims to connect the Ashgar Gardens and Al-Hosary areas via a rail line spanning more than 16km.

    The fourth phase will be more than 38km long and will connect the Al-Rehab area with the capital’s international airport east of Cairo.

    Once completed across all phases, Line 4 will link 6th of October City with southern and eastern Cairo, the New Administrative Capital and Capital International airport, making it one of the longest transport networks in the country.

    In April last year, MEED reported on Egypt’s future rail project plans, which include eight key projects spanning metro, high-speed rail and light rail transit.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18825481/main.jpg
    Yasir Iqbal
  • RTA opens bridge connecting DWTC to Al-Mustaqbal Street

    18 August 2026

    Dubai’s Roads & Transport Authority (RTA) has opened a new 500-metre, two-lane bridge connecting traffic from Dubai World Trade Centre (DWTC) and One Central to Al-Mustaqbal Street.

    The bridge will reduce travel time from DWTC to Al-Mustaqbal Street from around 10 minutes to about two minutes during major events.

    The bridge is part of the $172m Al-Mustaqbal Street Development Project. The wider scheme includes around 2,000 metres of bridges and tunnels, along with a pedestrian bridge on Al-Sukook Street, and runs from Zaabeel Palace Street to Financial Centre Street.

    As part of the project, Al-Mustaqbal Street will be widened from three to four lanes in each direction, increasing overall capacity by 33% to 8,800 vehicles per hour in both directions.

    The RTA added that this is expected to cut end-to-end travel time along the corridor from 13 minutes to six minutes.

    Three tunnels, totalling 1,500 metres, at the intersection of Al-Mustaqbal Street and Trade Centre Street are scheduled to open in February 2027.

    These include a three-lane tunnel towards Deira with a capacity of 4,500 vehicles per hour, a two-lane tunnel for left-turn movements between the two streets, and a one-lane tunnel serving One Central.

    The RTA said that the overall project completion rate has reached 85%.

    In February last year, MEED exclusively reported that the RTA had selected local firm Wade Adams to undertake improvement works on Al-Mustaqbal Street.

    Planning for growth

    The Dubai 2040 Urban Master Plan was launched in March 2021. Its launch referenced studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.

    In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan. 

    In addition to the road projects, the RTA’s Dubai Metro Blue Line extension and Dubai Metro Gold Line form part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.

    The policy aims for residents to have 80% of their daily requirements within a 20-minute journey, on foot or by bicycle. This goal will be achieved by developing integrated service centres with all necessary facilities and increasing population density around mass transit stations.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18822891/main.jpg
    Yasir Iqbal