Saudi Arabia’s power sector motors on

11 September 2024

 

Saudi Arabia’s power sector has sustained its project activity momentum over the past six months.

The principal buyer, Saudi Power Procurement Company (SPPC), awarded the contracts to develop two publicly-tendered wind independent power producer (IPP) projects, with a total combined capacity of 1,100MW, under the fourth round of the kingdom’s National Renewable Energy Programme (NREP).

The Public Investment Fund (PIF), responsible for procuring through direct negotiations 70% of the kingdom’s 2030 target renewable energy capacity, let three large-scale solar photovoltaic (PV) projects with a total combined capacity of around 5,500MW.

State majority-owned Saudi Aramco also awarded a contract to develop an independent cogeneration project with an electricity generation capacity of 475MW.

During the same period, SPPC began the tendering process for two combined-cycle gas turbine (CCGT) projects, the Remah and Nairiyah IPPs, each with a capacity of 3,600MW, and for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round.

“It has been a very busy summer,” notes a senior executive with an international utility developer, referring to the submission of bids in August for the contracts to develop the Remah 1 & 2, Nairiyah 1 & 2, and the NREP round-five solar PV schemes.

Notably, the principal buyer has initiated the selection process for consultants who will advise on its next pair of independent CCGT power plants – the 2,400MW Al-Rais and the 3,600MW Riyadh 16 projects.

Saudi Electricity Company (SEC) and SPPC are also understood to be conducting bilateral talks for the development of five CCGT power plants, which, along with those currently being built or tendered, support the kingdom’s mandate to replace fleets running on liquid fuel.

Essentially, the reported SEC projects, each with a capacity of 1,500MW-2,000MW, bear some similarities to PIF’s directly negotiated renewable energy schemes.

These projects help substantiate previous reports that SEC has been seeking to lock in gas turbine equipment deals with a total capacity of 30GW, in line with an overall capacity expansion plan within and outside Saudi Arabia.

The next few years can only get busier, with Saudi Arabia's Energy Minister, Prince Abdulaziz Bin Salman Bin Abdulaziz Al-Saud, confirming in June plans to tender 20,000MW of renewable energy projects annually starting this year, in line with reaching 100GW-130GW of installed capacity by 2030, "depending on electricity demand growth".

This represents a major upward revision to the official 2030 renewable energy capacity target of 58,700MW.

However, it is unclear if this new target considers the renewable capacity that will be installed to power Neom, Saudi Arabia’s largest gigaproject, as well as the requirement of green hydrogen projects that the PIF plans to codevelop.

Wind IPPs

In May, SPPC awarded a team led by Japanese utility developer Marubeni Corporation the contracts to develop the 600MW Al-Ghat wind and 700MW Waad Al-Shamal wind IPPs.

The team of Marubeni and its partner, the local Alajlan Brothers, is also expected to win the contract to develop the 700MW Yanbu wind IPP, the final wind scheme included in NREP’s round four.

These are important awards for Marubeni, which last won an IPP contract in Saudi Arabia in 2021 for the 300MW Rabigh solar scheme.

Notably, the Al-Ghat and Waad Al-Shamal wind IPPs will be developed at world-record-low levelised electricity costs of $c1.565 a kilowatt-hour (kWh), or roughly 5.87094 halalas/kWh, and $c1.70187/kWh or 6.38201 halalas/kWh.

PIF projects

In June, three Saudi utility developers and investors signed power-purchase agreements (PPAs) with SPPC to develop and operate three solar PV projects with a combined capacity of 5,500MW.

The Haden and Muwayh solar PVs, located in Mecca, will each have a capacity of 2,000MW, while the Al-Khushaybi solar PV power plant in Qassim will be able to generate 1,500MW of electricity.

The team that will develop the three projects consists of Acwa Power, PIF-backed Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco), a subsidiary of the state majority-owned oil giant.

The project companies formed for each solar IPP have since signed financing documents for the projects, which will require a total investment of SR12.3bn ($3.3bn). The financing sought was $2.6bn.

These projects comprise round four of PIF’s Price Discovery Scheme, with Acwa Power as the preferred developer partner.

Energy storage systems

The scale of new conventional and renewable energy capacity being developed in the kingdom – some 3,500MW of solar PV and wind capacity is now online, with over 10,500MW under construction – has increased the urgency to build energy storage systems to balance the kingdom’s energy system and stabilise its grid.

SPPC has signalled plans to procure gigawatt-sized battery energy storage systems (bess) using an IPP model. The tendering process for the first bess IPP package is expected to begin by the year-end or early 2025.

In parallel, National Grid Saudi Arabia, an SEC subsidiary, has started awarding contracts to build energy storage systems capacity using an engineering, procurement and construction (EPC) model. The local Algihaz Holding is understood to have won the contracts to build four energy storage systems in Najran, Madaya and Khamis Mushait, which will have a total combined capacity of 7.8 gigawatt-hours (GWh).

Also in August, SEC tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW, or roughly 10GWh.

The planned facilities, each with a capacity of 500MW or roughly 2GWh, are located in or within the proximity of the following key cities and load centres:

  • Riyadh
  • Qaisumah
  • Dawadmi
  • Al-Jouf
  • Rabigh

Saudi Arabia’s plan to build its first large-scale nuclear power plant in Duwaiheen, which appeared to be making progress before October last year, has faced delays following shifting geopolitics involving stakeholders that include the US and Israel. The tender bid deadline for nuclear technology providers is understood to have been postponed and no new date has been set.

As it is, Saudi Arabia’s ever-expanding power projects pipeline, particularly for renewables and bess, will require investors, contractors and lenders to allocate sizeable resources, perhaps more than they have historically done in the past, over the next several years as various stakeholders endeavour to meet Vision 2030-tied peak demand scenarios.

This applies less to CCGT projects, which, pending a clear carbon-capture strategy from the offtaker or the Energy Ministry, appear to attract a decreasing number of developers and investors.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12496716/main.jpg
Jennifer Aguinaldo
Related Articles
  • Dewa receives eight bids for 132kV cable works

    11 August 2026

    Eight companies have submitted bids for a contract to supply, install, test and commission 132kV cable works serving multiple substations across Dubai.

    The tender was issued by Dubai Electricity & Water Authority (Dewa) in April.

    It covers 132kV cable works for the Autosouq, Crystal, Danaroad, Dsrtisld, Elwood, Horizion, Mesmgolf, Naseemst, Orchidst, Yfravaly and Ylysisld 132/11kV substations. The scope also includes a new 132kV cable circuit and cable shifting works.

    The bidders include:

    • Acume Electrical Engineering Services (UAE, $10.7m)
    • Sociedad Espanola de Montajes Industriales (Spain, $17.8m)
    • Danway Electricity & Mechanical Engineering (UAE, $67.6m)
    • Arar Utility Company (UAE, $71.9m)
    • Mannai Trading Company (Qatar, $91.3m)
    • AASA Middle East Contracting Company (UAE, $174.5m)
    • Centaur Electro Mechanical Contracting Company (UAE, $199.6m)
    • Saudi Modern Company for Metals, Cables & Plastic Industries (Saudi Arabia, $351.4m)
    Transmission investment

    Dewa has been accelerating investment in Dubai’s electricity transmission network to meet rising electricity demand. In July, the utility said that its investments in transmission projects had exceeded AED10bn ($2.7bn).

    Dewa is currently building 65 new 132kV substations and one 400kV substation. It plans to issue tenders for more than 30 additional 132kV substations over the next three years, alongside plans to extend 340 kilometres of underground transmission cables and construct two 400kV substations.

    In the first half of 2026, Dewa said it awarded 21 contracts for 132kV transmission substations and contracts to extend 132kV cables connecting the substations to the main network. The cable contracts cover 64km and have a combined value of AED3bn ($817m).

    The utility also commissioned eight 132kV substations with a combined conversion capacity of 1,200MVA and an investment of AED970m ($264m). The projects included 20km of transmission cables.

    Dewa said it had 402 transmission substations in operation at the end of June, with 374 substations at the 132kV level. The rest are 400kV substations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18322875/main.jpg
    Mark Dowdall
  • Adnoc Gas to move prudently on Bab gas cap project

    10 August 2026

    Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), has said it is treading cautiously towards a final investment decision (FID) on its estimated $8bn Bab gas cap development project.

    The project aims to build a gas processing plant in the Bab area, about 170 kilometres from Abu Dhabi city, along with associated pipeline networks and ancillary units, to process up to 1.85 billion cubic feet a day (cf/d) of additional raw gas once its parent company starts production from the Bab gas caps.

    “We are at an early stage when it comes to engagement with the market on Bab gas cap. At this stage, we are not in a position to discuss any of the technical or commercial aspects of the Bab gas cap project,” Fatema Al-Nuaimi, Adnoc Gas CEO, said in response to a question from MEED during a press conference on 10 August.

    Adnoc Gas has divided the engineering, procurement and construction (EPC) scope of work on the Bab gas cap development project into four main packages:

    • EPC package 1 – Main Bab gas cap plant
    • EPC package 2 – Early civil works
    • EPC package 3 – Pipelines
    • EPC package 4 – Non-process facilities and associated works package

    Adnoc Gas issued the tender for the main Bab gas cap plant on 25 June and set an initial deadline of 17 July for contractors to submit technical bids. The company then extended the technical bid submission deadline by four months until 16 November, MEED recently reported.

    Peter Van Driel, chief financial officer of Adnoc Gas, said: “There are two parts to this. You have an upstream decision and an Adnoc Gas decision.

    “Upstream [Adnoc Group] has started to develop the Bab gas cap reservoir. At Adnoc Gas, we have a funnel of opportunities. Today, we announced the FID on phases two and three of the Rich Gas Development project,” Van Driel said.

    “As part of future opportunities, we may invest in infrastructure specifically for the Bab gas cap project, and that is a pending decision,” he added.

    “We have focused our decision-making on phases two and three of the Rich Gas Development project. With all of these decisions, we do a very thorough assessment. We are not in a hurry to make these decisions. We want to ensure we have the right feed composition, competitive landscape and demand.

    “[Gas] demand in the UAE remains strong. Electricity demand, for example, grows by approximately 3% every year, and we also see a very robust demand profile for gas in export markets,” he told journalists on the call.

    Bab Gas Cap project tendering

    As part of its upstream production growth targets for 2030, Adnoc Group is working to extract gas from four underdeveloped gas cap reservoirs at the Bab onshore field – Thammama A, Thammama B, Thammama F and Thammama H. The Thammama A, B and H reservoirs are estimated to collectively produce 1.45 billion cubic feet a day (cf/d) of gas, while output from the Thammama F gas cap is expected to reach 396 million cf/d.

    Existing trains at the Habshan processing complex in Abu Dhabi will be unable to handle the new gas volumes. Adnoc Gas is therefore required to build new facilities to process up to 1.85 billion cf/d of additional raw gas when its parent company starts production from the Bab gas caps.

    Abu Dhabi Securities Exchange-listed Adnoc Gas issued an expression of interest (EoI) to contractors for the main EPC tendering process for the Bab gas cap plant on 10 February. The company set an initial EoI submission deadline of 17 February, which it later extended to 20 February. Contractors submitted responses by that date, MEED reported.

    Following completion of the prequalification phase, contractors that expressed interest formed the following teams to compete in the main contract tendering round, according to sources:

    • Larsen & Toubro Energy Hydrocarbon (India) + Samsung E&A (South Korea)
    • Saipem (Italy) + NMDC Energy (UAE)
    • Technip Energies (France) + JGC Corporation (Japan) + Sinopec (China)
    • Tecnimont (Italy) + China Petroleum Engineering and Construction Corporation (CPECC)

    The other three packages are also in the main contract tendering stages, sources have said. Separately, another Adnoc Group subsidiary, Adnoc Onshore, is preparing to issue the main tender for a project involving the tie-in of gas-producing and injection wells at the gas cap reservoirs of Abu Dhabi’s onshore Bab field, which forms part of the wider integrated Bab gas cap development programme.

    Prior to issuing the EoIs for the Bab gas cap development project packages, Adnoc Gas completed an early engagement process with contractors in September and October last year, as MEED previously reported.

    In December last year, Adnoc Gas awarded the front-end engineering and design (feed) works for the Bab gas cap development project – which will increase its gas processing capacity by about 20% – to Australia-based consultancy Worley. The feed contract covers more than 1.2 million man-hours, making it the largest engineering job awarded by Adnoc Gas to date.

    Bab Gas Cap concession

    In addition to Adnoc Gas overseeing the main EPC tendering exercise for the gas processing plant, Abu Dhabi’s Supreme Council for Financial and Economic Affairs (SCFEA) awarded concession agreements in June for the development and production of the Bab gas cap reserve in the emirate.

    Adnoc will hold the majority 60% participating interest in the concession. The remaining stakes will be held by France’s TotalEnergies (10%), the UK’s BP (10%), China National Petroleum Corporation (CNPC) International (8%), Japan Oil Development Company (Jodco) Onshore (5%), China ZhenHua Oil (4%) and Korea GS E&P (3%).

    According to SCFEA, the Bab gas cap development and production concession represents the largest gas cap development project of its kind globally, the Abu Dhabi Media Office said in a report.

    A gas cap refers to the free natural gas that sits above an underlying oil reservoir — in this case, the giant Bab onshore oil field in Abu Dhabi.

    The project, operated by Adnoc Onshore, is expected to have a production capacity of approximately 1.5 billion cf/d of natural gas, equivalent to about 15% of Adnoc Gas’ total operational gas processing capacity.

    “This underscores the strategic significance of the project, which is expected to contribute to the UAE’s gas self-sufficiency, support the continued development of the country’s petrochemicals sector and advance Adnoc’s plans to expand its liquefied natural gas export capacity,” the Abu Dhabi Media Office said in its report.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18281827/main4640.jpg
    Indrajit Sen
  • Adnoc Gas reaffirms $28bn capex for 2026-30

    10 August 2026

    Register for MEED’s 14-day trial access 

    Adnoc Gas, the gas processing subsidiary of Abu Dhabi National Oil Company (Adnoc Group), has announced it is executing a capital expenditure (capex) budget of $28bn for 2026 to 2030, reaffirming the spending plan it previously committed to for the period.

    As part of that capex plan, Adnoc Gas said it achieved final investment decision (FID) on the second and third phases of its Rich Gas Development (RGD) programme earlier this year.

    The company awarded $8.2bn of engineering, procurement and construction (EPC) contracts for the second and third phases of the RGD programme. These relate to the construction of a new gas processing train at the Habshan complex and a natural gas liquids (NGL) fractionation train at the Ruwais gas processing facility, respectively.

    MEED reported in March that Adnoc Gas had selected the main EPC contractors for both the Habshan 7 gas processing train and the Ruwais NGL Train 5 projects.

    Adnoc Gas officially announced the award of EPC contracts for the two projects, saying it awarded China-based Wison Engineering a $3.9bn contract for RGD phase 2, while Italy’s Tecnimont was selected for the $4.3bn third phase.

    Phase 2 will add a new natural gas processing train at the Habshan facility, “expanding Adnoc Gas’ natural gas processing capacity, enhancing operational flexibility, and supporting the UAE’s expanding downstream and petrochemical sectors”, the company said in a statement.

    Phase 3 will add a new NGL fractionation train at Ruwais, “increasing the recovery of higher-value liquids from rich natural gas for export, strengthening Adnoc Gas’ global customer portfolio”, it said in its statement on 10 August.

    Adnoc Gas also reiterated its $5bn capex for the first phase of the RGD scheme, which is under construction. The company awarded $5bn of engineering, procurement and construction management contracts in three tranches for phase 1 of the RGD in June last year, marking the company’s largest-ever capital investment.

    With all three phases combined, Adnoc Gas has made a total investment of $13.2bn in the RGD programme.

    “We continued investing through the cycle and advancing megaprojects that will define the next phase of Adnoc Gas’ growth, expanding our processing capacity and product volumes,” the company’s CEO, Fatema Al-Nuaimi, said.

    “Together with Ruwais LNG and our wider portfolio of strategic projects, we are executing one of the industry’s most ambitious gas growth programmes,” she said.

    Al-Nuaimi added: “These investments support our upgraded target of 60% [earnings before interest, taxes, depreciation and amortisation] Ebitda growth by 2030, which was previously 40%. Delivering that ambition will see us invest approximately $28bn between 2026 and 2030.

    “We’re able to make these investments because we’re in a strong financial position. What matters here is this: we are reaffirming our dividend policy, we fund this growth programme and we deliver returns to shareholders. That is not an either/or,” she said.

    Second-quarter financial results

    Adnoc Gas detailed its capex plan as part of a media roundtable to discuss its financial results for the second quarter of the year (Q2 2026).

    The company achieved net income of $665m in Q2 2026 – above the upper end of the $400m-$600m guidance range provided in the first quarter – “reflecting strong operational performance in a challenging operating environment. This was supported by resilient margins in the domestic gas business”.

    Supported by its cash flow from operations, the company’s board has approved a quarterly dividend of $940m, payable in September, in line with its commitment to deliver annual dividend growth of 5% through 2030.

    Adnoc Gas remains the largest dividend payer on the Abu Dhabi Securities Exchange (ADX), where it listed in March 2023.

    Additionally, the company said: “Continued disruption to maritime movements through the Strait of Hormuz affected product liftings during the second quarter. Through proactive inventory, logistics and supply-chain management, Adnoc Gas worked closely with customers and partners to mitigate the impact of these disruptions, manage temporary constraints and fulfil commitments wherever possible.”

    For Q3 2026, Adnoc Gas said it expects profit in the range of $600m to $800m, “based on the assumption that maritime routes through the Strait of Hormuz continue to be disrupted”.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18268452/main.jpg
    Indrajit Sen
  • Chinese contractor wins Morocco solar plant deal

    10 August 2026

    China Harbour Engineering Company (CHEC), a subsidiary of China Communications Construction Company (CCCC), has won a contract to build a solar photovoltaic (PV) power plant in Fez in northern Morocco.

    Known as GreenPower Morocco 4 (GPM4), the project is being developed by Moroccan company GPM Holding through its utility-scale solar subsidiary GPM Parks.

    The project covers engineering design, equipment procurement and installation, construction of an operation and maintenance building, grid connection and commissioning. It also includes upgrades to the associated substation.

    According to CHEC, the completed plant will supply electricity to the local grid, although it did not disclose the project’s capacity or contract value. 

    The project is being developed under Law 13-09, which provides Morocco’s framework for private renewable energy generation.

    According to its website, GPM Holding is also developing another solar PV project called GreenPower Morocco 2 (GPM2). This follows the completion of its first solar project, the 34MW project (GPM1) commissioned in Tangier in 2024. 

    GPM1 was developed by Green Power Morocco, a special purpose vehicle owned by GPM Holding and UAE-based Amea Power. The $30m project covers 75 hectares and includes 91,000 PV panels. It is expected to generate about 66,149MWh a year.

    The project has a 25-year power purchase agreement in place with Amendis, a subsidiary of Veolia Morocco. PowerChina was the main engineering, procurement and construction (EPC) contractor.

    Chinese contractors have previously been involved in other projects in Morocco’s renewable energy sector.

    Shandong Electric Power Construction Company (Sepco 3), a subsidiary of PowerChina, was part of the EPC consortium for the 200MW Noor 2 concentrated solar plants and 150MW Noor 3 concentrated solar power projects at the Noor Ouarzazate complex.

    New contract awards have been limited in Morocco in 2026, although six solar PV plants are now in the execution stage under phases one and two of the 305MW Noor Atlas solar PV programme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18263680/main.jpg
    Mark Dowdall
  • Aramco puts out fire at Jizan refinery after Houthi strike

    10 August 2026

    Saudi Aramco said it had extinguished a fire that broke out at its Jizan refinery on Saudi Arabia’s Red Sea coast after the facility was hit in drone strikes by Yemen-based Houthi rebels on 9 August.

    The kingdom’s Ministry of Energy said the fire occurred at an Aramco refinery facility in Jizan and that emergency authorities had completed the necessary procedures to deal with the incident.

    The energy ministry did not say what started the fire, saying only that the incident caused no injuries.

    The Houthi rebels later claimed responsibility for the attack.

    The province of Jizan lies close to Saudi Arabia’s border with Yemen and has repeatedly been targeted by the Houthis in attacks on the kingdom’s energy infrastructure.

    The strike on the Jizan refinery was the second attack on the facility by the Houthis in as many weeks. Aramco shut the refinery on 27 July following a similar drone strike, which, according to media reports, damaged the integrated gasification combined-cycle unit and tank farm at the complex.

    On a call with investors to discuss Aramco’s second-quarter results, CEO Amin Nasser said recent attacks on the company’s facilities in the world’s top oil-exporting country had caused some disruption to production, but that he was confident operations could be restored quickly. He said the attacks had had no material operational or financial impact.

    Jizan refinery complex

    Saudi Aramco’s sprawling Jizan refinery complex entered operations in 2021.

    Aramco undertook the estimated $16bn-plus project in late 2010. The scheme consists of a refinery with an output capacity of 400,000 barrels a day (b/d), a major marine terminal and a 4GW combined-cycle power plant in Baish, in Saudi Arabia’s southwestern Jizan region.

    The Jizan refinery covers an area of 12 square kilometres. The complex processes Arabian Heavy and Arabian Medium crude grades to produce 80 million b/d of gasoline, 250 million b/d of diesel and more than 1 million tonnes a year of petrochemical products such as benzene and paraxylene.

    A multiple-pier marine terminal supports the supply of crude oil from oil fields located mainly in the kingdom’s Eastern Province to the refinery, as well as the export of surplus refined products to overseas markets. The terminal has been designed to accommodate very large crude carriers.

    A 4,000MW combined-cycle power plant uses approximately 90,000 b/d of vacuum residue from the refinery to generate electricity, hydrogen and water for the refinery, while conveying excess power to the national grid.

    The hydrocracker unit comprises two parallel trains with a combined capacity of 54,500 b/d. The diesel hydrotreater plant comprises two trains, each with a capacity of 87,500 b/d.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18262347/main.jpg
    Indrajit Sen