Saudi Arabia’s power sector motors on

11 September 2024

 

Saudi Arabia’s power sector has sustained its project activity momentum over the past six months.

The principal buyer, Saudi Power Procurement Company (SPPC), awarded the contracts to develop two publicly-tendered wind independent power producer (IPP) projects, with a total combined capacity of 1,100MW, under the fourth round of the kingdom’s National Renewable Energy Programme (NREP).

The Public Investment Fund (PIF), responsible for procuring through direct negotiations 70% of the kingdom’s 2030 target renewable energy capacity, let three large-scale solar photovoltaic (PV) projects with a total combined capacity of around 5,500MW.

State majority-owned Saudi Aramco also awarded a contract to develop an independent cogeneration project with an electricity generation capacity of 475MW.

During the same period, SPPC began the tendering process for two combined-cycle gas turbine (CCGT) projects, the Remah and Nairiyah IPPs, each with a capacity of 3,600MW, and for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round.

“It has been a very busy summer,” notes a senior executive with an international utility developer, referring to the submission of bids in August for the contracts to develop the Remah 1 & 2, Nairiyah 1 & 2, and the NREP round-five solar PV schemes.

Notably, the principal buyer has initiated the selection process for consultants who will advise on its next pair of independent CCGT power plants – the 2,400MW Al-Rais and the 3,600MW Riyadh 16 projects.

Saudi Electricity Company (SEC) and SPPC are also understood to be conducting bilateral talks for the development of five CCGT power plants, which, along with those currently being built or tendered, support the kingdom’s mandate to replace fleets running on liquid fuel.

Essentially, the reported SEC projects, each with a capacity of 1,500MW-2,000MW, bear some similarities to PIF’s directly negotiated renewable energy schemes.

These projects help substantiate previous reports that SEC has been seeking to lock in gas turbine equipment deals with a total capacity of 30GW, in line with an overall capacity expansion plan within and outside Saudi Arabia.

The next few years can only get busier, with Saudi Arabia's Energy Minister, Prince Abdulaziz Bin Salman Bin Abdulaziz Al-Saud, confirming in June plans to tender 20,000MW of renewable energy projects annually starting this year, in line with reaching 100GW-130GW of installed capacity by 2030, "depending on electricity demand growth".

This represents a major upward revision to the official 2030 renewable energy capacity target of 58,700MW.

However, it is unclear if this new target considers the renewable capacity that will be installed to power Neom, Saudi Arabia’s largest gigaproject, as well as the requirement of green hydrogen projects that the PIF plans to codevelop.

Wind IPPs

In May, SPPC awarded a team led by Japanese utility developer Marubeni Corporation the contracts to develop the 600MW Al-Ghat wind and 700MW Waad Al-Shamal wind IPPs.

The team of Marubeni and its partner, the local Alajlan Brothers, is also expected to win the contract to develop the 700MW Yanbu wind IPP, the final wind scheme included in NREP’s round four.

These are important awards for Marubeni, which last won an IPP contract in Saudi Arabia in 2021 for the 300MW Rabigh solar scheme.

Notably, the Al-Ghat and Waad Al-Shamal wind IPPs will be developed at world-record-low levelised electricity costs of $c1.565 a kilowatt-hour (kWh), or roughly 5.87094 halalas/kWh, and $c1.70187/kWh or 6.38201 halalas/kWh.

PIF projects

In June, three Saudi utility developers and investors signed power-purchase agreements (PPAs) with SPPC to develop and operate three solar PV projects with a combined capacity of 5,500MW.

The Haden and Muwayh solar PVs, located in Mecca, will each have a capacity of 2,000MW, while the Al-Khushaybi solar PV power plant in Qassim will be able to generate 1,500MW of electricity.

The team that will develop the three projects consists of Acwa Power, PIF-backed Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco), a subsidiary of the state majority-owned oil giant.

The project companies formed for each solar IPP have since signed financing documents for the projects, which will require a total investment of SR12.3bn ($3.3bn). The financing sought was $2.6bn.

These projects comprise round four of PIF’s Price Discovery Scheme, with Acwa Power as the preferred developer partner.

Energy storage systems

The scale of new conventional and renewable energy capacity being developed in the kingdom – some 3,500MW of solar PV and wind capacity is now online, with over 10,500MW under construction – has increased the urgency to build energy storage systems to balance the kingdom’s energy system and stabilise its grid.

SPPC has signalled plans to procure gigawatt-sized battery energy storage systems (bess) using an IPP model. The tendering process for the first bess IPP package is expected to begin by the year-end or early 2025.

In parallel, National Grid Saudi Arabia, an SEC subsidiary, has started awarding contracts to build energy storage systems capacity using an engineering, procurement and construction (EPC) model. The local Algihaz Holding is understood to have won the contracts to build four energy storage systems in Najran, Madaya and Khamis Mushait, which will have a total combined capacity of 7.8 gigawatt-hours (GWh).

Also in August, SEC tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW, or roughly 10GWh.

The planned facilities, each with a capacity of 500MW or roughly 2GWh, are located in or within the proximity of the following key cities and load centres:

  • Riyadh
  • Qaisumah
  • Dawadmi
  • Al-Jouf
  • Rabigh

Saudi Arabia’s plan to build its first large-scale nuclear power plant in Duwaiheen, which appeared to be making progress before October last year, has faced delays following shifting geopolitics involving stakeholders that include the US and Israel. The tender bid deadline for nuclear technology providers is understood to have been postponed and no new date has been set.

As it is, Saudi Arabia’s ever-expanding power projects pipeline, particularly for renewables and bess, will require investors, contractors and lenders to allocate sizeable resources, perhaps more than they have historically done in the past, over the next several years as various stakeholders endeavour to meet Vision 2030-tied peak demand scenarios.

This applies less to CCGT projects, which, pending a clear carbon-capture strategy from the offtaker or the Energy Ministry, appear to attract a decreasing number of developers and investors.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12496716/main.jpg
Jennifer Aguinaldo
Related Articles
  • Jordan sets market briefing for Amman water PPP

    10 April 2026

    Jordan’s Ministry of Investment, through its Public-Private Partnership Unit (PPPU), has announced a public information session for the South Amman non-revenue water (NRW) reduction PPP project.

    The session will be held on 15 April and is being organised in collaboration with the Ministry of Water & Irrigation and Miyahuna, according to a notice published by the PPPU. 

    The project covers the southern and southeastern areas of Amman and aims to reduce water losses and improve the efficiency of the capital’s distribution network.

    According to the ministry, the scheme will serve about 1.4 million people across 17 zones and forms part of Jordan’s wider National Water Strategy. 

    The planned market briefing is intended to provide early detail on the project’s PPP structure, procurement pathway and performance-based contracting model.

    It is also expected to outline the project’s risk allocation and bankability framework to prospective investors, operators and infrastructure companies.

    The Ministry of Investment opened prequalification for the scheme in March.

    Qualified companies and consortiums have been invited to participate in a two-stage procurement process for the performance-based contract. 

    The project aims to reduce NRW levels to 25% by 2040, while modernising and expanding the existing network using smart technologies and advanced leak detection systems. 

    The original deadline was 23 April. That has since been extended to 12 May.

    Jordan is among the most water-scarce countries in the world, and losses from distribution networks are estimated to account for about 45% of water supplied.

    The country is also advancing its $6bn Aqaba-Amman water desalination and conveyance project that aims to meet about 40% of Jordan’s municipal water demand by 2040.

    As MEED recently reported, the project is nearing financial close. Once complete, it will supply about 300 million cubic metres of potable water a year from the Red Sea to Amman and other regions.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16340931/main.jpg
    Mark Dowdall
  • OQ allows more time for natural gas liquids project proposals

    10 April 2026

     

    Omani state energy conglomerate OQ Group has allowed contractors more time to prepare proposals for a major project to build a natural gas liquids (NGL) facility in the sultanate.

    The planned NGL facility will extract condensates in Saih Nihayda in central Oman and transport those volumes to Duqm, located along the sultanate’s Arabian Sea coastline, for fractionation and export, OQ Group has said.

    OQ Group intends to deliver the project using a front-end engineering and design (feed)-to-engineering, procurement and construction (EPC) competition model.

    The state enterprise issued the main tender for the feed-to-EPC competition “earlier in March”, setting an initial deadline of 8 April for contractors to submit proposals, MEED previously reported. The deadline has now been extended to 6 May, according to sources.

    MEED previously reported that OQ had started the prequalification process for the feed-to-EPC contest for the planned NGL project in November last year, with contractors submitting responses by 15 December.

    The following contractors, among others, are understood to have been invited to participate in the feed-to-EPC contest for OQ’s planned NGL project, sources told MEED:

    • Chiyoda (Japan) / CTCI (Taiwan)
    • G S Engineering & Construction (South Korea)
    • Hyundai Engineering & Construction (South Korea) / KBR (US)
    • JGC Corporation (Japan)
    • Kent (UAE)
    • Petrofac (UK)
    • Saipem (Italy)
    • Samsung E&A (South Korea) / Larsen & Toubro Energy Hydrocarbon (India) / Wood (UAE)
    • Technip Energies (France)
    • Tecnicas Reunidas (Spain)
    • Tecnimont (Italy)

    The scope of work on the project covers the development, verification and integration of feed deliverables for the following facilities and systems:

    • NGL extraction facility – Saih Nihayda:
      • Verification and updating of the existing feed to enable dual-mode operation (ethane recovery and ethane rejection).
      • Identification and implementation of required process, equipment, utilities, and control system modifications.
         
    • NGL Pipeline – Saih Nihayda to Duqm:
      Feed for a new approximately 230km NGL transmission pipeline, including routing, hydraulics, stations, pigging facilities, metering, corrosion protection, leak detection, and safety systems.
       
    • Fractionation unit at Duqm:
      • Feed for a new fractionation facility to process ethane and propane + NGL and recover propane, butane, condensate, and provision for future ethane recovery.
      • Design accommodating licensed or open-art technology and future tie-in to a planned petrochemical project in Duqm.
         
    • Product pipelines, storage and export facilities at Duqm jetty:
      • Feed for product pipelines, cryogenic and atmospheric storage tanks, vapour recovery systems, marine loading arms, and export facilities.
      • Integration with existing port and refinery infrastructure, where feasible.
         
    • Supporting systems and studies:
      Utilities, offsites, flare systems, safety and environmental studies, cost estimates (class 2+10%), project schedules, constructability assessments, and EPC tender documentation.
    Natural gas liquids projects

    Gulf national oil companies have been allocating significant capital expenditure to building or expanding NGL production facilities.

    QatarEnergy, in September last year, awarded the main EPC contract for its project to add a fifth NGL train at its fractionation complex in Qatar’s Mesaieed Industrial City. The aim of the project, which is estimated to be worth $2.5bn, is to build a fifth NGL train (NGL-5) with the capacity to process up to 350 million cubic feet a day of rich associated gas from QatarEnergy’s offshore and onshore oil fields.

    The main EPC contract for the QatarEnergy NGL-5 project was won by a consortium of India’s Larsen & Toubro Energy Hydrocarbons Onshore and Greece-headquartered Consolidated Contractors Group.

    Separately, the gas processing business of Abu Dhabi National Oil Company (Adnoc Gas) has also selected the main contractor for a project to install a fifth NGL fractionation train at its Ruwais gas processing facility in Abu Dhabi.

    The fifth NGL fractionation train will have an output capacity of 22,000 tonnes a day, or about 8 million tonnes a year.

    The Ruwais NGL Train 5 project represents the second phase of Adnoc Gas’ ambitious Rich Gas Development (RGD) programme, and its budget value is estimated to be around $4bn, Peter Van Driel, Adnoc Gas’ chief financial officer, confirmed in February. The company expects to achieve final investment decision on the project within the first quarter of 2026, Van Driel said at the time.

    ALSO READ: PDO awards Oman gas plant expansion project
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16340039/main5958.jpg
    Indrajit Sen
  • Masdar’s move abroad will not be the last

    10 April 2026

    Commentary
    Mark Dowdall
    Power & water editor

    Masdar’s new joint-venture agreement with France’s TotalEnergies will not be the last time we see regional energy investors use strong balance sheets and domestic growth to build larger positions overseas.

    For Masdar in particular, the deal broadens its international exposure at a time when investors are asking questions about the Middle East’s geopolitical risk.

    By combining portfolios, the two companies start with 3GW of operational capacity and another 6GW in advanced development.

    The deal covers nine Asian countries, reflecting a prudent strategy that spreads capital across markets with different risk profiles and growth trajectories.

    In Kazakhstan, which already includes 2.6GW of assets under development, there is clear logic behind this move.

    The country is expected to see a significant increase in renewable generation over the next decade, supported by strong wind resources and the availability of large land areas for utility-scale developments.

    There is also a practical advantage in partnering with TotalEnergies, which already has project delivery experience and an established presence in several of these markets.

    The US-Iran ceasefire announced on 8 April has brought some respite to energy infrastructure stakeholders in the region.

    For investors and developers, however, the long-term uncertainty remains. Until there is clear evidence of regime change, the removal of sanctions or lasting peace in the region, the outlook will be less clear.

    With uncertainty one of the biggest killers of investor confidence, many will now be looking at this agreement and thinking whether they should also follow suit.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16340038/main.jpg
    Mark Dowdall
  • Turkish firm launches Mecca villas project

    10 April 2026

    Register for MEED’s 14-day trial access 

    Turkish real estate investment firm Emlak Konut has announced the launch of Hayat Makkah, its first development in Saudi Arabia.

    The project is part of the National Housing Company’s (NHC) wider Mecca Gate masterplan.

    According to the company, Hayat Makkah will feature 1,014 villas, with home sizes ranging from 150 to 5,000 square metres.

    NHC and Emlak Konut signed an investment agreement worth over SR1bn ($266m) in November last year to develop the project.

    The agreement was signed on the sidelines of the Cityscape Global 2025 event in Riyadh.

    Ertan Keles, chairman of Emlak Konut, said the firm is in talks with stakeholders about launching a second project, while a third development is also being lined up in Jeddah.

    GlobalData expects the Saudi Arabian construction industry to grow by 3.6% in real terms in 2026, supported by an increase in foreign direct investment (FDI) and investments in the housing and manufacturing sectors.

    The residential construction sector is expected to grow by 3.8% in real terms in 2026 and register an average annual growth rate of 4.7% between 2027 and 2030, supported by the country’s aim – under Saudi Vision 2030 – to increase homeownership from 65.4% in 2024 to 70% by 2030, including by building 600,000 homes by 2030.

    According to the General Authority for Statistics, Saudi Arabia attracted a net FDI inflow of SR72.3bn ($19.3bn) in the first nine months of 2025, an increase of 32.7% year-on-year (YoY) compared to the same period in 2024.

    Similarly, the total value of real estate loans from banks grew by 11.5% YoY in 2025, preceded by an annual growth of 13.3% in 2024, according to the Saudi Central Bank (Sama).


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16340004/main.png
    Yasir Iqbal
  • Kuwait gives bidders more time for Al-Khairan IWPP

    10 April 2026

     

    Kuwait has extended bidding for the first phase of the Al-Khairan independent water and power producer (IWPP) project.

    The project is being procured by the Kuwait Authority for Partnership Projects (Kapp) and the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant.

    The new deadline is 30 April. The original deadline was 31 March.

    The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate.

    These include:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) / Jera (Japan)
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)
    • China Power / Malakoff International (Malaysia) / Abdul Aziz Al-Ajlan Sons (Saudi Arabia)
    • Nebras Power (Qatar)                                                                                                                                        
    • Sumitomo Corporation (Japan)

    The Al-Khairan IWPP project is part of Kuwait’s long-term plan to expand power and water production capacity through public-private partnerships (PPPs).

    The winning bidder will sign a set of PPP agreements covering financing, design, construction, operation and transfer of the project.

    The energy conversion and water purchase agreement is expected to cover a 25-year supply period.

    Kapp extended another deadline recently for a contract to develop zone two of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    The PPP authority is procuring the 500MW solar photovoltaic independent power project (IPP) in partnership with the ministry.

    The bid submission deadline was moved to the end of April, a source close to the project told MEED.

    According to the MEWRE, the total generation capacity currently offered under partnership projects has reached 6,100MW, equivalent to about 30% of Kuwait’s existing power capacity.

    The ministry and Kapp are also preparing to tender the main contract for the 3,600MW Nuwaiseeb power and water desalination plant after plans were approved by Kuwait’s Council of Ministers last November.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16339960/main.jpg
    Mark Dowdall