Saudi Arabia’s power sector motors on
11 September 2024

Saudi Arabia’s power sector has sustained its project activity momentum over the past six months.
The principal buyer, Saudi Power Procurement Company (SPPC), awarded the contracts to develop two publicly-tendered wind independent power producer (IPP) projects, with a total combined capacity of 1,100MW, under the fourth round of the kingdom’s National Renewable Energy Programme (NREP).
The Public Investment Fund (PIF), responsible for procuring through direct negotiations 70% of the kingdom’s 2030 target renewable energy capacity, let three large-scale solar photovoltaic (PV) projects with a total combined capacity of around 5,500MW.
State majority-owned Saudi Aramco also awarded a contract to develop an independent cogeneration project with an electricity generation capacity of 475MW.
During the same period, SPPC began the tendering process for two combined-cycle gas turbine (CCGT) projects, the Remah and Nairiyah IPPs, each with a capacity of 3,600MW, and for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round.
“It has been a very busy summer,” notes a senior executive with an international utility developer, referring to the submission of bids in August for the contracts to develop the Remah 1 & 2, Nairiyah 1 & 2, and the NREP round-five solar PV schemes.
Notably, the principal buyer has initiated the selection process for consultants who will advise on its next pair of independent CCGT power plants – the 2,400MW Al-Rais and the 3,600MW Riyadh 16 projects.
Saudi Electricity Company (SEC) and SPPC are also understood to be conducting bilateral talks for the development of five CCGT power plants, which, along with those currently being built or tendered, support the kingdom’s mandate to replace fleets running on liquid fuel.
Essentially, the reported SEC projects, each with a capacity of 1,500MW-2,000MW, bear some similarities to PIF’s directly negotiated renewable energy schemes.
These projects help substantiate previous reports that SEC has been seeking to lock in gas turbine equipment deals with a total capacity of 30GW, in line with an overall capacity expansion plan within and outside Saudi Arabia.
The next few years can only get busier, with Saudi Arabia's Energy Minister, Prince Abdulaziz Bin Salman Bin Abdulaziz Al-Saud, confirming in June plans to tender 20,000MW of renewable energy projects annually starting this year, in line with reaching 100GW-130GW of installed capacity by 2030, "depending on electricity demand growth".
This represents a major upward revision to the official 2030 renewable energy capacity target of 58,700MW.
However, it is unclear if this new target considers the renewable capacity that will be installed to power Neom, Saudi Arabia’s largest gigaproject, as well as the requirement of green hydrogen projects that the PIF plans to codevelop.
Wind IPPs
In May, SPPC awarded a team led by Japanese utility developer Marubeni Corporation the contracts to develop the 600MW Al-Ghat wind and 700MW Waad Al-Shamal wind IPPs.
The team of Marubeni and its partner, the local Alajlan Brothers, is also expected to win the contract to develop the 700MW Yanbu wind IPP, the final wind scheme included in NREP’s round four.
These are important awards for Marubeni, which last won an IPP contract in Saudi Arabia in 2021 for the 300MW Rabigh solar scheme.
Notably, the Al-Ghat and Waad Al-Shamal wind IPPs will be developed at world-record-low levelised electricity costs of $c1.565 a kilowatt-hour (kWh), or roughly 5.87094 halalas/kWh, and $c1.70187/kWh or 6.38201 halalas/kWh.
PIF projects
In June, three Saudi utility developers and investors signed power-purchase agreements (PPAs) with SPPC to develop and operate three solar PV projects with a combined capacity of 5,500MW.
The Haden and Muwayh solar PVs, located in Mecca, will each have a capacity of 2,000MW, while the Al-Khushaybi solar PV power plant in Qassim will be able to generate 1,500MW of electricity.
The team that will develop the three projects consists of Acwa Power, PIF-backed Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco), a subsidiary of the state majority-owned oil giant.
The project companies formed for each solar IPP have since signed financing documents for the projects, which will require a total investment of SR12.3bn ($3.3bn). The financing sought was $2.6bn.
These projects comprise round four of PIF’s Price Discovery Scheme, with Acwa Power as the preferred developer partner.
Energy storage systems
The scale of new conventional and renewable energy capacity being developed in the kingdom – some 3,500MW of solar PV and wind capacity is now online, with over 10,500MW under construction – has increased the urgency to build energy storage systems to balance the kingdom’s energy system and stabilise its grid.
SPPC has signalled plans to procure gigawatt-sized battery energy storage systems (bess) using an IPP model. The tendering process for the first bess IPP package is expected to begin by the year-end or early 2025.
In parallel, National Grid Saudi Arabia, an SEC subsidiary, has started awarding contracts to build energy storage systems capacity using an engineering, procurement and construction (EPC) model. The local Algihaz Holding is understood to have won the contracts to build four energy storage systems in Najran, Madaya and Khamis Mushait, which will have a total combined capacity of 7.8 gigawatt-hours (GWh).
Also in August, SEC tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW, or roughly 10GWh.
The planned facilities, each with a capacity of 500MW or roughly 2GWh, are located in or within the proximity of the following key cities and load centres:
- Riyadh
- Qaisumah
- Dawadmi
- Al-Jouf
- Rabigh
Saudi Arabia’s plan to build its first large-scale nuclear power plant in Duwaiheen, which appeared to be making progress before October last year, has faced delays following shifting geopolitics involving stakeholders that include the US and Israel. The tender bid deadline for nuclear technology providers is understood to have been postponed and no new date has been set.
As it is, Saudi Arabia’s ever-expanding power projects pipeline, particularly for renewables and bess, will require investors, contractors and lenders to allocate sizeable resources, perhaps more than they have historically done in the past, over the next several years as various stakeholders endeavour to meet Vision 2030-tied peak demand scenarios.
This applies less to CCGT projects, which, pending a clear carbon-capture strategy from the offtaker or the Energy Ministry, appear to attract a decreasing number of developers and investors.
Exclusive from Meed
-
L&T announces major contract win from Adnoc Offshore4 August 2026
-
Masdar renews $300m revolving credit facility4 August 2026
-
Jordan awards EPC contract for Maan wind farm4 August 2026
-
Chinese contractor wins Saudi power and gas contracts4 August 2026
-
Contractors submit bids for key Aramco offshore tenders4 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
L&T announces major contract win from Adnoc Offshore4 August 2026
Indian contractor Larsen & Toubro (L&T) has announced that it has been awarded a major contract by the offshore business of Abu Dhabi National Oil Company (Adnoc Offshore).
Mumbai-headquartered L&T described the order as “ultra-mega”, a term the company uses for contracts valued at more than INR150bn ($1.57bn).
The project will be executed through a consortium, with its subsidiary LTEH Offshore serving as the lead partner, L&T said in a statement on 4 August.
MEED understands that the contract won by L&T relates to an offshore package that forms part of a major Adnoc Offshore project to produce up to 600 million cubic feet a day (cf/d) of natural gas by developing the Umm Shaif gas cap in Abu Dhabi.
L&T won the first offshore package of the Umm Shaif gas cap and surface pressure boosting project in a consortium with Saudi Arabia/UAE-based Lamprell, MEED reported in July.
The following contractors have secured the two offshore packages and one onshore package of the Umm Shaif gas cap project, MEED previously reported:
- First offshore package – fabrication of a 30,000-tonne gas compression system: Larsen & Toubro Energy Hydrocarbon (India) / Lamprell (Saudi Arabia/UAE)
- Second offshore package – fabrication of another 30,000-tonne gas compression system: McDermott (US)
- Onshore package – EPC of gas inlet and processing systems on Das Island: China Petroleum Engineering & Construction Company (CPECC)
“The project involves the development of multiple offshore facilities. As the lead consortium partner, LTEH Offshore will execute the major share of the project scope, covering engineering, procurement, construction, installation and commissioning (EPCIC) of the offshore facilities, in addition to the upgrade of existing facilities,” L&T said in its statement.
“A significant portion of the fabrication work will be undertaken at L&T’s state-of-the-art fabrication yards, leveraging the company’s integrated EPCIC capabilities and extensive track record in delivering large and complex offshore developments across the region,” the Bombay Stock Exchange-listed company added.
Umm Shaif gas cap project
Adnoc Offshore operates the Umm Shaif hydrocarbons development, which is located 150 kilometres (km) northwest of the city of Abu Dhabi. The field is located within Abu Dhabi’s offshore Umm Shaif and Nasr hydrocarbons concession, previously operated by former Adnoc Group companies Adma-Opco and Zadco.
In March and April 2018, Abu Dhabi’s Supreme Council for Financial and Economic Affairs (SCFEA) awarded a 10% stake in the Umm Shaif and Nasr offshore block to Italy’s Eni, 20% to France’s TotalEnergies and 10% to China National Petroleum Corporation (CNPC). Adnoc Group retained the majority 60% interest. The operators produce a total of about 460,000 b/d of oil from the Umm Shaif and Nasr block.
Adnoc, along with its foreign partners, announced achieving a final investment decision (FID) worth $6.2bn on the Umm Shaif gas cap project on 21 July. The FID includes three EPC packages totalling $5.1bn for large-scale offshore infrastructure, “awarded to consortiums comprising major UAE and international contractors,” the state enterprise said without disclosing the contractors it had selected or the scope of work on the packages.
Adnoc added that, as part of the FID, it has also awarded a $365m contract to its subsidiary Adnoc Drilling for a 14-well drilling and integrated drilling services scope, to be delivered over 18 months using three existing rigs.
Production from the development is expected by 2030, the Abu Dhabi energy giant said.
The primary objective of the Umm Shaif gas cap and surface pressure boosting project is to increase gas production by 550 million cubic feet a day (cf/d) and raise associated condensate output by 50,000 barrels a day (b/d).
Adnoc Offshore intends to feed about 520 million cf/d of the additional produced gas into Adnoc Group’s sales gas grid.
Adnoc Offshore is understood to have issued the main EPC tender for the Umm Shaif gas cap and surface pressure boosting project in the first quarter of 2025.
Contractors submitted technical bids for the three EPC packages by the 30 October deadline last year, while commercial bids were submitted by the deadline of 2 February this year.
The following contractors are among those understood to have been bidding for the three EPC packages, according to sources:
Offshore package 1:
- Saipem (Italy) / Seatrium (Singapore)
- Larsen & Toubro Energy Hydrocarbon (India) / Lamprell (Saudi Arabia/UAE)
- NMDC Energy (UAE) / Hyundai Heavy Industries (South Korea)
Offshore package 2:
- China Offshore Oil Engineering Company (COOEC)
- McDermott (US)
- Larsen & Toubro Energy Hydrocarbon (India) / Lamprell (Saudi Arabia/UAE)
- NMDC Energy (UAE) / Hyundai Heavy Industries (South Korea)
Onshore package:
- Archirodon (Greece)
- China Petroleum Engineering & Construction Company (CPECC)
- Engineering for the Petroleum & Process Industries (Enppi; Egypt)
- Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
- Target Engineering Construction Company (UAE)
Australian firm Worley has performed front-end engineering and design (feed) work on the project.
Gas is produced from the Umm Shaif Khuff and Uweinat reservoirs, as well as from the Arab C and Arab D Early Production Scheme 2. The Umm Shaif Khuff reservoir is a formation that consists of dry gas volumetric reservoirs located in the Umm Shaif field.
Khuff reservoirs have been in production in Abu Dhabi since August 1989. Umm Shaif Khuff gas is currently produced from 28 active wells within the Umm Shaif field. A majority of these wells supply gas to Adnoc Group subsidiaries Adnoc LNG and Adnoc Gas Processing, with the rest supporting oil reservoirs at the Umm Shaif field through gas injection.
The Umm Shaif Super Complex (USSC) processes and transports oil, condensates and natural gas in separate pipelines to Das Island for further processing and export. The condensates collected from the USSC are transported to Das Island through an 18-inch pipeline stretching 34.4km, or are spiked into the 36-inch Adnoc main oil line.
The gas collected from the USSC is transported to Das Island through two 46-inch pipelines, which also run 34.4km.
Pressure at the Umm Shaif Khuff gas reservoirs will start to decline by the end of 2028. The flowing wellhead pressures at some of the Khuff gas wellhead towers are likely to reduce, so boosting well deliverability and increasing the flowrates is necessary.
Therefore, new Khuff surface pressure boosting facilities are required to maintain the plateau – with a goal of achieving a 90% gas recovery factor – and increase production beyond the end of the plateau by lowering pressure at the Khuff reservoirs.
ALSO READ: Adnoc initiates oil production project at key offshore block
https://image.digitalinsightresearch.in/uploads/NewsArticle/18087628/main.jpeg -
Masdar renews $300m revolving credit facility4 August 2026
Abu Dhabi Future Energy Company (Masdar) has renewed its five-year $300m revolving credit facility with a syndicate of 25 international banks.
The company said the refinancing strengthens its liquidity position and overall balance sheet resilience as it works towards its target of reaching 100GW of renewable energy portfolio capacity by 2030.
According to Masdar, the lending syndicate comprises 14 banks from Europe, four from the US and seven from Asia.
Masdar’s renewable energy portfolio reached 65GW earlier this year, placing the company about two-thirds of the way towards its 100GW target by 2030. Of that, Masdar said 45GW is operational, under construction or has reached final close, while a further 20GW comprises projects in advanced stages of development.
The company has said it plans to deploy a further $30bn-$35bn in equity and project finance by 2030 to achieve its capacity target, adding an average of 10GW of new capacity each year.
The next phase of growth will be funded through a combination of equity, green bonds and long-term project finance.
Last month, Masdar reached financial close on its $6.1bn round-the-clock renewable energy project in Abu Dhabi, securing a $5.1bn financing package from a consortium of 13 local and international banks.
The project combines 5.2GW of solar generation with 19GWh of battery energy storage and is expected to begin operations in 2027.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18086886/main.jpg -
Jordan awards EPC contract for Maan wind farm4 August 2026
Jordan’s state-owned Samra Electric Power Company (Sepco) has awarded an engineering, procurement and construction (EPC) contract to Al-Mawakea General Contracting Technology Company for a 25MW wind power project in the Batn Al-Ghul area of Maan Governorate.
The project is being developed by Jordan’s Ministry of Energy & Mineral Resources (MEMR) under a cooperation agreement signed with Abu Dhabi Future Energy Company (Masdar) in February. The UAE, represented by Masdar, is fully financing the project.
The project will comprise five wind turbines with a combined generation capacity of 25MW. Masdar is responsible for providing technical oversight, supervising implementation, managing logistics and shipping, and monitoring progress during the execution phase.
Sepco will operate and maintain the wind farm after construction is completed and the facility is handed over. MEMR is responsible for securing the project site and obtaining the required regulatory approvals and permits.
Sepco operates and maintains the government-owned 80MW Maan wind farm in Maan Governorate. The $150m Maan wind power plant (phases one and two) was commissioned in 2017, with Spain’s Elecnor working as the main EPC contractor. The two phases combined have a total installed capacity of 80MW.
Separately, Masdar signed a joint development agreement with MEMR in 2023 to develop a 1GW wind project with a battery energy storage system near the Port of Aqaba in Jordan. It is understood that the project is still in its initial stages of development.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18084627/main.jpg -
Chinese contractor wins Saudi power and gas contracts4 August 2026
Chinese contractor Ningxia Power Construction has announced it has won two contracts in Saudi Arabia covering power and gas infrastructure projects with a combined value of about RMB280m ($39m).
The awards cover the third phase of cable laying and connection works for Saudi Aramco’s Master Gas System (MGS-III) project and the first phase of a 380kV transmission line for the Red Sea Aluminium project, the company said in a statement.
The MGS gas booster station contract covers electrical, instrumentation and control, communications, pre-commissioning, commissioning and defect rectification works.
The project is located northwest of Al-Mendassah in Medina Province. Construction is scheduled to last 670 days and continue through to partial mechanical completion and mechanical completion.
The Red Sea Aluminium contract involves the first phase of a 380kV overhead transmission line project.
The scope includes eight new transmission circuits. Four incoming double-circuit lines will extend about 15.2 kilometres from the connection point to the switchyard. Four outgoing double-circuit lines will run about 0.2 kilometres from the switchyard to the aluminium plant power station. Provision has also been made for two additional outgoing circuits in the future.
The Red Sea Aluminium complex is a planned integrated aluminium production facility in Yanbu Industrial City being developed by Red Sea Aluminium Holdings (RSAH), a joint venture of Innovation Global Industries, Innovation New Materials and Shandong Innovation Group
In June, RSAH awarded China’s Shandong Electric Power Construction Corporation (Sepco) an estimated $100m engineering, procurement and construction contract for a 380kV overhead transmission line project at the Red Sea Aluminium complex.
READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDFSaudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.
Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:
> WORLD CUP: What the 2026 World Cup means for Saudi Arabia 2034> MARKET FOCUS: Maghreb fortunes diverge> INDUSTRY REPORT: GCC banks prove resilient amid turmoil> LEADERSHIP: Private capital and the GCC infrastructure inflection> INTERVIEW: Developers look beyond standalone solarTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/18081852/main.jpg -
Contractors submit bids for key Aramco offshore tenders4 August 2026

Register for MEED’s 14-day trial access
Contractors in Saudi Aramco’s Long-Term Agreement (LTA) pool of offshore service providers have submitted bids for five offshore tenders covering the engineering, procurement, construction and installation (EPCI) of structures at the Abu Safah, Berri, Manifa, Marjan, Safaniya and Zuluf offshore oil and gas fields in Saudi Arabia.
The tenders are numbers 167, 168, 169, 170 and 171 on Aramco’s Contract Release and Purchase Order (CRPO) system, according to sources.
Aramco issued the five CRPOs to its offshore LTA contractors in December, setting an initial bid submission deadline of 3 February.
The Saudi energy giant has since extended the bid submission deadline several times – to 31 March, 1 June, 1 July and then 30 July – to allow LTA contractors sufficient time to prepare proposals.
At the request of certain bidders, Aramco granted a final two-day extension, with LTA contractors submitting their proposals for the five CRPOs on 1 August, sources told MEED.
The basic scope of EPCI work on the tenders is as follows:
- CRPO 167 – eight jackets at the Marjan field development
- CRPO 168 – four production deck modules (PDMs) at the Abu Safah, Berri, Manifa and Safaniya fields
- CRPO 169 – three PDMs at the Marjan field development
- CRPO 170 – three PDMs at the Marjan field development
- CRPO 171 – three PDMs at the Zuluf field development
Offshore contract awards
Aramco spent almost $11bn on offshore EPCI contracts last year, more than double its capital expenditure on offshore projects in 2024, marking another year of robust upstream project spending in Saudi Arabia.
In July, Aramco selected contractors for five CRPOs – numbers 150, 157, 158, 159 and 160 – worth over $3bn. These involve EPCI work and infrastructure upgrades at the Abu Safah, Berri, Manifa, Marjan and Zuluf offshore fields.
The Saudi energy giant then picked contractors for four more CRPOs that are part of the large-scale project to expand infrastructure at the Zuluf offshore field development. The tenders are CRPOs 145, 146, 147 and 148, and their combined value is estimated to be almost $6bn.
In late December last year, Italian contractor Saipem announced securing contracts for CRPOs 162 and 165. The scope of work on CRPO 162 covers the EPCI of two rigid pipelines – a 30-inch pipeline stretching 23.98 kilometres (km) and a 20-inch pipeline, 10.23km-long; replacement of a flexible 10-inch pipeline that spans 5.1km; and modification work on topsides at the Berri and Abu Safah field developments. The duration of this contract is 32 months, Saipem said.
The scope of work on CRPO 165, lasting 12 months, includes subsea interventions at the Marjan field development and the EPCI of 300 metres of onshore pipeline and associated tie-ins.
In early January 2026, MEED reported that Aramco had selected US-based McDermott International for CRPO 166. The scope of work is understood to have been carved out of the $15bn Marjan offshore field development project, under which Aramco issued contracts for 20 EPCI packages in 2019. McDermott won the largest share of work on the project, securing an estimated $4.5bn of contracts across two packages.
The contract for CRPO 166 was single-sourced to McDermott without a competitive tendering process and issued as a change order, sources told MEED.
Aramco then awarded its second offshore contract of the year, CRPO 156, to Saipem. The scope of work covers the EPCI of a 48-inch trunkline, spanning roughly 65km offshore and 12km onshore, from the Safaniya offshore oil field to the onshore processing facility, plus associated works such as subsea hook-ups.
CRPO 156 comprises the third package in Aramco’s latest expansion phase at Safaniya – the world’s largest offshore oil field, with a production capacity of nearly 1.2 million barrels a day (b/d). Discovered in 1951, the field is located in Gulf waters approximately 265km north of Aramco’s headquarters in Dhahran.
MEED also reported that Saipem was selected by Aramco for two more tenders as part of the Safaniya field development expansion phase – CRPOs 154 and 155. The combined contract value for CRPOs 154 and 155 is estimated at $600m, sources said.
In April, state-owned China Offshore Oil Engineering Company won CRPO 161, which covers the EPCI of four gas jackets at the Arabiyah, Hasbah and Karan offshore fields.
Healthy contract award pipeline
Looking ahead, in addition to CRPOs 167-171, which are currently under bidding, Aramco is evaluating bids submitted by its offshore LTA contractors in July and August last year for at least two additional tenders.
These are CRPOs 163 and 164, relating to the EPCI of infrastructure at the Abu Safah, Berri, Karan, Marjan and Safaniya fields.
Separately, the offshore LTA contractors are also bidding for a new tender – CRPO 176 – that was issued by Aramco in May, according to sources.
The scope of work on CRPO 176 covers the EPCI of seven flexible subsea pipelines with a combined length of 17km at the Berri and Marjan offshore field developments.
Aramco’s LTA pool of offshore service providers comprises the following entities:
- Saipem (Italy)
- McDermott International (US)
- Larsen & Toubro Energy Hydrocarbon (LTEH, India) / Subsea7 (UK)
- NMDC Energy (UAE)
- Lamprell (UAE/Saudi Arabia)
- China Offshore Oil Engineering Company (China)
- Dynamic Industries (US)
- Sapura Energy (Malaysia)
- TechnipFMC (France) / MMHE (Malaysia)
- Hyundai Heavy Industries (South Korea)
In April 2025, Aramco renewed its LTAs with the following contractors, whose contracts had either lapsed or were close to expiry:
- Saipem
- McDermott International
- Larsen & Toubro Energy Hydrocarbon / Subsea7
- NMDC Energy
- Lamprell
- China Offshore Oil Engineering Company
ALSO READ: Aramco moves apace with Jafurah unconventional gas campaign
https://image.digitalinsightresearch.in/uploads/NewsArticle/18080836/main0627.jpg