Saudi Arabia’s power sector motors on
11 September 2024

Saudi Arabia’s power sector has sustained its project activity momentum over the past six months.
The principal buyer, Saudi Power Procurement Company (SPPC), awarded the contracts to develop two publicly-tendered wind independent power producer (IPP) projects, with a total combined capacity of 1,100MW, under the fourth round of the kingdom’s National Renewable Energy Programme (NREP).
The Public Investment Fund (PIF), responsible for procuring through direct negotiations 70% of the kingdom’s 2030 target renewable energy capacity, let three large-scale solar photovoltaic (PV) projects with a total combined capacity of around 5,500MW.
State majority-owned Saudi Aramco also awarded a contract to develop an independent cogeneration project with an electricity generation capacity of 475MW.
During the same period, SPPC began the tendering process for two combined-cycle gas turbine (CCGT) projects, the Remah and Nairiyah IPPs, each with a capacity of 3,600MW, and for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round.
“It has been a very busy summer,” notes a senior executive with an international utility developer, referring to the submission of bids in August for the contracts to develop the Remah 1 & 2, Nairiyah 1 & 2, and the NREP round-five solar PV schemes.
Notably, the principal buyer has initiated the selection process for consultants who will advise on its next pair of independent CCGT power plants – the 2,400MW Al-Rais and the 3,600MW Riyadh 16 projects.
Saudi Electricity Company (SEC) and SPPC are also understood to be conducting bilateral talks for the development of five CCGT power plants, which, along with those currently being built or tendered, support the kingdom’s mandate to replace fleets running on liquid fuel.
Essentially, the reported SEC projects, each with a capacity of 1,500MW-2,000MW, bear some similarities to PIF’s directly negotiated renewable energy schemes.
These projects help substantiate previous reports that SEC has been seeking to lock in gas turbine equipment deals with a total capacity of 30GW, in line with an overall capacity expansion plan within and outside Saudi Arabia.
The next few years can only get busier, with Saudi Arabia's Energy Minister, Prince Abdulaziz Bin Salman Bin Abdulaziz Al-Saud, confirming in June plans to tender 20,000MW of renewable energy projects annually starting this year, in line with reaching 100GW-130GW of installed capacity by 2030, "depending on electricity demand growth".
This represents a major upward revision to the official 2030 renewable energy capacity target of 58,700MW.
However, it is unclear if this new target considers the renewable capacity that will be installed to power Neom, Saudi Arabia’s largest gigaproject, as well as the requirement of green hydrogen projects that the PIF plans to codevelop.
Wind IPPs
In May, SPPC awarded a team led by Japanese utility developer Marubeni Corporation the contracts to develop the 600MW Al-Ghat wind and 700MW Waad Al-Shamal wind IPPs.
The team of Marubeni and its partner, the local Alajlan Brothers, is also expected to win the contract to develop the 700MW Yanbu wind IPP, the final wind scheme included in NREP’s round four.
These are important awards for Marubeni, which last won an IPP contract in Saudi Arabia in 2021 for the 300MW Rabigh solar scheme.
Notably, the Al-Ghat and Waad Al-Shamal wind IPPs will be developed at world-record-low levelised electricity costs of $c1.565 a kilowatt-hour (kWh), or roughly 5.87094 halalas/kWh, and $c1.70187/kWh or 6.38201 halalas/kWh.
PIF projects
In June, three Saudi utility developers and investors signed power-purchase agreements (PPAs) with SPPC to develop and operate three solar PV projects with a combined capacity of 5,500MW.
The Haden and Muwayh solar PVs, located in Mecca, will each have a capacity of 2,000MW, while the Al-Khushaybi solar PV power plant in Qassim will be able to generate 1,500MW of electricity.
The team that will develop the three projects consists of Acwa Power, PIF-backed Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco), a subsidiary of the state majority-owned oil giant.
The project companies formed for each solar IPP have since signed financing documents for the projects, which will require a total investment of SR12.3bn ($3.3bn). The financing sought was $2.6bn.
These projects comprise round four of PIF’s Price Discovery Scheme, with Acwa Power as the preferred developer partner.
Energy storage systems
The scale of new conventional and renewable energy capacity being developed in the kingdom – some 3,500MW of solar PV and wind capacity is now online, with over 10,500MW under construction – has increased the urgency to build energy storage systems to balance the kingdom’s energy system and stabilise its grid.
SPPC has signalled plans to procure gigawatt-sized battery energy storage systems (bess) using an IPP model. The tendering process for the first bess IPP package is expected to begin by the year-end or early 2025.
In parallel, National Grid Saudi Arabia, an SEC subsidiary, has started awarding contracts to build energy storage systems capacity using an engineering, procurement and construction (EPC) model. The local Algihaz Holding is understood to have won the contracts to build four energy storage systems in Najran, Madaya and Khamis Mushait, which will have a total combined capacity of 7.8 gigawatt-hours (GWh).
Also in August, SEC tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW, or roughly 10GWh.
The planned facilities, each with a capacity of 500MW or roughly 2GWh, are located in or within the proximity of the following key cities and load centres:
- Riyadh
- Qaisumah
- Dawadmi
- Al-Jouf
- Rabigh
Saudi Arabia’s plan to build its first large-scale nuclear power plant in Duwaiheen, which appeared to be making progress before October last year, has faced delays following shifting geopolitics involving stakeholders that include the US and Israel. The tender bid deadline for nuclear technology providers is understood to have been postponed and no new date has been set.
As it is, Saudi Arabia’s ever-expanding power projects pipeline, particularly for renewables and bess, will require investors, contractors and lenders to allocate sizeable resources, perhaps more than they have historically done in the past, over the next several years as various stakeholders endeavour to meet Vision 2030-tied peak demand scenarios.
This applies less to CCGT projects, which, pending a clear carbon-capture strategy from the offtaker or the Energy Ministry, appear to attract a decreasing number of developers and investors.
Exclusive from Meed
-
-
Nakheel awards $953m Palm Jebel Ali villas deal27 April 2026
-
Iraq’s first LNG terminal to be completed in June27 April 2026
-
-
Kuwait approves Doha desalination plant award27 April 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Partners launch feed-to-EPC contest for Duqm petchems project27 April 2026

Register for MEED’s 14-day trial access
Omani state energy conglomerate OQ Group and Kuwait Petroleum International (KPI), the overseas subsidiary of Kuwait Petroleum Corporation, have initiated a feed-to-EPC competition among contractors to develop a major petrochemicals complex at Duqm.
Under a feed-to-EPC model, the project operator selects contractors to carry out front-end engineering and design (feed). It then awards the engineering, procurement and construction (EPC) contract to the contractor with the most competitive feed proposal, while compensating the other contestants for their work.
OQ8, the 50:50 joint venture of OQ and KPI, is understood to have issued the tender for the Duqm petrochemicals project’s feed-to-EPC competition in mid-March, with a deadline of 6 May for contractors to submit proposals, sources told MEED.
Several local and international contractors based in Oman are believed to be participating in the competition, according to sources.
OQ Group CEO Ashraf Bin Hamad Al-Maamari and KPI’s CEO Shafi Bin Taleb Al-Ajmi signed an agreement on 3 February, during the Kuwait Oil & Gas Show and Conference, to develop a major petrochemicals-producing complex in Oman’s Duqm. The parties did not disclose details at the time.
ALSO READ: Duqm petrochemicals revival provides fillip to Gulf projects market
The agreement represented a significant step forward in Oman and Kuwait’s long-held plans to jointly develop a petrochemicals complex next to the existing Duqm refinery, which will benefit from favourable feedstock access and strong cost competitiveness.
The planned facility will also benefit from in Al-Wusta governorate, along Oman’s Arabian Sea coastline.
OQ8 had struggled to make meaningful progress on the Duqm petrochemicals project since the plan was conceived as early as 2018, for a variety of reasons.
The original plan for the Duqm petrochemicals facility, estimated at $7bn, centred on a mixed-feed steam cracker with a capacity to produce 1.6 million tonnes a year (t/y) of ethylene. The project also included a polypropylene (PP) plant with a capacity of 280,000 t/y and a high-density polyethylene (HDPE) plant with a capacity of 480,000 t/y.
The complex was also expected to include an aromatics plant, as well as storage facilities for naphtha and liquefied petroleum gas (LPG).
The project’s prospects were temporarily boosted when Saudi Basic Industries Corporation (Sabic) expressed interest in investing by signing a non-binding memorandum of understanding with OQ in December 2021.
Reuters reported in December that Sabic was withdrawing from the project, leaving OQ to look for other partners. The new agreement between OQ and KPI is understood to have followed the Saudi chemical giant’s departure.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16577785/main.jpg -
Nakheel awards $953m Palm Jebel Ali villas deal27 April 2026
Dubai-based real estate developer Nakheel, now part of Dubai Holding, has awarded two contracts worth AED3.5bn ($953m) to local firms for the construction of 544 villas at its Palm Jebel Ali project in Dubai.
The first contract was awarded to Ginco General Contracting for the construction of 354 villas across fronds A to D.
The second contract was awarded to United Engineering Construction Company (Unec) for the construction of 190 villas on fronds E and F.
Construction is expected to begin in Q2 this year, with completion scheduled for 2028.
Earlier phases
In October 2024, Nakheel awarded three contracts worth AED5bn ($1.3bn) for the construction of 723 villas on fronds K to P. The contracts went to Ginco, Unec and the local Shapoorji Pallonji.
Under these awards, Ginco is delivering 197 villas on fronds O and P, Shapoorji Pallonji is constructing 275 villas on fronds M and N, and Unec is building 251 villas on fronds K and L. Villa construction is expected to be completed by 2026.
Infrastructure works
This was followed by Nakheel awarding infrastructure contracts worth over AED750m ($204m) to local firm Dutco Construction for works on Palm Jebel Ali.
The infrastructure work includes utility connections, excavation, backfilling, and the construction of roads and pavements across fronds A to G. It also covers 11-kilovolt power distribution and telecommunications-related utility works.
Reclamation contract
In August 2024, Nakheel awarded an AED810m ($220m) contract to complete the reclamation works for the project.
The contract was awarded to Belgium’s Jan De Nul. Its scope includes dredging, land reclamation, beach profiling and sand placement to support the construction of villas across all fronds.
Masterplan details
Nakheel released details of the new masterplan for Palm Jebel Ali in June 2023. Twice the size of Palm Jumeirah, Palm Jebel Ali will have 110 kilometres of shoreline and extensive green spaces. The development will feature more than 80 hotels and resorts, along with a range of entertainment and leisure facilities.
It includes seven connected islands that will cater to approximately 35,000 families. The development also emphasises sustainability, with 30% of public facilities expected to be powered by renewable energy.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16577782/main.jpg -
Iraq’s first LNG terminal to be completed in June27 April 2026
Iraq’s first liquefied natural gas (LNG) import terminal is expected to be completed in early June, according to the country’s Ministry of Electricity.
The terminal, which has an estimated investment value of $450m, is being developed at the Port of Khor Al-Zubair and will have a capacity of 750 million standard cubic feet a day (cf/d).
Ministry spokesperson Ahmed Mousa told the Iraqi News Agency that “work is proceeding at an accelerated pace to complete the LNG platform”, noting that “the government has set 1 June as the date for finishing the project”.
In October last year, US-based Excelerate Energy signed a commercial agreement with a subsidiary of Iraq’s Ministry of Electricity to develop the floating LNG terminal.
The contract was signed at the office of Iraq’s Prime Minister Mohammed Shia Al-Sudani during a ceremony attended by senior officials from both countries, including the US deputy secretary of energy James Danly.
The contract included a five-year agreement for regasification services and LNG supply with extension options, featuring a minimum contracted offtake of 250 million cf/d.
Ahmed Mousa said that “under the contract, the company is responsible for completing the facility as well as securing the agreed gas quantities from any source, in line with the specified terms”.
He added: “Work is continuing according to the planned timelines to complete the project on schedule, as part of the Ministry of Electricity’s plans to keep pace with peak summer loads.”
Although Iraq is Opec’s second-largest oil producer after Saudi Arabia, it is a net natural gas importer because its lack of infrastructure investment has meant that, until 2023, it flared roughly half of the estimated 3.12 billion cf/d of gas produced in association with crude oil.
Iraq’s reliance on flaring associated gas instead of gathering and processing it has prevented the country from fully realising its potential as a gas producer and forced the Iraqi government to rely on costly gas and electricity imports from Iran.
Recently, Iraq’s oil and gas sector has been disrupted by fallout from the US and Israel’s attack on Iran on 28 February and the subsequent regional conflict.
Over recent weeks, Iraq’s oil exports have collapsed by about 80% amid problems shipping crude through the Strait of Hormuz.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16577746/main.jpg -
Iraqi LNG import terminal raises questions about energy strategy27 April 2026
Commentary
Wil Crisp
Oil & gas reporterIraq’s first LNG import terminal is set to come online in early June, at a time when global LNG prices are likely to remain close to their highest levels in more than three years.
The disruption to global oil and gas exports in the wake of the US and Israel’s attack on Iran on 28 February led to LNG prices soaring, with natural gas prices in Asia and Europe rising to their highest levels since January 2023 during March.
So far, there has been little progress towards a diplomatic or military solution to reopen the Strait of Hormuz, and most analysts do not forecast significant price declines in the near term.
On 24 April, the International Energy Agency (IEA) said that the combined effect of short-term supply losses and slower capacity growth could result in a cumulative loss of around 120 billion cubic metres of LNG supply between 2026 and 2030.
While the IEA expects new liquefaction projects in other regions to offset these losses over time, it still believes the crisis will lead to prolonged tight market conditions through 2026 and 2027.
This means that Iraq will likely have to pay elevated prices for imported LNG for some time to come – if it can receive shipments at all.
The port of Khor Al-Zubair is located in the Arabian Gulf, and LNG shipments from the US or Australia would need to pass through the Strait of Hormuz before reaching the terminal.
This will only be possible if a solution is found to the ongoing blockade of the shipping route.
Investment debate
Iraq’s project to develop a floating LNG terminal is estimated to cost $450m, and many in Iraq may question whether this was the best use of these funds.
While it may have been difficult for Iraqi policymakers to foresee the attack by the US and Israel on Iran and its impact on LNG markets, Iraq had several strong options to enhance domestic energy security rather than turning to LNG imports.
The most obvious of these was investing in infrastructure to enable it to utilise its domestic gas reserves.
According to the World Bank’s 2025 Global Gas Flaring Tracker Report, in 2024, Iraq burned off more unused gas than any other country, except Russia and Iran, which ranked first and second, respectively.
That year, an estimated total of more than 18 billion cubic metres of natural gas was flared in Iraq due to a lack of infrastructure to properly capture and process it.
It is highly likely that projects to gather and process this gas would have been more reliable and cost-effective than investing in a new floating LNG terminal, which increases the country’s exposure to global LNG price fluctuations and shipping disruptions.
Other options could have included developing domestic gas fields or investing in solar and battery storage projects, which have become increasingly affordable in recent years.
The cost of solar panels has fallen by more than 95% over the past decade.
Power shortfall
As things stand, Iraq is likely to face severe electricity shortages this summer.
On 21 April, Iraq’s Ministry of Electricity said it plans to produce 30,000MW this summer, well short of the predicted peak demand of around 55,000MW.
Ahmed Musa, a spokesperson for the Electricity Ministry, told the state-run Iraqi News Agency that the shortfall will result in planned outages across the country.
He also said that even meeting the 30,000MW target is contingent on sufficient gas supplies.
If Iraq experiences the same level of power outages as last year – or worse – many are likely to view the $450m spent on an LNG import terminal as a waste of money and an expensive symbol of poor planning.
Power cuts this summer could stoke unrest at a time that is already politically precarious due to the ongoing regional conflict.
In recent years, electricity shortages have repeatedly fuelled protests in Iraq during the summer months, particularly in Basra, where blackouts and poor public services have driven people to take to the streets.
If the Strait of Hormuz does not reopen soon, Iraq’s economic crisis will deepen, and electricity shortages are likely to further undermine the country’s stability.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16577743/main.jpg -
Kuwait approves Doha desalination plant award27 April 2026
Kuwait’s Central Agency for Public Tenders has approved the recommendation of the Ministry of Electricity & Water to award a KD114.28m ($371.5m) contract to supply, install, operate and maintain the second phase of the Doha seawater reverse osmosis (SWRO) desalination plant.
A joint venture of Kuwait-based Heavy Engineering Industries & Shipbuilding Company (Heisco) and India’s VA Tech Wabag has been selected for the project, with the award understood to be pending final approval from the Audit Bureau.
The project will deliver a production capacity of about 60 million imperial gallons a day (MIGD) and will include the desalination plant with full reverse osmosis trains, pre- and post-treatment systems, recarbonation equipment, booster pumps, and safety and filtration systems.
The total project duration is 96 months. The Doha SWRO desalination plant is part of Kuwait’s broader programme to expand water production capacity and reduce reliance on thermal desalination methods.
MEED previously reported that the Heisco/Wabag joint venture submitted the lowest bid. Bidders and prices included:
- Heavy Engineering Industries & Shipbuilding / Wabag: $373.2m
- Cox Water (Spain): $538.1m
- Orascom Construction (Egypt): $568.4m
In April 2025, MEED reported that Kuwait had retendered the contract for the facility after the ministry cancelled the initial tender in June 2024.
The Ministry of Electricity & Water awarded South Korea’s Doosan Heavy Industries & Construction – now known as Doosan Enerbility – a $422m contract in May 2016 to build the 60 MIGD Doha 1 SWRO plant.
https://image.digitalinsightresearch.in/uploads/NewsArticle/16577722/main.jpg
