Saudi Arabia’s power sector motors on

11 September 2024

 

Saudi Arabia’s power sector has sustained its project activity momentum over the past six months.

The principal buyer, Saudi Power Procurement Company (SPPC), awarded the contracts to develop two publicly-tendered wind independent power producer (IPP) projects, with a total combined capacity of 1,100MW, under the fourth round of the kingdom’s National Renewable Energy Programme (NREP).

The Public Investment Fund (PIF), responsible for procuring through direct negotiations 70% of the kingdom’s 2030 target renewable energy capacity, let three large-scale solar photovoltaic (PV) projects with a total combined capacity of around 5,500MW.

State majority-owned Saudi Aramco also awarded a contract to develop an independent cogeneration project with an electricity generation capacity of 475MW.

During the same period, SPPC began the tendering process for two combined-cycle gas turbine (CCGT) projects, the Remah and Nairiyah IPPs, each with a capacity of 3,600MW, and for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round.

“It has been a very busy summer,” notes a senior executive with an international utility developer, referring to the submission of bids in August for the contracts to develop the Remah 1 & 2, Nairiyah 1 & 2, and the NREP round-five solar PV schemes.

Notably, the principal buyer has initiated the selection process for consultants who will advise on its next pair of independent CCGT power plants – the 2,400MW Al-Rais and the 3,600MW Riyadh 16 projects.

Saudi Electricity Company (SEC) and SPPC are also understood to be conducting bilateral talks for the development of five CCGT power plants, which, along with those currently being built or tendered, support the kingdom’s mandate to replace fleets running on liquid fuel.

Essentially, the reported SEC projects, each with a capacity of 1,500MW-2,000MW, bear some similarities to PIF’s directly negotiated renewable energy schemes.

These projects help substantiate previous reports that SEC has been seeking to lock in gas turbine equipment deals with a total capacity of 30GW, in line with an overall capacity expansion plan within and outside Saudi Arabia.

The next few years can only get busier, with Saudi Arabia's Energy Minister, Prince Abdulaziz Bin Salman Bin Abdulaziz Al-Saud, confirming in June plans to tender 20,000MW of renewable energy projects annually starting this year, in line with reaching 100GW-130GW of installed capacity by 2030, "depending on electricity demand growth".

This represents a major upward revision to the official 2030 renewable energy capacity target of 58,700MW.

However, it is unclear if this new target considers the renewable capacity that will be installed to power Neom, Saudi Arabia’s largest gigaproject, as well as the requirement of green hydrogen projects that the PIF plans to codevelop.

Wind IPPs

In May, SPPC awarded a team led by Japanese utility developer Marubeni Corporation the contracts to develop the 600MW Al-Ghat wind and 700MW Waad Al-Shamal wind IPPs.

The team of Marubeni and its partner, the local Alajlan Brothers, is also expected to win the contract to develop the 700MW Yanbu wind IPP, the final wind scheme included in NREP’s round four.

These are important awards for Marubeni, which last won an IPP contract in Saudi Arabia in 2021 for the 300MW Rabigh solar scheme.

Notably, the Al-Ghat and Waad Al-Shamal wind IPPs will be developed at world-record-low levelised electricity costs of $c1.565 a kilowatt-hour (kWh), or roughly 5.87094 halalas/kWh, and $c1.70187/kWh or 6.38201 halalas/kWh.

PIF projects

In June, three Saudi utility developers and investors signed power-purchase agreements (PPAs) with SPPC to develop and operate three solar PV projects with a combined capacity of 5,500MW.

The Haden and Muwayh solar PVs, located in Mecca, will each have a capacity of 2,000MW, while the Al-Khushaybi solar PV power plant in Qassim will be able to generate 1,500MW of electricity.

The team that will develop the three projects consists of Acwa Power, PIF-backed Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco), a subsidiary of the state majority-owned oil giant.

The project companies formed for each solar IPP have since signed financing documents for the projects, which will require a total investment of SR12.3bn ($3.3bn). The financing sought was $2.6bn.

These projects comprise round four of PIF’s Price Discovery Scheme, with Acwa Power as the preferred developer partner.

Energy storage systems

The scale of new conventional and renewable energy capacity being developed in the kingdom – some 3,500MW of solar PV and wind capacity is now online, with over 10,500MW under construction – has increased the urgency to build energy storage systems to balance the kingdom’s energy system and stabilise its grid.

SPPC has signalled plans to procure gigawatt-sized battery energy storage systems (bess) using an IPP model. The tendering process for the first bess IPP package is expected to begin by the year-end or early 2025.

In parallel, National Grid Saudi Arabia, an SEC subsidiary, has started awarding contracts to build energy storage systems capacity using an engineering, procurement and construction (EPC) model. The local Algihaz Holding is understood to have won the contracts to build four energy storage systems in Najran, Madaya and Khamis Mushait, which will have a total combined capacity of 7.8 gigawatt-hours (GWh).

Also in August, SEC tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW, or roughly 10GWh.

The planned facilities, each with a capacity of 500MW or roughly 2GWh, are located in or within the proximity of the following key cities and load centres:

  • Riyadh
  • Qaisumah
  • Dawadmi
  • Al-Jouf
  • Rabigh

Saudi Arabia’s plan to build its first large-scale nuclear power plant in Duwaiheen, which appeared to be making progress before October last year, has faced delays following shifting geopolitics involving stakeholders that include the US and Israel. The tender bid deadline for nuclear technology providers is understood to have been postponed and no new date has been set.

As it is, Saudi Arabia’s ever-expanding power projects pipeline, particularly for renewables and bess, will require investors, contractors and lenders to allocate sizeable resources, perhaps more than they have historically done in the past, over the next several years as various stakeholders endeavour to meet Vision 2030-tied peak demand scenarios.

This applies less to CCGT projects, which, pending a clear carbon-capture strategy from the offtaker or the Energy Ministry, appear to attract a decreasing number of developers and investors.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12496716/main.jpg
Jennifer Aguinaldo
Related Articles
  • Hydrom targets hyperscalers in round four

    19 November 2026

     

    Oman’s green hydrogen company Hydrom is turning to domestic demand to support the sector as export markets slow, says managing director Abdulaziz Al-Shidhani.

    Speaking to MEED after Hydrom awarded two projects under its third auction round and launched a fourth round linked to data centres at UN climate change conference Cop31 in Antalya, Al-Shidhani says interest in the third round had been satisfactory but below earlier levels. 

    “There was a good interest, satisfactory to the auction itself, but it was not as big as it was in round one specifically,” he says. “[That is] reflecting the overall market sentiment when it comes to green hydrogen.”

    Hydrom does not disclose the number of auction bids it receives.

    Domestic demand

    According to Al-Shidhani, regulatory slowdowns in Europe and slower progress in markets such as South Korea and Japan prompted Hydrom to look for buyers at home.

    “We decided last year to start exploring each and every avenue domestically to support decarbonising our industries and introducing green solutions for expanding the industrial base within Oman itself,” he says.

    Steel, methanol, mobility, hydrogen-to-power and data centres are among the applications that are under review. A natural gas supply agreement was recently signed for a green direct reduced iron (DRI) plant, which carries a mandate to replace natural gas with green hydrogen in the early 2030s. Hydrom is helping first-round developers in Duqm reach a commercial agreement with the DRI investor.

    Data centres

    The fourth round, the Green-Powered Data Centre Hydrogen Auction, will be held in Dhofar Governorate. The city of Salalah was chosen for its connectivity, cooler climate and seawater cooling.

    Al-Shidhani says the national grid is not yet in a position to supply hyperscalers requiring 100MW or more. The Energy & Minerals Ministry and the Transport, Communications & Information Technology Ministry mandated Hydrom to design a captive power solution.

    “Our work yielded that the best techno-commercial proposition is a blend of renewable electrons supported by batteries and supported by up to 20% firming power through hydrogen gensets,” he says.

    The auction is designed for integrated consortiums covering power, hydrogen and data centre hubs. Hydrom will also offer matchmaking for investors that want a partner to supply the energy.

    Registration for expressions of interest is open until February 2027. Al-Shidhani says a market sounding exercise had given “a very positive signal”. Hydrom plans to issue the request for qualification by the end of the first quarter of 2027, with requests for proposals expected around mid-year.

    Round three

    The awards went to a consortium of Petrogas E&P and Italy’s Bio3Energy, which plans to produce about 625,000 tonnes a year (t/y) of green ammonium nitrate, and a consortium of PLN Indonesia Power Renewables, Alawi Enterprises and HBA Offshore International, which plans to produce about 400,000 t/y of green ammonia. Combined green hydrogen output is expected to reach about 121,000 t/y by 2032.

    The block offered covers 300 square kilometres and could accommodate up to three projects. One winner has an option on a further 100 square kilometres, which would use the full block.

    Al-Shidhani says the land usufruct agreements will be registered with Oman’s Housing Ministry within two to three weeks. Developers then have three and a half years for development work, with a final investment decision expected by the end of year three and financial close six months later. Construction is allotted three and a half years, followed by 40 years of operations.

    He says the 2032 production date does not represent a delay to Oman’s 2030 target. 

    “It is a rolling process,” he says. “The 2030 [projects] were signed in 2023 and 2024. It is a moving target.”

    One of the new projects has opted for solar power only at the outset. Hydrom does not specify generation or electrolyser technology. Project finance remains the most common funding route, although Al-Shidhani says export credit agencies could also play a role.

    This is a demonstration that Oman is able to produce [some of] the lowest-cost hydrogen

    First production

    The first phase of India-based Acme Group’s project in Duqm, which will produce 100,000 t/y of green ammonia, is expected to start production in Q2 2027. Al-Shidhani, who visited the site in October, says major components were almost complete.

    “This is a demonstration that Oman is able to produce [some of] the lowest-cost hydrogen and deliver it competitively to markets, and we are not talking about small quantities,” he says.

    He expects the first export cargo to convince sceptical investors that Oman can produce hydrogen for less than $3 a kilogram. Other first- and second-round developers are still negotiating offtake before moving to front-end engineering and design.

    Further rounds

    Al-Shidhani says the awarded projects use approximately 4% of the land available to Hydrom, and that further auctions are certain. Oman’s strategy targets 8.5 million t/y of green hydrogen by 2050.

    Hydrom paused for almost a year after the second auction round, and the timing of future rounds will depend on the market.

    “It is all about selecting the right time to go to the market,” he says. “In terms of whether there would be round five or round six, the answer is definitely there would be.”  

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21573009/main.gif
    Colin Foreman
  • Contractors submit best offers for Oxagon Highway 55

    19 November 2026

     

    Contractors have submitted their best and final offers for a design-and-build contract to upgrade Highway 55 in Saudi Arabia’s Oxagon region.

    The first phase of the project includes the construction of 14 kilometres of road, with two lanes in each direction, as well as one bridge and three interchanges.

    The project is expected to take 22 months to complete.

    Contractors initially submitted bids on 28 September, as MEED exclusively reported.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August last year that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21556022/main.jpg
    Yasir Iqbal
  • Construction starts on Damascus hotel and mall

    19 November 2026

    Construction has started on the Movenpick Hotel and Arab Mall development in the Kafr Sousa district of Damascus.

    Rotana Star Holding and Sankari Holding are backing the project, which Syria’s Ministry of Tourism is developing under its patronage.

    The project marks Accor’s entry into the Syrian market. The France-based hotel group signed an agreement earlier this year to manage the project’s Movenpick Hotel component.

    The integrated development will cover more than 90,000 square metres (sq m) and combine hotel, retail, entertainment and supporting facilities.

    The Movenpick Hotel will occupy more than 25,000 sq m and include 300 accommodation units. Facilities will include event and celebration halls, restaurants with panoramic views, and health and fitness amenities.

    Arab Mall will cover more than 65,000 sq m across seven levels. It will include retail units, entertainment facilities and service areas.

    The developers expect Arab Mall to open in the first quarter of 2028, followed by the hotel in the first quarter of 2029.

    Accor acquired the Swiss-founded Movenpick brand in 2018. Under the management agreement, Accor will operate the hotel and provide access to its global reservation, distribution and marketing platforms.

    The development is expected to create direct and indirect employment across construction, engineering, hospitality, retail and services.

    The project is being advanced as Syria seeks to expand its tourism and hospitality capacity.

    Syria’s Ministry of Tourism has reported that the country received 3.52 million visitors in the first half of 2026, 111% more than in the same period of 2025.

    The ministry said foreign tourist arrivals increased by 448%, while Arab visitor numbers rose by 107%.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21555695/main.jpeg
    Yasir Iqbal
  • Kuwait discusses retender of $7.7bn of oil projects

    19 November 2026

     

    State-owned upstream operator Kuwait Oil Company (KOC) is discussing the retendering of upstream projects worth an estimated $7.7bn, according to industry sources.

    The tender processes for all four contracts were cancelled earlier this year after the lowest bids exceeded the projects’ approved budgets.

    The projects are:

    • Separation Gathering Centre 1 (SGC-I) and Water Injection Plant (WIP-1)
      Previous low bidder: Tecnicas Reunidas (Spain) – $2.47bn
    • Separation Gathering Centre 3 (SGC-3) and Water Injection Plant (WIP-3)
      Previous low bidder: Larsen & Toubro (India) – $2.48bn
    • Installation of Water Injection Plant (WIP-4)
      Previous low bidder: Petrofac (UK) – $1.48bn
    • Effluent Water Disposal Plants 1 & 2 expansion project (EWDP 1&2)
      Previous low bidder: Larsen & Toubro (India) – $1.30bn

    KOC is considering a strategy under which pipeline and network installation work would be removed from the main contract scopes and tendered separately, the sources said.

    The company is also planning to relaunch the four main packages under a build-own-operate model rather than the engineering, procurement and construction (EPC) model used previously.

    KOC is expected to tender the pipeline and network packages on an EPC basis, or under a similar delivery model.

    In addition, KOC is discussing increases to the projects’ approved budgets to enable contractors to submit compliant bids, the sources said.

    Since KOC cancelled the four tenders in January, Kuwait’s oil and gas sector and the wider economy have faced disruption linked to the regional conflict that began after the US and Israel attacked Iran on 28 February.

    The conflict has reduced shipping through the Strait of Hormuz, limiting Kuwait’s ability to export crude oil.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21532374/main.jpg
    Wil Crisp
  • Saudi Arabia cancels more water tenders

    19 November 2026

     

    Two tenders for a major water pipeline project in Saudi Arabia have been cancelled, marking the second major water infrastructure project in the kingdom to have its tender process called off this month.

    The tenders cover Package B and the combined Packages C1 and C3 of the New Water Pipeline to Feed Riyadh City 2 project, being developed by Water Transmission Company (WTCO). 

    A source close to the project told MEED that bidders were notified of the decision earlier in November.

    The three packages have a combined value of about $556m and involve the construction of a long-distance potable-water transmission system to strengthen supplies to Riyadh.

    The wider masterplan includes approximately 136 kilometres of pipeline, with diameters ranging from 64 inches to 100 inches. The scope also includes 10 steel storage tanks with capacities ranging from 100,000 cubic metres to 170,000 cubic metres.

    According to regional tracker MEED Projects, Saudi Services for Electro-Mechanic Works was appointed as the main contractor for Package B in 2025, with a reported contract value of $279.6m. Another local firm, Al-Rawaf Trading & Contracting, was appointed for Packages C1 and C3, with a combined contract value of $276m. Multiple other contractors submitted bids for the three packages.

    As MEED understands, construction was expected to start earlier this year.

    The cancellations follow the withdrawal of a tender for a 300-million-litres-a-day seawater reverse osmosis desalination plant at Yanbu, valued at $272m.

    As reported by MEED on 16 November, Saudi Water Authority cancelled the Yanbu tender despite India’s VA Tech Wabag receiving the contract award in July 2025.

    The contractor disclosed the decision in a filing to Indian stock exchanges, saying the tender was cancelled due to “internal reasons” on the authority’s side.

    It is the second time a tender has been cancelled for the project at the final award stage.

    It is unclear whether the desalination or transmission-pipeline projects will be retendered and, if so, whether their scopes will remain unchanged. MEED has contacted WTCO for comment.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21527730/main.jpg
    Mark Dowdall