Saudi Arabia’s power sector motors on

11 September 2024

 

Saudi Arabia’s power sector has sustained its project activity momentum over the past six months.

The principal buyer, Saudi Power Procurement Company (SPPC), awarded the contracts to develop two publicly-tendered wind independent power producer (IPP) projects, with a total combined capacity of 1,100MW, under the fourth round of the kingdom’s National Renewable Energy Programme (NREP).

The Public Investment Fund (PIF), responsible for procuring through direct negotiations 70% of the kingdom’s 2030 target renewable energy capacity, let three large-scale solar photovoltaic (PV) projects with a total combined capacity of around 5,500MW.

State majority-owned Saudi Aramco also awarded a contract to develop an independent cogeneration project with an electricity generation capacity of 475MW.

During the same period, SPPC began the tendering process for two combined-cycle gas turbine (CCGT) projects, the Remah and Nairiyah IPPs, each with a capacity of 3,600MW, and for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round.

“It has been a very busy summer,” notes a senior executive with an international utility developer, referring to the submission of bids in August for the contracts to develop the Remah 1 & 2, Nairiyah 1 & 2, and the NREP round-five solar PV schemes.

Notably, the principal buyer has initiated the selection process for consultants who will advise on its next pair of independent CCGT power plants – the 2,400MW Al-Rais and the 3,600MW Riyadh 16 projects.

Saudi Electricity Company (SEC) and SPPC are also understood to be conducting bilateral talks for the development of five CCGT power plants, which, along with those currently being built or tendered, support the kingdom’s mandate to replace fleets running on liquid fuel.

Essentially, the reported SEC projects, each with a capacity of 1,500MW-2,000MW, bear some similarities to PIF’s directly negotiated renewable energy schemes.

These projects help substantiate previous reports that SEC has been seeking to lock in gas turbine equipment deals with a total capacity of 30GW, in line with an overall capacity expansion plan within and outside Saudi Arabia.

The next few years can only get busier, with Saudi Arabia's Energy Minister, Prince Abdulaziz Bin Salman Bin Abdulaziz Al-Saud, confirming in June plans to tender 20,000MW of renewable energy projects annually starting this year, in line with reaching 100GW-130GW of installed capacity by 2030, "depending on electricity demand growth".

This represents a major upward revision to the official 2030 renewable energy capacity target of 58,700MW.

However, it is unclear if this new target considers the renewable capacity that will be installed to power Neom, Saudi Arabia’s largest gigaproject, as well as the requirement of green hydrogen projects that the PIF plans to codevelop.

Wind IPPs

In May, SPPC awarded a team led by Japanese utility developer Marubeni Corporation the contracts to develop the 600MW Al-Ghat wind and 700MW Waad Al-Shamal wind IPPs.

The team of Marubeni and its partner, the local Alajlan Brothers, is also expected to win the contract to develop the 700MW Yanbu wind IPP, the final wind scheme included in NREP’s round four.

These are important awards for Marubeni, which last won an IPP contract in Saudi Arabia in 2021 for the 300MW Rabigh solar scheme.

Notably, the Al-Ghat and Waad Al-Shamal wind IPPs will be developed at world-record-low levelised electricity costs of $c1.565 a kilowatt-hour (kWh), or roughly 5.87094 halalas/kWh, and $c1.70187/kWh or 6.38201 halalas/kWh.

PIF projects

In June, three Saudi utility developers and investors signed power-purchase agreements (PPAs) with SPPC to develop and operate three solar PV projects with a combined capacity of 5,500MW.

The Haden and Muwayh solar PVs, located in Mecca, will each have a capacity of 2,000MW, while the Al-Khushaybi solar PV power plant in Qassim will be able to generate 1,500MW of electricity.

The team that will develop the three projects consists of Acwa Power, PIF-backed Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco), a subsidiary of the state majority-owned oil giant.

The project companies formed for each solar IPP have since signed financing documents for the projects, which will require a total investment of SR12.3bn ($3.3bn). The financing sought was $2.6bn.

These projects comprise round four of PIF’s Price Discovery Scheme, with Acwa Power as the preferred developer partner.

Energy storage systems

The scale of new conventional and renewable energy capacity being developed in the kingdom – some 3,500MW of solar PV and wind capacity is now online, with over 10,500MW under construction – has increased the urgency to build energy storage systems to balance the kingdom’s energy system and stabilise its grid.

SPPC has signalled plans to procure gigawatt-sized battery energy storage systems (bess) using an IPP model. The tendering process for the first bess IPP package is expected to begin by the year-end or early 2025.

In parallel, National Grid Saudi Arabia, an SEC subsidiary, has started awarding contracts to build energy storage systems capacity using an engineering, procurement and construction (EPC) model. The local Algihaz Holding is understood to have won the contracts to build four energy storage systems in Najran, Madaya and Khamis Mushait, which will have a total combined capacity of 7.8 gigawatt-hours (GWh).

Also in August, SEC tendered contracts for the construction of five battery energy storage systems with a total combined capacity of 2,500MW, or roughly 10GWh.

The planned facilities, each with a capacity of 500MW or roughly 2GWh, are located in or within the proximity of the following key cities and load centres:

  • Riyadh
  • Qaisumah
  • Dawadmi
  • Al-Jouf
  • Rabigh

Saudi Arabia’s plan to build its first large-scale nuclear power plant in Duwaiheen, which appeared to be making progress before October last year, has faced delays following shifting geopolitics involving stakeholders that include the US and Israel. The tender bid deadline for nuclear technology providers is understood to have been postponed and no new date has been set.

As it is, Saudi Arabia’s ever-expanding power projects pipeline, particularly for renewables and bess, will require investors, contractors and lenders to allocate sizeable resources, perhaps more than they have historically done in the past, over the next several years as various stakeholders endeavour to meet Vision 2030-tied peak demand scenarios.

This applies less to CCGT projects, which, pending a clear carbon-capture strategy from the offtaker or the Energy Ministry, appear to attract a decreasing number of developers and investors.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12496716/main.jpg
Jennifer Aguinaldo
Related Articles
  • H&H continues to deliver Dubai projects

    29 October 2026

     

    Dubai-based developer H&H has launched Water Gardens, a mixed-use development in Dubai International Financial Centre (DIFC), and expects to award most of the construction contracts for its wider pipeline before summer 2027.

    Water Gardens comprises four buildings designed by UK architect David Chipperfield, arranged around a central garden and pedestrian-friendly public realm. The scheme combines offices, residences, hospitality and retail offerings, including the Four Seasons Private Residences Dubai at DIFC and residences under H&H’s Eden House brand.

    Construction is under way, and the developer says the project is scheduled for completion in 2028. DIFC Investments describes it as one of the final components of the original Gate District masterplan.

    Speaking to MEED at the launch, H&H chairman Shahab Lutfi said the office building and Eden House are due for completion in about 18 months. The Four Seasons residences are scheduled for delivery at the end of 2028, with a five-star hotel following later.

    Water Gardens is one of several projects H&H has under way. The company undertakes a selective portfolio of high-end real estate developments in prime locations in Dubai. These include the Carlyle Residences in DIFC; an Eden Hills villa community in Mohammed Bin Rashid City; and Dubai Peninsula, a waterfront scheme in the Jumeirah area that will include hotels operated by Aman and Rosewood.

    “We are awarding day in, day out,” says Lutfi. “I think we are awarding most of our contracts from now until summer next year.”

    Most of the company’s construction volume is in DIFC and Dubai Peninsula, with the Eden Hills villas accounting for a smaller share. Lutfi says H&H is talking to several of the emirate’s biggest contractors about upcoming packages.

    We are awarding [contracts] day in, day out

    Staged procurement

    H&H is managing cost pressures by splitting up its procurement. It awards main contracts covering concrete works with a large number of provisional sums, then tenders further packages as designs are completed. “We are taking on some of the risk, but we know how to manage the risk instead of just offloading it on the contract,” says Lutfi.

    He does not expect construction costs to fall in the next 12 months. Global inflation, driven by fuel prices and logistics costs, is already factored into the company’s plans. 

    “Waiting and trying to award at a cheaper price is not an option for us,” he says.

    Lutfi says rising costs need not erode margins for developers that keep unsold stock to sell at higher prices later in a project. Developers that sell out early are more exposed. “If you have already sold out two years ago, you are hurting your profitability,” he says.

    H&H is comfortable leaving 15%-20% of a project to sell on completion. The market usually expects developers to sell out before handover. 

    The company has not revised its masterplans or product mix in response to market conditions and continues to focus on large units.

    Supply chains have been a challenge this year, but Lutfi says the company is over that hurdle. H&H has sourced more materials locally and planned logistics further in advance. 

    Materials are reaching Dubai through bonded routes from Oman, Fujairah and Khor Fakkan in the UAE, and Jeddah in Saudi Arabia. 

    “It takes a little bit longer, but at least things are coming in,” he says.

    H&H relies on a relatively small group of contractors that work on most of its projects, and treats them as long-term partners. 

    Lutfi says contractors are attracted by the company’s financial stability and volume of work. “That can keep some people busy for the next five or six years,” he says.

    Lutfi notes that sales in the Dubai market have dropped, although enquiries have picked up since the summer as buyers weigh whether it is the right time to purchase. The distressed sales that some had expected have not materialised.

    “A 5% discount in some units is not really a distress sale,” he says. “It is just someone trying to get a discount because of the region’s situation, which actually builds confidence.”

    For Water Gardens, H&H has sold 85% of Four Seasons Private Residences Dubai at DIFC since sales began in 2024. The company launched sales at the Carlyle Residences before the regional disruption and has since sold units one-to-one to selected clients. More Four Seasons units have been sold in the past two weeks. 

    “Branding makes a big difference,” says Lutfi.

    The company markets its branded residences through a global network of brokers rather than via public campaigns or launch events. Eden Hills, which is aimed mainly at Dubai residents, is marketed more widely.

    Lutfi expects buyers to be more cautious about buying off-plan. H&H is building new sales centres at Dubai Peninsula and in DIFC so that clients can see the product before they commit. 

    “People have to come in, know exactly what they are buying, and they will feel comfortable paying the price – instead of just having a pretty brochure,” he says.

    He expects demand for villas to become more local and regional, while branded residences will continue to attract international buyers. 

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21012636/main.gif
    Colin Foreman
  • Riyadh Expo sets November bid deadline for Souq construction

    29 October 2026

     

    Expo 2030 Riyadh Company (ERC), responsible for delivering the Expo 2030 Riyadh venue, has allowed contractors until 11 November to submit bids for a contract to deliver the Souq areas within the Expo site.

    The tender was floated on 30 July, with an initial submission deadline of 9 October.

    The Souq areas are divided into five distinct precincts, with a total development area of about 300,000 square metres (sq m).

    The scope includes the five precincts and their associated vertical elements, infrastructure and public realm works. 

    The precincts comprise:

    • Precinct 1 – The Icon: 41,417 sq m
    • Precinct 2 – Place & Planet: 62,306 sq m 
    • Precinct 3 – Culture of Wisdom: 67,112 sq m  
    • Precinct 4 – Kingdom of Saudi Arabia: 45,967 sq m  
    • Precinct 5 – Adaptation & Innovation: 82,358 sq m

    The package will interface with three public parks. It will also tie into the Natural Corridor, including bridges.

    The Souq areas will form a mixed-use destination at the centre of Expo 2030 Riyadh, connecting the site’s iconic and thematic assets.

    The development will include rented and partnership pavilions, alongside a range of food and beverage, retail and visitor-experience offerings.

    Site progress

    Construction activity at the Expo site is accelerating, with Riyadh moving to award its first major vertical contracts and advancing infrastructure works across the programme.

    Earlier this month, Saudi Arabia’s Royal Commission for Riyadh City awarded a design-and-build contract to build a new metro station serving the Expo 2030 site.

    In April, ERC awarded two contracts to local firm Al-Yamama Company for the next phase of infrastructure works at the site.

    The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.

    These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners.

    That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.

    The masterplan covers 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.

    The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20998514/main.jpg
    Yasir Iqbal
  • Iraq oilfield water scheme to hit milestone next year

    29 October 2026

     

    China Petroleum Pipeline Engineering (CPP) expects to start laying pipeline for Iraq’s Common Seawater Supply Project (CSSP) in Basra in mid- or late next year, according to industry sources.

    The project is behind schedule, partly because importing sections of pipeline is proving challenging due to disruptions to shipping through the Strait of Hormuz.

    The project is being managed by state-owned Basra Oil Company (BOC), with Australia’s ILF acting as a project management consultant after completing the front-end engineering design (feed).

    Under current plans, the pipelines will be buried, which is expected to make them more secure than if they were installed on the surface.

    Phased development

    The client for the first phase of the CSSP is France’s TotalEnergies in partnership with QatarEnergy and BOC.

    The first phase is split into two packages currently under execution and will ultimately have the capacity to transport 5 million barrels a day (b/d) of water.

    The first package focuses on developing pipelines, and the second on developing a water treatment facility.

    CPP is executing the pipeline package contract.

    It signed a $2.5bn contract with BOC for the package in September last year.

    Also in September 2025, South Korea’s Hyundai announced that it had signed a contract worth 4.39tn won ($3.16bn) for the processing plant package.

    In September this year, MEED reported that early groundworks had started for both packages of the first phase of the CSSP.

    Phase one of the project is scheduled to start up in late 2028 or early 2029.

    Earlier this month, US-headquartered Exxon Mobil signed a memorandum of understanding related to the project’s second phase, which is expected to add 2.5 million b/d of water capacity.

    The CSSP will inject processed water into several of Iraq’s biggest oil fields. These include Rumaila, Zubair, West Qurna 1, West Qurna 2 and Majnoon. Water from the project will also be used in the Maysan and Dhi Qar fields.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20981033/main.jpg
    Wil Crisp
  • Dubai tenders Al-Awir sewerage and stormwater works

    29 October 2026

     

    Dubai Municipality has invited contractors to bid for a contract to build sewerage and stormwater infrastructure in New Al-Awir 1st.

    The project (DS317-C1) comprises about 95 kilometres of sewerage gravity network, excluding house connections, and about 105km of stormwater pipelines. The scope also includes house connection pipes, a stormwater pond and oil interceptors.

    According to tender documents seen by MEED, the tender was issued on 23 October, with a bid submission deadline of 12 November.

    The project comes amid wider residential and infrastructure development in Al-Awir 1. In January 2025, Dubai’s Roads & Transport Authority (RTA) announced plans to build 16.5km of internal roads in the area, including a new entrance from Emirates Road.

    In February 2025, MEED exclusively reported that the RTA had selected a local firm to undertake the road construction works.

    The Mohammed Bin Rashid Housing Establishment has also reported progress on housing projects in Al-Awir as part of a wider programme to develop residential communities across Dubai.

    The sewerage and stormwater project is relatively large compared with recent stormwater tenders, with the total cost estimated at up to AED1bn ($272m).

    The works will include approximately 69.2km of house connection pipes and 4,630 inspection chambers. The sewerage network will also include about 1,511 manholes, while the stormwater network will comprise approximately 1,247 manholes.

    Contractors will also be required to use no-dig construction methods for sections of the pipeline. The scope includes ground investigations, utility protection and traffic management.

    The bill of quantities specifies a stormwater pond with a composite volume of approximately 1.2 million cubic metres.

    Earlier this week, Dubai Municipality confirmed it had awarded contracts worth AED3bn ($817m) to expand the emirate’s stormwater drainage network by about 100 square kilometres under phase three of the Tasreef programme.

    The projects are part of Dubai’s AED30bn Tasreef programme and will cover Jumeirah, Umm Suqeim, Al-Quoz, Al-Barsha, Al-Wasl and Al-Marmoom. 

    The overall programme aims to increase the emirate’s stormwater drainage capacity by 700% and reduce costs associated with pumping stations, network operations and maintenance by 20%.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20977734/main.jpg
    Mark Dowdall
  • Contractors bid for QatarEnergy’s North Field West topsides

    28 October 2026

     

    QatarEnergy has received technical bids from contractors for a key tender covering the engineering, procurement, construction and installation (EPCI) of large platforms for the North Field gas field in Qatari waters.

    Contractors submitted their technical bids by the 26 October deadline, according to sources.

    Commercial bids are currently due on 10 November.

    The following contractors, among others, are understood to be bidding for the North Field West (NFW) production deck modules (PDMs) tender:

    • China Offshore Oil Engineering Company (China)
    • Larsen & Toubro Energy Hydrocarbon (India)
    • McDermott (US)
    • Saipem (Italy)

    The core scope comprises the EPCI of four PDMs and associated structures. The modules will increase gas production from North Field reservoirs and supply additional gas feedstock to the NFW liquefied natural gas (LNG) development.

    Issued earlier this year, the tender forms part of the wider NFW project, the third and final phase of QatarEnergy’s North Field LNG expansion programme.

    The technical-bid deadline has been extended several times, from 30 August to 15 September, 28 September, 12 October and 19 October. Commercial bids were previously due on 25 October, as MEED reported.

    Before issuing the PDMs tender, QatarEnergy awarded US firm McDermott an EPCI contract for four offshore jackets to support gas feedstock supply for the NFW LNG project. The contract is estimated to be worth about $200m, MEED reported in January.

    North Field LNG expansion

    QatarEnergy is advancing the three phases of its estimated $40bn North Field LNG expansion project. EPC works on all three projects are progressing.

    QatarEnergy is understood to have committed nearly $30bn to the first two phases – North Field East (NFE) and North Field South (NFS) – which will lift Qatar’s LNG production capacity from 77.5 million tonnes a year (t/y) to 126 million t/y by 2028.

    QatarEnergy awarded the main EPC contracts for NFE in 2021. The project was intended to raise LNG output to 110 million t/y by 2025. The $13bn EPC package – covering the EPCI of four LNG trains, each with a capacity of 8 million t/y – was awarded in February 2021 to a consortium of Japan’s Chiyoda and France’s Technip Energies.

    In May 2023, QatarEnergy awarded the $10bn main EPC contract for NFS to a consortium of Technip Energies and Consolidated Contractors Company (CCC). The contract includes two LNG trains, each with a capacity of 7.8 million t/y.

    Once fully operational, the first two phases are expected to add 48 million t/y of LNG supply to the global market.

    QatarEnergy took the final investment decision on NFW earlier this year, awarding an EPC contract estimated at $8bn to a joint venture comprising Technip Energies, CCC and Gulf Asia Contracting in February.

    Chiyoda carried out the front-end engineering and design work for the NFW LNG project.

    The NFW scope covers the EPC of two LNG trains with a combined capacity of 16 million t/y, as well as associated facilities for gas treatment, natural gas liquids recovery and helium extraction.

    In addition to LNG, NFW is expected to produce about 175,000 barrels of oil equivalent a day of condensate, ethane and liquefied petroleum gas.

    With all three phases under EPC execution – and NFE scheduled for commissioning later this year – QatarEnergy is positioning itself to remain one of the world’s largest LNG suppliers in the long term.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20973187/main.jpg
    Indrajit Sen