Saudi Arabia under project pressure
28 March 2023

Saudi Arabia’s projects market is overheating. The volume of projects announced in the past six years vastly exceeds the resources that are available to work in the kingdom.
Combined with tight deadlines to complete projects as part of Vision 2030, the pressure on the construction industry to deliver is ratcheting up and turning the tables on the supply chain as the shift from a buyer’s to a seller’s market accelerates.
For the five years from 2016 to 2020, there was an average of about $14bn-worth of contract awards a year in Saudi Arabia for the construction and transport sectors. After rising to $21bn in 2021, the total rose to $32bn in 2022 – the second-best year on record.
The near doubling of the total annual value of contract awards by the end of 2022 has required a significant scale-up of resources in the kingdom, and the ramp-up is set to continue.
Much of this pressure is due to the five official gigaprojects, which are major programmes of work that will involve a sustained flow of contract awards for years to come.
Gigaproject focus
The project most recently classified as a gigaproject by the Saudi authorities is the Diriyah Gate development on the western outskirts of Riyadh. It joins the $500bn Neom development in the northwest of the kingdom, Qiddiya entertainment city outside Riyadh, Red Sea Global’s projects on the Red Sea coast and Roshn’s housing developments across the kingdom.
These projects are relatively new. They began to be launched in 2017 and spent much of the following three years in the design phase.
After a start that was hampered by the work and travel restrictions required to manage the Covid-19 pandemic, construction activity on these projects has accelerated sharply since the start of 2022.
According to regional project tracker MEED Projects, there have been $36bn-worth of contract awards across these official gigaprojects since 2017. Compared to the entire Saudi projects market over the same period that represents 14.5 per cent of contract awards.
The percentage rises to 20 per cent if a more recent time frame is used and only contract awards since the start of 2022 are included. As work gathers pace on the gigaprojects, their significance is expected to grow even further.
More major projects
Saudi Arabia’s ambitions are not limited to the five gigaprojects. In January, Crown Prince Mohammed bin Salman al-Saud launched the world’s largest modern downtown in Riyadh.
Known as the New Murabba project, it involves the development of 19 square kilometres of land to the northwest of the capital. The centrepiece of the project is the Mukaab, which is a 400-metre-cubed structure with a tower standing inside it.
New Murabba is part of a plan announced in January 2021 to double the size of Riyadh from 7.5 million residents to 15-20 million residents in 2030. Other major projects in the capital include King Salman International airport, King Salman Park, Sports Boulevard and Mohammed bin Salman Non-Profit City.
Beyond the capital there are development projects planned in all major urban centres by Saudi Downtown Company, as well as entertainment centres being developed by Saudi Entertainment Ventures (Seven).
Connecting these cities and projects will be railways, roads, ports and airports that form part of the National Transport & Logistics strategy, which aims to turn the kingdom into a global hub for travel and trade by 2030.
World’s largest piling project shifts to The Line’s marina
Resourcing challenges
One of the key challenges for the development firms and government agencies responsible for delivering these projects is securing the resources they need.
As client bodies attempt to make their projects more attractive for companies to work on, the industry is changing. The first signs of this change can be seen in the consultancy market.
After years of searching for project opportunities, the big consultancy businesses are now only selectively bidding for projects in the kingdom. This is because their orderbooks are already full, and for many international firms there is a concern that they could become over-exposed to the Saudi market.
On contracts that have already been won there are also challenges. Staffing projects is proving difficult as the kingdom remains a hard sell for many project professionals, despite significant social reforms that have taken place in recent years.
Then, once staff have been recruited and deployed on projects, there is the prospect of losing them to competitors or clients that require the same human resources.
Securing contractors
As activity on site accelerates, the bigger concern is contracting resources. As things stand, there are not enough contractors working in Saudi Arabia to deliver all of the planned projects.
The first way to deal with this problem is to increase the capacity of contractors in the kingdom. In February this year, the Public Investment Fund (PIF) invested $1.3bn in four local construction firms: Al-Bawani Holding Company, Almabani General Contractors Company, El-Seif Engineering Contracting Company and Nesma & Partners Contracting Company.
This investment will allow the companies to scale up their capacity, adopt advanced technologies and improve local supply chains.
As these firms grow, the hope is that it will encourage other local companies to also expand.
International or regional companies can also help, and over the past two years foreign players have become active in the kingdom again. Firms such as Bouygues, Samsung C&T, Hyundai Engineering Construction, China State, Webuild, FCC, Alec, Consolidated Contractors Company and Urbacon Trading Contracting Company have all secured major orders.
In some cases, these contract awards have been supported with foreign finance, which gives the contractor an additional level of comfort when it comes to potential payment for projects. For others, the contract awards reflect growing assurance in the Saudi market.
Boosting appeal
Confidence has been lifted by measures to make the Saudi market more attractive. Payment terms are improving and many of the frustrations typically faced by contractors are being addressed.
One example is the use of performance guarantees. Red Sea Global, which is developing the Red Sea Project and Amaala gigaprojects on the Red Sea coast, no longer requires contractors to submit bid bonds and returns performance bonds on completion of the project, along with half of the retention.
Alternative procurement methods and contract types are also being used, notably early contractor involvement and design and build.
These different approaches reduce risk for the contractor and allow the client to lock in resources at a much earlier stage of the procurement process.
Red Sea Global has adopted a different approach and is self-delivering the bulk of its projects. By acting as its own management contractor, it engages with subcontractors itself. While this means it does not need to secure the services of a main contractor, it still requires engaging with the supply chain, which – like the main contractor market – has finite resources in Saudi Arabia.
Payment terms are improving and many of the frustrations typically faced by contractors are being addressed
Driving efficiency
On the other side of the equation, making construction more efficient could also help to limit the resources required.
Client bodies are exploring modern methods of construction to increase the speed of delivery, reduce costs and cut the amount of resources needed on site.
The market could also be self-limiting. Decision-making in the kingdom remains centralised, which means key project decisions can be slow. While this is changing as development companies are left to run their own projects, bureaucracy can impact the speed of delivery, which ultimately reduces the immediate demand for resources on a project.
While slow decision-making could impact progress on some projects, the overriding story for 2023 will be one of sustained pressure on the kingdom’s construction sector as it becomes a seller’s market.
With that, there is the likelihood that contractor margins will start to creep up, just as they did in the UAE when its construction market overheated in 2003 and 2008.
So far, that does not appear to have happened, as clients in Saudi Arabia have managed to find sufficient resources. For that to remain the case will be a major challenge, however, as on-site activity for most projects in the kingdom is still several years away from peaking.
|
International contractors continue to see a level of risk in the Saudi market “There is a lot of opportunity. A large volume of work is being planned, designed and rolled out. With that, there is significant pressure right now on the market in terms of resources and supply chain. “On the consultancy side, the market is tremendously difficult. “Even with the best incentives and best set of practices, retaining staff is a challenge. People are being attracted elsewhere and the competition is fierce. “For the contractors, there are a lot of tenders being let. The perception that the market has risk remains, however. That is certainly the perception for international contractors, and they are still looking at the Saudi market with some level of risk appreciation in terms of how quickly they are going to be paid and what the margins really are. “That approach will likely prevail for the short to medium term, until clients’ practices change in terms of contractual frameworks and payment practices. “Varied procurement practices are coming into play to guarantee supply chain. It might be early contractor involvement or partnering, but the main purpose is to guarantee the right level of contractors.” |
|
To prevent resource shortages, supply chain and procurement must be carefully considered “It is imperative to consider alternative methods of procurement during boom times, and the current boom in Saudi Arabia is unprecedented considering the types, size, nature and complexity of projects that have been announced in line with Vision 2030. “This necessitates giving due consideration to the supply chain and type of procurement. “It is not enough to look for resources locally or even regionally to cope with such projects. One needs to reach out to where such resources are available globally, either due to slowdowns in certain regions or the completion of other major projects. “Cost-plus contracts were used previously in many projects in Saudi Arabia. However, the risk for such contracts rests with the client and sometimes the cost ends up much more than expected. That is why financiers prefer the lump-sum type of contracts. “Nonetheless, I can see this type of contract being used for fast-track projects with very tight schedules, for instance to meet deadlines for facilities required for international or regional sporting events. “In any case, the evaluation and selection of contractors needs to be done with extreme diligence.” |
MEED's April 2023 special report on Saudi Arabia includes:
> ECONOMY: Riyadh steps up the Vision 2030 tempo
> CONSTRUCTION: Saudi construction project ramp-up accelerates
> UPSTREAM: Aramco slated to escalate upstream spending
> DOWNSTREAM: Petchems ambitions define Saudi downstream
> POWER: Saudi Arabia reinvigorates power sector
> WATER: Saudi water begins next growth phase
> BANKING: Saudi banks bid to keep ahead of the pack
Exclusive from Meed
-
Adnoc Distribution signs deal to enter South Africa14 July 2026
-
Expo 2030 Riyadh construction gathers pace14 July 2026
-
-
Jordan tenders IPP8 power project14 July 2026
-
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Adnoc Distribution signs deal to enter South Africa14 July 2026
Adnoc Distribution, the fuel retailing business of Abu Dhabi National Oil Company (Adnoc Group), has entered into a definitive agreement to acquire 100% of the share capital of UK energy major Shell’s downstream unit in South Africa.
The proposed acquisition is estimated to have an enterprise value of approximately $1bn for 100% of the share capital of Shell Downstream South Africa (SDSA), part of Shell South Africa Holdings, prior to adjustment for net debt and working capital.
The transaction is expected to close in 2027, subject to customary regulatory conditions, other conditions precedent and closing conditions, Abu Dhabi Securities Exchange-listed Adnoc Distribution said.
Additionally, Adnoc Distribution intends to sell a 28% stake in SDSA to a local empowerment partner and employee stock option plan following completion of the acquisition.
Furthermore, Adnoc Distribution will enter into a long-term brand licensing agreement upon completion of the acquisition, to retain the Shell brand for retail service stations and lubricants businesses in South Africa.
BofA Securities acted as the sole financial advisor. A&O Shearman and ENS provided legal counsel to Adnoc Distribution on the transaction.
SDSA represents Shell’s downstream business in South Africa, including a network of 580 company- and dealer-owned mobility and convenience sites, as well as lubricants, commercial fuels, aviation and marine businesses. The brand had fuel volumes of approximately 3.5 billion litres and operated 360 convenience stores as of 2025.
The proposed acquisition will mark a step forward in Adnoc Distribution’s international expansion, as well as in its drive to grow its fuel retail presence in Africa.
South Africa is the fourth country where Adnoc Distribution will operate and follows its acquisition of a 50% stake in TotalEnergies Marketing Egypt in 2023 and the 2018 launch of its retail fuel stations in Saudi Arabia.
Established in 1973, Adnoc Distribution has 1,032 service stations – 568 in the UAE, 219 in Saudi Arabia and 245 in Egypt, as of 31 March this year.
As a non-fuel retail leader in the UAE, it operates 386 Adnoc Oasis convenience stores, 37 vehicle inspection centres and other services such as car wash and lube change, and has 400 electric vehicle charging points installed under the E2Go brand in the UAE.
The company is also a marketer and distributor of fuels to commercial, industrial and government customers throughout the UAE.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17664769/main4804.jpg -
Expo 2030 Riyadh construction gathers pace14 July 2026

Construction activity at the Expo 2030 Riyadh site is accelerating, with Expo Riyadh 2030 Company (ERC) moving to award its first major vertical contracts and advancing infrastructure works across a programme that will eventually require between 50,000 and 70,000 workers at peak.
Saudi Arabia’s first World Expo runs from 1 October 2030 to 31 March 2031. Riyadh was awarded the hosting rights in November 2023, winning the vote in the first round, and the event is projected to attract more than 40 million visits over its six months. Beyond the event itself, the project carries significant economic weight: ERC, wholly owned by the Public Investment Fund (PIF), expects the construction phase and legacy development to contribute around $64bn to Saudi GDP and generate approximately 171,000 direct and indirect jobs, with the live event contributing a further $5.6bn.
The masterplan covers 6 million square metres to the north of Riyadh, adjacent to the future King Salman International airport. After the event closes, ERC plans to transform the site into a global village combining retail, food and beverage and an international residential community – meaning every asset being built now is being designed with its post-Expo purpose in mind.

Infrastructure works under way
The earliest works on site – bulk earthworks including cut, fill and levelling – have been completed by local contractor Binyah, with millions of cubic metres of material moved to bring the site to design level.
The programme has now moved into utility infrastructure, which has been split into two packages. Nesma is constructing the primary utility networks – the main corridor running around the site carrying high-voltage power lines, water mains, sewerage and communications – while Al-Yamama is delivering the secondary networks that bring services into the central event area, with construction expected to commence this month.
Power has been a priority. ERC has worked with the Saudi electricity sector since 2025 to develop the site’s demand profile, and an agreement for permanent supply has been signed. Design and procurement of the main substation and primary power infrastructure are under way, with a contract award expected within weeks and full permanent power – at a capacity of 400MW – targeted approximately 18 months ahead of the event.
An initial 25MW supply to power site operations and support testing and commissioning is already installed and ready to be energised.
On water, ERC is finalising an agreement with the Royal Commission for Riyadh City (RCRC), the Saudi Water Authority and the National Water Company, with an announcement expected in Q3 and construction targeted to start in 2027.
Transport and connectivity
With more than 42 million visits anticipated over the six-month event, transport connectivity is treated as central to the project’s success. ERC is working with RCRC on a mobility plan that covers several modes. Two road enhancement projects around the airport and along King Salman Road are expected to be announced shortly, increasing capacity on the main arteries approaching the site.
A dedicated Expo metro station on Riyadh Metro Line 4 – which connects the airport to the city centre – will be built within the site boundary, forming the first stop from the airport towards Riyadh, and providing a direct link for international arrivals.
A park-and-ride programme using dedicated bus lanes will serve domestic visitors parking at locations across the city.
A hotel within the fenced Expo site is also nearing contract, with a design agreement close to signature. ERC says the intention is to give guests staying on site “the full experience from early morning when the gates open until late at night when the gates close” – an offer it expects will prove particularly popular with international visitors.

Pavilions and vertical assets
The Expo's masterplan is organised around five districts, each echoing one of the event’s sub-themes under its overarching theme of Foresight for Tomorrow: planet, people, technology, collaboration and culture. ERC is responsible for delivering a signature pavilion in each district, plus an iconic structure in the Global Collaboration district and a convention centre intended to serve both the event and Riyadh’s long-term conference market.
The Kingdom of Saudi Arabia (KSA) Pavilion, one of the centrepieces of the event, is also under ERC’s delivery responsibility. Design work is progressing across all these assets with engineering firms taking concepts through to schematic and detailed design.
For international participating countries, this edition of the Expo marks a significant departure from previous editions. Rather than grouping lower-income countries into shared halls, all participants will have their own national pavilion.
“In this edition, we are following the ‘one nation, one pavilion’ model, whereby each country has its own pavilion, and we have a dedicated budget to help up to 100 eligible countries deliver those pavilions,” says Murad Al-Sayed, ERC’s chief delivery officer.
Contracting strategy
The contracting approach for vertical assets is being calibrated to the complexity of each building. Less complex assets will be procured on a design-and-build basis.
For the most complex – the KSA Pavilion and the iconic structure – ERC is using a two-stage model, separating enabling works and substructure from the main contract. This allows construction to begin on site while the main package is finalised and brings contractors into the design process earlier.
“We are adopting different contracting strategies depending on the asset – its size, complexity and anticipated construction duration,” Al-Sayed says.
For the KSA Pavilion, enabling and substructure works are already in the market, with an award targeted in Q3, allowing construction to start before the main contract – for which nine tier-one contractors, local and international, have been invited to bid – is awarded towards the end of the year. Packages for the remaining signature pavilions are expected to follow later this year and into 2027.
On commercial terms, ERC is favouring lump-sum contracts where design maturity allows, with provisional sum or remeasurement provisions used where elements remain in development. A final public realm package, covering site-wide finishing works, remains under design and is expected to be tendered in 2026, sequenced deliberately to be installed last and once only ahead of the event.
Bidding appetite from the market has been strong. ERC says all tenders issued to date have attracted healthy numbers of qualified bids, reflecting a contracting market that has eased over the past 18 months as several gigaprojects elsewhere in the kingdom have reached completion or had their timelines revised.
Programme and supply chain
ERC is targeting completion of major construction by the end of 2029, leaving six to nine months for finishing, snagging and operational testing. To ease the build programme for international participants, ERC is making plots available up to 36 months before the event – around nine to 12 months longer than the industry norm – giving countries more schedule float to complete their pavilions.
On the supply chain, ERC is leaning heavily on local manufacturers for current infrastructure work, covering piping, cabling, electrical equipment and bulk materials. As construction moves above ground and international participants begin work on their pavilions from 2027 onwards, ERC will make its database of prequalified local contractors, suppliers and consultants available to them through a dedicated one-stop shop – a registration exercise already under way and expected to remain open until the event itself.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17664502/main.gif -
Masdar reaches financial close on world-first 24/7 solar project14 July 2026
Abu Dhabi Future Energy Company (Masdar) has reached financial close on the world's first gigascale round-the-clock renewable energy project, securing a $5.1bn financing package from a consortium of 13 international and local banks.
The project, being developed in Abu Dhabi with state offtaker Emirates Water & Electricity Company (Ewec), represents a total capital investment of $6.1bn, with Masdar providing $1bn of equity. It integrates a 5.2GW solar photovoltaic (PV) plant with a 19 gigawatt-hour battery energy storage system, which Masdar says is the largest of its kind in the world.
The 13 lenders providing the financing are Abu Dhabi Commercial Bank, Abu Dhabi Islamic Bank, France's BNP Paribas, Bank of China, France's Credit Agricole Corporate & Investment Bank, Dubai Islamic Bank, First Abu Dhabi Bank, UK-based HSBC, Germany's KfW Ipex-Bank, France's Natixis, Japan's Sumitomo Mitsui Banking Corporation, UK-based Standard Chartered Bank and France's Societe Generale.
The independent power project is designed to deliver 1GW of baseload power around the clock, addressing the challenge of solar intermittency by pairing large-scale generation with battery storage. It is intended to serve large energy users requiring 24/7 clean electricity, including data centre operators and technology firms driving artificial intelligence deployment in the region.
Ewec will act as offtaker under a long-term power purchase agreement, while private offtakers such as data centres will access electricity through back-to-back arrangements.
India's Larsen & Toubro and Beijing-headquartered PowerChina are handling engineering, procurement and construction works, with PwC Middle East advising Ewec on financial structuring. China's CATL will supply the battery storage system, while Jinko Solar and JA Solar will each provide 2.6GW of PV modules.
Masdar broke ground on the project in October 2025, and it is expected to be operational in 2027. The scheme will avoid 5.7 million tonnes of carbon dioxide emissions a year and provide enough clean energy to power nearly half a million homes.
The developer has a diversified portfolio of more than 65GW and has set a target of reaching 100GW of renewable energy capacity by 2030.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17664609/main.jpg -
Jordan tenders IPP8 power project14 July 2026
Jordan’s National Electric Power Company (Nepco) has issued a tender for a contract to develop the 700MW combined-cycle gas turbine (CCGT) power project known as independent power project 8 (IPP8).
Companies understood to have prequalified include France’s EDF, Saudi Arabia’s Acwa and Egypt’s Orascom Construction. Bids are due in July, although the market expects the closing date may be extended.
MEED reported in November last year that Nepco had invited developers to submit prequalification documents for IPP8. The project will be developed on a build, own and operate (BOO) basis and will supply power to the national grid under a 25-year agreement.
Natural gas will serve as the primary fuel, with light distillate as backup. The facility will be connected to Nepco’s 132kV/400kV transmission infrastructure, which will be built separately.
In April, MEED reported that Nepco had signed an agreement to establish a natural gas supply point for the 700MW IPP7. The agreement was signed with Fajr Jordanian-Egyptian for Natural Gas Transmission and Supply to support fuel provision for the CCGT plant.
The plant will be developed in partnership with Etihad Development Company, a subsidiary of the UAE’s Etihad Water & Electricity (EtihadWE), following recent approval by the Ministry of Energy & Mineral Resources.
The IPP7 plant is expected to meet about 10% of Jordan’s electricity demand once operational. It is also intended to enhance the reliability and efficiency of the national power system.
The project is scheduled to become operational between 2027 and 2028.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17662814/main.jpg -
Indian firm wins Oman’s Al-Dhahirah economic zone deal14 July 2026
Oman Shapoorji Company, the local branch of India's Shapoorji Pallonji, has won an estimated $67m contract to construct an administrative and commercial buildings complex within the Economic Zone at Al-Dhahirah (Ezad).
The scope of work includes the construction of an administration building, a commercial centre, a hotel and a health centre.
The scope also covers the construction of roads, sewers and water, irrigation and landscaping works.
Oman’s Public Authority for Special Economic Zones & Free Zones (Opaz) tendered the contract.
In July last year, MEED reported that Opaz had signed seven agreements and memorandums of understanding (MoUs) for the first phase of development of Ezad.
The zone is located in Al-Dhahirah Governorate in northwestern Oman, on the sultanate’s borders with Saudi Arabia and the UAE. Oman’s Finance Ministry and the Saudi Fund for Development signed an MoU in February 2023 to jointly invest $320m in developing Ezad.
Among the agreements was a contract awarded by Opaz for the construction of main roads and the surface water drainage system at Ezad, valued at $58m. A consortium of Omani and Saudi contractors won the contract, which had a duration of 24 months.
Opaz awarded two further contracts for engineering consultancy work to Oman-based Al-Watanyiah United Engineering and Saudi Arabia’s Dar Al-Riyadh. As part of their contracts, both firms were to prepare architectural, structural and infrastructure designs for projects in Ezad; provide technical advice; perform feasibility studies; and assist with approvals.
Opaz intends to develop 20 square kilometres (sq km) of the total land area allocated to Ezad as part of the first phase of development, with 7.5 sq km of that earmarked for fast-track development.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17661726/main.gif

Daniel King, director, Currie & Brown
Adel Karem Jemah, senior vice-president, Hill International