Saudi Arabia under project pressure
28 March 2023

Saudi Arabia’s projects market is overheating. The volume of projects announced in the past six years vastly exceeds the resources that are available to work in the kingdom.
Combined with tight deadlines to complete projects as part of Vision 2030, the pressure on the construction industry to deliver is ratcheting up and turning the tables on the supply chain as the shift from a buyer’s to a seller’s market accelerates.
For the five years from 2016 to 2020, there was an average of about $14bn-worth of contract awards a year in Saudi Arabia for the construction and transport sectors. After rising to $21bn in 2021, the total rose to $32bn in 2022 – the second-best year on record.
The near doubling of the total annual value of contract awards by the end of 2022 has required a significant scale-up of resources in the kingdom, and the ramp-up is set to continue.
Much of this pressure is due to the five official gigaprojects, which are major programmes of work that will involve a sustained flow of contract awards for years to come.
Gigaproject focus
The project most recently classified as a gigaproject by the Saudi authorities is the Diriyah Gate development on the western outskirts of Riyadh. It joins the $500bn Neom development in the northwest of the kingdom, Qiddiya entertainment city outside Riyadh, Red Sea Global’s projects on the Red Sea coast and Roshn’s housing developments across the kingdom.
These projects are relatively new. They began to be launched in 2017 and spent much of the following three years in the design phase.
After a start that was hampered by the work and travel restrictions required to manage the Covid-19 pandemic, construction activity on these projects has accelerated sharply since the start of 2022.
According to regional project tracker MEED Projects, there have been $36bn-worth of contract awards across these official gigaprojects since 2017. Compared to the entire Saudi projects market over the same period that represents 14.5 per cent of contract awards.
The percentage rises to 20 per cent if a more recent time frame is used and only contract awards since the start of 2022 are included. As work gathers pace on the gigaprojects, their significance is expected to grow even further.
More major projects
Saudi Arabia’s ambitions are not limited to the five gigaprojects. In January, Crown Prince Mohammed bin Salman al-Saud launched the world’s largest modern downtown in Riyadh.
Known as the New Murabba project, it involves the development of 19 square kilometres of land to the northwest of the capital. The centrepiece of the project is the Mukaab, which is a 400-metre-cubed structure with a tower standing inside it.
New Murabba is part of a plan announced in January 2021 to double the size of Riyadh from 7.5 million residents to 15-20 million residents in 2030. Other major projects in the capital include King Salman International airport, King Salman Park, Sports Boulevard and Mohammed bin Salman Non-Profit City.
Beyond the capital there are development projects planned in all major urban centres by Saudi Downtown Company, as well as entertainment centres being developed by Saudi Entertainment Ventures (Seven).
Connecting these cities and projects will be railways, roads, ports and airports that form part of the National Transport & Logistics strategy, which aims to turn the kingdom into a global hub for travel and trade by 2030.
World’s largest piling project shifts to The Line’s marina
Resourcing challenges
One of the key challenges for the development firms and government agencies responsible for delivering these projects is securing the resources they need.
As client bodies attempt to make their projects more attractive for companies to work on, the industry is changing. The first signs of this change can be seen in the consultancy market.
After years of searching for project opportunities, the big consultancy businesses are now only selectively bidding for projects in the kingdom. This is because their orderbooks are already full, and for many international firms there is a concern that they could become over-exposed to the Saudi market.
On contracts that have already been won there are also challenges. Staffing projects is proving difficult as the kingdom remains a hard sell for many project professionals, despite significant social reforms that have taken place in recent years.
Then, once staff have been recruited and deployed on projects, there is the prospect of losing them to competitors or clients that require the same human resources.
Securing contractors
As activity on site accelerates, the bigger concern is contracting resources. As things stand, there are not enough contractors working in Saudi Arabia to deliver all of the planned projects.
The first way to deal with this problem is to increase the capacity of contractors in the kingdom. In February this year, the Public Investment Fund (PIF) invested $1.3bn in four local construction firms: Al-Bawani Holding Company, Almabani General Contractors Company, El-Seif Engineering Contracting Company and Nesma & Partners Contracting Company.
This investment will allow the companies to scale up their capacity, adopt advanced technologies and improve local supply chains.
As these firms grow, the hope is that it will encourage other local companies to also expand.
International or regional companies can also help, and over the past two years foreign players have become active in the kingdom again. Firms such as Bouygues, Samsung C&T, Hyundai Engineering Construction, China State, Webuild, FCC, Alec, Consolidated Contractors Company and Urbacon Trading Contracting Company have all secured major orders.
In some cases, these contract awards have been supported with foreign finance, which gives the contractor an additional level of comfort when it comes to potential payment for projects. For others, the contract awards reflect growing assurance in the Saudi market.
Boosting appeal
Confidence has been lifted by measures to make the Saudi market more attractive. Payment terms are improving and many of the frustrations typically faced by contractors are being addressed.
One example is the use of performance guarantees. Red Sea Global, which is developing the Red Sea Project and Amaala gigaprojects on the Red Sea coast, no longer requires contractors to submit bid bonds and returns performance bonds on completion of the project, along with half of the retention.
Alternative procurement methods and contract types are also being used, notably early contractor involvement and design and build.
These different approaches reduce risk for the contractor and allow the client to lock in resources at a much earlier stage of the procurement process.
Red Sea Global has adopted a different approach and is self-delivering the bulk of its projects. By acting as its own management contractor, it engages with subcontractors itself. While this means it does not need to secure the services of a main contractor, it still requires engaging with the supply chain, which – like the main contractor market – has finite resources in Saudi Arabia.
Payment terms are improving and many of the frustrations typically faced by contractors are being addressed
Driving efficiency
On the other side of the equation, making construction more efficient could also help to limit the resources required.
Client bodies are exploring modern methods of construction to increase the speed of delivery, reduce costs and cut the amount of resources needed on site.
The market could also be self-limiting. Decision-making in the kingdom remains centralised, which means key project decisions can be slow. While this is changing as development companies are left to run their own projects, bureaucracy can impact the speed of delivery, which ultimately reduces the immediate demand for resources on a project.
While slow decision-making could impact progress on some projects, the overriding story for 2023 will be one of sustained pressure on the kingdom’s construction sector as it becomes a seller’s market.
With that, there is the likelihood that contractor margins will start to creep up, just as they did in the UAE when its construction market overheated in 2003 and 2008.
So far, that does not appear to have happened, as clients in Saudi Arabia have managed to find sufficient resources. For that to remain the case will be a major challenge, however, as on-site activity for most projects in the kingdom is still several years away from peaking.
|
International contractors continue to see a level of risk in the Saudi market “There is a lot of opportunity. A large volume of work is being planned, designed and rolled out. With that, there is significant pressure right now on the market in terms of resources and supply chain. “On the consultancy side, the market is tremendously difficult. “Even with the best incentives and best set of practices, retaining staff is a challenge. People are being attracted elsewhere and the competition is fierce. “For the contractors, there are a lot of tenders being let. The perception that the market has risk remains, however. That is certainly the perception for international contractors, and they are still looking at the Saudi market with some level of risk appreciation in terms of how quickly they are going to be paid and what the margins really are. “That approach will likely prevail for the short to medium term, until clients’ practices change in terms of contractual frameworks and payment practices. “Varied procurement practices are coming into play to guarantee supply chain. It might be early contractor involvement or partnering, but the main purpose is to guarantee the right level of contractors.” |
|
To prevent resource shortages, supply chain and procurement must be carefully considered “It is imperative to consider alternative methods of procurement during boom times, and the current boom in Saudi Arabia is unprecedented considering the types, size, nature and complexity of projects that have been announced in line with Vision 2030. “This necessitates giving due consideration to the supply chain and type of procurement. “It is not enough to look for resources locally or even regionally to cope with such projects. One needs to reach out to where such resources are available globally, either due to slowdowns in certain regions or the completion of other major projects. “Cost-plus contracts were used previously in many projects in Saudi Arabia. However, the risk for such contracts rests with the client and sometimes the cost ends up much more than expected. That is why financiers prefer the lump-sum type of contracts. “Nonetheless, I can see this type of contract being used for fast-track projects with very tight schedules, for instance to meet deadlines for facilities required for international or regional sporting events. “In any case, the evaluation and selection of contractors needs to be done with extreme diligence.” |
MEED's April 2023 special report on Saudi Arabia includes:
> ECONOMY: Riyadh steps up the Vision 2030 tempo
> CONSTRUCTION: Saudi construction project ramp-up accelerates
> UPSTREAM: Aramco slated to escalate upstream spending
> DOWNSTREAM: Petchems ambitions define Saudi downstream
> POWER: Saudi Arabia reinvigorates power sector
> WATER: Saudi water begins next growth phase
> BANKING: Saudi banks bid to keep ahead of the pack
Exclusive from Meed
-
Oil prices rise above $100 a barrel as conflict escalates9 September 2026
-
What actually slows a gigaproject down9 September 2026
-
Qatari firm wins $221m Qiddiya stadium MEP deal9 September 2026
-
Jordan tenders advisory for wastewater treatment plant9 September 2026
-
Consultants bid for Abu Dhabi light rail project management9 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Oil prices rise above $100 a barrel as conflict escalates9 September 2026
Register for MEED’s 14-day trial access
Oil prices rose above $100 a barrel on 9 September for the first time since July as the US-Iran conflict escalated and Iran-backed Houthi forces attacked Saudi energy infrastructure.
Brent crude futures reached $100.95 a barrel, while US benchmark West Texas Intermediate (WTI) rose to $95.60. Brent had last traded above $100 on 24 July.
The latest escalation has heightened concerns about oil supplies from the region, with shipping through both the Strait of Hormuz and the Red Sea facing disruption.
Flows through the Strait of Hormuz had fallen below 2 million barrels a day (b/d) from about 8-9 million b/d before the latest escalation, according to Rystad Energy.
At the same time, Houthi attacks on Saudi Arabia threaten another important route for oil exports, with the group targeting energy infrastructure and shipping in and around the Red Sea.
US strikes on Iranian tankers
US forces destroyed five Iranian crude oil carriers on 8 September after Iran’s Islamic Revolutionary Guard Corps (IRGC) targeted a US Navy warship with ballistic missiles.
The US Central Command (Centcom) said the warship successfully evaded two Iranian attacks and that no US personnel were harmed.
Four of the Iranian vessels – Kaviz, Charminar, Horizon 1 and Riesco – were struck in the Gulf of Oman, while the Derya was attacked near Kharg Island, Iran’s main crude export hub.
The M/T Riesco subsequently sank in the Gulf of Oman, according to Centcom.
Iran responded by launching ballistic missiles towards Jordan. Jordan’s armed forces said 18 of 20 missiles were intercepted, with the remaining two falling in unpopulated areas.
Iran’s IRGC also said it had attacked two US naval vessels, eight oil tankers and 10 other vessels in the Gulf, although it did not identify the vessels or provide evidence of the attacks.
The latest exchanges mark a further escalation in the US-Iran conflict, which began on 28 February.
Houthi attacks raise supply concerns
The conflict has also widened into a renewed confrontation between Saudi Arabia and Yemen’s Iran-backed Houthi movement.
On 8 September, Saudi authorities said Houthi attacks had targeted civilian and economic sites in Abha, Khamis Mushait, Jazan and Najran in the south of the kingdom, injuring 73 people.
Saudi Arabia’s Ministry of Energy said several energy sector facilities and installations had been targeted, causing fires and forcing a temporary halt to some operations.
The Houthis said their attacks were in response to Saudi military action in Yemen, including what they described as attacks on Houthi positions and a Saudi blockade of ports and airports.
Riyadh condemns attacks
Saudi Arabia has strongly condemned the Houthi attacks and warned that it would take measures to defend its territory and national assets.
In a statement on 8 September, the Ministry of Energy said authorities were working to address the impact of the attacks and ensure the safety of facilities and personnel while maintaining operations in accordance with approved plans.
Saudi Arabia’s Ministry of Foreign Affairs also condemned the attacks and said the kingdom had the right to take measures to defend its sovereignty and protect its citizens, residents and national assets.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19505512/main0138.jpg -
What actually slows a gigaproject down9 September 2026

Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.
“None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.
For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.
“The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.
The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.
“Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”
Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.
Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.
Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.
“The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”
Integration needs to be well understood
“Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.
Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.
Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.
“The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”
That shared view, he argues, will be what the next phase of Gulf delivery is judged on.
Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.
“This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.
From reporting progress to managing risk before it lands
Digital tools have a role here, Caldwell says, but not as a headline in themselves.
Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.
“The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."
None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”
Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.
With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.
“The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.
What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.
“The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif -
Qatari firm wins $221m Qiddiya stadium MEP deal9 September 2026

Register for MEED’s 14-day trial access
Qatari contractor Elegancia MEP, part of Estithmar Holding, has won a SR829m ($221m) mechanical package contract for the Prince Mohammed Bin Salman Stadium in Qiddiya, Saudi Arabia.
The contract covers full mechanical, electrical and plumbing (MEP) works for the stadium, and is Elegancia MEP’s largest award in Saudi Arabia to date.
The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.
The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.
Saudi gigaproject developer Qiddiya Investment Company awarded an estimated SR15bn ($4bn) deal to build the stadium in October 2024, as MEED exclusively reported.
The contract covered the construction of a multipurpose stadium on top of the 200-metre-high Tuwaiq cliff in the new sports and entertainment district of Qiddiya City.
Once completed, the stadium will be the home ground for Saudi Pro League football clubs Al-Nassr and Al-Hilal.
US-based architect Populous is the project consultant.
The stadium is one of the venues for the kingdom’s 2034 Fifa World Cup bid and will host events such as the Saudi King Cup, the Asian Cup and the 2034 Asian Games.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19501493/main.jpg -
Jordan tenders advisory for wastewater treatment plant9 September 2026
The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.
The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).
The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.
The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.
The submission deadline is 21 September.
The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.
The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.
The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.
WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.
The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.
The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg -
Consultants bid for Abu Dhabi light rail project management9 September 2026

Register for MEED’s 14-day trial access
Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.
The notice was issued on 7 September, with a submission deadline of 9 November.
The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.
The key sections of the tram are:
AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.
This section covers 13km and includes 13 at-grade stations and one underground station.
Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.
Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.
The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.
The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.
Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.
Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.
Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.
The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19493532/main.jpg

Daniel King, director, Currie & Brown
Adel Karem Jemah, senior vice-president, Hill International