Saudi Arabia under project pressure

28 March 2023

 

Saudi Arabia’s projects market is overheating. The volume of projects announced in the past six years vastly exceeds the resources that are available to work in the kingdom. 

Combined with tight deadlines to complete projects as part of Vision 2030, the pressure on the construction industry to deliver is ratcheting up and turning the tables on the supply chain as the shift from a buyer’s to a seller’s market accelerates.

For the five years from 2016 to 2020, there was an average of about $14bn-worth of contract awards a year in Saudi Arabia for the construction and transport sectors. After rising to $21bn in 2021, the total rose to $32bn in 2022 – the second-best year on record. 

The near doubling of the total annual value of contract awards by the end of 2022 has required a significant scale-up of resources in the kingdom, and the ramp-up is set to continue. 

Much of this pressure is due to the five official gigaprojects, which are major programmes of work that will involve a sustained flow of contract awards for years to come.

Gigaproject focus

The project most recently classified as a gigaproject by the Saudi authorities is the Diriyah Gate development on the western outskirts of Riyadh. It joins the $500bn Neom development in the northwest of the kingdom, Qiddiya entertainment city outside Riyadh, Red Sea Global’s projects on the Red Sea coast and Roshn’s housing developments across the kingdom.

These projects are relatively new. They began to be launched in 2017 and spent much of the following three years in the design phase. 

After a start that was hampered by the work and travel restrictions required to manage the Covid-19 pandemic, construction activity on these projects has accelerated sharply since the start of 2022. 

According to regional project tracker MEED Projects, there have been $36bn-worth of contract awards across these official gigaprojects since 2017. Compared to the entire Saudi projects market over the same period that represents 14.5 per cent of contract awards. 

The percentage rises to 20 per cent if a more recent time frame is used and only contract awards since the start of 2022 are included. As work gathers pace on the gigaprojects, their significance is expected to grow even further.

More major projects

Saudi Arabia’s ambitions are not limited to the five gigaprojects. In January, Crown Prince Mohammed bin Salman al-Saud launched the world’s largest modern downtown in Riyadh. 

Known as the New Murabba project, it involves the development of 19 square kilometres of land to the northwest of the capital. The centrepiece of the project is the Mukaab, which is a 400-metre-cubed structure with a tower standing inside it. 

New Murabba is part of a plan announced in January 2021 to double the size of Riyadh from 7.5 million residents to 15-20 million residents in 2030. Other major projects in the capital include King Salman International airport, King Salman Park, Sports Boulevard and Mohammed bin Salman Non-Profit City. 

Beyond the capital there are development projects planned in all major urban centres by Saudi Downtown Company, as well as entertainment centres being developed by Saudi Entertainment Ventures (Seven).

Connecting these cities and projects will be railways, roads, ports and airports that form part of the National Transport & Logistics strategy, which aims to turn the kingdom into a global hub for travel and trade by 2030.

World’s largest piling project shifts to The Line’s marina

Resourcing challenges  

One of the key challenges for the development firms and government agencies responsible for delivering these projects is securing the resources they need. 

As client bodies attempt to make their projects more attractive for companies to work on, the industry is changing. The first signs of this change can be seen in the consultancy market. 

After years of searching for project opportunities, the big consultancy businesses are now only selectively bidding for projects in the kingdom. This is because their orderbooks are already full, and for many international firms there is a concern that they could become over-exposed to the Saudi market. 

On contracts that have already been won there are also challenges. Staffing projects is proving difficult as the kingdom remains a hard sell for many project professionals, despite significant social reforms that have taken place in recent years. 

Then, once staff have been recruited and deployed on projects, there is the prospect of losing them to competitors or clients that require the same human resources.

Securing contractors

As activity on site accelerates, the bigger concern is contracting resources. As things stand, there are not enough contractors working in Saudi Arabia to deliver all of the planned projects. 

The first way to deal with this problem is to increase the capacity of contractors in the kingdom. In February this year, the Public Investment Fund (PIF) invested $1.3bn in four local construction firms: Al-Bawani Holding Company, Almabani General Contractors Company, El-Seif Engineering Contracting Company and Nesma & Partners Contracting Company. 

This investment will allow the companies to scale up their capacity, adopt advanced technologies and improve local supply chains. 

As these firms grow, the hope is that it will encourage other local companies to also expand.

International or regional companies can also help, and over the past two years foreign players have become active in the kingdom again. Firms such as Bouygues, Samsung C&T, Hyundai Engineering Construction, China State, Webuild, FCC, Alec, Consolidated Contractors Company and Urbacon Trading Contracting Company have all secured major orders. 

In some cases, these contract awards have been supported with foreign finance, which gives the contractor an additional level of comfort when it comes to potential payment for projects. For others, the contract awards reflect growing assurance in the Saudi market. 

Boosting appeal

Confidence has been lifted by measures to make the Saudi market more attractive. Payment terms are improving and many of the frustrations typically faced by contractors are being addressed. 

One example is the use of performance guarantees. Red Sea Global, which is developing the Red Sea Project and Amaala gigaprojects on the Red Sea coast, no longer requires contractors to submit bid bonds and returns performance bonds on completion of the project, along with half of the retention. 

Alternative procurement methods and contract types are also being used, notably early contractor involvement and design and build. 

These different approaches reduce risk for the contractor and allow the client to lock in resources at a much earlier stage of the procurement process. 

Red Sea Global has adopted a different approach and is self-delivering the bulk of its projects. By acting as its own management contractor, it engages with subcontractors itself. While this means it does not need to secure the services of a main contractor, it still requires engaging with the supply chain, which – like the main contractor market – has finite resources in Saudi Arabia.

Payment terms are improving and many of the frustrations typically faced by contractors are being addressed 

Driving efficiency

On the other side of the equation, making construction more efficient could also help to limit the resources required. 

Client bodies are exploring modern methods of construction to increase the speed of delivery, reduce costs and cut the amount of resources needed on site.

The market could also be self-limiting. Decision-making in the kingdom remains centralised, which means key project decisions can be slow. While this is changing as development companies are left to run their own projects, bureaucracy can impact the speed of delivery, which ultimately reduces the immediate demand for resources on a project. 

While slow decision-making could impact progress on some projects, the overriding story for 2023 will be one of sustained pressure on the kingdom’s construction sector as it becomes a seller’s market. 

With that, there is the likelihood that contractor margins will start to creep up, just as they did in the UAE when its construction market overheated in 2003 and 2008. 

So far, that does not appear to have happened, as clients in Saudi Arabia have managed to find sufficient resources. For that to remain the case will be a major challenge, however, as on-site activity for most projects in the kingdom is still several years away from peaking. 

Daniel King, director, Currie & Brown

International contractors continue to see a level of risk in the Saudi market

“There is a lot of opportunity. A large volume of work is being planned, designed and rolled out. With that, there is significant pressure right now on the market in terms of resources and supply chain. 

“On the consultancy side, the market is tremendously difficult. 

“Even with the best incentives and best set of practices, retaining staff is a challenge. People are being attracted elsewhere and the competition is fierce. 

“For the contractors, there are a lot of tenders being let. The perception that the market has risk remains, however. That is certainly the perception for international contractors, and they are still looking at the Saudi market with some level of risk appreciation in terms of how quickly they are going to be paid and what the margins really are. 

“That approach will likely prevail for the short to medium term, until clients’ practices change in terms of contractual frameworks and payment practices. 

“Varied procurement practices are coming into play to guarantee supply chain. It might be early contractor involvement or partnering, but the main purpose is to guarantee the right level of contractors.”

Adel Karem Jemah, senior vice-president, Hill International

To prevent resource shortages, supply chain and procurement must be carefully considered

“It is imperative to consider alternative methods of procurement during boom times, and the current boom in Saudi Arabia is unprecedented considering the types, size, nature and complexity of projects that have been announced in line with Vision 2030. 

“This necessitates giving due consideration to the supply chain and type of procurement.

“It is not enough to look for resources locally or even regionally to cope with such projects. One needs to reach out to where such resources are available globally, either due to slowdowns in certain regions or the completion of other major projects. 

“Cost-plus contracts were used previously in many projects in Saudi Arabia. However, the risk for such contracts rests with the client and sometimes the cost ends up much more than expected. That is why financiers prefer the lump-sum type of contracts. 

“Nonetheless, I can see this type of contract being used for fast-track projects with very tight schedules, for instance to meet deadlines for facilities required for international or regional sporting events. 

“In any case, the evaluation and selection of contractors needs to be done with extreme diligence.”


MEED's April 2023 special report on Saudi Arabia includes:

> ECONOMY: Riyadh steps up the Vision 2030 tempo

> CONSTRUCTION: Saudi construction project ramp-up accelerates

> UPSTREAM: Aramco slated to escalate upstream spending

> DOWNSTREAM: Petchems ambitions define Saudi downstream

> POWER: Saudi Arabia reinvigorates power sector

> WATER: Saudi water begins next growth phase

> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10705629/main.gif
Colin Foreman
Related Articles
  • Contractors submit bids for key Aramco offshore tenders

    4 August 2026

     

    Register for MEED’s 14-day trial access 

    Contractors in Saudi Aramco’s Long-Term Agreement (LTA) pool of offshore service providers have submitted bids for five offshore tenders covering the engineering, procurement, construction and installation (EPCI) of structures at the Abu Safah, Berri, Manifa, Marjan, Safaniya and Zuluf offshore oil and gas fields in Saudi Arabia.

    The tenders are numbers 167, 168, 169, 170 and 171 on Aramco’s Contract Release and Purchase Order (CRPO) system, according to sources.

    Aramco issued the five CRPOs to its offshore LTA contractors in December, setting an initial bid submission deadline of 3 February.

    The Saudi energy giant has since extended the bid submission deadline several times – to 31 March, 1 June1 July and then 30 July – to allow LTA contractors sufficient time to prepare proposals.

    At the request of certain bidders, Aramco granted a final two-day extension, with LTA contractors submitting their proposals for the five CRPOs on 1 August, sources told MEED.

    The basic scope of EPCI work on the tenders is as follows:

    • CRPO 167 – eight jackets at the Marjan field development
    • CRPO 168 – four production deck modules (PDMs) at the Abu Safah, Berri, Manifa and Safaniya fields
    • CRPO 169 – three PDMs at the Marjan field development
    • CRPO 170 – three PDMs at the Marjan field development
    • CRPO 171 – three PDMs at the Zuluf field development
    Offshore contract awards

    Aramco spent almost $11bn on offshore EPCI contracts last year, more than double its capital expenditure on offshore projects in 2024, marking another year of robust upstream project spending in Saudi Arabia.

    In July, Aramco selected contractors for five CRPOs – numbers 150, 157, 158, 159 and 160 – worth over $3bn. These involve EPCI work and infrastructure upgrades at the Abu Safah, Berri, Manifa, Marjan and Zuluf offshore fields.

    The Saudi energy giant then picked contractors for four more CRPOs that are part of the large-scale project to expand infrastructure at the Zuluf offshore field development. The tenders are CRPOs 145, 146, 147 and 148, and their combined value is estimated to be almost $6bn.

    In late December last year, Italian contractor Saipem announced securing contracts for CRPOs 162 and 165. The scope of work on CRPO 162 covers the EPCI of two rigid pipelines – a 30-inch pipeline stretching 23.98 kilometres (km) and a 20-inch pipeline, 10.23km-long; replacement of a flexible 10-inch pipeline that spans 5.1km; and modification work on topsides at the Berri and Abu Safah field developments. The duration of this contract is 32 months, Saipem said.

    The scope of work on CRPO 165, lasting 12 months, includes subsea interventions at the Marjan field development and the EPCI of 300 metres of onshore pipeline and associated tie-ins.

    In early January 2026, MEED reported that Aramco had selected US-based McDermott International for CRPO 166. The scope of work is understood to have been carved out of the $15bn Marjan offshore field development project, under which Aramco issued contracts for 20 EPCI packages in 2019. McDermott won the largest share of work on the project, securing an estimated $4.5bn of contracts across two packages.

    The contract for CRPO 166 was single-sourced to McDermott without a competitive tendering process and issued as a change order, sources told MEED.

    Aramco then awarded its second offshore contract of the year, CRPO 156, to Saipem. The scope of work covers the EPCI of a 48-inch trunkline, spanning roughly 65km offshore and 12km onshore, from the Safaniya offshore oil field to the onshore processing facility, plus associated works such as subsea hook-ups.

    CRPO 156 comprises the third package in Aramco’s latest expansion phase at Safaniya – the world’s largest offshore oil field, with a production capacity of nearly 1.2 million barrels a day (b/d). Discovered in 1951, the field is located in Gulf waters approximately 265km north of Aramco’s headquarters in Dhahran.

    MEED also reported that Saipem was selected by Aramco for two more tenders as part of the Safaniya field development expansion phase – CRPOs 154 and 155. The combined contract value for CRPOs 154 and 155 is estimated at $600m, sources said.

    In April, state-owned China Offshore Oil Engineering Company won CRPO 161, which covers the EPCI of four gas jackets at the Arabiyah, Hasbah and Karan offshore fields.

    Healthy contract award pipeline

    Looking ahead, in addition to CRPOs 167-171, which are currently under bidding, Aramco is evaluating bids submitted by its offshore LTA contractors in July and August last year for at least two additional tenders.

    These are CRPOs 163 and 164, relating to the EPCI of infrastructure at the Abu Safah, Berri, Karan, Marjan and Safaniya fields.

    Separately, the offshore LTA contractors are also bidding for a new tender – CRPO 176 – that was issued by Aramco in May, according to sources.

    The scope of work on CRPO 176 covers the EPCI of seven flexible subsea pipelines with a combined length of 17km at the Berri and Marjan offshore field developments.

    Aramco’s LTA pool of offshore service providers comprises the following entities:

    • Saipem (Italy)
    • McDermott International (US)
    • Larsen & Toubro Energy Hydrocarbon (LTEH, India) / Subsea7 (UK)
    • NMDC Energy (UAE)
    • Lamprell (UAE/Saudi Arabia)
    • China Offshore Oil Engineering Company (China)
    • Dynamic Industries (US)
    • Sapura Energy (Malaysia)
    • TechnipFMC (France) / MMHE (Malaysia)
    • Hyundai Heavy Industries (South Korea)

    In April 2025, Aramco renewed its LTAs with the following contractors, whose contracts had either lapsed or were close to expiry:

    • Saipem
    • McDermott International
    • Larsen & Toubro Energy Hydrocarbon / Subsea7
    • NMDC Energy
    • Lamprell
    • China Offshore Oil Engineering Company
    ALSO READ: Aramco moves apace with Jafurah unconventional gas campaign

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18080836/main0627.jpg
    Indrajit Sen
  • Credit ratings key to infrastructure finance

    4 August 2026

    A global convergence in how infrastructure is financed is creating new pools of capital for Gulf projects, but the region’s non-OECD status means credit ratings will be central to unlocking the largest of these, according to Fitch Ratings.

    The ratings agency said the boundaries between project finance, corporate credit and structured finance are blurring as investors seek to optimise financing for the infrastructure required to support the digital buildout and energy transition. Rising interest from institutional investors in private credit, particularly asset-backed lending, is accelerating the adoption of tailored financing structures.

    For the GCC, the shift is important because of a specific regulatory constraint. Under EU Solvency II rules, unrated infrastructure debt sourced from outside the OECD cannot be treated as qualifying infrastructure. Fitch said this means that for investors seeking to access infrastructure opportunities in Saudi Arabia, India and other non-OECD markets, a credit rating is necessary for regulatory capital treatment.

    The distinction is significant for a region running one of the world’s largest project pipelines. Saudi Arabia, the UAE and their neighbours are financing large-scale projects across the power, water, transport and digital infrastructure sectors, and much of the incremental capital Fitch identifies is held by regulated institutions for which ratings determine capital charges.

    Insurers pivot

    Insurers and pension funds are among the most significant structural sources of infrastructure capital, with global aggregated assets of about $45tn and $40tn respectively. Fitch says their increasing involvement is directly intertwined with the role of credit ratings, as cost-of-duration mismatches within solvency regimes push insurers towards liability-driven investment strategies that better match assets with liabilities.

    Insurer allocations to infrastructure have historically been low, at a global median of about 1% of investment portfolios. Fitch said this is changing rapidly. It cited a Nuveen survey conducted at the end of 2025 indicating that private market infrastructure debt is set to be the most favoured destination for fixed-income allocation for the third consecutive year, with 46% of respondents planning to grow allocations over the next two years.

    Sovereign wealth funds also play a major role, with over 30% of their private market fund allocations going to infrastructure, with AI-linked infrastructure the dominant sub-theme, displacing transport and logistics for new commitments. Energy transition ranked a close second, often aligned with national strategic objectives.

    Larger funds with more than $100bn in assets are deploying directly and through co-investments, bypassing fund structures to reduce fees and increase control. Fitch said such funds are increasingly price-setters in large infrastructure deals, and that their strategic national mandates mean they will absorb assets at returns that pure financial investors would reject.

    Regional outlook

    For the GCC specifically, Fitch said additional investment is likely to support security enhancements for core infrastructure assets in response to conflict in the region, alongside upgrades to transport and social infrastructure. It expects increased renewable power capacity and enhanced oil and gas-related infrastructure.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18079923/main.gif
    Colin Foreman
  • AtkinsRealis confirms Sphere Abu Dhabi role

    4 August 2026

    AtkinsRealis has confirmed it has been appointed lead design and supervision consultant on the $1.7bn Sphere Abu Dhabi project on Yas Island.

    The Canadian engineering and project management firm said it will partner with local firm Alec Engineering & Contracting on the venue, which is scheduled to open in 2029.

    AtkinsRealis will be responsible for overall design coordination across architecture, structural engineering and specialist immersive technologies. Alec – appointed by Abu Dhabi’s Department of Culture & Tourism (DCT Abu Dhabi) – will oversee procurement, construction delivery and project completion.

    The project is being delivered under a design-and-build framework.

    Alec Holdings confirmed in May that its subsidiary, Alec Engineering & Contracting, had received a letter of award for the construction contract. MEED previously reported that Alec was the selected contractor and had been working on the project during the pre-construction phase.

    Sphere Abu Dhabi will be built on Yas Island on a plot between Yas Mall and SeaWorld Abu Dhabi. It will be the first Sphere venue outside the US and is expected to echo the scale of Sphere Las Vegas, with a capacity of up to 20,000, depending on configuration.

    The venue will feature a fully programmable LED exosphere and a wraparound interior display capable of delivering 16K-resolution visuals, alongside beamforming audio technology that can direct sound to individual seats.

    DCT Abu Dhabi is developing Sphere Abu Dhabi with US-based Sphere Entertainment.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18079715/main.jpg
    Colin Foreman
  • Oman opens door to direct power sales

    4 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    Oman’s Direct Sales Framework has been in place since April, but its success will ultimately depend on whether developers and large electricity users choose to adopt it.

    The framework establishes a regulated process that allows qualifying private renewable energy developers to sell electricity directly to eligible consumers, instead of through Oman’s traditional single-buyer model.

    For the first time, large electricity consumers have a formal mechanism to procure renewable power directly from developers, rather than relying solely on electricity supplied through the wider grid.

    The recently tendered 280MW Marsa solar independent power project could provide an early indication of how the framework will be used in practice.

    The project has been identified as a potential early application of the new regime, with electricity generated near Haima expected to be supplied to the Marsa LNG facility at Sohar through Oman’s transmission network.

    The framework also requires grid-connection studies, network approvals and annual capacity limits, underscoring that direct sales will continue to operate within a regulated market rather than an open one.

    Developers will also need customers willing to sign long-term agreements, while large electricity users will need to see clear value in procuring renewable power directly.

    The scale of electricity demand expected over the coming decade will be a key factor in driving these decisions. Large industrial consumers are expected to account for a growing share of Oman’s future electricity demand as mining, green hydrogen, metals and other energy-intensive industries expand.

    Oman’s procurement of utility-scale generation through competitive tenders is not slowing down either, as evidenced by recent advisory tenders for up to 4GW of solar projects targeted for commercial operation by Q2 2030.

    In the meantime, for some users, securing renewable electricity directly from developers may become an attractive alternative to relying solely on the traditional supply model.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18038648/main.jpg
    Mark Dowdall
  • Opec+ agrees sixth straight month of oil output hikes

    3 August 2026

    Opec+ has approved an oil production quota increase of around 188,000 barrels a day (b/d) from September, completing the unwinding of a layer of voluntary output cuts by its main member countries.

    Due to export disruptions from the Gulf, Russia and Kazakhstan caused by the Iran and Ukraine wars, successive monthly Opec+ output hikes over most of this year have remained largely on paper, with little impact on the market.

    The September increase agreed by core Opec+ members – Saudi Arabia, Russia, Iraq, Kuwait, Algeria, Kazakhstan and Oman – at a meeting on 2 August completes the phased rollback of a 1.65 million b/d supply cut originally agreed in 2023, when the group still included the UAE, which left Opec in May.

    separate Opec+ meeting of a panel called the Joint Ministerial Monitoring Committee also met on 2 August and reiterated concern about attacks on energy assets during the US-Israeli war on Iran, saying they are expensive and time-consuming to repair and therefore can affect supply.

    With September’s output hike now agreed, Opec+ still has one more layer of output cuts in place that applies to most of the group’s members. These roughly 2 million b/d of cuts date back to 2022 and are due to remain in place until the end of this year.

    Opec+ is carrying out a review of its members’ oil production capacity that will be used to set the 2027 output baselines from which quotas are calculated.

    It faces potentially difficult talks over new production quotas, with some members, including Iraq, pushing for higher individual quotas to reflect their higher capacity.

    Opec+ is an alliance of 21 countries, comprising members of Opec along with a group of 10 non-Opec states led by Russia.

    In recent years, only the seven core countries – and the UAE until its departure – have been involved in monthly production management.

    The seven members will hold their next meeting on 6 September.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18043979/main4234.jpg
    Indrajit Sen