Saudi Arabia under project pressure

28 March 2023

 

Saudi Arabia’s projects market is overheating. The volume of projects announced in the past six years vastly exceeds the resources that are available to work in the kingdom. 

Combined with tight deadlines to complete projects as part of Vision 2030, the pressure on the construction industry to deliver is ratcheting up and turning the tables on the supply chain as the shift from a buyer’s to a seller’s market accelerates.

For the five years from 2016 to 2020, there was an average of about $14bn-worth of contract awards a year in Saudi Arabia for the construction and transport sectors. After rising to $21bn in 2021, the total rose to $32bn in 2022 – the second-best year on record. 

The near doubling of the total annual value of contract awards by the end of 2022 has required a significant scale-up of resources in the kingdom, and the ramp-up is set to continue. 

Much of this pressure is due to the five official gigaprojects, which are major programmes of work that will involve a sustained flow of contract awards for years to come.

Gigaproject focus

The project most recently classified as a gigaproject by the Saudi authorities is the Diriyah Gate development on the western outskirts of Riyadh. It joins the $500bn Neom development in the northwest of the kingdom, Qiddiya entertainment city outside Riyadh, Red Sea Global’s projects on the Red Sea coast and Roshn’s housing developments across the kingdom.

These projects are relatively new. They began to be launched in 2017 and spent much of the following three years in the design phase. 

After a start that was hampered by the work and travel restrictions required to manage the Covid-19 pandemic, construction activity on these projects has accelerated sharply since the start of 2022. 

According to regional project tracker MEED Projects, there have been $36bn-worth of contract awards across these official gigaprojects since 2017. Compared to the entire Saudi projects market over the same period that represents 14.5 per cent of contract awards. 

The percentage rises to 20 per cent if a more recent time frame is used and only contract awards since the start of 2022 are included. As work gathers pace on the gigaprojects, their significance is expected to grow even further.

More major projects

Saudi Arabia’s ambitions are not limited to the five gigaprojects. In January, Crown Prince Mohammed bin Salman al-Saud launched the world’s largest modern downtown in Riyadh. 

Known as the New Murabba project, it involves the development of 19 square kilometres of land to the northwest of the capital. The centrepiece of the project is the Mukaab, which is a 400-metre-cubed structure with a tower standing inside it. 

New Murabba is part of a plan announced in January 2021 to double the size of Riyadh from 7.5 million residents to 15-20 million residents in 2030. Other major projects in the capital include King Salman International airport, King Salman Park, Sports Boulevard and Mohammed bin Salman Non-Profit City. 

Beyond the capital there are development projects planned in all major urban centres by Saudi Downtown Company, as well as entertainment centres being developed by Saudi Entertainment Ventures (Seven).

Connecting these cities and projects will be railways, roads, ports and airports that form part of the National Transport & Logistics strategy, which aims to turn the kingdom into a global hub for travel and trade by 2030.

World’s largest piling project shifts to The Line’s marina

Resourcing challenges  

One of the key challenges for the development firms and government agencies responsible for delivering these projects is securing the resources they need. 

As client bodies attempt to make their projects more attractive for companies to work on, the industry is changing. The first signs of this change can be seen in the consultancy market. 

After years of searching for project opportunities, the big consultancy businesses are now only selectively bidding for projects in the kingdom. This is because their orderbooks are already full, and for many international firms there is a concern that they could become over-exposed to the Saudi market. 

On contracts that have already been won there are also challenges. Staffing projects is proving difficult as the kingdom remains a hard sell for many project professionals, despite significant social reforms that have taken place in recent years. 

Then, once staff have been recruited and deployed on projects, there is the prospect of losing them to competitors or clients that require the same human resources.

Securing contractors

As activity on site accelerates, the bigger concern is contracting resources. As things stand, there are not enough contractors working in Saudi Arabia to deliver all of the planned projects. 

The first way to deal with this problem is to increase the capacity of contractors in the kingdom. In February this year, the Public Investment Fund (PIF) invested $1.3bn in four local construction firms: Al-Bawani Holding Company, Almabani General Contractors Company, El-Seif Engineering Contracting Company and Nesma & Partners Contracting Company. 

This investment will allow the companies to scale up their capacity, adopt advanced technologies and improve local supply chains. 

As these firms grow, the hope is that it will encourage other local companies to also expand.

International or regional companies can also help, and over the past two years foreign players have become active in the kingdom again. Firms such as Bouygues, Samsung C&T, Hyundai Engineering Construction, China State, Webuild, FCC, Alec, Consolidated Contractors Company and Urbacon Trading Contracting Company have all secured major orders. 

In some cases, these contract awards have been supported with foreign finance, which gives the contractor an additional level of comfort when it comes to potential payment for projects. For others, the contract awards reflect growing assurance in the Saudi market. 

Boosting appeal

Confidence has been lifted by measures to make the Saudi market more attractive. Payment terms are improving and many of the frustrations typically faced by contractors are being addressed. 

One example is the use of performance guarantees. Red Sea Global, which is developing the Red Sea Project and Amaala gigaprojects on the Red Sea coast, no longer requires contractors to submit bid bonds and returns performance bonds on completion of the project, along with half of the retention. 

Alternative procurement methods and contract types are also being used, notably early contractor involvement and design and build. 

These different approaches reduce risk for the contractor and allow the client to lock in resources at a much earlier stage of the procurement process. 

Red Sea Global has adopted a different approach and is self-delivering the bulk of its projects. By acting as its own management contractor, it engages with subcontractors itself. While this means it does not need to secure the services of a main contractor, it still requires engaging with the supply chain, which – like the main contractor market – has finite resources in Saudi Arabia.

Payment terms are improving and many of the frustrations typically faced by contractors are being addressed 

Driving efficiency

On the other side of the equation, making construction more efficient could also help to limit the resources required. 

Client bodies are exploring modern methods of construction to increase the speed of delivery, reduce costs and cut the amount of resources needed on site.

The market could also be self-limiting. Decision-making in the kingdom remains centralised, which means key project decisions can be slow. While this is changing as development companies are left to run their own projects, bureaucracy can impact the speed of delivery, which ultimately reduces the immediate demand for resources on a project. 

While slow decision-making could impact progress on some projects, the overriding story for 2023 will be one of sustained pressure on the kingdom’s construction sector as it becomes a seller’s market. 

With that, there is the likelihood that contractor margins will start to creep up, just as they did in the UAE when its construction market overheated in 2003 and 2008. 

So far, that does not appear to have happened, as clients in Saudi Arabia have managed to find sufficient resources. For that to remain the case will be a major challenge, however, as on-site activity for most projects in the kingdom is still several years away from peaking. 

Daniel King, director, Currie & Brown

International contractors continue to see a level of risk in the Saudi market

“There is a lot of opportunity. A large volume of work is being planned, designed and rolled out. With that, there is significant pressure right now on the market in terms of resources and supply chain. 

“On the consultancy side, the market is tremendously difficult. 

“Even with the best incentives and best set of practices, retaining staff is a challenge. People are being attracted elsewhere and the competition is fierce. 

“For the contractors, there are a lot of tenders being let. The perception that the market has risk remains, however. That is certainly the perception for international contractors, and they are still looking at the Saudi market with some level of risk appreciation in terms of how quickly they are going to be paid and what the margins really are. 

“That approach will likely prevail for the short to medium term, until clients’ practices change in terms of contractual frameworks and payment practices. 

“Varied procurement practices are coming into play to guarantee supply chain. It might be early contractor involvement or partnering, but the main purpose is to guarantee the right level of contractors.”

Adel Karem Jemah, senior vice-president, Hill International

To prevent resource shortages, supply chain and procurement must be carefully considered

“It is imperative to consider alternative methods of procurement during boom times, and the current boom in Saudi Arabia is unprecedented considering the types, size, nature and complexity of projects that have been announced in line with Vision 2030. 

“This necessitates giving due consideration to the supply chain and type of procurement.

“It is not enough to look for resources locally or even regionally to cope with such projects. One needs to reach out to where such resources are available globally, either due to slowdowns in certain regions or the completion of other major projects. 

“Cost-plus contracts were used previously in many projects in Saudi Arabia. However, the risk for such contracts rests with the client and sometimes the cost ends up much more than expected. That is why financiers prefer the lump-sum type of contracts. 

“Nonetheless, I can see this type of contract being used for fast-track projects with very tight schedules, for instance to meet deadlines for facilities required for international or regional sporting events. 

“In any case, the evaluation and selection of contractors needs to be done with extreme diligence.”


MEED's April 2023 special report on Saudi Arabia includes:

> ECONOMY: Riyadh steps up the Vision 2030 tempo

> CONSTRUCTION: Saudi construction project ramp-up accelerates

> UPSTREAM: Aramco slated to escalate upstream spending

> DOWNSTREAM: Petchems ambitions define Saudi downstream

> POWER: Saudi Arabia reinvigorates power sector

> WATER: Saudi water begins next growth phase

> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10705629/main.gif
Colin Foreman
Related Articles
  • Qiddiya seeks firms for light rail transit system

    11 May 2026

     

    Saudi gigaproject developer Qiddiya Investment Company (QIC) has requested contractors to express interest in a contract to design and build the first phase of the light rail transit system at Qiddiya Entertainment City.

    The notice was issued on 5 May, with firms given until 20 June to submit expressions of interest.

    The project, also known as the Primary Urban Axis, comprises a 22-kilometre automated, driverless rail line as part of its first phase.

    The contract scope includes about 16 stations – 11 elevated and five underground – along with 8km of tunnels, viaducts and other associated structures. It covers all civil, architectural, and mechanical, electrical and plumbing works.

    Stations will be located at Resort Core East Village, Grand Central Station, Anime Hub Integrated Station and Primary Urban Axis 1 & 2 Hub Station.

    A subsequent phase will extend the railway network by a further 11km.

    QIC is accelerating plans to develop additional assets at Qiddiya City.

    Separately, QIC, the Royal Commission for Riyadh City and the National Centre for Privatisation & PPP received prequalification statements from firms on 30 April for the public-private partnership (PPP) package of the Qiddiya high-speed rail project in Riyadh. This follows submission of prequalification statements for the engineering, procurement, construction and financing package on 16 April, as previously reported by MEED.

    The Qiddiya high-speed rail project, also known as Q-Express, will connect King Salman International airport and the King Abdullah Financial District (KAFD) with Qiddiya City. The line will operate at up to 250 kilometres per hour, reaching Qiddiya in 30 minutes.

    Contractors are also preparing bids for a 13 May deadline for a contract covering new infrastructure works at Qiddiya Entertainment City. The scope includes two infrastructure development packages for District 0, including the construction of four event park-and-ride facilities.

    QIC’s other major projects include an e-games arena, Prince Mohammed Bin Salman Stadium, a motorsports track, the Dragon Ball and Six Flags theme parks, and Aquarabia.

    QIC officially opened the Six Flags theme park to the public in December last year.

    The park covers 320,000 square metres and features 28 rides and attractions, including 10 thrill rides and 18 aimed at families and young children.

    The Qiddiya project is a key part of Riyadh’s strategy to boost leisure tourism in the kingdom.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16779176/main.jpg
    Yasir Iqbal
  • Contractors submit bids for Saudi gas processing plant project

    8 May 2026

     

    Contractors have submitted bids to Saudi Aramco subsidiary Aramco Gulf Operations Company (AGOC) for a project to build an onshore gas processing plant in Saudi Arabia’s Khafji that will draw and process gas from the Dorra offshore gas field, located in waters of the Saudi-Kuwait Neutral Zone.

    MEED previously reported that AGOC had divided the engineering, procurement and construction (EPC) on the Khafji gas plant project into seven packages, and issued the main tenders for those last year.

    Contractors were initially set deadlines of 24 October for technical bid submissions and 9 November for commercial bids. AGOC later extended the bid submission deadline to 22 December, and then until 22 April. A final deadline of 30 April was set, with contractors submitting bids by that date, according to sources.

    The seven EPC packages cover works including open-art and licensed process facilities, pipelines, industrial support infrastructure, site preparation, overhead transmission lines, power supply systems and main operational and administrative buildings, with their breakdown as follows:

    • Package 1 – Open-art facilities
    • Package 2 – Licensed facilities
    • Package 3 – Industrial support facilities
    • Package 4 – Pipelines
    • Package 5 – Site preparation
    • Package 6 – Overhead transmission lines plus power supply (from Saudi Electricity Company)
    • Package 7 – Headquarters complex

    Saudi Arabia and Kuwait have been pressing ahead with their plan to jointly produce 1 billion cubic feet a day (cf/d) of gas from the Dorra gas field.

    The two countries have been producing oil from the Neutral Zone – primarily from the onshore Wafra field and offshore Khafji field – since at least the 1950s. With a growing need to increase natural gas production, they have been working to exploit the Dorra offshore field, understood to be the only gas field in the Neutral Zone.

    Discovered in 1965, the Dorra gas field is estimated to hold 20 trillion cubic metres of gas and 310 million barrels of oil.

    The Khafji gas plant project is one of three multibillion-dollar projects launched by subsidiaries of Saudi Aramco and Kuwait Petroleum Corporation (KPC) to produce and process gas from the Dorra field that has advanced in recent months.

    Dorra field facilities project

    Al-Khafji Joint Operations (KJO), which is jointly owned by AGOC and KPC subsidiary Kuwait Gulf Oil Company (KGOC), has divided the scope of work on the Dorra field facilities project into four EPC packages – three offshore and one onshore.

    India’s Larsen & Toubro Energy Hydrocarbon (L&TEH) won the contract for package one of the Dorra facilities project, which covers the EPC of seven offshore jackets and the laying of intra-field pipelines. The contract awarded by KJO to L&TEH is estimated to be valued at $140m-$150m, MEED reported in October.

    Additionally, Italian, Indian and Spanish contractors have emerged as the lowest bidders for the other three EPC packages that form part of the Dorra facilities project.

    A consortium of Italian contractor Saipem and L&TEH is understood to have submitted the lowest bid for offshore packages 2A and 2B, according to sources. The only other consortium understood to have submitted bids for packages 2A and 2B comprises Abu Dhabi-based NMDC Energy and South Korea’s Hyundai Heavy Industries.

    The EPC scope of work for package 2A includes Dorra gas field wellhead topsides, flowlines and umbilicals. Package 2B involves the central gathering platform complex, export pipelines and cables.

    Spanish contractor Tecnicas Reunidas is understood to have emerged as the lowest bidder for onshore package three, sources told MEED. Package three covers the EPC of onshore gas processing facilities.

    KGOC onshore processing facilities

    The third component of the overall Dorra gas field development programme is a planned onshore gas processing facility to be built in Kuwait, which has been undertaken by KGOC.

    KGOC had been progressing with the front-end engineering and design (feed) work on the project, before the destabilising impact of the US-Israel conflict with Iran compelled the operator to put the project on hold, MEED reported in April.

    The proposed facility, estimated to be worth $3.3bn, will receive gas from a pipeline from the Dorra offshore field, which is being separately developed by KJO. The complex will have the capacity to process up to 632 million cf/d of gas and 88.9 million barrels a day of condensates from the Dorra field.

    The facility will be located near the Al-Zour refinery, owned by another KPC subsidiary, Kuwait Integrated Petroleum Industries Company.

    A 700,000-square-metre plot has been allocated next to the Al-Zour refinery for the gas processing facility and discussions regarding survey work are ongoing. The site could require shoring, backfilling and dewatering.

    The onshore gas processing plant will also supply surplus gas to KPC’s upstream business, Kuwait Oil Company, for possible injection into its oil fields.

    Additionally, KGOC plans to award licensed technology contracts to US-based Honeywell UOP and Shell subsidiary Shell Catalysts & Technologies for the plant’s acid gas removal unit and sulphur recovery unit, respectively.

    France-based Technip Energies has carried out a concept study and feed work on the entire Dorra gas field development programme.

    Progress has been hampered by a dispute over ownership of the Dorra gas field. Iran, which refers to the field as Arash, claims it partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development. Kuwait and Saudi Arabia maintain that the field lies entirely within their jointly administered Neutral Zone – also known as the Divided Zone – and that Iran has no legal basis for its claim.

    In February 2024, Kuwait and Saudi Arabia reiterated their claim to the Dorra field in a joint statement issued during an official meeting in Riyadh between Kuwaiti Emir Sheikh Mishal Al-Ahmad Al-Jaber Al-Sabah and Saudi Crown Prince and Prime Minister Mohammed Bin Salman Bin Abdulaziz Al-Saud.

    Since that show of strength and unity, projects to produce and process gas from the Dorra field have gained momentum.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16734353/main5834.jpg
    Indrajit Sen
  • Teams prepare bids for Riyadh East sewage treatment plant

    8 May 2026

     

    At least six consortiums are preparing to submit bids for Saudi Arabia's Riyadh East independent sewage treatment plant (ISTP) project, according to sources.

    The project will be developed under a build‑own‑operate‑transfer model with a 25‑year concession term.

    The plant will have a treatment capacity of 200,000 cubic metres a day (cm/d) in its first phase, expanding to 500,000 cm/d in the second phase.

    MEED understands that the following consortiums are in discussions to submit bids for the project, which has a recently extended bid submission deadline of 30 June:

    • Suez (France) / Civil Works Company (Saudi Arabia) / Alwael (Saudi Arabia)
    • Saur (France) / Samsung E&A (South Korea) / Al-Bawani (Saudi Arabia) / Nesma (Saudi Arabia)
    • Alkhorayef (Saudi Arabia) / GS Inima (Spain)
    • EtihadWE (UAE) / Metito (UAE)
    • Veolia (France) / AlJomaih Energy & Water (Saudi Arabia)
    • Miahona (Saudi Arabia) / Marafiq  (Saudi Arabia)

    In December 2025, a group comprising Metito, EtihadWE and SkyBridge was selected as the preferred bidder for the Hadda ISTP project. Miahona, Marafiq Company and Buhur for Investment was selected as the reserved bidder.

    That same month, the Miahona-led consortium was selected as preferred bidder for the Arana ISTP and the Metito-led consortium was selected as the reserved bidder. Both projects have yet to reach financial close.

    The Riyadh East, Hadda and Arana ISTPs are being undertaken by state water offtaker Sharakat, formerly Saudi Water Partnership Company, in collaboration with the National Centre for Privatisation & PPP.

    In 2024, Sharakat prequalified 53 companies that could bid for the Riyadh East ISTP, part of seven planned ISTP projects it said it would procure between 2024 and 2026. The request for proposals was issued last October. 

    WSP is the technical adviser and KPMG Middle East is the lead and financial adviser on the project.

    The targeted commercial operation date for the facility is 2029.

    ISTP plans

    According to Sharakat’s recent seven-year statement, it has identified six additional large ISTPs in the development pipeline.

    These are:

    • Kharj (75,000 cm/d)
    • Abu Arish (50,000 cm/d)
    • Hafar Al-Batin (100,000 cm/d)
    • Riyadh North (TBD)
    • Najran South (50,000 cm/d)
    • Khamis Mushait (50,000 cm/d)

    The company is also pursuing a nationwide small sewage treatment plant programme covering about 139 smaller ISTPs grouped into seven clusters.

    These are designed to add about 521,450 cm/d of additional treatment capacity across the kingdom.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16734156/main.jpg
    Mark Dowdall
  • Saudi Arabia tenders Jeddah-Mecca highway PPP

    8 May 2026

     

    Saudi Arabia’s Roads General Authority (RGA) and the National Centre for Privatisation & PPP (NCP) have tendered the contract for the development of the Jeddah-Mecca highway project.

    The tender was issued on 19 April, with a bid submission deadline of 19 August.

    The scope of the tender is split into two sections: development of motor service areas (MSA) and highway services. 

    Under the MSA component, the company will develop, permit, finance, design, engineer, procure, construct, complete, test, commission, insure, operate and maintain three MSAs along the highway.

    The contract term is 25 years, including two years of the construction period.

    Each MSA plot will cover 34,500 square metres and will include facilities such as fuel stations, electric vehicle charging, truck services, tyre and oil change, car wash and repair, retail and food outlets, ATMs, restrooms, mosques, parking, landscaping and other associated utilities.

    The highway services component will include insurance, operation and maintenance of highway assets for 10 years.

    The 64-kilometre (km) Jeddah-Mecca highway has four lanes in each direction. The construction works on 51km are complete, while the rest is under construction and scheduled for completion in 2027.

    In March, the RGA and NCP prequalified three bidders to develop the project. These were:

    • Algihaz Holding / ICA Construction (local/Turkiye)
    • Lamar Holding / Shaanxi Construction Engineering Group Corporation (Bahrain/China)
    • Mada International Holding (local)

    The expression of interest notice for the project was first issued in October 2024, as MEED reported.

    The project is one of four planned highway schemes in the kingdom’s privatisation and public-private partnership (P&PPP) pipeline.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16731199/main.jpg
    Yasir Iqbal
  • US sanctions Iraq’s deputy oil minister

    8 May 2026

    The US has sanctioned Iraq’s Deputy Oil Minister Ali Maarij Al-Bahadly, in another blow for the country’s oil and gas sector.

    In a statement released by the US Treasury, it said that he “abuses his position to facilitate the diversion of oil to be sold for the benefit of the Iranian regime and its proxy militias in Iraq”.

    The US Department of the Treasury’s Office of Foreign Assets Control (Ofac) has also designated three senior leaders of the militias Kata’ib Sayyid Al-Shuhada and Asa’ib Ahl Al-Haq. 

    In its statement, it said that the US will continue to hold these groups and other militias in Iraq, such as Kata’ib Hizballah, accountable for their attacks against US personnel and civilians, diplomatic facilities and businesses across Iraq.

    Secretary of the Treasury, Scott Bessent, said: “Like a rogue gang, the Iranian regime is pillaging resources that rightfully belong to the Iraqi people.”

    He added: “Treasury will not stand idly by as Iran's military exploits Iraqi oil to fund terrorism against the United States and our partners.”

    Ofac said that it designated Iraq’s deputy minister of oil on 7 May because he had been “instrumental in facilitating the diversion of Iraqi oil products to benefit known Iran-affiliated oil smuggler Salim Ahmed Said, as well as Iran-backed terrorist militia Asa’ib Ahl Al-Haq (AAH)”.

    It added: “For years, Maarij has used his official positions, first as the head of the Iraqi parliament’s oil and gas committee, and then within the Iraq Ministry of Oil, to enrich Said, AAH, and by extension, Iran.”

    The US Treasury said that it designated Said in June 2025 for running a network of companies selling Iranian oil falsely declared as Iraqi oil to avoid sanctions.

    In its statement, it said: “Integral to this operation was Said’s ability to obtain favoured access to Iraqi oil and procure forged documentation from Iraqi government officials, legitimising illicit oil.

    “To that end, Said was responsible for bribing complicit officials in the Iraqi government, as well as reportedly installing Maarij in his official position.”

    Since 2018, Maarij has held several positions in Iraq’s Oil Ministry, including head of the licensing and contracts office, deputy minister, and acting oil minister. 

    The US Treasury said that, in his official capacities, Maarij enabled Said to illicitly procure oil products by granting exportation rights to Said’s companies. 

    It claimed that Maarij authorised trucking several million dollars’ worth of oil a day from the Qayarah oil field to VS Oil Terminal in Khor Zubayr for export.

    The US sanctioned VS Oil Terminal in July last year.

    The US Treasury said that VS Oil oversaw the mixing of Iranian oil with Iraqi oil before being shipped to market. 

    It also said that Maarij is also responsible for falsifying documentation on the provenance of oil for Said’s network, enabling it to be smuggled to market disguised as purely Iraqi oil.

    Neither Iraq nor Iran has responded to the announcement of the new sanctions.

    The sanctions were announced as the US and Iran battle over control of the Strait of Hormuz, which has seen significant disruption to shipping since the US and Israel started their war with Iran on 28 February 2026.

    Iraq’s oil and gas sector is currently going through a crisis due to the disruption to shipping through the Strait of Hormuz, which has caused the country’s oil exports to collapse.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16729987/main.png
    Wil Crisp