Saudi Arabia under project pressure

28 March 2023

 

Saudi Arabia’s projects market is overheating. The volume of projects announced in the past six years vastly exceeds the resources that are available to work in the kingdom. 

Combined with tight deadlines to complete projects as part of Vision 2030, the pressure on the construction industry to deliver is ratcheting up and turning the tables on the supply chain as the shift from a buyer’s to a seller’s market accelerates.

For the five years from 2016 to 2020, there was an average of about $14bn-worth of contract awards a year in Saudi Arabia for the construction and transport sectors. After rising to $21bn in 2021, the total rose to $32bn in 2022 – the second-best year on record. 

The near doubling of the total annual value of contract awards by the end of 2022 has required a significant scale-up of resources in the kingdom, and the ramp-up is set to continue. 

Much of this pressure is due to the five official gigaprojects, which are major programmes of work that will involve a sustained flow of contract awards for years to come.

Gigaproject focus

The project most recently classified as a gigaproject by the Saudi authorities is the Diriyah Gate development on the western outskirts of Riyadh. It joins the $500bn Neom development in the northwest of the kingdom, Qiddiya entertainment city outside Riyadh, Red Sea Global’s projects on the Red Sea coast and Roshn’s housing developments across the kingdom.

These projects are relatively new. They began to be launched in 2017 and spent much of the following three years in the design phase. 

After a start that was hampered by the work and travel restrictions required to manage the Covid-19 pandemic, construction activity on these projects has accelerated sharply since the start of 2022. 

According to regional project tracker MEED Projects, there have been $36bn-worth of contract awards across these official gigaprojects since 2017. Compared to the entire Saudi projects market over the same period that represents 14.5 per cent of contract awards. 

The percentage rises to 20 per cent if a more recent time frame is used and only contract awards since the start of 2022 are included. As work gathers pace on the gigaprojects, their significance is expected to grow even further.

More major projects

Saudi Arabia’s ambitions are not limited to the five gigaprojects. In January, Crown Prince Mohammed bin Salman al-Saud launched the world’s largest modern downtown in Riyadh. 

Known as the New Murabba project, it involves the development of 19 square kilometres of land to the northwest of the capital. The centrepiece of the project is the Mukaab, which is a 400-metre-cubed structure with a tower standing inside it. 

New Murabba is part of a plan announced in January 2021 to double the size of Riyadh from 7.5 million residents to 15-20 million residents in 2030. Other major projects in the capital include King Salman International airport, King Salman Park, Sports Boulevard and Mohammed bin Salman Non-Profit City. 

Beyond the capital there are development projects planned in all major urban centres by Saudi Downtown Company, as well as entertainment centres being developed by Saudi Entertainment Ventures (Seven).

Connecting these cities and projects will be railways, roads, ports and airports that form part of the National Transport & Logistics strategy, which aims to turn the kingdom into a global hub for travel and trade by 2030.

World’s largest piling project shifts to The Line’s marina

Resourcing challenges  

One of the key challenges for the development firms and government agencies responsible for delivering these projects is securing the resources they need. 

As client bodies attempt to make their projects more attractive for companies to work on, the industry is changing. The first signs of this change can be seen in the consultancy market. 

After years of searching for project opportunities, the big consultancy businesses are now only selectively bidding for projects in the kingdom. This is because their orderbooks are already full, and for many international firms there is a concern that they could become over-exposed to the Saudi market. 

On contracts that have already been won there are also challenges. Staffing projects is proving difficult as the kingdom remains a hard sell for many project professionals, despite significant social reforms that have taken place in recent years. 

Then, once staff have been recruited and deployed on projects, there is the prospect of losing them to competitors or clients that require the same human resources.

Securing contractors

As activity on site accelerates, the bigger concern is contracting resources. As things stand, there are not enough contractors working in Saudi Arabia to deliver all of the planned projects. 

The first way to deal with this problem is to increase the capacity of contractors in the kingdom. In February this year, the Public Investment Fund (PIF) invested $1.3bn in four local construction firms: Al-Bawani Holding Company, Almabani General Contractors Company, El-Seif Engineering Contracting Company and Nesma & Partners Contracting Company. 

This investment will allow the companies to scale up their capacity, adopt advanced technologies and improve local supply chains. 

As these firms grow, the hope is that it will encourage other local companies to also expand.

International or regional companies can also help, and over the past two years foreign players have become active in the kingdom again. Firms such as Bouygues, Samsung C&T, Hyundai Engineering Construction, China State, Webuild, FCC, Alec, Consolidated Contractors Company and Urbacon Trading Contracting Company have all secured major orders. 

In some cases, these contract awards have been supported with foreign finance, which gives the contractor an additional level of comfort when it comes to potential payment for projects. For others, the contract awards reflect growing assurance in the Saudi market. 

Boosting appeal

Confidence has been lifted by measures to make the Saudi market more attractive. Payment terms are improving and many of the frustrations typically faced by contractors are being addressed. 

One example is the use of performance guarantees. Red Sea Global, which is developing the Red Sea Project and Amaala gigaprojects on the Red Sea coast, no longer requires contractors to submit bid bonds and returns performance bonds on completion of the project, along with half of the retention. 

Alternative procurement methods and contract types are also being used, notably early contractor involvement and design and build. 

These different approaches reduce risk for the contractor and allow the client to lock in resources at a much earlier stage of the procurement process. 

Red Sea Global has adopted a different approach and is self-delivering the bulk of its projects. By acting as its own management contractor, it engages with subcontractors itself. While this means it does not need to secure the services of a main contractor, it still requires engaging with the supply chain, which – like the main contractor market – has finite resources in Saudi Arabia.

Payment terms are improving and many of the frustrations typically faced by contractors are being addressed 

Driving efficiency

On the other side of the equation, making construction more efficient could also help to limit the resources required. 

Client bodies are exploring modern methods of construction to increase the speed of delivery, reduce costs and cut the amount of resources needed on site.

The market could also be self-limiting. Decision-making in the kingdom remains centralised, which means key project decisions can be slow. While this is changing as development companies are left to run their own projects, bureaucracy can impact the speed of delivery, which ultimately reduces the immediate demand for resources on a project. 

While slow decision-making could impact progress on some projects, the overriding story for 2023 will be one of sustained pressure on the kingdom’s construction sector as it becomes a seller’s market. 

With that, there is the likelihood that contractor margins will start to creep up, just as they did in the UAE when its construction market overheated in 2003 and 2008. 

So far, that does not appear to have happened, as clients in Saudi Arabia have managed to find sufficient resources. For that to remain the case will be a major challenge, however, as on-site activity for most projects in the kingdom is still several years away from peaking. 

Daniel King, director, Currie & Brown

International contractors continue to see a level of risk in the Saudi market

“There is a lot of opportunity. A large volume of work is being planned, designed and rolled out. With that, there is significant pressure right now on the market in terms of resources and supply chain. 

“On the consultancy side, the market is tremendously difficult. 

“Even with the best incentives and best set of practices, retaining staff is a challenge. People are being attracted elsewhere and the competition is fierce. 

“For the contractors, there are a lot of tenders being let. The perception that the market has risk remains, however. That is certainly the perception for international contractors, and they are still looking at the Saudi market with some level of risk appreciation in terms of how quickly they are going to be paid and what the margins really are. 

“That approach will likely prevail for the short to medium term, until clients’ practices change in terms of contractual frameworks and payment practices. 

“Varied procurement practices are coming into play to guarantee supply chain. It might be early contractor involvement or partnering, but the main purpose is to guarantee the right level of contractors.”

Adel Karem Jemah, senior vice-president, Hill International

To prevent resource shortages, supply chain and procurement must be carefully considered

“It is imperative to consider alternative methods of procurement during boom times, and the current boom in Saudi Arabia is unprecedented considering the types, size, nature and complexity of projects that have been announced in line with Vision 2030. 

“This necessitates giving due consideration to the supply chain and type of procurement.

“It is not enough to look for resources locally or even regionally to cope with such projects. One needs to reach out to where such resources are available globally, either due to slowdowns in certain regions or the completion of other major projects. 

“Cost-plus contracts were used previously in many projects in Saudi Arabia. However, the risk for such contracts rests with the client and sometimes the cost ends up much more than expected. That is why financiers prefer the lump-sum type of contracts. 

“Nonetheless, I can see this type of contract being used for fast-track projects with very tight schedules, for instance to meet deadlines for facilities required for international or regional sporting events. 

“In any case, the evaluation and selection of contractors needs to be done with extreme diligence.”


MEED's April 2023 special report on Saudi Arabia includes:

> ECONOMY: Riyadh steps up the Vision 2030 tempo

> CONSTRUCTION: Saudi construction project ramp-up accelerates

> UPSTREAM: Aramco slated to escalate upstream spending

> DOWNSTREAM: Petchems ambitions define Saudi downstream

> POWER: Saudi Arabia reinvigorates power sector

> WATER: Saudi water begins next growth phase

> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10705629/main.gif
Colin Foreman
Related Articles
  • Contractor progresses with Qatar LNG decarbonisation project

    30 October 2025

    Engineering, procurement and construction (EPC) works are progressing on an estimated $2bn to $2.5bn carbon dioxide (CO2) sequestration complex project of QatarEnergy LNG covering its liquefied natural gas (LNG) production operations in Qatar’s Ras Laffan Industrial City (RLIC).

    Once commissioned, the planned sequestration facility will be capable of capturing 4.3 million tonnes a year (t/y) of CO2 from QatarEnergy LNG’s production operations in RLIC.

    QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, awarded the main EPC contract for the CO2 sequestration project to South Korean contractor Samsung C&T, sources told MEED.

    The letter of award for the EPC contract was issued by QatarEnergy LNG to Samsung C&T on 27 May, according to a source.

    The following contractors are among those that are understood to have submitted bids in April for EPC works on the QatarEnergy LNG CO2 sequestration project:

    • Chiyoda (Japan) / Consolidated Contractors Company (Greece/Lebanon)
    • Larsen & Toubro Energy Hydrocarbon (India)
    • Samsung C&T (South Korea)

    Based on the initial evaluation of bids, Larsen & Toubro Energy Hydrocarbon is understood to have pulled ahead in the race for the project’s contract, MEED previously reported. However, sources, at the time, added that the situation could change.

    QatarEnergy LNG awarded Australia-headquartered consultancy Worley a contract in September 2023 to execute the front-end engineering and design (feed) work on the project and to prepare the EPC scope of work.

    CO2 sequestration facility

    The planned sequestration facility will capture CO2 from seven LNG trains at the QG North complex and three LNG trains at the QG South complex.

    The CO2 captured from the trains is to be dehydrated, compressed and transferred via a new 154-kilometre pipeline, to be injected into wells at the Dukhan oil field development onshore Qatar for a related enhanced oil recovery pilot scheme.

    The pilot project is part of QatarEnergy’s long-term strategy for the redevelopment of the Dukhan fields that will contribute to the recovery of additional crude.

    The detailed EPC scope of work on the CO2 sequestration project covers the following:

    • QG North complex:
      • Installation of four new electric-driven compressors
      • New power substation for power import from Kahramaa 65MW
      • New ITR for DCS/ESD/F&G
      • Tie-ins with utility units
      • Dehydration package
      • Pig launcher
         
    • QG South complex:
      • Installation of two new electric-driven compressors
      • Integration with South injection system unit 85
      • Solvent reformulation for South trains 1/23
      • New power substation for power import from Kahramaa 35MW
      • New SIH for DCS/ESD/F&G
      • Tie-ins with utility units
      • Dehydration package
      • Chillers package
      • Pig launcher
         
    • RLIC corridors
      • Common 22-inch export pipeline stretching 18 kilometres
      • Power tie-in RLF3 with Kahramaa
      • Electric cables
      • Fiber optic cable
         
    • Lot W15
      • Six injection wells by QatarEnergy LNG subsurface
      • Six injection flowlines and metring skid
      • Six wellhead control panels
      • Power tie-in from Barzan
      • Substation
      • Pig receiver
      • Access road and fencing

    The project will directly reduce CO2 emissions because some of the CO2 injected into wells at the Dukhan oil field will remain in the reservoir after injection.

    The CO2 sequestration complex in RLIC is expected to start operations by the end of 2027.

    North Field LNG expansion

    Meanwhile, QatarEnergy LNG continues to press forward with its North Field LNG expansion programme.

    The estimated $40bn North Field LNG expansion programme aims to raise Qatar’s total LNG production capacity from 77.5 million t/y to 142 million t/y in three phases.

    QatarEnergy is understood to have spent almost $30bn on the two phases of the North Field LNG expansion programme, North Field East and North Field South, which will increase its LNG production capacity from 77.5 million t/y to 126 million t/y by 2028.

    EPC works on the two projects are making progress.

    QatarEnergy awarded the main EPC contracts in 2021 for the North Field East project, which is projected to increase LNG output to 110 million t/y by this year. The main $13bn EPC package, which covers the engineering, procurement, construction and installation of four LNG trains with capacities of 8 million t/y each, was awarded to a consortium of Japan’s Chiyoda Corporation and France’s Technip Energies in February 2021.

    QatarEnergy awarded the main EPC contract for the North Field South LNG project, worth $10bn, in May 2023. The contract covers two large LNG processing trains, each with a capacity of 7.8 million t/y, and was awarded to a consortium of Technip Energies and Lebanon-based Consolidated Contractors Company.

    When fully commissioned, the first two phases of the North Field LNG expansion programme will contribute a total supply capacity of 48 million t/y to the global LNG market.

    In February 2024, QatarEnergy announced the third phase of its North Field LNG expansion programme. To be called North Field West, the project will further increase QatarEnergy’s LNG production capacity to 142 million t/y when it is commissioned by 2030.

    The North Field West project will have an LNG production capacity of 16 million t/y, which is expected to be achieved through two 8 million t/y LNG processing trains, based on the two earlier phases of QatarEnergy’s LNG expansion programme. The new project will draw feedstock for LNG production from the western zone of Qatar’s North Field offshore gas reserve.

    The state enterprise recently started a prequalification process for the main tendering exercise for dredging works on the North Field West project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14981287/main2210.jpg
    Indrajit Sen
  • New Murabba signs up consultants for project delivery

    30 October 2025

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s New Murabba Development Company (NMDC) has signed agreements with three US-based engineering firms to undertake design works on various assets at the New Murabba downtown project in Riyadh.

    The client signed an agreement with New York-headquartered firm Kohn Pedersen Fox (KPF) to lead early design works for the first residential community within the New Murabba development.

    The other agreements were signed with Aecom and Jacobs, who have been appointed as the lead design consultants for the Mukaab district.

    The latest agreements build on NMDC’s August signing of a memorandum of understanding (MoU) with another US-based firm, Falcons Creative Group, to develop the creative vision and immersive experiences for the Mukaab project at the New Murabba development.

    The Mukaab is a Najdi-inspired landmark that is set to become one of the largest buildings in the world, standing 400 metres high, 400 metres wide and 400 metres long.

    Internally, it will feature a tower atop a spiral base, with 2 million square metres (sq m) of floor space dedicated to hospitality. The structure will include commercial areas, cultural and tourist attractions, residential and hotel units and recreational facilities.

    This latest announcement follows other MoUs that NMDC has signed in recent months. In August, NMDC signed an MoU with Alat, a Public Investment Fund-backed company, to explore the development and integration of technologies supporting the Mukaab project.

    This MoU also covers potential future technology needs across the wider New Murabba downtown development. 

    This followed NMDC’s signing of an MoU with South Korea’s Heerim Architects & Planners in July to explore additional design work for assets within the 14-square-kilometre New Murabba downtown project.

    In July, NMDC signed an MoU with another South Korean firm, Naver Cloud Corporation, to explore technological solutions for delivering the New Murabba downtown project.

    Also in July, NMDC announced the completion of excavation works for the Mukaab, the centrepiece of the overall development.

    Downtown destination

    The New Murabba destination will have a total floor area of more than 25 million sq m and will feature more than 104,000 residential units, 9,000 hotel rooms and over 980,000 sq m of retail space.

    The scheme will include 1.4 million sq m of office space, 620,000 sq m of leisure facilities and 1.8 million sq m of space dedicated to community facilities.

    The project will be developed around the concept of sustainability and will include green spaces and walking and cycling paths to promote active lifestyles and community activities.

    The living, working and entertainment facilities will be developed within a 15-minute walking radius. The area will use an internal transport system and will be about a 20-minute drive from the airport.

    The downtown area will feature a museum; a technology and design university; an immersive, multipurpose theatre; and more than 80 entertainment and cultural venues.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14981694/main.jpg
    Yasir Iqbal
  • Read the November 2025 MEED Business Review

    30 October 2025

    Download / Subscribe / 14-day trial access

    The GCC is projected to add at least 80 million tonnes a year (t/y) of liquefied natural gas (LNG) capacity by 2030, placing it firmly among the world’s top three producing regions.

    With soaring global demand for the super-chilled fuel, and regional producers committing tens of billions of dollars to significantly ramp up output, MEED’s latest issue focuses on the outlook for the Gulf’s LNG sector as it enters a new, prolific phase. 

    Beyond the Gulf, MEED finds other regional countries also investing in building LNG import infrastructure, driven by a need to increase the share of gas in their energy mixes.

    This month’s market focus covers the UAE, where physical and digital infrastructure projects are building a connected economy of the future. The UAE is demonstrating, once again, that strategic investment remains the cornerstone of its national progress.

    MEED’s latest issue also includes a report on the Gulf's project finance market, which is continuing to attract strong interest from local and international lenders. Iraq, meanwhile, is revealed as the leader in non-GCC project finance activity.

    This issue is bursting with analysis. The team looks at Abu Dhabi’s latest move to position itself at the forefront of the global transition to low-carbon heavy industry; examines the way in which Riyadh-based Digital Cooperation Organisation is using data to define and measure the digital economy; and asks if Saudi Arabia’s housing boom is leaving its citizens behind.  

    MEED and Saudi Arabia’s National Centre for Privatisation & PPP also showcase the scale and variety of opportunities available in the kingdom’s $190bn pipeline of public‑private partnership projects.

    We hope our valued subscribers enjoy the November 2025 issue of MEED Business Review

     

    Must-read sections in the November 2025 issue of MEED Business Review include:

    AGENDA: 
    Gulf LNG sector enters a new prolific phase

    Mena LNG infrastructure spending rises

    INDUSTRY REPORT:
    PROJECT FINANCE
    Region sees evolving project finance demand
    Iraq leads non-GCC project finance activity

    > PPPs: NCP showcases private sector project opportunities in Saudi Arabia

    > GREEN STEEL: Abu Dhabi takes the lead in green steel transition

    > DIGITISATION: Riyadh-based organisation drives digital growth

    > LEADERSHIP: Saudi Arabia’s housing boom risks leaving citizens behind

    > UAE MARKET REPORT: 
    > COMMENT: Investment shapes UAE growth story
    > GOVERNMENT: Public spending ties the UAE closer together

    > ECONOMY: UAE growth expansion beats expectations
    > BANKING: Stability is the watchword for UAE lenders
    > OIL & GAS: Adnoc strives to build long-term upstream potential
    > PETROCHEMICALS: Taziz fulfils Abu Dhabi’s chemical ambitions at pace
    > POWER: UAE power sector hits record $8.9bn in contracts
    > WATER: Tunnel projects set pace for UAE water sector
    > CONSTRUCTION: UAE construction faces delivery pressures
    > TRANSPORT: $70bn infrastructure schemes underpin UAE economic expansion
    > DATABANK: 
    UAE growth exceeds predictions

    MEED COMMENTS: 
    Neom omitted from Saudi pre-budget statement

    Qiddiya high-speed rail PPP is a bold but risky move
    Wood leadership change holds promise for future
    Power market reshapes contractor landscape

    > GULF PROJECTS INDEX: Gulf projects market leaders return to fore

    > SEPTEMBER 2025 CONTRACTS: Qatar leads awards as regional activity slows

    > ECONOMIC DATA: October 2025: Data drives regional projects

    > OPINIONPeace mission impossible

    BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/14974210/main.gif
    MEED Editorial
  • Contractors submit UAE high-speed rail bids

    30 October 2025

     

    The UAE’s Etihad Rail received bids on 29 October from contractors for the tender to design and build the civil works and station packages for the high-speed railway (HSR) line connecting Abu Dhabi and Dubai.

    Earlier in October, MEED exclusively reported that contractors were forming joint ventures to bid for upcoming design-and-build work packages for the UAE’s high-speed railway project.

    MEED understands that the group formations for the civil works packages are as follows:

    • Limak / Dogus / Ozkar (Turkiye) – Dubai section
    • NPC / Trojan Tunnelling / Kalyon / China State (UAE/UAE/Turkiye/China) – Dubai and Abu Dhabi section
    • WeBuild / Tristar (Italy/UAE) – Abu Dhabi section
    • L&T / China Harbour / Hilalco / Wade Adams (India/China/local/local) – Dubai and Abu Dhabi
    • China Civil Engineering Construction Corporation (China) – Dubai and Abu Dhabi
    • China Railway Engineering Corporation (China) – Dubai section
    • China Railway Engineering Corporation / WBG (China/local) – Abu Dhabi

    French engineering firm Systra is the designer for the Limak-led consortium.

    US-based Jacobs is the designer for the NPC group.

    A joint venture of Systra and US-based Aecom is the designer for the WeBuild group.

    French engineering firm Egis and Singapore’s Surbana Jurong are the designers for the L&T-led consortium.

    Switzerland’s ARX is working with China Civil Engineering Construction Corporation as its designer.

    Chinese firm China Railway Eryuan Engineering Group is working with China Railway Engineering Corporation as its lead designer for both sections of the project.

    Teams are also forming for the systems package. These are:

    • Siemens / Rowad / Salcef (Germany/Egypt/Italy)
    • Hitachi / Orascom (Japan/Egypt)
    • Alstom / L&T (France/India)
    • CRRC (China)
    • Hyundai Rotem / Posco (South Korea)
    • Talgo / Hassan Allam (Spain/Egypt)
    • CAF (Spain)

    The design speed of the trains running on the UAE’s HSR network will be 350 kilometres an hour (km/h) and the operating speed will be 320km/h, as MEED reported last year.

    The proposed HSR programme will be constructed in four phases, gradually adding further connectivity to other areas within the UAE.

    The first phase involves constructing a railway line connecting Abu Dhabi and Dubai, which is expected to be operational by 2030.

    The second phase will develop an inner‑city railway network with 10 stations within the city of Abu Dhabi.

    The third phase of the railway network involves constructing a connection between Abu Dhabi and Al-Ain.

    The fourth phase involves developing an inter-emirate connection between Dubai and Sharjah.

    The 150km first phase of the HSR will stretch from the Al-Zahiyah area of Abu Dhabi to Al-Jaddaf in Dubai.

    The project’s civil works have been split into two packages – Abu Dhabi and Dubai – comprising four sections. The scope of these sections includes:

    • Phase 1A: Al-Zahiyah to Yas Island (23.5km) 
    • Phase 1B: Yas Island to the border of Abu Dhabi/Dubai (64.2km)
    • Phase 1C: Abu Dhabi/Dubai border to Al-Jaddaf (52.1km)
    • Phase 1D: Abu Dhabi airport delta junction and connection with Abu Dhabi airport station (9.2km)

    The rail line will have five stations: Al-Zahiyah (ADT), Saadiyat Island (ADS), Yas Island (YAS), Abu Dhabi International Airport (AUH) and Al-Jaddaf (DJD).

    The ADT, AUH and DJD stations will be underground, while ADS will be elevated and YAS will be at grade.

    The overall construction package also includes provisions for rolling stock, railway systems and two maintenance depots.

    The high-speed project will slash journey times between the UAE’s two largest cities and economic centres. The journey time between the YAS and DJD stations will be 30 minutes.

    Preliminary site testing works have begun. Dubai-based Matcon Testing Laboratory and Abu Dhabi’s Engineering & Research International are conducting drilling tests to ascertain the ground conditions in areas through which the HSR will pass. 

    Spanish engineering firms Sener and Ineco are the project’s engineering consultants.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14979930/main.jpg
    Yasir Iqbal
  • Kuwait Oil Company seeks approval to increase budgets

    30 October 2025

     

    State-owned upstream operator Kuwait Oil Company (KOC) is seeking approval from Kuwait Petroleum Corporation (KPC) to increase budgets for key projects, according to industry sources.

    Approvals are currently being sought for three upstream projects, which saw bids submitted significantly over budget.

    The first project, with a low bid of $2.47bn, involves the development of two facilities: Separation Gathering Centre 1 (SGC-1) and Water Injection Plant 1 (WIP-1).

    The second project, with a low bid of $2.48bn, focuses on developing SGC‑3 and WIP‑3.

    The third project, which involves the development of effluent water disposal plants for injector wells, had a low bid of $1.3bn.

    If approval is given by KPC, then final approval will be sought from the country’s Ministry of Finance, industry sources said.

    Already cancelled

    One Kuwaiti oil project tender that received bids significantly above budget has already been cancelled.

    On 7 October, MEED reported that the tender for the SGC-2 oil project – focused on the installation of a separation gathering centre – was cancelled by Kuwait’s Central Agency for Public Tenders.

    In May, MEED reported that UK-based engineering firm Petrofac submitted a bid more than double the project’s proposed budget.

    Petrofac’s bid was KD422.45m ($1.37bn), while the provisional budget stood at KD207m ($670.2m).

    This contract is expected to be retendered, but there is significant uncertainty over when a new invitation to bid will be issued and how the scope may be changed.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/14978340/main.png
    Wil Crisp