Saudi Arabia under project pressure

28 March 2023

 

Saudi Arabia’s projects market is overheating. The volume of projects announced in the past six years vastly exceeds the resources that are available to work in the kingdom. 

Combined with tight deadlines to complete projects as part of Vision 2030, the pressure on the construction industry to deliver is ratcheting up and turning the tables on the supply chain as the shift from a buyer’s to a seller’s market accelerates.

For the five years from 2016 to 2020, there was an average of about $14bn-worth of contract awards a year in Saudi Arabia for the construction and transport sectors. After rising to $21bn in 2021, the total rose to $32bn in 2022 – the second-best year on record. 

The near doubling of the total annual value of contract awards by the end of 2022 has required a significant scale-up of resources in the kingdom, and the ramp-up is set to continue. 

Much of this pressure is due to the five official gigaprojects, which are major programmes of work that will involve a sustained flow of contract awards for years to come.

Gigaproject focus

The project most recently classified as a gigaproject by the Saudi authorities is the Diriyah Gate development on the western outskirts of Riyadh. It joins the $500bn Neom development in the northwest of the kingdom, Qiddiya entertainment city outside Riyadh, Red Sea Global’s projects on the Red Sea coast and Roshn’s housing developments across the kingdom.

These projects are relatively new. They began to be launched in 2017 and spent much of the following three years in the design phase. 

After a start that was hampered by the work and travel restrictions required to manage the Covid-19 pandemic, construction activity on these projects has accelerated sharply since the start of 2022. 

According to regional project tracker MEED Projects, there have been $36bn-worth of contract awards across these official gigaprojects since 2017. Compared to the entire Saudi projects market over the same period that represents 14.5 per cent of contract awards. 

The percentage rises to 20 per cent if a more recent time frame is used and only contract awards since the start of 2022 are included. As work gathers pace on the gigaprojects, their significance is expected to grow even further.

More major projects

Saudi Arabia’s ambitions are not limited to the five gigaprojects. In January, Crown Prince Mohammed bin Salman al-Saud launched the world’s largest modern downtown in Riyadh. 

Known as the New Murabba project, it involves the development of 19 square kilometres of land to the northwest of the capital. The centrepiece of the project is the Mukaab, which is a 400-metre-cubed structure with a tower standing inside it. 

New Murabba is part of a plan announced in January 2021 to double the size of Riyadh from 7.5 million residents to 15-20 million residents in 2030. Other major projects in the capital include King Salman International airport, King Salman Park, Sports Boulevard and Mohammed bin Salman Non-Profit City. 

Beyond the capital there are development projects planned in all major urban centres by Saudi Downtown Company, as well as entertainment centres being developed by Saudi Entertainment Ventures (Seven).

Connecting these cities and projects will be railways, roads, ports and airports that form part of the National Transport & Logistics strategy, which aims to turn the kingdom into a global hub for travel and trade by 2030.

World’s largest piling project shifts to The Line’s marina

Resourcing challenges  

One of the key challenges for the development firms and government agencies responsible for delivering these projects is securing the resources they need. 

As client bodies attempt to make their projects more attractive for companies to work on, the industry is changing. The first signs of this change can be seen in the consultancy market. 

After years of searching for project opportunities, the big consultancy businesses are now only selectively bidding for projects in the kingdom. This is because their orderbooks are already full, and for many international firms there is a concern that they could become over-exposed to the Saudi market. 

On contracts that have already been won there are also challenges. Staffing projects is proving difficult as the kingdom remains a hard sell for many project professionals, despite significant social reforms that have taken place in recent years. 

Then, once staff have been recruited and deployed on projects, there is the prospect of losing them to competitors or clients that require the same human resources.

Securing contractors

As activity on site accelerates, the bigger concern is contracting resources. As things stand, there are not enough contractors working in Saudi Arabia to deliver all of the planned projects. 

The first way to deal with this problem is to increase the capacity of contractors in the kingdom. In February this year, the Public Investment Fund (PIF) invested $1.3bn in four local construction firms: Al-Bawani Holding Company, Almabani General Contractors Company, El-Seif Engineering Contracting Company and Nesma & Partners Contracting Company. 

This investment will allow the companies to scale up their capacity, adopt advanced technologies and improve local supply chains. 

As these firms grow, the hope is that it will encourage other local companies to also expand.

International or regional companies can also help, and over the past two years foreign players have become active in the kingdom again. Firms such as Bouygues, Samsung C&T, Hyundai Engineering Construction, China State, Webuild, FCC, Alec, Consolidated Contractors Company and Urbacon Trading Contracting Company have all secured major orders. 

In some cases, these contract awards have been supported with foreign finance, which gives the contractor an additional level of comfort when it comes to potential payment for projects. For others, the contract awards reflect growing assurance in the Saudi market. 

Boosting appeal

Confidence has been lifted by measures to make the Saudi market more attractive. Payment terms are improving and many of the frustrations typically faced by contractors are being addressed. 

One example is the use of performance guarantees. Red Sea Global, which is developing the Red Sea Project and Amaala gigaprojects on the Red Sea coast, no longer requires contractors to submit bid bonds and returns performance bonds on completion of the project, along with half of the retention. 

Alternative procurement methods and contract types are also being used, notably early contractor involvement and design and build. 

These different approaches reduce risk for the contractor and allow the client to lock in resources at a much earlier stage of the procurement process. 

Red Sea Global has adopted a different approach and is self-delivering the bulk of its projects. By acting as its own management contractor, it engages with subcontractors itself. While this means it does not need to secure the services of a main contractor, it still requires engaging with the supply chain, which – like the main contractor market – has finite resources in Saudi Arabia.

Payment terms are improving and many of the frustrations typically faced by contractors are being addressed 

Driving efficiency

On the other side of the equation, making construction more efficient could also help to limit the resources required. 

Client bodies are exploring modern methods of construction to increase the speed of delivery, reduce costs and cut the amount of resources needed on site.

The market could also be self-limiting. Decision-making in the kingdom remains centralised, which means key project decisions can be slow. While this is changing as development companies are left to run their own projects, bureaucracy can impact the speed of delivery, which ultimately reduces the immediate demand for resources on a project. 

While slow decision-making could impact progress on some projects, the overriding story for 2023 will be one of sustained pressure on the kingdom’s construction sector as it becomes a seller’s market. 

With that, there is the likelihood that contractor margins will start to creep up, just as they did in the UAE when its construction market overheated in 2003 and 2008. 

So far, that does not appear to have happened, as clients in Saudi Arabia have managed to find sufficient resources. For that to remain the case will be a major challenge, however, as on-site activity for most projects in the kingdom is still several years away from peaking. 

Daniel King, director, Currie & Brown

International contractors continue to see a level of risk in the Saudi market

“There is a lot of opportunity. A large volume of work is being planned, designed and rolled out. With that, there is significant pressure right now on the market in terms of resources and supply chain. 

“On the consultancy side, the market is tremendously difficult. 

“Even with the best incentives and best set of practices, retaining staff is a challenge. People are being attracted elsewhere and the competition is fierce. 

“For the contractors, there are a lot of tenders being let. The perception that the market has risk remains, however. That is certainly the perception for international contractors, and they are still looking at the Saudi market with some level of risk appreciation in terms of how quickly they are going to be paid and what the margins really are. 

“That approach will likely prevail for the short to medium term, until clients’ practices change in terms of contractual frameworks and payment practices. 

“Varied procurement practices are coming into play to guarantee supply chain. It might be early contractor involvement or partnering, but the main purpose is to guarantee the right level of contractors.”

Adel Karem Jemah, senior vice-president, Hill International

To prevent resource shortages, supply chain and procurement must be carefully considered

“It is imperative to consider alternative methods of procurement during boom times, and the current boom in Saudi Arabia is unprecedented considering the types, size, nature and complexity of projects that have been announced in line with Vision 2030. 

“This necessitates giving due consideration to the supply chain and type of procurement.

“It is not enough to look for resources locally or even regionally to cope with such projects. One needs to reach out to where such resources are available globally, either due to slowdowns in certain regions or the completion of other major projects. 

“Cost-plus contracts were used previously in many projects in Saudi Arabia. However, the risk for such contracts rests with the client and sometimes the cost ends up much more than expected. That is why financiers prefer the lump-sum type of contracts. 

“Nonetheless, I can see this type of contract being used for fast-track projects with very tight schedules, for instance to meet deadlines for facilities required for international or regional sporting events. 

“In any case, the evaluation and selection of contractors needs to be done with extreme diligence.”


MEED's April 2023 special report on Saudi Arabia includes:

> ECONOMY: Riyadh steps up the Vision 2030 tempo

> CONSTRUCTION: Saudi construction project ramp-up accelerates

> UPSTREAM: Aramco slated to escalate upstream spending

> DOWNSTREAM: Petchems ambitions define Saudi downstream

> POWER: Saudi Arabia reinvigorates power sector

> WATER: Saudi water begins next growth phase

> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10705629/main.gif
Colin Foreman
Related Articles
  • Construction begins on Aman Dubai Hotel and Residences

    28 April 2026

    Dubai-based developer H&H Development and Switzerland’s Aman Group have broken ground on the Aman Dubai Hotel and Residences project in Dubai’s Jumeirah area.

    The project’s enabling works contract has been awarded to local firm Swissboring.

    Foundation works are expected to start this quarter.

    The developers said ground improvement works have now been completed. Another local firm, DBB Contracting, carried out the works.

    The project comprises a hotel, 78 branded residences and villas.

    Singapore-headquartered architectural firm Kerry Hill Architects is the project consultant.

    Dubai real estate developments continue to dominate the UAE’s construction market, with schemes worth more than $323bn either under execution or in planning.

    This aligns with a GlobalData forecast that the UAE construction sector will grow by 3% in real terms in 2026, supported by infrastructure, energy and utilities, and residential projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16591687/main.jpg
    Yasir Iqbal
  • Regional war deepens Kuwait oil sector’s tender crisis

    28 April 2026

    Commentary
    Wil Crisp
    Oil & gas reporter

    Contractors in Kuwait expect the regional conflict and disruption to shipping to worsen the country’s existing oil and gas tendering problems, causing long-term disruption in the sector.

    In the months prior to the US and Israel attacking Iran on 28 February, contract tenders worth an estimated $9.1bn were cancelled after bids came in above the projects’ allocated budgets.

    Contractors largely blamed the cancellations on long delays to tender processes after budgets had been set.

    The delays, which often extended for several years, meant inflation drove up the cost of materials and labour, making it almost impossible for contractors to submit bids within the original budgets.

    One industry source said: “The reason all of these contracts were cancelled was because the tender processes for large projects had started moving again after stalling for a long time.

    “Bids came in and unfortunately they were over budget. It was then expected that tender processes would restart and these projects would ultimately be awarded – but now the war means that Kuwait is facing a whole new wave of project delays and nobody knows when it is going to end.”

    War impact

    Many industry insiders believe delays caused by the war and the closure of the Strait of Hormuz will once again seriously disrupt projects, just as many stakeholders believed the country was about to see an uptick in project progress.

    One source said: “Bid bonds are going to have to be renewed and some bidders might just use that as an opportunity to drop out of the bidding process.

    “It’s also possible that work that has already been done, like feasibility studies, will no longer be relevant and will have to be repeated.”

    2025 rebound

    Last year, Kuwait recorded its highest total annual value for oil, gas and chemicals contract awards since 2017, according to data from regional project tracker MEED Projects.

    A total of 19 contract awards with a combined value of $1.9bn were awarded.

    This was more than four times the value of contract awards across the same sectors in 2024, when awards were worth just $436m.

    It was also above the $1.7bn peak recorded in 2021, but it remained far lower than the values seen in 2014-17, when several large-scale, multibillion-dollar projects were awarded in the country.

    The surge in the value of contract awards came after Kuwait’s emir indefinitely dissolved parliament and suspended some of the country’s constitutional articles in May 2024.

    Prior to the suspension of parliament, Kuwait suffered from very low levels of project awards for several years amid political gridlock and infighting between the cabinet and parliament.

    This meant important decisions about projects could not be made – a major obstacle to the progression of strategic oil projects.

    Forward outlook

    With several major oil and gas projects under development in late 2025 and early 2026, some expected 2026 to record a far higher volume of oil and gas contract awards than 2025.

    Projects expected to be tendered – and potentially awarded – this year included a $3.3bn onshore production facility due to be developed next to the Al-Zour refinery.

    This project has already been delayed and put on hold as a result of fallout from the US and Israel’s conflict with Iran.

    Had it been awarded, it would have been the biggest single oil and gas contract award in Kuwait in more than 10 years.

    Now, as a result of the conflict, many of the large tenders expected to take place this year are likely to be significantly delayed.

    One source said: “Right now, everyone in the oil and gas sector is waiting for some sort of sign of improving stability before they make a decision and there’s a lot of uncertainty.

    “The state-owned oil companies aren’t communicating with contractors like they normally do and the price of a lot of materials has increased dramatically.”

    Even if the standoff between the US and Iran over reopening the Strait of Hormuz is resolved in the near future, it is likely to take months or years before Kuwait’s oil and gas project market regains the momentum it had at the beginning of 2026.

    Given the lack of flexibility within Kuwait’s existing tendering system, delays can easily lead to tenders being cancelled, and the conflict’s inflationary impact will make it even harder for contractors to meet budgets set before the latest disruption.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16590560/main0421.png
    Wil Crisp
  • Partners launch feed-to-EPC contest for Duqm petchems project

    27 April 2026

     

    Register for MEED’s 14-day trial access 

    Omani state energy conglomerate OQ Group and Kuwait Petroleum International (KPI), the overseas subsidiary of Kuwait Petroleum Corporation, have initiated a feed-to-EPC competition among contractors to develop a major petrochemicals complex at Duqm.

    Under a feed-to-EPC model, the project operator selects contractors to carry out front-end engineering and design (feed). It then awards the engineering, procurement and construction (EPC) contract to the contractor with the most competitive feed proposal, while compensating the other contestants for their work.

    OQ8, the 50:50 joint venture of OQ and KPI, is understood to have issued the tender for the Duqm petrochemicals project’s feed-to-EPC competition in mid-March, with a deadline of 6 May for contractors to submit proposals, sources told MEED.

    Several local and international contractors based in Oman are believed to be participating in the competition, according to sources.

    OQ Group CEO Ashraf Bin Hamad Al-Maamari and KPI’s CEO Shafi Bin Taleb Al-Ajmi signed an agreement on 3 February, during the Kuwait Oil & Gas Show and Conference, to develop a major petrochemicals-producing complex in Oman’s Duqm. The parties did not disclose details at the time.

    ALSO READ: Duqm petrochemicals revival provides fillip to Gulf projects market

    The agreement represented a significant step forward in Oman and Kuwait’s long-held plans to jointly develop a petrochemicals complex next to the existing Duqm refinery, which will benefit from favourable feedstock access and strong cost competitiveness.

    The planned facility will also benefit from  in Al-Wusta governorate, along Oman’s Arabian Sea coastline.

    OQ8 had struggled to make meaningful progress on the Duqm petrochemicals project since the plan was conceived as early as 2018, for a variety of reasons.

    The original plan for the Duqm petrochemicals facility, estimated at $7bn, centred on a mixed-feed steam cracker with a capacity to produce 1.6 million tonnes a year (t/y) of ethylene. The project also included a polypropylene (PP) plant with a capacity of 280,000 t/y and a high-density polyethylene (HDPE) plant with a capacity of 480,000 t/y.

    The complex was also expected to include an aromatics plant, as well as storage facilities for naphtha and liquefied petroleum gas (LPG).

    The project’s prospects were temporarily boosted when Saudi Basic Industries Corporation (Sabic) expressed interest in investing by signing a non-binding memorandum of understanding with OQ in December 2021.

    Reuters reported in December that Sabic was withdrawing from the project, leaving OQ to look for other partners. The new agreement between OQ and KPI is understood to have followed the Saudi chemical giant’s departure.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577785/main.jpg
    Indrajit Sen
  • Nakheel awards $953m Palm Jebel Ali villas deal

    27 April 2026

    Dubai-based real estate developer Nakheel, now part of Dubai Holding, has awarded two contracts worth AED3.5bn ($953m) to local firms for the construction of 544 villas at its Palm Jebel Ali project in Dubai.

    The first contract was awarded to Ginco General Contracting for the construction of 354 villas across fronds A to D.

    The second contract was awarded to United Engineering Construction Company (Unec) for the construction of 190 villas on fronds E and F.

    Construction is expected to begin in Q2 this year, with completion scheduled for 2028.

    Earlier phases

    In October 2024, Nakheel awarded three contracts worth AED5bn ($1.3bn) for the construction of 723 villas on fronds K to P. The contracts went to Ginco, Unec and the local Shapoorji Pallonji.

    Under these awards, Ginco is delivering 197 villas on fronds O and P, Shapoorji Pallonji is constructing 275 villas on fronds M and N, and Unec is building 251 villas on fronds K and L. Villa construction is expected to be completed by 2026.

    Infrastructure works

    This was followed by Nakheel awarding infrastructure contracts worth over AED750m ($204m) to local firm Dutco Construction for works on Palm Jebel Ali.

    The infrastructure work includes utility connections, excavation, backfilling, and the construction of roads and pavements across fronds A to G. It also covers 11-kilovolt power distribution and telecommunications-related utility works.

    Reclamation contract

    In August 2024, Nakheel awarded an AED810m ($220m) contract to complete the reclamation works for the project.

    The contract was awarded to Belgium’s Jan De Nul. Its scope includes dredging, land reclamation, beach profiling and sand placement to support the construction of villas across all fronds.

    Masterplan details

    Nakheel released details of the new masterplan for Palm Jebel Ali in June 2023. Twice the size of Palm Jumeirah, Palm Jebel Ali will have 110 kilometres of shoreline and extensive green spaces. The development will feature more than 80 hotels and resorts, along with a range of entertainment and leisure facilities.

    It includes seven connected islands that will cater to approximately 35,000 families. The development also emphasises sustainability, with 30% of public facilities expected to be powered by renewable energy.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577782/main.jpg
    Yasir Iqbal
  • Iraq’s first LNG terminal to be completed in June

    27 April 2026

    Iraq’s first liquefied natural gas (LNG) import terminal is expected to be completed in early June, according to the country’s Ministry of Electricity.

    The terminal, which has an estimated investment value of $450m, is being developed at the Port of Khor Al-Zubair and will have a capacity of 750 million standard cubic feet a day (cf/d).

    Ministry spokesperson Ahmed Mousa told the Iraqi News Agency that “work is proceeding at an accelerated pace to complete the LNG platform”, noting that “the government has set 1 June as the date for finishing the project”.

    In October last year, US-based Excelerate Energy signed a commercial agreement with a subsidiary of Iraq’s Ministry of Electricity to develop the floating LNG terminal.

    The contract was signed at the office of Iraq’s Prime Minister Mohammed Shia Al-Sudani during a ceremony attended by senior officials from both countries, including the US deputy secretary of energy James Danly.

    The contract included a five-year agreement for regasification services and LNG supply with extension options, featuring a minimum contracted offtake of 250 million cf/d.

    Ahmed Mousa said that “under the contract, the company is responsible for completing the facility as well as securing the agreed gas quantities from any source, in line with the specified terms”.

    He added: “Work is continuing according to the planned timelines to complete the project on schedule, as part of the Ministry of Electricity’s plans to keep pace with peak summer loads.”

    Although Iraq is Opec’s second-largest oil producer after Saudi Arabia, it is a net natural gas importer because its lack of infrastructure investment has meant that, until 2023, it flared roughly half of the estimated 3.12 billion cf/d of gas produced in association with crude oil.

    Iraq’s reliance on flaring associated gas instead of gathering and processing it has prevented the country from fully realising its potential as a gas producer and forced the Iraqi government to rely on costly gas and electricity imports from Iran.

    Recently, Iraq’s oil and gas sector has been disrupted by fallout from the US and Israel’s attack on Iran on 28 February and the subsequent regional conflict.

    Over recent weeks, Iraq’s oil exports have collapsed by about 80% amid problems shipping crude through the Strait of Hormuz.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16577746/main.jpg
    Wil Crisp