Saudi Arabia under project pressure

28 March 2023

 

Saudi Arabia’s projects market is overheating. The volume of projects announced in the past six years vastly exceeds the resources that are available to work in the kingdom. 

Combined with tight deadlines to complete projects as part of Vision 2030, the pressure on the construction industry to deliver is ratcheting up and turning the tables on the supply chain as the shift from a buyer’s to a seller’s market accelerates.

For the five years from 2016 to 2020, there was an average of about $14bn-worth of contract awards a year in Saudi Arabia for the construction and transport sectors. After rising to $21bn in 2021, the total rose to $32bn in 2022 – the second-best year on record. 

The near doubling of the total annual value of contract awards by the end of 2022 has required a significant scale-up of resources in the kingdom, and the ramp-up is set to continue. 

Much of this pressure is due to the five official gigaprojects, which are major programmes of work that will involve a sustained flow of contract awards for years to come.

Gigaproject focus

The project most recently classified as a gigaproject by the Saudi authorities is the Diriyah Gate development on the western outskirts of Riyadh. It joins the $500bn Neom development in the northwest of the kingdom, Qiddiya entertainment city outside Riyadh, Red Sea Global’s projects on the Red Sea coast and Roshn’s housing developments across the kingdom.

These projects are relatively new. They began to be launched in 2017 and spent much of the following three years in the design phase. 

After a start that was hampered by the work and travel restrictions required to manage the Covid-19 pandemic, construction activity on these projects has accelerated sharply since the start of 2022. 

According to regional project tracker MEED Projects, there have been $36bn-worth of contract awards across these official gigaprojects since 2017. Compared to the entire Saudi projects market over the same period that represents 14.5 per cent of contract awards. 

The percentage rises to 20 per cent if a more recent time frame is used and only contract awards since the start of 2022 are included. As work gathers pace on the gigaprojects, their significance is expected to grow even further.

More major projects

Saudi Arabia’s ambitions are not limited to the five gigaprojects. In January, Crown Prince Mohammed bin Salman al-Saud launched the world’s largest modern downtown in Riyadh. 

Known as the New Murabba project, it involves the development of 19 square kilometres of land to the northwest of the capital. The centrepiece of the project is the Mukaab, which is a 400-metre-cubed structure with a tower standing inside it. 

New Murabba is part of a plan announced in January 2021 to double the size of Riyadh from 7.5 million residents to 15-20 million residents in 2030. Other major projects in the capital include King Salman International airport, King Salman Park, Sports Boulevard and Mohammed bin Salman Non-Profit City. 

Beyond the capital there are development projects planned in all major urban centres by Saudi Downtown Company, as well as entertainment centres being developed by Saudi Entertainment Ventures (Seven).

Connecting these cities and projects will be railways, roads, ports and airports that form part of the National Transport & Logistics strategy, which aims to turn the kingdom into a global hub for travel and trade by 2030.

World’s largest piling project shifts to The Line’s marina

Resourcing challenges  

One of the key challenges for the development firms and government agencies responsible for delivering these projects is securing the resources they need. 

As client bodies attempt to make their projects more attractive for companies to work on, the industry is changing. The first signs of this change can be seen in the consultancy market. 

After years of searching for project opportunities, the big consultancy businesses are now only selectively bidding for projects in the kingdom. This is because their orderbooks are already full, and for many international firms there is a concern that they could become over-exposed to the Saudi market. 

On contracts that have already been won there are also challenges. Staffing projects is proving difficult as the kingdom remains a hard sell for many project professionals, despite significant social reforms that have taken place in recent years. 

Then, once staff have been recruited and deployed on projects, there is the prospect of losing them to competitors or clients that require the same human resources.

Securing contractors

As activity on site accelerates, the bigger concern is contracting resources. As things stand, there are not enough contractors working in Saudi Arabia to deliver all of the planned projects. 

The first way to deal with this problem is to increase the capacity of contractors in the kingdom. In February this year, the Public Investment Fund (PIF) invested $1.3bn in four local construction firms: Al-Bawani Holding Company, Almabani General Contractors Company, El-Seif Engineering Contracting Company and Nesma & Partners Contracting Company. 

This investment will allow the companies to scale up their capacity, adopt advanced technologies and improve local supply chains. 

As these firms grow, the hope is that it will encourage other local companies to also expand.

International or regional companies can also help, and over the past two years foreign players have become active in the kingdom again. Firms such as Bouygues, Samsung C&T, Hyundai Engineering Construction, China State, Webuild, FCC, Alec, Consolidated Contractors Company and Urbacon Trading Contracting Company have all secured major orders. 

In some cases, these contract awards have been supported with foreign finance, which gives the contractor an additional level of comfort when it comes to potential payment for projects. For others, the contract awards reflect growing assurance in the Saudi market. 

Boosting appeal

Confidence has been lifted by measures to make the Saudi market more attractive. Payment terms are improving and many of the frustrations typically faced by contractors are being addressed. 

One example is the use of performance guarantees. Red Sea Global, which is developing the Red Sea Project and Amaala gigaprojects on the Red Sea coast, no longer requires contractors to submit bid bonds and returns performance bonds on completion of the project, along with half of the retention. 

Alternative procurement methods and contract types are also being used, notably early contractor involvement and design and build. 

These different approaches reduce risk for the contractor and allow the client to lock in resources at a much earlier stage of the procurement process. 

Red Sea Global has adopted a different approach and is self-delivering the bulk of its projects. By acting as its own management contractor, it engages with subcontractors itself. While this means it does not need to secure the services of a main contractor, it still requires engaging with the supply chain, which – like the main contractor market – has finite resources in Saudi Arabia.

Payment terms are improving and many of the frustrations typically faced by contractors are being addressed 

Driving efficiency

On the other side of the equation, making construction more efficient could also help to limit the resources required. 

Client bodies are exploring modern methods of construction to increase the speed of delivery, reduce costs and cut the amount of resources needed on site.

The market could also be self-limiting. Decision-making in the kingdom remains centralised, which means key project decisions can be slow. While this is changing as development companies are left to run their own projects, bureaucracy can impact the speed of delivery, which ultimately reduces the immediate demand for resources on a project. 

While slow decision-making could impact progress on some projects, the overriding story for 2023 will be one of sustained pressure on the kingdom’s construction sector as it becomes a seller’s market. 

With that, there is the likelihood that contractor margins will start to creep up, just as they did in the UAE when its construction market overheated in 2003 and 2008. 

So far, that does not appear to have happened, as clients in Saudi Arabia have managed to find sufficient resources. For that to remain the case will be a major challenge, however, as on-site activity for most projects in the kingdom is still several years away from peaking. 

Daniel King, director, Currie & Brown

International contractors continue to see a level of risk in the Saudi market

“There is a lot of opportunity. A large volume of work is being planned, designed and rolled out. With that, there is significant pressure right now on the market in terms of resources and supply chain. 

“On the consultancy side, the market is tremendously difficult. 

“Even with the best incentives and best set of practices, retaining staff is a challenge. People are being attracted elsewhere and the competition is fierce. 

“For the contractors, there are a lot of tenders being let. The perception that the market has risk remains, however. That is certainly the perception for international contractors, and they are still looking at the Saudi market with some level of risk appreciation in terms of how quickly they are going to be paid and what the margins really are. 

“That approach will likely prevail for the short to medium term, until clients’ practices change in terms of contractual frameworks and payment practices. 

“Varied procurement practices are coming into play to guarantee supply chain. It might be early contractor involvement or partnering, but the main purpose is to guarantee the right level of contractors.”

Adel Karem Jemah, senior vice-president, Hill International

To prevent resource shortages, supply chain and procurement must be carefully considered

“It is imperative to consider alternative methods of procurement during boom times, and the current boom in Saudi Arabia is unprecedented considering the types, size, nature and complexity of projects that have been announced in line with Vision 2030. 

“This necessitates giving due consideration to the supply chain and type of procurement.

“It is not enough to look for resources locally or even regionally to cope with such projects. One needs to reach out to where such resources are available globally, either due to slowdowns in certain regions or the completion of other major projects. 

“Cost-plus contracts were used previously in many projects in Saudi Arabia. However, the risk for such contracts rests with the client and sometimes the cost ends up much more than expected. That is why financiers prefer the lump-sum type of contracts. 

“Nonetheless, I can see this type of contract being used for fast-track projects with very tight schedules, for instance to meet deadlines for facilities required for international or regional sporting events. 

“In any case, the evaluation and selection of contractors needs to be done with extreme diligence.”


MEED's April 2023 special report on Saudi Arabia includes:

> ECONOMY: Riyadh steps up the Vision 2030 tempo

> CONSTRUCTION: Saudi construction project ramp-up accelerates

> UPSTREAM: Aramco slated to escalate upstream spending

> DOWNSTREAM: Petchems ambitions define Saudi downstream

> POWER: Saudi Arabia reinvigorates power sector

> WATER: Saudi water begins next growth phase

> BANKING: Saudi banks bid to keep ahead of the pack

https://image.digitalinsightresearch.in/uploads/NewsArticle/10705629/main.gif
Colin Foreman
Related Articles
  • Iraq boosts oil exports after talks with Iran

    7 September 2026

    Iraq has boosted its oil export capacity to more than 3 million barrels a day (b/d) after holding talks with Iran, according to Oil Minister Basim Mohammed Khudair.

    In a video statement released on 5 September, he said the country has been able to ship more than 3 million b/d since the start of this month.

    He also said: “The government plans to raise export capacity to 5 million b/d after completing the strategic pipelines extending towards Fishakhpur and Banias, as well as the export outlets in the Strait of Hormuz.”

    Iraq’s oil exports rose to around 2.34 million b/d in August, according ⁠to ⁠officials.

    The increase came after Iran granted special permission for a number of Iraqi oil tankers to pass through the Strait of Hormuz in August, following repeated requests from Baghdad.

    On 22 August, Iraqi President Nizar Amidi said Iran had facilitated the passage of “some ships carrying Iraqi oil in the strait” in recent days, and Baghdad had discussed exporting Iraqi oil through Hormuz with Iranian officials.

    The details of Iraq’s agreement have not been released by officials, but Amidi said that his government “will not accept Iraqi territory being used to launch attacks against any other country”.

    The Iraqi president said attacks launched from inside Iraq against countries in the region “have no justification”.

    Prior to the deal being announced, Iraqi exports had been dramatically reduced amid fallout from the regional war that started when the US and Israel attacked Iran on 28 February 2026.

    The regional war has led to significant disruption to shipping through the Strait of Hormuz, which is a key export route for Iraqi oil.

    Iraq’s crude exports fell from more than 3.3 million b/d before the war to a low of about 330,000 b/d in April, while exports from its southern terminals were temporarily halted altogether in March.

    Tensions still remain high in the region, and some shipping is still being disrupted by the ongoing conflict.

    On 2 September, Saudi Arabia condemned an Iranian attack on an oil tanker owned by its national shipping company that resulted in the deaths of two citizens of the Philippines.

    In a statement, Saudi Arabia’s Foreign Ministry said Iran targeted the Sidr tanker, owned by national carrier Bahri, while it was transiting the Strait of Hormuz two days earlier.

    It said: “The kingdom stressed the necessity of halting escalations and respecting international maritime safety and the security of global energy supplies.”

    Kuwait and Qatar’s foreign ministries said the attack violated international law and freedom of maritime navigation.

    Qatar called the attack a “flagrant violation of the rules of international law and freedom of maritime navigation”. Doha further rejected the use of the Strait of Hormuz as a “bargaining chip”.

    Iran has repeatedly attacked and threatened tankers attempting to sail through the strategic waterway without authorisation, impeding energy exports from neighbouring oil-rich Gulf countries.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19424826/main.jpg
    Wil Crisp
  • Customs clearance delays Iraqi oil field development

    7 September 2026

     

    Problems getting critical equipment through customs are delaying a key part of Iraq’s $27bn Gas Growth Integrated Project (GGIP), according to industry sources.

    Phase one of the GGIP is expected to be worth about $10bn. France’s TotalEnergies holds a 45% stake in the project, while Iraq’s Basra Oil Company (BOC) and QatarEnergy hold 30% and 25% respectively.

    The specific part of the project that is being delayed by customs issues is known as Ratawi phase 1.

    It is focused on developing Iraq’s Ratawi oil and gas field as part of the wider GGIP.

    Previously, this project was expected to come online before the end of June this year.

    Speaking on 23 July 2026, TotalEnergies CEO Patrick Pouyanne said that Ratawi phase 1 was being delayed due to issues related to the conflict with Iran, but he still expected it to start up before the end of September 2026.

    Although recent complications are expected to delay the project further, it is on track to come online in mid-to-late October at the earliest, according to industry sources.

    One source said: “Right now, the main issue causing delays to the project isn’t the crisis in the Strait of Hormuz; it’s Iraqi customs clearance.

    “TotalEnergies is having trouble getting critical equipment released.”

    TotalEnergies did not respond to a request to comment on the progress of Ratawi phase 1.

    In November last year, the French company said that phase 1 aimed to increase production to 120,000 barrels a day (b/d).

    At the time, it also said that it was expected to come on stream “by early 2026”.

    It also said that the launch of phase 2 of the project, which would be considered “full field development”, would enable the company to increase production to 210,000 b/d starting in 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19424624/main.png
    Wil Crisp
  • Firms prepare bids for NWC sewage treatment package 14

    4 September 2026

     

    At least three contractors are preparing to make offers for package 14 of Saudi Arabia’s long-term operations and maintenance (LTOM) sewage treatment programme, according to sources.

    Known as Eastern A Cluster (LTOM14), the package was tendered by the state-owned National Water Company (NWC) in April, with a bid submission deadline of 30 September.

    The contract covers the upgrade of six existing sewage treatment plants (STPs), with a capacity expansion of 30,000 cubic metres a day (cm/d) at the Al-Jarodia STP.

    This will increase total treatment capacity from about 263,000 cm/d to approximately 293,000 cm/d, with an estimated cost of $180m.

    According to sources, the firms preparing to submit bids include:

    • Alkhorayef Water & Power Technologies (Saudi Arabia)
    • Civil Works Company (Saudi Arabia)
    • Miahona (Saudi Arabia)

    The latest phase follows the formal signing of a $347m contract between NWC and a Saudi-Chinese consortium for Northern Cluster Sewage Treatment Plants Package 10 (LTOM10) on 2 September.

    The same consortium led by United Water (China) is not planning to bid for LTOM14 and is expected to formally sign a contract for LTOM11 in the coming months, a source said.

    In April, MEED exclusively reported that the group had won the contract for package 11, which will have a combined capacity of about 440,000 cm/d.

    It is also understood that Beijing Enterprises, a bidder for North Western B Cluster (LTOM12), is not preparing to bid for package 14.

    In the meantime, the contract for LTOM12 is moving towards award, with bids currently under evaluation.

    The contract covers the construction and upgrade of seven STPs with a combined capacity of about 162,000 cm/d. As previously reported, NWC opened financial bids for the project in April.

    US/India-based Synergy Consulting is Financial Advisor to NWC for the full LTOM programme.

    Future phases

    In total, the LTOM programme comprises 19 packages split into two phases. In May 2024, NWC announced it had awarded $2.5bn-worth of contracts in the first phase. Phase two of the programme includes 10 packages covering 117 treatment plants.

    In April, MEED exclusively reported that NWC had held several discussions regarding changes in scope details and potential expansions to upcoming projects. This involved “grouping some upcoming projects”.

    The request for proposals for LTOM13 was subsequently put on hold and it is now understood that this tender has likely been merged with other packages in the programme.

    According to a source, Eastern B Cluster (LTOM15) has also been cancelled and has likely been merged. LTOM15 had comprised two STPs with a total capacity of 152,000 cm/d.

    The next contract to be tendered will be Central Cluster (LTOM16), potentially in November, a source added.

    Under the original scope, LTOM16 covers the construction of 14 STPs with a total capacity of 153,000 cm/d.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19358188/main.jpg
    Mark Dowdall
  • Egyptian contractor wins Abu Dhabi Ramhan Island deal

    4 September 2026

    Egypt-headquartered contractor Rowad Modern Engineering has been awarded the main works contract for the Marina Apartments project on Ramhan Island, Abu Dhabi.

    The contract was awarded by the local firm Eagle Hills, which is led by Mohamed Alabbar, the founder and chairman of Emaar Properties.

    Rowad’s scope includes structural and architectural works, finishing, and mechanical, electrical and plumbing systems.

    The company will also deliver infrastructure works, including utility connections to external networks, testing and commissioning.

    The development comprises two residential towers offering 187 residential units.

    The works will be carried out under the consultancy supervision of local engineering firm Mirage Leisure & Development.

    The latest contract award follows Eagle Hills awarding the local firm Arabian Construction Company (ACC) an estimated AED2.5bn ($680m) construction contract to build about 500 villas at the Ramhan Island development, as reported by MEED previously.

    Located off the coast of Abu Dhabi, the Ramhan Island development spans an area of over 4 million square metres.

    The overall development includes the construction of 1,800 villas, 900 residences, a hotel and retail facilities.

    Mohamed Alabbar launched the Ramhan Island development in May 2024.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19355437/main.jpg
    Yasir Iqbal
  • Dubai sets deadline for Jebel Ali waste-to-energy PPP

    4 September 2026

     

    Register for MEED’s 14-day trial access 

    Dubai Municipality has set a 27 September deadline for developers to submit expressions of interest (EOIs) for its planned Jebel Ali waste-to-energy (WTE) public-private partnership (PPP), according to a source.

    The greenfield facility is planned to treat up to 6,000 tonnes of municipal solid waste a day.

    The municipality is seeking international and local developers to develop, finance and operate the facility. It is planning to prequalify developers later this year before issuing a request for proposals (RFP) in the first quarter of next year, a source said.

    The Jebel Ali facility is intended to support Dubai’s waste-management strategy and its target of reducing reliance on landfill.

    Dubai Municipality is being advised by a team led by Abu Dhabi’s Tribe Infrastructure Group, with UK-headquartered Ashurst and Germany’s Fichtner also involved.

    It was confirmed to MEED that the project is separate from the planned second phase of the Warsan WTE facility, for which Dubai Municipality issued a consultancy tender in February.

    That facility will be located in Warsan 2, next to the Al-Aweer sewage treatment plant. The expansion is expected to increase waste-conversion capacity at the existing Warsan site with an estimated budget of $500m. The consultancy contract has a duration of six years.

    The original Warsan WTE plant, Dubai’s first major WTE public-private partnership (PPP) project, reached full commercial operations in 2024.

    Located in the Warsan area, the AED4bn ($1.1bn) facility treats 1.9 million tonnes of municipal solid waste annually, generating up to 220MW of thermal energy that is fed into the local grid.

    In February 2023, state utility Dubai Electricity & Water Authority (Dewa) and Dubai Waste Management Company signed the power-purchase agreement (PPA) for the project.

    Dubai Waste Management Company, the special-purpose vehicle implementing the scheme, reached financial close in June 2021 for the project.

    The Warsan project was developed under a 35-year PPP concession by a consortium comprising Dubai Holding, Dubai Aluminium, Tech Group and Itochu Corporation. 

    The main contractor was a joint venture of Belgium’s Besix Group and Hitachi Zosen Inova of Switzerland.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19354502/main.jpg
    Mark Dowdall