Saudi Arabia to expand grid by 60% by 2030

21 March 2025

State utility Saudi Electricity Company (SEC) aims to expand its power transmission network to approximately 160,000 kilometres (km) by 2030, up 60% over its existing network of about 99,800km.

An increased subscriber base and higher electricity consumption, as well as the integration of renewables, underpin plans to expand the SEC network over the next five years.

"By 2030, SEC aims to expand its transmission network to encompass approximately 160,000km of transmission lines, [and] install nine new high-voltage, direct current lines between regions and neighbouring countries," SEC said in its 2024 earnings report.

"These targets are underscoring our commitment to building a robust and future-ready grid infrastructure."

MEED understands that SEC energised 26 new transmission substations, increasing the kingdom's transmission network to 1,260, a 2.1% increase over 2023.

These new substations increased the cumulative substation capacity to 497,902 megavolt-amperes, a 2% growth over the previous year.

Of the total, SEC installed and energised 10 substations and added 148.5km of transmission lines, integrating 6.6GW of renewables in 2024.

An additional 24 substations and 4,327km of transmission lines are under construction to integrate about 34.4GW of renewable energy capacity into the grid by 2027.

Generation

SEC said generation capacity connected to the grid reached 92.15GW in 2024, up 6.9% over 2023, when installed capacity stood at 86.23GW.

The firm said its directly owned capacity of the total now stands at 56.4GW, representing 61% of the kingdom's total capacity.

Electricity production at SEC's plants surged 7.5% to 236.4 terawatt-hours in 2024.

The firm said that 1,580MW of generation capacity was added or restored to SEC's power plant fleet in 2024, while the liquid-to-gas conversion of the Riyadh power plant 10 (PP10) and phase one is expected to be completed this year.

SEC is working with local contracting company Alfanar, in addition to US-based original equipment manufacturer GE Vernova, to convert the plant's fuel feedstock to natural gas, a lower carbon intensity fuel compared to the crude oil and distillate that currently power the plant.

According to the Energy Institute, Saudi Arabia's total electricity generation in 2023 reached 422.9 terawatt-hours (TWh). Oil accounted for 152.1TWh, or about 36% of the total, while natural gas accounted for 265TWh, or 63%, and renewables made up 5.8TWh or 1%. 

"Eight projects with a total capacity of 22.3GW are under transition by 2030," SEC said in its report.

It added: "SEC is currently developing 11 generation projects with an aggregate 23.4GW of capacity. These will be across directly owned capacity projects (10.476 GW), expansion and partnerships (5.324GW) and joint venture projects (7.610GW)."

Battery storage

SEC has been procuring battery energy storage system (bess) plants, with the aim of boosting the reliability and flexibility of the kingdom's electricity grid.

The first 500MW bess project in Bisha has been completed, while work is under way for 22 gigawatt-hours of bess capacity across five projects that are under development.

SEC is also prequalified to bid for the first round of independent bess projects in the kingdom, which is being produced by Saudi Power Procurement Company.    

Related reads: 


MEED’s April 2025 report on Saudi Arabia includes:

> UPSTREAM: Saudi oil and gas spending to surpass 2024 level
> DOWNSTREAM: Aramco’s recalibrated chemical goals reflect realism
> POWER: Saudi power sector enters busiest year
> WATER: Saudi water contracts set another annual record
> CONSTRUCTION: Reprioritisation underpins Saudi construction
> TRANSPORT: Riyadh pushes ahead with infrastructure development
> BANKING:
 Saudi banks work to keep pace with credit expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/13533430/main4249.jpg
Jennifer Aguinaldo
Related Articles
  • Saudi Arabia approves new procurement law

    17 August 2026

    Saudi Arabia’s Council of Ministers has approved a new Government Tenders and Procurement Law (GTPL), introducing changes to public procurement procedures and government contracting.

    The Ministry of Finance announced the approval on 5 August.

    The new law aims to strengthen governance and transparency, improve procurement planning and implementation, and promote fairness and equal opportunities in government contracting.

    The changes give government entities greater flexibility in procurement while introducing new provisions that could affect contractors and suppliers, including contract variations, outstanding payments and procurement procedures.

    Contract flexibility

    According to a Ministry of Finance summary of the key amendments, one of the main changes allows government entities to increase existing contract items by up to 20% of the contract value. Contractor approval is required for increases exceeding 10%, while the total increase from adding new items or increasing existing items cannot exceed 20% of the contract value.

    The amendments also introduce measures addressing outstanding payments to contractors. A government entity cannot make a new award when it has outstanding amounts owed to contractors for works or procurement and the required procedures have not been taken, after notification from the Ministry of Finance.

    Exceptions apply where non-payment relates to ministry procedures or where the government entity has taken the required action on a claim but does not have sufficient budget allocations.

    Single committee

    Under the new law, the committees responsible for opening and examining bids will be merged into a single committee.

    The maximum value for direct procurement will rise from SR100,000 ($26,700) to SR1m ($267,000) while government entities will be required to explain and document their use of direct procurement.

    Direct procurement will also be permitted in cases involving research, development and innovation and certain contracts with professional practitioners.

    The amendments reduce the minimum standstill period following a procurement award from five working days to three working days. Government entities will also be able to negotiate where the best bid exceeds the estimated cost plus the permitted contingency.

    Localisation

    The new framework includes provisions covering industrial localisation and knowledge transfer. The Ministry of Finance said it will issue rules for contracting for these purposes in cooperation with the Local Content and Government Procurement Authority.

    A new regulation will also cover research, development and innovation, including tendering and contracting provisions for these activities.

    Other changes involve contractors’ exposure to penalties. The maximum delay penalty on contracts, excluding supply contracts, will fall from 20% to 15% of contract value. The maximum penalty for non-performance in continuous-performance contracts will also fall from 20% to 15%.

    The value of purchases exempt from providing a final guarantee will rise from SR100,000 ($26,700) to SR300,000 ($80,000). Additional exemptions will apply to contracts with professional practitioners and emergency or urgent cases.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18805103/main.jpg
    Mark Dowdall
  • GCC reviews first phase of water interconnection study

    17 August 2026

    The GCC General Secretariat has completed the first phase of a study examining the feasibility of developing water interconnection projects between GCC member states.

    A two-day workshop reviewing the study’s findings concluded on 12 August at the headquarters of the GCC Interconnection Authority (GCCIA) in Dammam, Saudi Arabia.

    The GCC General Secretariat organised the workshop in cooperation with GCCIA, with representatives from relevant authorities and experts in water, infrastructure and water security taking part.

    Participants reviewed the first phase findings, including an assessment of existing water supply infrastructure and the actual water needs of GCC member states. They also discussed the technical requirements and data needed to complete the study.

    The study is intended to identify practical options and feasible solutions for developing a regional water interconnection network. This includes establishing an implementation roadmap.

    The initiative aims to improve the GCC states’ ability to respond to emergencies and crises and support continuity of water supplies.

    First meeting

    The workshop followed a virtual meeting on 22 July between the GCC General Secretariat and Saudi Arabia’s water authorities as part of the study.

    That meeting, which also involved consultancy Artelia, reviewed the study’s methodology and implementation stages. These include assessing existing water systems across GCC states, their resilience and emergency readiness, and developing technical options for bilateral water interconnection projects.

    In Saudi Arabia, the study is focused primarily on the Eastern Province and Riyadh. It is assessing water production and desalination facilities, transmission pipelines, strategic reservoirs, pumping stations and existing and planned projects.

    The study is also examining potential bilateral connections between Saudi Arabia and Bahrain, Kuwait and Qatar, as well as the possibility of a connection with the UAE.

    The 22 July meeting also discussed potential connection points and routes, water flow directions and the possibility of designing interconnection pipelines to operate in both directions.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18802726/main.jpg
    Mark Dowdall
  • Neom’s next phase is crucial to green hydrogen pipeline

    17 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The completion of construction at Neom Green Hydrogen comes at an important point for Saudi Arabia’s wider hydrogen ambitions.

    The project has already shown that a large green hydrogen scheme can secure financing by reaching financial close in 2023 with long-term offtake from Air Products.

    With the facility now moving into commissioning ahead of a targeted commercial operations date next year, Neom could soon give lenders and developers real evidence on the performance, costs and risks of a large-scale green hydrogen project.

    That could be important for projects still moving through development. Acwa’s Yanbu Green Hydrogen Hub, for example, is targeting commercial operations in 2030.

    The project has brought in Germany’s EnBW as a co-developer and minority investor and Japan’s Itochu as a co-developer, investor and offtaker. Acwa is targeting production of 2.5 million tonnes a year of green ammonia from the hub.

    Saudi Arabia is also putting more of the framework around the industry in place. In July, the government granted Acwa exclusive rights to export green hydrogen produced in the kingdom along with its derivatives, including green ammonia, methanol and fuels.

    However, partnerships and policy support alone will not remove the commercial questions facing projects. Yanbu still needs to progress through development and secure the financing needed to move into construction.

    Neom’s financing structure and 30-year offtake may be specific to the project, but its operating performance should give future developers and lenders a clearer reference point for assessing production, reliability and costs.

    While Neom will not make the next projects bankable on its own, if it stays on track and performs as expected, it could give lenders a stronger basis for assessing projects that follow. In the long-run, this could be one of its most important contributions.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18800285/main.jpg
    Mark Dowdall
  • Five bid for King Salman Bay construction work

    17 August 2026

     

    Five teams have submitted bids for the contract covering the marine infrastructure works at King Salman Bay on the Red Sea coast, north of Jeddah.

    MEED understands that the bids were submitted on 31 July.

    The bidders include:

    • Deme / Archirodon (Belgium/Netherlands)
    • ⁠Van Oord (Netherlands)
    • ⁠Abdulmohsen Altamimi / NMDC Group (local/UAE)
    • ⁠Urbacon / Negida Contracting  (Qatar/Egypt )
    • ⁠Modern Building Leaders / China Harbour (local/China)

    The scope includes dredging and earthworks, as well as quay wall and edge protection works spanning about 11 kilometres.

    King Salman Bay is expected to be a waterfront development that aims to reshape the city’s northern Red Sea frontage into a mixed-use destination, anchored by public-realm improvements and leisure-led development.

    Saudi gigaproject developer Red Sea Global (RSG) is developing the project.

    The latest development follows RSG’s award of an estimated SR100m ($27m) contract to construct a solid waste management centre at its Red Sea Project. The scope includes four buildings: a materials recycling facility, a transfer station, an administration building and a vehicle maintenance building.

    In October last year, MEED reported that RSG had secured a SR6.5bn ($1.7bn) credit facility to further develop Amaala, its luxury tourism destination on Saudi Arabia’s northwestern Red Sea coast.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18800910/main.jpg
    Yasir Iqbal
  • PDO allows more time for Al-Ghubar field project prices

    17 August 2026

     

    Petroleum Development Oman (PDO) has allowed contractors additional time to prepare commercial bids for a project to build a new facility to handle additional oil production from the Al-Ghubar field in the sultanate.

    The Al-Ghubar field is located in the Ghaba Salt Basin at Qarn Alam, within majority state-owned PDO’s Block 6 concession area.

    The Al-Ghubar gas-oil gravity drainage (GOGD) facility will be designed as a sour (hydrogen sulphide) facility and is expected to handle maximum oil production of 1,800 standard cubic metres a day (cm/d), a maximum total water flow rate of 10,421 standard cm/d, and maximum gas lift of 256,934 standard cm/d. Production from the planned Al-Ghubar GOGD facility will be exported to PDO’s main oil line.

    Following receipt of the technical bids for the project in July, PDO granted contractors additional time – until 16 August – to submit commercial bids for the project, MEED recently reported.

    The project operator has now extended the deadline for submitting commercial bids to 1 September, sources told MEED.

    PDO floated the tender for the Al-Ghubar GOGD facility project in March, setting an initial bid submission deadline of 4 May, MEED previously reported.

    PDO later extended the deadlines for submission of technical and commercial bids to 26 July and 7 August, respectively. Contractors submitted technical proposals by the revised deadline, according to sources.

    The following contractors, among others, are understood to be bidding for the project:

    • Archirodon (Greece)
    • Engineering for the Petroleum & Process Industries (Egypt) / Petrojet (Egypt)
    • Jereh (China)
    • Kent (UAE)
    • Larsen & Toubro Energy Hydrocarbon (India)

    The scope of work on the Al-Ghubar GOGD facility project covers the engineering, procurement and construction (EPC) of the following:

    • On-plot scope consists of:
      • Production separator  
      • Test separator  
      • Concentric wash tank
      • Wet oil pump
      • Water bath heater
      • Surge tank
      • Gas injection/gas lift compressor (centrifugal)
      • Utilities (Instrument Air compressors, chemical injection skids, drain system, vent system) 
      • Suction scrubber
      • Air coolers
      • Discharge scrubbers
      • Condensate flash drum
      • Atmospheric pressure knock-out drum 
      • Flare system
      • Gas heater
      • Water disposal pump
      • Oil shipping pump
      • New 132kV substation and plant substation (housing 6.6kV & 415-Volt switchboard)
      • New control room
         
    • Off-plot scope consists of:
      • Off-plot pipeline network (bulk header, test header, gathering infrastructure/ gathering line header, instrument air header, water disposal header)
      • Two remote manifold stations 
      • Tie-in connection to main oil line
      • Tie-in to gas network pipeline

    PDO previously intended to tender the Al-Ghubar GOGD project under its framework structure with selected EPC contractors, but eventually tendered it separately.

    PDO is the operator of the Block 6 hydrocarbons concession in Oman, which is the sultanate’s largest and most prolific concession. Situated onshore and covering an area of 75,119 square kilometres, Block 6 contains 202 oil fields and 43 gas fields, with PDO producing a total of approximately 680,000 barrels a day (b/d) of oil and condensates from those fields.

    The Omani government holds a 60% stake in PDO through Energy Development Oman (EDO). The other shareholders are UK-based Shell (34%), France’s TotalEnergies (4%) and Thailand’s state-owned PTTEP (2%).

    ALSO READ: PDO floats tender for major flare gas monetisation scheme
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18799485/main.jpg
    Indrajit Sen