Saudi Arabia to expand grid by 60% by 2030

21 March 2025

State utility Saudi Electricity Company (SEC) aims to expand its power transmission network to approximately 160,000 kilometres (km) by 2030, up 60% over its existing network of about 99,800km.

An increased subscriber base and higher electricity consumption, as well as the integration of renewables, underpin plans to expand the SEC network over the next five years.

"By 2030, SEC aims to expand its transmission network to encompass approximately 160,000km of transmission lines, [and] install nine new high-voltage, direct current lines between regions and neighbouring countries," SEC said in its 2024 earnings report.

"These targets are underscoring our commitment to building a robust and future-ready grid infrastructure."

MEED understands that SEC energised 26 new transmission substations, increasing the kingdom's transmission network to 1,260, a 2.1% increase over 2023.

These new substations increased the cumulative substation capacity to 497,902 megavolt-amperes, a 2% growth over the previous year.

Of the total, SEC installed and energised 10 substations and added 148.5km of transmission lines, integrating 6.6GW of renewables in 2024.

An additional 24 substations and 4,327km of transmission lines are under construction to integrate about 34.4GW of renewable energy capacity into the grid by 2027.

Generation

SEC said generation capacity connected to the grid reached 92.15GW in 2024, up 6.9% over 2023, when installed capacity stood at 86.23GW.

The firm said its directly owned capacity of the total now stands at 56.4GW, representing 61% of the kingdom's total capacity.

Electricity production at SEC's plants surged 7.5% to 236.4 terawatt-hours in 2024.

The firm said that 1,580MW of generation capacity was added or restored to SEC's power plant fleet in 2024, while the liquid-to-gas conversion of the Riyadh power plant 10 (PP10) and phase one is expected to be completed this year.

SEC is working with local contracting company Alfanar, in addition to US-based original equipment manufacturer GE Vernova, to convert the plant's fuel feedstock to natural gas, a lower carbon intensity fuel compared to the crude oil and distillate that currently power the plant.

According to the Energy Institute, Saudi Arabia's total electricity generation in 2023 reached 422.9 terawatt-hours (TWh). Oil accounted for 152.1TWh, or about 36% of the total, while natural gas accounted for 265TWh, or 63%, and renewables made up 5.8TWh or 1%. 

"Eight projects with a total capacity of 22.3GW are under transition by 2030," SEC said in its report.

It added: "SEC is currently developing 11 generation projects with an aggregate 23.4GW of capacity. These will be across directly owned capacity projects (10.476 GW), expansion and partnerships (5.324GW) and joint venture projects (7.610GW)."

Battery storage

SEC has been procuring battery energy storage system (bess) plants, with the aim of boosting the reliability and flexibility of the kingdom's electricity grid.

The first 500MW bess project in Bisha has been completed, while work is under way for 22 gigawatt-hours of bess capacity across five projects that are under development.

SEC is also prequalified to bid for the first round of independent bess projects in the kingdom, which is being produced by Saudi Power Procurement Company.    

Related reads: 


MEED’s April 2025 report on Saudi Arabia includes:

> UPSTREAM: Saudi oil and gas spending to surpass 2024 level
> DOWNSTREAM: Aramco’s recalibrated chemical goals reflect realism
> POWER: Saudi power sector enters busiest year
> WATER: Saudi water contracts set another annual record
> CONSTRUCTION: Reprioritisation underpins Saudi construction
> TRANSPORT: Riyadh pushes ahead with infrastructure development
> BANKING:
 Saudi banks work to keep pace with credit expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/13533430/main4249.jpg
Jennifer Aguinaldo
Related Articles
  • Contractor wins Riyadh airport sewage plant deal

    10 September 2026

     

    The local Safari Company has been selected to build a sewage treatment plant at the King Salman International airport (KSIA) development in Riyadh.

    The contract for the facility is yet to be formally signed with King Salman International Airport Development Company (KSIADC), a source close to the project told MEED.

    The facility will have a treatment capacity of 92,000 cubic metres a day and is estimated to be worth SR700m ($187m).

    In July, MEED reported that Safari was one of seven contractors awaiting a decision on a contract to build the sewage treatment plant.

    It is understood that bids were submitted in March, following the tender’s release earlier this year.

    The plant will treat wastewater generated by the airport and surrounding developments, including passenger terminals, runways, residential districts, commercial facilities and logistics areas.

    The bidders (all local) are:

    • Al-Rawaf Trading & Contracting
    • Almajal Alarabi
    • Nesma Water & Energy
    • Safari Company
    • Saudi Services for Electro-Mechanic Works
    • Washnah Contracting
    • Water & Environment Technologies (Wetico)

    The project scope includes the construction of the treatment plant, the installation of preliminary, secondary and tertiary treatment systems, sewage collection and conveyance pipelines, pumping stations, and electrical and control systems.

    US-headquartered Jacobs is acting as the main project consultant. Commercial operations for the plant are scheduled for 2029.

    The sewage treatment plant is one of several water infrastructure packages planned for the airport. KSIADC is also evaluating bids for a separate $30m engineering, procurement and construction (EPC) contract covering potable water and fire water tanks and an associated pumping station. The same seven companies submitted bids for that package.

    Earlier in July, MEED exclusively reported that a joint venture of Beijing-headquartered China Civil Engineering Construction Corporation and Dammam-based Mofarreh AlHarbi & Partners had won a deal to undertake the enabling and substructure works for Terminal 6 at KSIA.

    That same month, MEED exclusively reported that contract details were being finalised for the main construction contract for the expansion of Hail airport. It is understood that Safari Company was appointed as the contractor for this project.

    The terminal expansion works include the south expansion, which encompasses the construction of a new building covering 5,600 square metres. This building will connect to the existing terminal from the southern side.

    The expansion will increase the airport’s capacity to about 1.7 million passengers a year by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19539284/main.jpg
    Mark Dowdall
  • Azizi to announce $8bn Sharjah residential community

    10 September 2026

    Dubai-based real estate developer Azizi Developments is preparing to launch Azizi Florence, a AED30bn ($8bn) masterplanned community in Sharjah.

    Named Azizi Florence, the project will mark the developer’s first venture in the emirate of Sharjah.

    The community will include 1,130 villas, over 6,000 townhouses and 3,500 apartments.

    Planned as a fully integrated destination, Azizi Florence will combine residential, retail, hospitality, education, leisure, and wellness components, anchored by a 1.7 million-square-foot central park.

    The development will be organised into six residential clusters, each featuring its own park, clubhouse, community centre and landscaped gardens.

    Azizi Florence is another major addition to the developer’s UAE portfolio. 

    In April last year, Azizi announced plans to develop the Azizi Milan community in Dubai’s City of Arabia area.

    According to media reports, the project will be developed at an estimated cost of AED75bn ($20bn) and will offer over 81,200 residential units.

    The developer said the project will cover an area of about 40 million square feet, making it one of the largest mixed-use communities in the UAE.

    In 2023, Azizi launched the Azizi Venice project in the Dubai South area. The estimated AED30bn ($8.17bn) mixed-use development will offer more than 30,000 residential units, including 100 mid-rise apartment complexes and 400 villas, two five-star hotels and an opera house.

    The development will also include schools, a hospital, cycling and jogging tracks, a 3-kilometre-long swimmable lagoon, water features and landscaped parks.

    Dubai real estate developments dominate the UAE’s construction market, with schemes worth over $323bn in the execution or planning stages.

    This is in line with a forecast by GlobalData, which projects that the output of the UAE construction sector will grow by 4.2% in real terms in 2025, supported by developments in infrastructure, energy and utilities and residential construction projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19535526/main.jpg
    Yasir Iqbal
  • Saudi Arabia’s power award activity slows

    10 September 2026

     

    Saudi Arabia’s power market has seen a sharp fall in contract awards in 2026 following a major wave of renewable energy investment last year.

    According to regional project tracker MEED Projects, about $3.38bn of power sector contracts were awarded in the kingdom as of early September, compared with $27.5bn in 2025, $54.2bn in 2024 and $26.1bn in 2023.

    The relatively low level of contract awards this year has partly been influenced by a shift towards wider infrastructure such as battery energy storage systems (bess) and transmission projects, alongside delays in the procurement of renewable energy projects under the National Renewable Energy Programme (NREP) Round 7.

    In September, Saudi Power Procurement Company (SPPC) awarded four Group 1 storage service agreements representing more than SR4.35bn ($1.16bn) of investment. The projects will provide a combined 2,000MW of capacity and 8,000MWh of storage.

    Three bess projects, Al-Muwyah, Haden and Al-Kahafa, were awarded to a consortium of Saudi Energy, Acwa and Al-Sharif Contracting & Commercial Development Company. Another consortium of France’s Engie and Haji Abdullah Alireza & Co won the contract for the remaining Al-Khushaybi bess project.

    Transmission awards

    The battery storage projects are part of a broader shift towards the infrastructure needed to support Saudi Arabia’s expanding power system, with transmission accounting for most of the contracts awarded this year, reaching $3.35bn in new awards.

    The largest is the estimated $500m contract awarded to Alfanar Projects in March for the 500kV overhead transmission line linking Saudi Arabia’s Eastern and Central operating areas. The 508-kilometre project will have a transmission capacity of 3,000MW.

    Saudi Energy, formerly Saudi Electricity Company, is implementing a $58.7bn grid investment programme through 2030, including 130 high-voltage substations, about 12,900km of overhead transmission lines and 1,100km of underground cables.

    Saudi Energy is the largest owner by value so far this year, accounting for about $1.9bn of contract awards, while SPPC has awarded more than $1.1bn in new contracts.

    The focus on storage and transmission follows strong growth in renewable generation investment in 2025. Wind power contract awards reached $4.4bn, while 11 major solar contracts were also awarded.

    In May 2025, developers signed $8.3bn of power purchase agreements with SPPC for five solar plants and two wind farms with a combined capacity of 15,000MW, somewhat inflating last year’s figures. The projects, backed by the Public Investment Fund, reached financial close in November.

    Renewables projects

    The next major phase of renewable procurement is now moving through the tender process. The seventh round of NREP, tendered in January, will add 5,300MW through four solar and two wind projects.

    Based on the procurement timeline for the Round 6 projects, which were tendered and awarded in 2026, it was reasonable to expect Round 7 to follow a similar schedule.

    However, according to one developer, rising supply costs have been a factor in recent deadline extensions for these projects, with those involved “waiting till these come down”.

    With the latest bid submission deadlines set for September, the timing of the procurement process means contracts from NREP Round 7 may now fall into 2027 rather than materially lifting this year’s total.

    The solar projects comprise the 1,400MW Tabarjal 2, 600MW Mawqqaq, 600MW Tathleeth and 500MW South Al-Ula independent power projects (IPPs). The round also includes the 1,300MW Bilgah and 900MW Shagra wind IPPs.

    This helps explain why Saudi Arabia’s power sector contracting could remain relatively subdued in 2026 despite a substantial volume of projects progressing through procurement.

    Project pipeline

    According to MEED Projects, about $5.1bn of power projects are currently under bid evaluation and a further $7.3bn are at the main contract tender stage.

    Solar projects make up the largest share, at about $5.1bn, or 41% of the total. There continues to be relatively strong diversification, with cable and overhead-line projects accounting for about $3bn, followed by wind at $2.2bn, oil and gas-fired power at $1.1bn and substations at about $1bn.

    Renewable energy remains a particularly significant part of the development programme. Saudi Arabia raised its renewable energy target to 130GW by 2030 in 2023 and needs to add roughly 20GW of capacity a year to meet it.

    Large-scale storage is also expected to continue expanding. The latest SPPC projects build on five bess facilities awarded by Saudi Energy through National Grid Saudi Arabia to Alfanar in 2025. The facilities have a combined capacity of up to 2,500MW, equivalent to about 10,000MWh.

    SPPC has also issued the request for proposals for the second phase of its independent bess programme in Saudi Arabia. The Group 2 programme comprises six independent storage provider projects with a total capacity of 3GW, equivalent to 12,000MWh based on a four-hour storage duration. Developers are due to submit bids in October. 

    The timing means the Group 2 projects could contribute to contracting activity in 2027, alongside this next batch of renewable projects under NREP Round 7.

    Nuclear power could provide another potential source of activity over the next 12 months. The US and Saudi Arabia signed a civil nuclear cooperation agreement in July, providing the legal foundation for a long-term, multibillion-dollar nuclear partnership.

    While the agreement is unlikely to translate immediately into major contract values, further progress on Saudi Arabia’s nuclear programme could add another area of activity in the sector as the kingdom moves into 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19535830/main.gif
    Mark Dowdall
  • Chinese contractor wins NHC Al-Fursan Riyadh deal

    10 September 2026

     

    Register for MEED’s 14-day trial access 

    Beijing-headquartered China Airport Construction Group (CACC) has won a contract for the main construction works on the Al-Ruba project, located within the Al-Fursan master development in Riyadh.

    The Al-Fursan project developer, National Housing Company (NHC), awarded the contract.

    The scope covers the construction of 48 eight-storey buildings, comprising 2,556 residential apartments.

    CACC is already working with NHC to deliver the Rehab Al-Sadan residential project at the Al-Sadan development in Jeddah.

    It comprises the delivery of about 1,400 residential units across several buildings.

    In 2023, NHC and Saudi Arabia’s Housing Ministry signed investment agreements totalling more than SR24bn ($6.4bn) to launch the Al-Fursan residential project.

    Al‑Fursan is described as the largest scheme in terms of area and number of housing units that NHC is implementing in partnership with other real estate developers. 

    For the district’s first phase, 18 real estate development agreements were signed with companies including Retal Urban Development Company and Sumou Real Estate Company.

    NHC also signed four consultancy contracts to manage projects and supervise implementation of phase one and the deployment of comprehensive infrastructure works.

    Other deals involved the development of facilities, including commercial and recreational areas, hospitals, health and sports centres, mosques and schools.

    MEED reported in 2020 that Riyadh planned to oversee the development of more than 1 million homes by 2025 to meet growing demand in the kingdom.

    By 2030, the Saudi capital aims to more than double its population, from 7-8 million to 15-20 million, and become one of the 10 wealthiest cities in the world.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19533391/main.jpg
    Yasir Iqbal
  • Seven tenders Dammam water park and hotel project

    10 September 2026

     

    Saudi Entertainment Ventures (Seven), a wholly owned subsidiary of the Public Investment Fund, has tendered a contract for the main construction package of its Dammam Water Park and Hotel project in the Al-Hamra district.

    The bid submission deadline is 14 October.

    The waterfront development sits on a 324,300-square-metre (sq m) plot.

    In July, MEED exclusively reported that Seven was preparing to shortlist general contractors for the project.

    Seven is seeking firms capable of delivering a lump-sum, turnkey solution for both the water park and a 321-key lifestyle hotel. Construction is expected to take 24 months from contract award.

    The water park is designed around five themed zones and will feature what is billed as the world’s first double-tornado/triple-wave waterslide.

    The park will include 21 major rides and attractions, 21 food and beverage outlets, 66 cabanas, parking for 1,100 vehicles and a daily peak capacity of 4,500 guests.

    Slide procurement has already been completed directly by Seven. The selected contractor will be responsible for locally sourcing slide towers, integrating them with rockwork and secondary steel, and installing the units.

    Detailed design and issued-for-construction packages are complete.

    Marine works, piling, dewatering and site utilities are being progressed separately by the existing early works contractor.

    The hotel component covers roughly 31,700 sq m of gross floor area and will offer 321 guest rooms, four F&B outlets, spa and wellness facilities, a family pool, and meeting, incentive, conference and exhibition space.

    The new contractor’s scope includes superstructure concrete works, façade and roof works, mechanical, electrical and plumbing, interior fit-out and landscaping.

    Seven will consider only contractors with demonstrated experience delivering water parks with complex aquatics, theming and rockwork – either directly or through clearly defined subcontractor partnerships – along with a track record in high-end turnkey hotel fit-outs.

    Construction of Seven’s Dammam entertainment complex is under way. In October 2023, Saudi Binladin Group won contracts worth around SR5bn ($1.3bn) from Seven to build two entertainment destinations in the Dammam and Al-Khobar areas of the kingdom’s Eastern Province.

    The Al-Khobar entertainment complex is being built on reclaimed waterfront land. The complex spans around 300,000 sq m and is also known as ‘The Waves’.

    The Dammam entertainment complex spans 360,000 sq m and is being built on reclaimed land on the Dammam waterfront.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19530456/main.jpg
    Yasir Iqbal