Saudi Arabia to expand grid by 60% by 2030

21 March 2025

State utility Saudi Electricity Company (SEC) aims to expand its power transmission network to approximately 160,000 kilometres (km) by 2030, up 60% over its existing network of about 99,800km.

An increased subscriber base and higher electricity consumption, as well as the integration of renewables, underpin plans to expand the SEC network over the next five years.

"By 2030, SEC aims to expand its transmission network to encompass approximately 160,000km of transmission lines, [and] install nine new high-voltage, direct current lines between regions and neighbouring countries," SEC said in its 2024 earnings report.

"These targets are underscoring our commitment to building a robust and future-ready grid infrastructure."

MEED understands that SEC energised 26 new transmission substations, increasing the kingdom's transmission network to 1,260, a 2.1% increase over 2023.

These new substations increased the cumulative substation capacity to 497,902 megavolt-amperes, a 2% growth over the previous year.

Of the total, SEC installed and energised 10 substations and added 148.5km of transmission lines, integrating 6.6GW of renewables in 2024.

An additional 24 substations and 4,327km of transmission lines are under construction to integrate about 34.4GW of renewable energy capacity into the grid by 2027.

Generation

SEC said generation capacity connected to the grid reached 92.15GW in 2024, up 6.9% over 2023, when installed capacity stood at 86.23GW.

The firm said its directly owned capacity of the total now stands at 56.4GW, representing 61% of the kingdom's total capacity.

Electricity production at SEC's plants surged 7.5% to 236.4 terawatt-hours in 2024.

The firm said that 1,580MW of generation capacity was added or restored to SEC's power plant fleet in 2024, while the liquid-to-gas conversion of the Riyadh power plant 10 (PP10) and phase one is expected to be completed this year.

SEC is working with local contracting company Alfanar, in addition to US-based original equipment manufacturer GE Vernova, to convert the plant's fuel feedstock to natural gas, a lower carbon intensity fuel compared to the crude oil and distillate that currently power the plant.

According to the Energy Institute, Saudi Arabia's total electricity generation in 2023 reached 422.9 terawatt-hours (TWh). Oil accounted for 152.1TWh, or about 36% of the total, while natural gas accounted for 265TWh, or 63%, and renewables made up 5.8TWh or 1%. 

"Eight projects with a total capacity of 22.3GW are under transition by 2030," SEC said in its report.

It added: "SEC is currently developing 11 generation projects with an aggregate 23.4GW of capacity. These will be across directly owned capacity projects (10.476 GW), expansion and partnerships (5.324GW) and joint venture projects (7.610GW)."

Battery storage

SEC has been procuring battery energy storage system (bess) plants, with the aim of boosting the reliability and flexibility of the kingdom's electricity grid.

The first 500MW bess project in Bisha has been completed, while work is under way for 22 gigawatt-hours of bess capacity across five projects that are under development.

SEC is also prequalified to bid for the first round of independent bess projects in the kingdom, which is being produced by Saudi Power Procurement Company.    

Related reads: 


MEED’s April 2025 report on Saudi Arabia includes:

> UPSTREAM: Saudi oil and gas spending to surpass 2024 level
> DOWNSTREAM: Aramco’s recalibrated chemical goals reflect realism
> POWER: Saudi power sector enters busiest year
> WATER: Saudi water contracts set another annual record
> CONSTRUCTION: Reprioritisation underpins Saudi construction
> TRANSPORT: Riyadh pushes ahead with infrastructure development
> BANKING:
 Saudi banks work to keep pace with credit expansion

https://image.digitalinsightresearch.in/uploads/NewsArticle/13533430/main4249.jpg
Jennifer Aguinaldo
Related Articles
  • March 2025: Data drives regional projects

    31 March 2025

    Click here to download the PDF

    Includes: Commodity tracker | Construction risk | Brent Spot Price | Construction output


    READ THE MARCH MEED BUSINESS REVIEW – click here to view PDF

    Chinese contractors win record market share; Cairo grapples with political and fiscal challenges; Stronger upstream project spending beckons in 2025

    Distributed to senior decision-makers in the region and around the world, the March 2025 edition of MEED Business Review includes:

    > GULF PROJECTS INDEX: Gulf hits six-month growth streak
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/13578533/main.gif
    MEED Editorial
  • Two bid for Madinat Zayed IPP contract

    28 March 2025

     

    Abu Dhabi-based utility and offtaker Emirates Water & Electricity Company (Ewec) has received bids for a contract to develop and operate the Madinat Zayed open-cycle gas turbine (OCGT) power generation plant project in the emirate.

    According to industry sources, two teams led separately by France’s Engie and Saudi Arabia’s Aljomaih Energy & Water submitted bids for the Madinat Zayed OCGT independent power producer (IPP) project on 28 March.

    Aljomaih is understood to have partnered with the local Etihad Water & Electricity (Etihad WE) for its bid.

    The Madinat Zayed IPP is expected to begin commercial operations in Q3 2027. It will provide up to 1,500MW of backup generation, which can be operational “at very short notice”. 

    “Gas-fired plants like Madinat Zayed are key to ensuring a reliable energy supply while the country transitions to a decarbonised water and electricity system,” Ewec said when it issued the tender for the project in July last year.

    “[This type of plant] will be particularly important for supporting the growth of solar power, providing crucial flexibility during peak power demand periods and acting as a bridge to a future powered exclusively by clean and renewable sources.”

    Capacity buildout

    Abu Dhabi’s current electricity generation installed capacity sits at about 22GW, with gas-fired plants accounting for 68.7% of the total, and renewable and nuclear power contributing 12% and 19%, respectively.

    Construction work is under way for a 1,500MW solar photovoltaic (PV) power plant and a 2,457MW combined-cycle gas turbine (CCGT) plant.

    Two solar IPPs with a combined capacity of 3,000MW are under bid evaluation or main contract bid, while the tendering proceedings are under way for the Taweelah C CCGT IPP, in addition to the Madinat Zayed OCGT.

    The procurement processes are also under way for the 140MW Al-Sila wind IPP, the emirate’s first independent battery energy storage system plant, and another major CCGT, the 3.3GW Al-Nouf 1 project.

    In January, Ewec and Abu Dhabi Future Energy Company (Masdar) signed a power-purchase agreement for a 5,200MW solar PV plant with a 19 gigawatt-hour battery energy storage system, which is expected to provide round-the-clock solar power.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13579141/main.gif
    Jennifer Aguinaldo
  • Masdar completes Valencia solar deal

    28 March 2025

    Abu Dhabi Future Energy Company (Masdar), through its Spanish subsidiary Satea, has closed an investment agreement for the construction and commissioning of solar photovoltaic installations with a total capacity of 234MW in Valencia, Spain.

    The project has the potential to add a battery energy storage system with a capacity of 259MW, Masdar announced on 27 March.

    A joint venture of Genia Solar Energy and Solar Ventures initially promoted the project.

    The plant will be located in the municipalities of Ayora, Jarafuel and Zarra. 

    It is expected to be operational in the first half of 2027.

    Watson Farley & Williams, G-advisory, EY and Finergreen advised Solar Ventures and Genia Solar Energy, while Broseta, Solida and Perez-Llorca advised Saeta Yield on the transaction.

    In July last year, Masdar announced it had reached an agreement with Spanish utility company Endesa to become a partner for 2.5GW of renewable energy assets in Spain.

    Masdar said at the time that it planned to invest €817m ($887m) to acquire a 49.99% stake, with an enterprise value of €1.7bn, representing one of Spain’s biggest renewable energy deals.

    The portfolio that Masdar planned to acquire consisted of 48 operational solar plants with an aggregated capacity of 2GW.

    Masdar and Endesa, a subsidiary of Italian energy giant Enel, said at the time that they aim to add 500MW of battery energy storage systems to the projects.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13578644/main.jpg
    Jennifer Aguinaldo
  • Miahona wins $267m Modon wastewater plant deal

    28 March 2025

    Saudi Authority for Industrial Cities and Technology Zones (Modon) has awarded the local Miahona Company a contract for the construction and operation of an industrial wastewater treatment plant in Jeddah.

    The contract is valued at SR1bn ($266.7m), Miahona said in a bourse filing on 26 March.

    This project scope includes the rehabilitation, development, construction, operation and maintenance of wastewater treatment systems.

    The wastewater treatment plant will be located in Jeddah 1st Industrial City.

    According to Miahona, the project scope includes capital investment, land utilisation, service provision and revenue generation through treated water sales, within a 25-year rehabilitation, operation and transfer (ROT) framework.

    Last year, Miahona Company and Belgium’s Besix won the contract to develop and operate the Al-Haer independent sewage treatment plant (ISTP) project in Riyadh, Saudi Arabia.

    Another local firm, Power & Water Utility Company for Jubail & Yanbu (Marafiq), subsequently joined the developer team.

    The Al-Haer ISTP project involves the development of a water treatment plant with a capacity of 200,000 cubic metres a day (cm/d).

    It also includes the development of a treated sewage effluent (TSE) reuse system that covers a 32-kilometre pipeline with a capacity of 400,000 cm/d, a pumping station and TSE reservoir tanks with a capacity of 200,000 cubic metres.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/13578624/main.jpg
    Jennifer Aguinaldo