Saudi Arabia to expand grid by 60% by 2030
21 March 2025
State utility Saudi Electricity Company (SEC) aims to expand its power transmission network to approximately 160,000 kilometres (km) by 2030, up 60% over its existing network of about 99,800km.
An increased subscriber base and higher electricity consumption, as well as the integration of renewables, underpin plans to expand the SEC network over the next five years.
"By 2030, SEC aims to expand its transmission network to encompass approximately 160,000km of transmission lines, [and] install nine new high-voltage, direct current lines between regions and neighbouring countries," SEC said in its 2024 earnings report.
"These targets are underscoring our commitment to building a robust and future-ready grid infrastructure."
MEED understands that SEC energised 26 new transmission substations, increasing the kingdom's transmission network to 1,260, a 2.1% increase over 2023.
These new substations increased the cumulative substation capacity to 497,902 megavolt-amperes, a 2% growth over the previous year.
Of the total, SEC installed and energised 10 substations and added 148.5km of transmission lines, integrating 6.6GW of renewables in 2024.
An additional 24 substations and 4,327km of transmission lines are under construction to integrate about 34.4GW of renewable energy capacity into the grid by 2027.
Generation
SEC said generation capacity connected to the grid reached 92.15GW in 2024, up 6.9% over 2023, when installed capacity stood at 86.23GW.
The firm said its directly owned capacity of the total now stands at 56.4GW, representing 61% of the kingdom's total capacity.
Electricity production at SEC's plants surged 7.5% to 236.4 terawatt-hours in 2024.
The firm said that 1,580MW of generation capacity was added or restored to SEC's power plant fleet in 2024, while the liquid-to-gas conversion of the Riyadh power plant 10 (PP10) and phase one is expected to be completed this year.
SEC is working with local contracting company Alfanar, in addition to US-based original equipment manufacturer GE Vernova, to convert the plant's fuel feedstock to natural gas, a lower carbon intensity fuel compared to the crude oil and distillate that currently power the plant.
According to the Energy Institute, Saudi Arabia's total electricity generation in 2023 reached 422.9 terawatt-hours (TWh). Oil accounted for 152.1TWh, or about 36% of the total, while natural gas accounted for 265TWh, or 63%, and renewables made up 5.8TWh or 1%.
"Eight projects with a total capacity of 22.3GW are under transition by 2030," SEC said in its report.
It added: "SEC is currently developing 11 generation projects with an aggregate 23.4GW of capacity. These will be across directly owned capacity projects (10.476 GW), expansion and partnerships (5.324GW) and joint venture projects (7.610GW)."
Battery storage
SEC has been procuring battery energy storage system (bess) plants, with the aim of boosting the reliability and flexibility of the kingdom's electricity grid.
The first 500MW bess project in Bisha has been completed, while work is under way for 22 gigawatt-hours of bess capacity across five projects that are under development.
SEC is also prequalified to bid for the first round of independent bess projects in the kingdom, which is being produced by Saudi Power Procurement Company.
Related reads:
- Saudi power projects hit record high
- Riyadh joins global battery storage race
- Saudi Electricity Company profit falls by 33%
MEED’s April 2025 report on Saudi Arabia includes:
> UPSTREAM: Saudi oil and gas spending to surpass 2024 level
> DOWNSTREAM: Aramco’s recalibrated chemical goals reflect realism
> POWER: Saudi power sector enters busiest year
> WATER: Saudi water contracts set another annual record
> CONSTRUCTION: Reprioritisation underpins Saudi construction
> TRANSPORT: Riyadh pushes ahead with infrastructure development
> BANKING: Saudi banks work to keep pace with credit expansion
Exclusive from Meed
-
-
-
Houthi truce collapse widens Gulf risk map15 July 2026
-
Saudi Downtown awards Al-Khobar infrastructure deal15 July 2026
-
Saudi Arabia opens third round of gas-fired IPPs15 July 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Egypt intensifies efforts to create petroleum stockpile16 July 2026
Egypt is intensifying its efforts to secure and maintain a sufficient strategic stockpile of petroleum products, according to a statement from the country’s cabinet and its Ministry of Petroleum & Mineral Resources.
The Egyptian government is closely monitoring regional developments and their potential repercussions on the energy sector, according to the statement.
Egyptian Prime Minister Mostafa Madbouly said that the government is implementing flexible plans and looking at alternative scenarios so that it can respond quickly to emergencies while ensuring the uninterrupted supply of fuel to citizens and key industrial sectors.
Egypt is intensifying its efforts to build up strategic stockpiles amid heightened uncertainty about future global oil and gas supplies.
Since the US and Israel attacked Iran on 28 February, there has been significant disruption to shipping through the Strait of Hormuz, which is a key transit route for oil and gas exports from the Middle East.
On top of this, the regional war has involved multiple direct attacks on refineries in the GCC, increasing uncertainty about the future availability of refined products.
Aside from Motafa Madbouly, the meeting was also attended by Hassan Abdullah, who is governor of the Central Bank, Minister of Finance Ahmed Koguk and Minister of Petroleum and Minerals Karim Badawi.
During the meeting, Badawi gave a presentation on the available quantities of different petroleum products and explained the details of the procedures currently being implemented to increase the strategic stock of petroleum products.
A review of the coordination framework and joint work between the Ministry of Finance and the Central Bank also took place during the meeting.
This was in order to ensure the management of financial tools needed to strengthen the country’s strategic inventory, according to the statement.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17685719/main.jpg -
PIF developer tenders 365-metre Mecca residential tower16 July 2026

Rua Al-Haram Al-Makki has tendered the main construction package for the Ajyad residential tower, a 365-metre high-rise development in Mecca’s central area, close to the grand mosque.
The bid submission deadline is 30 September.
Rua Al-Haram Al-Makki Company was established in October 2017 and is a wholly owned subsidiary of Saudi Arabia’s Public Investment Fund.
The project team includes US-based Marriott International as residential operator, Hanmi Global Saudi as project management consultant, Saudi Diyar Consultants as construction supervision consultant, and PLP Architecture as lead design consultant and construction-stage design guardian.
The tower rises 84 floors with four basement levels. It comprises a total of 212 units, including 82 three-bedroom apartments, 85 four-bedroom units, 29 penthouses and 16 duplex villas.
The scheme has a gross floor area of 209,231 square metres (sq m) and a built-up area of 242,976 sq m.
The site is currently being cleared by a demolition contractor, with the existing mat foundation and retaining walls to be handed over to the main contractor, who will build the new superstructure on the retained raft.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17683664/main.jpg -
Houthi truce collapse widens Gulf risk map15 July 2026
Register for MEED’s 14-day trial access
The Houthis’ declaration ending the de facto truce with Saudi Arabia has significantly increased the likelihood of renewed attacks on Red Sea shipping and regional infrastructure, broadening the threat environment beyond the Strait of Hormuz.
S&P Global Market Intelligence says the 13 July exchange is best understood as a potential widening of the renewed US-Iran escalation cycle into the Yemen and Red Sea theatres.
Houthi claims that Saudi Arabia was responsible for a strike on Sanaa International airport have not been independently confirmed. Saudi Arabia had not formally commented at the time the analysis was written.
The Yemeni militant group is likely to use the incident as a trigger that allows it to justify renewed military action while aligning with Iran’s wider effort to impose costs on US and Gulf interests, according to the research firm.
The decision to declare an end to de-escalation with Riyadh materially increases the likelihood of further missile and unmanned aerial vehicle (UAV) activity against infrastructure near the Yemen-Saudi border, as well as renewed pressure on maritime routes in the Red Sea and Bab Al-Mandab.
Aviation exposure
The resumption of direct hostilities broadens the range of vessels and ports likely to be subject to Houthi targeting, and presents severe risk to airports and stationary aircraft, S&P Global Market Intelligence says.
While the Houthis would probably not intentionally down civilian aircraft, there is a significant risk to aircraft in flight, particularly at lower altitudes close to airports, due to incoming UAVs and missiles and interceptor activity.
The broader risk is to regional logistics rather than any single target set, the analysis says.
If escalation around the Strait of Hormuz coincides with renewed Houthi activity in the southern Red Sea, Bab Al-Mandab and the Gulf of Aden, commercial operators face a more complex dual-chokepoint environment, with the added likelihood that the Houthis will seek to target Hormuz bypass infrastructure across the Gulf.
That would raise the likelihood of shipping delays, higher insurance costs, more conservative routing decisions and greater interest in alternative corridors or bypass routes.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17680608/main.jpg -
Saudi Downtown awards Al-Khobar infrastructure deal15 July 2026
Register for MEED’s 14-day trial access
Saudi Downtown Company, a wholly owned subsidiary of the Public Investment Fund (PIF), has awarded a contract for infrastructure works in downtown Al-Khobar.
The contract was awarded to local contractor Ansab General Contracting Company.
The scope of work includes the design and development of overall infrastructure, road networks and street lighting for the downtown Al-Khobar project.
Saudi Downtown Company was officially launched in 2022 by Saudi Crown Prince Mohammed Bin Salman Bin Abdulaziz Al-Saud, who is also chairman of PIF.
At the time, the company announced plans to develop downtown areas in 12 cities across the kingdom: Medina, Al-Khobar, Al-Ahsa, Buraidah, Najran, Jizan, Hail, Al-Baha, Arar, Taif, Dumat Al-Jandal and Tabuk.
SDC’s mandate is to develop more than 10 million square metres of land across its projects
https://image.digitalinsightresearch.in/uploads/NewsArticle/17677176/main.jpg -
Saudi Arabia opens third round of gas-fired IPPs15 July 2026
Register for MEED’s 14-day trial access
Principal buyer Saudi Power Procurement Company (SPPC) has opened the qualification process for the third round of conventional independent power projects (IPPs) using combined-cycle gas turbine (CCGT) technology.
The round is being tendered under the supervision of the Ministry of Energy. Each plant will be built with provision for carbon capture unit readiness, allowing the technology to be deployed at a later stage.
Each project will be developed on a build-own-operate (BOO) basis, with the winning consortium taking 100% equity in a special purpose vehicle (SPV) set up to develop and operate the plant.
Each SPV will sign a power purchase agreement with SPPC, which is licensed by the Saudi Electricity Regulatory Authority (SERA) to prepare preliminary studies, tender and award IPPs, and purchase electricity from energy projects in the kingdom.
The programme forms part of Saudi Arabia’s Circular Carbon Economy approach, which underpins the energy sector element of the Vision 2030 strategy. Riyadh is displacing liquid fuels with natural gas in power generation to cut emissions intensity, while designing new plants so that carbon capture equipment can be retrofitted in support of national emissions targets.
In April, Acwa and Saudi Energy (formerly Saudi Electricity Company) signed a 31-year power purchase agreement (PPA) with SPPC for the Rabigh 2 IPP expansion.
The project involves the development of a CCGT plant in the Mecca region. It will have a total capacity of 2,313.5MW.
The contract is valued at SR11.5bn ($3.07bn), the companies said in separate stock exchange filings.
https://image.digitalinsightresearch.in/uploads/NewsArticle/17676286/main.jpg