Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Hydrom targets hyperscalers in round four

    19 November 2026

     

    Oman’s green hydrogen company Hydrom is turning to domestic demand to support the sector as export markets slow, says managing director Abdulaziz Al-Shidhani.

    Speaking to MEED after Hydrom awarded two projects under its third auction round and launched a fourth round linked to data centres at UN climate change conference Cop31 in Antalya, Al-Shidhani says interest in the third round had been satisfactory but below earlier levels. 

    “There was a good interest, satisfactory to the auction itself, but it was not as big as it was in round one specifically,” he says. “[That is] reflecting the overall market sentiment when it comes to green hydrogen.”

    Hydrom does not disclose the number of auction bids it receives.

    Domestic demand

    According to Al-Shidhani, regulatory slowdowns in Europe and slower progress in markets such as South Korea and Japan prompted Hydrom to look for buyers at home.

    “We decided last year to start exploring each and every avenue domestically to support decarbonising our industries and introducing green solutions for expanding the industrial base within Oman itself,” he says.

    Steel, methanol, mobility, hydrogen-to-power and data centres are among the applications that are under review. A natural gas supply agreement was recently signed for a green direct reduced iron (DRI) plant, which carries a mandate to replace natural gas with green hydrogen in the early 2030s. Hydrom is helping first-round developers in Duqm reach a commercial agreement with the DRI investor.

    Data centres

    The fourth round, the Green-Powered Data Centre Hydrogen Auction, will be held in Dhofar Governorate. The city of Salalah was chosen for its connectivity, cooler climate and seawater cooling.

    Al-Shidhani says the national grid is not yet in a position to supply hyperscalers requiring 100MW or more. The Energy & Minerals Ministry and the Transport, Communications & Information Technology Ministry mandated Hydrom to design a captive power solution.

    “Our work yielded that the best techno-commercial proposition is a blend of renewable electrons supported by batteries and supported by up to 20% firming power through hydrogen gensets,” he says.

    The auction is designed for integrated consortiums covering power, hydrogen and data centre hubs. Hydrom will also offer matchmaking for investors that want a partner to supply the energy.

    Registration for expressions of interest is open until February 2027. Al-Shidhani says a market sounding exercise had given “a very positive signal”. Hydrom plans to issue the request for qualification by the end of the first quarter of 2027, with requests for proposals expected around mid-year.

    Round three

    The awards went to a consortium of Petrogas E&P and Italy’s Bio3Energy, which plans to produce about 625,000 tonnes a year (t/y) of green ammonium nitrate, and a consortium of PLN Indonesia Power Renewables, Alawi Enterprises and HBA Offshore International, which plans to produce about 400,000 t/y of green ammonia. Combined green hydrogen output is expected to reach about 121,000 t/y by 2032.

    The block offered covers 300 square kilometres and could accommodate up to three projects. One winner has an option on a further 100 square kilometres, which would use the full block.

    Al-Shidhani says the land usufruct agreements will be registered with Oman’s Housing Ministry within two to three weeks. Developers then have three and a half years for development work, with a final investment decision expected by the end of year three and financial close six months later. Construction is allotted three and a half years, followed by 40 years of operations.

    He says the 2032 production date does not represent a delay to Oman’s 2030 target. 

    “It is a rolling process,” he says. “The 2030 [projects] were signed in 2023 and 2024. It is a moving target.”

    One of the new projects has opted for solar power only at the outset. Hydrom does not specify generation or electrolyser technology. Project finance remains the most common funding route, although Al-Shidhani says export credit agencies could also play a role.

    This is a demonstration that Oman is able to produce [some of] the lowest-cost hydrogen

    First production

    The first phase of India-based Acme Group’s project in Duqm, which will produce 100,000 t/y of green ammonia, is expected to start production in Q2 2027. Al-Shidhani, who visited the site in October, says major components were almost complete.

    “This is a demonstration that Oman is able to produce [some of] the lowest-cost hydrogen and deliver it competitively to markets, and we are not talking about small quantities,” he says.

    He expects the first export cargo to convince sceptical investors that Oman can produce hydrogen for less than $3 a kilogram. Other first- and second-round developers are still negotiating offtake before moving to front-end engineering and design.

    Further rounds

    Al-Shidhani says the awarded projects use approximately 4% of the land available to Hydrom, and that further auctions are certain. Oman’s strategy targets 8.5 million t/y of green hydrogen by 2050.

    Hydrom paused for almost a year after the second auction round, and the timing of future rounds will depend on the market.

    “It is all about selecting the right time to go to the market,” he says. “In terms of whether there would be round five or round six, the answer is definitely there would be.”  

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21573009/main.gif
    Colin Foreman
  • Contractors submit best offers for Oxagon Highway 55

    19 November 2026

     

    Contractors have submitted their best and final offers for a design-and-build contract to upgrade Highway 55 in Saudi Arabia’s Oxagon region.

    The first phase of the project includes the construction of 14 kilometres of road, with two lanes in each direction, as well as one bridge and three interchanges.

    The project is expected to take 22 months to complete.

    Contractors initially submitted bids on 28 September, as MEED exclusively reported.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August last year that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21556022/main.jpg
    Yasir Iqbal
  • Construction starts on Damascus hotel and mall

    19 November 2026

    Construction has started on the Movenpick Hotel and Arab Mall development in the Kafr Sousa district of Damascus.

    Rotana Star Holding and Sankari Holding are backing the project, which Syria’s Ministry of Tourism is developing under its patronage.

    The project marks Accor’s entry into the Syrian market. The France-based hotel group signed an agreement earlier this year to manage the project’s Movenpick Hotel component.

    The integrated development will cover more than 90,000 square metres (sq m) and combine hotel, retail, entertainment and supporting facilities.

    The Movenpick Hotel will occupy more than 25,000 sq m and include 300 accommodation units. Facilities will include event and celebration halls, restaurants with panoramic views, and health and fitness amenities.

    Arab Mall will cover more than 65,000 sq m across seven levels. It will include retail units, entertainment facilities and service areas.

    The developers expect Arab Mall to open in the first quarter of 2028, followed by the hotel in the first quarter of 2029.

    Accor acquired the Swiss-founded Movenpick brand in 2018. Under the management agreement, Accor will operate the hotel and provide access to its global reservation, distribution and marketing platforms.

    The development is expected to create direct and indirect employment across construction, engineering, hospitality, retail and services.

    The project is being advanced as Syria seeks to expand its tourism and hospitality capacity.

    Syria’s Ministry of Tourism has reported that the country received 3.52 million visitors in the first half of 2026, 111% more than in the same period of 2025.

    The ministry said foreign tourist arrivals increased by 448%, while Arab visitor numbers rose by 107%.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21555695/main.jpeg
    Yasir Iqbal
  • Kuwait discusses retender of $7.7bn of oil projects

    19 November 2026

     

    State-owned upstream operator Kuwait Oil Company (KOC) is discussing the retendering of upstream projects worth an estimated $7.7bn, according to industry sources.

    The tender processes for all four contracts were cancelled earlier this year after the lowest bids exceeded the projects’ approved budgets.

    The projects are:

    • Separation Gathering Centre 1 (SGC-I) and Water Injection Plant (WIP-1)
      Previous low bidder: Tecnicas Reunidas (Spain) – $2.47bn
    • Separation Gathering Centre 3 (SGC-3) and Water Injection Plant (WIP-3)
      Previous low bidder: Larsen & Toubro (India) – $2.48bn
    • Installation of Water Injection Plant (WIP-4)
      Previous low bidder: Petrofac (UK) – $1.48bn
    • Effluent Water Disposal Plants 1 & 2 expansion project (EWDP 1&2)
      Previous low bidder: Larsen & Toubro (India) – $1.30bn

    KOC is considering a strategy under which pipeline and network installation work would be removed from the main contract scopes and tendered separately, the sources said.

    The company is also planning to relaunch the four main packages under a build-own-operate model rather than the engineering, procurement and construction (EPC) model used previously.

    KOC is expected to tender the pipeline and network packages on an EPC basis, or under a similar delivery model.

    In addition, KOC is discussing increases to the projects’ approved budgets to enable contractors to submit compliant bids, the sources said.

    Since KOC cancelled the four tenders in January, Kuwait’s oil and gas sector and the wider economy have faced disruption linked to the regional conflict that began after the US and Israel attacked Iran on 28 February.

    The conflict has reduced shipping through the Strait of Hormuz, limiting Kuwait’s ability to export crude oil.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21532374/main.jpg
    Wil Crisp
  • Saudi Arabia cancels more water tenders

    19 November 2026

     

    Two tenders for a major water pipeline project in Saudi Arabia have been cancelled, marking the second major water infrastructure project in the kingdom to have its tender process called off this month.

    The tenders cover Package B and the combined Packages C1 and C3 of the New Water Pipeline to Feed Riyadh City 2 project, being developed by Water Transmission Company (WTCO). 

    A source close to the project told MEED that bidders were notified of the decision earlier in November.

    The three packages have a combined value of about $556m and involve the construction of a long-distance potable-water transmission system to strengthen supplies to Riyadh.

    The wider masterplan includes approximately 136 kilometres of pipeline, with diameters ranging from 64 inches to 100 inches. The scope also includes 10 steel storage tanks with capacities ranging from 100,000 cubic metres to 170,000 cubic metres.

    According to regional tracker MEED Projects, Saudi Services for Electro-Mechanic Works was appointed as the main contractor for Package B in 2025, with a reported contract value of $279.6m. Another local firm, Al-Rawaf Trading & Contracting, was appointed for Packages C1 and C3, with a combined contract value of $276m. Multiple other contractors submitted bids for the three packages.

    As MEED understands, construction was expected to start earlier this year.

    The cancellations follow the withdrawal of a tender for a 300-million-litres-a-day seawater reverse osmosis desalination plant at Yanbu, valued at $272m.

    As reported by MEED on 16 November, Saudi Water Authority cancelled the Yanbu tender despite India’s VA Tech Wabag receiving the contract award in July 2025.

    The contractor disclosed the decision in a filing to Indian stock exchanges, saying the tender was cancelled due to “internal reasons” on the authority’s side.

    It is the second time a tender has been cancelled for the project at the final award stage.

    It is unclear whether the desalination or transmission-pipeline projects will be retendered and, if so, whether their scopes will remain unchanged. MEED has contacted WTCO for comment.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21527730/main.jpg
    Mark Dowdall