Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Firms prepare Hudayriat East PPP tunnels advisory bids

    25 June 2026

     

    Abu Dhabi’s Modon Infrastructure, formerly Gridora, has tendered a contract for technical advisory services for the construction of two underwater tunnels connecting the eastern side of Hudayriat Island with mainland Abu Dhabi.

    Consultants have until 26 June to submit their proposals.

    The project includes the construction of a 4.8-kilometre (km) highway, with four lanes in each direction, connecting Hudayriat Island to Mussafah 8th Street.

    The project will be delivered on a public-private partnership (PPP) basis in coordination with the Abu Dhabi Department of Municipalities and Transport and the Abu Dhabi Investment Office.

    The contract term is expected to be 25 years.

    The latest infrastructure development in Abu Dhabi follows Modon Infrastructure’s invitation in May for firms to register for the next phase of Abu Dhabi’s Mid Island Parkway Project (MIPP), which will also be developed on a PPP basis.

    Modon Infrastructure will act as the lead developer, holding the majority equity stake in the project company. It will award the engineering, procurement and construction contract, as well as the operations and maintenance services and advisory appointments.

    The second phase of the MIPP involves the construction of about 11km of highways, including a mix of three-, four- and five-lane sections. The highways will connect the Um-Yifeenah, Al-Jubail, Al-Sammaliyyah and Sas Al-Nakhl islands to Khalifa City and the E10 road.

    The scope also covers the construction of three interchanges: the E20, E10 and Dumbbell interchanges on Al-Sammaliyyah Island.

    The project includes several major structures, such as the E20 interchange, which will feature cast-in-place box-girder and void-slab bridges, and the E10 interchange with cast-in-place box-girder bridges. It also includes I-girder bridges between Raha Beach West and Sas Al-Nakhl Island, as well as a causeway at Sas Al-Nakhl Island.

    Further key elements include a cast-in-place balanced cantilever bridge between Sas Al-Nakhl Island and Al-Sammaliyyah Island; a tunnel between Al-Sammaliyyah Island and Bilrimaid Island; and a cut-and-cover (open) tunnel on Bilrimaid Island. The project will be completed with another tunnel connecting Bilrimaid Island to Um-Yifeenah Island.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17410214/main.jpg
    Yasir Iqbal
  • Algeria tenders upstream oil project contract

    25 June 2026

    Algeria’s state-owned national oil and gas company, Sonatrach, has tendered a contract for the development and rehabilitation of the central processing facility (CPF) at the Bir Berkine oil and gas field.

    The scope of the contract includes the study, supply, construction and commissioning of a project to rehabilitate the CPF facilities at the field, which is located in the Hassi Mesaoud region.

    Sonatrach says in the tender documents that the objective of the project is to ensure the continuity of production activities “under stable and secure operating conditions”.

    It also says the project aims to improve production yields and quality.

    The contract includes both initial and detailed studies as well as the supply of all equipment and materials.

    It also includes the execution of works, the assembly of all equipment and materials, and the commissioning of all relevant facilities.

    The tender has a two-stage submission process, with the first stage requiring technical bids to be submitted by 23 August.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17423013/main3916.jpg
    Wil Crisp
  • Red Sea Global tenders King Salman Bay construction work

    25 June 2026

     

    Saudi gigaproject developer Red Sea Global (RSG) has tendered a contract inviting firms to undertake marine infrastructure works at King Salman Bay on the Red Sea coast, north of Jeddah.

    The scope includes dredging and earthworks, as well as quay wall and edge protection works spanning about 11 kilometres.

    The bid submission deadline is 31 July.

    King Salman Bay is expected to be a waterfront development aimed at reshaping the city’s northern Red Sea frontage into a mixed-use destination, anchored by public-realm improvements and leisure-led development.

    The update follows RSG’s award of an estimated SR100m ($27m) contract to construct a solid waste management centre at its Red Sea Project. The scope includes four buildings: a material recycling facility, a transfer station, an administration building and a vehicle maintenance building.

    In October last year, MEED reported that RSG had secured a SR6.5bn ($1.7bn) credit facility to further develop Amaala, its luxury tourism destination on Saudi Arabia’s northwestern Red Sea coast.

    According to an official statement, “The funding is led by Riyad Bank as the sole underwriter, along with Saudi Investment Bank and Bank Al-Bilad as mandated lead arrangers.

    “The loan arrangement comprises a mix of conventional and Islamic financing and adheres to RSG’s Green Loan Framework, which was first established when it secured private funding from a consortium of four banks for the Red Sea destination in 2021,” the statement added.

    The announcement followed RSG’s opening of its first properties for sale at Amaala, including branded residential communities and a five-bedroom villa on a private island.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17430045/main.jpg
    Yasir Iqbal
  • MECC submits lowest bid on three Kuwaiti oil and gas contracts

    25 June 2026

     

    Kuwait-based Mechanical Engineering & Contracting Company (MECC) has submitted the lowest bid across three separate contracts tendered by the state-owned upstream operator Kuwait Oil Company (KOC).

    The total value of the low bids is $427m, and all of the contracts are focused on developing substations to power industrial lift pumps and remote header manifolds

    Five companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 6, 10 and 12 in southern and eastern Kuwait.

    The bidders were:

    • MECC: KD65,760,000 ($212m)
    • Heavy Engineering Industries & Shipbuilding Company: KD70,630,000 ($228m)
    • Amco Engineering & Construction: KD73,446,100 ($237m)
    • Combined Group Contracting Company: KD76,186,000 ($246m)
    • Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD79,332,417 ($256m)

    Six companies submitted bids for a contract to develop several substations to power industrial lift pumps and remote header manifolds in areas 8 and 13 in southern and eastern Kuwait.

    The bidders were:

    • MECC: KD30,760,000 ($99m)
    • Badr Al-Mulla & Brothers: KD32,662,040 ($106m)
    • Heavy Engineering Industries & Shipbuilding Company: KD34,139,000 ($110m)
    • Industrial Company for Electrical Projects: KD36,375,520 ($118m)
    • Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD37,278,526 ($120m)
    • Combined Group Contracting Company: KD37,790,000 ($122m)

    Eight companies submitted bids for a contract focused on developing several substations to power industrial lift pumps and remote header manifolds in areas 7, 9, and 11 in southern and eastern Kuwait.

    The bidders were:

    • MECC: KD35,760,000 ($116m)
    • Badr Al-Mulla & Brothers: KD39,447,165 ($127m)
    • Amco Engineering & Construction: KD39,736,800 ($128m)
    • Heavy Engineering Industries & Shipbuilding Company: KD40,105,000 ($130m)
    • Industrial Company for Electrical Projects: KD43,238,265 ($140m)
    • Engineering Company for Petroleum & Chemical Industries (Enppi): KD43,514,805 ($141m)
    • Combined Group Contracting Company: KD43,650,000 ($141m)
    • Nasser Mohammed Al-Badah & Partner General Trading & Contracting: KD43,706,826 ($141m)

    Kuwait’s oil and gas sector has been in crisis in recent months due to disruption from the regional conflict that started after the US and Israel attacked Iran on 28 February 2026.

    A preliminary peace agreement between the US and Iran, which was announced on 14 June, has increased optimism that disruption to the sector will decrease in the coming weeks.

    Under the terms of the agreement, both sides have stated that the free flow of vessels will be permitted through the Strait of Hormuz, through which nearly all of Kuwait’s crude oil is normally exported.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17423009/main.jpg
    Wil Crisp
  • Chinese firm wins $265m Saudi hospital contract

    24 June 2026

    Zhejiang Construction International, the local subsidiary of Chinese contractor Zhejiang Construction Investment Group, has won a $265m contract to build the Prince Mohammed Bin Fahd University Speciality Hospital in Al-Khobar.

    Construction is expected to take three years from the start date.

    Prince Mohammed Bin Fahd University awarded the contract.

    Located in Al-Raja district, Al-Khobar, in Saudi Arabia’s Eastern Province, the hospital project will cover about 60,000 square metres.

    The contract covers the construction of a 10-storey hospital building, two five-storey auxiliary buildings connected by corridors and a basement.

    Work will include civil works, mechanical and electrical installation, curtain walling, landscaping, detailed design and the procurement of medical equipment.

    The award is the latest in a series of contracts secured by Chinese contractors from Saudi entities in recent months.

    Last week, MEED reported that Saudi Arabia’s Ministry of Municipalities & Housing awarded contracts worth more than SR1.9bn ($506m) to Chinese contractors for two residential developments in the kingdom.

    China Architectural Construction Corporation won the first contract, valued at SR875m ($233m), to build 2,010 housing units at the Al-Ruba residential project in Riyadh.

    China State Construction Engineering Corporation secured the other contract, valued at more than SR1bn ($266m), for the Al-Rasha Al-Faisaliah residential project in Dammam, comprising 2,426 housing units.

    GlobalData expects Saudi Arabia’s construction industry to record average annual growth of 5.2% in 2025-28, supported by investments in transport, electricity, housing and tourism infrastructure, as well as the $850bn-plus gigaprojects programme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17412846/main.jpg
    Yasir Iqbal