Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Dubai approves metro extension to Al-Maktoum airport

    10 November 2026

    Dubai’s Executive Council has approved a project to extend the Dubai Metro’s Route 2020 to Al-Maktoum International Airport City, with passenger services scheduled to begin operations in 2031.

    Sheikh Hamdan bin Mohammed bin Rashid Al-Maktoum, Crown Prince of Dubai, announced the decision following a council meeting held during the UAE Government Annual Meetings 2026.

    The rail project forms part of a package of strategic schemes worth over AED11bn ($3bn) approved by the council.

    The wider approvals include a comprehensive framework to upgrade community facilities and public services by 2040, with priority given to residential communities for UAE citizens.

    The project approval follows the procurement of detailed design work for the rail link. MEED exclusively reported in September that Dubai’s Roads & Transport Authority (RTA) had awarded US-based engineering consultancy Aecom the design contract for the Route 2020 extension.

    The planned extension will run for about 3 kilometres from the existing Expo 2020 terminus station to connect directly with the West Terminal of Al-Maktoum International airport. The scheme will add two new stations to the network.

    The existing Route 2020 corridor is a 15km spur that branches off the Dubai Metro Red Line at Jebel Ali station. It comprises 11.8km of elevated viaduct and 3.2km of underground track, serving five elevated and two underground stations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21301168/main.png
    Yasir Iqbal
  • Egypt seeks to accelerate gas pipeline project with Libya

    10 November 2026

    Egypt aims to accelerate a range of energy projects with Libya, including gas pipeline links, according to a statement from the Egyptian Foreign Minister Badr Abdelatty.

    Other projects include a scheme to refine Libyan crude in Egypt and an electricity interconnection.

    Abdelatty’s comments came in a ministry statement after a meeting with Libya’s acting oil and gas minister, Khalifa Abdulsadek, in the Libyan capital of Tripoli.

    Egypt is currently trying to address an energy squeeze that has escalated ​due to elevated global liquefied natural gas (LNG) prices since the ​start of the US-Israeli war on Iran in February of this year.

    In his statement, Abdelatty called ‌for ⁠cooperation on petroleum products and the completion of projects to refine Libyan oil in Egypt and re-export ​it.

    He also said that Abdulsadek would ​visit ⁠Cairo soon to continue technical talks with Egypt’s petroleum and electricity ministers.

    The ⁠statement ​did not provide ​details on costs or the status of the projects.

    Plans for new gas pipeline links with Libya are just one of several ambitious gas pipeline plans Egypt is pursuing.

    In October, the Italian oil and gas company Eni signed the main engineering, procurement, construction and drilling contracts for a project to export gas from reserves in Cyprus using a major pipeline to Egypt.

    The project includes contracts with several companies that will develop infrastructure in both Egypt and Cyprus.

    The awards included a $170m contract won by Egypt’s Petrojet for a new onshore gas pipeline in Egypt that will help transport gas to Egypt’s Damietta LNG facility.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21273777/main.jpg
    Wil Crisp
  • Omani company signs Kuwait drilling contract

    10 November 2026

    Oman’s MBPS has signed a drilling rig contract worth $127.3m with state-owned upstream operator Kuwait Oil Company (KOC).

    Under the terms of the deal, MBPS will supply and operate three newly built 1,000-horsepower land rigs for drilling and workover operations, according to a company statement.

    The UAE-based oil field services company Adnoc Drilling is a majority shareholder in MBPS.

    The chief executive of MBPS, Salim Al-Harthy, said: “This is another important milestone for MBPS and a strong reflection of KOC’s confidence in our capabilities.

    “It further strengthens our presence in Kuwait and our commitment to delivering safe, reliable and efficient drilling and workover services across the region.”

    He : “My sincere appreciation to KOC for their continued trust, and to our MBPS team for their hard work and dedication in making this possible.”

    In October last year, KOC said it planned to spend KD1.2bn ($3.92bn) on its exploration drilling programme through 2030.

    The spending was part of a KD9.8bn budget, the company’s biggest ever, allocated for drilling and maintenance of up to 6,193 wells by the end of this decade.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21273731/main.png
    Wil Crisp
  • Adnoc Drilling wins $315m Kuwait offshore rig deals

    10 November 2026

    Register for MEED’s 14-day trial access 

    Abu Dhabi National Oil Company (Adnoc Group) subsidiary, Adnoc Drilling, has been selected for two offshore drilling rig contracts in Kuwait with a combined maximum value of KD96.55m ($315m), according to documents published by Kuwait’s Official Gazette.

    The Higher Purchasing Committee of state-owned Kuwait Petroleum Corporation (KPC) has given approval for its subsidiary Kuwait Oil Company (KOC) to award the contracts to the Abu Dhabi-listed drilling contractor after Adnoc Drilling submitted the lowest compliant bids.

    While the maximum combined contract value has been confirmed as KD96.55m ($315m), the individual contract values, rig identities, durations and expected commencement dates have not been disclosed.

    The approval comes as Kuwait moves to expand offshore exploration and development following a series of discoveries in its territorial waters.

    It is currently unclear how Kuwait will provide security for its planned offshore oil and gas projects in the Gulf, adding uncertainty to the outlook for these plans.

    On 5 October, KPC chief executive Shaikh Nawaf Al-Sabah reiterated the company’s commitment to developing three major offshore oil discoveries in the region.

    KPC initially launched the Al-Seef project to develop the three fields in February, just weeks before the US and Israel attacked Iran, triggering a regional war that has sparked a crisis in Kuwait’s oil and gas sector.

    The regional conflict has seriously disrupted shipping through the Strait of Hormuz, a key export route for Kuwaiti oil.

    The war has also led to dozens of attacks on Kuwaiti oil and gas infrastructure, with at least one causing damage to a Kuwaiti offshore platform.

    This attack took place on 12 July, when a drone struck a KOC offshore drilling platform in Kuwaiti territorial waters, causing damage to the platform and injuring one worker.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21273678/main2430.jpg
    Wil Crisp
  • Aramco-backed firm tenders logistics hub expansion

    9 November 2026

     

    Asmo, the logistics joint venture of Saudi Aramco and DHL Supply Chain, has set a 15 November deadline for a contract to expand the logistics complex at King Salman Energy Park (Spark) in Saudi Arabia’s Eastern Province.

    The logistics hub will add over 124,000 square metres (sq m) at Spark.

    Al-Khobar-based engineering firm House of Consulting Office is the project consultant.

    The tender for the expansion works comes shortly after Asmo awarded an estimated SR820m ($218m) contract to build the logistics complex’s first phase in May this year.

    The overall project will feature a 43,000 sq m, temperature-controlled Grade A warehouse; more than 3,000 sq m of offices and staff amenities; 5,300 sq m dedicated to chemicals storage; and an open yard covering about 1.2 million sq m.

    Asmo signed an agreement with Bahrain‑headquartered Arcapita Group Holdings in February to deliver the project at Spark.

    Planned for large-scale industrial use, the site is expected to incorporate advanced warehouse and building management systems, end-to-end digital connectivity, automation and robotics.

    It will also be developed in line with internationally recognised sustainability standards, featuring solar photovoltaic readiness, electric-vehicle charging infrastructure and a target of Leed Gold certification.

    The development aims to support the next stage of Saudi Arabia’s logistics and supply chain expansion.

    Under the deal structure, Arcapita will provide funding and retain ownership of the asset, while Asmo will develop the facility and then lease and operate it under a 22-year occupational lease.

    According to a statement, “the scheme will be executed via a forward-funding model, underscoring a long-term commitment to national infrastructure”.

    Asmo added that this will be its first purpose-built logistics centre and one of four strategic locations planned to anchor its nationwide logistics network, aligned with the National Transport and Logistics Strategy under Saudi Vision 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21267403/main.gif
    Yasir Iqbal