Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Emirates awards $5bn engineering complex deal

    18 May 2026

    Register for MEED’s 14-day trial access 

    Emirates Airline has awarded a AED19bn ($5bn) contract to build one of the world's largest engineering complexes in Dubai South.

    The contract was awarded to Beijing-headquartered China Railway Construction Corporation (CRCC).

    CRCC is being supported by French firm Artelia, as the project consultant.

    The complex will cover over 1 million square metres (sq m).

    It will comprise 77,000 sq m of dedicated workshop space for maintenance and repairs, 380,000 sq m of storage and logistics capacity, a 50,000 sq m administrative building for Emirates Engineering and 15,000 sq m of training facilities.

    It will be the world's only complex with a capacity to service 28 wide-body aircraft simultaneously.

    The airline officially broke ground on the project on 18 May. 

    The groundbreaking ceremony was attended by Sheikh Ahmed Bin Saeed Al-Maktoum, chairman and CEO of Emirates Group; Tim Clark, president of Emirates Airline; Khalifa Al-Zaffin, executive chairman of Dubai Aviation City Corporation and Dubai South; and Dai Hegen, chairman of CRCC.

    The facility will enable large-scale retrofits, cabin redesigns and structural modifications to be performed in-house, thereby reducing turnaround times.

    The engineering complex is scheduled for completion in 2030 and will be located at Al-Maktoum International airport.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16895218/main.jpg
    Yasir Iqbal
  • Contractors submit King Salman Bay project interest

    18 May 2026

     

    Contractors submitted expressions of interest in April for a contract to undertake marine infrastructure works at King Salman Bay, on the Red Sea coast north of Jeddah.

    The scope includes dredging and earthworks, as well as quay wall and edge protection works spanning about 11 kilometres (km).

    The project client is gigaproject developer Red Sea Global (RSG).

    The invited firms include:

    • Archirodon (Greece)
    • Boskalis (Netherlands)
    • China Harbour Engineering Company (China)
    • Jan de Nul (Netherlands)
    • Modern Building Leaders (local)
    • Nesma & Partners (local)
    • NMDC Group (UAE)

    King Salman Bay is expected to be a waterfront development aimed at reshaping the city’s northern Red Sea frontage into a mixed-use destination anchored by public realm improvements and leisure-led development.

    The update follows RSG’s award of an estimated SR100m ($27m) contract to construct a solid waste management centre at its Red Sea Project. The scope includes four buildings: a material recycling facility, a transfer station, an administration building and a vehicle maintenance building.

    In October last year, MEED reported that RSG had secured a SR6.5bn ($1.7bn) credit facility to further develop Amaala, its luxury tourism destination on Saudi Arabia’s northwestern Red Sea coast.

    According to an official statement, “The funding is led by Riyad Bank as the sole underwriter, along with Saudi Investment Bank and Bank Al-Bilad as mandated lead arrangers.

    “The loan arrangement comprises a mix of conventional and Islamic financing and adheres to RSG’s Green Loan Framework, which was first established when it secured private funding from a consortium of four banks for the Red Sea destination in 2021,” the statement added.

    The announcement followed RSG’s opening of its first properties for sale at Amaala, including branded residential communities and a five-bedroom villa on a private island.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16894122/main.jpg
    Yasir Iqbal
  • Saudi Arabia tenders Mecca metro design

    18 May 2026

     

    The Royal Commission for Makkah City & Holy Sites (RCMC) has tendered a contract inviting firms to undertake initial design studies for its long-planned metro network in the holy city.

    The scope includes the review of existing studies, preparing a concept design, land acquisition studies, future phases integration concept and other related studies.

    The notice was issued earlier this month, with a submission deadline of 5 August.

    The latest development follows RCMC’s invitation to contractors to attend an early market engagement meeting for the project in September last year, as MEED reported.

    In an explanatory document inviting companies to attend the event, the RCMC’s General Transport Centre said it was seeking to gauge market interest in the multibillion-dollar project and obtain feedback on its proposed procurement approach.

    MEED exclusively reported in June last year that the project was restarting. Current plans envisage a four-line network, named lines A-D, with 89 stations and three depots, to be implemented over three phases between 2032 and 2045.

    Project scope

    Stage 1 focuses on lines B and C, involving 2.4 kilometres of tunnelling under the Masar project and integration with the existing Mashaer line.

    The network will run just over 62km and comprise 31 stations, 21 of which will be underground, including three iconic stations. A total of 19.5km will run through tunnels, while 41.2km will be elevated, with the remainder at grade.

    The 66 required trainsets are projected to provide a daily passenger capacity of about 450,000, equating to annual ridership of 171 million.

    The 84.7km-long second phase, due to be operational by 2038, will extend the two lines towards the outskirts of Mecca and includes construction of the initial inner and central segments of lines A and D.

    Comprising 61.1km elevated and 18.6km underground, Phase 2 is planned to add 45 stations serving the two new lines, as well as two depots and a potential interconnection with the planned Saudi Landbridge. The 59 trainsets for Phase 2 will increase the network’s projected total annual passenger capacity to more than 500 million.

    Phase 3 covers the elevated 36km extension of lines A and D and involves procurement of a further 72 trainsets, increasing the network’s ultimate passenger capacity to 1.2 million daily and 642 million annually by completion in 2045.

    Associated development

    The metro plan also envisages several transit-oriented developments (TODs) at different points on the route. These will typically comprise commercial, residential and retail elements to maximise the investment case.

    The client’s proposed procurement approach involves three distinct packages: civil and systems works, TODs, and operations and maintenance.

    The initial concept calls for some of the project to be delivered on a public-private partnership (PPP) basis, wherein the private sector, through special purpose vehicles, will part-finance, build, operate and then transfer commercially viable elements of the scheme.

    The then-called Mecca Mass Rail Transit Company (MMRTC) first launched the metro project in 2013; however, the scheme has faltered for more than a decade due to funding issues, land acquisition challenges and scope changes.

    The relaunch of the procurement process raises hopes that the project will now come to fruition, although it is likely to be at least 18 months before any definitive works are expected to start.

    Mecca is home to Saudi Arabia’s first metro, the nine-station, 18km-long Mashaer line, which opened in 2010. It operates only seven days a year during Hajj, but carries more than 2 million pilgrims during that time.

    Some 30 million pilgrims visit the city each year, with this number set to grow. The presence of a known, quantifiable and growing demand base will help facilitate the use of a PPP mechanism should the framework be adopted.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16893520/main.jpg
    Yasir Iqbal
  • Montage launches Ras El-Hekma hotel and residences project

    18 May 2026

    Abu Dhabi-listed Modon Holding has partnered with US-based hotel operator Montage Hotels & Resorts to launch Montage Ras El-Hekma, a new project within the Ras El-Hekma master development on Egypt’s Mediterranean coast.

    The Montage development will be situated in Wadi Yemm, the first of 17 planned precincts to move into active delivery.

    Wadi Yemm is a mixed-use cultural and hospitality district, anchored by the Ras El-Hekma Lighthouse and a 10,000-seat amphitheatre designed to host cultural and entertainment programming.

    Montage Ras El-Hekma is expected to feature approximately 200 guestrooms and suites, along with 96 branded villas.

    The villas will range from three to six bedrooms and will mark the first branded residences available for purchase at Ras El-Hekma, according to Modon.

    No construction budget or project handover timeline was provided.

    Ras El-Hekma is on a spur of land on Egypt’s northern Mediterranean coastline, about 240 kilometres west of Alexandria.

    Abu Dhabi-based holding company ADQ appointed Modon Holding as the master developer for the Ras El-Hekma project in 2024.

    Modon will act as the master developer for the entire development, covering more than 170 million sq m. 

    Modon Holding will develop the first phase of the project, which will cover 50 million sq m.

    The remaining 120 million sq m will be developed in partnership with private developers under the supervision of the recently established ADQ subsidiary Ras El-Hekma Urban Development Project Company and Modon Holding.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16893415/main.jpg
    Yasir Iqbal
  • Bahrain completes repairs to chemical plant after Iran strike

    18 May 2026

    Repair and remediation work has been completed at the Gulf Petrochemical Industries Company (GPIC) facility in Bahrain, according to a statement from the country’s Ministry of Interior.

    The repairs and clean-up operation were focused on damage caused by an Iranian drone strike on 5 April, the ministry said.

    It also said that the strike was an act of aggression that constituted a war crime.

    Prior to the repair works, an Iranian drone was lodged inside an ammonia storage tank at the facility, which had become a “grave and ongoing risk”, according to the ministry statement.

    The ministry noted that, were it not for the swift pre-emptive measures taken by Bahrain’s government as part of its broader efforts to strengthen civil protection, the consequences could have been catastrophic.

    It said that an ammonia leak would have spread across several kilometres, causing mass casualties and threatening the lives of civilians in the surrounding areas.

    The ministry commended GPIC for its proactive decision to drain the ammonia tank prior to intervention — a critical step given the tank’s location in a densely populated area.

    All residents evacuated from the surrounding area have now returned to their homes.

    The evacuation, which covered a two-kilometre radius, was carried out on a voluntary basis, with temporary alternative housing provided as a precautionary measure.

    GPIC manufactures ammonia, methanol and urea.

    It operates as a joint venture equally owned by Bapco Energies of Bahrain, Saudi Basic Industries Corporation (Sabic) of Saudi Arabia and Kuwait’s Petrochemical Industries Company (PIC).

    The facility that was attacked is located in the Sitra region of Bahrain.


    READ THE MAY 2026 MEED BUSINESS REVIEW – click here to view PDF

    Global energy sector forced to recalibrate; Conflict hits debt issuance and listings activity; UAE’s non-oil sector faces unclear recovery period amid disruption.

    Distributed to senior decision-makers in the region and around the world, the May 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16892300/main.png
    Wil Crisp