Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Adnoc Onshore selects contractors for well tie-ins project

    27 October 2026

     

    Abu Dhabi National Oil Company’s onshore operating arm (Adnoc Onshore) has selected contractors for a major project to tie in wells across the Bab and North East Bab oil field developments in Abu Dhabi.

    Located 84 kilometres southwest of Abu Dhabi city, the Bab field has been in production since 1960 and is the emirate’s first oil-producing asset. The North East Bab cluster comprises the Al-Nouf, Rumaitha and Shanayel fields. 

    The Bab and North East Bab One Tie-In project is central to Adnoc Onshore’s contribution to Adnoc Group’s target of expanding crude oil production capacity to 5 million barrels a day (b/d) by 2027, an initiative known as the Accelerated Integrated Programme 5. The state energy company’s total production capacity currently stands at approximately 4.85 million b/d.

    According to industry sources, Adnoc Onshore has selected local contractor Robt Stone Middle East and China’s Jereh Group to carry out engineering, procurement and construction (EPC) works on the project. While both firms have been notified of their selection, a formal project kick-off meeting has yet to take place.

    Adnoc Onshore is understood to have started the tendering process for the Bab and North East Bab One Tie-In project last year, with contractors submitting technical and commercial bids earlier this year.

    Following the evaluation of bids, Adnoc Onshore sought best commercial offers from the bidders, which contractors submitted in May, MEED previously reported.

    The project budget is estimated at $1.2bn.

    Bidders for the contract are understood to have included:

    • Galfar Emirates (UAE branch of Oman’s Galfar Engineering & Construction)
    • Jereh (China)
    • Kalpataru Projects International (India)
    • Matrix Construction (UAE)
    • Robt Stone Middle East (UAE)
    • Target Engineering Construction Company (UAE)

    The project scope covers residual engineering, procurement of materials not supplied as free-issue items, site surveys, construction, installation, inspection, testing, and pre-commissioning and commissioning support. The works will deliver new wellsite facilities, including a new mini-pad, well bays and clusters across the Bab and North East Bab developments.

    Adnoc Onshore is Adnoc Group’s largest production subsidiary, accounting for roughly 2 million b/d of crude and about 7 billion cubic feet a day of associated gas from four primary onshore asset clusters: Bab, Bu Hasa, North East Bab and South East.

    ALSO READ:

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20951928/main.jpg
    Indrajit Sen
  • Ashghal tenders Al-Udeid air base access road works

    27 October 2026

     

    Qatar’s Public Works Authority (Ashghal) has invited contractors to bid on a contract to build roads and related infrastructure around Al-Udeid Air Base.

    The project is located in Zone 95 of Al-Wakra Municipality, adjacent to Al-Majd Road. 

    The tender was issued on 22 October, with a submission deadline of 22 November.

    The scope includes the construction of a dual-lane carriageway to improve access to the air base, together with three roundabouts. The alignment will connect to Al-Majd Road to the east and tie into Street 203 in Zone 95 to the west. The contractor will also resurface and maintain connections to the existing road network.

    Associated works include street lighting, intelligent transport systems, directional signage and a surface-water drainage collection system.

    The contractor will provide crossing ducts, protect and relocate conflicting existing utilities, and complete detailed utility designs as required by relevant stakeholders through the Qatar Design Review System.

    The project also includes the design and construction of two electrical substations. The contractor must secure the necessary stakeholder and authority approvals before starting these works.

    The scheme will be delivered on a remeasurable, build-only basis using designs approved by others. It will also include designated contractor-designed elements and design-and-build packages for the substations.

    Bidders must submit two commercial pricing options: a base offer subject to material price-fluctuation provisions, and an alternative authority option without such provisions.

    The contract has a 550-day completion period from the commencement date, including mobilisation, followed by a 400-day maintenance period after the completion certificate is issued.

    Participation is restricted to local and international contractors registered under the Ministry of Finance classification system in Grade A or Grade B for road specialisation.

    Unclassified foreign firms may submit equivalent certified documentation from their country of origin, attested by Qatari diplomatic missions. They must obtain Ministry of Finance registration before contract award.

    For joint-venture bids, the lead partner must hold the required classification grade.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950810/main.jpg
    Yasir Iqbal
  • Saudi Arabia gauges interest for Al-Ula wastewater expansion

    27 October 2026

     

    Saudi Arabia’s Royal Commission for Al-Ula (RCU) is conducting market sounding for the first phase of the Mughayra wastewater treatment plant (WWTP) expansion before formally starting its tendering process, according to industry sources.

    The project is valued at SR400m ($107m) and is intended to increase the Mughayra plant’s wastewater treatment capacity to 62,000 cubic metres a day.

    RCU is gauging interest from potential contractors and has not yet issued a prequalification questionnaire, a source said.

    The scheme forms part of Saudi Arabia’s broader investment drive to develop its cultural and tourism offering across Al-Ula.

    The commission launched its Journey Through Time Masterplan in April 2021, with implementation scheduled in three phases through 2035. The masterplan covers infrastructure development, water management and irrigation, alongside the regeneration of a 9-kilometre cultural oasis.

    French engineering firm Artelia previously noted in its 2025 annual corporate report that it is involved in the design phase of the Mughayra WWTP.

    RCU is also developing strategic potable-water storage infrastructure in Al-Ula, including a design-and-build project covering a 50,000-cubic-metre reservoir at Hub 06 and a 15,000-cubic-metre reservoir at Hub 08.

    Local contractor Bin Omairah previously confirmed that it is serving as the engineering, procurement and construction contractor for the storage facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950333/main.jpg
    Mark Dowdall
  • Qatari firm wins $147m Syria road deal

    27 October 2026

    Qatari contractor Al-Mohannadi for Roads, Trading & Contracting has signed a $147m contract with Syria’s General Directorate of Roads to rehabilitate and expand a 215-kilometre (km) highway corridor connecting to the Iraqi border.

    The project covers the rehabilitation and dualisation of a 170km section linking the Al-Busairi junction to the Al-Tanf border crossing, alongside the construction of a 45km link between the Al-Sabaa Biyar junction and Al-Busairi. Work is scheduled for completion within 900 days.

    The agreement was signed in Damascus by Moaz Najjar, director-general of the General Directorate of Roads, and Abdullah Adnan Al-Zattam, chief executive of Al-Mohannadi, in the presence of Syrian Transport Minister Yarob Badr and Finance Minister Mohammad Yusr Barnieh.

    The upgrade is intended to restore and expand one of Syria’s primary overland arteries to Iraq, which has suffered significant deterioration and capacity bottlenecks following years of conflict. The Al-Tanf corridor represents the most direct overland link between Damascus, central Syrian industrial centres and Baghdad.

    The project is designed to accommodate heavier commercial freight vehicles and reduce transit times between the two countries.

    The investment also forms part of broader efforts to re-establish Syria’s role as a regional transit corridor connecting Mediterranean ports with landlocked trade routes into Iraq and the wider region.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20950332/main.gif
    Yasir Iqbal
  • Adnoc showcases $16.3bn local manufacturing potential

    27 October 2026

    Abu Dhabi National Oil Company (Adnoc Group) has identified more than AED60bn ($16.3bn) in local manufacturing opportunities through 2030.

    The Abu Dhabi energy company also announced changes to its procurement, supplier registration and In-Country Value (ICV) localisation frameworks.

    The measures were announced at the second Make it with Adnoc Forum, held in Abu Dhabi on October 25. They are intended to give manufacturers, suppliers and investors greater visibility of future demand and a faster, clearer route to compete for Adnoc contracts, the company said.

    The more than 200 manufacturing opportunities cover products required for Adnoc’s projects and operations, including:

    • Rotating equipment and power
    • Electrical, control and automation systems
    • Drilling and completion equipment
    • Chemicals and catalysts
    • Piping, fabrication and heavy equipment
    • Spare parts and advanced manufacturing

    Many of the identified products are currently imported, Adnoc said. “Manufacturing them in the UAE shortens lead times, reduces exposure to global supply disruptions and strengthens the resilience of Adnoc’s operations,” it said in its statement.

    Adnoc, the UAE Ministry of Industry & Advanced Technology and the Abu Dhabi Investment Office (Adio) will work together to connect manufacturers with these opportunities. The collaboration will combine visibility of Adnoc’s demand, access to the national industrial database and financing through the National Industrial Resilience Fund, the company said.

    Adnoc also signed two memorandums of understanding on the sidelines of the forum with Adio and Kezad Group.

    ICV scheme expansion

    Adnoc announced the expansion of its Local+ programme, part of its ICV framework, to more than 100 UAE manufacturers, compared with 70 at its launch in May. The programme gives UAE-made products priority in Adnoc projects by requiring engineering, procurement and construction (EPC) contractors bidding for new tenders to source relevant products from manufacturers approved under the programme.

    Separately, Adnoc announced a redesign of its supplier registration and prequalification process. The company is targeting a reduction of up to 80% in the time required for suppliers to complete the process and become eligible to compete for Adnoc opportunities.

    The new model halves the number of required documents and removes prequalification requirements for 60% of service categories.

    A single window brings together registration, qualification and compliance, with requirements tailored to the nature of the work and its level of risk. Artificial intelligence will support document verification and the reuse of existing data, reducing repetitive submissions and administrative processing.

    ALSO READ:
    Adnoc steps up crude oil capacity expansion
    Adnoc funnels billions into boosting gas processing

    “Adnoc’s enhanced ICV model will more closely connect procurement decisions with commercial value and suppliers’ contribution to the UAE economy. Under the new model, commercial and ICV offers will be integrated into a single evaluation model,” the company said.

    “The previous bid-matching approach will be retired, encouraging suppliers to submit their most competitive commercial and ICV offers from the outset. Requirements will be proportionate to contract size and scope.

    “The model also enhances the administration of ICV-related retention payments. Where retention applies, automated calculation and release processes through the Adnoc Supplier Hub will improve transparency, reduce manual follow-up and support suppliers’ cash flow as obligations are met.”

    Alongside the ICV and registration enhancements, Adnoc outlined a new commercial approach built around four strategic shifts: agile, competitive, strategic and forward-looking.

    “The approach will advance simpler procurement and faster decision-making, contracting models aligned with project and market dynamics, targeted commercial negotiations and earlier visibility of Adnoc’s future demand.”

    Since its launch in 2018, Adnoc’s ICV programme has directed more than AED307bn ($83.6bn) into the UAE economy, the company said. By the end of 2025, it had also supported the localisation of more than 130 products, the development of 95 UAE factories, and employment opportunities for more than 27,500 Emiratis at participating private sector companies.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20948385/main5518.jpg
    Indrajit Sen