Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Al-Maktoum airport is key to Dubai’s aviation hub status

    27 November 2026

    Commentary
    Colin Foreman
    Editor

    Dubai’s position as a global aviation hub is central to its economy, and the expansion of Al-Maktoum International airport is critical to maintaining that role.

    On 26 November, Dubai awarded AED56.5bn ($15bn) of contracts for the airport expansion, taking the total value of contracts awarded to more than AED80bn ($21.8bn). A workforce of 14,000 is working on the project, which will provide capacity for more than 260 million passengers a year when complete.

    The economic stakes are high. A study published by Emirates Group and Dubai Airports in October 2024 found that aviation accounted for 27% of Dubai’s GDP in 2023. The sector contributed AED137bn ($37.3bn) in gross value added and supported 631,000 jobs – about one in five jobs in the emirate. The study forecast that aviation’s share of GDP would rise to 32% by 2030, contributing AED196bn in gross value added and supporting 816,000 jobs.

    This year has demonstrated both the vulnerability and resilience of Dubai’s aviation model. Regional conflict has disrupted commercial air traffic across the Gulf since 28 February. Emirates Group’s profit before tax fell 66% year on year to AED4.1bn in the six months to 30 September, while Emirates carried 21.8 million passengers, down 22% on the prior-year period.

    However, the network recovered quickly. By 30 September, Emirates was operating 91% of its pre-disruption network, serving 150 airports in 78 countries and territories. Emirates SkyCargo revenue rose 52%, the fleet increased to 289 aircraft, and the airline broke ground in May on a $5.1bn maintenance facility at Al-Maktoum International airport.

    Maintaining that connectivity will require additional capacity. If aviation accounts for almost one-third of Dubai’s economy by 2030, as Emirates Group and Dubai Airports forecast, Al-Maktoum International airport will be central to the emirate’s ability to retain its position in global air travel.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21894329/main.jfif
    Colin Foreman
  • Emaar tenders Dubai Creek Harbour mall

    27 November 2026

     

    Register for MEED’s 14-day trial access 

    Dubai developer Emaar Properties has invited contractors to submit bids by 9 December for the main construction package of the Dubai Creek Harbour mall, known as Dubai Square.

    The development covers a total retail, hospitality and commercial area of 2.6 million square metres, and is scheduled to open within three years.

    Emaar unveiled Dubai Square in December 2025 as the anchor of its AED180bn ($49bn) Dubai Creek Harbour development.

    The scheme has undergone several redesigns. MEED first reported on Emaar’s plans for a major retail centre at Dubai Creek Harbour in 2016. At the time, the project was envisioned to surpass Dubai Mall as the world’s largest retail destination, though its scale and layout have since evolved.

    The mall will connect directly to the planned Dubai Creek Tower at the centre of the development.

    UK-headquartered Brewer Smith Brewer Group is the project’s lead consultant, executive architect, architect of record and structural engineer. It is also the construction supervision consultant.

    Dubai-based contractor Dutco Construction began mobilising last year for early site works.

    In March last year, MEED reported that Emaar was preparing to relaunch development of both the tower and the mall. The developer had earmarked roughly AED14bn ($3.81bn) for the two assets as part of a wider AED65bn ($18bn), five-year capital expenditure programme.

    Progress on the tower has been slower. First launched in 2015, it was promoted as the world’s tallest structure, designed to exceed the 828-metre Burj Khalifa. The original design was led by Spanish architect Santiago Calatrava and UK-based RMJM. The project stalled after concrete pile-cap works were completed in 2018.

    In 2023, Emaar founder Mohamed Alabbar confirmed design works were continuing following an international design competition. In January 2026, Alabbar stated that a tender for the redesigned tower would be issued within three months. He later said the tender would be deferred until regional geopolitical tensions ease.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21892263/main.jpg
    Yasir Iqbal
  • Contractor wins Arabian Beauty Horses Village in Qatar

    27 November 2026

     

    Qatar’s Culture Village Foundation (Katara) has awarded Qatar Trading & Contracting Group a QR574m ($158m) contract to build the Arabian Beauty Horses Village in Al-Uqdah Zone 74, in the Al-Khor area.

    The project will include supporting infrastructure and public facilities designed for Arabian show horses and equestrian operations in the Al-Uqdah district.

    Zone 74 is already an important centre for Qatar’s equestrian sector, anchored by the Al-Uqdah Equestrian Complex. The Qatar Racing & Equestrian Club began operating the complex in 2020 in coordination with Qatar’s Ministry of Culture and Sports.

    The Arabian Beauty Horses Village is part of a broader, multistage state strategy to develop Al-Uqdah, on the outskirts of Al-Khor, as Qatar’s second major equestrian hub, alongside Al-Rayyan and Al-Shaqab in Doha.

    According to UK analytics firm GlobalData, Qatar’s commercial construction sector is expected to grow at an average annual rate of 4.5% between 2025 and 2028, supported by investment in hotels, logistics facilities and data centres.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21890026/main.jpg
    Yasir Iqbal
  • King Salman airport sets new infrastructure bid deadline

    27 November 2026

     

    Saudi Arabia’s King Salman International Airport Development Company (KSIADC) has set a 10 January deadline for bids for the Zone C1+C2 roads, bridges and utility networks package for King Salman International airport (KSIA) in Riyadh.

    The tender was issued on 26 October, with an initial bid-submission deadline of 6 December.

    The request for proposals covers the procurement, construction, testing and commissioning of civil infrastructure supporting Terminal 6, alongside the existing Terminals 1-5.

    The scope includes upgrades to Airport Road 539, which runs west of Terminals 1-5, and part of Mohamed bin Faraj Road 5333, west of Junction 6.

    It also includes new roads, ramps, service roads and signalised at-grade junctions. An additional access road will connect the Terminal 6 site offices to Road 5333.

    Structures will include the Junction 6 and Terminal 6 bridges, retaining walls and reinforced-soil structures.

    The contractor will also construct the central ground services equipment (GSE) bridge. Before construction begins, the contractor must validate the design, complete any outstanding elements – including mechanically stabilised earth walls, approach slabs, drainage and lighting – and secure the required authority approvals.

    Dry utilities will comprise high- and extra-high-voltage containment, a 13.8kV medium-voltage network with package substations, low-voltage distribution and street lighting, and security-surveillance systems.

    Wet utilities will include potable water, fire water, irrigation water, treated sewage effluent, district cooling and wastewater networks. Wastewater pipes will range from 200mm u-PVC gravity lines to 1,700mm glass-reinforced plastic mains.

    The stormwater network will include channels, culverts, ponds and pipes ranging from 400mm to 1,400mm in diameter. Crossings will be constructed using open-cut excavation, horizontal directional drilling or microtunneling.

    Utilities serving the operational terminals will be diverted on a design-and-build basis. Enabling works will include earthworks and the relocation of the security fence and trees. The contractor will also demolish a temporary car park, existing bridges and a sewage pumping station.

    Optional works comprise two design-and-build elements that will proceed only at the client’s instruction.

    The first is the south GSE bridge. The second is an approximately 1,400-metre, multi-lane access road to the Terminal 6 Transportation Hub, including bridges, underpasses, ramps and tunnels, as well as provisions for future Wadi Loop utilities and structures.


    READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Gulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.

    Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21887157/main3955.png
    Yasir Iqbal
  • PIF secures inaugural A+ rating from S&P

    26 November 2026

    Saudi Arabia’s Public Investment Fund (PIF) has received an inaugural A+ long-term foreign and local currency issuer credit rating from S&P Global Ratings, with a stable outlook.

    The fund’s existing A-1 short-term rating from S&P is unchanged. PIF said its ratings are in line with those of Saudi Arabia.

    PIF said S&P’s assessment cited its diversified funding profile, moderate leverage and its focus on value realisation under its 2026-30 strategy. The agency also pointed to the fund’s role in driving the kingdom’s economic transformation.

    “The inaugural A+ long-term rating from S&P marks an important milestone in the continued development of PIF’s credit profile and our long-term funding plan,” said Ziyad Alfawzan, head of capital finance strategy at PIF.

    The new rating makes PIF one of a small number of sovereign wealth funds with long-term credit ratings from all three leading agencies.

    Moody’s Ratings confirmed PIF’s Aa3 long-term issuer rating and aa3 baseline credit assessment in September after a periodic review, with a stable outlook. In October, Fitch Ratings affirmed the fund’s long-term foreign and local currency issuer default ratings at A+, also with a stable outlook.

    The Moody’s rating is one notch higher than the A+ grades from S&P and Fitch.

    Debt is an increasingly important source of funding for PIF as it pays for domestic investment programmes and gigaprojects.

    The fund raised $2bn in January from a 10-year sukuk, its first debt sale of 2026. In May, it raised $7bn from a three-tranche bond, its first hard-currency public issuance since the Iran conflict disrupted regional capital markets.

    A full set of long-term ratings is likely to widen PIF’s investor base for future bond and sukuk issuance. The fund also borrows through loans and other debt instruments as part of its funding mix.

    PIF is entering what it calls the value realisation phase of its strategy, covering 2026 to 2030. Over this period, it aims to deliver sustainable financial returns while continuing to drive the diversification of the Saudi economy.


    MEED’s latest report on Saudi Arabia includes:

    > COMMENT: Saudi projects hold steady
    > GOVERNMENT: Riyadh looks to reset its regional defence outlook
    > ECONOMY: Conflict bolsters case for Saudi economic diversification

    > BANKING: Saudi lenders readjust to lower lending and deposit climate
    > UPSTREAM: Aramco upstream spending gathers pace
    > DOWNSTREAM: Sabic steps up Saudi petchems investment

    > POWER: Saudi Arabia’s power award activity slows
    > WATER: Saudi water sector hits sharp slowdown
    > CONSTRUCTION: Saudi construction defies the headwinds
    > TRANSPORT: Saudi infrastructure pushes forward amid conflict
    > DATABANK: Saudi data indicates project spending shift

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/21868102/main.gif
    Colin Foreman