Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Jordan sets market briefing for Amman water PPP

    10 April 2026

    Jordan’s Ministry of Investment, through its Public-Private Partnership Unit (PPPU), has announced a public information session for the South Amman non-revenue water (NRW) reduction PPP project.

    The session will be held on 15 April and is being organised in collaboration with the Ministry of Water & Irrigation and Miyahuna, according to a notice published by the PPPU. 

    The project covers the southern and southeastern areas of Amman and aims to reduce water losses and improve the efficiency of the capital’s distribution network.

    According to the ministry, the scheme will serve about 1.4 million people across 17 zones and forms part of Jordan’s wider National Water Strategy. 

    The planned market briefing is intended to provide early detail on the project’s PPP structure, procurement pathway and performance-based contracting model.

    It is also expected to outline the project’s risk allocation and bankability framework to prospective investors, operators and infrastructure companies.

    The Ministry of Investment opened prequalification for the scheme in March.

    Qualified companies and consortiums have been invited to participate in a two-stage procurement process for the performance-based contract. 

    The project aims to reduce NRW levels to 25% by 2040, while modernising and expanding the existing network using smart technologies and advanced leak detection systems. 

    The original deadline was 23 April. That has since been extended to 12 May.

    Jordan is among the most water-scarce countries in the world, and losses from distribution networks are estimated to account for about 45% of water supplied.

    The country is also advancing its $6bn Aqaba-Amman water desalination and conveyance project that aims to meet about 40% of Jordan’s municipal water demand by 2040.

    As MEED recently reported, the project is nearing financial close. Once complete, it will supply about 300 million cubic metres of potable water a year from the Red Sea to Amman and other regions.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16340931/main.jpg
    Mark Dowdall
  • OQ allows more time for natural gas liquids project proposals

    10 April 2026

     

    Omani state energy conglomerate OQ Group has allowed contractors more time to prepare proposals for a major project to build a natural gas liquids (NGL) facility in the sultanate.

    The planned NGL facility will extract condensates in Saih Nihayda in central Oman and transport those volumes to Duqm, located along the sultanate’s Arabian Sea coastline, for fractionation and export, OQ Group has said.

    OQ Group intends to deliver the project using a front-end engineering and design (feed)-to-engineering, procurement and construction (EPC) competition model.

    The state enterprise issued the main tender for the feed-to-EPC competition “earlier in March”, setting an initial deadline of 8 April for contractors to submit proposals, MEED previously reported. The deadline has now been extended to 6 May, according to sources.

    MEED previously reported that OQ had started the prequalification process for the feed-to-EPC contest for the planned NGL project in November last year, with contractors submitting responses by 15 December.

    The following contractors, among others, are understood to have been invited to participate in the feed-to-EPC contest for OQ’s planned NGL project, sources told MEED:

    • Chiyoda (Japan) / CTCI (Taiwan)
    • G S Engineering & Construction (South Korea)
    • Hyundai Engineering & Construction (South Korea) / KBR (US)
    • JGC Corporation (Japan)
    • Kent (UAE)
    • Petrofac (UK)
    • Saipem (Italy)
    • Samsung E&A (South Korea) / Larsen & Toubro Energy Hydrocarbon (India) / Wood (UAE)
    • Technip Energies (France)
    • Tecnicas Reunidas (Spain)
    • Tecnimont (Italy)

    The scope of work on the project covers the development, verification and integration of feed deliverables for the following facilities and systems:

    • NGL extraction facility – Saih Nihayda:
      • Verification and updating of the existing feed to enable dual-mode operation (ethane recovery and ethane rejection).
      • Identification and implementation of required process, equipment, utilities, and control system modifications.
         
    • NGL Pipeline – Saih Nihayda to Duqm:
      Feed for a new approximately 230km NGL transmission pipeline, including routing, hydraulics, stations, pigging facilities, metering, corrosion protection, leak detection, and safety systems.
       
    • Fractionation unit at Duqm:
      • Feed for a new fractionation facility to process ethane and propane + NGL and recover propane, butane, condensate, and provision for future ethane recovery.
      • Design accommodating licensed or open-art technology and future tie-in to a planned petrochemical project in Duqm.
         
    • Product pipelines, storage and export facilities at Duqm jetty:
      • Feed for product pipelines, cryogenic and atmospheric storage tanks, vapour recovery systems, marine loading arms, and export facilities.
      • Integration with existing port and refinery infrastructure, where feasible.
         
    • Supporting systems and studies:
      Utilities, offsites, flare systems, safety and environmental studies, cost estimates (class 2+10%), project schedules, constructability assessments, and EPC tender documentation.
    Natural gas liquids projects

    Gulf national oil companies have been allocating significant capital expenditure to building or expanding NGL production facilities.

    QatarEnergy, in September last year, awarded the main EPC contract for its project to add a fifth NGL train at its fractionation complex in Qatar’s Mesaieed Industrial City. The aim of the project, which is estimated to be worth $2.5bn, is to build a fifth NGL train (NGL-5) with the capacity to process up to 350 million cubic feet a day of rich associated gas from QatarEnergy’s offshore and onshore oil fields.

    The main EPC contract for the QatarEnergy NGL-5 project was won by a consortium of India’s Larsen & Toubro Energy Hydrocarbons Onshore and Greece-headquartered Consolidated Contractors Group.

    Separately, the gas processing business of Abu Dhabi National Oil Company (Adnoc Gas) has also selected the main contractor for a project to install a fifth NGL fractionation train at its Ruwais gas processing facility in Abu Dhabi.

    The fifth NGL fractionation train will have an output capacity of 22,000 tonnes a day, or about 8 million tonnes a year.

    The Ruwais NGL Train 5 project represents the second phase of Adnoc Gas’ ambitious Rich Gas Development (RGD) programme, and its budget value is estimated to be around $4bn, Peter Van Driel, Adnoc Gas’ chief financial officer, confirmed in February. The company expects to achieve final investment decision on the project within the first quarter of 2026, Van Driel said at the time.

    ALSO READ: PDO awards Oman gas plant expansion project
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16340039/main5958.jpg
    Indrajit Sen
  • Masdar’s move abroad will not be the last

    10 April 2026

    Commentary
    Mark Dowdall
    Power & water editor

    Masdar’s new joint-venture agreement with France’s TotalEnergies will not be the last time we see regional energy investors use strong balance sheets and domestic growth to build larger positions overseas.

    For Masdar in particular, the deal broadens its international exposure at a time when investors are asking questions about the Middle East’s geopolitical risk.

    By combining portfolios, the two companies start with 3GW of operational capacity and another 6GW in advanced development.

    The deal covers nine Asian countries, reflecting a prudent strategy that spreads capital across markets with different risk profiles and growth trajectories.

    In Kazakhstan, which already includes 2.6GW of assets under development, there is clear logic behind this move.

    The country is expected to see a significant increase in renewable generation over the next decade, supported by strong wind resources and the availability of large land areas for utility-scale developments.

    There is also a practical advantage in partnering with TotalEnergies, which already has project delivery experience and an established presence in several of these markets.

    The US-Iran ceasefire announced on 8 April has brought some respite to energy infrastructure stakeholders in the region.

    For investors and developers, however, the long-term uncertainty remains. Until there is clear evidence of regime change, the removal of sanctions or lasting peace in the region, the outlook will be less clear.

    With uncertainty one of the biggest killers of investor confidence, many will now be looking at this agreement and thinking whether they should also follow suit.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16340038/main.jpg
    Mark Dowdall
  • Turkish firm launches Mecca villas project

    10 April 2026

    Register for MEED’s 14-day trial access 

    Turkish real estate investment firm Emlak Konut has announced the launch of Hayat Makkah, its first development in Saudi Arabia.

    The project is part of the National Housing Company’s (NHC) wider Mecca Gate masterplan.

    According to the company, Hayat Makkah will feature 1,014 villas, with home sizes ranging from 150 to 5,000 square metres.

    NHC and Emlak Konut signed an investment agreement worth over SR1bn ($266m) in November last year to develop the project.

    The agreement was signed on the sidelines of the Cityscape Global 2025 event in Riyadh.

    Ertan Keles, chairman of Emlak Konut, said the firm is in talks with stakeholders about launching a second project, while a third development is also being lined up in Jeddah.

    GlobalData expects the Saudi Arabian construction industry to grow by 3.6% in real terms in 2026, supported by an increase in foreign direct investment (FDI) and investments in the housing and manufacturing sectors.

    The residential construction sector is expected to grow by 3.8% in real terms in 2026 and register an average annual growth rate of 4.7% between 2027 and 2030, supported by the country’s aim – under Saudi Vision 2030 – to increase homeownership from 65.4% in 2024 to 70% by 2030, including by building 600,000 homes by 2030.

    According to the General Authority for Statistics, Saudi Arabia attracted a net FDI inflow of SR72.3bn ($19.3bn) in the first nine months of 2025, an increase of 32.7% year-on-year (YoY) compared to the same period in 2024.

    Similarly, the total value of real estate loans from banks grew by 11.5% YoY in 2025, preceded by an annual growth of 13.3% in 2024, according to the Saudi Central Bank (Sama).


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16340004/main.png
    Yasir Iqbal
  • Kuwait gives bidders more time for Al-Khairan IWPP

    10 April 2026

     

    Kuwait has extended bidding for the first phase of the Al-Khairan independent water and power producer (IWPP) project.

    The project is being procured by the Kuwait Authority for Partnership Projects (Kapp) and the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant.

    The new deadline is 30 April. The original deadline was 31 March.

    The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate.

    These include:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) / Jera (Japan)
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)
    • China Power / Malakoff International (Malaysia) / Abdul Aziz Al-Ajlan Sons (Saudi Arabia)
    • Nebras Power (Qatar)                                                                                                                                        
    • Sumitomo Corporation (Japan)

    The Al-Khairan IWPP project is part of Kuwait’s long-term plan to expand power and water production capacity through public-private partnerships (PPPs).

    The winning bidder will sign a set of PPP agreements covering financing, design, construction, operation and transfer of the project.

    The energy conversion and water purchase agreement is expected to cover a 25-year supply period.

    Kapp extended another deadline recently for a contract to develop zone two of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    The PPP authority is procuring the 500MW solar photovoltaic independent power project (IPP) in partnership with the ministry.

    The bid submission deadline was moved to the end of April, a source close to the project told MEED.

    According to the MEWRE, the total generation capacity currently offered under partnership projects has reached 6,100MW, equivalent to about 30% of Kuwait’s existing power capacity.

    The ministry and Kapp are also preparing to tender the main contract for the 3,600MW Nuwaiseeb power and water desalination plant after plans were approved by Kuwait’s Council of Ministers last November.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16339960/main.jpg
    Mark Dowdall