Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • PIF to work with Egypt’s TMG on Saudi real estate schemes

    11 June 2026

    Saudi Arabia’s Public Investment Fund (PIF) and Egyptian real estate conglomerate Talaat Moustafa Group (TMG) have signed a memorandum of understanding (MoU) to explore collaboration on mixed-use real estate projects across PIF-owned developments in Saudi Arabia.

    The non-binding agreement covers potential cooperation across the residential, commercial, hospitality and retail sectors, as well as integrated urban environments. PIF said the partnership would accelerate project delivery and value creation across its portfolio.

    TMG, which has nearly 55 years of experience developing large-scale integrated cities, communities and hospitality projects across Egypt, brings technical and managerial capacity to the collaboration. The company previously signed an agreement with Saudi Arabia’s National Housing Company (NHC) in early 2024 to develop more than 27,000 residential units at the Banan City project in Riyadh’s Al-Fursan suburb.

    The MoU also establishes a framework to attract additional investors to future project phases and is intended to expand private sector participation as investors, partners and suppliers.

    PIF said the agreement forms part of its broader strategy to diversify Saudi Arabia’s economy and develop its urban development and livability ecosystem – one of six strategic ecosystems under its 2026-30 strategy. That ecosystem spans housing, retail, office and community spaces and essential services.

    The MoU is subject to the satisfaction of certain conditions precedent and receipt of all necessary regulatory and internal approvals.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17181887/main.png
    Colin Foreman
  • Egypt signs $420m Gabal El-Zeit wind agreements

    10 June 2026

    Egypt has signed agreements worth $420m for the investment, operation and power purchase of the 580MW Gabal El-Zeit wind power complex in the Red Sea region.

    Gabal El-Zeit 1 has a capacity of 240MW, while Gabal El-Zeit 2 and 3 have capacities of 220MW and 120MW, respectively.

    The agreements were signed between Egypt’s New and Renewable Energy Authority (NREA), the Egyptian Electricity Transmission Company (EETC) and Dubai-based Alcazar Energy.

    Under the agreements, Alcazar Energy will invest in, operate and manage the farms through a project company established under Egyptian law.

    The company will be responsible for technical operations, maintenance and efficiency upgrades while maintaining a minimum capacity of 580MW throughout the contract period.

    The Egyptian Electricity Transmission Company will purchase the electricity generated by the plant.

    The agreements follow earlier efforts to privatise the Gabal El-Zeit wind complex, involving a deal with UK-headquartered private equity firm Actis.

    According to the Egyptian government, the project supports the country’s state ownership policy and national energy strategy, which aim to increase the share of renewable energy in the electricity mix to 45%.

    The Gabal El-Zeit area on Egypt’s Red Sea coast is one of the country’s most established wind power development zones. The latest Gabal El-Zeit wind farm was completed in 2014, according to MEED Projects data. Germany’s Siemens Gamesa was the main contractor. 


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17170360/main.jpg
    Mark Dowdall
  • Majid Al-Futtaim awards $545m Ghaf Woods contract to ECC

    10 June 2026

    Majid Al-Futtaim Properties has appointed Engineering Contracting Company (ECC) as the main contractor for the Capria East, Capria West and Maravelle Residences developments at its Ghaf Woods community in Dubai, in a deal valued at AED2bn ($545m).

    The contract covers the construction of one-, two- and three-bedroom apartments and duplex residences across the two Capria clusters.

    The award adds to a series of major construction contracts Majid Al-Futtaim has issued across its Dubai communities in recent years.

    In May, local contractor Al-Sahel Contracting was awarded a AED700m contract for the Distrikt development, also at Ghaf Woods.

    In 2024, Majid Al-Futtaim awarded AED3bn in contracts for its Tilal Al-Ghaf community, appointing Innovo Build to build 94 waterfront villas at Elysian Mansions and United Engineering Construction (Unec) to deliver 130 villas at the Alaya development.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17170744/main.jpg
    Colin Foreman
  • Saudi Arabia and Turkiye sign railway agreements

    10 June 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia and Turkiye have signed two memorandums of understanding (MoUs) to strengthen bilateral cooperation in the railway and logistics sectors, advancing Riyadh’s ambitions to become a global logistics hub.

    Transport and Logistics Services Minister Saleh Al-Jasser and Turkish Transport and Infrastructure Minister Abdulkadir Uraloglu signed the agreements at the ministry’s headquarters in Riyadh on 9 June, following ministerial talks held with a high-level Turkish delegation. Transport General Authority president Fawaz Al-Sahli and officials from the kingdom’s transport and logistics sector were also present.

    Agreement scope

    The first MoU covers logistics services and operations, including the exchange of expertise, policies and regulations. The second focuses on railway technologies, signalling and communication systems, railway digitalisation, human capacity development, the localisation of the railway industry and measures to reduce the sector’s environmental impact.

    More broadly, the agreements cover cooperation on railway standards and related innovations, the exchange of expertise on the design, operation and maintenance of rail projects, and engineering, infrastructure and safety standards.

    The two sides will also cooperate on research and development, with provision for joint workforce training through specialist railway academies.

    Riyadh said the agreements will help support its National Strategy for Transport and Logistics Services and Saudi Vision 2030, which seeks to position the kingdom as a logistics bridge connecting three continents.

    Turkish projects

    Turkish contractors have already established themselves as key players in the region’s rail sector. In 2012, Yapi Merkezi secured a $2.1bn contract for work on the Haramain high-speed rail network in Saudi Arabia, while Turkish firms Mapa and Limak are leading the ongoing civil works on Dubai’s $5.5bn Metro Blue Line project as part of a China Railway Rolling Stock Corporation (CRRC) consortium. Turkish consultancy Proyapi Muhendislik ve Musavirlik Anonim Sirketi has also won design contracts for the 111km Kuwait National Rail Road project.

    The agreements signed by Saudi Arabia and Turkiye may also give momentum to longstanding discussions around a rail corridor linking the GCC with Turkiye. The route, which has been discussed for years, has gained renewed impetus in recent months as the effective closure of the Strait of Hormuz has pushed regional governments to accelerate the development of overland trade alternatives.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17169958/main.gif
    Colin Foreman
  • Joint venture tenders Algeria field development contract

    10 June 2026

     

    Register for MEED’s 14-day trial access 

    Hassi Bir Rekaiz Group (GHBR), which operates Algeria’s Hassi Bir Rekaiz field, has issued a tender for phase 2A of the asset’s field development project.

    GHBR is a joint venture of Algeria’s national oil and gas company Sonatrach and Thailand’s national exploration and production company PTTEP.

    The scope of the contract focuses on the “provision of engineering and supervision services”, according to documents published by Sonatrach.

    The tender has been issued with a bid deadline of 16 June 2026.

    In May, GHBR signed a $1.1bn contract for phase two of the Hassi Bir Rekaiz development project.

    The contract was won by a consortium of Egypt’s Petrojet and Italian engineering and contracting company Arkad.

    Petrojet’s portion of the project was estimated to be worth around $600m, and Arkad’s portion was estimated to be worth $500m.

    The contract used the engineering, procurement, construction and commissioning model.

    The scope of the project contract is focused on the construction of a central processing facility (CPF) capable of processing crude oil and associated gas.

    It also includes developing off-plot pipelines, as well as related utilities and infrastructure.

    The CPF will have the capacity to process 32,000 barrels a day (b/d) and will be designed to support future expansions.

    The related infrastructure will include an extensive pipeline network spanning approximately 217 kilometres, as well as a road network.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17163750/main3325.jpg
    Wil Crisp