Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Saudi Arabia approves new procurement law

    17 August 2026

    Saudi Arabia’s Council of Ministers has approved a new Government Tenders and Procurement Law (GTPL), introducing changes to public procurement procedures and government contracting.

    The Ministry of Finance announced the approval on 5 August.

    The new law aims to strengthen governance and transparency, improve procurement planning and implementation, and promote fairness and equal opportunities in government contracting.

    The changes give government entities greater flexibility in procurement while introducing new provisions that could affect contractors and suppliers, including contract variations, outstanding payments and procurement procedures.

    Contract flexibility

    According to a Ministry of Finance summary of the key amendments, one of the main changes allows government entities to increase existing contract items by up to 20% of the contract value. Contractor approval is required for increases exceeding 10%, while the total increase from adding new items or increasing existing items cannot exceed 20% of the contract value.

    The amendments also introduce measures addressing outstanding payments to contractors. A government entity cannot make a new award when it has outstanding amounts owed to contractors for works or procurement and the required procedures have not been taken, after notification from the Ministry of Finance.

    Exceptions apply where non-payment relates to ministry procedures or where the government entity has taken the required action on a claim but does not have sufficient budget allocations.

    Single committee

    Under the new law, the committees responsible for opening and examining bids will be merged into a single committee.

    The maximum value for direct procurement will rise from SR100,000 ($26,700) to SR1m ($267,000) while government entities will be required to explain and document their use of direct procurement.

    Direct procurement will also be permitted in cases involving research, development and innovation and certain contracts with professional practitioners.

    The amendments reduce the minimum standstill period following a procurement award from five working days to three working days. Government entities will also be able to negotiate where the best bid exceeds the estimated cost plus the permitted contingency.

    Localisation

    The new framework includes provisions covering industrial localisation and knowledge transfer. The Ministry of Finance said it will issue rules for contracting for these purposes in cooperation with the Local Content and Government Procurement Authority.

    A new regulation will also cover research, development and innovation, including tendering and contracting provisions for these activities.

    Other changes involve contractors’ exposure to penalties. The maximum delay penalty on contracts, excluding supply contracts, will fall from 20% to 15% of contract value. The maximum penalty for non-performance in continuous-performance contracts will also fall from 20% to 15%.

    The value of purchases exempt from providing a final guarantee will rise from SR100,000 ($26,700) to SR300,000 ($80,000). Additional exemptions will apply to contracts with professional practitioners and emergency or urgent cases.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18805103/main.jpg
    Mark Dowdall
  • GCC reviews first phase of water interconnection study

    17 August 2026

    The GCC General Secretariat has completed the first phase of a study examining the feasibility of developing water interconnection projects between GCC member states.

    A two-day workshop reviewing the study’s findings concluded on 12 August at the headquarters of the GCC Interconnection Authority (GCCIA) in Dammam, Saudi Arabia.

    The GCC General Secretariat organised the workshop in cooperation with GCCIA, with representatives from relevant authorities and experts in water, infrastructure and water security taking part.

    Participants reviewed the first phase findings, including an assessment of existing water supply infrastructure and the actual water needs of GCC member states. They also discussed the technical requirements and data needed to complete the study.

    The study is intended to identify practical options and feasible solutions for developing a regional water interconnection network. This includes establishing an implementation roadmap.

    The initiative aims to improve the GCC states’ ability to respond to emergencies and crises and support continuity of water supplies.

    First meeting

    The workshop followed a virtual meeting on 22 July between the GCC General Secretariat and Saudi Arabia’s water authorities as part of the study.

    That meeting, which also involved consultancy Artelia, reviewed the study’s methodology and implementation stages. These include assessing existing water systems across GCC states, their resilience and emergency readiness, and developing technical options for bilateral water interconnection projects.

    In Saudi Arabia, the study is focused primarily on the Eastern Province and Riyadh. It is assessing water production and desalination facilities, transmission pipelines, strategic reservoirs, pumping stations and existing and planned projects.

    The study is also examining potential bilateral connections between Saudi Arabia and Bahrain, Kuwait and Qatar, as well as the possibility of a connection with the UAE.

    The 22 July meeting also discussed potential connection points and routes, water flow directions and the possibility of designing interconnection pipelines to operate in both directions.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18802726/main.jpg
    Mark Dowdall
  • Neom’s next phase is crucial to green hydrogen pipeline

    17 August 2026

    Commentary
    Mark Dowdall
    Power & water editor

    The completion of construction at Neom Green Hydrogen comes at an important point for Saudi Arabia’s wider hydrogen ambitions.

    The project has already shown that a large green hydrogen scheme can secure financing by reaching financial close in 2023 with long-term offtake from Air Products.

    With the facility now moving into commissioning ahead of a targeted commercial operations date next year, Neom could soon give lenders and developers real evidence on the performance, costs and risks of a large-scale green hydrogen project.

    That could be important for projects still moving through development. Acwa’s Yanbu Green Hydrogen Hub, for example, is targeting commercial operations in 2030.

    The project has brought in Germany’s EnBW as a co-developer and minority investor and Japan’s Itochu as a co-developer, investor and offtaker. Acwa is targeting production of 2.5 million tonnes a year of green ammonia from the hub.

    Saudi Arabia is also putting more of the framework around the industry in place. In July, the government granted Acwa exclusive rights to export green hydrogen produced in the kingdom along with its derivatives, including green ammonia, methanol and fuels.

    However, partnerships and policy support alone will not remove the commercial questions facing projects. Yanbu still needs to progress through development and secure the financing needed to move into construction.

    Neom’s financing structure and 30-year offtake may be specific to the project, but its operating performance should give future developers and lenders a clearer reference point for assessing production, reliability and costs.

    While Neom will not make the next projects bankable on its own, if it stays on track and performs as expected, it could give lenders a stronger basis for assessing projects that follow. In the long-run, this could be one of its most important contributions.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/18800285/main.jpg
    Mark Dowdall
  • Five bid for King Salman Bay construction work

    17 August 2026

     

    Five teams have submitted bids for the contract covering the marine infrastructure works at King Salman Bay on the Red Sea coast, north of Jeddah.

    MEED understands that the bids were submitted on 31 July.

    The bidders include:

    • Deme / Archirodon (Belgium/Netherlands)
    • ⁠Van Oord (Netherlands)
    • ⁠Abdulmohsen Altamimi / NMDC Group (local/UAE)
    • ⁠Urbacon / Negida Contracting  (Qatar/Egypt )
    • ⁠Modern Building Leaders / China Harbour (local/China)

    The scope includes dredging and earthworks, as well as quay wall and edge protection works spanning about 11 kilometres.

    King Salman Bay is expected to be a waterfront development that aims to reshape the city’s northern Red Sea frontage into a mixed-use destination, anchored by public-realm improvements and leisure-led development.

    Saudi gigaproject developer Red Sea Global (RSG) is developing the project.

    The latest development follows RSG’s award of an estimated SR100m ($27m) contract to construct a solid waste management centre at its Red Sea Project. The scope includes four buildings: a materials recycling facility, a transfer station, an administration building and a vehicle maintenance building.

    In October last year, MEED reported that RSG had secured a SR6.5bn ($1.7bn) credit facility to further develop Amaala, its luxury tourism destination on Saudi Arabia’s northwestern Red Sea coast.


    READ THE AUGUST 2026 MEED BUSINESS REVIEW – click here to view PDF

    Saudi Arabia builds for the global stage; Rising uncertainty creates fresh set of challenges in the Maghreb; Gulf banks remain robust in the face of geopolitical tensions.

    Distributed to senior decision-makers in the region and around the world, the August 2026 edition of MEED Business Review includes:

    > MARKET FOCUS: Maghreb fortunes diverge
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18800910/main.jpg
    Yasir Iqbal
  • PDO allows more time for Al-Ghubar field project prices

    17 August 2026

     

    Petroleum Development Oman (PDO) has allowed contractors additional time to prepare commercial bids for a project to build a new facility to handle additional oil production from the Al-Ghubar field in the sultanate.

    The Al-Ghubar field is located in the Ghaba Salt Basin at Qarn Alam, within majority state-owned PDO’s Block 6 concession area.

    The Al-Ghubar gas-oil gravity drainage (GOGD) facility will be designed as a sour (hydrogen sulphide) facility and is expected to handle maximum oil production of 1,800 standard cubic metres a day (cm/d), a maximum total water flow rate of 10,421 standard cm/d, and maximum gas lift of 256,934 standard cm/d. Production from the planned Al-Ghubar GOGD facility will be exported to PDO’s main oil line.

    Following receipt of the technical bids for the project in July, PDO granted contractors additional time – until 16 August – to submit commercial bids for the project, MEED recently reported.

    The project operator has now extended the deadline for submitting commercial bids to 1 September, sources told MEED.

    PDO floated the tender for the Al-Ghubar GOGD facility project in March, setting an initial bid submission deadline of 4 May, MEED previously reported.

    PDO later extended the deadlines for submission of technical and commercial bids to 26 July and 7 August, respectively. Contractors submitted technical proposals by the revised deadline, according to sources.

    The following contractors, among others, are understood to be bidding for the project:

    • Archirodon (Greece)
    • Engineering for the Petroleum & Process Industries (Egypt) / Petrojet (Egypt)
    • Jereh (China)
    • Kent (UAE)
    • Larsen & Toubro Energy Hydrocarbon (India)

    The scope of work on the Al-Ghubar GOGD facility project covers the engineering, procurement and construction (EPC) of the following:

    • On-plot scope consists of:
      • Production separator  
      • Test separator  
      • Concentric wash tank
      • Wet oil pump
      • Water bath heater
      • Surge tank
      • Gas injection/gas lift compressor (centrifugal)
      • Utilities (Instrument Air compressors, chemical injection skids, drain system, vent system) 
      • Suction scrubber
      • Air coolers
      • Discharge scrubbers
      • Condensate flash drum
      • Atmospheric pressure knock-out drum 
      • Flare system
      • Gas heater
      • Water disposal pump
      • Oil shipping pump
      • New 132kV substation and plant substation (housing 6.6kV & 415-Volt switchboard)
      • New control room
         
    • Off-plot scope consists of:
      • Off-plot pipeline network (bulk header, test header, gathering infrastructure/ gathering line header, instrument air header, water disposal header)
      • Two remote manifold stations 
      • Tie-in connection to main oil line
      • Tie-in to gas network pipeline

    PDO previously intended to tender the Al-Ghubar GOGD project under its framework structure with selected EPC contractors, but eventually tendered it separately.

    PDO is the operator of the Block 6 hydrocarbons concession in Oman, which is the sultanate’s largest and most prolific concession. Situated onshore and covering an area of 75,119 square kilometres, Block 6 contains 202 oil fields and 43 gas fields, with PDO producing a total of approximately 680,000 barrels a day (b/d) of oil and condensates from those fields.

    The Omani government holds a 60% stake in PDO through Energy Development Oman (EDO). The other shareholders are UK-based Shell (34%), France’s TotalEnergies (4%) and Thailand’s state-owned PTTEP (2%).

    ALSO READ: PDO floats tender for major flare gas monetisation scheme
    https://image.digitalinsightresearch.in/uploads/NewsArticle/18799485/main.jpg
    Indrajit Sen