Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Ora Developers adds land bank to its Bayn masterplan

    17 April 2026

    Egyptian firm Ora Developers has signed a land acquisition agreement with Abu Dhabi-based developer Modon Holding to acquire an additional 4.8 million square metres (sq m) of land in the Ghantoot area between Abu Dhabi and Dubai.

    Ora Developers said that the land acquisition will increase the existing Bayn masterplan from 4.8 million sq m to 9.6 million sq m.

    The firm added that the total investment in the masterplan upon completion is expected to reach AED30bn ($8bn).

    In January, Ora Developers appointed six engineering consultancies to lead the development of the first phase of its Bayn residential community project.

    The developer appointed UK-based firm Mace to lead the overall project management.

    Canadian firm WSP will serve as the masterplan, infrastructure, landscape and water bodies design consultant, as reported by MEED in May last year.

    Another US firm, Aecom, will provide construction supervision services.

    Hong Kong’s 10 Design is the project’s architectural concept design consultant.

    Local firm Dewan Architects & Engineers is the project’s design consultant and architect of record.

    The UK’s Currie & Brown is the cost consultant.

    The first phase will offer 805 villas and townhouses, and the project is expected to be completed in 2028.

    The project will also include a neighbourhood park, sports facilities, a water park, a five-star hotel and a shopping mall.

    In December last year, Abu Dhabi government-owned contractor NMDC Group won a AED142m ($39m) contract from Ora Developers.

    The contract scope covers the execution of enabling works on the Bayn masterplan.

    The main construction works on the project's first phase are expected to begin in the second quarter of this year.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16439214/main.jpg
    Yasir Iqbal
  • SAR extends deadline for Riyadh section of Saudi Landbridge

    16 April 2026

     

    Saudi Arabia Railways (SAR) has set a deadline of 29 April for a design-and-build contract for the construction of a new railway line, the Riyadh Rail Link, which will run from north to south Riyadh.

    The tender was issued on 29 January. The previous bid submission deadline was 29 March.

    The scope of work includes constructing a 35-kilometre-long double-track railway line connecting SAR’s North-South railway to the Eastern railway network.

    The contract also covers the procurement, construction and installation of associated infrastructure such as viaducts, civil works, utility installations, signalling systems and other related works.

    The project is expected to form a key component of the Saudi Landbridge railway.

    In January, SAR said it will deliver the Saudi Landbridge project through a “new mechanism” by 2034, after failing to reach an agreement with a Chinese consortium for the construction of the project, as MEED reported.

    In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said the consortium failed to meet local content requirements and that the project will now be delivered in several phases under a different procurement model.

    The project has been under negotiation between Saudi Arabia and China-backed investors keen to develop it through a public-private partnership.

    Al-Malik said that the project cost is about SR100bn ($26.6bn).

    It comprises more than 1,500 kilometres (km) of new track. The core component is a 900km new railway between Riyadh and Jeddah, which will provide direct freight access to the capital from King Abdullah Port on the Red Sea.

    Other key sections include upgrading the existing Riyadh-Dammam line, a bypass around the capital called the Riyadh Link, and a link between King Abdullah Port and Yanbu.

    The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. Plans to develop it were first announced in 2004, but put on hold in 2010 before being revived a year later. Key stumbling blocks were rights-of-way issues, route alignment and its high cost.


    MEED’s April 2026 report on Saudi Arabia includes:

    > COMMENT: Risk accelerates Saudi spending shift
    > GVT &: ECONOMY: Riyadh navigates a changed landscape
    > BANKING: Testing times for Saudi banks
    > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
    > DOWNSTREAM: Saudi downstream projects market enters lean period
    > POWER: Wind power gathers pace in Saudi Arabia

    > WATER: Sharakat plan signals next phase of Saudi water expansion
    > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
    > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16418597/main.gif
    Yasir Iqbal
  • Public Investment Fund backs Neom

    16 April 2026

    Commentary
    Colin Foreman
    Editor

    Register for MEED’s 14-day trial access 

    Saudi Arabia’s Public Investment Fund (PIF) has backed Neom by including it as one of six strategic ecosystems in its newly approved 2026-30 strategy.

    The future of the $500bn gigaproject had been thrown into doubt following the postponement of the 2029 Asian Winter Games at the Trojena mountain resort, the cancellation of construction contracts – such as the $5bn deal with Italian contractor Webuild for dam works at Trojena – and the slowdown of development at The Line, where tunnelling contracts were cancelled and staff left the project.

    The backing comes as Neom’s operational focus appears to be evolving in response to shifting regional dynamics and global economic conditions. For example, on 15 April Neom posted on its official X account about a new Europe-Egypt-Neom-GCC corridor, describing it as a faster route for time-sensitive goods. It said the corridor combines trucking and ferry services to move goods quickly into the Gulf, adding that importers from several European markets are already using it to reach the UAE, Kuwait, Iraq, Oman and beyond.

    Powered by Pan Marine, DFDS and regional RoPax services, the initiative is positioned as a way to add flexibility and resilience to regional supply chains. This emphasis on logistics and immediate trade utility suggests a shift away from the more speculative architectural announcements that characterised Neom’s early years, towards activity more directly tied to current market realities.

    PIF’s broader 2026-30 strategy places heavy emphasis on “delivering competitive domestic ecosystems to connect sectors, unlock the full potential of strategic assets, maximise long-term returns and continue to drive the economic transformation of Saudi Arabia”.

    The inclusion of Neom as a standalone ecosystem within the Vision Portfolio suggests that while the project remains part of the kingdom’s Vision 2030 goals, it will be subject to the fund's focus on working with the private sector.

    That means the long-term success of Neom will increasingly depend on its ability to attract external investment and function as a viable economic hub rather than just a state-funded construction site.


    MEED’s April 2026 report on Saudi Arabia includes:

    > COMMENT: Risk accelerates Saudi spending shift
    > GVT &: ECONOMY: Riyadh navigates a changed landscape
    > BANKING: Testing times for Saudi banks
    > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
    > DOWNSTREAM: Saudi downstream projects market enters lean period
    > POWER: Wind power gathers pace in Saudi Arabia

    > WATER: Sharakat plan signals next phase of Saudi water expansion
    > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
    > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16417262/main.jpeg
    Colin Foreman
  • Kuwait gas project worth $3.3bn put on hold

    16 April 2026

     

    State-owned Kuwait Gulf Oil Company’s (KGOC’s) planned tender for the development of an onshore gas plant next to the Al-Zour refinery has been put on hold due to uncertainty created by the US and Israel’s war with Iran, according to industry sources.

    The project budget is estimated to be $3.3bn, and the last meeting with contractors to discuss the project took place in Kuwait on 10 February.

    Previously, it was expected to be tendered in late March, but the tendering process was delayed due to the regional conflict and disruption to shipping through the Strait of Hormuz.

    One source said: “This tender is now effectively on hold while KGOC waits for increased stability in the region before it invites companies to bid for the contract.”

    Under current plans, the plant will have the capacity to process up to 632 million cubic feet a day of gas and 88.9 million barrels a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.

    Ownership of the field is disputed by Iran, which refers to the field as Arash.

    Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.

    It is believed that the Dorra field’s close proximity to Iran will make development difficult due to the current security environment.

    The offshore elements of the project are expected to be especially difficult to protect from attacks from Iran.

    In July last year, MEED reported that KGOC had initiated the project by launching an early engagement process with contractors for the main engineering, procurement and construction tender.

    France-based Technip Energies completed the contract for the front-end engineering and design.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16413221/main.png
    Wil Crisp
  • Iraq pushes to revive oil pipeline through Saudi Arabia

    16 April 2026

    Iraq is pushing to revive an oil pipeline that passes through Saudi Arabia, allowing it to diversify export routes.

    Saheb Bazoun, a spokesman for Iraq’s Oil Ministry, said the pipeline would help to insulate Iraq from any future blockades of the Strait of Hormuz, which has been largely closed since 28 February.

    The original pipeline through Saudi Arabia has not been used for more than 30 years and would need work to be done in order to bring it online.

    It is 1,568km long, extending from the city of Zubair in Iraq to the Saudi port of Yanbu on the Red Sea.

    The pipeline was built in two phases during the 1980s. The first phase stretches between Zubair and Khurais, while the second extends to Yanbu. The pipeline’s operating capacity reached over 1.6 million barrels a day (b/d).

    Following the Gulf War, the pipeline was shut down in August 1990. It has remained out of operation for decades, despite Iraq’s several attempts to restart it.

    The original pipeline project cost over $2.6bn, including storage tanks and loading terminals.

    In the wake of the US and Israel attacking Iran on 28 February, global markets have lost 11 million barrels a day (b/d) of oil supply due to the effective closure of the Strait of Hormuz.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16413290/main.jpg
    Wil Crisp