Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Local firm makes hydrocarbon discovery in Oman’s Block 7

    14 April 2026

    Omani oil and gas exploration and production company Masar Petroleum has announced a discovery in the Hasirah Ridge in the sultanate’s Block 7.

    Masar Petroleum was the inaugural operator to appraise and produce hydrocarbons from the Hasirah reservoir in Block 7 in 2017.

    Building on that experience, Masar Petroleum has now successfully drilled a new exploration well south of its existing discoveries, validating the concept of the Hasirah Ridge — a geological trend 5 kilometres wide and 30km long mapped across Block 7 using 2D seismic data.

    This discovery represents the first step towards unlocking the Ridge’s prospective resource base of 100 million to 380 million barrels, Masar Petroleum said in a statement.

    Following this discovery, a planned 3D seismic survey and exploration and appraisal programme is expected to advance the development of the new resources by the end of 2028.

    First production from this field is expected to come on stream during the last quarter of this year.

    Masar Petroleum plans to rapidly advance appraisal and development opportunities across Block 7.

    “Masar is a proud Omani E&P company that has delivered significant value through a continuous and focused effort on unlocking our potential,” Abdulsattar AlMurshidi, CEO of Masar Petroleum, said.

    ALSO READ: Oman offers five hydrocarbon exploration blocks in new bidding round
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16383075/main2121.jpg
    Indrajit Sen
  • Bidders get more time for Saudi water transmission projects

    14 April 2026

     

    Saudi Arabia’s Water Transmission Company (WTCO) has extended the bid submission deadlines for engineering, procurement and construction (EPC) contracts for two major independent water transmission system projects.

    The Jubail-Buraidah and Ras Mohaisen-Baha-Mecca transmission projects were first tendered last September under the public-private partnership model.

    The deadlines for qualified contractors to submit technical and financial bids had initially been extended to March. 

    The new bid submission deadline for the Jubail-Buraidah project is 30 April.

    Scheduled to begin construction in 2027, the scheme comprises an approximately 348-kilometre-long greenfield water transmission system with a capacity of 840,650 cubic metres a day (cm/d), delivering water from the Ashmasiah reservoirs to cities and towns in Al-Qassim province.

    The project is large by WTCO standards. The company’s second phase of the Khobar-Hofuf system, completed in 2024, was 140km in length, with a capacity exceeding 530,000 cm/d. 

    Ras Mohaisen-Baha-Mecca

    For the Ras Mohaisen-Baha-Mecca water transmission system project, the new bid submission deadline is 7 May.

    The project involves constructing an approximately 325km-long greenfield independent water transmission system with a capacity of 542,000 cm/d, delivering water from Ras Mohaisen to the Adham and Aradhiyah regions.

    Prequalification for both projects closed on 15 January.

    It is understood that local firms Alkhorayef Water & Power Technologies and Mutlaq Al-Ghowairi Contracting Company (MGC) are among those qualified to bid for the Ras Mohaisen contract.

    MGC secured the EPC contract for an even larger independent water transmission pipeline project in June last year.

    The project, also linking Jubail and Buraidah, spans 587km and carries 650,000 cm/d.

    According to regional project tracker MEED Projects, construction works recently commenced on the project, which is estimated to cost about SR8.5bn ($2.2bn).

    WTCO is also planning to tender a contract for phase two of the Ras Mohaisen water transmission system project. This includes laying water transmission pipelines 408km in length with a capacity of 400,000 cm/d. This project is estimated to cost around $600m.

    It is understood that the main contract tender will be issued in 2027.


    READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

    Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

    Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

    > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16383056/main.jpg
    Mark Dowdall
  • Saudi firm wins $64.2m steel pipe orders from Aramco

    14 April 2026

    Saudi Arabia-based Arabian Pipes Company has announced it has won orders from Saudi Aramco to supply steel pipes, totalling SR241m ($64.2m).

    Under the terms of the contracts, Arabian Pipes Company will supply steel pipes over contract durations of nine months and 11 months, commencing from the date of signing.

    “These contract awards reinforce Arabian Pipes Company’s strong position as a key supplier to the kingdom’s energy sector and highlight its continued commitment to supporting major oil and gas infrastructure projects in Saudi Arabia,” the company said in a filing with the Saudi Exchange (Tadawul), where its shares trade.

    The company added that the orders will contribute positively to its financial performance over the contract period.

    Arabian Pipes Company last secured a contract from Aramco in August 2024, when it won an eleven-month steel pipe supply order worth approximately $28.53m.

    Prior to that, in July 2024, the company won a contract worth SR293m ($78.1m) to supply steel pipes for the second expansion phase of Aramco’s Jafurah unconventional gas development. That contract had a duration of 10 months.

    The order was placed as a subcontract by Denys Arabia, the main contractor performing engineering, procurement and construction works on one of the Jafurah second expansion phase project packages.


    MEED’s April 2026 report on Saudi Arabia includes:

    > COMMENT: Risk accelerates Saudi spending shift
    > GVT &: ECONOMY: Riyadh navigates a changed landscape
    > BANKING: Testing times for Saudi banks
    > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
    > DOWNSTREAM: Saudi downstream projects market enters lean period
    > POWER: Wind power gathers pace in Saudi Arabia

    > WATER: Sharakat plan signals next phase of Saudi water expansion
    > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
    > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/16382513/main2830.jpg
    Indrajit Sen
  • Spanish firm wins Saudi Landbridge design

    14 April 2026

     

    Spanish engineering firm Typsa has won the lead design consultancy services contract for the long-planned Saudi Landbridge railway network.

    Saudi Arabia Railways (SAR) issued the tender in April last year. It included concept design and options development for the preliminary and Issued for Construction (IFC) design stages of the network, as MEED reported.

    The estimated SR100bn ($27bn) project comprises more than 1,500km of new track. The core component is a 900km new railway between Riyadh and Jeddah, which will provide direct freight access to the capital from King Abdullah Port on the Red Sea.

    Other key sections include upgrading the existing Riyadh-Dammam line, a bypass around the capital called the Riyadh Link, and a link between King Abdullah Port and Yanbu.

    The Saudi Landbridge is one of the kingdom’s most anticipated project programmes. Plans to develop it were first announced in 2004, but put on hold in 2010 before being revived a year later. Key stumbling blocks were rights-of-way issues, route alignment and its high cost.

    In January, SAR said it would deliver the Saudi Landbridge project through a "new mechanism" by 2034, after failing to reach an agreement with a Chinese consortium to construct it.

    In an interview with local media, SAR CEO Bashar Bin Khalid Al-Malik said the consortium failed to meet local content requirements, and the project would now be delivered in several phases through a different procurement model.

    In December 2023, MEED reported that a team comprising US-based Hill International, Italy’s Italferr and Spain’s Sener had been awarded the contract to provide project management services for the programme.

    If it proceeds, the Saudi Landbridge will be one of the largest railway projects ever undertaken in the Middle East and among the biggest globally.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16382020/main.jpg
    Yasir Iqbal
  • Trump insider key in brokering Libya budget deal

    14 April 2026

    Commentary
    Wil Crisp
    Oil & gas reporter

    Massad Boulos, the father-in-law of Donald Trump’s youngest daughter and an adviser to the US president, is being credited by many Libyans as being instrumental in brokering the country’s recent budget agreement.

    The Central Bank of Libya confirmed on 11 April that the country’s rival legislative bodies had approved a unified state budget for the first time in more than 13 years.

    The budget is valued at LD190bn ($29.95bn), with LD12bn ($1.9bn) allocated to the country’s National Oil Corporation (NOC), and LD40bn ($6.3bn) allocated for “development projects”.

    After the Central Bank’s announcement, Boulos posted on social media, stating that he had called the Prime Minister of Libya’s Government of National Unity, Abdul Hamid Dbeibah, to congratulate him on the deal.

    In his social media post, the Lebanese-American businessman said that during the call, they discussed “the vital role of the National Oil Corporation in maintaining and expanding oil and gas production”.

    Boulos was appointed as the US president’s senior adviser for Arab and African affairs in January last year and first travelled to Libya in July the same year, when he met with leaders from both of the country’s rival legislatures.

    Since his first trip, he has ramped up US diplomatic activity in the country and held meetings in Tripoli and Benghazi during January of this year.

    In February, speaking at a UN Security Council session on Libya, he said that the US was ‘‘working on concrete steps for economic and military integration by bringing together senior officials from eastern and western Libya”.

    During the same session, which took place less than two months ago, the head of the United Nations Support Mission in Libya (UNSMIL), Hanna Tetteh, said: ‘‘Regrettably, there has been no meaningful progress between the House of Representatives (HoR) and the High Council of State (HCS) in completing the first two steps of the roadmap, despite UNSMIL’s efforts’’.

    Many Libyans credit Boulos’ ability to secure compromises from both of Libya’s legislatures to his decision to deviate from the UN roadmap, which focuses on moving towards a new round of elections to create a unified government.

    One source said: “The priority of the US in Libya isn’t holding elections; it’s doing commercial deals that the US can benefit from – especially in the oil sector.

    “The timing of this latest budget deal isn’t accidental. Right now, the US is desperate to bring new oil and gas production online in order to help lower global oil prices.

    “Forging a deal between the HoR and the HCS is a great way of bringing large volumes of crude onto the market in a relatively short timeframe.”

    Donald Trump is coming under increasing pressure domestically due to high oil prices after partnering with Israel in his war against Iran, which started on 28 February.

    As a result of the conflict, global markets are losing 11 million barrels a day (b/d) of oil supply due to the effective closure of the Strait of Hormuz.

    On top of this, 20% of the world’s LNG production cannot be shipped.

    The energy crunch has caused prices to spike and sent countries that are dependent on imported oil and gas scrambling to secure new supplies.

    Libya has Africa’s largest oil reserves and has the potential to produce much more than its current 1.43 million barrels a day.

    One of the central reasons NOC has struggled to bring new production online over recent years has been the ongoing political gridlock over the country’s budget.

    Now, many Libyans are expecting hundreds of projects across all sectors to start moving forward in the country.

    The budget approval has sparked a surge of optimism about potential development and economic growth, but the country’s political and security situation remains fragile.

    It remains to be seen whether the pragmatic dealmaking of Boulos will lead to long-term stability.

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16381648/main.png
    Wil Crisp