Saudi Arabia reinvigorates power sector
7 March 2023

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.
Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.
The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.
The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.
Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.
This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.
As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.
This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.
The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.
“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.
Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.
In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round.
Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.
In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.
The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.
Going nuclear
Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.
The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.
The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.
As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.
The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.
While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.
RELATED READ: Saudi nuclear move has geopolitical significance
Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.
Ramping up gas
In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.
These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.
Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.
Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.
The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.
“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.
Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.
The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.
Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.
In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.
Exclusive from Meed
-
-
-
-
-
Riyadh seeks contractors for Expo Icon structure22 July 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Adnoc initiates oil production project at key offshore block22 July 2026

Abu Dhabi National Oil Company (Adnoc Group) and its international partner, Pakistan International Oil (PIOL), have initiated a project to produce oil from Offshore Block 5 in Abu Dhabi’s waters, in which they are both stakeholders.
Adnoc, the leader on the project, intends to execute it through a front-end engineering and design (feed) competition, according to sources.
The Abu Dhabi energy giant recently selected the following three contractors for the Offshore Block 5 feed competition:
- CNPC Offshore Engineering Co (China)
- Saipem (Italy)
- Sinopec (China)
Offshore Block 5 covers 6,223 square kilometres in Gulf waters near the Zakum field and is located 100 kilometres northeast of the city of Abu Dhabi.
Abu Dhabi’s Supreme Council for Financial & Economic Affairs awarded a production concession agreement for Offshore Block 5 to Adnoc and PIOL in June 2025, with Adnoc holding the majority 60% participating interest and PIOL the other 40%.
Prior to that, Adnoc had signed an exploration concession agreement in August 2021 with PIOL, which is a consortium of four Pakistani state-owned companies – Pakistan Petroleum, Mari Petroleum Company, Oil & Gas Development Company and Government Holdings (Private).
The Pakistani consortium is understood to have invested up to $304.7m in exploration and appraisal drilling, including a participation fee, to explore for and appraise oil and gas opportunities in Offshore Block 5.
Potential oil production from Offshore Block 5 is expected to contribute to Adnoc Group’s objective of achieving an oil production capacity of 5 million barrels a day (b/d) by 2027 – a campaign known as Accelerated Integrated Programme 5. The Abu Dhabi energy giant currently has a spare capacity of 4.85 million b/d.
Pakistan, which is heavily reliant on energy imports for its economy, will also benefit from potential oil production by its companies from the Abu Dhabi concession.
ALSO READ: Adnoc announces FID on $6.2bn Umm Shaif gas cap project
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17726345/main.jpg -
Chinese contractor appointed for 500MW Oman solar plant22 July 2026
China's Shanxi Installation Group has secured an estimated $222m engineering, procurement and construction (EPC) contract for the 500MW Al-Kamil 1 solar independent power project (IPP) in Oman.
In a filing on the Hong Kong stock exchange, the company said the deal marks its first major project in the Middle East.
The contract covers the EPC, grid connection, testing and commissioning of the utility-scale solar photovoltaic (PV) plant, as well as 2.5 years of operations and maintenance.
A consortium comprising France's EDF Power Solutions, Oman National Engineering & Investment Company and OQ Alternative Energy signed the power purchase agreement for the project with Nama Power & Water Procurement Company (Nama PWP) in June.
Nama PWP is the sole procurer of new electricity generation capacity in Oman.
The Al-Kamil 1 solar IPP is EDF Power Solutions' third renewable energy project in Oman, following the 500MW Manah 1 solar PV IPP and the 120MW JBB wind IPP.
As MEED has previously reported, the Al-Kamil 1 project is part of Nama PWP's renewable energy development pipeline, which also includes the 400MW Sinaw and 280MW Marsa solar IPPs.
Nama PWP is currently tendering supervisory services for the Marsa IPP, with a bid submission deadline of 26 July.
The pipeline also comprises the 800MW Mahout and 300MW Duqm 2 wind IPPs, both targeted for commissioning between 2027 and 2029.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17725741/main.jpg -
Fluor wins feed contract for key Bahrain aromatics facility22 July 2026
Bahrain’s Gulf Petrochemical Industries Company (GPIC) has awarded US-based consultant Fluor a contract for front-end engineering and design (feed) on an aromatics facility in the country.
The project will be an expansion of GPIC’s existing petrochemicals facility in Bahrain’s downstream complex in Sitra, which produces ammonia, urea and methanol.
The new aromatics facility will utilise “commercially-proven process technologies” to produce approximately 1.2 million metric tonnes a year (t/y) of paraxylene and 500,000 metric t/y of benzene, Texas-headquartered Fluor said.
Paraxylene and benzene are critical building blocks for plastics, polyester fibers and packaging materials, supporting global demand for high‑performance consumer and industrial products.
Founded in 1979, GPIC is a joint venture of Bahraini state energy enterprise Bapco Energies, known at the time as Nogaholding; chemicals giant Saudi Basic Industries Corporation (Sabic); and Petrochemical Industries Company – a subsidiary of state energy conglomerate Kuwait Petroleum Corporation. The three partners hold equal stakes of 33.3% in GPIC.
GPIC utilises locally available natural gas as feedstock to manufacture high-quality chemicals and fertilisers for domestic consumption and export, including 1,200 metric tonnes a day (t/d) of ammonia, 1,200 metric t/d of methanol and 1,700 metric t/d of granular urea.
ALSO READ: Bahrain taps consultants for studying use of nuclear power
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17725737/main1255.jpg -
Firms submit bids for second Hassyan SWRO pipeline contract22 July 2026
Dubai Electricity & Water Authority (Dewa) has received bids from three contractors for a second pipeline contract relating to the Hassyan seawater reverse osmosis (SWRO) network expansion.
Project two requires contractors to supply, install, test and commission glass-reinforced epoxy (GRE) water transmission pipelines and associated works for the plant's phase two network.
Local firm Tristar Engineering & Construction submitted the lowest offer of AED792.59m ($215.8m), according to tender results published by the state utility.
Green Oasis General Contracting (UAE) submitted a bid of AED800.02m ($217.8m) and Wade Adams Contracting (UAE) made the other compliant offer of AED989.65m ($269.5m).
In January, Dewa announced that construction of the 180-million-imperial-gallon-a-day phase one of the Hassyan SWRO independent water project was 90% complete.
Earlier in July, eight contractors submitted bids for project one of the Hassyan pipeline network expansion.
Dewa also has a third contract out for tender for GRE water transmission pipeline work related to the Hassyan SWRO phase two network.
Project three was tendered on 26 January and has a bid submission deadline of 29 July.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17723861/main.jpg -
Riyadh seeks contractors for Expo Icon structure22 July 2026

Expo 2030 Riyadh Company (ERC), which is tasked with delivering the Expo 2030 Riyadh venue, has asked contractors to express interest in the construction of the Icon, one of the key landmarks at the site.
The structure will be located at the entrance of the Expo 2030 Riyadh site, within the Collaboration Precinct.
ERC issued the expressions of interest notice on 20 July. The deadline for submissions of interest is 23 July.
The structure will be connected to the metro station and will serve as a gateway to the event.
It will be 66 metres tall and will comprise an observation platform, food and beverage outlets and other features.
The total built-up area will be approximately 16,279 square metres and it will be able to accommodate more than 1,450 visitors an hour during the event.
The contract duration is 29 months from the start of construction.
ERC tendered the contract for the construction of the Saudi Arabia pavilion at the site in May.
The pavilion is a major asset located within the venue's KSA District, on the eastern side of the Expo 2030 Riyadh masterplan, within the Loop of Nations district.
Construction progress
The tendering of the pavilion structure followed swift progress on the site’s infrastructure development works.
In April, ERC awarded two contracts for the next phase of infrastructure works at the site to local firm Al-Yamama Company.
The scope covered the construction of road networks and infrastructure for water, sewage, electricity, telecommunications and electric vehicle charging.
These awards followed ERC’s January award of an estimated SR1bn ($267m) contract for initial infrastructure works at the site to local firm Nesma & Partners. That scope covered about 50 kilometres of integrated infrastructure networks, including internal roads and essential utilities such as water, sewage, electrical and communications systems, and electric vehicle charging stations.
The overall infrastructure works – covering the construction of main utilities and civil works at Expo 2030 Riyadh – are split into three packages:
- Lot 1 covers the main utilities corridor;
- Lot 2 includes the northern cluster of the nature corridor;
- Lot 3 comprises the southern cluster of the nature corridor.
The masterplan encompasses an area of 6 square kilometres, making it one of the largest sites ever designated for a World Expo event. Situated to the north of the Saudi capital, the site will be located near the future King Salman International airport and will provide direct access to landmarks within Riyadh.
The Public Investment Fund, Saudi Arabia’s sovereign wealth vehicle, launched ERC – a wholly owned subsidiary – in June 2025 to build and operate facilities for Expo 2030.
READ THE JULY 2026 MEED BUSINESS REVIEW – click here to view PDFStress test for Gulf aviation; Mixed performance as country outlooks diverge in the Levant; GCC tourism sector pivots from crisis to recovery mode.
Distributed to senior decision-makers in the region and around the world, the July 2026 edition of MEED Business Review includes:
> AIRPORTS: Dubai and Riyadh reaffirm airport ambitions> INDUSTRY REPORT: Dubai eyes tourism sector recovery> DATA CENTRES: Big Tech falls short on data centre promise> LEADERSHIP: Aramco’s citizen developers accelerate digital changeTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/17723204/main.jpg
