Saudi Arabia reinvigorates power sector
7 March 2023

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.
Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.
The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.
The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.
Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.
This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.
As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.
This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.
The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.
“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.
Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.
In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round.
Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.
In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.
The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.
Going nuclear
Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.
The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.
The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.
As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.
The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.
While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.
RELATED READ: Saudi nuclear move has geopolitical significance
Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.
Ramping up gas
In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.
These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.
Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.
Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.
The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.
“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.
Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.
The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.
Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.
In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.
Exclusive from Meed
-
-
UAE cuts trade and financial links with Iran19 August 2026
-
Abu Dhabi begins Dar Al-Funoon Saadiyat construction19 August 2026
-
Contractor wins Dubai Canal drainage deal19 August 2026
-
Maaden and Aramco sign deal to create joint venture18 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Libya and Tunisia reschedule joint oil and gas licensing round19 August 2026
The Libyan-Tunisian Joint Oil Exploration, Exploitation and Petroleum Services Company (Joint Oil) has rescheduled its planned licensing round for offshore exploration and development projects in a zone spanning the waters of both countries.
The bidding process is now due to open on 7 September 2026, with bid submissions due by 8 January 2027.
Previously, in May, Joint Oil said it planned to open the bid round on 1 August 2026.
The upcoming round will offer two oil and gas packages. The first is an exploration package across the 3,000-square-kilometre Joint Oil Block, in water depths of 80-120 metres.
Significant data are available on the geology of this area, including 6,500km of 2D and 1,900 square kilometres of 3D seismic data. Data also exists from a run of legacy wells dating to 1976.
The second package covers development of the Zarat discovery specifically. This is a gas-condensate reservoir straddling the boundary between Tunisia’s national acreage and the jointly-held Joint Oil Block.
Joint Oil is equally owned by Tunisia’s national oil company, ETAP, and OLA Energy Holdings, a subsidiary of the Libya Africa Investment Portfolio (LAIP).
LAIP is a subsidiary of Libya’s sovereign wealth institution, the Libya Investment Authority.
Joint Oil was established under a bilateral agreement between Libya and Tunisia in 1988 to explore and develop hydrocarbons in offshore areas shared by the two countries.
The key dates from the new schedule for the licensing round are:
- 7 September 2026: Bid round opens; qualified offshore operators can apply for access to the Virtual Data Room
- 9 September 2026: Joint Oil presents the opportunity at the MMEA Scout Group meeting in London
- 29-30 September 2026: Joint Oil presents at the World Energy Summit in London
- 31 December 2026: Bid round closes
- 8 January 2027: Bid submissions due
- 26 February 2027: Winning bidders notified
- 30 April 2027: Formal awards expected
Texas-based Moyes & Co is acting as a strategic adviser on the licensing round.
Houston-headquartered Marathon discovered the Zarat field in 1992. It is estimated to hold around 0.4 trillion cubic feet of recoverable gas and 50 million barrels of liquids.
A previous development project concept centred on a mobile production unit, worth around $1bn, tied back to the nearby Miskar platform.
Despite this, the field has remained undeveloped for over three decades.
One of the key challenges to developing the reserve is its high carbon dioxide content.
Joint Oil has run bid rounds for the acreage before without success, including as recently as late 2023.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18861047/main.jpg -
UAE cuts trade and financial links with Iran19 August 2026
Register for MEED’s 14-day trial access
The UAE has halted all trade, commercial exchanges and financial transactions with Iran until further notice, the Ministry of Foreign Affairs said on 19 August.
The suspension has been imposed in light of escalations that undermine regional and international peace and security, the ministry said. It did not specify a timeframe for any resumption.
The ministry rejected allegations regarding the status of the economic relationship between the UAE and Iran, and restated the UAE's commitment to dialogue, cooperation and regional integration as means of advancing peace, stability and prosperity in the region.
It said the UAE remains committed to safeguarding the integrity of the financial system, in line with international law and global standards.
The suspension covers the full range of commercial and financial links between the two countries. The UAE has historically been one of Iran's most significant trading partners, with much of the relationship built on re-export trade routed through Dubai to Iranian ports across the Gulf.
The ministry statement did not detail the mechanism for enforcing the halt, the sectors affected, or arrangements for existing contracts and in-transit cargo.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18857953/main0856.jpg -
Abu Dhabi begins Dar Al-Funoon Saadiyat construction19 August 2026

Register for MEED’s 14-day trial access
Abu Dhabi-based piling contractor APCC Piling & Marine Contracting has started the enabling works on Dar Al-Funoon, a cultural development near the Saadiyat Cultural District.
The project, commissioned by the Department of Culture & Tourism – Abu Dhabi, was designed by the late Canadian-American architect Frank Gehry.
The venue is scheduled to open in 2030.
MEED understands that the main contract bids are under evaluation and the project is slated for award soon.
The complex will feature a multipurpose hall with more than 2,000 seats, a 3,500-seat open-air amphitheatre, a 400-seat studio theatre and a 250-seat jazz venue, bringing total capacity to more than 6,000 across its performance spaces.
The venue will host leading international productions, delivering high-quality cultural experiences for audiences locally, regionally and globally.
Upon completion, it will become one of the region’s largest performing arts venues.
The project was announced by Sheikh Khaled Bin Mohamed Bin Zayed Al-Nahyan, Crown Prince of Abu Dhabi and Chairman of the Abu Dhabi Executive Council in June, as MEED reported.
During a review of the plans, he was briefed on the architectural concept and the development and construction phases, as well as the venue’s advanced technical capabilities, which are being designed to meet the highest international standards for staging major global productions.
The announcement is part of the ongoing development of Saadiyat Island, which already includes Louvre Abu Dhabi, Zayed National Museum, Natural History Museum Abu Dhabi, teamLab Phenomena Abu Dhabi and the upcoming Guggenheim Abu Dhabi.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18852155/main4145.jpg -
Contractor wins Dubai Canal drainage deal19 August 2026

Register for MEED’s 14-day trial access
Local firm Detech Contracting has won an engineering, procurement and construction (EPC) contract to upgrade and rehabilitate the East Dubai Canal stormwater system.
The project, known as TF-16-C1, is part of Dubai’s Tasreef strategic plan to improve the emirate’s stormwater network, increase flood protection and enhance the resilience of Dubai’s infrastructure.
According to a source, Lebanon's Khatib & Alami has also been appointed as a consultant on the project.The works will focus on upgrading existing stormwater infrastructure to increase capacity and improve reliability during heavy rainfall.
The scope includes upgrading the stormwater drainage system, laying pipelines and constructing manholes and gullies. It also includes the construction of pumping stations and diversion works, site clearance and other associated facilities.
In February, MEED reported that the municipality had invited consultants to qualify for a contract to supervise three stormwater drainage projects (TF-16-C1, TF-15-C2 and TF-13-C1)
China State Construction Engineering Corporation announced in July that it had won the EPC contract for the TF-15-C2 stormwater drainage network project located on Umm Suqeim Road in the Al-Barsha and Al-Quoz areas of Dubai.
MEED understands contractor bids are still being evaluated for the TF-13-C1 project, which focuses on developing a drainage system for the Al-Marmum area.
Detech has been awarded several packages under the Tasreef programme in the past 18 months.
These include:
- TF-16-C1: upgrading and rehabilitation of East Dubai Canal stormwater system
- TF-15-C1: stormwater drainage system at Al-Wasl Road for communities west of Dubai Canal
- TF-05-C1: stormwater drainage system in Jebel Ali
- TF-04: stormwater drainage system on Sheikh Mohammed Bin Zayed Road and Al-Yalayis Road
- DS-419: Tasreef rainwater drainage network: West Deira stormwater system upgrade and rehabilitation
As MEED exclusively reported, the municipality recently issued a letter of award for the TF-15-C1 project, covering the construction of a stormwater drainage system on Al-Wasl Road and communities west of Dubai Canal.
The project includes the construction of a gravity-based stormwater pipeline network with diameters of up to 3.5 metres. It is estimated to cost $100m.
This week, Dubai Municipality also issued three tenders for stormwater and sewerage infrastructure projects serving Hind City, Dubailand and surrounding areas.
The projects cover drainage networks for Hind 4, connections to the stormwater network in Dubailand and a stormwater trunk line serving Hind 3, Hind 4 and Umm Al-Daman.
All three have bid submission deadlines of 10 September.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18850438/main.jpg -
Maaden and Aramco sign deal to create joint venture18 August 2026
Register for MEED’s 14-day trial access
Saudi Arabian Mining Company (Maaden) and Saudi Aramco have signed a shareholders’ agreement to form a joint venture (JV). Maaden will hold a 51% stake in the JV, while Aramco will own the remaining 49%.
Before signing the shareholders’ agreement, the two Saudi state-owned companies signed a non-binding heads of agreement in January 2025 aimed at establishing the JV.
“Combining the strengths of two leaders in their respective fields, the JV will focus on copper and other minerals critical to the energy transition,” the two parties said in a joint statement.
The JV will focus on exploration across Zone 4, also known as the Transition Zone, within the Arabian Platform in Saudi Arabia. Spanning approximately 182,000 square kilometres – nearly 10% of the kingdom’s total land area – the expected exploration area stretches along a 100-kilometre-wide corridor running parallel to the Arabian Shield.
“It represents a major new opportunity for mineral discovery in the kingdom,” Maaden and Aramco said.
Copper, which is increasingly significant for electric vehicles, power networks, energy storage and renewable energy systems, will be a main focus of the JV.
Copper accounts for more than 20% of the $1.2tn mined-metals market. The copper market is currently valued at about $250bn and is projected to grow to more than $400bn by 2035.
The JV will also explore for other energy transition minerals, including zinc, lead and rare earth elements, “that are expected to be crucial to industries of the future”.
“Leveraging advanced computational algorithms, [artificial intelligence] AI, and high-performance computing, the JV intends to target areas most likely to contain copper and valuable minerals, accelerating the path from regional screening to target definition and discovery. This is expected to support long-term sector development, reinforce the kingdom’s role in the global minerals value chain, and help meet rising demand for transition minerals,” the partners said.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18833329/main.jpg
