Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Riyadh tenders Expo 2030 Adaptation and Innovation Pavilion

    21 October 2026

     

    Register for MEED’s 14-day trial access 

    Expo 2030 Riyadh has tendered the design-and-build main contract for the Adaptation and Innovation Pavilion in the exhibition’s Technology District.

    The pavilion will be built on a plot of at least 12,710 square metres and will feature a two-level basement, ground-level public areas, an elevated skywalk, visitor experience areas, food and beverage outlets, retail space, VIP facilities, offices, back-of-house areas, exhibition spaces, an amphitheatre and a resonance hall.

    The facility is being designed to accommodate a minimum of 20,000 visitors a day at peak periods, with an anticipated average of about 15,000 visitors a day. The project targets LEED Gold certification.

    The tender was issued on 1 October, with bids due on 6 January 2027.

    The design-and-build contractor will be responsible for completing, reviewing, verifying, coordinating and technically integrating the design, including specialist contractor design portions and coordination with the novated lead design consultant.

    The scope includes completing early works and substructure activities, including grading, bulk earthworks, excavation, cut and fill, soil improvement, raft foundations, reinforced-concrete basement walls, basement columns through to the ground-floor slab, waterproofing, mechanical, electrical and plumbing (MEP) provisions, and backfilling.

    The contractor will also deliver the superstructure and building envelope, including structural works, facade engineering and installation, roofs, waterproofing, external finishes, and permanent facade access and maintenance systems. The internal works will cover front-of-house and back-of-house areas, public and core spaces, internal finishes, fixtures, fixed fittings, joinery, circulation areas, lobbies, stairs, toilets, storage, waste areas and associated builder’s works.

    The building services package includes MEP systems, information and communications technology, extra-low-voltage systems, building management systems, security, fire and life safety systems, specialist lighting and vertical transportation.

    The contract also covers the visitor experience package, including procurement, installation, integration, testing, commissioning and handover of visitor-facing environments, media, immersive and audiovisual technologies, interactive elements, experiential lighting, digital content, interpretive and wayfinding systems, controls and supporting infrastructure.

    Within-plot infrastructure and utilities, landscaping, public realm works, paving, planting, irrigation, signage, street furniture, drainage, stormwater systems, external lighting, security, and fire and life safety systems are also included.

    The contractor will be responsible for procurement, off-site fabrication, construction, testing and commissioning, performance verification, training, operations and maintenance documentation, operational readiness, handover, defects rectification and close-out.

    The main works tender is based on a 60% RIBA Stage 3 design, with the Stage 3 design to be completed to 100% through an addendum.

    Early works and substructure works, as well as the lead design consultant, will be novated to the contractor. Visitor experience works are included as a provisional sum.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20801465/main.jpeg
    Yasir Iqbal
  • Mubadala Bio lands Lilly logistics deal

    21 October 2026

    Mubadala Bio, the life sciences subsidiary of Abu Dhabi state investor Mubadala Investment Company, has signed an agreement with US drugmaker Eli Lilly to localise the packaging and logistics of Lilly’s glucagon-like peptide-1 (GLP-1) medicines in Abu Dhabi.

    The work will take place at a 125,000-square-metre site in Khalifa Economic Zones Abu Dhabi (Kezad), which includes packaging and warehousing facilities. Mubadala Bio said the facilities would strengthen its pharmaceutical contract manufacturing, packaging and logistics capabilities and its ability to serve international clients from the UAE.

    The packaging and logistics activities will be introduced in phases and will be subject to technical, quality and regulatory requirements. The companies did not disclose the value of the agreement or a timeline for the first phase.

    The Emirates Drug Establishment approved Lilly’s oral GLP-1 drug Foundayo (orforglipron) for chronic weight management in April. The companies said this made the UAE the second country in the world to register the medicine.

    In Abu Dhabi, the treatment is available to eligible patients under a weight management programme launched by the Abu Dhabi Department of Health and the Abu Dhabi Public Health Centre in June 2025. The UAE was also an early launch market for Lilly’s injectable treatment Mounjaro (tirzepatide) in August 2022.

    Mubadala launched Mubadala Bio in 2025 to expand domestic drug manufacturing and distribution, with a focus on national drug security. It is one of Mubadala’s designated national champions, set up to support strategic sectors. At launch, its combined facilities covered 110,000 square metres, with an annual capacity of more than 2.5 billion tablets and capsules and 120 million intravenous and injectable units.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20801279/main.jpg
    Colin Foreman
  • Chinese/local joint venture wins Qiddiya stadium facade

    21 October 2026

    Register for MEED’s 14-day trial access 

    A joint venture of China’s Fangda Group and Saudi Arabia’s IKK Group has secured a SR1.15bn ($306m) contract to deliver curtain wall facade works for the Prince Mohammed Bin Salman Stadium in Qiddiya City, Riyadh.  

    The contract was awarded by the joint venture of Spain’s FCC Construccion and local contractor Nesma & Partners, which is building the stadium under an estimated SR15bn ($4bn) main contract awarded by Qiddiya Investment Company (QIC) in October 2024.  

    The IKK-Fangda joint venture will design, supply and install curtain wall façade systems for the main stadium (Lot 1), as well as for the museum and ancillary buildings (Lot 3).

    The contract has an execution period of 863 days.  

    The stadium will seat about 47,000 spectators and will be the home ground for Saudi Pro League clubs Al-Nassr and Al-Hilal.

    The facade award follows the appointment of Elegancia Arabia, a subsidiary of Qatar-based Elegancia MEP and Estithmar Holding, to deliver the stadium’s mechanical, electrical and plumbing works.

    The SR829m ($221m) contract is Elegancia Arabia’s largest award in Saudi Arabia to date.

    The project is being designed by US-based consultant Populous.

    It is among the venues planned for the 2034 Fifa World Cup and will also host the Saudi King Cup, the AFC Asian Cup and the 2034 Asian Games.  

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20799367/main.jpg
    Yasir Iqbal
  • Zamil Steel wins $82m Qiddiya tennis centre contract

    21 October 2026

    Advanced Building Industries Company (Senaat) has announced that its subsidiary, Zamil Structural Steel Company (Zamil Steel), has secured a SR308m ($82m) contract for the National Tennis Centre in Qiddiya City, Riyadh.  

    The 19-month contract was awarded by the joint venture of France’s Bouygues Batiment International and local contractor Almabani General Contractors Company.  

    Zamil Steel’s scope includes the fabrication, supply and installation of structural steel and external facades for the scheme.   

    MEED reported in June that the Bouygues Batiment International-Almabani joint venture had started construction of the National Tennis Centre.  

    The development will include 30 tennis courts, comprising 28 hard courts and two clay courts. The main Centre Court will seat 15,000 spectators and feature a retractable roof.

    The facility is being designed to meet standards set by the Association of Tennis Professionals, the Women’s Tennis Association and the International Tennis Federation.  

    The development will also include an 8,000-seat multipurpose arena with a retractable roof, known as Court 3. Other facilities include a 5,000-seat Court 1, a 2,000-seat Court 2, six competition courts, six indoor courts and 14 practice courts. Each outdoor match court will provide 450 seats.  

    Total seating capacity across the complex will be 33,000. US-based architect Populous designed the project.  

    Qiddiya Investment Company officially announced the project on 15 June. The developer has said the centre will be the region’s largest tennis complex and will host international tennis events.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20799055/main.jpg
    Yasir Iqbal
  • Eni starts to bring gas processing facility online in Egypt

    21 October 2026

    Register for MEED’s 14-day trial access 

    Italy’s Eni has started to bring its Meleiha Phase 2 (MP2) project online in Egypt’s Western Desert, according to statements from the company and Egypt’s Ministry of Petroleum & Mineral Resources.

    The project includes a new gas processing facility designed to process up to 100 million standard cubic feet of gas a day.

    Eni is a part owner of the project through Agiba Petroleum Company, a joint venture of Eni and state-owned Egyptian General Petroleum Corporation (EGPC)

    The main contract for the project was awarded to the Egyptian engineering, procurement and construction (EPC) company Petrojet.

    The scope of the project included:

    • Laying 200 kilometres of pipeline
    • Drilling 28 wells
    • Construction of a gas sweetening unit
    • Construction of a gas recovery unit
    • Installation of gas purification and liquids separation units
    • Installation of utilities and supporting infrastructure
    • Construction of natural gas processing plant
    • Construction of associated facilities

    In its statement, Eni said: “The project represents a key milestone in the development of a new gas hub within the Merged Meleiha concession and will significantly increase the gas processing capacity for production from the area’s fields, supporting the growth of domestic gas output and the valorisation of Egypt’s energy resources.”

    The Meleiha and Meleiha Deep concessions were combined into a single concession known as the Merged Meleiha concession in 2021.

    Eni said that the new facilities “will ensure the connection of new production to Egypt’s existing gas infrastructure, enabling the rapid monetisation of resources and enhanced operational efficiency”.

    It added: “The launch of the project confirms Eni’s role as a strategic partner of Egypt and reaffirms the company’s long-standing commitment to contributing to the country’s energy security through the development and valorisation of the Western Desert’s diversified resource base, one of the most promising areas of Egypt’s energy sector.”

    Eni has been present in Egypt since 1954 and produced approximately 242,000 barrels of oil equivalent a day in the country on an equity basis in 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20788394/main.gif
    Wil Crisp