Saudi Arabia reinvigorates power sector

7 March 2023

 

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.

Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.

The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.

The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.

Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.

This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.  

As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.

This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.

The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.

“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.

Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.

In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round. 

Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.

In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.

The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.

Going nuclear

Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.

The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.

The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.

As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.

The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.

While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.

RELATED READ: Saudi nuclear move has geopolitical significance

Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.

Ramping up gas

In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.

These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.

Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.

Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.

The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.

“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.

Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.

The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.

Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.

In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10654009/main.gif
Jennifer Aguinaldo
Related Articles
  • Consortiums prepare bids for Al-Khairan phase one IWPP

    14 May 2026

     

    Two developer consortiums are finalising bids for the first phase of Kuwait’s Al-Khairan independent water and power producer (IWPP) project, the deadline for which has been extended to 1 June.

    The facility will have a capacity of 1,800MW and 150,000 cubic metres a day of desalinated water. It will be located in Al-Khairan, adjacent to the Al-Zour South thermal plant. 

    The project is expected to run on Low Sulphur Fuel Oil (LSFO) as the primary fuel and to accommodate crude oil, gas oil, and natural gas as backup fuels. Later phases will further expand capacity.

    The main contract was tendered last September. Three consortiums and two individual companies were previously prequalified to participate, with the following groups currently preparing offers:

    • Abu Dhabi National Energy Company (Taqa) / A H Al-Sagar & Brothers (Saudi Arabia) 
    • Acwa (Saudi Arabia) / Gulf Investment Corporation (Kuwait)

    The two individual companies, Sumitomo Corporation (Japan) and Nebras Power (Qatar), are now “unlikely” to submit a bid, according to a source close to the project.

    It is also understood that the third consortium of China Power, Malakoff International (Malaysia) and Abdul Aziz Al-Ajlan Sons (Saudi Arabia) is no longer bidding for the contract.

    The project is being procured by the Kuwait Authority for Partnership Projects (Kapp) and the Ministry of Electricity, Water & Renewable Energy (MEWRE).

    The Al-Khairan IWPP project is part of Kuwait’s long-term plan to expand power and water production capacity through public-private partnerships (PPPs).

    The winning bidder will sign a set of PPP agreements covering financing, design, construction, operation and transfer of the project.

    The energy conversion and water purchase agreement is expected to cover a 25-year supply period.

    Upcoming awards

    Kuwait is also preparing to offer a contract to develop zone one of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    In January, three consortiums submitted bids for a contract to develop Kuwait’s first utility-scale solar photovoltaic (PV) plant.

    The Al-Dibdibah power and Al-Shagaya renewable energy phase three, zone one independent power project (IPP) will have a total power-generating capacity of 1,100MW.

    MEED understands that the preferred bidder announcement will happen after the bid closes for zone two of the third phase of the Al-Dibdibah power and Al-Shagaya renewable energy project.

    The PPP authority is procuring the 500MW solar photovoltaic IPP in partnership with the ministry.

    The bid deadline for this project was recently extended to 31 May.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16835649/main.jpg
    Mark Dowdall
  • Bidders compete for new Dubai Metro line project

    14 May 2026

     

    Register for MEED’s 14-day trial access 

    Dubai’s Roads & Transport Authority (RTA) has held a pre-bid meeting for the Dubai Metro Airport Express Line with consultants understood to be competing for work on the project.

    It is understood that the RTA has requested firms to form joint ventures for the project. The firms that attended the meeting include:

    • Aecom (US)
    • Arup (UK)
    • ARX (Switzerland)
    • AtkinsRealis (Canada)
    • DB (Germany)
    • Egis (France)
    • Jacobs (US)
    • Mott Macdonald (UK)
    • Parsons (US)
    • Sener (Spain)
    • Surbana Jurong (Singapore)
    • Systra (France)
    • WSP (Canada)

    The consultancy contract covers the study and design of the Airport Express Line, which will extend from the Al-Garhoud area of the city to Al-Maktoum International airport (DWC) in the Jebel Ali area. The proposed line will stretch about 55 kilometres (km) and include five stations, providing passengers with facilities such as remote airline check-in, baggage drop-off and security screening.

    Consultants have been allowed until June to submit their proposals.

    The new line will run from the Red Line metro station at Dubai International airport through Al-Jaddaf, along Al-Khail Road to a new station at Jumeirah Village Circle (JVC) before continuing on to DWC.

    There will be two spur lines. The first will run from the new JVC station to the Al-Fardan Exchange metro station at Emirates Golf Club, while the second will branch out towards Business Bay, where another station will be built.

    The new line appears to follow a similar route to the Etihad Rail high-speed railway project, which is now under construction and due to be completed by 2030.

    Route 2020 extension

    The Airport Express Line scheme is the latest metro project to be tendered by the RTA this year. Tendering activity is already ongoing for the Route 2020 extension, which will start from the Expo 2020 metro station and connect to DWC’s West Terminal.

    In April, MEED exclusively reported that consultants had submitted bids for the project.

    The extension to the line will run for about 3km and will feature two stations.

    The existing Route 2020 metro link is a 15km-long line that branches off the Red Line at Jebel Ali metro station. The line comprises 11.8km of elevated tracks and 3.2km of tunnels, and has five elevated stations and two underground stations.

    The RTA awarded the AED10.6bn ($2.9bn) design-and-build contract for the project to a consortium of Spain’s Acciona, Turkiye’s Gulermak and France’s Alstom in 2016.

    Gold Line

    Dubai’s plans for its metro network do not stop with connecting the extension of the Route 2020 metro line to DWC. There are long-term plans for further extensions.

    In October last year, MEED exclusively reported that the RTA had selected US-based engineering firm Aecom to provide consultancy services for the upcoming Dubai Metro Gold Line project, also known as Metro Line 4.

    The Gold Line will start at Al-Ghubaiba in Bur Dubai. It will run parallel to – and alleviate pressure on – the existing Red Line, before heading inland to Business Bay, Meydan, Global Village and residential developments in Dubailand.

    The existing network includes the Red and Green lines of the Dubai Metro and the Dubai Tram, which connects Al-Sufouh and Dubai Marina to the metro network. The last rail project to start operations in Dubai was the Red Line extension that opened for Expo 2020.

    There are also existing and planned rail lines connecting Dubai to other emirates that are being developed and operated by Abu Dhabi-based Etihad Rail. These include passenger and freight services, as well as a high-speed rail connection.

    Blue Line

    In December 2024, the RTA awarded a AED20.5bn main contract for the Dubai Metro Blue Line project to a consortium of Turkish firms Limak Holding and Mapa Group and the Hong Kong office of China Railway Rolling Stock Corporation.

    The Blue Line consists of 14 stations, including three interchange stations at Jaddaf, Rashidiya and International City 1, as well as a station in Dubai Creek Harbour.

    By 2040, the number of daily passengers on the Blue Line is projected to reach 320,000. It will be the first Dubai Metro line to cross Dubai Creek, doing so on a 1,300-metre viaduct.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16833450/main.jpg
    Colin Foreman
  • Local firm wins $100m Kuwait substation contract

    14 May 2026

     

    The local Al-Ahleia Switchgear Company has won an engineering, procurement and construction contract for a $100m substation project in Wafra in Kuwait’s Al-Ahmadi Governorate.

    According to a source, the firm has been appointed as the contractor for the Wafra 2Z substation 400/132/33kV project, with construction scheduled for completion in January 2029.

    The contract was awarded by US-headquartered Chevron, which is undertaking its first major power project in Kuwait, according to data from MEED Projects.

    It is understood that contractor bids for the project were first submitted in 2023 by National Contracting Company (Kuwait), Al-Ahleia Switchgear (Kuwait), Imco Engineering & Construction Company (Kuwait) and Larsen & Toubro (India).

    The tender was cancelled in 2024, and a new tender was issued last year.

    In April, Al-Ahleia Switchgear won a contract to build a 400/132/11kV substation at the South Surra township for Kuwait’s Public Authority for Housing Welfare.

    The firm also recently won a separate contract in Oman for the supply, installation, execution and maintenance of a main power substation.

    The contract was awarded by Oman’s Public Authority for Social Insurance as part of its affordable housing project, known locally as Al-Masaken Al-Muyassara.

    According to MEED Projects, Chevron owns about $11.2bn-worth of operational oil and gas projects across the Middle East and Africa. It also owns four major power generation projects in Saudi Arabia, valued at $810m.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16832909/main.jpg
    Mark Dowdall
  • Al-Ain breaks ground on Four Seasons Saadiyat

    14 May 2026

    Al-Ain Asset Management has held a groundbreaking ceremony for its Four Seasons Private Residences Abu Dhabi project at Saadiyat Beach.

    Due for completion in 2029, the gated beachfront scheme will comprise 116 ultra-luxury homes with direct beach access. The unit mix includes villas, beachfront mansions, suites and penthouses, alongside a range of bespoke amenities and Four Seasons-branded services, Wam reported.

    Al-Ain Asset Management said the majority of the residences have been sold, and that AED250m ($68m) of new villa sales were recorded within one week, underlining demand for ultra-prime homes in Abu Dhabi.

    The developer added that the development set new pricing benchmarks for the emirate’s luxury coastal real estate, achieving prices above AED14,000 a square foot. Total sales have exceeded AED4bn since the project launched less than a year ago.

    The groundbreaking ceremony was attended by senior leadership and key partners, including Four Seasons, Killa Design and Mirage Leisure & Development. LW Design Group is also involved in the development.

    Al-Ain Asset Management is also developing another residential scheme on Saadiyat Island. The Vida Residences development will comprise apartment units geared towards long-stay living, supported by hotel-style facilities and operational spaces. Mimar Architecture & Engineering is working as the consultant.

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16833035/main.jpeg
    Colin Foreman
  • Aldar acquires Dubai Studio City development

    14 May 2026

    Abu Dhabi-based developer Aldar has acquired a residential and community retail development in Dubai Studio City from Dubai-based developer SRG for AED1.1bn ($300m).

    The deal is part of Aldar’s long-term strategy to build a high-quality, recurring-income portfolio and to scale its presence in the city.

    Scheduled for delivery in 2028, the project comprises six mid-rise buildings with 312 homes, including one-, two- and three-bedroom apartments and duplexes. It also includes a community mall with retail, leisure and food-and-beverage offerings, as well as a 16,000-square-metre park.

    “Dubai is a priority growth market for Aldar, and this acquisition reflects our belief in the city’s residential market and the central role that institutionally owned, professionally managed rental housing plays in meeting the needs of a growing population,” said Jassem Saleh Busaibe, CEO of Aldar Investment. 

    “Dubai Studio City’s established infrastructure, vibrant community and strong connectivity make it an excellent location for a high-quality, professionally managed living environment. This transaction is the latest step in a deliberate and broadening strategy to build a diversified portfolio of income-generating assets in Dubai, one that we expect to continue growing as the city attracts increasing global interest and talent,” he added. 

    The transaction expands Aldar’s activities in Dubai across a range of property types. Aldar Investment’s recurring-income portfolio in the emirate now includes residential, commercial, logistics and mixed-use assets. Key holdings include a mixed-use joint venture with Expo City Dubai, a signature office tower in Dubai International Financial Centre, a Grade A office building on Sheikh Zayed Road, and logistics facilities in National Industries Park and Dubai South.

    On the development front, Aldar’s partnership with Dubai Holding continues to gain traction, with three master-planned residential communities already launched and a pipeline exceeding 2.3 million sq m of new gross floor area. 

    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/16832033/main.jpg
    Colin Foreman