Saudi Arabia reinvigorates power sector
7 March 2023

Recent developments indicate that Saudi Arabia is more determined than ever to continue pursuing a multi-pronged energy diversification approach.
Between December 2022 and early March, the kingdom received bids for the contract to build its first nuclear power plant project; issued the tender for the development of 7,200MW of combined-cycle gas turbine (CCGT) independent power producer (IPP) schemes; and appointed a consultant to assess three solar parks with a potential capacity of 30GW.
The rush of new projects contrasts with the sector’s lacklustre performance in 2016-21, when the cumulative value of contracts awarded totalled a mere $5.5bn, reaching a record low of $55m in 2017.
The new-found momentum began last year, with $8.1bn-worth of contracts awarded, the highest over the 10-year period starting in 2013.
Last year’s contract awards include the estimated $4bn contract for the renewable energy and battery storage facility catering to the Neom green hydrogen project. Contracts for the 1.2GW third round of the kingdom’s National Renewable Energy Programme (NREP) and the Public Investment Fund's (PIF) 2.06GW Shuaibah 2 solar photovoltaic (PV) project were also awarded.
This has taken the overall capacity of solar projects under construction in Saudi Arabia to roughly 6,230MW, excluding the captive facility catering to the Neom green hydrogen project – a remarkable feat given that the kingdom has significantly lagged behind its renewable energy targets.
As of last year, the kingdom only has an estimated 842MW of renewable energy installed capacity, mainly from the 300MW Sakaka solar PV facility and 400MW Dumat al-Jandal wind farm.
This equates to just 3 per cent of its initial national goal to install 27.3GW of renewable energy capacity by 2024 and 1.4 per cent of its 2030 goal of 58.7GW.
The impact of the Covid-19 pandemic and war in Ukraine has affected the delivery of most of the projects, according to a Saudi-based expert, due to disrupted supply chains and global inflation.
“The Covid-19 pandemic affected projects not just in Saudi Arabia, but everywhere in the world,” he says.
Other experts insist that the kingdom needs to make an unprecedented adjustment to meet its ambitious 2030 target.
In response, state offtaker Saudi Power Procurement Company (SPPC) launched the procurement process last year for NREP’s fourth round.
Phase four comprises two solar PV IPP schemes with a total combined capacity of 1.5GW and three wind IPPs with a total combined capacity of 1.8GW. Bids for these contracts are due by April and May this year, respectively.
In early March, Germany-based ILF Consulting Engineers (ICE) also announced that it had been selected to undertake the pre-development studies for three solar PV parks in Saudi Arabia with a potential combined capacity of 30GW, the largest of its kind ever planned in the region, if not globally.
The locations and procurement timeline for the projects have not yet been announced, but the tendering process will most likely commence once the initial studies are complete, according to a source familiar with the projects.
Going nuclear
Saudi Arabia’s Finance Ministry’s disclosure that it received bids in late December last year for the contract to build the kingdom’s first nuclear power plant has also significantly raised the power generation sector’s momentum.
The entire project’s budget of roughly $33.5bn, as estimated by MEED Projects, accounts for over a third of the total value of planned and unawarded power generation projects across the kingdom.
The potential award of the nuclear power project – the initial phase of which is understood to be 2.8GW – is not expected to slow down the pace of contract awards for other power generation assets.
As previously stated, the kingdom’s energy diversification programme expects clean and renewable energy to account for half – up from roughly 1 per cent today – of its electricity production mix by 2030.
The long lead time to construct and develop a nuclear power plant could also mean the first reactor is not likely to be ready by the end of the decade.
While the kingdom has not disclosed the list of companies bidding for the project, there is mounting speculation that at least three companies, including Russia’s Rosatom, China National Nuclear Corporation and South Korea’s Kepco, may have submitted a proposal to develop the facility.
RELATED READ: Saudi nuclear move has geopolitical significance
Unlike the solar and wind energy projects, the results of the nuclear energy bids are expected to be announced only by the highest level of leadership within the kingdom due to the strategic and geopolitical importance of nuclear power.
Ramping up gas
In January, SPPC retendered contracts to develop its next gas-fired IPP projects. Initially comprising two projects, each with a capacity of 3.6GW, the Taiba and Al-Qassim IPPs were each split into two 1.8GW schemes, with bids for the four contracts due by mid-2023.
These are the first gas-fired power generation plants to be procured since 2016, when Saudi Arabia awarded the 1,500MW Fadhili IPP to a consortium led by France’s Engie.
Before the retender, SPPC received only a single bid for the 3.6GW Taiba IPP. Wary of net-zero carbon emission targets, many international utility developers declined to bid for the package citing insufficient decarbonisation provisions.
Despite this setback, SPPC sought consultants last year for the transaction advisory contract for its next round of CCGT projects, which will be developed using a build-own-operate model.
The two projects, to be located in Riyadh and Al-Khafji, will each have a design capacity of 3,600MW.
“It is a moving target,” a senior official with a utility developer said about the kingdom’s energy diversification goal.
Various official sources suggest that the country’s current installed power generation capacity stands at 80-90GW, with little to no publicly available figures in terms of the capacity forecast by 2030.
The original target to install 57.8GW of renewable energy capacity by the end of the decade vis-à-vis a goal for renewable energy to account for 50 per cent of the total implies that the 2030 figure could be around 110-120GW.
Keeping this in mind, and the need to retire ageing fossil fuel-fired fleets during the intervening period, appears to justify the need for the kingdom to build more gas-fired power plants while pursuing significant renewable and nuclear capacity.
In terms of attracting more bidders for its current and future CCGT schemes, much will depend on how SPPC and the Energy Ministry address developers’ concerns regarding measures to minimise carbon footprint at the same time as ensuring the assets’ long-term economic feasibility.
Exclusive from Meed
-
Bahrain keeps moving through a difficult year20 November 2026
-
Gulf needs $40bn of pipelines to bypass Hormuz20 November 2026
-
Riyadh gives bidders more time for aviation complex20 November 2026
-
Dar Global launches Trump project in Qatar20 November 2026
-
Saipem wins Egypt offshore drilling contract20 November 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Bahrain keeps moving through a difficult year20 November 2026
Commentary
Colin Foreman
EditorWhen Formula 1 cars took to the grid at Malaysia’s Sepang International Circuit on 4 October, they were racing in the Bahrain Grand Prix. The race, originally scheduled for April, was postponed because of the regional conflict. Rather than lose its place on the calendar, Bahrain backed a one-off arrangement to stage it in Southeast Asia as the Formula 1 Gulf Air Bahrain Grand Prix in Malaysia.
The episode captures Manama’s approach to 2026. With the Strait of Hormuz closed and the country’s airspace shut for 40 days, Bahrain has sought alternative routes to keep its economy moving.
Gulf Air relocated its hub to Saudi Arabia’s Dammam airport during the airspace closure, taking passengers by road across the King Fahd Causeway, and expects to report higher revenues this year than in 2025. Aluminium Bahrain (Alba) is running at about 80% of capacity, with 300-350 trucks a day delivering alumina using ports in Oman and Saudi Arabia. The company has also agreed the $2.2bn acquisition of the Aluminium Dunkerque smelter in France.
Project activity has continued. Gulf Petrochemical Industries Company has appointed Fluor and Honeywell for its planned Sitra aromatics complex. Bids for the $1.5bn Sitra independent water and power project are under evaluation.
Construction contract awards reached $737m by the end of October, already exceeding the total for 2025.
In early November, Manama went ahead with the fourth edition of the Gateway Gulf investment forum, which produced more than 110 announcements valued at over $20bn.
The cost of the regional conflict is nonetheless steep. The Washington-based IMF expects the economy to contract by 11.3% this year. Public debt reached BD20.3bn ($54bn) at the end of August, and foreign exchange reserves have been supported by a BD2bn ($5.3bn) currency swap line from the UAE.
Lasting recovery will depend on factors that lie largely beyond Bahrain’s control. The IMF is forecasting real GDP growth of 13.9% in 2027, but this is contingent on the reopening of Gulf trade routes and a return to normal levels of energy production.

MEED’s December 2026 report on Bahrain includes:
> GOVERNMENT: Bahrain creaks under the strain of war
> BANKING: Manama’s lenders hold out for better times
> OIL & GAS: GPIC’s expansion project lifts Bahrain’s energy sector
> POWER & WATER: Bahrain’s utility pipeline shows signs of progress
> CONSTRUCTION: Bahrain construction activity remains subduedTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21389640/main.gif -
Gulf needs $40bn of pipelines to bypass Hormuz20 November 2026
Register for MEED’s 14-day trial access
Gulf producers would need to spend about $40bn on new pipelines to route most of their oil exports around the Strait of Hormuz, according to the International Energy Agency (IEA).
The estimate, published in the agency's World Energy Outlook 2026, covers 6.8 million barrels a day (b/d) of export capacity that is either under construction or proposed in Saudi Arabia, the UAE and Iraq. The IEA calculates that the investment would add about $2 to the cost of each barrel exported from the Middle East.
The figure gives the clearest indication yet of the scale of the pipeline programme that could follow the 2026 crisis, which the IEA describes as the largest energy supply shock the world has faced. Oil volumes transiting the strait collapsed from 20 million b/d to an average of about 3 million b/d in March, April and May.
Project pipeline
The only scheme under construction in the IEA’s list is Abu Dhabi National Oil Company’s (Adnoc) West-East pipeline, which will add 1.8 million b/d of capacity. MEED has reported that the 520-kilometre line from Jebel Dhanna to Fujairah is being built in three sections. It is expected to double Adnoc’s crude export capacity through Fujairah when it is commissioned in 2027.
Separately, Adnoc expects to tender the main engineering, procurement and construction (EPC) contract for a new offshore line linking its Gulf processing islands to Jebel Dhanna, which will eventually connect to the West-East pipeline, by the end of the year.
The largest proposed project is a 3 million b/d expansion of Saudi Aramco’s East-West pipeline from Abqaiq to Yanbu on the Red Sea. Aramco president and CEO Amin Nasser has said engineering work began in the early days of the conflict. Saudi Energy Minister Prince Abdulaziz bin Salman said in October that the kingdom is looking to expand its crude export capacity by pipeline to as much as 10 million b/d.
In Iraq, the IEA counts two 1 million b/d lines from Haditha. One would run to Baniyas in Syria. The other would run to Fishkhabur, where it would link to the Iraq-Turkiye pipeline to Ceyhan. MEED has reported that a consortium led by Qatar’s UCC, including Chevron and TotalEnergies, is discussing terms for four interconnected pipeline packages worth about $5bn, with a contract expected to be signed before year-end. Iraq and Saudi Arabia are also considering reviving the 1,568km pipeline from Zubair to Yanbu, which was halted in 1990.
The agency says the new routes would not help all Gulf producers. Bahrain, Kuwait and Qatar would still depend on the strait for their exports.
Bypass flows
About 8 million b/d of bypass pipeline capacity is already available, according to the report. These lines carried about 2 million b/d in 2025 and ramped up to a peak of 6.8 million b/d during the crisis.
In the IEA’s Stated Policies Scenario (STEPS), only the Adnoc project is completed and bypass flows return to about 3 million b/d by 2035. If every existing, under-construction and proposed route were built and used to capacity, bypass flows could reach about 14.5 million b/d. Most Saudi and UAE exports, along with more than 60% of Iraq’s, would then avoid the strait.
The IEA’s new Low Hormuz Case adds higher output from producers outside the Gulf and demand cuts by importers. In that case, oil transit through the strait falls below 2 million b/d by 2035. Raising supply outside the strait would require about $200bn of additional upstream investment between 2025 and 2035.
Security caveats
The agency cautions that the pipelines would not remove the risk. Drone attacks temporarily shut the East-West pipeline in September, and any exports to the Red Sea must pass through the Bab Al-Mandab Strait. MEED has reported that Houthi attacks on Aramco’s Red Sea assets since July, including the Jizan refinery, have cost Riyadh that alternative route. Even in the Low Hormuz Case, the Middle East still exports nearly 15 million b/d in 2035, about 20% of global oil trade.
The IEA also notes that if the strait is at least partially open, Gulf producers would have few reasons not to use it. That could weaken the commercial case for the most expensive bypass schemes.
Execution risks are emerging in Iraq. MEED has reported that the Common Seawater Supply Project is behind schedule, largely because pipeline segments cannot easily be imported through the strait. The same problem could force contractors on new export lines to use more costly routes.
The IEA says there is no feasible bypass for liquefied natural gas (LNG). About 110 billion cubic metres of gas passed through the strait in 2025, most of it from Qatar. Adnoc is pursuing a 4 million tonne-a-year LNG export facility at Fujairah, fed by pipeline from Abu Dhabi. MEED has reported that it has selected three teams for front-end engineering and design work.
Cost pressures
The wider upstream picture is less encouraging for contractors. The IEA expects global upstream oil and gas investment to rise by about 1% to $550bn in 2026, with increases elsewhere largely offset by reductions in the Middle East. Its Upstream Capital Cost Index is forecast to rise by about 8% this year, which the agency says will raise the risk of overruns and delays.
The agency also warns that a resolution of the crisis could create a buyers’ market for oil and gas. Lower prices would test whether the security case for bypass pipelines survives once the strait reopens.
https://image.digitalinsightresearch.in/uploads/NewsArticle/21612651/main.jpg -
Riyadh gives bidders more time for aviation complex20 November 2026

Contractors have been given an extension until 31 January to submit proposals for an estimated SR3bn ($817m) contract to build an aviation complex within the King Salman International airport master development in Riyadh.
Government-owned aviation organisation Saudi Royal Aviation (SRA) tendered the contract in August, with an initial bid submission deadline of 8 October, which was later extended to 19 November.
Phase one of the programme comprised the concept design stage, which the design consultant has completed.
SRA is now seeking to deliver the second phase, covering design development, detailed design, procurement, construction, testing, commissioning and close-out of the works.
The scope covers 30 landside buildings, including 16 screening areas and gates, plus 15 airside buildings, including four gates.
The assets include maintenance hangars, workshops, office and administrative buildings (including interior fit-out), warehouses, storage, security and catering facilities, aprons and access roads, and site utilities and civil works.
King Salman International airport will provide primary utilities to designated tie-in points, with the contractor taking responsibility from there.
Although the site is within King Salman International airport’s boundaries, it is classified as landside and is a greenfield development. The contractor must therefore meet airport security, safety and access requirements, in addition to SRA’s own clearance processes.
Project scale
The King Salman International airport project covers an area of about 57 square kilometres (sq km), allowing for six parallel runways, and will include the existing terminals at King Khalid International airport. It will also include 12 sq km of airport support facilities, residential and recreational facilities, retail outlets and other logistics real estate.
The airport aims to accommodate up to 100 million passengers by 2030. The goal for cargo is to process 2 million tonnes a year by 2030.
Saudi Arabia plans to invest significantly in its aviation sector. The Saudi Aviation Strategy, announced by the General Authority of Civil Aviation, aims to triple Saudi Arabia’s annual passenger traffic to 330 million travellers by 2030.
It also aims to increase air cargo traffic to 4.5 million tonnes and raise the country’s total air connections to more than 250 destinations.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21611358/main.png -
Dar Global launches Trump project in Qatar20 November 2026
London-listed developer Dar Global and The Trump Organisation have launched the QR2.5bn ($686m) Trump International Simaisma development in Qatar.
The project combines beachfront residences, a golf course and lifestyle amenities, according to senior company officials speaking at a launch ceremony in Palm Beach, Florida.
The residential element, Trump Residences, will comprise a gated community of three-, four- and five-bedroom branded villas. Each villa will have beach access and views of the sea and golf course.
The development will also include the Trump International Golf Club, Simaisma, Qatar, anchored by an 18-hole championship golf course, a members-only clubhouse and a beach club.
A private community centre will provide sports, recreation and wellness facilities for residents.
The project forms part of Qatar’s wider Simaisma tourism development, launched by Qatar’s Ministry of Municipality in June 2024.
The Simaisma project covers eight square kilometres and extends along seven kilometres of beachfront on Qatar’s eastern coast, north of Doha. It includes 16 tourism zones available for private sector development, with planned resorts, a theme park, an 18-hole golf course, residential villas, a yacht marina, restaurants and retail facilities.
Qatari Diar Real Estate Investment Company is managing the wider development.
The integrated tourism project supports the objectives of Qatar’s Third National Development Strategy 2024-30, which aims to increase the contribution of non-oil sectors to the economy.
The launch extends the partnership between Dar Global and The Trump Organisation into Qatar.
Dar Global develops luxury residential and hospitality projects across Europe and the Middle East.
As of 30 June 2026, Dar Global’s portfolio had a total gross development value of $23bn, the company said.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21609076/main.jpeg -
Saipem wins Egypt offshore drilling contract20 November 2026
Italy’s Saipem has been awarded an offshore drilling contract for three oil and gas wells in Egypt, according to a company statement.
Burullus Gas Company, a joint venture of UK-based Shell, Malaysia’s Petronas and the state-owned Egyptian General Petroleum Corporation (EGPC), awarded the contract.
The operations are scheduled to begin in the first quarter of 2027 and will use the semi-submersible unit Scarabeo 9.
In the same statement, Saipem also said it had been awarded a separate contract by France’s TotalEnergies to drill in Suriname with the same semi-submersible unit, once the campaign in Egypt was completed.
Saipem said the two contracts were worth approximately $181m in total.
In its statement, the Italian company said: “These new awards bolster the backlog for Saipem’s offshore drilling fleet, ensuring operational continuity and greater visibility regarding the utilisation of the Scarabeo 9 throughout 2027 and 2028, while strengthening the long-standing partnerships with Burullus Gas Company and TotalEnergies.”
Since the US and Israel attacked Iran on 28 February, sparking a regional conflict, there has been increased interest in oil and gas assets in North African countries such as Egypt.
The ongoing conflict has made exporting oil and gas through the Strait of Hormuz and the Bab Al-Mandab Strait more difficult due to attacks on shipping.
Unlike many Middle East nations, Egypt, Algeria and Libya do not need to use these export routes and can continue to ship oil and gas without disruption.
READ THE NOVEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFGulf projects keep moving amid conflict; UAE's state spending and oil output flexibility cushion Iran war shock; Project finance lenders weigh risk against infrastructure needs.
Distributed to senior decision-makers in the region and around the world, the November 2026 edition of MEED Business Review includes:
> AGENDA: GCC projects market holds its nerve> MARKET FOCUS: UAE economy shows resilience> INDUSTRY REPORT: Project financiers hold the line> STADIUMS: Stadium spending set to jump 39% in 2027> CONFLICT: Hormuz closure wipes out growth in 2026> INTERVIEW: WSP regional president Dean McGrail> INTERVIEW: Ministry of Energy & InfrastructureTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/21597235/main.jpg
