Saudi Arabia moves nuclear bid deadline

2 November 2023

Saudi Arabia's Duwaiheen Nuclear Energy Company has extended the tendering process for the contract to build the kingdom's first large-scale nuclear power plant facility.

According to a source close to the project, the client expects to receive proposals for the contract by 31 December, two months later than the previous bid submission deadline.

Companies that have been invited and are expected to bid for the contract include:

  • China National Nuclear Corporation (CNNC, China)
  • Korea Electric Power Corporation (Kepco, South Korea)
  • Rosatom (Russia) 
  • EDF Group (France)

    Neither King Abdullah City for Atomic and Renewable Energy (KA-Care) nor the apparent bidders have confirmed the bidders list.

    The project is in the so-called bid invitation specification stage, and there are no direct negotiations taking place between the client and the potential bidders at this stage, as MEED reported in July.

    Saudi Arabia plans to build a large-scale nuclear power plant facility as part of its energy diversification agenda. 

    Earlier this month, a source close to the project said the ongoing conflict in Gaza is not likely to help advance negotiations between the countries with a key stake in the project.

    Consultants

    Duwaiheen Nuclear Energy Company this year received three bids for the project management consultancy package for the nuclear plant project.

    MEED understands the following companies submitted proposals for the contract:

    • Atkins (UK/Canada)
    • Worley (Australia)
    • Assystems (France)

    Two of the three bidders have had previous engagements with the Saudi nuclear energy project. 

    In July 2018, France’s Assystem was appointed to conduct a site characterisation study, environmental impact assessment and preliminary safety analysis report to assist with the selection of the preferred site for the kingdom’s first planned nuclear power project.

    A site at Khor Duwaiheen, on the coast near the UAE and Qatari borders, was subsequently chosen for the first project.

    The same year, KA-Care appointed Worley for the project management office consultancy role for the nuclear energy programme. Worley is understood to have previously completed the Large Nuclear Power Plant (LNPP) site selection study for KA-Care.

    KA-Care also awarded three separate contracts for the project's legal, technical and financial advisory works.  It awarded a team led by UK-headquartered EY the financial advisory contract in May 2022. Legal and technical consultancy contracts for the project were signed earlier. 

    2.8GW project

    The Duwaiheen nuclear power plant is expected to be procured using a traditional design-and-build model. 

    In September 2016, MEED reported that Saudi Arabia was carrying out technical and economic feasibility studies for the first reactors, and was also looking at possible locations for the kingdom’s first nuclear project, a 2.8GW facility.

    In March 2022, Saudi Arabia announced the establishment of a holding company – understood to be the Duwaiheen Nuclear Energy Company – to develop nuclear power projects in the country to produce electricity, desalinate seawater and support thermal energy applications. 

    Related reads: 

    Prince Abdullah bin Khalid bin Sultan, Saudi ambassador to Austria and permanent representative to the International Atomic Energy Agency (IAEA), said at the time that the kingdom was working on a framework programme for nuclear energy in 2022-27, which includes “capacity building and collaboration with international institutes for research and development”.

    This followed Saudi Energy Minister Prince Abdulaziz bin Salman al-Saud's announcement in January 2022 that Saudi Arabia has uranium resources that it wants to exploit transparently through partnerships.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11265079/main.gif
    Jennifer Aguinaldo
    Related Articles
    • Public Investment Fund backs Neom

      16 April 2026

      Commentary
      Colin Foreman
      Editor

      Register for MEED’s 14-day trial access 

      Saudi Arabia’s Public Investment Fund (PIF) has backed Neom by including it as one of six strategic ecosystems in its newly approved 2026-30 strategy.

      The future of the $500bn gigaproject had been thrown into doubt following the postponement of the 2029 Asian Winter Games at the Trojena mountain resort, the cancellation of construction contracts – such as the $5bn deal with Italian contractor Webuild for dam works at Trojena – and the slowdown of development at The Line, where tunnelling contracts were cancelled and staff left the project.

      The backing comes as Neom’s operational focus appears to be evolving in response to shifting regional dynamics and global economic conditions. For example, on 15 April Neom posted on its official X account about a new Europe-Egypt-Neom-GCC corridor, describing it as a faster route for time-sensitive goods. It said the corridor combines trucking and ferry services to move goods quickly into the Gulf, adding that importers from several European markets are already using it to reach the UAE, Kuwait, Iraq, Oman and beyond.

      Powered by Pan Marine, DFDS and regional RoPax services, the initiative is positioned as a way to add flexibility and resilience to regional supply chains. This emphasis on logistics and immediate trade utility suggests a shift away from the more speculative architectural announcements that characterised Neom’s early years, towards activity more directly tied to current market realities.

      PIF’s broader 2026-30 strategy places heavy emphasis on “delivering competitive domestic ecosystems to connect sectors, unlock the full potential of strategic assets, maximise long-term returns and continue to drive the economic transformation of Saudi Arabia”.

      The inclusion of Neom as a standalone ecosystem within the Vision Portfolio suggests that while the project remains part of the kingdom’s Vision 2030 goals, it will be subject to the fund's focus on working with the private sector.

      That means the long-term success of Neom will increasingly depend on its ability to attract external investment and function as a viable economic hub rather than just a state-funded construction site.


      MEED’s April 2026 report on Saudi Arabia includes:

      > COMMENT: Risk accelerates Saudi spending shift
      > GVT &: ECONOMY: Riyadh navigates a changed landscape
      > BANKING: Testing times for Saudi banks
      > UPSTREAM: Offshore oil and gas projects to dominate Aramco capex in 2026
      > DOWNSTREAM: Saudi downstream projects market enters lean period
      > POWER: Wind power gathers pace in Saudi Arabia

      > WATER: Sharakat plan signals next phase of Saudi water expansion
      > CONSTRUCTION: Saudi construction enters a period of strategic readjustment
      > TRANSPORT: Rail expansion powers Saudi Arabia’s infrastructure push

      To see previous issues of MEED Business Review, please click here
      https://image.digitalinsightresearch.in/uploads/NewsArticle/16417262/main.jpeg
      Colin Foreman
    • Kuwait gas project worth $3.3bn put on hold

      16 April 2026

       

      State-owned Kuwait Gulf Oil Company’s (KGOC’s) planned tender for the development of an onshore gas plant next to the Al-Zour refinery has been put on hold due to uncertainty created by the US and Israel’s war with Iran, according to industry sources.

      The project budget is estimated to be $3.3bn, and the last meeting with contractors to discuss the project took place in Kuwait on 10 February.

      Previously, it was expected to be tendered in late March, but the tendering process was delayed due to the regional conflict and disruption to shipping through the Strait of Hormuz.

      One source said: “This tender is now effectively on hold while KGOC waits for increased stability in the region before it invites companies to bid for the contract.”

      Under current plans, the plant will have the capacity to process up to 632 million cubic feet a day of gas and 88.9 million barrels a day of condensates from the Dorra offshore field, located in Gulf waters in the Saudi-Kuwait Neutral Zone.

      Ownership of the field is disputed by Iran, which refers to the field as Arash.

      Iran claims the field partially extends into Iranian territory and asserts that Tehran should be a stakeholder in its development.

      It is believed that the Dorra field’s close proximity to Iran will make development difficult due to the current security environment.

      The offshore elements of the project are expected to be especially difficult to protect from attacks from Iran.

      In July last year, MEED reported that KGOC had initiated the project by launching an early engagement process with contractors for the main engineering, procurement and construction tender.

      France-based Technip Energies completed the contract for the front-end engineering and design.


      READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

      Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

      Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

      > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
      To see previous issues of MEED Business Review, please click here
      https://image.digitalinsightresearch.in/uploads/NewsArticle/16413221/main.png
      Wil Crisp
    • Iraq pushes to revive oil pipeline through Saudi Arabia

      16 April 2026

      Iraq is pushing to revive an oil pipeline that passes through Saudi Arabia, allowing it to diversify export routes.

      Saheb Bazoun, a spokesman for Iraq’s Oil Ministry, said the pipeline would help to insulate Iraq from any future blockades of the Strait of Hormuz, which has been largely closed since 28 February.

      The original pipeline through Saudi Arabia has not been used for more than 30 years and would need work to be done in order to bring it online.

      It is 1,568km long, extending from the city of Zubair in Iraq to the Saudi port of Yanbu on the Red Sea.

      The pipeline was built in two phases during the 1980s. The first phase stretches between Zubair and Khurais, while the second extends to Yanbu. The pipeline’s operating capacity reached over 1.6 million barrels a day (b/d).

      Following the Gulf War, the pipeline was shut down in August 1990. It has remained out of operation for decades, despite Iraq’s several attempts to restart it.

      The original pipeline project cost over $2.6bn, including storage tanks and loading terminals.

      In the wake of the US and Israel attacking Iran on 28 February, global markets have lost 11 million barrels a day (b/d) of oil supply due to the effective closure of the Strait of Hormuz.


      READ THE APRIL 2026 MEED BUSINESS REVIEW – click here to view PDF

      Economic shock threatens long-term outlook; Riyadh adjusts to fiscal and geopolitical risk; GCC contractor ranking reflects gigaprojects slowdown.

      Distributed to senior decision-makers in the region and around the world, the April 2026 edition of MEED Business Review includes:

      > GCC CONTRACTOR RANKING: Construction guard undergoes a shift
      To see previous issues of MEED Business Review, please click here
      https://image.digitalinsightresearch.in/uploads/NewsArticle/16413290/main.jpg
      Wil Crisp
    • Algeria opens bidding for water treatment plant

      15 April 2026

       

      State-owned Cosider Pipelines, part of Algeria’s public infrastructure group Cosider, has issued a tender for the construction of a demineralisation plant in In Salah in Algeria.

      The contract covers the design, supply, installation, testing and commissioning of a plant with a treatment capacity of 62,000 cubic metres a day (cm/d).

      The tender is open to local and international companies specialising in the design and construction of demineralisation and reverse osmosis desalination plants.

      The bid submission deadline is 26 April.

      The project will be located at In Salah, a key industrial area in southern Algeria, where treated water supply is important for both municipal and industrial use.

      Cosider said that individual bidders must demonstrate that they have completed at least one reverse osmosis demineralisation or desalination plant with a capacity of 20,000 cubic metres a day or more.

      They must also show an average annual turnover of at least AD1bn ($7.7m) for their five best years over the past decade.

      For consortium bids, all partners must share full responsibility for the contract, while the lead company must meet the technical and financial requirements.

      Recent projects

      In 2023, MEED reported that Riyadh-based water utility developer Wetico had won two contracts to develop water desalination plants in Algeria.

      Societe Algerienne de Realisation de Projects Industriels (Sarpi) awarded the contract for the El-Tarf desalination plant, while Entreprise Nationale de Canalisations (Enac) is the client for the Bejaja facility.

      Both plants were commissioned in 2025, each with a production capacity of 300,000 cm/d.

      Separately, Wetico was the main contractor on a third plant commissioned last year. The Cap Dijinet 2 seawater desalination plant in Boumerdes province covers 18 hectares and also has a capacity of 300,000 cm/d.

      Like many countries, Algeria is facing pressure on resources due to longer and more frequent droughts. Seawater desalination is seen as a key driver of the government’s strategy to guarantee drinking water supply.

      According to previous reports, the government is planning to build up to six additional plants by 2030.

      https://image.digitalinsightresearch.in/uploads/NewsArticle/16404325/main.jpg
      Mark Dowdall
    • WEBINAR: UAE Projects Market 2026

      15 April 2026

      Webinar: UAE Projects Market 2026
      Tuesday, 28 April 2026 | 11:00 GST  |  Register now


      Agenda:

      • Overview of the UAE projects market landscape
      • 2025 projects market performance
      • Value of work awarded 2026 YTD
      • Impact of the Iran conflict on the projects market and real estate, assessing supply chain disruptions, material cost inflation and war risk premiums
      • Key drivers, challenges and opportunities
      • Size of future pipeline by sector and status
      • Ranking of the top contractors and clients
      • Summary of key current and future projects
      • Short and long-term market outlook
      • Audience Q&A

      Hosted by: Colin Foreman, editor of MEED 

      Colin Foreman is editor and a specialist construction journalist for news and analysis on MEED.com and the MEED Business Review magazine. He has been reporting on the region since 2003, specialising in the construction sector and its impact on the broader economy. He has reported exclusively on a wide range of projects across the region including Dubai Metro, the Burj Khalifa, Jeddah Airport, Doha Metro, Hamad International airport and Yas Island. Before joining MEED, Colin reported on the construction sector in Hong Kong.

      Click here to register

      https://image.digitalinsightresearch.in/uploads/NewsArticle/16401868/main.gif
      Colin Foreman