Saudi Arabia moves nuclear bid deadline

2 November 2023

Saudi Arabia's Duwaiheen Nuclear Energy Company has extended the tendering process for the contract to build the kingdom's first large-scale nuclear power plant facility.

According to a source close to the project, the client expects to receive proposals for the contract by 31 December, two months later than the previous bid submission deadline.

Companies that have been invited and are expected to bid for the contract include:

  • China National Nuclear Corporation (CNNC, China)
  • Korea Electric Power Corporation (Kepco, South Korea)
  • Rosatom (Russia) 
  • EDF Group (France)

    Neither King Abdullah City for Atomic and Renewable Energy (KA-Care) nor the apparent bidders have confirmed the bidders list.

    The project is in the so-called bid invitation specification stage, and there are no direct negotiations taking place between the client and the potential bidders at this stage, as MEED reported in July.

    Saudi Arabia plans to build a large-scale nuclear power plant facility as part of its energy diversification agenda. 

    Earlier this month, a source close to the project said the ongoing conflict in Gaza is not likely to help advance negotiations between the countries with a key stake in the project.

    Consultants

    Duwaiheen Nuclear Energy Company this year received three bids for the project management consultancy package for the nuclear plant project.

    MEED understands the following companies submitted proposals for the contract:

    • Atkins (UK/Canada)
    • Worley (Australia)
    • Assystems (France)

    Two of the three bidders have had previous engagements with the Saudi nuclear energy project. 

    In July 2018, France’s Assystem was appointed to conduct a site characterisation study, environmental impact assessment and preliminary safety analysis report to assist with the selection of the preferred site for the kingdom’s first planned nuclear power project.

    A site at Khor Duwaiheen, on the coast near the UAE and Qatari borders, was subsequently chosen for the first project.

    The same year, KA-Care appointed Worley for the project management office consultancy role for the nuclear energy programme. Worley is understood to have previously completed the Large Nuclear Power Plant (LNPP) site selection study for KA-Care.

    KA-Care also awarded three separate contracts for the project's legal, technical and financial advisory works.  It awarded a team led by UK-headquartered EY the financial advisory contract in May 2022. Legal and technical consultancy contracts for the project were signed earlier. 

    2.8GW project

    The Duwaiheen nuclear power plant is expected to be procured using a traditional design-and-build model. 

    In September 2016, MEED reported that Saudi Arabia was carrying out technical and economic feasibility studies for the first reactors, and was also looking at possible locations for the kingdom’s first nuclear project, a 2.8GW facility.

    In March 2022, Saudi Arabia announced the establishment of a holding company – understood to be the Duwaiheen Nuclear Energy Company – to develop nuclear power projects in the country to produce electricity, desalinate seawater and support thermal energy applications. 

    Related reads: 

    Prince Abdullah bin Khalid bin Sultan, Saudi ambassador to Austria and permanent representative to the International Atomic Energy Agency (IAEA), said at the time that the kingdom was working on a framework programme for nuclear energy in 2022-27, which includes “capacity building and collaboration with international institutes for research and development”.

    This followed Saudi Energy Minister Prince Abdulaziz bin Salman al-Saud's announcement in January 2022 that Saudi Arabia has uranium resources that it wants to exploit transparently through partnerships.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11265079/main.gif
    Jennifer Aguinaldo
    Related Articles
    • Egypt strengthens its economic position

      4 March 2026

      https://image.digitalinsightresearch.in/uploads/NewsArticle/15858071/main.gif
      MEED Editorial
    • Power and water assets face strategic risk amid Iran attacks

      4 March 2026

       

      Recent attacks on energy infrastructure across the GCC have drawn renewed attention to the strategic importance of the region’s power and water sector.

      On 2 March, Qatar’s Ministry of Defence announced that the country had come under two drone attacks launched from Iran.

      One drone targeted a water tank owned by Mesaieed Power Plant, while another targeted a power facility in Ras Laffan Industrial City.

      Elsewhere in the region, Saudi Aramco shut down its Ras Tanura refinery following a drone strike, while US cloud provider Amazon Web Services reported service outages after incidents at two data centres in the UAE.

      Desalination reliance

      Across the GCC, desalination now provides the majority of drinking water. In Kuwait, about 90% of potable water comes from desalination plants, while the figure is about 70% in Saudi Arabia. In the UAE and Oman, the figures are 42% and 86%, respectively. While the geopolitical narrative tends to be dominated by oil, it is power and water infrastructure that is perhaps most critical to everyday life.

      For instance, the Ras Al-Khair desalination plant in Saudi Arabia is among the largest operational facilities of its kind. According to MEED Projects, the plant produces about 1.1 million cubic metres a day (cm/d) of desalinated water.

      Using a typical domestic water consumption benchmark of roughly 250 litres per person per day, that output is sufficient to supply potable water for around four million people.

      Other large projects operate on a similar scale. The Yanbu phase 3 desalination plant produces roughly 550,000 cm/d, while the Shuaibah 3 independent water project (IWP), commissioned near Jeddah last year, has a capacity of 600,000 cm/d. Facilities of this scale can supply drinking water to populations of between two million and four million people.

      The region’s reliance on large coastal desalination facilities also creates structural vulnerabilities, as most plants are located along the Gulf coastline to allow seawater intake.

      Many are also integrated with thermal power plants, producing electricity and desalinated water at the same site. This configuration offers operational efficiencies, but concentrates critical infrastructure in a limited number of locations.

      In February, Kuwait signed a 25-year energy conversion and water purchase agreement for the Al-Zour North independent water and power plant (IWPP) phases two and three. Once completed, the facility will add 2,700MW of power and 545,000 cm/d of desalinated water to Kuwait’s supply network

      Separately, Kuwait’s Council of Ministers recently approved plans for the Kuwait Authority for Partnership Projects (Kapp) to tender the first phase of the Nuwaiseeb power and water desalination plant as an IWPP project. The first phase of the scheme will have an estimated power generation capacity of 3,600MW and a desalination capacity of 341,000 cm/d.

      While several GCC states maintain strategic water storage reserves, these typically cover only a limited number of days of consumption in major cities. This makes water infrastructure one of the most sensitive categories of critical assets in the region.

      Electricity infrastructure

      Standalone electricity infrastructure is equally central to the functioning of GCC economies. Power generation supports residential demand, large industrial complexes, transport networks and digital infrastructure.

      One example is the UAE’s Barakah nuclear power plant in Abu Dhabi, which has a total capacity of 5.6GW across four reactors. According to Emirates Nuclear Energy Corporation (Enec), the plant’s four APR1400 reactors produce 40TWh annually, which is equivalent to around 25% of the UAE’s electricity needs.

      At the same time, Gulf electricity systems are becoming increasingly interconnected. The GCC Interconnection Authority grid links the national networks of member states and enables countries to exchange electricity during periods of peak demand or supply disruption.

      According to WorldBank studies, desalination plants typically operate continuously because water storage capacity is limited relative to demand. Similarly, power grids must balance supply and demand in real time.

      Amid ongoing missile and drone attacks on GCC states, Iran said on Monday that it was closing off the Strait of Hormuz, a critical maritime route. GCC countries import roughly 85% of their food, much of it transported by sea, while the strait handles about a fifth of global oil supply. Disruptions to power and water infrastructure across the region could have even more immediate consequences.


      READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDF

      Riyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.

      Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:

      To see previous issues of MEED Business Review, please click here
      https://image.digitalinsightresearch.in/uploads/NewsArticle/15856956/main.jpg
      Mark Dowdall
    • Algeria tenders multiple railway consultancy contracts

      4 March 2026

      Algeria’s state railway company, Agence Nationale d’Etudes et de Suivi de la Realisation des Investissements Ferroviaires (Anesrif), has tendered several consultancy tenders for various railway schemes in the country.

      The first tender was issued for the study of the new Bouinane/Meftah/Khemis El-Khechna railway line.

      The tender was issued on 3 March, with a bid submission deadline of 12 April.

      The second tender covers the detailed study of the Sidi Arcine railway station.

      The tender for the project was floated on 1 March. The bid submission deadline is 30 March.

      The other tender covers the completion of the study of the Zeralda/Gouraya railway line.

      The notice was floated in late February, with a bid submission deadline of the end of March.

      The latest consultancy tenders follow Anesrif’s formal start of the procurement process for its multibillion-dollar Laghouat-Ghardaia-El-Meniaa railway project, as MEED reported earlier this week.

      International and local firms have been given until 8 March to submit expressions of interest for the overall client’s engineer role on the 495-kilometre-long railway development.

      Consultancies have also been given until 12 March for two separate contracts covering the project supervision and control of the first 265km-long element between Laghouat and Ghardaia, and the 230km-long line between Ghardaia and El-Meniaa.

      This Laghouat-Ghardaia section, which is estimated to cost about $1.4bn, will comprise 21 viaducts, one tunnel, 55 pipe crossings and five stations.

      The 230km-long Ghardaia to El-Meniaa second section will start at Metlili station and extend south to El-Meniaa. It will comprise six viaducts, 35 railway structures and three stations, and have an estimated total construction cost of about $1.2bn.

      The speed of passenger trains on the railway will be 220 kilometres an hour (km/h) and 100km/h for freight trains.

      The solicitations of interest for the construction of the two sections were originally scheduled for February, but to date have not been released.


      READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDF

      Riyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.

      Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:

      To see previous issues of MEED Business Review, please click here
      https://image.digitalinsightresearch.in/uploads/NewsArticle/15855965/main.jpg
      Yasir Iqbal
    • Conflict has limited impact on GCC projects

      4 March 2026

       

      Register for MEED’s 14-day trial access 

      The conflict in the Gulf has so far had a limited impact on projects in the GCC, with most sites operating normally since hostilities began on 28 February. In total, there are 6,738 projects under execution across the GCC, with a combined value of $951bn, according to regional projects tracker MEED Projects.

      Contracting companies in the region say that the majority of their projects have not been affected by the conflict, and work has continued onsite without disruption. However, a few sites have temporarily halted operations, either at the request of the authorities or because they were considered at risk due to their strategic locations.

      “Work has continued on our projects in Dubai. We have only one site where we were asked to stop work,” says a contractor overseeing projects across Dubai.

      Another contractor operating across the UAE has also continued work but halted operations at one site following a nearby security incident. “We have one site that was close to a facility that was struck by debris, so we stopped work,” the contractor says.

      Work has also continued on projects outside of the UAE. In Saudi Arabia and Qatar, contractors continue to work on projects, including strategically sensitive oil and gas projects. “We have continued work on most of our projects. There are a few sites where we have been asked to stop work, but this is the minority, and at most sites we are still working,” says an international contractor.

      Supply chain concerns

      While operations largely continue as normal, there are concerns that projects could be impacted later due to supply chain disruption. Ports in the region have been targets, and with international shipping passing through the Strait of Hormuz effectively stopping, there is an expectation that international shipments will be delayed. A related concern is the sharp spike in oil prices that will be inflationary.

      How the disruption is handled will depend on the terms of specific contracts and on how companies choose to navigate the issue. The general consensus among contractors and lawyers is that it is not a force majeure event. Instead, it is general disruption that should be noted and documented, should there be cost or time implications later in the project.

      One Dubai-based contractor said the strategy for now is to support clients as best as possible amid this uncertainty, while noting that there may be cost implications later.

      The region has been considered a safe place for tourism, and also for the rich to live in a tax-free haven. The attacks on Dubai may change that perception, and that will impact the market in the future
      International contractor

      Future prospects

      There are also concerns about the market’s future. There have been record levels of contract awards in recent years, and the worry is that the pace of contract awards may slow as uncertainty grips the market.

      At the same time, some contract awards have been expedited. One Dubai-based contractor has signed two contracts since the conflict started. “We have signed deals that had been lingering for a while. I think the logic is that the client wants to lock in resources before prices or anything else changes,” says the contractor.

      Longer term, it is expected that priorities for construction could shift. Contractors say that defence will become more of a priority for governments in the future, and so will strategic infrastructure projects such as power and water.

      There might also be increased interest in making infrastructure more secure, which will add an additional layer of complexity for construction companies. “Facilities like data centres may be located underground in the future to protect them from attacks,” says a UAE-based contractor.

      The outlook for other sectors is more challenged, particularly real estate and tourism.

      “The region has been considered a safe place for tourism, and also for the rich to live in a tax-free haven,” says the international contractor. “The attacks on Dubai may change that perception, and that will impact the market in the future. Tourism is a key component of national visions across the GCC, so I think there will have to be a rethink of economic strategies for the future.”


      READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDF

      Riyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.

      Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:

      To see previous issues of MEED Business Review, please click here
      https://image.digitalinsightresearch.in/uploads/NewsArticle/15855051/main.jpg
      Colin Foreman
    • Contractors begin Riyadh metro Line 2 extension works

      4 March 2026

      Contractors have started construction on two new metro stations within King Saud University, as part of the Riyadh Metro Line 2 extension.

      In a statement published on its website, the Royal Commission for Riyadh City (RCRC) said that the first station will serve the University Medical City and health colleges, and the second station will serve the university concourse.

      In July last year, MEED exclusively reported that RCRC had awarded an estimated $800m-$900m contract for the project.

      The contract was awarded to the Arriyadh New Mobility Consortium, led by Italy’s Webuild. 

      The group also includes India’s Larsen & Toubro, Saudi Arabia’s Nesma & Partners and France’s Alstom.

      The Line 2 extension is 8.4 kilometres (km) long, of which 1.3km is elevated and 7.1km is underground. It includes five stations – two elevated and three underground.

      It will run from where Line 2 currently ends at King Saud University, then travel to new stations at KSU Medical City, KSU West and Diriyah East, where it interchanges with the planned Line 7, and finally to Diriyah South.

      In 2013, the Arriyadh New Mobility Consortium secured Riyadh Metro’s Line 3 project for $5.21bn.

      Line 3, also known as the Orange Line, stretches from east to west, from Jeddah Road to the Second Eastern Ring Road, covering a total distance of 41km. 


      READ THE MARCH 2026 MEED BUSINESS REVIEW – click here to view PDF

      Riyadh urges private sector to take greater role; Chemical players look to spend rationally; Economic uptick lends confidence to Cairo’s reforms.

      Distributed to senior decision-makers in the region and around the world, the March 2026 edition of MEED Business Review includes:

      To see previous issues of MEED Business Review, please click here
      https://image.digitalinsightresearch.in/uploads/NewsArticle/15855032/main.png
      Yasir Iqbal