Saudi Arabia launches 200 PPP projects

6 April 2023

Saudi Arabia has announced a Privatisation & PPP (P&PPP) pipeline that includes 200 projects across 17 sectors.

This new P&PPP pipeline aims to attract local and international investors and ensure their readiness to participate in the schemes tendered to the market.

The initiative comes as the kingdom strives to increase the attractiveness of its economy and raise the private sector's contribution to GDP.

Minister of Finance and chairman of the Board of the National Centre for Privatisation & PPP (NCP), Mohammed al-Jadaan, said the list of projects aligns with the aims of Vision 2030, reinforces the strength of public-private partnerships (PPPs) and will contribute to attracting new international investments.

The pipeline of projects for each sector will be available for investors through the NCP portal.

Information about the first 140 projects has already been published, and more projects are expected soon.

Four PPP airports projects

In line with Saudi Arabia's aviation strategy to increase the country’s annual passenger handling capacity to 330 million by 2030, the kingdom has announced plans to tender four airports under the P&PPP pipeline: Abha International airport, Taif International airport, Hail International airport and Prince Naif International airport in Al-Qassim.

The Ministry of Transport & Logistics Services will procure the schemes.

The launch dates for the PPP tenders were not specified. However, MEED reported in July 2022 that through NCP, Saudi Arabia’s Matarat Holding Company was expected to start the procurement process to develop airport PPP projects in 2023.

In the initial plan, the Abha and Taif airport PPPs were scheduled to be tendered in the first half of 2023, while the Hail and Qassim airport projects were to be potentially tendered in the second half of 2023.

The P&PPP pipeline list includes:

Abha International airport

The existing Abha International airport is operating above capacity with 4.4 million passengers annually against the originally designed capacity of 1.5 million. The targeted capacity for the new airport is 8.5 million passengers a year by 2030 and 13 million passengers by 2053. The contract type is the build-transfer-operate (BTO) model and the project duration is 30 years.

Taif International airport

The capacity of the current Taif International airport is 600,000 passengers. The targeted capacity of the new airport is 4 million passengers by 2030 and 7.4 million passengers by 2053. The project will be developed under the design-build-finance-operate-maintain (DBFOM) concession; its duration is 30 years.

Hail International airport

This project aims to develop the airport and service facilities following the standards approved by the International Civil Aviation Organisation (ICAO). The targeted airport capacity increase is 3 million passengers a year. The contract type, duration and launch details are not specified.

Prince Naif International airport in Al-Qassim

The scheme involves developing the airport in Al-Qassim in line with ICAO standards and increasing its capacity to 5.3 million passengers annually. The contract type, duration and launch details are not specified.

The Taif, Hail and Al-Qassim airport schemes were previously tendered and awarded as PPP projects using a BTO model.

Saudi Arabia’s General Authority of Civil Aviation (Gaca) awarded the contracts to develop four airport PPP projects to two consortiums in 2017. A team of Tukey’s TAV Airports and the local Al-Rajhi Holding Group won the 30-year concession agreement to build, transfer and operate airport passenger terminals in Yanbu, Qassim and Hail.

A second team, comprising Lebanon’s Consolidated Contractors Company, Germany’s Munich Airport International and local firm Asyad Group, won the BTO contract to develop Taif International airport.

These projects then stalled following the restructuring of the kingdom’s aviation sector.

Saudi Arabia has already privatised airports including the $1.2bn Prince Mohammed bin Abdulaziz International airport in Medina, which was developed as a PPP and opened in 2015.

Four PPP highways schemes

The kingdom has also announced plans to tender four highway schemes under the P&PPP pipeline. The following schemes will be procured by the Ministry of Transport & Logistic Services:

  • The 136-kilometre Asir-Jizan highway will include six intersections, 18km of bridges and a 9km-long tunnel network. The project starts at Al-Farah in Asir and extends to the Red Sea through Jizan. The contract type is DFBOM, and the project duration is 30 years. The launch date is not specified.

     
  • The 570km Jeddah-Jizan highway will comprise 43 intersections, 11 wildlife crossings and 29 bridges. The project scope includes converting the current 280km of double lanes into three lanes. The contract model is not specified; the project duration is 30 years.

     
  • The 447km Yanbu-Jubail highway will contain 17 intersections, 14 wildlife crossings, four bridges, one tunnel and 18 service areas. Construction work on a 39km section towards the Al-Zulfi area has been completed. The contract model, duration and launch date are not specified.

     
  • The Jeddah-Makkah road spans a length of 64km. It consists of seven interchanges and four camel crossings. The construction is under way for 51km of the road and is being carried out in three phases. The construction works for phase four are yet to begin. The construction cost for phase four of the road will be funded by the government, similar to the ongoing construction works for phases one to three. The proposed scope of work is for the operation and maintenance of the Jeddah-Makkah road, and developing and operating motorway service areas. The contract's duration and the tender's launch date are not specified.
Other planned PPP projects

Saudi Arabia has also announced plans to tender seven PPP desalination projects.

The independent water projects (IWPs) represent an aggregate desalination capacity of 2.8 million cubic metres a day (cm/d). Owned by the Ministry of Environment, Water & Agriculture, the IWPs will be procured under 25-year build-own-operate (BOO) contracts.

The first project, Ras al-Khair 2 with a capacity of 600,000 cm/d, will be launched in February 2024.

This will be followed by the launch of another IWP, the 400,000 cm/d Ras al-Khair 3, in April 2024.

In March 2025, the kingdom plans to launch the Tabuk IWP with a capacity of 400,000 cm/d. The Alshuqaiq 4 IWP is set for launch in July 2025, with a capacity of 400,000 cm/d.

These schemes will be followed by the Rabigh 5 IWP, with a capacity of 400,000 cm/d, to be launched in April 2027, and the Rayis 2 IWP, with a capacity of 300,000 cm/d, set for launch in July 2035.

Finally, the Jizan IWP is set to have a capacity of 300,000 cm/d. Its launch date is not yet disclosed.

In addition, the kingdom plans to tender six wastewater treatment projects starting in 2024. The five independent sewage treatment plants (ISTPs), one small sewage treatment plant (SSTP) and collection network will treat wastewater for reuse in non-agricultural municipal and industrial applications.

The five ISTPs represent an aggregate wastewater treatment capacity of 650,000 cm/d.

The Ministry of Environment, Water & Agriculture will procure the projects under build-own-operate-transfer (BOOT) models.

Other projects to be tendered under the P&PPP pipeline include several medical centres, health centres, hospitals, educational buildings, schools, colleges, universities, strategic water reservoirs, marine services schemes, land ports and power stations.

https://image.digitalinsightresearch.in/uploads/NewsArticle/10739699/main.jpg
Eva Levesque
Related Articles
  • Firms submit Dubai multibillion-dollar road scheme interest

    19 October 2026

     

    Contractors submitted expressions of interest on 10 October for a design-and-build contract for a multibillion-dollar new road that will run parallel to Sheikh Zayed Road.

    Dubai’s Roads & Transport Authority (RTA) held an online meeting after the submissions to prepare for the prequalification phase of tendering, expected to start in a few weeks.

    The scope covers about 30 kilometres (km) of works.

    These include about 15km of viaduct along First Al-Khail Street and more than 14.5km of bridge ramps, along with other associated infrastructure works.

    The RTA floated the expression of interest notice to contractors in early September.

    The project is another significant initiative aimed at alleviating pressure on the existing Sheikh Zayed Road section from Hadiqa Street to Hessa Street.

    Dubai has previously explored bold concepts to expand capacity on Sheikh Zayed Road, including proposals to introduce double-decker sections to add extra lanes without widening the existing corridor.

    The idea was discussed in the context of rising congestion and limited right-of-way along one of the city’s busiest arterial roads, with elevated decks potentially carrying through traffic while existing at-grade lanes served local access.

    The plans ultimately became standalone schemes, with subsequent efforts focusing instead on corridor-wide upgrades, interchange improvements and complementary public transport expansions to manage demand more sustainably.

    The latest project aligns with Dubai’s continued investment in upgrading and expanding its road network to keep pace with rapid population growth and rising commuting demand.

    Planning for growth

    Dubai launched the 2040 Urban Master Plan in March 2021, referencing studies indicating that the emirate’s population will reach 5.8 million by 2040, up from 3.3 million in 2020. The daytime population is set to increase from 4.5 million in 2020 to 7.8 million in 2040.

    In December 2022, Sheikh Mohammed Bin Rashid Al-Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, approved the 20-Minute City Policy as part of the second phase of the Dubai 2040 Urban Master Plan. 

    In addition to the road projects, the RTA’s Dubai Metro Blue Line extension and Dubai Metro Gold Line form part of Dubai’s plans to improve residents’ quality of life by cutting journey times, as outlined in the policy.

    The policy aims for residents to have 80% of their daily requirements within a 20-minute journey, on foot or by bicycle. This goal will be achieved by developing integrated service centres with all necessary facilities and increasing population density around mass transit stations.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20745908/main.jpg
    Yasir Iqbal
  • Bahrain awards Sitra 400kV grid contracts

    19 October 2026

    Bahrain’s Electricity & Water Authority (EWA) has awarded two contracts related to the establishment of new Sitra 400kV grid substations, according to sources.

    The first contract covers transformer and reactor works including the supply and installation of three 400 kV, 500 MVA power transformers along with associated reactors. The package covers design, manufacturing, supply, transportation, erection, testing, and commissioning.

    Switzerland-headquartered Hitachi Energy has been appointed as the main contractor for these works after submitting a bid of BD17.8m ($47.1m) in April, as reported by MEED.

    Germany’s Siemens Energy previously submitted the only other offer of BD23.9m ($63.2m).

    The second contract involves 400kV and 220kV feeder cable works for the same Sitra 400kV grid substations. The package covers the design, manufacture, supply, transportation, installation, testing and commissioning of 400kV and 220kV feeder cables.

    Earlier this year, MEED reported that three South Korean companies had made offers for the feeder cable packages, with Iljin Electric submitting the lowest bid of BD35m ($92.7m).

    It is understood that the contractor has now been appointed to carry out the main works for the project.

    The works are part of the broader “Establishment of New 400 kV Grid Substations & Subsystem” initiative, aiming to bolster the power grid’s capacity and support integration with new power and water infrastructure at Sitra.

    In September 2025, Siemens Energy won a contract worth BD48.1m ($127m) to build a 400kV transmission substation in Sitra to provide the transmission link for the planned Sitra independent water and power plant (IWPP), which is expected to generate at least 1,200MW of electricity.

    Bahrain’s fourth IWPP is being procured by EWA under a public-private partnership framework for 20-25 years.

    The combined-cycle gas turbine plant includes a seawater reverse osmosis desalination facility, which will have a production capacity of 30 million imperial gallons a day of potable water.

    Last month, MEED exclusively reported on proposed first-year tariffs for the project following the opening of financial bids. Saudi Arabia’s Acwa submitted the lowest offer for both the power and water components.

    This includes a first-year power tariff of BD17.1652 ($45.65) a megawatt-hour and a water tariff of BD0.4915 ($1.307) a cubic metre.

    Abu Dhabi National Energy Company (Taqa) submitted a first-year power tariff of BD17.48190 ($46.49) a megawatt-hour and a water tariff of BD0.54285 ($1.444 ) a cubic metre.

    The main contract for the build-own-operate project is expected to be awarded by the end of the year.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20673857/main.jpg
    Mark Dowdall
  • Algeria tenders 310km Tamanrasset railway

    16 October 2026

     

    Algeria’s state railway project developer, Agence Nationale d’Etudes et de Suivi de la Realisation des Investissements Ferroviaires (Anesrif), has invited national and international contractors to bid for the construction of a 310-kilometre (km) railway line between Hotel Station and Moulay Lahcen Station. 

    The planned line is a key segment of the proposed railway corridor connecting El-Menea, In-Salah and Tamanrasset across the southern wilayas of In-Salah and Tamanrasset.

    The tender notice was issued on 12 October, with bids due by 10 November.

    The tender is open to single contractors and consortiums. To qualify, single firms must have executed at least 200km of new railway lines or track-doubling works since 2010, with accepted project certificates covering sections of at least 100km, along with a cumulative 800 metres of railway bridges with individual spans exceeding 30 metres.

    Bidders must also provide at least two rail-tamping machines, two ballast regulators, and a project director with an engineering degree and at least five years of railway construction management experience.

    From a commercial and classification perspective, single bidders and consortium leaders must hold a category-nine (IX) professional qualification in public works.

    Bidders must also demonstrate an average annual turnover in construction of at least DZ260bn ($1.96bn) across the 2023-2025 financial period.

    For joint ventures, the cumulative turnover of all members must meet the $1.96bn threshold, with the consortium leader accounting for at least $1.3bn.

    Offers must be accompanied by a bid bond exceeding 1% of the total bid value for submissions exceeding $7.4m, with proposals remaining valid for 90 days beyond the submission date.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20665591/main.jpg
    Yasir Iqbal
  • Joint venture wins $246m RCRC bridges contract

    16 October 2026

     

    A joint venture of local contractor Mofarreh Group and Turkey-based Gulsan Holding has won an estimated SR923m ($246m) contract from the Royal Commission for Riyadh City (RCRC) to construct a series of grade-separated steel flyovers across the capital.

    The contract, known as Package 2 (Groups 2 and 3), is part of RCRC’s urgent bridges programme under the wider project to build steel bridges at 10 junctions across Riyadh.

    The works have a 12-month execution timeline to fast-track traffic decongestion across major arterial corridors.

    The joint venture’s scope covers the engineering and construction of grade-separated steel bridge interchanges across seven key intersections:

    • IC04: Al-Khair Road and King Salman Bin Abdulaziz Road
    • IC05: Prince Turki Road and Imam Saud Road
    • IC06: Al-Takhassosi Road and Saeed Al-Sulami Road
    • IC07: Khurais Road and Al-Hareth Bin Abdullah Road
    • IC08: Khurais Road and Ash-Sharq Road
    • IC09: Khurais Road and Marmar Road
    • IC10: Al-Kharj Road and Al-Hilla Road

    The total length of the flyovers is 8.86 kilometres, excluding Junction IC10.

    In addition to the structural steel superstructures, concrete bridge foundations, decks and approach ramps, the contract includes retaining walls, utility diversions, temporary phased traffic arrangements, associated roadworks, drainage networks, roadway lighting, intelligent transportation systems and landscaping.

    The client received commercial proposals from several local and international contractors. Other bidders included:

    • Masco
    • Nesma & Partners
    • Al-Omaier Trading & Contracting Company 
    • Yuksel Saudia 
    • Batco 
    • Modern Building Leaders
    • Sapac

    The urgent bridges initiative is part of Riyadh’s rapid transport infrastructure programme to improve traffic throughput, enhance safety and ease vehicular congestion across central and ring-road corridors ahead of major events, including Expo 2030 and the 2034 Fifa World Cup.

    In July, Mofarreh Group and Turkiye’s Gulsan Holding formed a joint venture to bid for and deliver transport infrastructure projects in Riyadh for RCRC.

    The joint venture said it will target road, bridge, viaduct and interchange projects.

    Mofarreh will provide local market access and operational capacity, while Gulsan will contribute international experience in large-scale transport projects.

    The companies said the new venture will support knowledge transfer and localisation, and promote the use of international engineering and construction standards aligned with Saudi Arabia’s Vision 2030 infrastructure and sustainability goals.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20663255/main.png
    Yasir Iqbal
  • Humain tenders 100MW Riyadh AI data centre

    16 October 2026

     

    Register for MEED’s 14-day trial access 

    Saudi artificial intelligence infrastructure developer Humain has issued a request for proposals for an engineering, procurement and construction (EPC) contract to deliver a 100MW artificial intelligence (AI) data centre facility in Riyadh’s Al-Saad area.

    The tender was issued on 17 September, with bids due by 8 November.

    The contract includes core-and-shell works; civil works; mechanical, electrical and plumbing installation; testing and commissioning; and site infrastructure across a 350,200-square-metre plot.

    The project also includes an optional expansion phase that could raise total site capacity to 200MW.

    The initial 100MW development is split into two equal 50MW phases, structured across two single-storey IT buildings housing four 25MW data halls.

    Phase one targets a ready-for-service date by October 2028, followed by phase two in January 2029.

    Under the optional phase three, an additional 100MW facility would be brought online by July 2029.

    The data centre will be designed to support high-density graphics processing unit clusters and AI-compute workloads, with rack densities of 240kW to 250kW.

    The facility will be built to Uptime Institute Tier III topology and LEED Silver standards as a baseline, targeting LEED Gold.

    The operational design targets an annualised power usage effectiveness below 1.35.

    Power will be delivered through four 33kV connections supplied by Saudi Electricity Company from two separate high-voltage/medium-voltage primary substations. The scope requires 15 transformers, 15 static 2,250kW IT uninterruptible power supply (UPS) units, and 450kW mechanical UPS systems with lithium-ion battery storage for each 25MW block. 

    Backup emergency diesel generators will be provided on an owner-furnished, contractor-installed basis, with the EPC contractor handling their installation, connection and testing. Fuel storage will provide 24 hours of autonomous run-time, split between on-site underground bulk tanks and generator belly tanks.

    Thermal management combines air and liquid cooling. High-density server racks will be equipped with direct-to-chip liquid cooling loops using coolant distribution units and technical water distribution, paired with air-cooled chillers operating in dual high- and low-temperature loops, alongside fan-wall units.

    The total construction timeline is capped at 25 months from site handover or contract signing, with pre-execution early mobilisation scheduled to start in January 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/20661045/main.jpg
    Yasir Iqbal