Saudi power projects hit record high

21 February 2025

 

Saudi Arabia has entered what could be the busiest period for power generation capacity buildout in its history.

According to data from regional projects tracker MEED Projects and MEED, power generation projects with a total capacity of 53GW are under construction, or are about to start construction following the formal award of contracts or the selection of bidders.

Generation and cogeneration plants powered by natural gas account for two-thirds, or 66.7%, of the total capacity under construction, with renewable energy plants – mainly solar – accounting for the rest.

Solar and wind power plants dominate the pre-execution pipeline, however, accounting for about 94% of the capacity that is currently under bid or prequalification.

The total thermal and renewable generation capacity being planned and tendered in Saudi Arabia, inclusive of projects in the study and design phases, stood at about 80GW as of February 2025.

The major capacity buildout is in line with the kingdom's liquid displacement programme, as well as its target for renewable energy sources to account for half its electricity production by 2030.

According to the Energy Institute, Saudi Arabia's total electricity generation in 2023 reached 422.9 terawatt-hours (TWh). Oil accounted for 152.1TWh, or about 36% of the total, while natural gas accounted for 265TWh, or 63%, and renewables made up 5.8TWh or 1%.

CCGT plants

The urgency of displacing the kingdom's oil-fired fleet underpins the successive contract awards for combined-cycle gas turbine (CCGT) power generation plants, which are being developed as independent power projects (IPPs) or via engineering, procurement and construction (EPC) contracts.

About 47% of the 35.8GW of gas-fired capacity that is under construction is being built via an EPC or design-and-build model, mainly by Saudi Electricity Company (SEC). The rest is being constructed using an IPP model.

Of the total thermal capacity under construction, about 45% will be generated by greenfield power plants that are being built as an expansion to existing power generation facilities in the kingdom.

Chinese contractors such as Sepco 3 and China Energy Engineering Corporation are among the firms constructing 10 of the 19 gas-fired power generation and cogeneration plants that are under execution in Saudi Arabia. An 11th plant is being constructed by Sepco 3 in partnership with Doosan Enerbility of South Korea. The 11 plants equate to a capacity of about 21GW.

South Korean contractors – primarily Doosan and Samsung C&T – are involved in four of the 19 projects.

"I think the Chinese EPC contractors are already at capacity, so SEC has started tapping Egyptian and Spanish EPC contractors," an industry source tells MEED, in reference to Tecnicas Reunidas, Orascom and Elsewedy, which were selected last year to undertake the EPC contracts for several CCGT plants.

The peak for new gas-fired contract awards may have passed, however.

Data from MEED Projects indicates that four cogeneration plants with a combined capacity of about 1.5GW are in the pre-execution stage. Meanwhile, at least two gas-fired IPP schemes – Shoaiba and Al-Shuqaiq – are currently under study, each with a planned capacity of 2.6GW.

However, the possibility of an unexpected new project, like the 3GW expansion of the Qurayyah IPP, which was announced on 20 February, cannot be ruled out. 

Renewables  

A reverse trend could be seen for renewable solar power generation capacity.

As of February 2025, nearly all renewable energy capacity under construction in Saudi Arabia is being developed as IPPs.

About 43% of these IPPs are publicly tendered by the principal buyer, Saudi Power Procurement Company (SPPC). The rest are directly negotiated by Saudi sovereign wealth vehicle the Public Investment Fund (PIF) and the dominant local utility developer, Acwa Power.

The pre-execution pipeline for solar and wind energy projects that will be procured by SEC and gigaproject developer Neom is extensive, especially given that the Energy Ministry has issued a directive that up to 20GW of renewable energy capacity be procured annually until 2030, subject to demand growth.

"It is a massive pipeline," notes a Dubai-based senior transaction adviser.

However, he also notes that a re-scoping process is under way, especially for renewable energy projects that are designed to cater to Neom, the $500bn development in northwestern Saudi Arabia, which aims to be powered 100% by renewables by 2030.

Issues related to land allocation may also arise, if they haven't already, notes another industry expert.

The deployment of additional renewable energy capacity also requires a major battery energy storage system buildout. Efforts towards this got under way last year to ensure the flexibility of the electricity grid. 

"The question is how many batteries they will need and how many batteries will be available to support that ambition," the source said.    

Data centres

In addition to the liquid displacement programme and the 50% renewable energy production target by 2030, Saudi Arabia has been seeing a major uptick in data centre construction projects, in line with a plan to become a major artificial intelligence (AI) hub.

Hyperscalers such as Amazon Web Services, Google and Microsoft plan to expand their digital or cloud infrastructure in Saudi Arabia in line with this strategy. These and other AI players, as well as local firms such as DataVolt, Ezditek, Alfanar and the UAE-based Gulf Data Hub, pledged about $15bn of investments in this type of infrastructure during the Leap technology conference, which took place in Riyadh on 9-12 February. More investments are expected to be announced in the coming months and years.

These projects, assuming they all come to fruition, will significantly increase computing, cooling and overall electricity demand. The need to make these advanced data centres as sustainable as possible will also further incentivise the kingdom's national renewable energy programme.


JOIN THE LEADERS BUILDING VISION 2030 AT THE 3RD EDITION OF MEED's SAUDI GIGAPROJECTS SUMMIT
12-14 May – Riyadh, Saudi Arabia
CLICK HERE TO REGISTER YOUR INTEREST


https://image.digitalinsightresearch.in/uploads/NewsArticle/13414408/main2137.gif
Jennifer Aguinaldo
Related Articles
  • Egypt signs $420m Gabal El-Zeit wind agreements

    10 June 2026

    Egypt has signed agreements worth $420m for the investment, operation and power purchase of the 580MW Gabal El-Zeit wind power complex in the Red Sea region.

    Gabal El-Zeit 1 has a capacity of 240MW, while Gabal El-Zeit 2 and 3 have capacities of 220MW and 120MW, respectively.

    The agreements were signed between Egypt’s New and Renewable Energy Authority (NREA), the Egyptian Electricity Transmission Company (EETC) and Dubai-based Alcazar Energy.

    Under the agreements, Alcazar Energy will invest in, operate and manage the farms through a project company established under Egyptian law.

    The company will be responsible for technical operations, maintenance and efficiency upgrades while maintaining a minimum capacity of 580MW throughout the contract period.

    The Egyptian Electricity Transmission Company will purchase the electricity generated by the plant.

    The agreements follow earlier efforts to privatise the Gabal El-Zeit wind complex, involving a deal with UK-headquartered private equity firm Actis.

    According to the Egyptian government, the project supports the country’s state ownership policy and national energy strategy, which aim to increase the share of renewable energy in the electricity mix to 45%.

    The Gabal El-Zeit area on Egypt’s Red Sea coast is one of the country’s most established wind power development zones. The latest Gabal El-Zeit wind farm was completed in 2014, according to MEED Projects data. Germany’s Siemens Gamesa was the main contractor. 


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17170360/main.jpg
    Mark Dowdall
  • Majid Al-Futtaim awards $545m Ghaf Woods contract to ECC

    10 June 2026

    Majid Al-Futtaim Properties has appointed Engineering Contracting Company (ECC) as the main contractor for the Capria East, Capria West and Maravelle Residences developments at its Ghaf Woods community in Dubai, in a deal valued at AED2bn ($545m).

    The contract covers the construction of one-, two- and three-bedroom apartments and duplex residences across the two Capria clusters.

    The award adds to a series of major construction contracts Majid Al-Futtaim has issued across its Dubai communities in recent years.

    In May, local contractor Al-Sahel Contracting was awarded a AED700m contract for the Distrikt development, also at Ghaf Woods.

    In 2024, Majid Al-Futtaim awarded AED3bn in contracts for its Tilal Al-Ghaf community, appointing Innovo Build to build 94 waterfront villas at Elysian Mansions and United Engineering Construction (Unec) to deliver 130 villas at the Alaya development.


    > Be recognised among the best in the industry at the MEED Projects Awards 2026 …

    https://image.digitalinsightresearch.in/uploads/NewsArticle/17170744/main.jpg
    Colin Foreman
  • Saudi Arabia and Turkiye sign railway agreements

    10 June 2026

    Register for MEED’s 14-day trial access 

    Saudi Arabia and Turkiye have signed two memorandums of understanding (MoUs) to strengthen bilateral cooperation in the railway and logistics sectors, advancing Riyadh’s ambitions to become a global logistics hub.

    Transport and Logistics Services Minister Saleh Al-Jasser and Turkish Transport and Infrastructure Minister Abdulkadir Uraloglu signed the agreements at the ministry’s headquarters in Riyadh on 9 June, following ministerial talks held with a high-level Turkish delegation. Transport General Authority president Fawaz Al-Sahli and officials from the kingdom’s transport and logistics sector were also present.

    Agreement scope

    The first MoU covers logistics services and operations, including the exchange of expertise, policies and regulations. The second focuses on railway technologies, signalling and communication systems, railway digitalisation, human capacity development, the localisation of the railway industry and measures to reduce the sector’s environmental impact.

    More broadly, the agreements cover cooperation on railway standards and related innovations, the exchange of expertise on the design, operation and maintenance of rail projects, and engineering, infrastructure and safety standards.

    The two sides will also cooperate on research and development, with provision for joint workforce training through specialist railway academies.

    Riyadh said the agreements will help support its National Strategy for Transport and Logistics Services and Saudi Vision 2030, which seeks to position the kingdom as a logistics bridge connecting three continents.

    Turkish projects

    Turkish contractors have already established themselves as key players in the region’s rail sector. In 2012, Yapi Merkezi secured a $2.1bn contract for work on the Haramain high-speed rail network in Saudi Arabia, while Turkish firms Mapa and Limak are leading the ongoing civil works on Dubai’s $5.5bn Metro Blue Line project as part of a China Railway Rolling Stock Corporation (CRRC) consortium. Turkish consultancy Proyapi Muhendislik ve Musavirlik Anonim Sirketi has also won design contracts for the 111km Kuwait National Rail Road project.

    The agreements signed by Saudi Arabia and Turkiye may also give momentum to longstanding discussions around a rail corridor linking the GCC with Turkiye. The route, which has been discussed for years, has gained renewed impetus in recent months as the effective closure of the Strait of Hormuz has pushed regional governments to accelerate the development of overland trade alternatives.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17169958/main.gif
    Colin Foreman
  • Joint venture tenders Algeria field development contract

    10 June 2026

     

    Register for MEED’s 14-day trial access 

    Hassi Bir Rekaiz Group (GHBR), which operates Algeria’s Hassi Bir Rekaiz field, has issued a tender for phase 2A of the asset’s field development project.

    GHBR is a joint venture of Algeria’s national oil and gas company Sonatrach and Thailand’s national exploration and production company PTTEP.

    The scope of the contract focuses on the “provision of engineering and supervision services”, according to documents published by Sonatrach.

    The tender has been issued with a bid deadline of 16 June 2026.

    In May, GHBR signed a $1.1bn contract for phase two of the Hassi Bir Rekaiz development project.

    The contract was won by a consortium of Egypt’s Petrojet and Italian engineering and contracting company Arkad.

    Petrojet’s portion of the project was estimated to be worth around $600m, and Arkad’s portion was estimated to be worth $500m.

    The contract used the engineering, procurement, construction and commissioning model.

    The scope of the project contract is focused on the construction of a central processing facility (CPF) capable of processing crude oil and associated gas.

    It also includes developing off-plot pipelines, as well as related utilities and infrastructure.

    The CPF will have the capacity to process 32,000 barrels a day (b/d) and will be designed to support future expansions.

    The related infrastructure will include an extensive pipeline network spanning approximately 217 kilometres, as well as a road network.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17163750/main3325.jpg
    Wil Crisp
  • Algeria extends deadline for urea-formaldehyde project

    10 June 2026

     

    Algeria’s national oil and gas company Sonatrach has extended the bid deadline for a project to develop a new concentrated urea-formaldehyde unit in its Arzew industrial zone.

    The latest bid deadline is 15 June.  

    The contract uses the engineering, procurement, construction and commissioning model, and the bid deadline for technical tender submissions was originally set for early April.

    The condensed urea-formaldehyde unit will be located at the CP1-Z facility.

    The CP1-Z facility began operations in 1975 and has a capacity of 152,000 tonnes a year. It produces products including methanol, resin and formol.

    It is a two-phase tender. The first phase is a technical bid submission, and the second phase is a commercial bid submission.

    To be eligible to win this contract, companies must specialise in petrochemical industrial installation projects.

    They also need to have a share capital of at least $7m and more than 15 years of relevant experience.

    The new unit, UFC85, will have the capacity to produce 40,000 metric tonnes of concentrated and condensed urea-formaldehyde annually.

    The project’s scope also includes the development of auxiliary equipment and installations.

    Urea-formaldehyde has a wide range of uses, including the production of laminates, textiles and paper.

    In the wood industry, it is used as a thermosetting adhesive to bond wood to create plywood and particleboard. In agriculture, urea-formaldehyde is widely used as a slow-release fertiliser.


    READ THE JUNE 2026 MEED BUSINESS REVIEW – click here to view PDF

    GCC looks beyond the Strait; Iraq’s reform window narrows as fiscal assumptions shatter; MEED Top 100 companies.

    Distributed to senior decision-makers in the region and around the world, the June 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/17163657/main.jpg
    Wil Crisp