Saudi power projects hit record high

21 February 2025

 

Saudi Arabia has entered what could be the busiest period for power generation capacity buildout in its history.

According to data from regional projects tracker MEED Projects and MEED, power generation projects with a total capacity of 53GW are under construction, or are about to start construction following the formal award of contracts or the selection of bidders.

Generation and cogeneration plants powered by natural gas account for two-thirds, or 66.7%, of the total capacity under construction, with renewable energy plants – mainly solar – accounting for the rest.

Solar and wind power plants dominate the pre-execution pipeline, however, accounting for about 94% of the capacity that is currently under bid or prequalification.

The total thermal and renewable generation capacity being planned and tendered in Saudi Arabia, inclusive of projects in the study and design phases, stood at about 80GW as of February 2025.

The major capacity buildout is in line with the kingdom's liquid displacement programme, as well as its target for renewable energy sources to account for half its electricity production by 2030.

According to the Energy Institute, Saudi Arabia's total electricity generation in 2023 reached 422.9 terawatt-hours (TWh). Oil accounted for 152.1TWh, or about 36% of the total, while natural gas accounted for 265TWh, or 63%, and renewables made up 5.8TWh or 1%.

CCGT plants

The urgency of displacing the kingdom's oil-fired fleet underpins the successive contract awards for combined-cycle gas turbine (CCGT) power generation plants, which are being developed as independent power projects (IPPs) or via engineering, procurement and construction (EPC) contracts.

About 47% of the 35.8GW of gas-fired capacity that is under construction is being built via an EPC or design-and-build model, mainly by Saudi Electricity Company (SEC). The rest is being constructed using an IPP model.

Of the total thermal capacity under construction, about 45% will be generated by greenfield power plants that are being built as an expansion to existing power generation facilities in the kingdom.

Chinese contractors such as Sepco 3 and China Energy Engineering Corporation are among the firms constructing 10 of the 19 gas-fired power generation and cogeneration plants that are under execution in Saudi Arabia. An 11th plant is being constructed by Sepco 3 in partnership with Doosan Enerbility of South Korea. The 11 plants equate to a capacity of about 21GW.

South Korean contractors – primarily Doosan and Samsung C&T – are involved in four of the 19 projects.

"I think the Chinese EPC contractors are already at capacity, so SEC has started tapping Egyptian and Spanish EPC contractors," an industry source tells MEED, in reference to Tecnicas Reunidas, Orascom and Elsewedy, which were selected last year to undertake the EPC contracts for several CCGT plants.

The peak for new gas-fired contract awards may have passed, however.

Data from MEED Projects indicates that four cogeneration plants with a combined capacity of about 1.5GW are in the pre-execution stage. Meanwhile, at least two gas-fired IPP schemes – Shoaiba and Al-Shuqaiq – are currently under study, each with a planned capacity of 2.6GW.

However, the possibility of an unexpected new project, like the 3GW expansion of the Qurayyah IPP, which was announced on 20 February, cannot be ruled out. 

Renewables  

A reverse trend could be seen for renewable solar power generation capacity.

As of February 2025, nearly all renewable energy capacity under construction in Saudi Arabia is being developed as IPPs.

About 43% of these IPPs are publicly tendered by the principal buyer, Saudi Power Procurement Company (SPPC). The rest are directly negotiated by Saudi sovereign wealth vehicle the Public Investment Fund (PIF) and the dominant local utility developer, Acwa Power.

The pre-execution pipeline for solar and wind energy projects that will be procured by SEC and gigaproject developer Neom is extensive, especially given that the Energy Ministry has issued a directive that up to 20GW of renewable energy capacity be procured annually until 2030, subject to demand growth.

"It is a massive pipeline," notes a Dubai-based senior transaction adviser.

However, he also notes that a re-scoping process is under way, especially for renewable energy projects that are designed to cater to Neom, the $500bn development in northwestern Saudi Arabia, which aims to be powered 100% by renewables by 2030.

Issues related to land allocation may also arise, if they haven't already, notes another industry expert.

The deployment of additional renewable energy capacity also requires a major battery energy storage system buildout. Efforts towards this got under way last year to ensure the flexibility of the electricity grid. 

"The question is how many batteries they will need and how many batteries will be available to support that ambition," the source said.    

Data centres

In addition to the liquid displacement programme and the 50% renewable energy production target by 2030, Saudi Arabia has been seeing a major uptick in data centre construction projects, in line with a plan to become a major artificial intelligence (AI) hub.

Hyperscalers such as Amazon Web Services, Google and Microsoft plan to expand their digital or cloud infrastructure in Saudi Arabia in line with this strategy. These and other AI players, as well as local firms such as DataVolt, Ezditek, Alfanar and the UAE-based Gulf Data Hub, pledged about $15bn of investments in this type of infrastructure during the Leap technology conference, which took place in Riyadh on 9-12 February. More investments are expected to be announced in the coming months and years.

These projects, assuming they all come to fruition, will significantly increase computing, cooling and overall electricity demand. The need to make these advanced data centres as sustainable as possible will also further incentivise the kingdom's national renewable energy programme.


JOIN THE LEADERS BUILDING VISION 2030 AT THE 3RD EDITION OF MEED's SAUDI GIGAPROJECTS SUMMIT
12-14 May – Riyadh, Saudi Arabia
CLICK HERE TO REGISTER YOUR INTEREST


https://image.digitalinsightresearch.in/uploads/NewsArticle/13414408/main2137.gif
Jennifer Aguinaldo
Related Articles
  • Kuwait awards $381m oil project

    23 September 2026

    Register for MEED’s 14-day trial access 

    State-owned upstream operator Kuwait Oil Company (KOC) has awarded an oil project contract worth KD117m ($381m) to India’s Megha Engineering & Infrastructure (Meil).

    The Supreme Purchasing Committee for Kuwait Petroleum Corporation (KPC) approved the contract last month, paving the way for the official award.

    The project focuses on a water separation unit at the Al-Rawdatain facility in Kuwait.

    The water separation facility will be developed at Gathering Centre 25 (GC-25), along with a pumping facility at GC-30.

    The project will deliver a wide-ranging upgrade of processing and utility infrastructure, including new low-pressure separation and gas-handling equipment such as a three-phase wet separator package, a gas knock-out drum and associated low-pressure gas pipelines, as well as a high-integrity pressure protection system and a high-pressure flare.

    Meil will develop the new three-phase low-pressure wet separation facility at GC-25.

    The main process equipment will include two wet separator packages, each with a capacity of 150,000 barrels of liquid a day, and a low-pressure gas knock-out drum with a capacity of 53 million standard cubic feet a day, together with associated gas-handling facilities.

    The facility will also incorporate an effluent water treatment and transfer system, including an effluent water balance tank equipped with microbubble flotation and induced gas flotation systems, as well as transfer pumps.

    Additional GC-25 facilities will include fuel gas treatment, chemical injection, oil recovery and flare connections, along with firewater and deluge systems.

    The scope also covers control and safety systems, substations, and associated civil, structural, mechanical, electrical and instrumentation works.

    At GC-30, the project will focus on treated-water filtration and high-pressure injection infrastructure.

    The scope includes nutshell filters and associated feed pumps with a combined capacity of approximately 500,000 barrels of water a day.

    Booster and injection pumps will transfer treated effluent water to designated injection wells.

    Additional facilities at GC-30 will include fuel gas treatment, sludge collection and disposal systems, oil recovery systems, control and safety systems, substations, laboratory and workshop facilities, and associated civil, structural, piping, mechanical, electrical and instrumentation works.

    The project also includes transfer pipelines connecting GC-25, GC-15 and GC-30.

    Meil will carry out modifications to existing tanks at GC-30, as well as process and utility tie-ins, electrical and instrumentation modifications and other infrastructure required to integrate the new facilities with KOC’s existing assets.

    Meil’s responsibilities cover the project lifecycle from design and engineering through procurement, construction, testing, pre-commissioning, commissioning, start-up and performance testing.

    The contract also includes operation, maintenance, repair and insurance responsibilities for the designated facilities during the applicable operations and maintenance period.

    Seven companies submitted bids for the project last November.

    The full list of bids was:

    • Meil (India) – KD117m ($381m)
    • Mechanical Engineering & Contracting Company (Kuwait) – KD130m
    • Spetco (Kuwait) – KD158m
    • Al-Kharafi (Kuwait) – KD164m
    • China Oil HBP Science & Technology (China) – KD169m
    • Alghanim International (Kuwait) – KD169m
    • Jereh Oil & Gas Engineering (China) – KD191m

    In October last year, KOC awarded Meil a separate contract for a project to develop a gas sweetening and recovery facility in west Kuwait.

    Meil submitted the lowest bid for that tender, at KD69.2m ($225.5m), in February 2025.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911322/main.jpg
    Wil Crisp
  • Kuwait refinery project on track for year-end completion

    23 September 2026

     

    A $65m project to replace a substation at the Mina Al-Ahmadi (MAA) refinery is on schedule to be mechanically complete before the end of the year, according to industry sources.

    The project is being executed by India’s Larsen & Toubro (L&T), which was awarded the contract in October 2024.

    One source said: “This project is approaching completion and is currently on schedule to be completed before the end of the year, although it could still see delays related to the ongoing regional conflict.”

    The client is state-owned downstream operator Kuwait National Petroleum Company (KNPC).

    Kuwait’s Ministry of Electricity, Water & Renewable Energy (MEW) is also involved in the project and will provide final approvals and sign-off.

    The scope of the project includes:

    • Construction of a substation
    • Installation of transformers
    • Installation of medium-voltage switchgear
    • Installation of low-voltage auxiliary systems
    • Installation of network protection systems
    • Installation of disconnecting switches
    • Installation of surge arrestors
    • Installation of feeder breakers and cubicles
    • Installation of low-voltage A/C and D/C equipment
    • Installation of battery banks and battery chargers
    • Installation of related relay and control panel boards
    • Installation of fire alarm and fire protection equipment
    • Installation of a SCADA system
    • Installation of cables
    • Civil works
    • Associated facilities

    The current project to replace a substation at the MAA refinery closely resembles another project tendered by KNPC more than a decade ago, which L&T also won.

    On 18 May 2015, KNPC signed a contract with L&T to build a new 240MW substation at the MAA refinery, valued at KD21.866m.

    The new substation, known as M20, was designed to replace an existing substation that was considered old and obsolete.

    Mohammed Al-Mutairi, who was KNPC’s chief executive at the time, said the substation building would be explosion-proof and use state-of-the-art control systems.

    He said the station’s capacity would increase from 180MW to 240MW, supplying most of the refinery’s electricity needs.

    Given the similarities between the two projects, L&T has been able to reuse some designs, creating efficiencies, according to industry sources.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19911319/main.jpg
    Wil Crisp
  • Contractor wins $208m Almoosa hospital MEP contract

    23 September 2026

    Register for MEED’s 14-day trial access 

    Riyadh-based construction firm BEC Arabia has won a SR781m ($208m) contract for the mechanical, electrical and plumbing (MEP) works at Almoosa Hospital in Al-Khobar.

    Saudi Arabia’s Almoosa Health Company awarded the contract.

    The hospital complex consists of two towers: a 24-storey in-patient tower with 380 beds, and an 11-storey tower with 224 clinics and 113 additional treatment spaces.

    It will be built on a 45,000-square-metre site.

    A podium spanning the ninth and 10th floors will connect the two towers.

    The hospital will also include parking for 1,700 cars.

    BEC Arabia won the SR656m ($175m) main construction contract for the hospital in November last year.

    In August 2025, MEED reported that Almoosa Health Company had announced it had secured a sharia-compliant credit facility worth SR650m ($173m) from Banque Saudi Fransi.

    In a statement published on the Saudi stock exchange (Tadawul), the company said the seven-year facility would be used to support its expansion and growth strategy.

    Lebanon’s Dar, US-based Perkins&Will and French design firm Pierre-Yves Rochon designed the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19910889/main.jpg
    Yasir Iqbal
  • UAE to develop integrated waste-to-resource pilot

    23 September 2026

    Emirates Biotech and United Arab Emirates University (UAEU) have launched a pilot project in Al-Ain that could provide a model for larger waste-to-resource facilities.

    The project involves developing the UAE’s first integrated organic-waste valorisation pilot plant, which will test whether food waste and compostable packaging can be processed together to recover resources and reduce waste sent to landfill.

    Located near the UAEU campus, the 40kg-a-day facility will process organic waste to produce renewable biogas and nutrient-rich compost. The project is intended to generate technical and operating data that could support the development of larger-scale facilities.

    Emirates Biotech and UAEU will design, build and operate the pilot plant as part of a two-year research project running from August 2026 to August 2028. Installation and commissioning are expected to be completed by August 2027.

    The plant will combine anaerobic digestion and composting. Anaerobic digestion will convert the organic waste into renewable biogas, while the resulting digestate will be composted to produce nutrient-rich compost.

    A laboratory-scale assessment will also examine the potential to convert the biogas into renewable hydrogen.

    Food waste accounts for nearly 40% of daily municipal solid waste in the UAE, according to Emirates Biotech, and much of it is currently disposed of in landfills.

    The pilot will therefore assess the technical and operational feasibility of recovering value from two waste streams through a single integrated process.

    If successfully scaled, Emirates Biotech says an integrated organic-waste valorisation plant could reduce CO₂ emissions by 89% compared with landfilling.

    The project is expected to provide a scalable and modular model for converting food waste and compostable packaging into renewable biogas and compost, with the findings intended to inform the development of larger waste-to-resource facilities.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19908972/main.jpg
    Mark Dowdall
  • Contractors prepare Oxagon Highway 55 bids

    23 September 2026

     

    Contractors are preparing to submit bids on 28 September for a design-and-build contract for permanent upgrade works on Highway 55 in the kingdom’s Oxagon region.

    The first phase of the project includes constructing 14 kilometres of road, with two lanes in each direction. It also includes one bridge and three interchanges.

    The project duration is 22 months.

    Highway 55 connects the Red Sea coast with the mainland in northwestern Saudi Arabia. It is currently the only road providing north-south connectivity between Duba and the Neom region.

    MEED reported exclusively in August 2025 that contractors had submitted responses to an expression of interest notice that Neom had issued earlier that month.

    The project is expected to support cargo movement from Duba Port to other parts of the kingdom and the wider region.

    Last year, Neom tested a pilot initiative by handling a shipment that travelled from Cairo via the Port of Safaga, across the Red Sea to the Port of Neom, and then inland to Erbil, Iraq.

    In a statement, Neom said: “The shipment travelled through an intermodal corridor spanning over 900 kilometres, marking a significant milestone in the kingdom’s transformation into a regional and global logistics hub.”

    The Port of Neom is located on the Red Sea near the Arar border, a key entry point into Iraq.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19907876/main.jpg
    Yasir Iqbal