Saudi Arabia and Greece set up grid link

10 October 2023

Greece and Saudi Arabia have agreed to set up a jointly-owned company that will look at linking their electricity grids.

Greece's Independent Power Transmission Operator (IPTO) and Saudi Arabia's National Grid will set up a company, provisionally called Saudi Green Interconnection, Reuters reported in late September citing the Greek energy ministry.

The new company is tasked "with examining the commercial viability of the power interconnection".

Related readRegion plans vital big grid connections

The deal follows initial discussions conducted last year between Saudi Energy Minister Prince Abdulaziz Bin Salman and his Greek counterpart, Kostas Skrekas, in Riyadh.

At the time, the discussions involved cooperation in renewable energy and the promotion of an electricity interconnection that will export clean energy to Greece and Europe.

They also discussed the potential of transporting clean hydrogen to Europe through Greece.

Greece is also working on a potential project to connect its electricity grid with Egypt's. 

In February this year, US engineering firm McDermott signed a memorandum of understanding (MoU) with Athens-based Eunice Energy Group for the 2GW electricity interconnection project between Egypt and Greece.

Eunice Energy leads the consortium known as Greece-Africa Power (GAP), which is developing the project.

McDermott is expected to provide "engineering and construction guidance for the project".

In October 2021, Egypt signed separate power interconnection agreements with Greece and Cyprus.

The agreements were expected to pave the way for implementing the so-called Eastern Mediterranean energy corridor.

The planned interconnector aims to enable the exchange of between 2,000MW and 3,000MW of electricity between Egypt, Cyprus and Greece and potentially with other European countries, as MEED reported.

The agreement with Greece entails setting up an undersea cable network that will transmit renewable energy produced from North Africa to Europe.

Skrekas and his Egyptian counterpart, Mohamed Shaker, signed an MoU for the project at a ceremony in Athens on 14 October 2021.

The deal follows the signing of a similar agreement between Greece, Cyprus and Israel to build the Euro-Asia Interconnector, understood to be the world's longest and deepest underwater power cable crossing the Mediterranean, estimated to cost $900m.

An electricity grid linking Egypt and the GCC states is also under way. Egypt and Saudi Arabia awarded substation, subsea and overhead transmission contracts for the $1.8bn interconnector linking the GCC states and North Africa in October 2021.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11206759/main.gif
Jennifer Aguinaldo
Related Articles
  • Mace confirms Muscat cultural complex appointment

    3 September 2026

    UK-headquartered engineering firm Mace Consult has confirmed its appointment to manage the construction of the Sayyid Tarik Bin Taimur Cultural Complex in the Al-Seeb area of Muscat.

    The firm will provide project leadership, programme management, commercial oversight and delivery assurance services.

    The complex will be developed on a 400,000-square-metre (sq m) site. Centred on an urban plaza, it will bring together a range of cultural and institutional facilities.

    These include a 23,000 sq m national library, a 15,500 sq m national archives, four facilities buildings with a combined area of 14,000 sq m, and a 5,000 sq m energy and data centre.

    At the heart of the development is the national theatre, which will include a 1,000-seat auditorium and a 250-seat auditorium. The facilities will sit within landscaped gardens and water features, alongside a signature canopy structure.

    In October 2023, the Ministry of Culture, Sports & Youth awarded a design-and-build contract for the complex to a joint venture of local firm Saif Salim Issa Al-Harrasi and Turkiye’s Sembol Construction, MEED reported.

    In January 2026, UAE-based steel structure manufacturer Emirates Building Systems, a wholly owned subsidiary of Dubai Investments, won a contract to deliver the project’s structural steel package.

    Last month, Kuwait-based engineering and architecture consultancy SSH was appointed as the project’s construction supervision consultant.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19314737/main.jpg
    Yasir Iqbal
  • Read the September 2026 MEED Business Review

    3 September 2026

    Download / Subscribe / 14-day trial access

    Nuclear energy is becoming an increasingly important part of the GCC’s long-term power strategy, as governments seek to strengthen energy security, diversify generation and meet decarbonisation goals.

    Saudi Arabia’s civil nuclear cooperation deal with the US marks a major step forward for its plans to develop its first commercial nuclear power plant, while rising electricity demand across the region is creating further momentum.

    With the UAE already operating the Middle East’s first commercial nuclear power station, Saudi Arabia targeting up to 17GW by 2040 and Bahrain exploring small modular reactor technologies, our latest Agenda feature examines the growing role of nuclear energy in the GCC’s future power projects pipeline.

    September’s Market Focus turns to Kuwait, where the country’s oil-dependent economy has weathered unprecedented disruption, yet major investment and infrastructure deals point to resilience.

    This edition also includes a downstream industry report, exploring the accelerating investment in gas processing and associated infrastructure across Mena, the major projects driving spending, and the growing focus on NGL recovery, efficiency and higher-value gas products.

    In the latest issue, we speak to Emsteel chief commercial officer Michael Rion about the Abu Dhabi steelmaker’s plans to strengthen its position in domestic and international markets, including the launch of its ES600 steel rebar and the expansion of its long-standing partnership with Adnoc Group.

    We also examine the GCC’s accelerating tunnelling boom, as major metro, sewerage and road projects increasingly move underground. The feature explores the scale of investment, the contractors and technology driving the market, and the challenges facing the region as demand for tunnelling expertise and equipment grows.

    We hope our valued subscribers enjoy the September 2026 issue of MEED Business Review

     

    Must-read sections in the September 2026 issue of MEED Business Review include:

    AGENDA: Gulf nuclear revival takes shape

    INDUSTRY REPORT:
    Downstream
    Gas processing takes centre stage in Mena region

    > INTERVIEW: Emsteel persists with business productivity and efficiency

    > TUNNELS: The Gulf’s next construction boom is happening underground

    > KUWAIT MARKET FOCUS
    > COMMENT: Kuwait keeps dealmaking alive under fire
    > GOVERNMENT: Kuwait shows tentative signs of economic development
    > BANKING: Necessity is the mother of invention for Kuwaiti lenders
    > OIL & GAS: Regional war to have lasting impact on Kuwaiti oil sector
    > POWER & WATER: Kuwait utilities investment shifts towards water
    > CONSTRUCTION: Kuwait construction holds up despite regional strife
    > MARKET TALK: Kuwait stands resilient amid regional tensions
    > DATABANK: Kuwait’s economic gains are dented by conflict in 2026

    MEED COMMENTS: 
    Cash is king for Dubai construction

    Aramco moves apace with Jafurah unconventional gas campaign
    Neom’s next phase is crucial to green hydrogen pipeline
    Oman opens door to direct power sales

    > GULF PROJECTS INDEX: Qatar leads gains as Gulf total holds

    > JUNE 2026 CONTRACTS: Middle East contract awards

    > ECONOMIC DATA: Data drives regional projects

    > OPINIONThe history of false dawns

    BUSINESS OUTLOOK: Finance, oil and gas, construction, power and water contracts

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19308287/main.gif
    MEED Editorial
  • Contractors submit bids for Dukhan field facilities upgrade

    3 September 2026

     

    Contractors have submitted bids to QatarEnergy for a key tender to upgrade facilities at the Dukhan oil field in Qatar, about 80 kilometres west of Doha.

    Dukhan, Qatar’s first and only onshore oil field, was discovered in 1938, with oil production starting in 1939-40. The country currently produces about 1.8 million barrels a day (b/d) of crude, with the Dukhan field accounting for about 350,000 b/d of output.

    QatarEnergy issued the tender for the Dukhan production facilities upgrade (DPFU) Phase 1B (Part 2) project on 8 June, and initially set a bid submission deadline of 26 July for contractors, which it later extended to 9 August.

    The following local contractors, among others, are understood to have submitted bids for the DPFU Phase 1B (Part 2) tender, according to information obtained by MEED Projects:

    • Doha Petroleum Construction Company (Dopet)
    • Galfar Al-Misnad Engineering & Contracting
    • Qatar Engineering & Construction Company (Q-con)

    QatarEnergy originally stipulated a bond validity of 150 days (until 23 December) and a bid validity of 120 days (until 23 November) for the project.

    The engineering, procurement, installation and commissioning (EPIC) scope covers upgrades to 56 oil manifolds, 108 gas-lift manifold slots, chemical injection systems and key pumping facilities, along with associated piping, instrumentation, control, electrical and civil works.

    The scope includes demolition of obsolete equipment, degassing station enhancements, and full testing and handover. It also encompasses additional capacity enhancement works under Part 3, mainly the installation of new oil export and produced-water transfer pumps, along with supporting facility modifications.

    The project involves complex interfaces and shutdown-critical activities requiring expertise in live-plant integration.

    The Dukhan oil field extends over an area of about 80km by 8km and consists of four reservoirs: Khatiyah, Fahahil, Jaleha and Diyab. The first three are oil reservoirs. The more recently developed Diyab reservoir contains non-associated gas and is estimated to hold around 2 billion barrels of crude oil reserves. Diyab lies on the southern flank of Dukhan.

    ALSO READ: Frontrunners emerge for Qatar offshore oil field expansion
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19312615/main.jpeg
    Indrajit Sen
  • Oman tenders advisory for 3GW solar IPPs

    3 September 2026

    Nama Power & Water Procurement Company (Nama PWP) has invited bids for legal consultancy services for the development of three 1GW solar independent power projects (IPPs).

    The projects will connect to Oman’s main interconnected system (MIS) and are targeted to reach commercial operation by the second quarter of 2030.

    The bid submission deadline is 10 October.

    The state offtaker has now tendered three separate consultancy contracts for the solar IPPs, including two issued in July.

    The bid submission deadline for the financial and commercial consultancy services tender is 10 September.

    Earlier, on 15 July, a technical advisory tender was issued for the three projects as part of a 4GW programme.

    As MEED reported, the financial advisory tender covers four 1GW solar projects connected to the MIS, also targeting commercial operation by the second quarter of 2030.

    It is understood that bids were submitted for this contract on 26 August.

    Oman Electricity Transmission Company (OETC) had earlier outlined the planned grid connection for four 1GW solar IPPs as part of the sultanate’s renewable energy expansion through 2030.

    The projects are included in OETC’s Five-Year Annual Transmission Capability Statement for 2026-30.

    The first, the 1GW Adam solar IPP, is scheduled for grid integration in 2028 and is further ahead in the procurement process, with Nama PWP issuing a request for qualification for the project in June.

    OETC said it expects the 1GW Al-Kamil 2 solar project to be integrated in 2030 through the planned Sadaf 400kV grid station. The 1GW Dhofar solar IPP and 1GW Mahadha solar IPP are also scheduled for integration in 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19311796/main.jpg
    Mark Dowdall
  • US firm wins work on QatarEnergy NGL train project

    3 September 2026

    Register for MEED’s 14-day trial access 

    US-based Nessco has  that it has won a subcontract to provide telecommunications, radio and security systems for QatarEnergy’s project to add a fifth natural gas liquids (NGL) train at its fractionation complex in Qatar’s Mesaieed Industrial City.

    The subcontract was awarded to Houston-headquartered Nessco by India’s Larsen & Toubro Energy Hydrocarbon (LTEH), in its capacity as the main contractor performing engineering, procurement and construction (EPC) works on the NGL-5 project.

    MEED reported last September that QatarEnergy had selected a consortium of LTEH and Greece-headquartered Consolidated Contractors Group (CCC) to execute EPC works on the NGL-5 project.

    The aim of the project, estimated to be worth $2.5bn, is to build a fifth NGL train with the capacity to process up to 350 million cubic feet a day of rich associated gas from QatarEnergy’s offshore and onshore oil fields.

    In a statement confirming its contract award in October last year, LTEH said the scope of work on its contract “encompasses engineering, procurement, construction, installation and commissioning of a natural gas liquids plant and allied facilities for processing rich associated gas (RAG). This also involves all associated utilities and offsites and integration with existing facilities.

    “The RAG sourced from offshore and onshore oil fields will be treated at the plant to remove impurities like H2S, CO2 and H2O, producing value-added products such as lean sales gas, ethane, propane, butane and hydrocarbon condensate,” Bombay Stock Exchange-listed L&T said. 

    Under the consortium arrangement, LTEH, as the lead partner, will be responsible for engineering and procurement, while CCC will handle construction activities.

    Project scope of work

    Associated gas from the PS1, PS2 and PS3 offshore fields, as well as the Dukhan onshore field, is processed at existing facilities at the NGL complex in Mesaieed – specifically, the Fahahil stripping plant, NGL-1 and Qapco ethane recovery units.

    The planned NGL-5 facility will replace these three units at the Mesaieed complex and process gas from the PS1, PS2 and Dukhan fields.

    The scope of work on the project involves EPC of units for the following functions:

    • Feed gas compression
    • Slug handling
    • Gas sweetening
    • Dehydration
    • Mercury removal
    • NGL fractionation
    • NGL recovery
    • Product treatment
    • Propane refrigeration
    • Acid gas enrichment
    • Sulphur recovery
    • Anti-flaring
    • Utilities
    • Boil-off gas recovery
    • Drains and collection networks
    • Effluent water treatment plant
    • Carbon dioxide treatment and sequestration/export
    • Brownfield modifications
    • Product rundown pipelines

    QatarEnergy intends to start operations at the NGL-5 facility by the second quarter of 2028.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19310738/main5414.jpeg
    Indrajit Sen