Saudi Arabia and France hold energy meeting
10 July 2023
The Saudi and French governments have affirmed plans to cooperate in the energy sector following a meeting in Riyadh between Saudi Energy Minister Abdulaziz bin Salman and France's Energy Transition Minister Agnes Pannier-Rucnacher.
This follows the signing in February of a preliminary agreement to cooperate on nuclear and renewable energy projects. That agreement was inked by Abdulaziz bin Salman and French Foreign Affairs Minister Catherine Colonna.
The latest statement indicates that both countries recognise “that clean hydrogen is an essential fuel to reach the shared objective of promoting a sustainable economic development while mitigating the impact of climate change”.
The two countries agreed to enhance cooperation in the field of electricity and exchange experiences in the field of electricity generation from renewable energy resources.
They will also cooperate on grid interconnection projects and encourage the participation of private sector companies in power sector projects including generation, transmission, distribution, storage and network automation technologies.
They have agreed to engage in joint efforts to enhance energy efficiency and boost cooperation in nuclear energy “in a peaceful and safe framework, the management of radioactive waste and the nuclear applications, and the development of human capabilities”.
According to the statement, Saudi Arabia and France have also agreed to cooperate on advancing climate technologies and solutions, including carbon capture utilisation and storage (CCUS) for hard-to-abate sectors such as cement, aviation, marine and petrochemicals, among others.
RELATED READ: Nuclear power investment potential grows
In February, the ministers also signed a memorandum of understanding (MoU) related to energy cooperation between the two countries.
The MoU encourages cooperation in “electricity, renewable energy, energy efficiency, energy storage, smart grids, oil and gas and their derivatives, refining, petrochemicals, and the distribution and marketing sectors”.
The MoU also covers cooperation in digital transformation; localisation of materials, products and services in the energy supply chain; and collaboration between companies and universities.
Exclusive from Meed
-
What actually slows a gigaproject down9 September 2026
-
Jordan tenders advisory for wastewater treatment plant9 September 2026
-
Consultants bid for Abu Dhabi light rail project management9 September 2026
-
Medina’s KEC signs real estate project development deal9 September 2026
-
Morocco signs agreement for synthetic fuel complex9 September 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
What actually slows a gigaproject down9 September 2026

Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.
“None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.
For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.
“The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.
The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.
“Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”
Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.
Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.
Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.
“The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”
Integration needs to be well understood
“Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.
Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.
Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.
“The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”
That shared view, he argues, will be what the next phase of Gulf delivery is judged on.
Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.
“This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.
From reporting progress to managing risk before it lands
Digital tools have a role here, Caldwell says, but not as a headline in themselves.
Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.
“The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."
None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”
Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.
With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.
“The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.
What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.
“The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”
https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif -
Jordan tenders advisory for wastewater treatment plant9 September 2026
The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.
The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).
The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.
The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.
The submission deadline is 21 September.
The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.
The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.
The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.
WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.
The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.
The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg -
Consultants bid for Abu Dhabi light rail project management9 September 2026

Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.
The notice was issued on 7 September, with a submission deadline of 9 November.
The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.
The key sections of the tram are:
AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.
This section covers 13km and includes 13 at-grade stations and one underground station.
Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.
Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.
The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.
The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.
Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.
Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.
Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.
The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.
https://image.digitalinsightresearch.in/uploads/NewsArticle/19493532/main.jpg -
Medina’s KEC signs real estate project development deal9 September 2026
Medina’s Knowledge Economic City (KEC) has signed an agreement with Riyadh-based Kaden Investment Company to develop a mixed-use project in Medina.
The project will have an estimated gross floor area of about 230,000 square metres (sq m).
According to a statement filed by KEC with the Saudi Exchange (Tadawul), the project – called Multaqa Al-Madinah 2 – will be built on a 92,000 sq m plot located directly north of the first phase of the Multaqa Al-Madinah development.
It is expected to include about 1,527 residential units across three residential zones, along with commercial and office space totalling about 31,108 sq m of net leasable area.
It will also feature parking, recreational and service facilities, landscaping and other supporting infrastructure.
KEC and Kaden intend to deliver the project through a closed-ended real estate investment fund regulated by Saudi Arabia’s Capital Market Authority.
Under the proposed structure, KEC will contribute the land as an in-kind contribution and hold 75% of the fund units, while Kaden will contribute cash and hold the remaining 25%.
Kaden will also serve as the development manager.
KEC said the land has been initially valued at about SR692.3m ($184.6m), while the total equity required for the project is estimated at around SR833m.
Once final agreements are signed, KEC expects to receive SR67.7m in cash and fund units valued at approximately SR624.6m.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19492407/main.png -
Morocco signs agreement for synthetic fuel complex9 September 2026
Switzerland-based Synhelion has signed an agreement with the Government of Morocco with the aim of developing a large-scale commercial synthetic fuel plant in the country’s southern Tan-Tan province.
The memorandum of understanding (MoU) relates to a facility with the capacity to produce 100,000 tonnes a year of fuel, according to a statement released by the company.
Synhelion has secured land for the project site and established a subsidiary in Morocco to develop the fuel complex.
Gianluca Ambrosetti, one of Synhelion’s co-chief executives, said: “Morocco’s exceptional renewable energy resources and its clear industrial strategy make it an ideal location for scaling our synthetic fuel technology.
“With the MoU signed, the land reservation secured and our branch in place, we are moving from evaluation to execution and toward our first commercial-scale plant in the region.”
Synhelion specialises in producing hydrocarbon fuels using renewable energy. Its products include synthetic jet fuel, gasoline and diesel.
READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDFNuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.
Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:
> AGENDA: Gulf nuclear revival takes shape> MARKET FOCUS: Kuwait keeps dealmaking alive under fire> INDUSTRY REPORT: Gas processing takes centre stage in Mena regionTo see previous issues of MEED Business Review, please click herehttps://image.digitalinsightresearch.in/uploads/NewsArticle/19489903/main.jpg