Saipem wins $4bn Qatar offshore gas project contract

16 September 2024

Register for MEED's 14-day trial access 

QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, has awarded Italian contractor Saipem an estimated $4bn engineering, procurement, construction and installation (EPCI) contract as part of the second phase of its North Field Production Sustainability (NFPS) project.

Saipem has won combined packages COMP3A and COMP3B of the NFPS project’s second phase, it said in a statement on 16 September.

The scope of work on the combined packages encompasses EPCI of a total of six platforms, approximately 100 kilometres (km) of corrosion resistance alloy rigid subsea pipelines of 28-inches and 24-inches diameter, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.

The aim of the second phase of the NFPS project is to support QatarEnergy’s North Field liquefied natural gas (LNG) expansion programme.

The second NFPS phase will mainly involve building gas compression facilities to sustain and gradually increase gas production from Qatar’s offshore North Field gas reserve over the long term.

This is the second contract win for Saipem in the NFPS project’s second phase, which consists of four main EPCI packages.

Prior to winning combined packages COMP3A and COMP3B, QatarEnergy LNG awarded Saipem a $4.5bn order in October 2022 to build and install gas compression facilities.

The main scope of work on the package, which is known as EPCI 2, covers two large gas compression complexes that will comprise decks, jackets, topsides, interconnecting bridges, flare platforms, living quarters and interface modules.

The gas compression complexes – CP65 and CP75 – will weigh 62,000 tonnes and 63,000 tonnes, respectively, and will be the largest fixed steel jacket compression platforms ever built.

NFPS first phase

Saipem is executing the main EPCI works on the entire first phase of the NFPS project, which consists of two packages.

Through the first phase of the NFPS scheme, QatarEnergy LNG aims to increase the early gas field production capacity of the North Field offshore development to 110 million tonnes a year.

QatarEnergy LNG, formerly Qatargas, awarded Saipem the contract for the EPCI package in February 2021. The package is the larger of the two NFPS phase one packages and has a value of $1.7bn.

Saipem’s scope of work on the EPCI package encompasses building several offshore facilities for extracting and transporting natural gas, including platforms, supporting and connecting structures, subsea cables and anti-corrosion internally clad pipelines.

The scope of work also includes decommissioning a pipeline and other significant modifications to existing offshore facilities.

In addition, in April 2021, QatarEnergy LNG awarded Saipem two options for additional work within the EPCI package, worth about $350m.

QatarEnergy LNG awarded Saipem the second package of the NFPS phase one project, estimated to be worth $1bn, in March 2021.

Saipem’s scope of work on the package, known as EPCL, mainly covers installing three offshore export trunklines running almost 300km from their respective offshore platforms to the QatarEnergy LNG north and south plants located in Ras Laffan Industrial City.

Saipem has performed the front-end engineering and design work on the main production package of the first phase of the NFPS as part of a $20m contract that it was awarded in January 2019. This provided a competitive advantage to the Italian contractor in its bid to win the package.

Saipem expects to complete work on both packages of the first phase of the NFPS project by the end of 2024.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12543882/main5022.jpeg
Indrajit Sen
Related Articles
  • Bidders await NWC decision on sewage contract

    17 February 2026

     

    Saudi Arabia’s National Water Company (NWC) is evaluating five bids for package 12 of its long-term operations and maintenance (LTOM12) sewage treatment programme.

    Known as the North Western B Cluster, LTOM12 forms part of the second phase of NWC’s rehabilitation of sewage treatment plants programme.

    The contract covers the construction and upgrade of seven sewage treatment plants with a combined capacity of about 162,000 cubic metres a day (cm/d).

    As MEED understands, the companies that have submitted proposals include:

    • Alkhorayef Water & Power Technologies (Saudi Arabia)
    • Civil Works Company (Saudi Arabia)
    • Miahona (Saudi Arabia)
    • Beijing Enterprises Water Group – BEWG (Hong Kong)
    • Al-Yamama (Saudi Arabia)

    Earlier this month, MEED exclusively reported that six contractors are competing for the North Western A Cluster Sewage Treatment Plants Package 11 (LTOM11), which has an estimated value of about $211m.

    The project involves the construction and upgrade of two sewage treatment plants with a combined capacity of about 440,000 cm/d.

    The scheme is being procured on an engineering, procurement and construction (EPC) basis with a long-term operations component. 

    It is understood that contracts for LTOM11 and LTOM12 will be awarded in May.

    In January, a consortium of United Water (China), Prosus Energy (UAE) and Armada Holding (Saudi Arabia) won the main contract for the Northern Cluster Sewage Treatment Plants Package 10 (LTOM10).

    This contract was the first to be awarded under the second phase of NWC’s rehabilitation of sewage treatment plants programme.

    NWC previously awarded $2.7bn-worth of contracts for the first phase of its LTOM programme. This comprises nine packages covering the treatment of 4.6 million cm/d of sewage water for the next 15 years.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15670141/main.jpg
    Mark Dowdall
  • Dubai tenders Al-Maktoum airport superstructure

    17 February 2026

     

    Dubai Aviation Engineering Projects (DAEP) has tendered three packages covering superstructure works for the first phase of the expansion of Al-Maktoum International airport.

    Interested bidders have until 23 March to submit their proposals.

    MEED understands that the selected contractor will undertake superstructure works on three packages:

    • West Terminal and concourse one
    • Concourse two
    • Concourse three

    Construction on these packages began in November last year, when DAEP formally selected a contractor to deliver the substructure works.

    According to an official description on DAEP’s website, the expanded airport’s West Terminal will be a seven-level, 800,000-square-metre facility with an annual capacity of 45 million passengers.

    It will be the second of three terminals at Al-Maktoum International airport, linked to the airside by a 14-station automated people-mover (APM) system.

    In August, MEED exclusively reported that DAEP had received bids from firms to build the APM at the airport. 

    The system will run under the apron of the entire airfield and the airport’s terminals. It will consist of several tracks, taking passengers from the terminals to the concourses.

    Four underground stations will be built as part of the first phase. The overall plan includes 14 stations across the airport.

    The airport’s construction is planned to be undertaken in three phases. The airport will cover an area of 70 square kilometres (sq km) south of Dubai and will have five parallel runways, five terminal buildings and 400 aircraft gates.

    It will be five times the size of the existing Dubai International airport and will have the world’s largest passenger-handling capacity of 260 million passengers a year. For cargo, it will have the capacity to handle 12 million tonnes a year.

    Construction progress

    Construction on the first phase has already begun. In May last year, MEED exclusively reported that DAEP had awarded a AED1bn ($272m) deal to UAE firm Binladin Contracting Group to construct the second runway at the airport.

    The enabling works on the terminal are also ongoing and are being undertaken by Abu Dhabi-based Tristar E&C.

    Construction on the project’s first phase is expected to be completed by 2032.

    The government approved the updated designs and timelines for its largest construction project in April 2024.

    In a statement, the authorities said the plan is for all operations from Dubai International airport to be transferred to Al-Maktoum International within 10 years.

    The statement added that the project will create housing demand for 1 million people around the airport.

    In September 2024, MEED exclusively reported that a team comprising Austria’s Coop Himmelb(l)au and Lebanon’s Dar Al-Handasah had been confirmed as the lead masterplanning and design consultants on the expansion of Al-Maktoum airport.

    Project history

    The expansion of Al-Maktoum International, also known as Dubai World Central (DWC), is a long-standing project. It was officially launched in 2014, with a different design from the one approved in April 2024. At that time, it involved building the biggest airport in the world by 2050, with the capacity to handle 255 million passengers a year.

    An initial phase, due to be completed in 2030, involved increasing the airport’s capacity to 130 million passengers a year. The development was to cover an area of 56 sq km.

    Progress on the project slipped as the region grappled with the impact of lower oil prices and Dubai focused on developing the Expo 2020 site. Tendering for work on the project then stalled with the onset of the Covid-19 pandemic in early 2020.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15669879/main.jpg
    Yasir Iqbal
  • Contractors submit revised prices for Habshan 7 project

    17 February 2026

     

    Adnoc Gas has received revised commercial proposals from contractors for engineering, procurement and construction (EPC) works on a major project to add a new gas processing train at its Habshan complex in Abu Dhabi.

    Adnoc Gas, the natural gas processing business of Abu Dhabi National Oil Company (Adnoc Group), processes about 10 billion standard cubic feet a day (cf/d) of gas across several sites, including its Asab, Bab, Bu Hasa and Habshan facilities, as well as a natural gas liquids (NGL) fractionation plant at Ruwais.

    The Habshan complex is one of the largest gas processing facilities in the UAE and across the Middle East and North Africa. Its output capacity is 6.1 billion cf/d. The complex comprises five trains and 14 processing units that receive gas feedstock from onshore and offshore fields in Abu Dhabi.

    With Adnoc Group pressing ahead with its P5 programme to raise oil production potential to 5 million barrels a day by 2027, high volumes of associated gas are set to enter the grid.

    The new train at the Habshan complex, which Adnoc Gas expects to commission in 2029, will play a key role in handling these additional gas volumes.

    MEED previously reported that contractors had submitted commercial bids for the new Habshan 7 gas train project to Adnoc Gas by the deadline of 10 December.

    Following an initial evaluation of commercial bids received, Adnoc Gas sought “best offers” from contractors for the project. Bidders submitted their revised prices by 6 February, according to sources.

    The following contractors are understood to be competing for the Habshan 7 project’s main EPC contract, as per sources:

    • Enppi (Egypt) / Petrojet (Egypt)
    • Jereh (China)
    • Larsen & Toubro Energy Hydrocarbon (India)
    • Petrofac (UK)
    • Sinopec (China)
    • Wison Engineering (China)

    MEED previously reported that contractors submitted technical bids for the project to Adnoc Gas by the deadline of 6 October.

    Adnoc Gas intends to install the Habshan 7 train adjacent to the Habshan 5 train. This will enable the new train to utilise the ullage in the Habshan 5 sulphur recovery and tail gas treatment units and optimise operations.

    The scope of work on the Habshan 7 gas train project covers the EPC of the following units:

    • New high-pressure pipeline from the main Habshan complex to the new gas train
    • Separation and condensate stabiliser unit
    • Acid gas removal unit
    • Mercury removal unit
    • Deep NGL recovery unit
    • Sales gas and residue gas compressor
    • NGL product storage and transfer pump, as well as metering skid
    • Utility units (IA, N2, PW, FW, steam generation, DM)
    • Flare unit, to be located in Habshan 5 on common derrick
    • Flare gas recovery package
    • Water treatment package
    • Non-process buildings, to be located outside the Habshan 5 train
    • Power generation system
    • NGL pipeline from Habshan 5 to Ruwais, based on an existing pipeline assessment
    • Sales gas pipeline from Habshan 5 to sales gas network.

    UK-headquartered Wood Group has performed the concept study and initial engineering design for the project.

    The Habshan 7 gas train project represents the third phase of Adnoc Gas’ Rich Gas Development programme and is estimated to be valued at $3.5bn-$4bn, according to the company’s chief financial officer, Peter Van Driel.

    In a recent call with journalists to discuss Adnoc Gas’ financial results for the full year and fourth quarter of 2025, Van Driel said Adnoc Gas expects to achieve a final investment decision on the Habshan 7 gas train project, which is designed to increase the company’s production of high-value liquids such as liquefied petroleum gas, naphtha and condensates, in the first quarter of 2026.

    Adnoc Gas issued the main EPC tender for the new Habshan 7 gas train project to contractors between 5 and 8 August, MEED previously reported. It later extended the initial technical bid submission deadline from mid‑September to 6 October.

    In April, MEED reported that Adnoc Gas had started an early engagement process with contractors for the EPC tendering phase of the Habshan 7 gas train project.

    Prior to that, Adnoc Gas issued an expression of interest (EoI) document for the project in March, to which contractors submitted responses by 8 April.

    Separately, Adnoc Gas also completed the EoI exercise for early civil and site preparation works on the Habshan 7 project in June, and is understood to have issued the main tender in the third quarter.

    ALSO READ: Adnoc Gas stalls decision on Ruwais NGL project

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15663150/main5247.jpg
    Indrajit Sen
  • Dubai seeks contractors for Jebel Ali STP expansion

    16 February 2026

    Dubai Municipality has invited contractors to prequalify for a contract covering the expansion of the Jebel Ali sewage treatment plant (STP) phases one and two.

    The upgraded facility will be capable of treating an additional sewage flow of 100,000 cubic metres a day (cm/d).

    The scope includes the design, construction and commissioning of infrastructure and systems required to support the increased capacity.

    The bid submission deadline is 2 April.

    Located on a 670-hectare site in Jebel Ali, the original wastewater facility has a treatment capacity of about 675,000 cm/d following the completion of phase two in 2019, combining approximately 300,000 cm/d from phase one and 375,000 cm/d from phase two.

    As MEED understands, the project is part of long-term plans to treat about 1.05 million cm/d a day once all future phases are completed.

    The main element of the expansion, which is estimated to cost $300m, involves modifications to the secondary treatment process at Jebel Ali STP phase two.

    This includes conversion to Moving Bed Biofilm Reactor or Integrated Fixed-Film Activated Sludge systems.

    The project also includes decommissioning existing surface aerators. New blowers and associated works will be installed as part of the upgrade.

    UK-headquartered KPMG and UAE-based Tribe Infrastructure are serving as financial advisers on the project.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15661388/main.jpg
    Mark Dowdall
  • AD Ports to develop Douala port in Cameroon

    16 February 2026

    Abu Dhabi’s AD Ports Group and Africa Ports Development (APD) have signed an agreement to design, build and operate a new dry bulk terminal at the Port of Douala in Cameroon.

    AD Ports Group will invest about AED320m ($87m) in the development of the terminal’s first phase, which will comprise two berths and more than 450 metres of quay wall, with an annual handling capacity of about 4 million tonnes of dry bulk cargo.

    Construction is expected to begin this year, and the first phase is slated for completion in 2028.

    The concession period is 30 years.

    AD Ports Group has committed to long-term investments and operations across Africa, including in Egypt, Morocco, Tunisia, Kenya, Tanzania, Angola and the Republic of the Congo.

    The latest announcement comes shortly after it signed an agreement with Jordan’s Aqaba Development Corporation (ADC) to manage and operate the Aqaba multipurpose port.

    AD Ports will manage and operate the port under a 30-year concession agreement.

    In December last year, AD Ports Group signed a shareholder agreement with Tajikistan’s private industrial firm Avesto Group to establish a new joint venture that will provide integrated logistics and freight forwarding services across Tajikistan.

    Under the agreement, the joint venture will initially operate as an asset-light freight forwarder. It will have exclusive rights to consolidate and manage all freight and logistics activities across Avesto Group’s subsidiaries, while also offering services to third-party customers in the wider market.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/15661385/main.jpg
    Yasir Iqbal