Saipem wins $4bn Qatar offshore gas project contract

16 September 2024

Register for MEED's 14-day trial access 

QatarEnergy LNG, a subsidiary of state enterprise QatarEnergy, has awarded Italian contractor Saipem an estimated $4bn engineering, procurement, construction and installation (EPCI) contract as part of the second phase of its North Field Production Sustainability (NFPS) project.

Saipem has won combined packages COMP3A and COMP3B of the NFPS project’s second phase, it said in a statement on 16 September.

The scope of work on the combined packages encompasses EPCI of a total of six platforms, approximately 100 kilometres (km) of corrosion resistance alloy rigid subsea pipelines of 28-inches and 24-inches diameter, 100km of subsea composite cables, 150km of fibre optic cables and several other subsea units.

The aim of the second phase of the NFPS project is to support QatarEnergy’s North Field liquefied natural gas (LNG) expansion programme.

The second NFPS phase will mainly involve building gas compression facilities to sustain and gradually increase gas production from Qatar’s offshore North Field gas reserve over the long term.

This is the second contract win for Saipem in the NFPS project’s second phase, which consists of four main EPCI packages.

Prior to winning combined packages COMP3A and COMP3B, QatarEnergy LNG awarded Saipem a $4.5bn order in October 2022 to build and install gas compression facilities.

The main scope of work on the package, which is known as EPCI 2, covers two large gas compression complexes that will comprise decks, jackets, topsides, interconnecting bridges, flare platforms, living quarters and interface modules.

The gas compression complexes – CP65 and CP75 – will weigh 62,000 tonnes and 63,000 tonnes, respectively, and will be the largest fixed steel jacket compression platforms ever built.

NFPS first phase

Saipem is executing the main EPCI works on the entire first phase of the NFPS project, which consists of two packages.

Through the first phase of the NFPS scheme, QatarEnergy LNG aims to increase the early gas field production capacity of the North Field offshore development to 110 million tonnes a year.

QatarEnergy LNG, formerly Qatargas, awarded Saipem the contract for the EPCI package in February 2021. The package is the larger of the two NFPS phase one packages and has a value of $1.7bn.

Saipem’s scope of work on the EPCI package encompasses building several offshore facilities for extracting and transporting natural gas, including platforms, supporting and connecting structures, subsea cables and anti-corrosion internally clad pipelines.

The scope of work also includes decommissioning a pipeline and other significant modifications to existing offshore facilities.

In addition, in April 2021, QatarEnergy LNG awarded Saipem two options for additional work within the EPCI package, worth about $350m.

QatarEnergy LNG awarded Saipem the second package of the NFPS phase one project, estimated to be worth $1bn, in March 2021.

Saipem’s scope of work on the package, known as EPCL, mainly covers installing three offshore export trunklines running almost 300km from their respective offshore platforms to the QatarEnergy LNG north and south plants located in Ras Laffan Industrial City.

Saipem has performed the front-end engineering and design work on the main production package of the first phase of the NFPS as part of a $20m contract that it was awarded in January 2019. This provided a competitive advantage to the Italian contractor in its bid to win the package.

Saipem expects to complete work on both packages of the first phase of the NFPS project by the end of 2024.

https://image.digitalinsightresearch.in/uploads/NewsArticle/12543882/main5022.jpeg
Indrajit Sen
Related Articles
  • Mitsubishi Power to supply Rumah 1 and Nairiyah 1 turbines

    21 November 2024

    The developer and engineering, procurement and construction (EPC) teams that will develop and build the Rumah 1 and Nairiyah 1 combined-cycle gas turbine (CCGT) schemes in Saudi Arabia are understood to have partnered with Tokyo-headquartered Mitsubishi Power for the gas turbines to power the plants.

    The Rumah 1 and Nairiyah 1 independent power projects (IPPs) will each have a capacity of 1,800MW.

    The principal buyer, Saudi Power Procurement Company (SPPC), previously indicated that the power plants would operate using natural gas combined-cycle technology with a carbon-capture unit readiness provision.

    A consortium comprising Saudi Electricity Company (SEC), Riyadh-based utility developer Acwa Power and South Korea’s Korea Electric Power Corporation (Kepco) won the contract to develop the two CCGT independent power projects (IPP).

    The consortium signed the power-purchase agreements (PPAs) for the two projects with the SPPC on 18 November.

    China’s Sepco 3 and South Korea’s Doosan Enerbility will undertake the EPC contract for the projects, as MEED reported.

    The SEC, Acwa Power and Kepco team offered a levelised electricity cost (LCOE) of $cents 4.5859 a kilowatt-hour (kWh) for Rumah 1, and $cents 4.6114/kWh for Nairiyah 1.

    Acwa Power said that the two IPPs will require a combined investment of approximately SR15bn ($4bn). The IPPs are expected to reach commercial operations in Q2 2008. 

    Rumah 1 is located in the Central Region in Riyadh and is part of the previously planned Riyadh Power Plant 15 (PP15). Nairiyah 1 is located in the Eastern Region.

    SPPC received bids for the contracts for four thermal IPPs – the other two being the similarly configured Rumah 2 and Nairiyah 2 – on 21 August.

    The four power generation facilities will be developed using a build-own-operate (BOO) model over 25 years. 

    SPPC’s transaction advisory team for the Rumah 1 and 2 and Al-Nairiyah 1 and 2 IPP projects comprises US/India-based Synergy Consulting, Germany’s Fichtner and US-headquartered Baker McKenzie. 

    Najm and Mitsubishi Power

    The Rumah and Nairiyah 2 orders will be the second one this year for Mitsubishi Power, which in August confirmed receiving an order from South Korea's Samsung C&T Corporation to provide its M501JAC hydrogen-ready CCGT for the Najim industrial steam and electricity cogeneration plant in Jubail in the Eastern Province of Saudi Arabia.

    The M501JAC gas turbine will enable the new cogeneration plant to generate up to 475MW of power and approximately 452 tonnes an hour of steam.

    Samsung C&T is the engineering, procurement and construction (EPC) contractor for the project, which is being developed by a team comprising Abu Dhabi National Energy Company (Taqa) and Japanese power generation company Jera, the same team that won the contract to develop and operate the Rumah 2 and Nairiyah 2 CCGT contracts.

    Photo credit: Mitsubishi Power (for illustrative purposes only)

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12964755/main.jpg
    Jennifer Aguinaldo
  • Shanghai Electric to build 2GW Al-Sadawi solar project

    21 November 2024

    A developer team that includes Abu Dhabi Future Energy Company (Masdar), South Korea's Korea Electric Power Corporation (Kepco) and China's GD Power Development has tapped a Chinese firm to undertake the engineering, procurement and construction (EPC) contract for a 2GW solar project in Saudi Arabia.

    According to an industry source, Shanghai Electric will undertake the EPC work for the 2,000MW Al-Sadawi solar independent power project (IPP).

    The winning developer consortium signed the power-purchase agreement (PPA) with the principal buyer, Saudi Power Procurement Company (SPPC), for the project on 18 November.

    It offered a levelised cost of electricity of hals 4.847 ($c1.29) a kilowatt-hour (kWh) for the contract to develop the scheme, which is located in the Eastern Province.

    The second-lowest bidder is a team that includes China's SPIC Huanghe Hydropower Development and France's EDF Renewables, which offered to develop the project for $c1.31/kWh.

    SPPC received six proposals from companies for the contracts to develop and operate four solar photovoltaic (PV) IPP projects under the fifth procurement round of the kingdom's National Renewable Energy Programme (NREP) in August.

    According to SPPC, the lowest and second-lowest bidders in the remaining schemes under round five of the NREP are:

    Al-Masaa solar IPP (Hail): 1,000MW

    • L1: SPIC/EDF Renewables (France): $c1.36/kWh
    • L2: AlJomaih Energy & Water (local) / TotalEnergies Renewables (France): $c1.40/kWh

    Al-Hinakiyah 2 solar IPP (Medina): 400MW

    • L1: SPIC/EDF: $c1.51/kWh
    • L2: Masdar/Kepco/Nesma:  $c1.57/kWh

    Rabigh 2 solar IPP (Mecca): 300MW

    • L1: AlJomaih Energy & Water / TotalEnergies Renewables: $c1.78/kWh
    • L2: Masdar/Kepco/Nesma: $c1.89/kWh

    Saudi utility developer Acwa Power is not among the 23 companies that were prequalified to bid for the fifth round of NREP projects.

    US/India-based Synergy Consulting is providing financial advisory services to SPPC for the NREP fifth-round tender. Germany's Fichtner Consulting is providing technical consultancy services.

    The round five solar PV IPPs take the total capacity of publicly tendered renewable energy projects in Saudi Arabia to over 10,300MW. Solar PV IPPs account for 79%, or about 8,100MW, of the total capacity.

    Four wind IPPs, one of which has yet to be awarded, account for the remaining capacity.

    SPPC is procuring 30% of the kingdom's target renewable energy by 2030. Saudi sovereign wealth vehicle the Public Investment Fund (PIF) is procuring the rest through the Price Discovery Scheme. The PIF has appointed Acwa Power, which it partly owns, as principal partner for these projects.

    The Saudi Energy Ministry recently said that the kingdom plans to procure 20,000MW of renewable energy capacity annually, starting this year and until 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12964642/main.gif
    Jennifer Aguinaldo
  • Chinese firm wins 2.6GW Saudi inverter deals

    21 November 2024

    The engineering, procurement and construction (EPC) contractors implementing two of Saudi Arabia Public Investment Fund's (PIF) cluster-four solar photovoltaic (PV) projects have awarded contracts for the supply of inverters to China's Sineng Electric.

    The Jiangsu-headquartered company secured an order for 1GW of inverters from China Energy Engineering Group Consortium for the Haden solar PV project and 1GW from Indian contracting firm Larsen & Toubro for the Al-Khushaybi solar PV project.

    Sineng will provide its 8.8MW MV turnkey stations, each comprising 2 units of 4.4MW central inverter, a transformer and a ring main unit (RMU) for the solar projects.

    Designed to "withstand extreme temperatures [of] up to 51ºC… and strong sand-laden winds", the 8.8MW MV turnkey stations are expected to deliver consistent and reliable performance throughout the solar PV plants' operational lifespan.

    The PIF awarded the contracts to develop three cluster-four solar PV projects to a consortium led by Saudi utility developer Acwa Power earlier this year.

    The developer consortium, which includes PIF-backed Water & Electricity Holding Company (Badeel) and Saudi Aramco Power Company (Sapco), reached financial close for the three projects, which have a total combined capacity of  5,500MW, in September.

    The solar PV projects and their capacities are:

    • Haden solar PV (Mecca): 2,000MW
    • Muwayh (Mecca): 2,000MW
    • Al-Khushaybi (Qassim): 1,500MW

    The respective project companies that have been formed for the three projects are Buraiq Renewable Energy Company, Moya Renewable Energy Company and Nabah Renewable Energy Company.

    Acwa Power’s effective shareholding in each of the three projects is 35.1%. Badeel owns 34.9% and Sapco, a subsidiary of state majority-owned oil giant Saudi Aramco, owns the remaining shares.

    The project companies signed financing documents amounting to SR9.7bn ($2.6bn), Acwa Power previously announced. The financing duration is 27.3 years.

    The three projects are being procured under the National Renewable Energy Programme's (NREP) Price Discovery Scheme, which is being implemented by the PIF.

    Under this scheme, the projects are directly negotiated with Acwa Power and its selected partners.

    The three new solar PV facilities have a combined value of SR12.3bn ($3.3bn) and are expected to become operational in the first half of 2027.

    The PIF and its partners are currently developing several solar PV projects with a total capacity of 13.6GW, involving over $9bn in investments. These joint projects – including Sudair, Shuaibah 2, Ar Rass 2, Al-Kahfah and Saad 2 – are intended to enable and support the local private sector through domestic supply-chain participation.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12963512/main.jpg
    Jennifer Aguinaldo
  • Marubeni-led team reaches 1.1GW wind financial close

    21 November 2024

    A developer consortium led by Japan's Marubeni Corporation has reached financial close with a team of lenders for the contracts to develop two wind independent power producer (IPP) projects in Saudi Arabia.

    Marubeni and the local Ajlan & Bros won the contracts to develop the first two wind schemes of the kingdom's National Renewable Energy Programme (NREP) round four, the 600MW Al-Ghat and the 500MW Waad Al-Shamal wind IPPs, in May this year.

    According to an industry source, the following lenders will provide financing for the two projects:

    • Japan Bank for International Cooperation (Jbic)
    • Standard Chartered Bank (UK)
    • Sumitomo Mitsui Trust Bank (Japan)
    • Commercial Bank of Dubai (UAE)

    The consortium agreed to develop and operate the 600MW Al-Ghat wind IPP project with a new world-record-low levelised electricity cost (LCOE) from wind power of $cents 1.56558 a kilowatt-hour (kWh), or about 5.87094 halalas/kWh.

    The 500MW Waad Al-Shamal project has also achieved a second world-record-low tariff for wind power of $cents 1.70187/kWh or 6.38201 halalas/kWh, the energy ministry announced in May.

    The tariff achieved for Al-Ghat is almost 22% lower compared to the LCOE agreed for Saudi Arabia's first wind IPP, the 400MW Dumat Al-Jandal scheme, which a team comprising the UAE's Abu Dhabi Future Energy (Masdar) and France's EDF Renewables won in 2019.

    Marubeni will own 51% while Ajlan will maintain a 49% stake in the project company that will implement the projects.

    The Japanese-local team has appointed Power Construction Corporation of China (Power China) and Sepco 3 to undertake the wind projects' engineering, procurement and construction (EPC) contract.

    MEED previously reported that the same developer team is expected to win the contract to develop and operate the third wind scheme of NREP round four, the 700MW Yanbu wind IPP.

    The contract could be awarded before the year-end, according to a source.

    It is understood that other teams, separately led by local utility developer Acwa Power, France's Engie and EDF Renewables, submitted proposals for the contract to develop the Yanbu wind IPP scheme.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12959899/main.jpg
    Jennifer Aguinaldo
  • L&T signs $400m Riyadh-Kudmi transmission contract

    20 November 2024

    India-headquartered contracting firm Larsen & Toubro (L&T) has signed a contract with state utility Saudi Electricity Company (SEC) for the construction of a new 500-kilovolt (kV) high-voltage direct current (HVDC) project in Saudi Arabia.

    The contract is valued at SR1.51bn ($400m).

    The project involves constructing a section of the HVDC transmission lines from the Riyadh Power Plant 14 (PP14) in the capital to the southwest coastal region of Kudmi.

    MEED understands that the contract was awarded on a lump-sum turnkey basis.

    The other two sections of the HVDC transmission project, which has a total length of 1,089-kilometres (km), have been awarded to South Korea's Hyundai Engineering & Construction Company and Saudi Services for Electro Mechanic Works (SSEM).

    Earlier this month,  Hyundai E&C announced winning a KRW1tn ($725m) contract as part of the PP14-Kudmi HVDC network project. Hyundai E&C's portion of the total package extends over 369km, and is expected to be completed by January 2027.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/12955076/main.jpg
    Jennifer Aguinaldo