Royal commission engages with contractors for Mecca metro
9 September 2025

Register for MEED’s 14-day trial access
The Royal Commission for Makkah City & Holy Sites (RCMC) has invited contractors to attend an early market engagement meeting for its long-planned metro network in the holy city.
In an explanatory document inviting companies to attend the 21 September event, the RCMC’s General Transport Centre says it is seeking to gauge market interest in the multibillion-dollar project and obtain feedback on its proposed procurement approach.
MEED reported in June that the project was restarting. Current plans envisage a four-line network, named lines A-D, with 89 stations and three depots, to be implemented over three phases between 2032 and 2045.
Project scope
Stage 1 focuses on lines B and C, involving 2.4 kilometres of tunnelling under the Masar project and integration with the existing Mashaer line.
Running a length of just over 62km, it will comprise 31 stations, 21 of which will be underground, including three iconic stations. A total of 19.5km will run through tunnels, while 41.2km will be elevated, with the remainder at grade level.
Daily passenger capacity on the 66 required trainsets is projected to be about 450,000, equating to an annual ridership of 171 million.
The 84.7km-long second phase, due to be operational by 2038, will extend the two lines towards the outskirts of Mecca, and involves the construction of the initial inner, central segments of lines A and D.
Totalling 61.1km elevated and 18.6km underground, it is planned to have an additional 45 stations serving the two new lines, as well as two depots and a potential interconnection with the planned Saudi Landbridge.
The 59 trainsets for phase 2 will increase the network’s projected total yearly passenger capacity to more than 500 million.
Phase 3 covers the elevated 36km extension of lines A and D and involves the procurement of a further 72 trainsets to increase the network’s ultimate passenger capacity to 1.2 million daily and 642 million annually by its completion in 2045.
Associated development
The metro plan also envisages several transit-oriented developments at different points on the route. These will typically comprise commercial, residential and retail elements to maximise the investment case.
The client’s proposed procurement approach involves three distinct packages: civil and systems works, TODs, and operations and maintenance.
The initial concept calls for some of the project to be delivered on a public-private partnership (PPP) basis, wherein the private sector, through special purpose vehicles, will part-finance, build, operate and then transfer commercially viable elements of the scheme.
Following the 21 September job explanation meeting, RCMC will take questions and feedback from interested companies and says it hopes to publish the results of the early market engagement in early November.
The then-called Mecca Mass Rail Transit Company (MMRTC) first launched the metro project in 2013; however, the scheme has faltered for more than a decade due to funding issues, land acquisition challenges and scope changes.
The relaunch of the procurement process raises hopes that the project will now come to fruition, although it is likely to be at least 18 months before any definitive works are expected to start.
Mecca is home to Saudi Arabia’s first metro, the nine-station, 18km-long Mashaer line, which opened in 2010. It operates only seven days a year during Hajj, but carries more than 2 million pilgrims during that time.
Some 30 million pilgrims visit the city each year, with this number set to grow. The presence of a known, quantifiable and growing demand base will help facilitate the use of a PPP mechanism should the framework be adopted.
READ THE SEPTEMBER 2025 MEED BUSINESS REVIEW – click here to view PDF
Doha’s Olympic bid; Kuwait’s progress on crucial reforms reinforces sentiment; Downstream petrochemicals investments take centre stage
Distributed to senior decision-makers in the region and around the world, the September 2025 edition of MEED Business Review includes:
|
> OLYMPICS: Qatar banks on infrastructure for Olympic bid
> QATAR TOURISM: Olympics bid aims to extend tourism gains
> CURRENT AFFAIRS: Syria charts post-war reconstruction course
> INDUSTRY REPORT: Regional chemicals spending set to soar
> DOWNSTREAM: Adnoc set to become a chemicals major
> SAUDI STADIUMS: Stadiums become main event for Saudi construction
> CONSTRUCTION: Middle East to be a growth leader for global construction
> LEADERSHIP: Dubai’s sea-air logistics model powers resilient trade
> KUWAIT MARKET FOCUS: Kuwait’s political hiatus brings opportunity
|
Exclusive from Meed
-
Chinese contractor wins Morocco solar plant deal10 August 2026
-
Aramco puts out fire at Jizan refinery after Houthi strike10 August 2026
-
Shamal picks Dutco for Dubai Zoo site homes10 August 2026
-
WEBINAR: Mena Oil & Gas Projects Market 2026-2710 August 2026
-
Spanish firm renews Yanbu desalination O&M contract10 August 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Chinese contractor wins Morocco solar plant deal10 August 2026
China Harbour Engineering Company (CHEC), a subsidiary of China Communications Construction Company (CCCC), has won a contract to build a solar photovoltaic (PV) power plant in Fez in northern Morocco.
Known as GreenPower Morocco 4 (GPM4), the project is being developed by Moroccan company GPM Holding through its utility-scale solar subsidiary GPM Parks.
The project covers engineering design, equipment procurement and installation, construction of an operation and maintenance building, grid connection and commissioning. It also includes upgrades to the associated substation.
According to CHEC, the completed plant will supply electricity to the local grid, although it did not disclose the project’s capacity or contract value.
The project is being developed under Law 13-09, which provides Morocco’s framework for private renewable energy generation.
According to its website, GPM Holding is also developing another solar PV project called GreenPower Morocco 2 (GPM2). This follows the completion of its first solar project, the 34MW project (GPM1) commissioned in Tangier in 2024.
GPM1 was developed by Green Power Morocco, a special purpose vehicle owned by GPM Holding and UAE-based Amea Power. The $30m project covers 75 hectares and includes 91,000 PV panels. It is expected to generate about 66,149MWh a year.
The project has a 25-year power purchase agreement in place with Amendis, a subsidiary of Veolia Morocco. PowerChina was the main engineering, procurement and construction (EPC) contractor.
Chinese contractors have previously been involved in other projects in Morocco’s renewable energy sector.
Shandong Electric Power Construction Company (Sepco 3), a subsidiary of PowerChina, was part of the EPC consortium for the 200MW Noor 2 concentrated solar plants and 150MW Noor 3 concentrated solar power projects at the Noor Ouarzazate complex.
New contract awards have been limited in Morocco in 2026, although six solar PV plants are now in the execution stage under phases one and two of the 305MW Noor Atlas solar PV programme.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18263680/main.jpg -
Aramco puts out fire at Jizan refinery after Houthi strike10 August 2026
Saudi Aramco said it had extinguished a fire that broke out at its Jizan refinery on Saudi Arabia’s Red Sea coast after the facility was hit in drone strikes by Yemen-based Houthi rebels on 9 August.
The kingdom’s Ministry of Energy said the fire occurred at an Aramco refinery facility in Jizan and that emergency authorities had completed the necessary procedures to deal with the incident.
The energy ministry did not say what started the fire, saying only that the incident caused no injuries.
The Houthi rebels later claimed responsibility for the attack.
The province of Jizan lies close to Saudi Arabia’s border with Yemen and has repeatedly been targeted by the Houthis in attacks on the kingdom’s energy infrastructure.
The strike on the Jizan refinery was the second attack on the facility by the Houthis in as many weeks. Aramco shut the refinery on 27 July following a similar drone strike, which, according to media reports, damaged the integrated gasification combined-cycle unit and tank farm at the complex.
On a call with investors to discuss Aramco’s second-quarter results, CEO Amin Nasser said recent attacks on the company’s facilities in the world’s top oil-exporting country had caused some disruption to production, but that he was confident operations could be restored quickly. He said the attacks had had no material operational or financial impact.
Jizan refinery complex
Saudi Aramco’s sprawling Jizan refinery complex entered operations in 2021.
Aramco undertook the estimated $16bn-plus project in late 2010. The scheme consists of a refinery with an output capacity of 400,000 barrels a day (b/d), a major marine terminal and a 4GW combined-cycle power plant in Baish, in Saudi Arabia’s southwestern Jizan region.
The Jizan refinery covers an area of 12 square kilometres. The complex processes Arabian Heavy and Arabian Medium crude grades to produce 80 million b/d of gasoline, 250 million b/d of diesel and more than 1 million tonnes a year of petrochemical products such as benzene and paraxylene.
A multiple-pier marine terminal supports the supply of crude oil from oil fields located mainly in the kingdom’s Eastern Province to the refinery, as well as the export of surplus refined products to overseas markets. The terminal has been designed to accommodate very large crude carriers.
A 4,000MW combined-cycle power plant uses approximately 90,000 b/d of vacuum residue from the refinery to generate electricity, hydrogen and water for the refinery, while conveying excess power to the national grid.
The hydrocracker unit comprises two parallel trains with a combined capacity of 54,500 b/d. The diesel hydrotreater plant comprises two trains, each with a capacity of 87,500 b/d.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18262347/main.jpg -
Shamal picks Dutco for Dubai Zoo site homes10 August 2026
Dubai-based Shamal Holding has awarded local contractor Dutco Construction the main construction works contract for a low-rise residential project on the site of the former Dubai Zoo in Jumeirah 1.
The project will comprise 90 low-rise homes and is designed as a residential leasing community that will remain under Shamal’s ownership, with all homes offered for premium leasing.
The development will retain mature trees from the former zoo and is planned around shared courtyards, landscaped open spaces and a central park. Residents will have access to a clubhouse, wellness area, children’s play area, family pool, lounge and gym.
The architect is DXB Lab. The local H&H is the development manager for the project.
Dutco has previously worked with Shamal on infrastructure elements of the Dubai Harbour and Dubai Harbour Marinas developments.
Shamal’s wider real estate portfolio includes the Naia Island, Dubai Harbour and Nad Al-Sheba Gardens developments. The company also holds hospitality and leisure assets, including partnerships with Jumeirah, Hilton and Baccarat, and operates attractions such as Skydive Dubai and Deep Dive Dubai.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18262386/main.png -
WEBINAR: Mena Oil & Gas Projects Market 2026-2710 August 2026
Webinar: Mena Oil & Gas Projects Market 2026-27
Thursday 27 August 2026 | 11:00 AM GST | Register now
Agenda:
- Summary of the Mena oil, gas and petrochemicals projects market
- Overview of major megaprojects, including project programmes
- Analysis of active contracts and spending to date
- Review of top contracts by work already awarded
- Long-term capital expenditure outlays and forecasts
- Key contracts expected to be tendered and awarded over the next 18 months
- Leading clients, contractors and market participants
- Spending by segment: oil, gas and petrochemicals (upstream, downstream, onshore and offshore)
- Audience Q&A
Hosted by: Indrajit Sen, MEED’s oil & gas editor
https://image.digitalinsightresearch.in/uploads/NewsArticle/18260597/main.gif -
Spanish firm renews Yanbu desalination O&M contract10 August 2026
Spain’s Aqualia has announced it has renewed a contract to operate and maintain three floating desalination plants in Yanbu on Saudi Arabia’s Red Sea coast.
The contract was awarded by the National Shipping Company of Saudi Arabia (Bahri) and will run until 14 September 2028, with an option to extend for a further two years.
The three reverse osmosis (RO) plants are mounted on barges and have a combined production capacity of 150,000 cubic metres a day (cm/d). Each plant has a capacity of 50,000 cm/d.
The three plants were originally deployed at Al-Shuqaiq and are designed to be relocated along Saudi Arabia’s coastline according to water demand. The barges are currently located at Yanbu.
The $255m floating desalination project was commissioned for the Saudi Water Authority in 2022, with Bahri as the developer and UAE-based Metitio as the main contractor.
Bahri is publicly listed on the Saudi Exchange but has significant government ownership, with the Public Investment Fund (PIF) holding 22.5% and Saudi Aramco Development Company owning 20% of the company.
Aqualia is providing operation and maintenance services in Saudi Arabia through its joint venture Haji Abdullah Alireza Integrated Services Company (Haaisco), in which it holds a 51% stake.
https://image.digitalinsightresearch.in/uploads/NewsArticle/18259350/main.jpg