Riyadh to sustain power spending

12 March 2024

Latest news on Saudi Arabia’s power sector:

Neom to start qualification for $2.7bn hydropower scheme
Saudi power buyer holds Remah and Nairiyah meetings
Enowa gives extra day for Gayal and Shiqri bidders

Gayal and Shiqri bidders race to meet deadlines
Neom extends Duba Energy Park bid deadline
Data centre activity soars in Saudi Arabia
US firm wins Al Kahfah solar tracker package
> Saudi-Omani team to set up transformers plant


 

The project pipeline in Saudi Arabia’s power generation sector continues to expand unabated.

The value of projects in execution or about to start construction has increased by 17% to $34bn compared to six months earlier, according to the latest available data from regional projects tracker MEED Projects.

The value of projects in the pre-execution phase similarly increased by 16% to reach $51bn during the same period. New schemes are expected to be announced in the coming 12-18 months, including power generation projects catering to the $500bn Neom development.

Two key factors underpin the ramp-up of both conventional and renewable energy generation capacity in the kingdom, notes a Dubai-based senior executive with an international developer.

“Saudi Arabia intends to become the renewable supplier of choice on the GCC grid,” the executive said, referring to the regional network linking the electricity grids of Bahrain, Kuwait, Oman, Qatar, the UAE and Saudi Arabia.

The second factor is the kingdom's push for industrialisation and urbanisation, including the adoption of electric vehicles and data centres.

“Saudi Arabia has very strong regulations to keep data within its domicile and the digitalisation needed to achieve the kingdom’s modernisation plans needs large data centres and corresponding electricity supply,” she notes.

Overall, Saudi Arabia awarded power generation contracts worth more than $16.1bn in 2023, which is higher than the total value of contracts awarded in the preceding eight years and nearly six times the value of contracts awarded in 2022.

The kingdom’s principal buyer, Saudi Power Procurement Company (SPPC) and its sovereign wealth vehicle, the Public Investment Fund (PIF), awarded the bulk of these contracts.

Shrinking renewables share

The share of renewable energy in the total value of awarded contracts shrunk to 28%, from about 82% in 2022, due to the award last year of the first gas-fired independent power producer (IPP) projects since 2016.

SPPC awarded a consortium comprising Saudi Electricity Company and Saudi utility developer Acwa Power the $3.9bn contract to develop and operate the Qassim 1 and Taiba 1 IPP projects in November 2023. Each combined-cycle gas turbine (CCGT) plant has a capacity of 1,800MW.

A team comprising the local Al Jomaih Energy & Water, France’s EDF and the local Buhur for Investment won the contract to develop the other pair of CCGT-based plants – the Taiba 2 IPP and Qassim 2 IPP schemes, each of which has a capacity of 1,800MW.

SPPC also awarded the contracts for the solar photovoltaic (PV) schemes under the fourth procurement round of the kingdom’s National Renewable Energy Programme (NREP).

A consortium that includes France's EDF Renewables, Abu Dhabi Future Energy Company (Masdar) and the local company Nesma won the contract to develop the 1,100MW Hinakiyah solar IPP project. A consortium led by China's Jinko Power won the contract to develop and maintain the 400MW Tubarjal solar IPP scheme.

The PIF, meanwhile, awarded contracts last year for the development of three solar PV schemes with a total combined capacity of 4.5GW to Acwa Power and its partner Water & Electricity Holding Company (Badeel). The 2GW Al Rass 2, 1.1GW Saad 2 and 1.4GW Al Kahfah solar PV IPPs require a total investment of about $3.4bn.

Unawarded projects

Following the award of these contracts, SPPC started the procurement process for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round, and four new CCGT schemes with a total combined capacity of 7.2GW.

Bids are due on 10 June for the 2GW Al Sadawi, 1GW Al Mas, 400MW Hinakiyah 2 and 300MW Rabigh 2 solar PV IPP schemes.

Bids are also due in late June for the Remah 1 and 2 and Al Nairiyah 1 and 2 gas-fired CCGTs.

As of early March, Neom’s utility subsidiary, Enowa, had received bids for two renewable energy engineering, procurement and construction (EPC) contracts, the 1.2GW Gayal wind farm and 800MW Shiqri solar farm.

Enowa is understood to be preparing a site for two CCGT plants to be built on a fast-track basis at Duba Energy Park. The first phase comprises a transportable gas turbine generator (GTG) with a capacity of 300MW, which is designed to deliver emergency power to Neom.

The second phase is a permanently installed 500MW facility comprising heavy-duty GTGs. Both are considered fast-track projects, with the first phase due for completion in early 2024 and the second phase in early 2025.

The first phase of a multi-gigawatt programme to build renewable energy capacity in Neom using a public-private partnership model is also expected to start soon.

Soaring costs

The raft of new projects coming to the pipeline is exerting pressure, particularly for the CCGT supply chain, experts tell MEED. “On average, the EPC prices have more than doubled since before the Covid-19 pandemic began,” says an executive working for an original equipment manufacturer (OEM).

The average EPC cost per kilowatt for CCGT plants with a capacity of over 1.5GW is understood to have reached approximately $750 a kilowatt in 2023, which is more than twice the average cost in 2019. EPC costs for smaller plants have similarly posted significant increases.

Industry sources say the turbine supply chain problem arises from the decision by some OEMs to reduce capacity over the past few years, driven by a combination of the Covid-19 pandemic and the threat of curtailed demand due to the push to decarbonise electricity systems.

The post-Covid-19 recovery, as well as the resurgence of demand for gas-fired power plants in the Middle East – and even in some countries in Europe – along with the expressed preference by most GCC clients for European-made gas turbines, has resulted in a seller’s market.

A Dubai-based OEM executive told MEED last year that its EU-made turbines are booked for several years, but order deliveries can still be shuffled between customers, so they do not expect major delays in delivering to clients. "It's definitely a seller's market right now for turbines. We have capacity in other regions like China, but customers prefer [turbines made in] EU factories”.

In comparison, the jury is still out on solar PV costs, although historical tariff data indicates a general upward trend between the record-low tariffs seen in 2021 and those submitted last year.

Transmission and distribution

Transmission and distribution (T&D) contracts exceeding a total of $12bn are under execution in Saudi Arabia, with an estimated $22.4bn in the pre-execution phase.

The value of contracts awarded in 2023, which sits at $4bn, exceeded the previous year’s total by 41%. The contract to build a high-voltage, direct current transmission system between Neom’s Oxagon industrial cluster and Yanbu is the largest T&D contract to have been awarded last year.

Volume-wise, 59 T&D contracts were awarded in Saudi Arabia last year compared to 64 in 2022.

Saudi Arabia has been gradually expanding the reach of its grid, both domestically – due to the development of new communities and industries and the growth of renewable energy capacity – as well as internationally.

Projects to link with Egypt and other countries in the GCC, as well as with Iraq and Jordan, are under way, while preliminary studies are ongoing to link the kingdom’s power grid further afield, including to the grids of India and Greece.

Energy storage and nuclear

A new project activity segment within Saudi Arabia’s power sector is emerging. SPPC intends to start the procurement process this year for the 2GW first phase of a project to procure 10GW of battery energy storage system (bess) capacity by 2030.

Bess comprises rechargeable batteries that can store and discharge energy from various sources when needed.

Saudi Arabia plans to locate its bess facilities near demand centres to boost the electricity grid's spinning reserves as more renewable energy is expected to enter its electricity production mix.

The 2GW first phase of the project entails building several plants at different locations, with individual capacities ranging from 50MW to 300MW each. 

Finally, the procurement process is moving – albeit slowly – on the Duwaiheen nuclear power plant, Saudi Arabia’s first large-scale nuclear power project. Bids for the main contract are due in late April, following several deadline extensions since the kingdom invited selected companies to bid for the contract in 2022.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11584212/main2905.gif
Jennifer Aguinaldo
Related Articles
  • Decarbonising the global energy grid

    3 May 2024

    As the effort to tackle the climate crisis continues, global demand for renewable energy has been increasing. Unfortunately, the windiest and sunniest parts of the world are not necessarily where the need for energy is highest. This is where transmission plays a big role, linking energy generation to energy use as a product of global interconnection, and diversifying production from renewable sources to create a steadier supply of clean power. 

    Transporting energy across vast distances is not easy though. From the regulatory complexities of navigating cross-border infrastructure projects to the high costs of financing and the need for long-term planning and advanced technical capabilities, the challenges involved in successfully deploying long-distance transmission projects are varied. Overcoming these challenges is not a single party affair, but requires close collaboration across government, industry and non-governmental organisations. 

    We conducted a study with nearly 600 industry experts from across the world who highlighted the pressing need for co-ordinated global action to rapidly develop grid infrastructure. Integrating renewable energy into existing grids was cited by participants as one of the most significant barriers to achieving net-zero objectives, alongside supply chain vulnerabilities and ability to access the required capital.

    Multiple challenges

    From a technical standpoint, there are multiple considerations when implementing cross-border interconnections. Regions can operate using different technical parameters, such as different voltages or frequencies. Even within the same country, interregional variations can create bottlenecks. Adopting regional or international grid codes could mitigate these issues.

    Further challenges emerge when we take trading into account. This is where regulation can act as an enabler, facilitating the flow of electricity between countries. The European Union’s efforts to co-ordinate the design of its member state’s energy markets enables an increasingly smooth transmission of energy across the continent. Alongside this, existing infrastructure is outdated, requiring significant upfront investment to upgrade. Clarity on regulatory requirements and more transparency around plans for grid buildout, derisk funding for capital-intensive mega projects.

    Coordinated action is vital for the transfer of energy across borders and access to renewable sources of energy

    Positive benefits

    Despite these challenges, the upside must be stressed. Integrating power systems across borders has many positive societal benefits, decreasing costs and hence energy bills through economies of scale, increasing energy security and lowering the environmental impact of operations. On the latter more specifically, larger power systems are able to integrate higher shares of variable renewables. Globally, the sun is always shining and the wind blowing somewhere. 

    A common element, therefore, emerges: the need for increased cross-border co‑ordination. Whether it is bilateral, multi-lateral or unified, different models of inter-jurisdictional arrangements are needed for large-scale projects to support global energy interconnections. Our Xlinks project, which is using high-voltage direct current (HVDC) for transmission, is a standout example. 

    Such projects represent what is needed more in the world, the combination of infrastructure and renewable power across borders, bringing together the public and private sectors for energy security, supply and affordability in an environmentally friendly way. Transporting clean energy using HDVC cables is a crucial step in powering a net-zero and equitable future, and more of this is needed to aid the transition to lower-carbon and prosperous economies. 

    Political, technical and market hurdles can be overcome through collaboration and partnerships. Leveraging the collective expertise and resources of governments, regulators and the private sector can help ensure interconnections are developed quickly enough to support the energy transition. Grid buildout takes time. We have the resources required to meet ambitions, but stopping now is not viable. We must continue planning, building and maintaining large-scale infrastructure projects to meet the rising demand.

    Coordinated action is vital for the transfer of energy across borders and access to renewable sources of energy. This was the message from Cop28 and the UAE Consensus: to help progress and secure a cleaner, brighter future for us all, we must break down barriers and come together. 

     

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11736994/main.gif
  • Libya allocates $1.2bn for upstream oil project

    3 May 2024

     

    Register for MEED's guest programme 

    Libya has allocated LD6bn ($1.23bn) to develop the Hamada NC-7 concession in its latest budget, which was approved by Libya’s eastern-based parliament on 30 April, according to industry sources.

    The field development project was previously estimated to be worth between $4bn and $5bn.

    The project aims to develop 2.7 trillion cubic feet of gas reserves in the NC-7 block of the Ghadames basin.

    A consortium led by Italy’s Eni and including France’s TotalEnergies and UAE-based Adnoc operates the block.

    Development of the field was included in the 2024 annual budget of LD90bn ($18.5bn), excluding an item for development projects, which the Benghazi-based government of Osama Hamad unanimously approved.

    Hamad came to power in March 2023 and is allied with the military commander Khalifa Haftar, who controls the east and large parts of the southern region of Libya.

    Progress on developing the Hamada NC-7 concession has been slow amid concerns among politicians about the involvement of foreign oil companies in key hydrocarbon assets.

    On 15 December 2023, the Tripoli-based Ministry of Oil & Gas issued a statement condemning the terms of the planned gas development contract between Libya’s state-owned National Oil Corporation (NOC) and the consortium led by Eni.

    In the statement, the Ministry of Oil & Gas described the deal as a “violation of Libyan legislation on oil contracts”.

    Earlier this year, NOC announced a plan to execute 45 greenfield and brownfield projects to try to boost the country’s oil production from 1.25 million barrels a day (b/d) to 2 million b/d.

    Farhat Bengdara, the chairman of NOC, said that the projects had a total estimated cost of $17bn-$18bn.

    Bengdara also confirmed plans to launch an oil and gas licensing round at the end of 2024 or early 2025.

    Libya is aiming to hit its 2 million b/d target within three years.

    Bengdara said that gas monetisation will remain a strategic focus as the country pushes to increase exports to Europe.

    Libya is only using 25% of the capacity of its Greenstream pipeline to Italy.

    The North African country also flares significant volumes of natural gas and has 12 projects under way that aim to reduce gas flaring to almost zero, according to Bengdara.

    In recent years, Libya has struggled to execute large projects amid significant political instability.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11735260/main.gif
    Wil Crisp
  • GE Vernova invests in Xlinks

    2 May 2024

    US-headquartered GE Vernova has invested $10.2m in Xlinks First, the investment company established by UK-based startup Xlinks to deliver the $18bn Morocco-UK power project.

    This investment equates to a minority shareholding in the company, which is developing a project comprising wind and solar generation as well as battery storage, with a total combined capacity of 3,600MW, to be transmitted from Morocco to the UK.

    Xlinks said the investment will “further accelerate delivery and buildout of the project”.

    GE Vernova joins at least four other investors in the project.

    Other investors include Africa Finance Corporation, which invested $14.1m in April; Abu Dhabi National Energy Company (Taqa), $30.7m; the UK’s Octopus Energy, $6.23m; and France’s Total Energies, $25.4m.

    The planned electricity generation and battery storage facilities, located in south Morocco, will be connected exclusively to the UK via 4,000-kilometre high-voltage, direct current (HVDC) cables.

    In December last year, Xlinks signed a contract with Canada-headquartered WSP to provide technical advisory services for the project.

    WSP will support Xlinks with route optimisation, power systems and interface management for the plan to construct the project.

    The Morocco-UK power project entails building 10,500MW solar and wind farms in Morocco’s Guelmim-Oued Noun region and sending 3,600MW a day of energy exclusively to the UK via four 3,800-kilometre HVDC cables.

    The HVDC network is envisaged to run from the UK’s south coast, passing France, Spain and Portugal undersea and then onshore to a planned solar and wind energy project in Morocco.

    This renewable energy-sourced electricity amounts to nearly 8% of the UK’s current requirements, equivalent to powering 7 million homes by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11734222/main5830.jpg
    Jennifer Aguinaldo
  • Awards buoy Oman’s green hydrogen strategy

    2 May 2024

    Commentary
    Jennifer Aguinaldo
    Energy & technology editor

    Oman has awarded two additional land blocks designed to develop green hydrogen projects.

    The latest land block concessions in Dhofar were awarded to two consortiums. One comprises a team of France's EDF Group and EDF Renewables, with partners Japanese Electric Power Development Company (J-Power) and the UK-headquartered Yamna Company.

    Another team comprises UK investment firm Actis and Australian metals firm Fortescue.

    This brings the total number of land blocks awarded through the public auction process spearheaded by Hydrogen Oman (Hydrom) to four, exclusive of the four legacy initiatives signed or agreed upon already.

    *Budgets are MEED estimates if not publicly disclosed. Sources: MEED, Hydrom

    A limited gas supply and network strongly incentivises Oman to build a green hydrogen-centric downstream sector that will provide feedstock to domestic industrial plants and generate derivatives for the local and export markets.

    Stakeholders have implemented a strategy, including setting up an infrastructure company catering to these projects. The target is to generate 1 to 1.5 million tonnes a year (t/y) of green hydrogen by 2030 and 7.5 to 8.5 million t/y by 2050.

    The blueprint envisages a complete green hydrogen ecosystem, from the production of renewable energy and its distribution to electrolysis plants and hydrogen derivatives conversion plants to storage and export terminals.

    Omani ports' existing relationships with European stakeholders and growing alliances with other countries could also help seal future offtake agreements for the planned facilities.

    As things stand, the consortiums that won the land auctions and the legacy initiative partners provide much gravitas to Oman's green hydrogen programme. They comprise energy old guards such as BP and Shell that are keen to decarbonise, private companies aiming to balance their investment portfolios with clean energy investments, and offtakers or trading companies that are grappling with net-zero targets.

    Yet the most obvious question remains. Given the eye-popping foreign direct investments these complex projects entail, not all are likely to achieve a final investment decision within three years. This seems to be the window required for the projects to start production before 2030.

    But like any emerging industry, the risks can only be properly assessed and mitigated as the first projects move toward the execution phase.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11733331/main.gif
    Jennifer Aguinaldo
  • Operationalise loss and damage fund says Al Jaber

    2 May 2024

    Steps must be taken to ensure a fully functioning Loss and Damage Fund, following an agreement at Cop28 to operationalise the fund, according to Cop28 President Sultan Al Jaber.

    “While delivering an agreement to operationalise the Fund at Cop28 was a huge breakthrough for climate progress more needs to be done,” Al Jaber said during the first board meeting of the fund on 30 April.

    The Loss and Damage Fund, which was first proposed in the 1990s, aims to help developing countries cope with the impact of extreme global warming events such as droughts and floods.

    Al Jaber cited the need to build a fully functioning fund, which will be endorsed at Cop29 in Baku, which will be “disbursing funds soon after and a Fund that delivers lasting, positive, socio-economic impact for decades to come."

    "While it took over three decades to establish this Fund, climate change has not stood still. Every region of the world is now vulnerable…the impacts of climate change are a clear and present danger to lives and livelihoods everywhere."

    Al Jaber’s message resonates closer home given the recent storms hitting the UAE, which brought some emirates to a standstill in mid-April.

    Heavy rainfall inundated Dubai and the Northern Emirates on 16 April, causing flooding and significant property and infrastructure damages.

    A total of $792m has been pledged for loss and damage funding arrangements – of which $662m has been pledged to the Fund to date – including a $100m contribution each from the UAE and Germany and $75m from the UK.   

    https://image.digitalinsightresearch.in/uploads/NewsArticle/11732746/main.jpg
    Jennifer Aguinaldo