Riyadh to sustain power spending
12 March 2024
Latest news on Saudi Arabia’s power sector:
> Neom to start qualification for $2.7bn hydropower scheme
> Saudi power buyer holds Remah and Nairiyah meetings
> Enowa gives extra day for Gayal and Shiqri bidders
> Gayal and Shiqri bidders race to meet deadlines
> Neom extends Duba Energy Park bid deadline
> Data centre activity soars in Saudi Arabia
> US firm wins Al Kahfah solar tracker package
> Saudi-Omani team to set up transformers plant

The project pipeline in Saudi Arabia’s power generation sector continues to expand unabated.
The value of projects in execution or about to start construction has increased by 17% to $34bn compared to six months earlier, according to the latest available data from regional projects tracker MEED Projects.
The value of projects in the pre-execution phase similarly increased by 16% to reach $51bn during the same period. New schemes are expected to be announced in the coming 12-18 months, including power generation projects catering to the $500bn Neom development.
Two key factors underpin the ramp-up of both conventional and renewable energy generation capacity in the kingdom, notes a Dubai-based senior executive with an international developer.
“Saudi Arabia intends to become the renewable supplier of choice on the GCC grid,” the executive said, referring to the regional network linking the electricity grids of Bahrain, Kuwait, Oman, Qatar, the UAE and Saudi Arabia.
The second factor is the kingdom's push for industrialisation and urbanisation, including the adoption of electric vehicles and data centres.
“Saudi Arabia has very strong regulations to keep data within its domicile and the digitalisation needed to achieve the kingdom’s modernisation plans needs large data centres and corresponding electricity supply,” she notes.
Overall, Saudi Arabia awarded power generation contracts worth more than $16.1bn in 2023, which is higher than the total value of contracts awarded in the preceding eight years and nearly six times the value of contracts awarded in 2022.
The kingdom’s principal buyer, Saudi Power Procurement Company (SPPC) and its sovereign wealth vehicle, the Public Investment Fund (PIF), awarded the bulk of these contracts.
Shrinking renewables share
The share of renewable energy in the total value of awarded contracts shrunk to 28%, from about 82% in 2022, due to the award last year of the first gas-fired independent power producer (IPP) projects since 2016.
SPPC awarded a consortium comprising Saudi Electricity Company and Saudi utility developer Acwa Power the $3.9bn contract to develop and operate the Qassim 1 and Taiba 1 IPP projects in November 2023. Each combined-cycle gas turbine (CCGT) plant has a capacity of 1,800MW.
A team comprising the local Al Jomaih Energy & Water, France’s EDF and the local Buhur for Investment won the contract to develop the other pair of CCGT-based plants – the Taiba 2 IPP and Qassim 2 IPP schemes, each of which has a capacity of 1,800MW.
SPPC also awarded the contracts for the solar photovoltaic (PV) schemes under the fourth procurement round of the kingdom’s National Renewable Energy Programme (NREP).
A consortium that includes France's EDF Renewables, Abu Dhabi Future Energy Company (Masdar) and the local company Nesma won the contract to develop the 1,100MW Hinakiyah solar IPP project. A consortium led by China's Jinko Power won the contract to develop and maintain the 400MW Tubarjal solar IPP scheme.
The PIF, meanwhile, awarded contracts last year for the development of three solar PV schemes with a total combined capacity of 4.5GW to Acwa Power and its partner Water & Electricity Holding Company (Badeel). The 2GW Al Rass 2, 1.1GW Saad 2 and 1.4GW Al Kahfah solar PV IPPs require a total investment of about $3.4bn.
Unawarded projects
Following the award of these contracts, SPPC started the procurement process for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round, and four new CCGT schemes with a total combined capacity of 7.2GW.
Bids are due on 10 June for the 2GW Al Sadawi, 1GW Al Mas, 400MW Hinakiyah 2 and 300MW Rabigh 2 solar PV IPP schemes.
Bids are also due in late June for the Remah 1 and 2 and Al Nairiyah 1 and 2 gas-fired CCGTs.
As of early March, Neom’s utility subsidiary, Enowa, had received bids for two renewable energy engineering, procurement and construction (EPC) contracts, the 1.2GW Gayal wind farm and 800MW Shiqri solar farm.
Enowa is understood to be preparing a site for two CCGT plants to be built on a fast-track basis at Duba Energy Park. The first phase comprises a transportable gas turbine generator (GTG) with a capacity of 300MW, which is designed to deliver emergency power to Neom.
The second phase is a permanently installed 500MW facility comprising heavy-duty GTGs. Both are considered fast-track projects, with the first phase due for completion in early 2024 and the second phase in early 2025.
The first phase of a multi-gigawatt programme to build renewable energy capacity in Neom using a public-private partnership model is also expected to start soon.
Soaring costs
The raft of new projects coming to the pipeline is exerting pressure, particularly for the CCGT supply chain, experts tell MEED. “On average, the EPC prices have more than doubled since before the Covid-19 pandemic began,” says an executive working for an original equipment manufacturer (OEM).
The average EPC cost per kilowatt for CCGT plants with a capacity of over 1.5GW is understood to have reached approximately $750 a kilowatt in 2023, which is more than twice the average cost in 2019. EPC costs for smaller plants have similarly posted significant increases.
Industry sources say the turbine supply chain problem arises from the decision by some OEMs to reduce capacity over the past few years, driven by a combination of the Covid-19 pandemic and the threat of curtailed demand due to the push to decarbonise electricity systems.
The post-Covid-19 recovery, as well as the resurgence of demand for gas-fired power plants in the Middle East – and even in some countries in Europe – along with the expressed preference by most GCC clients for European-made gas turbines, has resulted in a seller’s market.
A Dubai-based OEM executive told MEED last year that its EU-made turbines are booked for several years, but order deliveries can still be shuffled between customers, so they do not expect major delays in delivering to clients. "It's definitely a seller's market right now for turbines. We have capacity in other regions like China, but customers prefer [turbines made in] EU factories”.
In comparison, the jury is still out on solar PV costs, although historical tariff data indicates a general upward trend between the record-low tariffs seen in 2021 and those submitted last year.
Transmission and distribution
Transmission and distribution (T&D) contracts exceeding a total of $12bn are under execution in Saudi Arabia, with an estimated $22.4bn in the pre-execution phase.
The value of contracts awarded in 2023, which sits at $4bn, exceeded the previous year’s total by 41%. The contract to build a high-voltage, direct current transmission system between Neom’s Oxagon industrial cluster and Yanbu is the largest T&D contract to have been awarded last year.
Volume-wise, 59 T&D contracts were awarded in Saudi Arabia last year compared to 64 in 2022.
Saudi Arabia has been gradually expanding the reach of its grid, both domestically – due to the development of new communities and industries and the growth of renewable energy capacity – as well as internationally.
Projects to link with Egypt and other countries in the GCC, as well as with Iraq and Jordan, are under way, while preliminary studies are ongoing to link the kingdom’s power grid further afield, including to the grids of India and Greece.
Energy storage and nuclear
A new project activity segment within Saudi Arabia’s power sector is emerging. SPPC intends to start the procurement process this year for the 2GW first phase of a project to procure 10GW of battery energy storage system (bess) capacity by 2030.
Bess comprises rechargeable batteries that can store and discharge energy from various sources when needed.
Saudi Arabia plans to locate its bess facilities near demand centres to boost the electricity grid's spinning reserves as more renewable energy is expected to enter its electricity production mix.
The 2GW first phase of the project entails building several plants at different locations, with individual capacities ranging from 50MW to 300MW each.
Finally, the procurement process is moving – albeit slowly – on the Duwaiheen nuclear power plant, Saudi Arabia’s first large-scale nuclear power project. Bids for the main contract are due in late April, following several deadline extensions since the kingdom invited selected companies to bid for the contract in 2022.
Exclusive from Meed
-
Riyadh tenders Expo 2030 Adaptation and Innovation Pavilion21 October 2026
-
Mubadala Bio lands Lilly logistics deal21 October 2026
-
Chinese/local joint venture wins Qiddiya stadium facade21 October 2026
-
Zamil Steel wins $82m Qiddiya tennis centre contract21 October 2026
-
Eni starts to bring gas processing facility online in Egypt21 October 2026
All of this is only 1% of what MEED.com has to offer
Subscribe now and unlock all the 153,671 articles on MEED.com
- All the latest news, data, and market intelligence across MENA at your fingerprints
- First-hand updates and inside information on projects, clients and competitors that matter to you
- 20 years' archive of information, data, and news for you to access at your convenience
- Strategize to succeed and minimise risks with timely analysis of current and future market trends
Related Articles
-
Riyadh tenders Expo 2030 Adaptation and Innovation Pavilion21 October 2026

Register for MEED’s 14-day trial access
Expo 2030 Riyadh has tendered the design-and-build main contract for the Adaptation and Innovation Pavilion in the exhibition’s Technology District.
The pavilion will be built on a plot of at least 12,710 square metres and will feature a two-level basement, ground-level public areas, an elevated skywalk, visitor experience areas, food and beverage outlets, retail space, VIP facilities, offices, back-of-house areas, exhibition spaces, an amphitheatre and a resonance hall.
The facility is being designed to accommodate a minimum of 20,000 visitors a day at peak periods, with an anticipated average of about 15,000 visitors a day. The project targets LEED Gold certification.
The tender was issued on 1 October, with bids due on 6 January 2027.
The design-and-build contractor will be responsible for completing, reviewing, verifying, coordinating and technically integrating the design, including specialist contractor design portions and coordination with the novated lead design consultant.
The scope includes completing early works and substructure activities, including grading, bulk earthworks, excavation, cut and fill, soil improvement, raft foundations, reinforced-concrete basement walls, basement columns through to the ground-floor slab, waterproofing, mechanical, electrical and plumbing (MEP) provisions, and backfilling.
The contractor will also deliver the superstructure and building envelope, including structural works, facade engineering and installation, roofs, waterproofing, external finishes, and permanent facade access and maintenance systems. The internal works will cover front-of-house and back-of-house areas, public and core spaces, internal finishes, fixtures, fixed fittings, joinery, circulation areas, lobbies, stairs, toilets, storage, waste areas and associated builder’s works.
The building services package includes MEP systems, information and communications technology, extra-low-voltage systems, building management systems, security, fire and life safety systems, specialist lighting and vertical transportation.
The contract also covers the visitor experience package, including procurement, installation, integration, testing, commissioning and handover of visitor-facing environments, media, immersive and audiovisual technologies, interactive elements, experiential lighting, digital content, interpretive and wayfinding systems, controls and supporting infrastructure.
Within-plot infrastructure and utilities, landscaping, public realm works, paving, planting, irrigation, signage, street furniture, drainage, stormwater systems, external lighting, security, and fire and life safety systems are also included.
The contractor will be responsible for procurement, off-site fabrication, construction, testing and commissioning, performance verification, training, operations and maintenance documentation, operational readiness, handover, defects rectification and close-out.
The main works tender is based on a 60% RIBA Stage 3 design, with the Stage 3 design to be completed to 100% through an addendum.
Early works and substructure works, as well as the lead design consultant, will be novated to the contractor. Visitor experience works are included as a provisional sum.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20801465/main.jpeg -
Mubadala Bio lands Lilly logistics deal21 October 2026
Mubadala Bio, the life sciences subsidiary of Abu Dhabi state investor Mubadala Investment Company, has signed an agreement with US drugmaker Eli Lilly to localise the packaging and logistics of Lilly’s glucagon-like peptide-1 (GLP-1) medicines in Abu Dhabi.
The work will take place at a 125,000-square-metre site in Khalifa Economic Zones Abu Dhabi (Kezad), which includes packaging and warehousing facilities. Mubadala Bio said the facilities would strengthen its pharmaceutical contract manufacturing, packaging and logistics capabilities and its ability to serve international clients from the UAE.
The packaging and logistics activities will be introduced in phases and will be subject to technical, quality and regulatory requirements. The companies did not disclose the value of the agreement or a timeline for the first phase.
The Emirates Drug Establishment approved Lilly’s oral GLP-1 drug Foundayo (orforglipron) for chronic weight management in April. The companies said this made the UAE the second country in the world to register the medicine.
In Abu Dhabi, the treatment is available to eligible patients under a weight management programme launched by the Abu Dhabi Department of Health and the Abu Dhabi Public Health Centre in June 2025. The UAE was also an early launch market for Lilly’s injectable treatment Mounjaro (tirzepatide) in August 2022.
Mubadala launched Mubadala Bio in 2025 to expand domestic drug manufacturing and distribution, with a focus on national drug security. It is one of Mubadala’s designated national champions, set up to support strategic sectors. At launch, its combined facilities covered 110,000 square metres, with an annual capacity of more than 2.5 billion tablets and capsules and 120 million intravenous and injectable units.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20801279/main.jpg -
Chinese/local joint venture wins Qiddiya stadium facade21 October 2026
Register for MEED’s 14-day trial access
A joint venture of China’s Fangda Group and Saudi Arabia’s IKK Group has secured a SR1.15bn ($306m) contract to deliver curtain wall facade works for the Prince Mohammed Bin Salman Stadium in Qiddiya City, Riyadh.
The contract was awarded by the joint venture of Spain’s FCC Construccion and local contractor Nesma & Partners, which is building the stadium under an estimated SR15bn ($4bn) main contract awarded by Qiddiya Investment Company (QIC) in October 2024.
The IKK-Fangda joint venture will design, supply and install curtain wall façade systems for the main stadium (Lot 1), as well as for the museum and ancillary buildings (Lot 3).
The contract has an execution period of 863 days.
The stadium will seat about 47,000 spectators and will be the home ground for Saudi Pro League clubs Al-Nassr and Al-Hilal.
The facade award follows the appointment of Elegancia Arabia, a subsidiary of Qatar-based Elegancia MEP and Estithmar Holding, to deliver the stadium’s mechanical, electrical and plumbing works.
The SR829m ($221m) contract is Elegancia Arabia’s largest award in Saudi Arabia to date.
The project is being designed by US-based consultant Populous.
It is among the venues planned for the 2034 Fifa World Cup and will also host the Saudi King Cup, the AFC Asian Cup and the 2034 Asian Games.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20799367/main.jpg -
Zamil Steel wins $82m Qiddiya tennis centre contract21 October 2026
Advanced Building Industries Company (Senaat) has announced that its subsidiary, Zamil Structural Steel Company (Zamil Steel), has secured a SR308m ($82m) contract for the National Tennis Centre in Qiddiya City, Riyadh.
The 19-month contract was awarded by the joint venture of France’s Bouygues Batiment International and local contractor Almabani General Contractors Company.
Zamil Steel’s scope includes the fabrication, supply and installation of structural steel and external facades for the scheme.
MEED reported in June that the Bouygues Batiment International-Almabani joint venture had started construction of the National Tennis Centre.
The development will include 30 tennis courts, comprising 28 hard courts and two clay courts. The main Centre Court will seat 15,000 spectators and feature a retractable roof.
The facility is being designed to meet standards set by the Association of Tennis Professionals, the Women’s Tennis Association and the International Tennis Federation.
The development will also include an 8,000-seat multipurpose arena with a retractable roof, known as Court 3. Other facilities include a 5,000-seat Court 1, a 2,000-seat Court 2, six competition courts, six indoor courts and 14 practice courts. Each outdoor match court will provide 450 seats.
Total seating capacity across the complex will be 33,000. US-based architect Populous designed the project.
Qiddiya Investment Company officially announced the project on 15 June. The developer has said the centre will be the region’s largest tennis complex and will host international tennis events.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20799055/main.jpg -
Eni starts to bring gas processing facility online in Egypt21 October 2026
Register for MEED’s 14-day trial access
Italy’s Eni has started to bring its Meleiha Phase 2 (MP2) project online in Egypt’s Western Desert, according to statements from the company and Egypt’s Ministry of Petroleum & Mineral Resources.
The project includes a new gas processing facility designed to process up to 100 million standard cubic feet of gas a day.
Eni is a part owner of the project through Agiba Petroleum Company, a joint venture of Eni and state-owned Egyptian General Petroleum Corporation (EGPC)
The main contract for the project was awarded to the Egyptian engineering, procurement and construction (EPC) company Petrojet.
The scope of the project included:
- Laying 200 kilometres of pipeline
- Drilling 28 wells
- Construction of a gas sweetening unit
- Construction of a gas recovery unit
- Installation of gas purification and liquids separation units
- Installation of utilities and supporting infrastructure
- Construction of natural gas processing plant
- Construction of associated facilities
In its statement, Eni said: “The project represents a key milestone in the development of a new gas hub within the Merged Meleiha concession and will significantly increase the gas processing capacity for production from the area’s fields, supporting the growth of domestic gas output and the valorisation of Egypt’s energy resources.”
The Meleiha and Meleiha Deep concessions were combined into a single concession known as the Merged Meleiha concession in 2021.
Eni said that the new facilities “will ensure the connection of new production to Egypt’s existing gas infrastructure, enabling the rapid monetisation of resources and enhanced operational efficiency”.
It added: “The launch of the project confirms Eni’s role as a strategic partner of Egypt and reaffirms the company’s long-standing commitment to contributing to the country’s energy security through the development and valorisation of the Western Desert’s diversified resource base, one of the most promising areas of Egypt’s energy sector.”
Eni has been present in Egypt since 1954 and produced approximately 242,000 barrels of oil equivalent a day in the country on an equity basis in 2025.
https://image.digitalinsightresearch.in/uploads/NewsArticle/20788394/main.gif
