Riyadh to sustain power spending

12 March 2024

Latest news on Saudi Arabia’s power sector:

Neom to start qualification for $2.7bn hydropower scheme
Saudi power buyer holds Remah and Nairiyah meetings
Enowa gives extra day for Gayal and Shiqri bidders

Gayal and Shiqri bidders race to meet deadlines
Neom extends Duba Energy Park bid deadline
Data centre activity soars in Saudi Arabia
US firm wins Al Kahfah solar tracker package
> Saudi-Omani team to set up transformers plant


 

The project pipeline in Saudi Arabia’s power generation sector continues to expand unabated.

The value of projects in execution or about to start construction has increased by 17% to $34bn compared to six months earlier, according to the latest available data from regional projects tracker MEED Projects.

The value of projects in the pre-execution phase similarly increased by 16% to reach $51bn during the same period. New schemes are expected to be announced in the coming 12-18 months, including power generation projects catering to the $500bn Neom development.

Two key factors underpin the ramp-up of both conventional and renewable energy generation capacity in the kingdom, notes a Dubai-based senior executive with an international developer.

“Saudi Arabia intends to become the renewable supplier of choice on the GCC grid,” the executive said, referring to the regional network linking the electricity grids of Bahrain, Kuwait, Oman, Qatar, the UAE and Saudi Arabia.

The second factor is the kingdom's push for industrialisation and urbanisation, including the adoption of electric vehicles and data centres.

“Saudi Arabia has very strong regulations to keep data within its domicile and the digitalisation needed to achieve the kingdom’s modernisation plans needs large data centres and corresponding electricity supply,” she notes.

Overall, Saudi Arabia awarded power generation contracts worth more than $16.1bn in 2023, which is higher than the total value of contracts awarded in the preceding eight years and nearly six times the value of contracts awarded in 2022.

The kingdom’s principal buyer, Saudi Power Procurement Company (SPPC) and its sovereign wealth vehicle, the Public Investment Fund (PIF), awarded the bulk of these contracts.

Shrinking renewables share

The share of renewable energy in the total value of awarded contracts shrunk to 28%, from about 82% in 2022, due to the award last year of the first gas-fired independent power producer (IPP) projects since 2016.

SPPC awarded a consortium comprising Saudi Electricity Company and Saudi utility developer Acwa Power the $3.9bn contract to develop and operate the Qassim 1 and Taiba 1 IPP projects in November 2023. Each combined-cycle gas turbine (CCGT) plant has a capacity of 1,800MW.

A team comprising the local Al Jomaih Energy & Water, France’s EDF and the local Buhur for Investment won the contract to develop the other pair of CCGT-based plants – the Taiba 2 IPP and Qassim 2 IPP schemes, each of which has a capacity of 1,800MW.

SPPC also awarded the contracts for the solar photovoltaic (PV) schemes under the fourth procurement round of the kingdom’s National Renewable Energy Programme (NREP).

A consortium that includes France's EDF Renewables, Abu Dhabi Future Energy Company (Masdar) and the local company Nesma won the contract to develop the 1,100MW Hinakiyah solar IPP project. A consortium led by China's Jinko Power won the contract to develop and maintain the 400MW Tubarjal solar IPP scheme.

The PIF, meanwhile, awarded contracts last year for the development of three solar PV schemes with a total combined capacity of 4.5GW to Acwa Power and its partner Water & Electricity Holding Company (Badeel). The 2GW Al Rass 2, 1.1GW Saad 2 and 1.4GW Al Kahfah solar PV IPPs require a total investment of about $3.4bn.

Unawarded projects

Following the award of these contracts, SPPC started the procurement process for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round, and four new CCGT schemes with a total combined capacity of 7.2GW.

Bids are due on 10 June for the 2GW Al Sadawi, 1GW Al Mas, 400MW Hinakiyah 2 and 300MW Rabigh 2 solar PV IPP schemes.

Bids are also due in late June for the Remah 1 and 2 and Al Nairiyah 1 and 2 gas-fired CCGTs.

As of early March, Neom’s utility subsidiary, Enowa, had received bids for two renewable energy engineering, procurement and construction (EPC) contracts, the 1.2GW Gayal wind farm and 800MW Shiqri solar farm.

Enowa is understood to be preparing a site for two CCGT plants to be built on a fast-track basis at Duba Energy Park. The first phase comprises a transportable gas turbine generator (GTG) with a capacity of 300MW, which is designed to deliver emergency power to Neom.

The second phase is a permanently installed 500MW facility comprising heavy-duty GTGs. Both are considered fast-track projects, with the first phase due for completion in early 2024 and the second phase in early 2025.

The first phase of a multi-gigawatt programme to build renewable energy capacity in Neom using a public-private partnership model is also expected to start soon.

Soaring costs

The raft of new projects coming to the pipeline is exerting pressure, particularly for the CCGT supply chain, experts tell MEED. “On average, the EPC prices have more than doubled since before the Covid-19 pandemic began,” says an executive working for an original equipment manufacturer (OEM).

The average EPC cost per kilowatt for CCGT plants with a capacity of over 1.5GW is understood to have reached approximately $750 a kilowatt in 2023, which is more than twice the average cost in 2019. EPC costs for smaller plants have similarly posted significant increases.

Industry sources say the turbine supply chain problem arises from the decision by some OEMs to reduce capacity over the past few years, driven by a combination of the Covid-19 pandemic and the threat of curtailed demand due to the push to decarbonise electricity systems.

The post-Covid-19 recovery, as well as the resurgence of demand for gas-fired power plants in the Middle East – and even in some countries in Europe – along with the expressed preference by most GCC clients for European-made gas turbines, has resulted in a seller’s market.

A Dubai-based OEM executive told MEED last year that its EU-made turbines are booked for several years, but order deliveries can still be shuffled between customers, so they do not expect major delays in delivering to clients. "It's definitely a seller's market right now for turbines. We have capacity in other regions like China, but customers prefer [turbines made in] EU factories”.

In comparison, the jury is still out on solar PV costs, although historical tariff data indicates a general upward trend between the record-low tariffs seen in 2021 and those submitted last year.

Transmission and distribution

Transmission and distribution (T&D) contracts exceeding a total of $12bn are under execution in Saudi Arabia, with an estimated $22.4bn in the pre-execution phase.

The value of contracts awarded in 2023, which sits at $4bn, exceeded the previous year’s total by 41%. The contract to build a high-voltage, direct current transmission system between Neom’s Oxagon industrial cluster and Yanbu is the largest T&D contract to have been awarded last year.

Volume-wise, 59 T&D contracts were awarded in Saudi Arabia last year compared to 64 in 2022.

Saudi Arabia has been gradually expanding the reach of its grid, both domestically – due to the development of new communities and industries and the growth of renewable energy capacity – as well as internationally.

Projects to link with Egypt and other countries in the GCC, as well as with Iraq and Jordan, are under way, while preliminary studies are ongoing to link the kingdom’s power grid further afield, including to the grids of India and Greece.

Energy storage and nuclear

A new project activity segment within Saudi Arabia’s power sector is emerging. SPPC intends to start the procurement process this year for the 2GW first phase of a project to procure 10GW of battery energy storage system (bess) capacity by 2030.

Bess comprises rechargeable batteries that can store and discharge energy from various sources when needed.

Saudi Arabia plans to locate its bess facilities near demand centres to boost the electricity grid's spinning reserves as more renewable energy is expected to enter its electricity production mix.

The 2GW first phase of the project entails building several plants at different locations, with individual capacities ranging from 50MW to 300MW each. 

Finally, the procurement process is moving – albeit slowly – on the Duwaiheen nuclear power plant, Saudi Arabia’s first large-scale nuclear power project. Bids for the main contract are due in late April, following several deadline extensions since the kingdom invited selected companies to bid for the contract in 2022.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11584212/main2905.gif
Jennifer Aguinaldo
Related Articles
  • Oil prices rise above $100 a barrel as conflict escalates

    9 September 2026

    Register for MEED’s 14-day trial access 

    Oil prices rose above $100 a barrel on 9 September for the first time since July as the US-Iran conflict escalated and Iran-backed Houthi forces attacked Saudi energy infrastructure.

    Brent crude futures reached $100.95 a barrel, while US benchmark West Texas Intermediate (WTI) rose to $95.60. Brent had last traded above $100 on 24 July.

    The latest escalation has heightened concerns about oil supplies from the region, with shipping through both the Strait of Hormuz and the Red Sea facing disruption.

    Flows through the Strait of Hormuz had fallen below 2 million barrels a day (b/d) from about 8-9 million b/d before the latest escalation, according to Rystad Energy.

    At the same time, Houthi attacks on Saudi Arabia threaten another important route for oil exports, with the group targeting energy infrastructure and shipping in and around the Red Sea.

    US strikes on Iranian tankers

    US forces destroyed five Iranian crude oil carriers on 8 September after Iran’s Islamic Revolutionary Guard Corps (IRGC) targeted a US Navy warship with ballistic missiles.

    The US Central Command (Centcom) said the warship successfully evaded two Iranian attacks and that no US personnel were harmed.

    Four of the Iranian vessels – Kaviz, Charminar, Horizon 1 and Riesco – were struck in the Gulf of Oman, while the Derya was attacked near Kharg Island, Iran’s main crude export hub.

    The M/T Riesco subsequently sank in the Gulf of Oman, according to Centcom.

    Iran responded by launching ballistic missiles towards Jordan. Jordan’s armed forces said 18 of 20 missiles were intercepted, with the remaining two falling in unpopulated areas.

    Iran’s IRGC also said it had attacked two US naval vessels, eight oil tankers and 10 other vessels in the Gulf, although it did not identify the vessels or provide evidence of the attacks.

    The latest exchanges mark a further escalation in the US-Iran conflict, which began on 28 February.

    Houthi attacks raise supply concerns

    The conflict has also widened into a renewed confrontation between Saudi Arabia and Yemen’s Iran-backed Houthi movement.

    On 8 September, Saudi authorities said Houthi attacks had targeted civilian and economic sites in Abha, Khamis Mushait, Jazan and Najran in the south of the kingdom, injuring 73 people.

    Saudi Arabia’s Ministry of Energy said several energy sector facilities and installations had been targeted, causing fires and forcing a temporary halt to some operations.

    The Houthis said their attacks were in response to Saudi military action in Yemen, including what they described as attacks on Houthi positions and a Saudi blockade of ports and airports.

    Riyadh condemns attacks

    Saudi Arabia has strongly condemned the Houthi attacks and warned that it would take measures to defend its territory and national assets.

    In a statement on 8 September, the Ministry of Energy said authorities were working to address the impact of the attacks and ensure the safety of facilities and personnel while maintaining operations in accordance with approved plans.

    Saudi Arabia’s Ministry of Foreign Affairs also condemned the attacks and said the kingdom had the right to take measures to defend its sovereignty and protect its citizens, residents and national assets.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19505512/main0138.jpg
    Indrajit Sen
  • What actually slows a gigaproject down

    9 September 2026

     

    Ask anyone delivering a major programme in the GCC what causes delays and sequencing will come up early. Utilities go in too late. Approvals lag behind construction. Stations, depots and access roads are procured as if they belong to different projects rather than one system.

    “None of this is new. The industry has understood these risks for years,” says Alan Caldwell, managing director for transport and infrastructure at WSP Middle East.

    For Caldwell, that is what makes the pattern worth interrogating rather than simply restating.

    “The more important question is why the same issues around interfaces, approvals, stakeholder alignment and delivery sequencing continue to slow major programmes when the risks are already so well understood,” he says.

    The answer, he argues, is not that these programmes are too big or too technically complex. What breaks a schedule is a wider system delivered as a set of disconnected parts; an approval sitting with an authority team with no visibility of the construction sequence downstream; or a station package proceeding without the utilities diversion it depends on.

    “Infrastructure programmes do not struggle because a railway is too large or a highway network is too complex,” Caldwell says. “They encounter difficulties when interconnected elements are delivered in the wrong order.”

    Sequencing decisions are rarely purely technical either, he adds. They are commercial – shaped by which assets need to unlock value first, which phases are tied to funding, and where sales or investment assumptions depend on infrastructure landing in a particular order.

    Approvals sit at the centre of that logic. On many programmes, they become one of the biggest sources of lost time – not because the requirements are unreasonable, but because approvals are not planned, evidenced or owned as part of the delivery logic from day one.

    Caldwell has seen the same pattern across three decades of Gulf delivery, from early work on Palm Jumeirah to today’s region-wide transport programmes.

    “The decisive factor has often been the same: whether interfaces, approvals, responsibilities and delivery sequencing are aligned early enough to prevent complexity becoming delay.”

    Integration needs to be well understood

    “Most programme teams in the region would say they understand the need for integration,” Caldwell says. Fewer are structured to deliver it. “The harder task is turning that understanding into the way projects are actually set up and managed,” he argues.

    Riyadh Metro is the reference point he returns to, precisely because engineering complexity was not the deciding factor in its delivery.

    Coordinating a city-scale transport system meant aligning design, construction, systems, utilities and stakeholder interfaces across every delivery vertical.

    “The lesson for the region today is clear,” Caldwell says. “Ambitious programmes need a delivery model that gives every contributor a shared view of progress, risk, decision-making and the business case driving programme priorities.”

    That shared view, he argues, will be what the next phase of Gulf delivery is judged on.

    Whether clients, consultants, contractors, operators and approval authorities can work to a single delivery logic will be key.

    “This requires more than coordination meetings. It requires integrated ways of working, shared common data environments and governance structures that make risks, decisions and dependencies visible before they become delays,” he says.

    From reporting progress to managing risk before it lands

    Digital tools have a role here, Caldwell says, but not as a headline in themselves.

    Digital twins, programme visualisation and data-led modelling matter only if they help teams identify and address problems before they affect the wider programme.

    “The real value is not technology for its own sake,” he says. “It is the ability to see, in one place, where approvals are outstanding, where interfaces are unresolved, where programme dates are slipping, where clashes are emerging and where decisions need to be escalated."

    None of it works without governance behind it, he cautions. “A dashboard will not resolve a delayed approval if nobody knows who owns the decision, when it needs to be made, or how it should be escalated.”

    Data only has value if the processes and responsibilities around it are clear, which is why Caldwell frames the shift the region needs not as digitisation, but as a move “from programme management as a discipline focused mainly on reporting and coordination, and towards project and programme intelligence”.

    With many of the region’s programmes running for a decade or more, he adds, delivery models also need to flex as funding assumptions, user needs and policy priorities change along the way.

    “The ambition behind the Gulf’s transformation programmes is not in question,” Caldwell says.

    What will determine how much of it is realised on time is whether delivery models evolve at the same pace: earlier integration, clearer approval pathways, shared data environments, and every contributor working to a delivery logic that connects technical sequencing with the funding and operational case behind it.

    “The region’s next challenge is not imagining bigger projects,” he says. “It is changing the way they are delivered, operated and adapted over time.”

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19502016/main.gif
    Yasir Iqbal
  • Qatari firm wins $221m Qiddiya stadium MEP deal

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Qatari contractor Elegancia MEP, part of Estithmar Holding, has won a SR829m ($221m) mechanical package contract for the Prince Mohammed Bin Salman Stadium in Qiddiya, Saudi Arabia.

    The contract covers full mechanical, electrical and plumbing (MEP) works for the stadium, and is Elegancia MEP’s largest award in Saudi Arabia to date.

    The 45,000-seat stadium will feature a fully combined retractable pitch, roof and LED wall.

    The stadium’s main construction works are being undertaken by a joint venture of Spanish firm FCC Construction and local firm Nesma & Partners.

    Saudi gigaproject developer Qiddiya Investment Company awarded an estimated SR15bn ($4bn) deal to build the stadium in October 2024, as MEED exclusively reported.

    The contract covered the construction of a multipurpose stadium on top of the 200-metre-high Tuwaiq cliff in the new sports and entertainment district of Qiddiya City.

    Once completed, the stadium will be the home ground for Saudi Pro League football clubs Al-Nassr and Al-Hilal.

    US-based architect Populous is the project consultant.

    The stadium is one of the venues for the kingdom’s 2034 Fifa World Cup bid and will host events such as the Saudi King Cup, the Asian Cup and the 2034 Asian Games.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19501493/main.jpg
    Yasir Iqbal
  • Jordan tenders advisory for wastewater treatment plant

    9 September 2026

    The Water Authority Jordan (WAJ) has issued an invitation to prequalify for advisory services for the rehabilitation and expansion of the Shallala wastewater treatment plant in Irbid, northern Jordan.

    The Shallala plant was commissioned in 2013 with a design capacity of about 14,000 cubic metres a day (cm/d).

    The rehabilitation and expansion project will increase its treatment capacity to about 30,500 cm/d to meet projected wastewater flows through 2050.

    The PIU Support and Construction Supervision Consultancy Services tender was released on 19 August.

    The submission deadline is 21 September.

    The consultancy will support the project implementation unit and provide construction supervision services for the project. The project has an estimated value of $69m and is being financed by the European Bank for Reconstruction and Development.

    The planned works include rehabilitating the existing activated sludge and treatment units and constructing a new treatment train.

    The scope also includes installing biogas combined heat and power units, improving sludge handling and dewatering systems, and installing odour control and chemical containment systems.

    WAJ is also undertaking the upgrade and expansion of the Ain Ghazal wastewater treatment plant in Amman.

    The existing facility had a capacity of 330,000 cm/d and is being upgraded to 726,712 cm/d to accept and treat expected incoming flows until 2045.

    The local Arab Towers Contracting Company was appointed as the main contractor for the project last year.


    READ THE SEPTEMBER 2026 MEED BUSINESS REVIEW – click here to view PDF

    Nuclear power ambitions gather pace; Kuwait keeps dealmaking alive despite war; Region invests in raising gas processing capacity.

    Distributed to senior decision-makers in the region and around the world, the September 2026 edition of MEED Business Review includes:

    To see previous issues of MEED Business Review, please click here
    https://image.digitalinsightresearch.in/uploads/NewsArticle/19498520/main.jpg
    Mark Dowdall
  • Consultants bid for Abu Dhabi light rail project management

    9 September 2026

     

    Register for MEED’s 14-day trial access 

    Abu Dhabi Transport Company (ADTC) has issued a request for prequalification (RFQ) notice to consultants for a contract for project management engineering consultancy services for the first phase of the light rail transit network, also known as ADT4.

    The notice was issued on 7 September, with a submission deadline of 9 November.

    The project’s first phase will span 19 kilometres (km) and include 23 stations, connecting Zayed International airport (AUH) with nearby areas, including Yas Island, Al‑Raha Beach and Khalifa City.

    The key sections of the tram are:

    AUH to Yas Island: The tram will start from Terminal A at AUH and run through the Yas tunnel to Yas Gateway Park. It will serve areas including Yas Bay, Media Zone, Yas Plaza, Yas Drive, Yas Mall, Sea World and Water Edge.

    This section covers 13km and includes 13 at-grade stations and one underground station.

    Al-Raha: This section will stretch for 4.3km and run along Al-Raha Street. It will serve areas including Al-Zeina, Al-Muneera and Al-Bandar, towards the Aldar head office. The section will include seven at-grade stations.

    Etihad Plaza: This section will pass the Etihad Aviation Training Centre and span about 1.7km. It will feature a main depot near the Etihad Airways headquarters, along with two at-grade stations.

    The tender also covers the procurement of 25 trams, each with a capacity of 270 people, along with associated systems.

    The project was officially launched at the GlobalRail exhibition in Abu Dhabi in October last year.

    Referred to as Abu Dhabi Tram Line 4, the project will be delivered in three phases.

    Construction of the first phase is expected to start next year. The tram is slated to begin operations by 2030.

    Future phases will extend towards Khalifa City and serve additional destinations across Yas Island.

    The project forms a key part of the recently announced AED170bn ($46bn) package of national transport and road projects to be implemented by 2030.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/19493532/main.jpg
    Yasir Iqbal