Riyadh to sustain power spending

12 March 2024

Latest news on Saudi Arabia’s power sector:

> Neom to start qualification for $2.7bn hydropower scheme
> Saudi power buyer holds Remah and Nairiyah meetings
> Enowa gives extra day for Gayal and Shiqri bidders

> Gayal and Shiqri bidders race to meet deadlines
> Neom extends Duba Energy Park bid deadline
> Data centre activity soars in Saudi Arabia
> US firm wins Al Kahfah solar tracker package
> Saudi-Omani team to set up transformers plant


 

The project pipeline in Saudi Arabia’s power generation sector continues to expand unabated.

The value of projects in execution or about to start construction has increased by 17% to $34bn compared to six months earlier, according to the latest available data from regional projects tracker MEED Projects.

The value of projects in the pre-execution phase similarly increased by 16% to reach $51bn during the same period. New schemes are expected to be announced in the coming 12-18 months, including power generation projects catering to the $500bn Neom development.

Two key factors underpin the ramp-up of both conventional and renewable energy generation capacity in the kingdom, notes a Dubai-based senior executive with an international developer.

“Saudi Arabia intends to become the renewable supplier of choice on the GCC grid,” the executive said, referring to the regional network linking the electricity grids of Bahrain, Kuwait, Oman, Qatar, the UAE and Saudi Arabia.

The second factor is the kingdom's push for industrialisation and urbanisation, including the adoption of electric vehicles and data centres.

“Saudi Arabia has very strong regulations to keep data within its domicile and the digitalisation needed to achieve the kingdom’s modernisation plans needs large data centres and corresponding electricity supply,” she notes.

Overall, Saudi Arabia awarded power generation contracts worth more than $16.1bn in 2023, which is higher than the total value of contracts awarded in the preceding eight years and nearly six times the value of contracts awarded in 2022.

The kingdom’s principal buyer, Saudi Power Procurement Company (SPPC) and its sovereign wealth vehicle, the Public Investment Fund (PIF), awarded the bulk of these contracts.

Shrinking renewables share

The share of renewable energy in the total value of awarded contracts shrunk to 28%, from about 82% in 2022, due to the award last year of the first gas-fired independent power producer (IPP) projects since 2016.

SPPC awarded a consortium comprising Saudi Electricity Company and Saudi utility developer Acwa Power the $3.9bn contract to develop and operate the Qassim 1 and Taiba 1 IPP projects in November 2023. Each combined-cycle gas turbine (CCGT) plant has a capacity of 1,800MW.

A team comprising the local Al Jomaih Energy & Water, France’s EDF and the local Buhur for Investment won the contract to develop the other pair of CCGT-based plants – the Taiba 2 IPP and Qassim 2 IPP schemes, each of which has a capacity of 1,800MW.

SPPC also awarded the contracts for the solar photovoltaic (PV) schemes under the fourth procurement round of the kingdom’s National Renewable Energy Programme (NREP).

A consortium that includes France's EDF Renewables, Abu Dhabi Future Energy Company (Masdar) and the local company Nesma won the contract to develop the 1,100MW Hinakiyah solar IPP project. A consortium led by China's Jinko Power won the contract to develop and maintain the 400MW Tubarjal solar IPP scheme.

The PIF, meanwhile, awarded contracts last year for the development of three solar PV schemes with a total combined capacity of 4.5GW to Acwa Power and its partner Water & Electricity Holding Company (Badeel). The 2GW Al Rass 2, 1.1GW Saad 2 and 1.4GW Al Kahfah solar PV IPPs require a total investment of about $3.4bn.

Unawarded projects

Following the award of these contracts, SPPC started the procurement process for four solar PV schemes with a total combined capacity of 3.7GW under the NREP fifth round, and four new CCGT schemes with a total combined capacity of 7.2GW.

Bids are due on 10 June for the 2GW Al Sadawi, 1GW Al Mas, 400MW Hinakiyah 2 and 300MW Rabigh 2 solar PV IPP schemes.

Bids are also due in late June for the Remah 1 and 2 and Al Nairiyah 1 and 2 gas-fired CCGTs.

As of early March, Neom’s utility subsidiary, Enowa, had received bids for two renewable energy engineering, procurement and construction (EPC) contracts, the 1.2GW Gayal wind farm and 800MW Shiqri solar farm.

Enowa is understood to be preparing a site for two CCGT plants to be built on a fast-track basis at Duba Energy Park. The first phase comprises a transportable gas turbine generator (GTG) with a capacity of 300MW, which is designed to deliver emergency power to Neom.

The second phase is a permanently installed 500MW facility comprising heavy-duty GTGs. Both are considered fast-track projects, with the first phase due for completion in early 2024 and the second phase in early 2025.

The first phase of a multi-gigawatt programme to build renewable energy capacity in Neom using a public-private partnership model is also expected to start soon.

Soaring costs

The raft of new projects coming to the pipeline is exerting pressure, particularly for the CCGT supply chain, experts tell MEED. “On average, the EPC prices have more than doubled since before the Covid-19 pandemic began,” says an executive working for an original equipment manufacturer (OEM).

The average EPC cost per kilowatt for CCGT plants with a capacity of over 1.5GW is understood to have reached approximately $750 a kilowatt in 2023, which is more than twice the average cost in 2019. EPC costs for smaller plants have similarly posted significant increases.

Industry sources say the turbine supply chain problem arises from the decision by some OEMs to reduce capacity over the past few years, driven by a combination of the Covid-19 pandemic and the threat of curtailed demand due to the push to decarbonise electricity systems.

The post-Covid-19 recovery, as well as the resurgence of demand for gas-fired power plants in the Middle East – and even in some countries in Europe – along with the expressed preference by most GCC clients for European-made gas turbines, has resulted in a seller’s market.

A Dubai-based OEM executive told MEED last year that its EU-made turbines are booked for several years, but order deliveries can still be shuffled between customers, so they do not expect major delays in delivering to clients. "It's definitely a seller's market right now for turbines. We have capacity in other regions like China, but customers prefer [turbines made in] EU factories”.

In comparison, the jury is still out on solar PV costs, although historical tariff data indicates a general upward trend between the record-low tariffs seen in 2021 and those submitted last year.

Transmission and distribution

Transmission and distribution (T&D) contracts exceeding a total of $12bn are under execution in Saudi Arabia, with an estimated $22.4bn in the pre-execution phase.

The value of contracts awarded in 2023, which sits at $4bn, exceeded the previous year’s total by 41%. The contract to build a high-voltage, direct current transmission system between Neom’s Oxagon industrial cluster and Yanbu is the largest T&D contract to have been awarded last year.

Volume-wise, 59 T&D contracts were awarded in Saudi Arabia last year compared to 64 in 2022.

Saudi Arabia has been gradually expanding the reach of its grid, both domestically – due to the development of new communities and industries and the growth of renewable energy capacity – as well as internationally.

Projects to link with Egypt and other countries in the GCC, as well as with Iraq and Jordan, are under way, while preliminary studies are ongoing to link the kingdom’s power grid further afield, including to the grids of India and Greece.

Energy storage and nuclear

A new project activity segment within Saudi Arabia’s power sector is emerging. SPPC intends to start the procurement process this year for the 2GW first phase of a project to procure 10GW of battery energy storage system (bess) capacity by 2030.

Bess comprises rechargeable batteries that can store and discharge energy from various sources when needed.

Saudi Arabia plans to locate its bess facilities near demand centres to boost the electricity grid's spinning reserves as more renewable energy is expected to enter its electricity production mix.

The 2GW first phase of the project entails building several plants at different locations, with individual capacities ranging from 50MW to 300MW each. 

Finally, the procurement process is moving – albeit slowly – on the Duwaiheen nuclear power plant, Saudi Arabia’s first large-scale nuclear power project. Bids for the main contract are due in late April, following several deadline extensions since the kingdom invited selected companies to bid for the contract in 2022.

https://image.digitalinsightresearch.in/uploads/NewsArticle/11584212/main2905.gif
Jennifer Aguinaldo
Related Articles
  • Contractors compete for Riyadh airport Terminal 6 work

    2 November 2026

     

    Contractors are preparing bids for the main construction contract for Terminal 6 at King Salman International airport (KSIA) in Riyadh.

    MEED understands that the consortiums have been given until January to submit their proposals.

    The participating consortiums are:

    • Al-Gihaz Holding / TAV Construction / Webuild (local/Turkiye/Italy)
    • Modern Building Leaders / Powerchina / Metallurgical Corporation of China (loca/China/China)
    • UCC Holding / Consolidated Contractors Company (Qatar/Greece)

    Last month, MEED exclusively reported that contractor teams have completed the early contractor involvement phase of the project.

    Under the completed phase, the shortlisted teams submitted detailed construction methodologies and technical design proposals.

    King Salman International Airport Development Company (KSIADC) is a subsidiary of Saudi sovereign wealth vehicle the Public Investment Fund.

    Terminal 6 is planned to boost the airport’s annual capacity by 40 million passengers. KSIADC aims to complete the terminal ahead of Expo 2030 Riyadh.

    In May 2025, MEED reported that US-based Bechtel had been appointed as delivery partner for the passenger terminals at KSIA.

    UK-based Foster + Partners designed the masterplan, including the terminals, six parallel runways and a multi-asset real estate district.

    US-based engineering firm Jacobs is providing specialist consultancy services for the masterplan and runway design, while UK-headquartered Mace is acting as delivery partner for the broader development. Local firm Nera secured the airspace design consultancy contract.

    The KSIA project covers about 57 square kilometres (sq km) and incorporates the existing terminals at King Khalid International airport. The scheme will feature 12 sq km of airport support facilities, residential and recreational zones, retail assets and logistics parks.

    The development is targeted to handle up to 120 million passengers a year by 2030 and 185 million passengers by 2050, in addition to an annual cargo throughput of 3.5 million tonnes by 2050.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21087339/main.jpg
    Yasir Iqbal
  • Contractors prepare bids for Morocco power line

    2 November 2026

     

    Contractors are preparing bids for a 160-kilometre (km), 400kV transmission line linking Guercif and Fes East in Morocco, following a site visit on 1 October.

    The project is being developed by the Office National de l'Electricite et de l'Eau Potable (Onee) to connect the Saka solar photovoltaic power plant to the national electricity grid.

    According to sources, at least eight contractors attended the site visit last month, including:

    • Butec (Lebanon)
    • CEEC Northeast Electric No.2 (China)
    • Cegelec (France)
    • EPME Electric (Morocco)
    • Hideleco (Egypt)
    • Kec International (India)
    • PowerChina (China)
    • Transrail (India)

    The project comprises two lots. The first involves a 90km transmission line between Guercif and Taza, while the second covers a 70km section between Taza and Fes East.

    The scope of work includes the construction of tower foundations, installation of transmission supports and conductors, and associated high-voltage equipment. It also includes optical fibre cables for communications and monitoring, access roads and other supporting infrastructure.

    The tender was issued in September with bids originally due by 21 October. The deadline has now been extended to 25 November.

    The project is part of a wider programme by Onee to expand Morocco's electricity transmission network and accommodate additional renewable energy capacity.

    In June, the utility commissioned a 274km, 400kV transmission line linking Chemaia and Mediouna, near Casablanca.

    Onee plans to expand its high- and extra-high-voltage transmission network from more than 30,700km to 37,000km by 2030.

    In August, it approved a $26.4bn investment programme for the 2026-30 period, covering electricity and drinking water infrastructure.

    The programme has allocated about $21.9bn to electricity projects and $4.5bn to drinking water infrastructure, with about 72% of the investment to be financed by the private sector, according to Onee.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21083507/main1257.jpg
    Mark Dowdall
  • Adnoc Onshore allows more time for Bab gas cap well tie-in bids

    2 November 2026

     

    The onshore business of Abu Dhabi National Oil Company (Adnoc Onshore) has allowed contractors more time to prepare proposals for a project to tie in gas-producing and injection wells at the gas cap reservoirs of Abu Dhabi’s onshore Bab field.

    The well tie-in scope, estimated to be worth more than $800m, forms part of Adnoc Group’s wider integrated Bab gas cap development programme.

    The overall programme is being led and overseen by Adnoc Gas, another Adnoc Group subsidiary. Its central element is the construction of gas-processing infrastructure to handle incremental gas output expected from developing the Bab gas caps.

    Adnoc Onshore issued the main tender for engineering, procurement and construction (EPC) works on the project in late September, MEED previously reported.

    Contractors have been given until 16 November to submit technical bids for the project, according to sources. The previous deadline was 29 October.

    MEED previously reported that Adnoc Onshore issued an expressions of interest (EoI) notice for the Bab gas production and injector well tie-in project on 13 May, with contractors submitting responses by 20 May.

    The scope of work on the project covers the following:

    • Tie-in of 99 new wells from Bab gas cap reservoirs KH-2, SH-1 and LK-1 (60 gas producers and 39 gas injectors);
    • Installation of well gathering structures: 10 gas pads, six well bays and three virtual pads;
    • Installation of a gas gathering network and a gas injection network;
    • Rerouting of the LK-3 production from the existing trunkline in Remote Manifold Station 3 (RMS-3) to the project’s production trunkline, Bab Gas TL-2;
    • Demolition of the existing 10-inch trunkline from RMS-3 to onshore gas development phase one.

    In the EoI document, Adnoc Onshore said it intends to award the EPC contract in the last quarter of the year, with a 45-month duration of works.

    Bab gas cap project infrastructure

    As part of its 2030 upstream production increase goals, Adnoc Group is working to extract gas from four underdeveloped gas cap reservoirs at the Bab onshore field development – Thammama A, Thammama B, Thammama F and Thammama H.

    While the Thammama A, B and H reservoirs are estimated to collectively produce 1.45 billion cubic feet a day (cf/d) of gas, output from the Thammama F gas cap is expected to be at a rate of 396 million cf/d.

    Existing trains at the Habshan processing complex in Abu Dhabi will be unable to handle the new gas volumes. Therefore, Adnoc Gas is required to build new facilities to process an additional volume of up to 1.85 billion cf/d of raw gas.

    Adnoc Gas is planning to build a gas processing plant in the Bab area, about 170 kilometres from Abu Dhabi, along with associated pipeline networks and other ancillary units, as part of the broader Bab gas cap development project. It has divided the EPC scope of work on the project into four packages:

    • EPC package 1 – Main Bab gas cap plant
    • EPC package 2 – Early civil works
    • EPC package 3 – Pipelines
    • EPC package 4 – Non-process area works

    Abu Dhabi Securities Exchange-listed Adnoc Gas issued the tender for the main Bab gas cap plant on 25 June and set an initial deadline of 17 July for contractors to submit technical bids. The company then extended the technical bid submission deadline by four months, until 16 November, MEED previously reported.

    Following a reshuffle of the consortiums gearing up to bid for the main Bab gas plant EPC package, estimated to be worth more than $6bn, the following teams have formed to compete in the main contract tendering round:

    • Larsen & Toubro Energy Hydrocarbon (India) + Petrofac Emirates (UAE)
    • Technip Energies (France) + JGC Corporation (Japan) + Sinopec (China)
    • Tecnimont (Italy) + China Petroleum Engineering and Construction Corporation (CPECC)

    The other three packages of the Bab gas cap project are also in the main contract tendering stages.

    Prior to issuing the EoIs for the project packages, Adnoc Gas completed an early engagement process with contractors in September and October last year, as MEED previously reported.

    In December last year, Adnoc Gas awarded the front-end engineering and design (feed) works for the development project  to Australia-based consultancy Worley. The feed contract has a duration of more than 1.2 million man-hours, making it the largest-ever engineering job awarded by Adnoc Gas.

    Bab Gas Cap concession

    In addition to Adnoc Gas overseeing the main EPC tendering exercise for the gas processing plant, Abu Dhabi’s Supreme Council for Financial and Economic Affairs (SCFEA) awarded concession agreements in June for the development and production of the Bab gas cap reserve.

    Adnoc will hold the majority 60% participating interest in the concession. The remaining stakes will be held by France’s TotalEnergies (10%), the UK’s BP (10%), China National Petroleum Corporation International (8%), Japan Oil Development Company Onshore (5%), China ZhenHua Oil (4%) and Korea GS E&P (3%).

    According to the SCFEA, the Bab gas cap development and production concession represents the largest gas cap development project of its kind globally, the Abu Dhabi Media Office said in a report.

    A gas cap refers to the free natural gas that sits above an underlying oil reservoir – in this case, the Bab onshore oil field in Abu Dhabi.

    The project, operated by Adnoc Onshore, is expected to have a production capacity of approximately 1.5 billion cf/d of natural gas, equivalent to about 15% of Adnoc Gas’ total operational gas processing capacity.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21083343/main.jpg
    Indrajit Sen
  • Gulf ministers insist Hormuz is still essential

    2 November 2026

    Register for MEED’s 14-day trial access 

    Senior Gulf officials have rejected suggestions that new pipelines and rail links will allow the region to do without the Strait of Hormuz, arguing that the waterway will remain essential to the GCC and the global economy.

    Speaking at the Gateway Gulf investment forum in Manama on 1 November, GCC secretary-general Jasem Mohamed Albudaiwi said keeping the strait open is the responsibility of the international community, not of any one country or group of partners. "We hear some voices that maybe we should seek alternatives to Hormuz," he said. "Fine, we will get the pipelines. We will get the GCC railway. But that doesn't mean Hormuz is nobody's business."

    Albudaiwi called for the strait to remain open in line with international law, including the 1982 UN Convention on the Law of the Sea.

    Shipping through the strait has been severely restricted since the US and Israel launched strikes on Iran on 28 February and Iran retaliated with attacks on GCC states and commercial vessels.

    Bahrain's Finance & National Economy Minister, Sheikh Salman Bin Khalifa Al-Khalifa, said building redundancy makes sense, but treating the strait as dispensable does not. He said the waterway carries 30% of global liquefied natural gas (LNG) exports, 20% of aluminium exports and 30% of fertiliser exports. "Any thinking about the alternative of Hormuz, as in we won't need it, is illogical, because we will need it for the world economy," he said.

    UAE Economy & Tourism Minister Abdulla Bin Touq Al-Marri said that "Hormuz matters, and Hormuz will keep mattering", adding that an economy dependent on a single trade route is exposed if that route closes.

    Sheikh Salman said the crisis has compressed years of GCC customs negotiations into weeks. During the conflict, containers cleared at Jeddah with final destinations in Bahrain or Kuwait moved on without further checks, and the same applied to cargo routed through Salalah and Fujairah, he said. GCC ministers have since agreed to make these emergency measures permanent.

    He also cited Gulf Air operating out of Saudi airports for more than 40 days without a written agreement, and a $5bn swap between the UAE and Bahraini central banks to stabilise currencies.

    Bin Touq said the bloc should use 2027 and 2028 to push through reforms, including removing remaining customs barriers between member states.

    Albudaiwi said GCC leaders meeting in Jeddah on 28 April had tasked the secretariat with advancing water connectivity, expanding the GCC electricity grid, planning new logistics infrastructure including ports, accelerating the GCC railway and enhancing oil and gas pipeline links.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21080732/main4958.jpg
    Colin Foreman
  • Bahrain’s Gateway Gulf brings $20bn of deals

    2 November 2026

    More than 110 announcements worth over $20bn will be made at the Gateway Gulf Investment Forum in Bahrain, according to the country's finance minister.

    "Over the next two days at Gateway Gulf, more than 110 announcements worth over $20bn will be made," Sheikh Salman Bin Khalifa Al-Khalifa, Finance & National Economy Minister, said at the opening of the forum's fourth edition on 1 November in Bahrain.

    He said the announcements will cover new partnerships, investments, projects and jobs. Sheikh Salman addressed an audience that included Bahrain's Crown Prince and Prime Minister, Prince Salman Bin Hamad Al-Khalifa.

    The minister said the region's economies have been "tested as never before" since the previous edition of the forum a year earlier.

    "In the face of unprecedented attacks, we did not waver," he said. He added that Bahrain has chosen to work more closely with its allies and partners to defend what it has built.

    Sheikh Salman said the Gulf economy has grown to $2.4tn in GDP. Non-oil sectors account for more than 86% of Bahrain's GDP and more than 77% across the Gulf, he said.

    He said Gulf banks hold more than $4tn in assets, while the region's sovereign wealth funds manage more than $5tn of investments. "These numbers describe a region that has chosen to build a more stable, a more prosperous future for its people," he said. "Bahrain is the gateway to that region."

    The minister said Bahrain is focusing on regulation, infrastructure and people to attract investment.

    He said the country has developed a regulatory framework over several decades that is "clear, modern and fast", allowing investors to commit with confidence.

    On infrastructure, he highlighted logistics, connectivity, digital networks and industrial land as areas where Bahrain is building the foundations for businesses to expand. He also named finance, logistics, tourism, manufacturing, technology and telecommunications, and oil and gas as the sectors into which he expects domestic, regional and international capital to flow.

    He said the investments will create jobs for young graduates and support the growth of family businesses.

    https://image.digitalinsightresearch.in/uploads/NewsArticle/21080593/main2015.jpg
    Colin Foreman